1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIET NAM POWER EGINEEMNG CONSULTING JOINT-STOCK COMPANY 1 PROJECT: KV QUANG NINH TPP - HOANH BO TRANSMISSION LINE RESETTLEMENT PLAN RP82 VOL. 30 POWER ENGINEERING CONSUL

2 '\ SEER Project \ Resettlement Plar 220kV Quang Ninh TPP - Hoanh Bo Transmission Line \ TABLE OF CONTENTS I ij Executive Summary Chapter I : Introduction Chapter I1 : Institutional and Legal Framework Chapter IU. : Entitlement Policy Chapter IV : Mitigation Measures Chapter V : Public Consultation Chapter VI : Baseline Information Chapter VII : Project Impacts Chapter VIII : Implementation Arrangement Chapter IX : Cost and Budget Annexes Annex 1 - Statistics on Line Length and Permanent Land Acquisition Annex 2 - Statistics on PAHs Annex 3 - Statistics on Affected Structures and Land Annex 4 - Classification of Temporary Impacts on Land within ROW Annex 5 - Classification of Permanent Impacts on Land within ROW Minutes of Community Meetings Layout of Line Route

3 SEIER Project 220kV QU&I~ Ninh TPP - Hoanh Bo Transmission Line ABBREVIATIONS wi3 GOV EVN PECC 1 NPPMB OD 4.12 PRB DRB PPC DPC CPC PPS PPFD DCD IMO RB CC RP RIB - "FS ROW HH PAH DP(s) SLS World Bank Government of Vietnam Electricity of Vietnam Power Engineering & Consulting Company No. 1 (now renamed as Power Engineering & Consulting Joint Stock Company No. 1 Northern Vietnam Power Project Management Board World Bank Operational Directive 4.12 Provincial Resettlement Board District Resettlement Board Provincial People's Committee District People's Committee Commune People's Committee Provincial Power Service : Provincial Pricing and Financial Department : District Cadastral Department : Independent Monitoring Organization : Resettlement Board Consulting Company Resettlement Information Booklet Feasibility Study Right-of-way Household Project Affected Household Displaced Person(s) Standards of Living Surveys

4 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line DMS L7"-Kc HV T/L : Detailed Measurement Survey - : Lana use Rignr Certificare : High Voltage : Transmission Line

5 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line EXECUTIVE SUMMARY 1 Introduction 1.1 Project objectives Investment in the construction of 220kV Quang Ninh - Hoanh Bo transmission line aims at transmitting electricity from the Quang Ninh and Cam Pha thermal power plants to the national power network. Meanwhile, it shall ensure a stable and reliable power supply for the socio-economic development for Quang Ninh, Hai Phong and Ha Noi which is the main economic region of northern Vietnam. The line covers several following areas: Quang Ninh province: district of Hoanh Bo: communes of Thong Nhat, Son Duong, Troi town; and Ha Long city: Viet Hung ward. 1.2 Project components Contruction of 220 kv Quang Ninh TPP - Hoanh Bo transmission line: 20.1 h.. Expansion of 220kV bays at 220kV Hoanh Bo substation. In-auguration : Total investment of project : 1 11 billions VND. 1.3 Implementation schedule Main milestones : - Completion of Investment report Completion of Technical design - Total estimate: Preparation of construction Construction, acceptance In-auguration Total estimate The total investment of project would be: 1 11 billions VND. 1.5 Policy framework This resettlement policy framework is prepared basing on the OP 4.12 of the World Bank. The principle objective of this Policy Framework is to ensure that all DPs will be compensated for their losses at the replacement cost and provided with rehabilitation measures to assist them. in improve or at least in maintaining their preproject living standards and income earning capability.

6 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line The Policy Framework lays down the principles and objectives, eligibility criteria of DP, entitlements, legal and institutional framework, manner of compensation and rehabilitation, features of consulted people, and grievances procedures that will guide compensation, resettlement and rehabilitation of DPs. 1.6 Displaced Persons The impacted structures would not have to move out of the ROW for the following reasons: The 220 kv Quang Ninh TPP - Hoanh Bo transmission line is designed to be in the ROW of the feeder No.175 of the 110 kv Hoanh Bo - Mong Duong transmission line. The line is designed in complaince with item 6 of the Decree No. 106/2005/ND-CP with the minimum vertical clearance to such structures of 13m in densely populated areas and 8m in sparsely populated areas. As such these houses do not have to be relocated. 1.7 Principles and Objectives The principles outlined in the World Bank's Operational Policies 4.12 (OP 4.12) have.been adopted in preparing this Policy Framework. In this regard, the following principles and objectives would be applied: a) All DPs residing, working, doing business or cultivating land in right of way (ROW) of transmission line (TIL), surrounding areas of tower foundations, the substation areas, in the service roads under the projects as of the date of the baseline surveys are entitled to be provided with rehabilitation measures. b) According to the Government Decree No. 106/2005/ND-CP, August 17th, 2005 on the protection of the high voltage networks, houses or building in ROW will be provided with subsidy allowance for fireproof materials and lightning arrestors for the existing house/building; cash compensation for the arable land; cash compensation for the directly affected rooms at the substitution cost and cost for demolishing an affected partlroom (No land-forland compensation). c) Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out via consultation with DPs to ensure minimal disturbance. Entitlements will be provided to DP prior to expected start-up of works at the respective project site. Compensation, resettlement, assistance and rehabilitation activities will only commence upon the WB's acceptance and PPC's approval of the RP. 2. Institutional framework

7 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line This RP has been prepared on the basis of the Project Policy Framework with all GOV and WB policies related to land acquisition, compensation and resettlement (OP 4.12) applied for this RP. Where GOV and WB poiicies are not compatible, the WB's OP 4.12 shall prevail with certain required waivers. 3. Entitlement policy This resettlement policy fiamework is prepared basing on the OP 4.12 of the World Bank. The principle objective of this Policy Framework is to ensure that all DPs will be compensated for their losses at the replacement cost and provided with rehabilitation measures to assist them in improve or at least in maintaining their preproject living standards and income earning capability. The Policy Framework lays down the principles and objectives, eligibility criteria of DP, entitlements, legal and institutional framework, manner of compensation and rehabilitation, resettlement and rehabilitation of DPs. Refer to entitlement matrix for detail. 4. Mitigation measures 4.1 Mitigation measures in design stage Expansion of 220kV bays at 220kV Hoanh Bo substation Expansion of 220kV bays at kV Hoanh Bo substation shall be in a hill with eucalyptus and mixed trees. The total land acquisition shall be 9,328 m2. The design is so selected to have an optimum site elevation in order to minimize soil and rock leveling. As such, the impact is rendered as inconsiderable kv Quang Ninh TPP - Hoanh Bo transmission line + The 220 kv Quang Ninh TPP - Hoanh Bo transmission line is designed to be in the ROW of the feeder No. 175 of the 1 10 kv Hoanh Bo - Mong Duong transmission line. Therefore, its ROW would be mainly the existing ROW area and expansion 4 meters on both sides. + Line route is designed as process and regulation of Electricity unit (distance between lowest line to earth is 13m in densely populated areas and 8m in sparsely populated areas) + Earthing: according to current regulation, all towers in line route are earthed as regulation to ensure construction operation and human safety. (This is also one of measures to minimize efects to property, building of habitants in right-ofway without removing;) + To minimize effects to highway and waterway transportation, at crossroad of highway and waterway, distance from the line to these construction sites should be calculated according to regulation.

8 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line + Height sign and danger sign is designed to avoid unfortunate problems happening in construction and operation. + Conductor and lightning line is protected by anti-shaking shot weight suitable for each kind of line. + Auxiliaries for conductor and lightning line are suitable for line size and ensure safe factor according to regulation. + All towers have restricted sign and number Impact mitigation measures in construction stage - Reasonable construction project, with many shifts, increasing produ.ctivity, finishing at given moment for each item to reduce temporary land requisition time. - Construction activities should be conducted after harvesting crops. - Do not allow the Contractor to extend plant cutting area outside of defined right-. of-way. - Do not cut trees under safe height as regulation. - Supervise quality of highway on temporary road to timely recover, repair damage and avoid effect to local transportation. - With special characteristics of this construction, we should build new camp for workers but renting houses at habitants region. Worker's camp and material store should be in region which the line goes through. 5. Public Participation Information dissemination to, consultation with and participation of affected people and involved agencies (i) reduce the potential for conflicts, (ii) minimize the risk of project delays, and (iii) enable the project to design the resettlement and rehabilitation program as a comprehensive development program to fit the needs and priorities of the affected people, thereby maximizing the economic and social benefits of the project investment. 6. ~aseline information 6.1 Data gathering activities Power Engineering Consulting Company No.1 with the help of local authorities conducted a census in rural areas, Inventory of project' impact in May The inventory works include: Survey on the project impact was conducted in Quang Ninh province: district of Hoanh Bo: communes of Thong Nhat, Son Duong, Troi town; and Ha Long city: Viet Hung ward. The survey shows that 77 PAHs would be affected by the project.

9 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line 6.2 Socio-economic survey Quang Ninh is a mountainous province, it is north east of the country. The province total area is 5,938.6 km2, its population in 2005 was - 1,184,200 Quang Ninh province has 12 urban districts and 1 city Statistics and survey Survey on the project impact was conducted in Quang Ninh province: district of Hoanh Bo: communes of Thong Nhat, Son Duong, Troi town; and Ha Long city: Viet Hung ward. The survey shows that: Total number of DPs: Permanently affected structures: 1,13 9 m2 Temporarily affected structures: 77 HHs (362 persons) 0 m2 Temporary impact on residential and garden land: 15 HHs DPs with houses/structures, which are partially impacted: 25 HHs DPs with permanent acquisition of residential land, agriculture or forestry land: 52 HHs HHs to be resettled: 0 Average income of PAHs: Average number of people per household : 5 PAHs' facilities : 13,000,000 VND/year above average All PAHs in the project area are supplied electricity by the power network Farmers represent 50% of PAHs Few PAHs have main income from trade. These PAHs mainly concentrate in the town center, along the highways. However, some farmer families also make earning from trade but the quantity is not much. 7. Project impacts * Impact on land - Temporary impact on residential land : 4,974 m 2 - Permanent impact on residential land :581 m2 - Temporary impact on agricultural land : 31,398 m 2 - Permanent impact on agricultural land : 1,940 m 2 - Temporary impact on forest land : 10,060 m 2 - Permanent impact on forest land : 7,790 m 2 - Temporary impact on other land : 33,912 m 2 - Permanent impact on other land : 5,669 m 2

10 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlement Plar * Impact on houses and structures - Temporary impact on houses - Permanent impact on houses * Impact on trees and crops - Temporary impact on rice - Permanent impact on rice - Temporary impact on litchi, longan - Permanent impact on litchi, longan - Temporary impact on keo - Permanent impact on keo - Temporary impact on eucalyptus - Permanent impact on eucalyptus - Temporary impact on pine - Permanent impact on pine * Displaced persons Total number of DPs is 77 HHs (362 persons), of these: DPs with houses/structures, which are partially impacted: 25 HHs DPs with permanent acquisition of residential land, agriculture or forestry land: 52 HHs a. Temporary land requisition Land will be requisited temporarily in 2 cases for: foundation works, tower erection, material transport to the line route, conductor and earthwire pulling and stringing. The total temporary requisition of the project is 80,344 m 2. Refer to Chapter VII for statistics on the project temporarily acquired land b. Impact on permanent land acquisition. The total permanent acquisition of the project is included of agricultural land, garden and residential land, waste land and pond area. Permanently occupied agricultural and land tenure land area for building foundation is: 15,979m 2 Refer to Chapter VII for statistics on the project permanently acquired land c. Impact on houses and structures

11 SEER Proiect 220kV QU& Ninh TPP - Hoanh Bo Transmission Line The line routes mainly traverse rice field, crop and fruit areas, populated areas. According to survey statistics, totally there are 5 structures crossed by the line and 20 ones located in the line ROW. Refer to Chapter VII for statistics on the impact on houses and structures. d. Impact on trees and crop Refer to Chapter VII for statistics on the impact on trees and crop. 8. Implementation arrangement ' 8.1. Main activities Activity I: Right after approval of the RAP, PME! must select and contract an independent monitoring organization, the organization shall be approved by Hai Phong PC and WB. Activity 2: Basing on the contract requirement of PME!, the involved provinces shall decide to start RAP programs. Activity 3: DRBs shall obtain statistics on affected assets and specify the compensation rates, check and adjust, if necessary, the compensation according to the unit price and equivalent cost. Activity 4: Upon completion of statistics works, DRBs shall review and specify the exact number of PAHs,affected assets and total compensation for PAHs. Activity 5: RBs shall inform RAP policies, project schedule and information on RAP implementation for PAHs via meetings. Such advices include issues relating to compensation and resettlement program. Activity 6: Compensation payment to PAHs having houses affected first, help them to repair houses and stable their lives. Then comes compensation for other properties. Temporary LURCs shall be granted to all PAHs and permanent LURCs shall be given to their representatives. Activify 7: During all implementation process, IMO, independent monitoring organization shall monitor the project implementation, propose keys for problems Grievance and appeals

12 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line The mechanism is designed. to be easy, transparent and fair, the procedures are as follows: First step: If any person is aggrieved by any aspects of the resettlement and rehabilitation program, helshe can lodge an oral or written grievance with the commune authorities. The Commune People's Committee will resolve the issue within fifteen days from the date it receive the complaint. Second step: If any aggrieved person is not satisfied with the decision in stage 1, shehe can bring the complaint to the District People's or District Resettlement Committee (CRC) within fifteen days from the date of the receipt of the decision in stage 1. The District Resettlement will reach a decision on the complaint within fifteen days. Third step: If the DP is still not satisfied with the decision at district level, helshe can appeal to the Provincial People's Committee (PPC) or Provincial Resettlement Committee (PRC) within 15 days of receiving the decision of the DPC or DRC. The Provincial People's Committee or Provincial Resettlement Committee will reach a decision on the complaint within fifteen days. Fourth step: If the DP is not satisfied with the decision of the Provincial level, the case may be submitted for consideration by the District Court within 15 days of receiving the decision of the PPC or PRC. The district court's decision will be a legal basis for compensation. DPs will be exempted from all administrative and legal fees. DPs can make an appeal on any aspects of resettlement and rehabilitation program, including the compensation unit price. The detail procedures of solving grievance will be disclosed to all DPs in the public meetings and at the CRC offices. This information is also contained in RIB, disseminates to all DPs promptly after the commencement of the project. 8.3 Monitoring and supervision The implementation of RP shall be constantly supervised and monitored by PMB in co-ordination with the local People's Committees Internal monitoring IMO shall prepare a detail report on activities to submit to PMB and WB every 3 months to see weather the process are in compliant with policies of the government, WB External monitoring

13 SEER Project 220kV Quang Ninh TPP - Moanh Bo Transmission Line Resettlement Pla - Write final report (6 months after entire accomplishment of the resettlement program). This report shall provide detailed evaluation of RP and its implementation? including the content of interview with DPs about the situation and their opinions after receiving compensation and resettlement. - Finally, on the bases of RP implementation experience, this final report shall provide suggestions to enhance the local RP implementation experience and improve RP in the future - Terms of reference for independent monitoring will be prepared by PMB and sent to WB for its concurrence prior to invitation for independent monitoring consultant. 9. Costs and Budget COST ESTIMATE Compensation cost : ( ) Permanent land acquisition: Residential land : 58 1m2 x 600,00Od/m2 Agricultural land : Rice, crop: 1,169 m2 x 16,90Od/m2 Fruit trees: 770 m2 x 105,00Od/m2 Other land : 5,669 m2 x 500d/m2 Forest land : 7,790 m2 x 2,625dIm2 Compensation for crops, trees : (a + b +c 1 Permanent land acquisition : Rice, crop: 1,169 m2 x 2,30Od/m2 Fruit trees: 180 trees x 150,00Od/tree Eucalyptus : 319 trees x30,000d/tree Temporary land requisition Rice : 23,936 m2 x 2300d/m2 Fruit trees: 700 trees x 150,00Od/tree Eucalyptus : 925 trees x30,000d/tree Keo : 450 trees x35,000d/tree Pine: 1230 trees x30,000d/tree Compensation for stringing works in the ROW Fruit trees: 3500 trees x 150,00Od/tree Eucalyptus : 4,625 trees x30,000d/tree Keo: 2250 trees x35,000d/tree Pine: 6,150 trees x30,000d/tree

14 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlement Pla d Compensation for safety cleareance in the ROW Eucalyptus : 260 trees x30,000d/tree Pine : 320 trees x30,000b/tree 3 Compensation for houses and other structures (a + b ) a Houses and structures Houses class-i: 145 mz x 1, 100,000d/m1 Houses class-iva : 954 m 2 x 650,000b/m2 Houses class-ivb : 40 m 2 x 550,000b/m3 b Allowances II Implementation cost 1 Administration cost : 2% (I) 2 Cost for independent mornitoring SUM (I+II) 111 Contingency cost (estimate) 10% (I+II) Total

15 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlement Plar CHAPTER I INTRODUCTION 1 Introduction a. Project Objectives Investment in the construction of 220kV Quang Ninh - Hoanh Bo transmission line aims at transmitting electricity fkom the thermal power plants to the national power network. Meanwhile, it shall ensure a stable and reliable power supply for the socio-economic development for Quang Ninh, Hai Phong and Ha Noi which is the main economic region of northern Vietnam. b. Project Scope ' The 220kV Quang Ninh - Hoanh Bo transmission line has the following main characteristics : Nominal voltage No. of circuits Beginning point : 220kV : Two circuits : 220kV portal (Feeders F08, F09) of 500kV Quang Nhih S/S Ending point : 220kV portal (Feeders F01, F03) of 220kV Hoanh Bo S/S Length of the line : a@,. Conduct or : 2xACSR 330/43 (2 conductors per phase) Overhead ground wire: PHLOX1 16 and OPGW9 1/3 8 Insulator Tower Foundation : Toughened glass or composite insulators : Double-circuit hot-dip galvanized steel towers : in-situ cast reinforced concrete foundation Earthing : Radial form (galvanized steel wire 4 12) Total investment : Approximately 111 billion Vietnam dong Implementation schedule: The line covers several following areas: Quang Ninh province: district of Hoanh Bo: communes of Thong Nhat, Son Duong, Troi town; and Ha Long city: Viet Hung ward. 2. Policy framework

16 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line.. This resettlement policy fiamework is prepared basing on the OP 4.12 of the World Bank. The principle objective of this Policy Framework is to ensure that all DPs will be compensated for their losses at the replacement cost and provided with rehabilitation measures to assist them in improve or at least in maintaining their preproject living standards and income earning capability. The Policy Framework lays down the principles and objectives, eligibility criteria of DP, entitlements, legal and institutional fiamework, manner of compensation and rehabilitation, features of consulted people, and grievances procedures that will guide compensation, resettlement and rehabilitation of DPs. 3. Displaced Persons The impacted structures would not have to move out of the ROW for the following reasons: The 220 kv Quang Ninh TPP - Hoanh Bo transmission line is designed with the minimum vertical clearance to such structures of 13m in densely populated areas and 8m in sparsely populated areas. As such these houses do not have to be relocated. 4. Principles and Objectives The principles outlined in the World Bank's Operational Policies 4.12 (OP 4. i2) have been adopted in preparing this Policy Framework. In this regard, the following principles and objectives would be applied: a) Acquisition of land and other assets, and resettlement of people will be minimized as much as possible. b) All DPs residing, working, doing business or cultivating land in right of way (ROW) of transmission line (T/L), surrounding areas of tower foundations, the substation areas, in the service roads under the projects as of the date of the baseline surveys are entitled to be provided with rehabilitation measures sufficient to assist them to improve or at least maintain their pre-project living standards, income earning capability. Lack of legal rights - to the assets lost should not bar the DP from entitlement to such rehabilitation measures. c) According to the Government Decree No. 106/2005/ND-CP, August 17th, 2005 on the protection of the high voltage networks, houses or building in ROW will be provided with subsidy allowance for fireproof materials and lightning arrestors for the existing househuilding; cash compensation for the arable land; cash compensation for the directly affected rooms at the substitution cost and cost for demolishing an affected partlroom (No land-forland compensation).

17 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line - d) Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out via consultation with DPs to ensure minimal iiispli~b~ce. Eniitlements wiii be provided to DP prior to expected start-up of works at the respective project site. e) Institutional arrangements will ensure defective and timely design, planning, consultation and implementation of RP. fl Effective and timely supervision, monitoring and evaluation of the implementation of RJ? will be carried out. The entitlement will be provided to DPs prior to expected constructiol~ commencement at the respective project site. This RP preparation has been carried out by Power Engineering Consulting Company No. 1 in accordance with the provision of the Policy Framework with consultation and participation of DPs and local authorities. This 'RP has been agreed upon by the relevant local authorities and will be valid after EVN's and WB's approval. Compensation, resettlement, assistance and rehabilitation activities will only commence upon the WB's acceptance and PPC's approval of the RP. 5. Project impacts Basing on the survey data, the impacts are summarized as follows: * Impact on land - Temporary impact on residential land : 4,974 m 2 - Permanent impact on residential land :581 m2 - Temporary impact on agricultural land : 31,398 m 2 - Permanent impact on agricultural land : 1,940m2 - Temporary impact on forest land : 10,060 m 2 - Permanent impact on forest land : 7,790 m 2 - Temporary impact on other land : 33,912 m 2 - Permanent impact on other land : 5,669 m 2 * Impact on houses and structures - Temporary impact on houses :Om2 - Permanent impact on houses : 1,139 m 2 * Impact on trees and crops - Temporary impact on rice : 23,936 m 2 - Permanent impact on rice : 1,169 m 2 - Temporary impact on litchi, longan : 7,462 m 2 - Permanent impact on litchi, longan : 770 m2 - Temporary impact on keo : 1,400m2

18 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line - Permanent impact on keo : 808m2 - Temporary impact on eucalyptus : 3,532 m 2 - Permanent impact on eucalyptus : 955 m2 - Temporary impact on pine : 5,128 m 2 - Permanent impact on pine : 6,027 m 2 * Displaced persons Total number of DPs is 77 HHs (362 persons), of these: DPs with houses/structures, which are partially impacted: 25 HHs DPs with permanent acquisition of residential land, agriculture or forestry land: 52 HHs 6. Mitigation measures a) Design stage In order to avoid or mitigate the adverse impacts on land, assets, structures and crop of local people, the line is so selected to be along or closed to the existing roads to facilitate future operation and maintenance; or cross the agricultural or garden land. By this solution, the route will cross over the road some times to avoid impact on houses or structures. Construction of the new roads are limited, try to use the existing ones. The temporary roads will be mainly built in the ROW area. b) Construction stage The suitable measures and construction arrangement are to be thoroughly considered as the construction period will be implemented after the harvest collection, and ended before the following harvest. To gain this target, some daily workings will be changed and planned in order to shorten the temporarily affected period. Workers' camps will be located at vacant site or at the public land nearby the commune steering board and will not be built near the residential areas. Appropriate workforces with working shifts will be scheduled to shorten the temporarily affected period.

19 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Chapter 11 INSTITUTIONAL AND LEGAL FRAMEWORK 2.1 Institutional framework Overall responsibility The overall responsibility for enforcement of the Policy Framework and for planning and implementing this RP is rest with Northern Vietnam Power Project Management Board, and related institutions/departments of Finance, Industry, Construction, etc.). Northern Vietnam Power Project Management Board, Power Engineering Consulting Company No.1 are responsible for carrying out census, socio-economic surveys, population and inventories and preparing RP within their respective jurisdiction. The related District and Commune People's Committees will participate in the RP preparation and implementation. These administrative units will also ensure the active and effective participation of the DPs in RP preparation and implementation. In order to make RP acceptable to the WB and to implement RP smoothly, PMB is responsible for (i) hiring a qualified consultant in preparing RP, (ii) appointing qualified social safeguard staffs at Northern Vietnam Power Project Management Board and provincial/district resettlement committees. Funds for implementing RP will be from EVN budget Detail responsibility a) EVN: is the project investor responsible for approving the project documents, providing PMB with fund and guidance on the project control and implementation as well as RAP preparation and implementation. b) PMB: MPPMB on behalf of EVN is the project manager and responsible for the whole project covering investigation, consultancy, design, bidding, resettlement, construction, assignment for specialized bodies to prepare and implement the project, submission to EVN for approval on decisions concerning resettlement submitted by PPCs, monitoring the resettlement activities. Overall planning, management and monitoring of the resettlement programs;

20 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line c) PECCl Ensuring that all eligible PAHs are identified, provided with their respective entitlement according to the resettlement policy and is relocated as per the implementation schedule and with minimum hardships to PAHs; Ensuring that all PAHs are informed about their entitlements and provided with the resettlement Information Booklet (RIB), as proof of their eligibility to resettlement benefits; Explaining the scope of the project to Peoples' Committees at various levels; Providing copies of the RAP to resettlement boards and explaining the approach adopted and the categories of entitlement that will be used. Coordinating with resettlement boards at each level on the implementation of resettlement activities; Carrying out internal monitoring of RAP implementation and appointing a competent agency for external monitoring of land acquisition and resettlement activities; Providing the budget for resettlement and rehabilitation; Reporting on the progress of resettlement activities to EVN. Surveying, measuring and confirming AA Coordinating with DRB in classification of affected property. Studying and classifying affected people and houses. Undertaking to collect data, plan RP for the project basing on collected data fiom RBs. Coordinating with PMB in training enumerators d) City/Provincial People's Committee The PPC is responsible for endorsing the RP and clearly direddemarcate the responsibilities for their relevant institutions in implementing RP Approve the compensation unit cost, allowances and establish evaluation committees, compensation committees at all administrative levels and approve lands for compensation. Redress complaints and grievances. e) RP related provincial departments The Provincial DOF is responsible for studying and issuing unit prices of compensation and submitting to PPC for approval. Right fiom the initial stage of

21 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line the RP implementation, the DOF will closely co-ordinate. with DOCS, DCH, DARDs, District People's Committees and independent external monitoring agency in order to evaluate the applicable unit prices in RP and submit to PPC for approval and ensuring that the compensation unit prices to be at the replacement value at the time of compensation payment. f) Provincial compensation/resettlement committee The Provincial CRCs are responsible for implementing RP according to the approvad schedule. The Provincial CRCs will be headed by the Vice Chairman of the Provincial People's Committees. The Provincial CRCs are responsible for: Assisting PMB and District CRCs in preparing detailed plans for compensation and resettlement. Checking all inventory of impacts and detailed implementation plans submitted by District CRCs, approving the implementation plans submitted by the District CRCs, ensuring that the compensation unit prices to be at the replacement value at the time of compensation payment. Solving complaints if the redressed.is fail at the districts level. The City/provincial CRCs will consist of representatives of: Department of Finance and Pricing Department of Construction Department of Natural Resources and Environment (Cadastral and Mousing section) Chairmen of People's Committees of related districts. Representatives of CityProvincial PMB. g) District People's Committees The District People's Committees are responsible for guiding the compensation and. resettlement activities in their respective district areas: Direct the relevant institutional for carrying out impact survey; public consultation, information dissemination on the resettlement policy and RP' implementation. Establish District CRCs. Be responsible for settling complaints of DPs at district level. h) Districts Compensation/Resettlement Committees

22 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resett1emen.t Plan The District CRCs are principal institutions responsible for guiding the, compensation of W in their respective districts areas. The District CRCs recruit experienced persons for gathering of baseline information and inventory. The District CRCs are responsible for: Organizing the survey team to carry out Detailed Measurement Survey (DM9 For affected houses and assets; finalize DMS and Entitlement forms for each DP. Checking the unit prices of compensation as applied in W, suggest for adjusting the unit prices in conformation with market priceslreplacement costs (if required). In co-ordination with PMB, organize meetings with DPs and communes, disseminate the RIB, DMS and entitlement forms to DPs. Based on the policy and approved process in W, prepare the detailed implementation plan (quarterly, semi-annual, annual plans) and together with PMB deliver entitlements to DPs in a timely manner. Settling the complaint and grievances of DPs, solving any difficulties during the implementation period, and suggest the solutions for the outstanding issues to ProvinciaVCity CRC. The District CRCs will be headed by the Vice Chairmen of the DistrictlCommune People's Committees. The District CRCs will consist of the following representatives: Department of Finance and Pricing Department of Natural Resources and Environment (Cadastral and Housing Section) Department of Industry - Affected Communes DPs i) Commune People's Committees People's Committees of communes will be responsible for: Participating in census surveys and asset inventory. In co-ordination with District CRCs for public meetings, information dissemination, compensation/allowance payment to DPs. Transferring all feedbacks of DPs to District CRCs and settle the complaint at the commune level. Suggesting solution for slient features.

23 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Arrange land in case DPs require compensation of 'land for land'. j) Displaced DPs prepare all necessary RP related papers i.e LURC, ownership of other assets. DPs are responsible for carefully checking their lost assets and respective: entitlements and clear land in a timely manner once DPs receive full entitlements Staffing Staffing of resettlement institutions involved in the project. Resettlement institutions Average No of staff PMB 1 5 Total No. of staff Qualification Working duration 10 1 Expert 6 months PECCl I 10 / Expert 6 months PRB Middle ranking Expert DRB Middle ranking Expert Middle ranking Expert 6 months 1 year 6 months 1 year 6 months 1 year Duties of the resettlement institutions involved in the project. Activities of RP Involved Institutions Holding meeting with PAHs to inform RP I DRB, CPC, PMB I Monitoring and identifying PAHs and assets I DRB, CPC, DPC I Detail Measurement Surveying I DRB, Consultant, CPC I Notifying to PAHs I DRl3 I Determining Compensation problems Compensation payment Internal monitoring Independent monitoring PRl3 1 PMB PMB, PRB, DRB -- Provincial Science, Technology and Environment Department or other qualified social institutions selected by PMB

24 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Fund for land acquisition and resettlement Fund for land acquisition and resettlement will be at EVN's costs as part of the project budgets. 2.2 Legal Framework Vietnamese laws Compensation and Resettlement The key national laws, decrees, circulars governing land acquisition, compensation and resettlement consist of the followings: Constitution of Vietnam (1992) confms the right of citizens to own a house and protect the ownership of the house. The new 2003 Land Law on December 10" GOV Decree No.l81//2004/ND-CP dated October 29" 2004 on guidance of implementation of the new 2003 Land Law. GOV Decree No.l97/2004/ND-CP dated December 3rd, 2004 on the compensation, assistance and resettlement in case of land acquisition by the state. - - GOV Decree No.l88/2004/ND-CP dated November 16", 2004 on methodology for price verification and price framework of various types and categories of land. Circular No. 1 14/2004/TT-BTC dated November 26", 2004 of the Ministry of Finance guiding the implementation of-~ecree No. 188/2004/NPCP. GOV Decree No.l7//2006/ND-CP dated 27/01/2004 on guidance of implementation of the new land Law. GOV Decree No.84//2007ND-CP dated May ~ on regulation of land management and land uses, land acquisition, implementation of land use, compensation, resettlement. Circular No.l16/2004/TT-BTC dated May 25", 2004 of the Ministry of Finance guiding the implementation of Decree No MD-CP dated -December 3", 2004 on the compensation, assistance and resettlement in case of land acquisition by the state World Bank policies The legal fiarnework governing the implementation of this Policy Framework and the Inventories and RP are OP 4.12 on Involuntary Resettlement of the World Bank. Involuntary resettlement (OP 4.12).

25 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line The primary objective of the World Bank policy is to explore all alternatives to avoid or- at least minimize involuntary resettlement. Where resettlement is unavoidable, the living standards of displaced persons should be restored or improved to the pre-project conditions. The policy applies to the taking of land and other assets when land acquisition results in the loss for the case of shelter, the loss of all or part of productive assets, or access to them and loss of income sources or other means of livelihood. According to the OP 4.12 on involuntary resettlement, DPs shall be compensated and assisted in such a way as to warrant the improvement or at least the maintenance of pre-project living standard condition. Measures to ensure that resettlement has a positive outcome include: Consulting.with potential displaced persons on feasible measures for resettlement and rehabilitation; Providing DPs with options for resettlement and rehabilitation; Enabling their participation in planning and selecting these options; Providing compensation at full replacement cost for losses; Choosing relocation sites that at least guarantee the same benefits and services as the sites they replace; Providing allowances, training as income support to assist a smooth transition period; Identifying vulnerable groups and providing special assistance to these groups; and Establishing an institutional and organizational structure that supports this process to a successful end. The Eligibility Criteria and Compensation defines that the DPs eligible for compensation include: a) Those who have formal legal rights to'land or other assets; b) Those who initially do not have formal legal rights to land or other assets but have to acclaim for legal rights based upon the laws of the country; upon the possession of documents such as land tax receipts and residence certificates; upon the permission of local authorities to occupy or use the project affected piots; and c) Those who have no recognizable legal right or claim to the land they are occupying.

26 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line.. DPs whose houses are in part or in total affected (temporarily or permanently) by the project or whose residential and premise andlor agricultural land is in part or in total affected (temporarily or perrnanently) by the project are provided compensation for the lost land, and other assistance as necessary to achieve the objectives set out in this policy, if they occupy the project area prior to the cut-offdate defined in this FW. DPs whose business are affected in part or in total (temporarily or perrnanently) by the project are provided with resettlement assistance and other supports as necessary to achieve the objectives set out in this policy, if they occupy the project area prior to the cut-off-date defined in this W. Persons who encroach on the areas after the cut-off-date defined in this RP are not entitled to compensation or any other forms of resettlement assistance. The methodology to be used in the valuation of losses for this project is based on the replacement cost. In this project, losses comprise land, structures and other assets. Residential cost for land includes the value of land at the market price plus the costitaxes and frees to get LURC. For houses and other structures, the market cost of the materials shall be used to calculate the replacement cost for an equivalent structure with area and quality should be at least as good as those affected. For both totally and partially affected structures, compensation includes market cost of material, plus the costs of materials transport, labor and contractor fees, and registration and transfer taxes. Depreciation of the asset and amount saved in material will not form part of replacement cost Comparison of GOV and WB approaches There are a number of ways in which approaches of the Vietnam Government-either in policy or practice-are compatible with the World Bank guidelines. The most important compatibilities are: Vietnam has a process. whereby most people without legal land rights may meet conditions of legalization and receive compensation for losses. Permanent residents are provided with options that include relocation to an improved site, or cash, or a combination of the two. Resettlement sites offer not only better improved infrastructure and services but represent a higher standard of living. Allowances are provided to help DPs in the transition period and there is an institutional structure through which people are informed, can negotiate compensation, and appeal.

27 SEER Project 220kV Ouang: Ninh TPP - Hoanh Bo Transmission Line Differences between approaches and measures that need to be addressed within the program also exist. However, in this context, procedures exist within national and city government that allow the granting of wavers of domestic iaw on specific projects which may be conflict with that of the funding agency. On the issue of land tenure and legal right to compensation, the Government and World Bank approaches are compatible. The Government has its own process in place whereby land occupied without legal documentation can be legalized; this land, however, is compensated for at a rate equal to 100% of land price minus the taxes and fee for land use right registration from October 15' 1993 (Clause 49,50 of Article 42 of the 2003 Land Law). Compensation at replacement cost is ensured in Article 6 of Decree No. 197/2004/ND-CP dated December 3rd, 2004 that '....People who have land being required shall be compensated with land of similar use purpose. If there is no land for compensation, cash compensation equal to land use rights value at the time of land acquisition shall be applied. If there is any differences in value, in case of compensation by new land or house, such differences shall be settled in cash' and, Article 19 of the same Decree that '...Houses and structures of domestic use of the household or individual shall be compensated with the value for construction of new houses, structures of similar technical standard....' Required waivers In order to meet the requirement of the world Bank OP 4.12 on Involuntary Resettlement, a number of articles in various Vietnamese laws and regulations which do not ensure compensation at the replacement cost or set eligibility provisions which do not extend the right to rehabilitation and or assistance to households without proper land papers, will be waived. The articles of law and regulations that will be waived are mentioned below. (i) Eligibility to compensation andlor assistance - Article 7 of the Decree No. l97/nd-cp dated December 3d, 2004 Article 7 - (Cases where land is recovered without compensation) stipulates that any person whose land is recovered and who has not met one of the conditions of Article 8 of this Decree, or who has violated the plan, or who violates the protecting ROW, or who illegally occupies land shall not receive compensation when the state: recovers the land. In case of necessity, the Provincial People's Committee shall consider and decide on a case-by-case basis. Article 18 (Items 3&4), Article 20 (Item 2b,c) of the Decree No.l97/ND-CP stipulate the compensation principle for assets:

28 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resett1emen.t Plan o.houses and structures on non-eligible-for-compensation land, which have not violated the announced land use plans or the right of way-shall be assisted at 80% of replacement compensation. o Houses and structures on non-eligible-for-compensation land but at the time of building violated the announced land use plans or the right of way will not be assisted. If necessary, the PPC will consider assistance on the case by case basis. To ensure that the objectives of this resettlement policy are met, a special decision of the Government waiving Articles 7,18,19,20,28,29 of Decree No. l97md-cp is needed to permit assistance and rehabilitation measures for illegal users of land as proposed in the policy. (ii) Land price for compensation calculation According to the Vietnamese regulation, calculation of the unit price for land compensation will be based on the GOV Decrees No MD-CP, MD-CP with their Guidance (Circular No. 114/2004/TT-BTC and No lTT-BTC, respectively) Decree No MD-CP dated December 03", 2004 Article 9 This article states that land price for the compensation calculation is the land price in respect of land use purpose at the time of land acquisition, promulgated by the provincial People's committee inline with the Government regulation (within the GOV's range of minimum and maximum prices). Decree No IND-CP dated November 1 6th, This Decree promulgates the methodologies to define land price and, at the same time, set forth the land price framework (min. and max. unit price for various types of land) throughout the country. Article 2 This Article states that the land price shall be defined by the Provincial People's committee and/or cities directly under the central govenament..the compensation unit prices established by the Provincial/District CRCs, provincial DOFs, DOCS and approved by the provincial People's committee may be adjusted to meet the replacement costs, by the time of compensation, to ensure the objectives of the RP policy are met. v) GOV commitment

29 SEER Project 220kV Quang Ninh TPP - Boanh Bo Transmission Line GOV Decree No. 13 1/2006/ND-CP dated November 1 l m 2006 guiding the ODA management (Addmendment of Decree No. 19/200 1/ND-CP dated May 4m 200 1) and Decree No. 197/2004/ND-CP dated December 3' The Item 2 (Article 2.5) of the GOV Decree No. 13 1/2006/ND-CP dated November 11& 2006 on guiding the ODA management stipulates that "in the case of the international agreement on ODA have been signed between GOV and sponsor stipulates other contents, the international agreements will prevail". The Item 1 (Article 2) of the GOV Decree No. 17/200 1MD-CP dated May 4m on guiding the ODA management clearly states that "in the case of the international agreement on ODA have been signed between GOV and sponsor stipulates other contents, the international agreements will prevail". The waivers will be approved by GOV in the decision of project investment before negotiation. The Project Provincial People's Committees will issue the official letter for their agreement implementing the policies set forth in RP. 2.3 Definition of eligibility and limitation to eligibility DPs are all individual, firms or institution with or without land registration papers that owned, rented, or used land, properties and business, which are affected by the project. All DPs will be entitled to full compensation for their respective losses as long as they are include in the RP inventory list or can prove that they owned the affected items before the cut-off date. The same applies to DPs whose incomes are affected by the project. The subproject surveys have been carried out; the sub-project issues have been communicated to the people in the project related localities along with community participation; and T/L routes have been approved by the local authorities. It is agreed between the local authorities and PMB that the cut-off date shall be August 2nd, The cut off date is officially declared by the competent local authorities. Encroachers who settled into the proposed affected area after the cut off date will have no entitlement to compensation and resettlement. They will be required to demolish their structure and cut the trees or harvest their crops for land clearances for the project. In necessary case, they will be forced to remove out of the proposed project area. Nevertheless, they do not have to pay any fine or sanction. The cut-off date and the provision of "no compensation for encroachers" have been clearly declared in the community meetings. 2.4 Eligibility to compensation entitlement The DPs eligible for compensation include:

30 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlemenit Plan a) Those who have formal legal rights to land or other assets; b) Those who initially do not have formal legal rights to land or other assets but have a claim to legal rights based upon the laws; upon the possession of documents such as land tax receipts and residence certificates; or upon permission of local authorities to occupy or use the project affected plots; and c) Those who have no recognizable legal right or claim to the land they are occupying, if they occupy the area prior to the cut off date defined in the RJ? The DPs are identified by the baseline information collected for RP: a) Persons whose houses are in part or in total affected (temporarily or permanently) by the project b) Persons whose residential and premise andlor agricultural land is in part or in total affected (temporarily or perrnanently) by the project. c) Persons whose crops and (annual and penenual) trees are affected in part or in total by the project. d) Persons whose businesses are affected in part or in total (temporarily or permanently) by the project

31 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlemer~t Plan CHAPTER Ill ENTITLEMENT POLICY 3.1 Definition of Eligibility and Limitation to Eligibility Project Affected Households (PAHs) are all individuals, households, firms or institutions with or without land registration papers who owned, rented, or used land, properties and businesses which are affected by the Project. All PAHs will be entitled to full compensation for their respective losses as long as they are included in the PAP inventory list or can prove that they use the affected items before the cut-off date. The same applies to PAHs whose incomes are affected by the project. Encroachers who settled into the proposed affected area after the cut-off date will have no entitlement to compensation and resettlement. They will be required to demolish their structures and cut the trees or harvest their crops for land clearance to the project. In necessary case, they will be forced to be removed out the proposed project area. Nevertheless, they do not have to pay any fine or sanction Principles on Compensation and Resettlement The principles and objectives of this RP are defined in accordance with Vietnamese laws and WE3 directives, which have been adapted to fit the specific conditions of the project. The principles outlined in the World Bank OP 4.10 have been adopted in preparing this policy framework. In this regard, the following principles and objective would be applied: a) Acquisition of land and other assets, and resettlement of people will be minimized as much as possible. b) All DPs residing, working, doing business or cultivating land in right of way (ROW) of transmission line (T/L), surrounding areas of tower foundations, the substation areas, in the service roads under the projects as of the date of the baseline surveys are entitled to be provided with rehabilitation measures sufficient to assist them to improve or at least maintain their pre-project living standards, income earning capability. Lack of legal rights to the assets lost should not bar the DP from entitlement to such rehabilitation measures.

32 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlement Plm c) According to the Government Decree No. 106/2005/ND-CP, August 17th, 2005 on the protection of the high voltage networks, houses or building in RO-W- wiii be provided with subsidy aiiowance for fireproof materiais and lightning arrestors for the existing househuilding; cash compensation for the arable land; cash compensation for the directly affected rooms at the substitution cost and cost for demolishing an affected partlroom (No land-forland compensation). d) Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out via consultation with DPs to ensure minimal disturbance. Entitlements will be provided to DP prior to expected start-up of works at the respective project site. e) Institutional arrangements will ensure defective and timely design, planning, consultation and implementation of RP. Effective and timely supervision, monitoring and evaluation of the implementation of RP will be carried out. The entitlement will be provided to DPs prior to expected construction commencement at the respective project site. Compensation for land losses less than 25% of total land holding of PAP and all other losses will be provided in cash. Compensation for land losses greater than 25% of' total land holding of PAP would be provided in terms of land at the equivalent area and quality of the land acquired by the project. This RP preparation has been carried out by Power Engineering Consulting Company No. 1 in accordance with the provision of the Policy Framework with consultation and participation of DPs and local authorities. This RP has been agreed upon by the relevant local authorities and will be valid after EVN's and WB's approval. Compensation, resettlement, assistance and rehabilitation activities will only commence upon the WB's acceptance and PPC's approval of the RP Compensation policy Compensation for crops will be provided at the market price; compensation of land, houses, buildings, trees, and other assets will be provided at the replacement cost basing on the provincial unit price.

33 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Since the time from RP preparation to time of project implementation may be long, at the implementation time such prices may not correspond to the replacement rates. - lherefore, aii applied prices wiii be checked again at the beginning of W implementation and adjusted, if necessary. The Detailed Measurement Survey (DMS) will be also carried out by Resettlement committees at the beginning of project implementation. The evaluation of unit prices at the implementation time will be done by independent monitoring agency, provincial DOF. This activity will later be required in TOR for independent monitoring Entitlement Policy PAHs are classified into two kinds on basis of impact property: 1. Temporary impact: including the Households whose lands, annual crops and trees of lower than 4m are within ROW or surround tower foundation area, access roads during construction process. 2. Permanent impact: including the households whose lands are acquired for tower foundations or affected by access roads for construction or for further use during operation and management as well as the households whose structures/houses and trees are over 4m high within ROW. ~ccordingly, -the entitlement policy is defined as the follows: A. Compensation policy: I. Households impacted on lands of agriculture, forestry and trees, crops within the ROW: Lands within the ROW that are temporarily affected during construction process (due to pulling and stringing line) will not be compensated. In case of rice and annual crops, the compensation will be paid in cash to the farmers at the full market value of affected crops on base of three recent years' average harvest for the affected area within the ROW. In case of perennial plants, trees of over 4m high will be cut down. Compensation for lost of timber trees will be in cash at substitution value on the basis of type, age and productive value. Additionally, PAHs will be entitled to an one-time allowance equal to the value of a crop harvest to enable PAHs to shift another cultivation (e.g: plants of not more than 4m high or crops). 2. Households impacted on residential and garden lands within the ROW:

34 SEER Project 220kV QU& Ninh TPP - Hoanh Bo Transmission Line - No compensation is made for land temporarily affected during construction process. Lands within the ROW will still be used in compliance with electricity safety regulations. The cut down trees or affected trees due to conductor and earthwire pulling and stringing will be compensated at the substitution cost on base of type, age and affected quantity. The temporarily affected area around the foundation will be cleared and cleaned before returning to the owner. All the PAHs without LURC will be granted identification by the local authority at the earliest possible time. B. Policy on allowances and subsidies: In addition to the compensation on damages, the PAHs will be granted the allowances and subsidies as regulated in Decree No. 197/2004/ND-CP dated December 3'*, Namely: - An allowance on business income will be granted to the Households borne damages in business due to the land requisition or removing to another place. The allowance will be equivalent to the PAHs' monthly income, namely 3,000,000~/H.H. - Special Allowance: Under the law of Vietnam, a special allowance of 2,000,000 to 3,000,000VND will be granted to revolutionary families. Table of categories of allowances Categories Income Allowance Special Allowance Amount VND 3,000,000/h.h, 1 time VND 2 to 3 millions/h.h, 1 time 3.6. Classification of impacts By the nature of the project as described above and based on the survey of the PAHs, the impacted categories could be classified as below: Impact with in R igh t-of- Way (RO

35 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line All the PAP has the agricultural land or forestry land, crops, trees or structures in ROW of transmission line, surrounding areas-of tower foundations, in the temporary service road, which are temporary affected only during the construction period. Categow I: PAHs are temporary impacted of agricultural land and forest, land in ROW. Category 2: PAHs are temporary impacted of residential land and garden land, no house or structure in ROW but h it trees and another trees. Catenow 3: PAP has houses/structures, which are partially damaged or cut, and the damaged portion will not affect to the safety or using purpose of the entire house or structure (the dismantle areas are less than 25% of total areas), and the lost house/structure portion could be rebuilt in adjacent areas already owned by the PAP. Impact on cleared residential areas would be temporary as it could be reused for restricted purposes. Catego? 4: PAP has house, which are partially or totally damaged, and the damaged portion will affect to the safety or using purpose of the entire house or structure (the dismantled areas are more than 25% of total areas), so the house need to be totally removed and rebuild in adjacent areas already owned by the PAHs. Impact on cleared residential areas will be temporary as it can be reused for restricted purposes. Catego? 5: PAP has house, which are partially or totally damaged, and the damaged portion will affect to the safety of the entire house or structure, so the house need to be totally removed and rebuild. But PAP does not have spare residential land for the reconstruction of a house of equal dimensions as the house lost. Impact within foundation or substation area Catenow 6: PAP - has residential land, agriculture or forestry land which will be acquired permanently for the project, including permanent roads construction and maintenance of the project. The proposed matrix for entitlement is as below:

36 SEIEK Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line ENTITLEMENT MATRIX Type of loss No. of HHs Application Definition of entitled P Ms Compensation policy Implementation issues 5 Temporary acquisition of agricultural and forest land in ROW All PAHs have trees, crops in ROW. PAHs withlwithout land certificate included in the inventory or able to prove land occupancy prior to cut-off date. - Cash compensation for affected trees at the replacement cost, crops at market price. Number of crops to be compensated based on the time of temporarily acquired of land. - No compensation for land. -Trees have to be cut are regulated by Article 5 of the Government Decree 106/2005/1VD-CP, August 17", 2005 on the protection of the high voltage networks. - PMU and local authorities determine and ensure that compensation for trees will be atlthe replacement cost and for crops at the market price. - Full compensation at least 01 montlh before land clearance. Payment to P Ms will be delivered by PMB and Resettlement Committees. - Land in ROW can be used with the restricted purposes. 1 - Finance available for compensation and well 1 information disclose/disseminate. -

37 2 Temporary acquisition of residential and garden land in ROW without house or structures in ROW Cash compensation for affected orchards and trees at replacement cost. - No compensation for land. - Trees have to be cut are regulated by Article 5 of the Government Decree 106/2005/ND-CP, August 17th, 2005 on the protection of the high voltage networks. - PMU and local authorities determine and ensure that compensation for trees will be at the replacement cost. - Full compensation to PAHs at least 01 month before land clearance. - Payment to PAHs will be delivered by PMB and RCs. - Finance available for compensation! and well information disclose/disseminate.

38 ' SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line - Impact of residential and garden land. Partial housetbuilding within ROW (area in ROW less than 25% of total area) and the demolished area does not impact to the rexnaining househuilding Residential land and garden land outside of ROW is sufficient for reorganizing (more than 60m 2 in the urban area and 100 m 2 in the rural area). All PAHs have house I, /building, and trees/ hit trees. in ROW. I I I I I - Ditto- - Houselbuilding: * For transmission lines 5 220kV: - PAP can opt for: i) Remain their houses or building in ROW with the conditions regulated by Article 6 of the Government Decree 106/2005/ND-CP, August 17th, 2005 on the protection of the high voltage networks. Subsidy allowance for fireproof materials and lightning arrestors for the existing househuilding; or ii) Cash compensation for the directly affected rooms at the substitution cost and cost for demolishing an affected partjroom. - No compensation for land. Tree and fruit tree: - Compensation for affected trees and hit trees at the replacement cost. Allowances: - Six months relocating allowance of 30kg of rice equivalent per person per month. I - House and building have to be demolished or could be existed are regulated by Article 6 of'the Government Decree lND-CP, August 17", 2005 on the protection of the high, voltage networks. - Consultation for PAP'S options. - PMU and local authorities determine and ensure that compensation will be at the subst,itution cost, without deduction for salvageable materials. - PAHs will demolish the impacted partlroom and reconstruct/or improve their houses themselves. - Full compensation for trees and fruit trees at least 01 month before land clearance. - Full entitlement to PAHs impacted on househuilding at least 03 months beibre land clearance. - Payment to PA.Hs will be delivered by PMB and RCs. - Cleared land could be used with restricted 1 purposes. - Finance available for compensation and well information disclose/disseminate.

39 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlelllent Plan Impact of All PAHs - House/building: - House and building have to be demolished or could residential and or have Ditto- * For transmission lines 5 220kY: be existed are regulated by Article 6 of'the garden land. house1 Government Decree 106/2005/ND-CP., August - PAP can opt for: i) Remain their Impact more than building houses or building in ROW with the 17~, 2005 on the protection of the high voltage 25% or less than and trees/ conditions regulated by Article 6 of the networks. 25% of total fruit trees Government Decree /ND-CP, - ~onsultation for PAP'S options. housejbuilding in ROW. August 17th, 2005 on the protection of - PMU and local authorities determine and ensure area but the the high voltage networks. Subsidy that compensation will be at the subsl.itution cost at demolished area allowance for fireproof materials and the time of payment. will impact to the lightning arrestors for the existing - PAHs will demolish the impacted areas and remaining househuilding; or ii) Cash reconstruct/or improve their houses tliemselves. structure. Land compensation at replacement cost for outside of ROW - Full compensation for trees and fruit trees to PAHs full areas of impacted househuilding is sufficient for at least 01 month before land clearance. - No compensation for land. reorganizing - Full compensation for impacted house: and (more than 60m 2 Tree and fruit tree: allowances to PAHs at least 03 months before land in the urban area - Compensation for affected trees and clearance. and 100 m 2 in the fruit trees at the replacement cost. - Payment to PAHs will be delivered by PMB and rural area). Allowances: RCs. - Six months relocating allowance of - Cleared residential could be re~sed with restricted 30kg of rice equivalent per person per month. purposes. - Finance available for compensation/r~ehabilitation and well information discloseldisseminate.

40 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Impact of residential and garden land in ROW. Full or partial house/buildin g impacted and land outside of ROW is not sufficient for reorganizing (less than 60m 2 in the urban area and 100 m 2 in the rural area). All PAHs have house/ building and trees/ fruit trees in ROW. - Ditto- PAP can opt for one of the followings: i) Cash compensation for the whole residential area which PAP occupied (not only for the impacted areas) and properties associated with occupied land at replacement cost. Impacted land will be obtained by local authorities; or ii) "Land for land" with the same area PAP occupied and cash at replacement cost for the affected assets associated with land. Land occupied by PAP will be obtained by local authorities. - Compensation for affected trees and fruit trees at the replacement cost. Allowances: - Six months relocating allowance of 30kg of rice equivalent per person per month. - Transportation allowance according to the Compensation Decree 197/2004 CP dated December 3rd, 2004 of GOV. - Rehabilitation assistance if PAHs losing business or more than 25% of their income. - House and building have to be demolishecl or could be existed are regulated by Article 6 of the Government Decree 106/2005/ND-CP, August 17", 2005 on the protection of the high voltage networks. - Consultation for PAP'S options. - PMU and local authorities determine and ensure that compensation will be at replacement cost at the time of payment. - Replacement land, and resettlement sites tllevelopment - PAHs receiving compensation will demolish the impacted areas and reconstruct/or improve their houses themselves. - Full compensation for trees and h it trees to PAHs at least 01 month before land clearance. - Full compensation for impacted house and allowances to PAHs at least 03 months before land clearance. - Payment to PAHs will be delivered by PMB and RCs. - Cleared residential could be used with restricted purposes. - Finance land available for compensation/rehabilitation and well information disclose/disseminate. - PMU consult with PAP who are eligible to rehabilitation for their options prepare proposal for rehabilitation programs.

41 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Permanent acquisition of land for tower foundations, substation, access and service roads, etc. 4 All PAHs occupied land and properties associated with land permanent ly impacted by towers foundations, substation and access road etc. Ditto or PAP losing agricultural land:. Land loss less than 25% of their total landholdings: Cash compensation for the lost area if the remaining plot is still economic viable. Cash compensation for the whole impacted plot if the remaining plot is not economic viable. Cash compensation for properties associated with land.. Land,loss equal or more than 25% of their total landholdings: "Land for land" with the same area and productive of impacted area if the remaining plots are still economic viable and for the whole impacted plots if the remaining plots are not economic viable. Compensation for trees and affected fruit trees at the replacement cost. Rehabilitation assistance. For PAP losing residential and garden land: If remaining land is sufficient for reorganizing (less than 60m2 in the urban area and 100 m 2 in the rural area): Cash compensation for lost area and assets associated with land. If remaining land is sufficient for reorganizing. PAP can opt for cash or "land for land" compensation for the whole residential area which PAP occupied (not only for the impacted area) and properties associated with occupied land. For affected house and building, the same entitlerhent to PAP of categories 3 or 4 or 5. Consultation for PAP'S opitions. PMU and local authorities determine and ensure that compensation will be at replacement cost at the time of payment. Replacement land, and resettlement sites development PAHs receiving compensattion will demolish the impacted areas and reconstructlor improve their houses themselves. Full compensation for trees and fruit trees to PAHs at least 01 month before land clearance. Full compensation for impacted house and allowances to PAHs ai least 03 months before land clearance. Payment to PAHs will be delivered by PMB and RCs. Finance land available for compensation/rehabilitation and well information disclose/disseminate. PMU consults with PAP who are eligible to rehabilitation for their options prepare proposal for rehabilitation programs.,

42 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Chapter IV Mitigation ineasures 4.1 Mitigation measures in design stage Expansion of 220kV bays at 220kV Hoah Bo substation Land for expansion of 220kV bays at 220/1 lokv Hoanh Bo substation shall be in a hill with eucalyptus and mixed trees. The total land acquisition shall be 9328 m 2. The design is so selected to have an optimum site elevation in order to minimize soil and rock leveling. As such, the impact is rendered as inconsiderable kv Quang Ninh TPP - Hoanh Bo transmission line - To minimize effects to soil (temporarily and permanently appropriated soil, amount of dug andfllled soil), water, air and damage of people's houses and property: in designing period, it should be defined line route direction, distance and tower position reasonably to make available for construction, material building transportation, reduce effects of property, building and to be convenient in line operation and maintain later - To minimize effects of magnetic filed to human health (effects of magnetic field and safety for human): In designing period, it should be noticed + Line routes is designed as process and regulation of Electricity unit (distance between lowest line to earth is 13m in densely populated areas and 8m in sparsely populated areas) + Earthing: according to current regulation, all towers in line route are earthed as regulation to ensure construction operation and human safety. (This is also one of measures to minimize efects to proper& building of habitants in right-of. way without removing;) - To minimize effects to highway and waterway transportation, at crossroad of highway and waterway, distance from line to these construction should be: calculated according to regulation + Height sign and danger sign is designed to avoid unfortunate problems happening in construction and operation + Conductor and lightning line is protected by anti-shaking shot weight suitable for each kind of line

43 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlemerlt Plan + Auxiliaries for conductor and lightning line are suitable for line size and ensure safe factor according to regulation + All towers have restricted sign and number 4.2. Impact mitigation measures in construction stage - Reasonable construction project, with many shifts, increasing productivity, finishing at given moment for each item to reduce temporary land requisition time. - Salvaging dug soil to fill foundation hole. The redundant is supplied for foundation foot or rammed to avoid transportation obstacles of habitants. - Construction activities should be conducted after harvesting crops. - Do not allow the Contractor to extend plant cutting area outside of defined right- of-way. - Do not cut trees under safe height as regulation. - Supervise quality of highway on temporary road to timely re.cover, repair damage and avoid effect to local transportation. - With special characteristics of this construction, we should build new camp for workers but renting houses at residential area. Worker's camp and material store should be in region which the line goes through.

44 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Chapter V Public Participation 5.1 Objectives of information campaign and consultation program Information dissemination to, consultation with and participation of affected people and involved agencies (i) reduce the potential for conflicts, (ii) minimize the risk of project delays, and (iii) enable the project to design the resettlement and rehabilitation program as a comprehensive development program to fit the needs and priorities of the affected people, thereby maximizing the economic and social benefits of the project investment. Minutes of community meetings are attached in the annex. The objectives of the Public Information Campaign and PAP consultation^ Program are as follows: - To share hlly information on the proposed project, its components and its activities, with the affected people. - To obtain information about the needs and priorities of the effected people, as well as information about their reactions to proposed policies and activities. - To obtain the cooperation and participation of the affected people and communities required to be undertaken for resettlement planning and implementation. - To ensure transparency in all activities related to land acquisition, resettlement and rehabilitation. There are two phases of the public information campaign and PAP consultation: Phase I: RP preparation During resettlement planning and RP preparation activities. This phase consisted of line route selection, detailed measurement survey (DMS) of affected assets, and identification of strategies for relocation. Phase 11: RP implementation During the implementation of resettlement and rehabilitation activities. This phase will consist of information dissemination and consultation regarding: resettlement policies and procedures; calcstilation and payment of compensation; relocation options, sits and designs, resettlement site and house construction, and clearance from the project area.

45 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line 5.2 Phase I: Information campaign, PAP & agency consultation during resettlement planning and RP preparation During phase I, the phase of detailed resettlement planning and RP preparation, the following activities were carried out sequentially: * Phase I - Activity 1: Information & discussion with local authorities on the line route to be rehabilitated. After studying maps and visiting the site, PECC 1 had envisaged a preliminary route on 1150,000 scale map. This map was sent to all locations passed by the line and relevant local authorities. The local authorities have agreed on the project line routes. This activity was completed in Phase I - Activity 2: Impact survey and statistics Based on the agreed line routes, survey teams had realized the routes at sites, made the piling and coordinated with the commune officials to make a list of PAHs' affected land and crops. The socio-economic survey forms were delivered to affected households (for each commune) as basis for SLS. This activity was completed in Phase I - Activity 3: Meetings with PAHs When the survey finished, PECC 1 in coordination with the commune officials held meetings with PAHs having land in the line ROW and with village representatives. In these meetings, PECC 1 officials informed the participants of the project purposes; presented the project impacts on land and crops in detail; introduce the principles and policies of compensation and advised people not to build new structures in the line ROW. PAHs were consulted on the entitlement policy and the compensation in cash had been accepted. This activity was completed in Phase I - Activity 4: Meetings with concerned PPCs Together with working with the communes, in 6+7/2007 PECC 1 would send missions to work with the provincial functional agencies such as Financial and pricing service, Planning and investment service, Agriculture and rural development service, Natural resources and environment service, etc. and make the project purposes clear to PPCs; at the same time discuss with local officials on the aims and principles of ground clearance, on the proposed policies of RP, legal and illegal issue, grant of LURC in the localities and the local organization working on resettlement and compensation; collect the local compensation rates for land and crops. Phase I - Activity 5: Consultation on RP

46 SEER Project Resettlement Pla 220kV Quang Ninh TPP - Hoanh Bo Transmission Line - Basing on the survey result, PECCl shall prepare RP to submit to Hai Phong power one-member company Ltd., WB and concerned PPCs for revision. All - comments shall be taken into consideration, incorporated in the next version for approval by relevant authorities. Phase I - Activity 6: Approval of RP The revised RP shall be submitted to WB for approval. EVN shall ask the provincial authority for approval of RP policies to enforce them in the province. This shall be legal basis for RP implementation. However, 25 PAHs are located sparsely in the project area and most of.them argreed to remain within the line ROW with adequate compensation. Therefore, there is no mention of a resettlement site in this report. 5.3 Information campaign & consultation during resettlement implementaltion Phase I1 - Activity 1: Information dissemination and training of RBs: After the signing of the loan agreement, the first resettlement activity is to sign contract with PRBs on resettlement implementation. NPPMB will provide local RBs at all levels with information on policies for PAHs, detailed information about RAP policies and implementation procedures of local meetings. Phase I1 - Activity 2: Information on resettlement document and compensation form distribution to PAHs before starting another DMS: Local RBs will carry out an additional DMS to make a detailed compensation form for PAHs as basis for preparing. The following activities must be implemented before starting the additional DMS: * Activity 2a: Distribution of compensation forms for lost assets and resettlement information booklets (RIBs) to PAHs. RIBS described in item 7.4 will be distributed to PAHs together with a form for listing lost assets. Additionally, they are given by radio, TV, local broadcasting means, posted public notices at tlhe offices of commune people's committee and DRBs. * Activity 2b: After distributing RIBS and compensation forms, RBs of ixll communes should organize meetings to explain RIB and instruct PAHs to list their affected assets in the compensation forms. Meeting invitations must be given to PAHs. Time, place of the meeting must be informed by local broadcasting means and posted public notices. In these meetings, PAHs can raise their questions on any resettlement issues. Phase I1 - Activity 3: Meeting with PAHs on compensation payment.

47 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line ' After getting statistics on lost assets in the line ROW, organize meeting with PAHs to introduce the compensation rates for different impacts. Table of compensation rates wiii be posted in the ofiices of commune peopie's committees. At the meeting PAHs can comment on the proposed compensation rates. Disagreement on compensation rates will be noted down and collected for consideration. Recommendations, if any, will be sent to PAHs for revision and modification if necessary. Besides, PAHs will be informed of time, location and process of compensation payment for the damages. plan. This meeting is scheduled to be held right after completion of compensation Phase 11 - Activity 4: Application of compensation price. The adjusted compensation rates are proposed to be made valid by DRBs and district RBs. PAHs who agree with compensation price for their assets will sign on the compensation form. Disagreement comments will be recorded. Phase I1 - Activity 5: Information to local authorities on implementation schedule. Inform commune authorities and PAHs about construction schedule and procedures as well as the project schedule. PPSs will keep the commune and district RBs informed of schedule for the project components concerning each locality. Commune and district RBs must coordinate with PPSs to ensure that all PAHs know well about compensation and implementation schedule. -

48 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line - Chapter VI BASELINE INFORMATION 6.1 Data gathering activities Power Engineering Consulting Company No.1 with the help of local authorities conducted a census in rural areas, Inventory of project impact in May The inventory works include: Census of all DPs impacted by the project. Survey for DPs, who have houses in the proposed location. Survey for DPs, who have trees impacted in the proposed locations or ROW (according to Decree No. 106/2005-NDICP dated 17/08/2005). Survey for impacted public infrastructure, properties, and means of transport. Survey for land acquisition area for tower foundation. Survey for temporary land acquisition area. Survey for other impacted area. 6.2 Socio-economic survey. The 220 kv Quang Ninh TPP - Hoanh Bo transmission line would traverse following areas: Quang Ninh province: district of Hoanh Bo: communes of Thong Nhat, Son Duon,g, Troi town; and Ha Long city: Viet Hung ward. The total length of the line in the selected alternative would be 20.1 km and its ROW would be m wide. Quang Ninh is a mountainous province, it is north east of the country. The province total are is 5,938.6 km2, its population in 2005 was - 1,184,200 Quang Ninh province has 12 urban districts and 1 city Statistics and survey Surveys on the project impact were conducted during preliminary survey stage. PECCl had sent 2 survey teams to the relevant provinces for site survey arid measurement. Each survey team of 5+6 persons was responsible for 10 km. Duririg the survey, these teams had worked with the local cadastral officials.

49 SEER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line In addition to statistics on the project impacts, socio-economic data on PAHs were also collected. These data are used not only for RAP but also for FS preparation, evaluate the project socio-economic benefits. The census forms were prepared for PAHs having houses in the line ROW (severe impact) and some PAHs having land in the line ROW (small impact). Refer to survey form in the Annex. Survey on socio-economic conditions was carried out to evaluate and. identify characteristics of the project communities, evaluate standings of population, houses, main economic activities and income, etc. These data were used in. establishment of RAP policies as well as assess the project economic efficiency. The survey shows that: *:* Population Household characteristics: - The average number of people per household is 5, compared to 5 of the: whole country. Large households usually comprise of 193 generations. - Most households are headed by men, female heads of households are mostly windows - Young people (Os17 years) represent 15-20%. - The productive age group (18s54 years) accounts for 35-55%. - Old people (over 55 years) take 25-50%. *:* Housing condition Type of dwellings Ministry of construction classifies buildings into 4 classes: 1,2,3,4. Buildings of class 1 & 2 are permanent structures with modem facilities & interior decorations, private toilets & bathrooms, separate living rooms & bedrooms. This type of buildings is usually located in big city centers, there is no such building in the ROW. Buildings of class 3 are permanent structures with brick wall, reinforced concrete roof, brick floor, conventional facilities & interior decorations. There are 3 structures of this type. Buildings of class 4 are semi-permanent structures with brick wall or wooden "wall in the rural areas, tile roof zind-"galvanized iron sheet, brick or cement floor and usually without toilets.

50 SEIER Project 220kV Quang Ninh TPP - Ho-an. Bo Transmission Line Beside the above mentioned classes, in the rural Vietnam there are a lot of non-standard houses such as class 4 houses with soil wall, thatched roof & soil floor. Additionally, there are huts with thatched roof surrounded by bamboo's only. These structures are usually used as auxiliary structures, by-road hutches, animal stables, etc. ones. The survey data show that most houses belong to class 4 and the temporary Plot size Most households have large arable plots. About 113 of households have garden area of over 500m 2. Houses are usually constructed in this area therefore: sometimes it is difficult to identify residential & arable area. Generally, the project areas are sparsely populated, the average residential area is m2/household~, very small compared to the household garden area. Beside garden, PAHs also have 500m2+3000m2 agricultural land for cultivation. Cultivation in this area is mainly on rice, maize, corn, industrial crops like teas, litchis, longans, eucalyplus, jacqkfruits, pines, etc. Amenities PAHs' modem facilities are not much. 80% PAHs have motorbikes, over 90% PAHs have TV sets, 95% have bicycles, 100% have radios. Pumped water accounts for 90% while stream water and well water account for 10% of the total PAHs. A11 PAHs in the project area are supplied electricity by the power network. *:* Economic activities Agriculture Farmers represent 50% of PAHs. Most of these PAHs are affected by agricultural land acquisition and impact on crops in the line ROW during construction process. The line traverses low population density area. The survey shows that PAHs have large arable land, many PAHs have over 1500m 2 of arable area. PAHs' main cultivation is on rice, maize, cassava. Besides, they also plant orchard trees, etc. Through working sessions with local au~horities, it is known that there are relatively large wild lands in the project areas. Some areas are not filly exploited. Water sources & initial investment capital (quite a big amount) for industrial trees are main difficulties.

51 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Trade PAHs with income mainly from trade account for moderate portion. These PAHs mainly concentrate in the town center, along the highways. However, some fmer families also make earning from trade but the quantity is not much. Forestry The affected forested land is scattered through out the concerned province. However, only few PAHs have gross income from forestry, they also make income fiom agriculture. It is usually very difficult to point out the main income source. Income * Source of income: PAP'S main source of income is from agriculture (30%), livestock breeding and services (10%). About 60% of survey PAHs have secondary source of income. This source accounts for 10% of the total income. * Level of income It is very difficult to specify PAP exact income as PAHs themselves can not point out their income exactly. PAP income changes frequently when the price of' agricultural products, especially coffees change so much & so often. The average monthly income of PAHs is 1,000,800 VND. Some PAHs earn over 30,400,000 VNDhonth. Meanwhile many PAHs earn less than 1,000,000 VND/month.

52 SEER project' 220kV Quang Ninh TPP - Hoanh Bo Transmission Line Resettlement P1a1 Chapter VII PROJECT IMPACTS The 220 kv Qnang Ninh TPP - Hoanh Bo transmission line would traverse mainly rice fields in Quang Ninh province: district of Hoanh Bo: communes of Thong Nhat, Son Duong, Troi town; and Ha Long city: Viet Hung ward. The total area of the project ROW is 80,344 m 2, of which 39,1% is agricultural land; 12.5% is forest land; 6.2% is garden and residential land; the remaining 42.2% is waste land. Project impacts: * Houses/structures 'in the ROW required to be allocated or remained with restrict conditions. * High trees planted in the tower foundation area of the ROW: the distance between the top of the tree to the lowest position of the T/L is not less than 3m. * Project permanent land acquisition (for tower foundations). * Temporarily affected land within the ROW * Land around the tower foundation during foundation excavation and tower erection * Land use for access road: material transportation to the tower locations * Temporarily affected land within the ROW 7.1 Types of impacts * Impact on land - Temporary impact on residential land : 4,974 m 2 - Permanent impact on residential land 1581m2 - Temporary impact on agricultural land : 31,398 m 2 - Permanent impact on agricultural land : 1,940m2 - Temporary impact on forest land : 10,060 m 2 - Permanent impact on forest land : 7,790 m 2 - Temporary impact on other land : 33,912 m 2 - Permanent impact on other land : 5,669 m 2 * Impact on houses and structures - Temporary impact on houses :Om2 - Permanent impact on houses * Impact on trees and crops

53 SEIER Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line - Temporary impact on rice : 23,936 m 2 - Permanent impact on rice : 1,169 m 2 - Temporary impact on litchi, longan : 7,462 m 2 - Permanent impact on litchi, longan r770m2 - Temporary impact on keo r 1,400 m 2 - Permanent impact on keo : 808m2 - Temporary impact on eucalyptus : 3,532 m 2 - Permanent impact on eucalyptus : 955 m 2 - Temporary impact on pine : 5,128 m 2 - Permanent impact on pine : 6,027 m 2 * Displaced persons Total number of DPs is 77 HHs (362 persons), of these: DPs with houses/structures, which are partially impacted: 25 HHs DPs with permanent acquisition of residential land, agriculture or forestry land: 52 HHs a. Temporary land requisition Land will be requisited temporarily in 2 cases for: foundation works, tower erection, material transport to the line route. Conductor and earthwire pulling and stringing. As the scope of the project is inconsiderable, each component can be completed in 2+4 months. Thus the impact will be on one crop time. Consider commencement right after harvest of annual crops, if possible, to minimize the project impacts. The total temporary requisition of the project is 80,344 m 2. Statistics on the project temporary acquired land:

54 SEIEK Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line CLASSIFICATION OF TEMPORARY IMPACTS ON LAND WITHIN ROW Location I Total temporary requisition I area (m2) Requisition Agricultural land (m 2 ) area within Longan+ ROW (m 2 ) Rice Litchi Forest land (m 2 ) Natural forest 1 Timber I Eucalyptus 1 Pine 1 Other non- agricultural land Residential land (m2) QUANG NINH PROVINCE HoPnh B$ district Th6ng nhit commune Sun Dung commune l'r& town Ha Long city 2840 ViCt Hng ward 2840 PERCENTAGE (%) 100

55 SEIER Project, 2201cV Quang Ninh TPP - Hoanh Bo Transmission Line b. Impact on permanent land acquisition The total permanent acquisition of the project is is included of agricultural land, garden and residential land, waste land andl pond area. Permanently occupied agricultural and land tenure, land area for building foundations is: 15,979 m2 Statistics on the project permanently acquired land: CLASSIFICATION OF PERMANENT IMPACTS ON LAND WITHIN ROW Location Temporary requisition area (m2) Agricultural land (m 2 ) I I Long an+ Rice Natural forest Litchi Forest land (m 2 ) I Timber I Eucalyptus Pine Other non- Residential agricultural land land (m') QUANG NINH PROVINCE Hoanh Bo district Th6ng nhgt commune Son DOng commune Trdi town Ha Long city Viet Hng ward PERCENTAGE (%)

56 abier Project 220kV Quang Ninh TPP - Hoanh Bo Transmission Line c. Impact on houses and structures The line routes mainly traverse low hills, rice field, crop and fruit areas, populated areas. According to survey statistics, totally there are 5 structures crossed by the line and 20 ones located in the line ROW. STATISTICS ON AFFECTED STRUCTURES Location Quing Ninh province (Total) Head of Household l No. Of Concrete house Tiled brick house Impact om house area (m 2 ) I I I Temporary Permanent I Temporary Permanent I Temporary ( impact Iron-roof house Permanent impact impact impact impact impact I t I I I Total --+- I Temporary Permanent impact impact Hohnh Bd district Th6ng nhd't commune Sun Dong commune Trdi town Ha Long city Viet Hng ward

57 Rural Distribution Project 220 kv Quang Ninh TPP - Hoanh Bo transmission line 8.1. Implementation measures Information to PAHs Chapter VIII IMPLEMENTATION ARRANGEMENT All PAHs are entitled to be informed of the entitlement policy, compensation rates for each type of impacts, right to participate into land acquisition, avenue l:o grievances, etc. RIB shall be distributed to all PAHs or at meetings of provinces, districts, communes; be announced on television, radios, newspapers; be macle public in places like CPCs' offices, schools. Dissemination to people right after project approval of EVN and WB. The content of the RIB are outlined below: 1. Date of project implementation 2. Eligibility and ineligibility to rights on compensation and resettlement 3. Principle on compensation for only PAHs that use the land before surve:y and official announcement of the state agencies for land acquisition Time for compensation and resettlement As the project only has impacts on houses, st&ctures, trees and crops, compensation payment shall be made only once for the entire loss. Compensatioln for land, houses and trees, crops shall be made at least 2 months prior to land acquisition. Allowances shall be made at beginning of each month (within 1-5 f ~st days) for the period entitled to allowance RAP implementation process RAP activities are classified into 3 types: a. Overall activity: takes place only once at beginning of the project implementation b. Separate activity: takes place at beginning of each project componerit implementation c. Continuous activity: takes place continuously during RAP implementation Basic activities of project Activity 1 :

58 Rural Distribution Project 220 kv Quang Ninh TPP - Hoanh Bo transmission line Right after approval of the RAP, PMB must select and contract an independent monitoring organization, the organization shall be approved by EVlN and wl3. Activity 2: Basing on the contract requirement of PMB, the involved provinces shall decide to start RAP programs. Activity 3: DRBs shall obtain statistics on affected assets and specify the compensatioln rates, check and adjust, if necessary, the compensation according to the unit price and equivalent cost. Activity 4: Upon completion of statistics works, DRBs shall review and specify th~e exact number of PAHs, affected assets and total compensation for PAHs. Activity 5: RBs shall inform RAP policies, project schedule and information on RAP implementation for PAHs via meetings. Such advices include issues relating to compensation and resettlement program. Activity 6: Compensation payment to PAHs having houses affected first, help them to repair houses and stable their lives then comes compensation for other properties. Temporary LURCs shall be granted to all PAHs and permanent LURCs shall be given to their representatives. Activity 7: During all implementation process, IMO, independent monitoring organization shall monitor the project implementation, propose keys for problems. 8.3 Grievance and appeals Since the entire resettlement and rehabilitation program is being carried out withthe participation of DPs and the impacted scale of this scale is relatively small, :it is expected that there would be no grievance (related to the resettlement and compensation), the detail procedures for solving grievance are prepared for the project. The mechanism is designed to be easy, transparent and fair, the procedures are as follows:

59 Rural Distribution Project 220 kv Quang Ninh TPP - Hoanh Bo transmission line First step: If any person is aggrieved by any aspects of the resettlement and rehabilitation program, he/she tail lodge an oral or written grievance with the commune authorities. The Commune People's Committee will resolve the issue within fifteen days fiom the date it receive the complaint. Second step: If any aggrieved person is not satisfied with the decision in stage 1, shehe can bring the complaint to the District People's Committee (DPC) lor District Resettlement Committee (CRC) within fifteen days fiom the date of the receipt of the decision in stage 1. The District Resettlement will reach a decision on the complaint within fifteen days. Third step: If the DP is still not satisfied with the decision at district level, he/she can appeal to the Provincial People's or Provincial Resettlement Committee (PRC) within 15 days of receiving the decision of the DPC or DRC. The Provincial People's Committee or Provincial Resettlement Committee will reach a decision on the complaint within fifteen days. Fourth step: If the DP is not satisfied with the decision of the Provincial level, the case may be submitted for consideration by the District Court within 15 days of receiving the decision of the PPC or PRC. The district court's decision will be a legal basis for compensation. DPs will be exempted fiom all administrative and legal fees. DPs can make an appeal on any aspects of resettlement and. rehabilitation program, including the compensation unit price. The detail procedures of solving grievance will be disclosed to all DPs in tlhe public meetings and at the CRC offices. This information is also contained in RIB, disseminates to all DPs promptly after the commencement of the project. 8.4 Monitoring and supervision The implementation of RP shall be constantly supervised and monitored by PMB in co-ordination with the local People's Committees Internal monitoring Internal monitoring includes the following activities: - Monitoring the population, socio-economic surveys, and inventory of DPs' assets. Monitoring whether the implementation of compensation, resettlement and rehabilitation for DPs in accordance with the provisions that DPs agreed. - Monitoring the implementation of compensation and resettlement tasks. - Monitoring the availability of finance and schedule of RP implementation. - Investigating and fairly assessing each case of grievance and complaint.

60 Rural Distribution Project 220 kv Quang Ninh TPP - Hoanh Bo transmission line - - Preparing the quarterly report detailing the process of RP implementation. Such report should be made available to GOV authorities, WB and external monitoring agencies External monitoring - In addition to verifying the information furnished in the internal supervision and monitoring reports of the respective PCs, the external monitoring agency will be responsible for the following: - At the beginning of RP implementation, review compensation unit cost applied in RP, check at the site for ensuring that the compensation costs are at the replacement value, or otherwise recommend to PMB and PPC for adjustment. - Evaluation of DMS, inventory and entitlement to DPs. - Evaluation of socio-economic project impact on the DPs. - Supervision of the implementation of RP to achieve the objectives of the RP in particular "to improve or at least maintain the incomes and living conditions of the DPs after resettlement" - Recommendations on amendments for the implementation of RP so as to achieve: the objective of this RP. - Recornniendations on improvement of RP programs. - Closely monitoring of compensation activities and be ready for evaluation of' complaint and grievance cases. - Preparation of reports and submission to PMB, appropriate GOV authorities, the WB and the representatives of the DPs every 6 months. - Write final report (6 months after entire accomplishment of the resettlement program). This report shall provide detailed evaluation of RP and its implementation, including the content of interview with DPs about the situation and their opinions after receiving compensation and resettlement. - Finally, on the bases of RP implementation experience, this final report shall provide suggestions to enhance the local RP implementation experience and improve FU? in the future - Terms of reference for independent monitoring will be prepared by PMB and will be sent to WB for its concurrence prior to invitation for independent monitoring consultant.

61 Rural Distribution Project 220 kv Quang ~ inh TPP - Hoanh Bo transmission line Chapter IX COSTS PY.W BUDGET 9.1. Budget Funds for implementing RPs: Fund for land acquisition and resettlement will be at E\Ws cost as part of the project budgets. The Provincial Investment Department will transfer money to PRBs and then money will be transferred to the following agencies: - DRBs: compensation for PAP, payment for ground clearance in their areas. - Other institutions engaging in resettlement activities: IMO and those providing training services. - DRBs receive money from PRBs and will be responsible for: (a) payment of compensation directly to affected persons for lost of land, crops, trees and structures, allowance (b) payment of compensation for permanerit land acquisition Inflation adjustment The rates of compensation and cash entitlements for rehabilitation and allowances payable to the affected persons will be adjusted amiually, based on the actual annual inflation rate upon request of Ms Implementation, administration and contingencies costs Preparation costs include costs already made for land demarcation, spotting and DMS. They include also the costs of training for various resettlement boards (PRB, DRB, CRB); payment (Salaries, per diem) for resettlement boards; payment to conduct necessary surveys; and payment to conduct monitoring Bases for cost estimation of land acquisition and resettlement - The new 2003 Land Law on December 10" Decree 106/2005lND-CP dated August 17", 2005: Protection for MV power network. - Government Decree No.64/CP dated 27th September 1993: Regulations concerning the distribution of agricultural land to households antd individuals to use in a long term and stable manner for agricultural production. - Government Decree No.871CP dated 1 7h August 1995 : Regul-ations concerning the price of different land types. - Government Decree No. 197lCP dated 3rd December 2004 and Circular No. 116 dated 7" December 2004 on compensation and resettlement when the State

62 Rural Distribution Project 220 kv Quang Ninh TPP - Hoanh Bo transmission line recovers land for national defense, security, national and :public interests in accordance with the existing Land Law. - Circular No.05-BXDDT dated Ogm: Regulations concerning the classification of house types. - Decision of PPC on Unit Prices of Compensation. - Decisions of PPC on Compensation for Land Requisition for purposes of security, national defense and public benefits. - Other decrees and circulars. - All prices will be checked again and if necessary adjuste:d one more time as of the Detailed Measurement to be carried out before project implementation. COST ESTIMATE Compensation cost : ( ) Permanent land acquisition: Residential land : 58 1m2 x 600,00Od/m2 Agricultural land : Rice, crop: 1,169 m2 x 16,90Od/rn2 Fruit trees: 770 m2 x 105,00Od/m2 Other land : 5,669 m2 x 500d/m2 Forest land : 7,790 m2 x 2,625d/m2 Com~ensation for crops, trees : (a + b +c 1 Permanent land acquisition : Rice, crop: 1,169 m2 x 2,30Od/m2 Fruit trees: 180 trees x 150,00Od/tree Eucalyptus : 319 trees x30,000d/tree Temporan land requisition Rice : 23,936 m2 x 2300dlm2 Fruit trees: 700 trees x 150,00Od/tree Eucalyptus : 925 trees x30,000d/tree Keo: 450 trees x35,000d/tree Pine: 1230 trees x30,000d/tree Compensation for stringing works in the ROW Fruit trees: 3500 trees x 150,00Od/tree Eucalyptus : 4,625 trees x30,000d/tree Keo: 2250 trees x35,000d/tree Pine: 6,150 trees x30,000d/tree Umit : VND 2,602,752, ,040, ,600,00(

63 Rural Distribution Project 220 kv Quang Ninll TPP - Hoanh Bo transmission line ReseElemen? Plan Compensation for safety cleareance in the ROW Eucalyptus : 260 trees x30,000d/tree Pine: 320 trees x30,ooodjtree Compensation for houses and other structures (a + b 1 Houses and structures Houses class-i: 145 m 2 x l,loo,oood/m l Houses class-iva : 954 m 2 x 650,000d/m 2 Houses class-ivb : 40 m 2 x 550,000d/m 3 Allowances Implementation cost Administration cost : 2% (I) Cost for independent mornitoring SUM (I+@ ' Contingency cost (estimate) 10% (I+II) Total

64 Rural Distribution Project 220 kv Quang Nidl TPP - Hoanh Bo transmission line ANNEXES

65 ANNEX 1 STATISTICS ON LINE LENGTH AND _PE_R_MAM,NT LAND ACQLJISTTION I Location QUANG NINH PROVINCE A l~ohnh Bb district 1 Th6ng nhgt commune 2 Sun Duung commune 3 Trdi town C B Ha Long city Line section TO To. 49, Line length (m) Area for substation -- Remark To To. 51 Total

66 ANNEX 2 ST-a,TISTICS ON P-4H.C Location 1 PAHs 1 PAPS I Annually average income (million dong) QUANG NINH PROVINCE Hoanh Bo district T'hdng nhgt commune Sun Dumg commune Trdi town Ha Long city Vi$t Hung ward

67 -- ANNEX 3 STATISTICS ON AFFECTED STRUCTURES Impact om house area (m 2 ) NO. of Concrete house T~led brick house Iron-roof house Location Head of Household HHs Temporary Permanent Temporary Permanent Temporary Permanent Temporru impact impact impact impact impact impact impact Quing Ninh province (Total) I I~ohnh Bd district 1 (~hbir~ nhal commune NguyBn Thj Quay 1 40 LR Van Qu6n U Val1 Minh - Nguyh Thi Ly 1 50 Db Van Hiing Db Van Xuan I 1 50 NguyBn Thi DuTmg 1 39 D6 Van Mai 1 40 Hoang Van Tj L Hohng Van Vien 1 50 Trdn Van Quang 1 L 40 ppp-p Trin Van Huang 1 50 Dang Van Hang Dang Van lniii

68

69

70

71

72

73 ANNEX 5 CLASSIFICATION OF PERMANENT IMPACTS ON LAND WITHIN ROW I Location

74

75

76

77 CONG HOA X& HOI C H NGH~A ~ VIET NAM Doc lap - Tg do - Hanh phuc BIEN BAN HOP THAM VAN CONG DONG BAO cao DEN BU TAI DINH cu Dkr in : Duhg day 220kV QuAng Ninh - HoBnh B6 H6rn nay, ngby {q thiing 4 nsm 200e tpi UBND ~.5.1/1&.dI%/~... Huyen... r...tinh...&.~.+..j82/!&...:... n + Dai dien.rfp.&.2... UBND xii :... v&..&*... y..... Hu yen :.Tinh...&...../N&.... bng.(8):....k;gm.y..h$... ~hlic vu..go..uw Dai dlen cic t6 chuc xa hqi... Ong (B": f@i&@"$..~&hirc vu:..w:.*.. hi..... Ong (BB):.&L?... M....&.Q.?... ~hirc vu:...&iu.h.:.&h..&/&kn-... Ong Chc vu:... ang (BB):... C h V~I:... A Ong (BB):... Chc vu:... + Dai dien C6ng ty CP. TL~ vgn xay dkrng dien 1. Bng (~a):.p~qc;l.~;rm~.&~hirc vy:...&:... RO~..;~TC... Ong (BB):... Chtlc VL!:... + dai dien cic 110 bj Hnh ll~rbng: (danh siich kkrn theo). + Cic ben d2 chng nhau xem xkt, thio lugn ph~rang in den bh, gii ph6ng mijt bhng c6ng tsinh: Duhg day 220kV Quing Ninh - Hohnh B6. - Dai dicn C6ng ty CP. TL~ viin xay dqng dien 1 d.5 tdnh bhy viec x&y dlrng D~rbng day 220kV Quing Ninh - Hohnh Bd cfing nhu th6ng qua sd lieu khbo sit, cli6u tra inh h~r6ng ci~a tup611 cl~rbng day cldi vdi d2n c~r, dja phurong c6 ~uy6n d~rbng day di qua, kg hoach vb ciic chin11 sich d6n bi~, giim thieu thiet hai: + C6c chinh sich d6n bh dubqc l+p tren co sh phip 19 sau: - Lu$t dgt dai n8m 2003 c6ng b4 nghy 24/12/ Nghj djnh 22/1998/ND-CP ngiy 24/04/1998 q~iy cljnh V/v d&n bii thiet 11ai khi NhB N~r6c thu h6i d6 sir dung v8o myc dich Qudc phbng, an ninh, lqi ich c6ng cong. - Nghj djnh sb 106/205/ND-CP v6 b60 ve an tohn l~r6i dien cao ip. - Nghj djnh s4 64/ND-CP nghy 27/09/1993 quy djnh V/v giao da"t nn8g nghiep cho cic h? gia dinh, ci nhan sir dung Bn dinh lau d8i vho muc dich SX ndng nghiep. - Nghj djnh so" 87/ND-CP ng&y 17/08/1995 quy dinh vc khung gi6 ccic lo$. - Th6ng tu 05-BXD / DT ngiy 09/02/1993 v6 phiin ciip nhb 3. - Quy pham trang bi dien, ph$n 2 HTD-llTCN do BQ c8ng Nghiep ban hbnh nghy 11/07/2006 Ong (BB):~..;&.:.CI; I&... chttc vv:... h.~.l.:'t&~!.$~i$

78 - Cic Th6ng tu chi.thi lien qua khic. + Cu6c hop bi d6n ke"t lugn nhu sau:... / ~ adien i.dai dicn Dai d:@n CTCP. TVXD bien 1.. T" UBNDXHY&&~ o chirc 1x2 hoi.. Dai dien Td chiicyl.=,. -.J-I hqi Dai dien Td ch3c xii hgi Dai di$n T6 chuc x2 hei

79 CONG HOA XA HOI CHU NGH~A NAM, Boc lap - Tq do - Hanh phuc... DU &I : Duhg diy 220kV Quing Ninh - C:,.... ha<& b y ~ b nay, h nghy.da thing 4 narn f tai UBND &i./... HsyCn...:...Tin...: Dai dien UBND xii :... Huyen...Tinh..., \. 29&. Ong.?%&? f. : ) ~i ( ,.>>... :.\ '.... Dai dlen cic tb chirc_xghqi; \.... a :., Ong ( ~ij:./jlj.. I:.L.~QLI.~LLQ?o...CMC vu:....cyui.?l~~. P?&~.?Z(T?~ Ong (Bi):...;... 3 vu: : A Ong (Bi):... Chc vu:... A Ong A (Bi):... Ch3c vu:.:... Ong (Bi):... Ch3c vu:... A Ong (Bi):... Ch3c vu:....(.. > Tq4; 6&.. VLI: f...&~t~k$~i...~4dz!.4? + Dai dien CBng ty I, CP. - 7 Tu va"n xiy dmg dien 1.. Ons (~i):/ii#.&yc'~?..~~~y..lii&chir~ vu:... C&..f..ZX... Ong (Bi):... '... Ch~c vu:... ;... + Dai dien c5c ho bj inh hubng: (danh sich kkm theo). + C6c b&n dii cbng nhau xem xkt, thio lugn phumg in den bg, gii phong m?t bang cbng trinh: Dtbng d8y 220kV Quing Ninh - Cdm Phi. - Dai dien C8ng ty CP. TL~ v$n xiy d~mg dien 1 d.3 trinh biy vice: xay dwg Dlrhlg day 220kV Quing Ninh - dm Phi cgng nhu th6ng qua sb lic~i khio sit, di6u tra inh.h~rhng ciia tuygn duhg day bbi v6i din cu, dja ph~rang c6 tuygn d~rhg d2y 'di qua, kg hoach v?i cic chinh sich den bb, giim thi$u thiet hai: + Ciic chinh s5ch den bb dugc l!p tren ca s6 phip 19 sau: - LuGt ba"t dai nam 2003 c6ng b6 ngiy 24/12/ Nghj djnh 22/1998/ND-CP ngiy 24/04/1998 quy djnh V/v din 132 thiet hai khi Nhi Nudc thu h6i dk sir dung vio muc dich Qudc phbng, an ninh, lgi ich c8ng c6ng. - Nghi djnh so" 106/205/ND-CP vc bao ve an toin ludi dien cao ip. - Nghi dinh sb 64/ND-CP ngiy 27/09/1993 quy dinh V/v giao diit nn8g nghiep cho c8c h6 gia dinh, c6 nhan sir dung 8n dinh liu dii vio muc dich SX nbng nghiep. - Nghj djnh so" 87/ND-CP ngiy 17/08/1995 quy djnh vd khung gig cic loai. - Th6ng tu 05-BXD / DT ngiy 09/02/1993 v6 phin cilp nhb 6. - Quy pham trang bi dien, ph6n 2 HTD-1 ltcn do Be c6ng Nghiep ban hinh ngiy 11/07/2006

80 Ph!i ltrc kt?m theo bien 6611 hop rham vhz dd'ng c6o din i5bir thi djnh rlr Nghy dd thdn$f ndm 200 f ~ : T ~ j&$,/ i. DANH SACH CAC HO BI ANH H ~ ~ N G STT Ho vh ten Ky ten STT ' Ho vh ten 8 c M..

81 - Cic Thong tu chi tq lien qua khk. + Cudc h ~ bi p be"n ke"t luan nhu sau:... /- - I?% a91*~.:. ha! ~(gtr;.&!.i.. lut.t.. -1%. a& ca&... r' R'--.:l@:....br.i....f.zpd..gut, L&iF~??' mfi 20. A! "1 ~CL4??!. ' A,:. 4...d~i.:. mi... afa n ~.Z.:... 8/47 ae+...qq. Dai dicn Dai di&n.-,..-if Dai dicn CTCP. TVXD dien dicn 1 --"' ".....A : xk :(L(i L8., 1 -:.idnd; -L.:.iU,gND:xk:..,..:.:.. - :-..I..y,..,!.:!-J '1', :.:. ; '. i r,.. :, j,.!;. I.., I - 6, Dai dicn TO chirc xz hqi Dai dicn T6 chirc xz hei Dai dien Td chlsrc x:i hbi

82 CONG HOA XA HOI C H~J NGH~A V@T NAM. Doc lap - Tu do - Hanh phuc....- * BIEN BAN HOP THAM VAN CONG DONG BAO cao DEN BU TAI DINH cu Du-an : Dirtmg day 220kV Quing Ninh - Holnh Bb H6m nay, ngby (Y thing l - nhm 2008 tai UBND xh /&f# Huyen...&a$...b*..~inh... P....&(L?L~....&ill& Dai dien UBND xzi :... Hu yen....,.-.,. A..., Tinh... L... ong (BB):..~...LON...~~L/~... ~hirc vu:...p..y~..&... + Dai dien cacf;, chirccxxl hoi:...,.... 'I"""""" Bng (B~)$QL... tft~... 9 hlic vi!:...u~...@'.m.&v4... <.Y y?ng (BB):... C c vy.... I 1... vng (BB):... Chc vli:... Ong (Bh):... Chllrc vu:... A......?ng (Bh): Chirc vy: Ong (Bh):... Chdc v~i:... ty CP. Tlr %n xay dmg dien J ~. ~.. ~ & V!I: ~..%..p7~ C ~ ~ C... Ong (BB):...:... ChGc vy:...'... + D+i dien cic he bi inh h~rhig: (danh sich k2m theo). +. C5c bkn dz chng nhau xem xkt, thio lugn phuang (in din bh, giii ph6ng m$t 'sing c6ng trinh: D~rbng day 220kV Quing Ninh - HoBnh Bo. - Dai dien C6ng ty CP. Tu v$n xay dung dicn 1 dii tl'lnh bhy viec: xay dkrng Dubng day 220kV Quing Ninh - Hohnh Bo tang nhu th6ng qua s6 lieu khio sitl didu tra inh-hubng ccia tuygn duhg day doi vdi dan cu, dja ph~wng co tuycn dutmg day bi qua, kc hoach vi cbc chin11 sich din bg, 2iHm thicu thiet hai: + Cbc chinh sich den bg dugc lap tren ca sh phip 19 sau: - Lu+t dgt dai n3m 2003 c6ng bd ngiy 24/12/ Nghi djnh 22/1998/ND-CP nghy 24/04/1998 quy dinh V/v den bi~.thiet hai khi NhB Nudc thu hdi dd sir dung vho muc dich Qu6c phbng, a.n ninh, lqi ich cdng ceng. - Nghi dinh so" 106/205/ND-CP v$ bio vc an to2n ludi dien cao (ip. - Nghi d/nh sb 64/ND-CP ngiy 27/09/1993 quy d/nh V/v giao d$t n6ng nghiep cho cic hq gia dinh, ci nhan sli dung dn dinh llu d8i vho muc dich SX ndng nghiep. - Nghi djnh so" 87/ND-CP ngiy 17/08/1995 quy djnh v6 khung gig cric loai. - Th6ng tu 05-BXD /DT ngby 09/02/1993 v6 phbn c&p nhh 3. - Quy pham trang bi dien, pmn 2 HTD- 1 ltcn do Be cdng Nghiep ban hbnh ngiy 11/07/2006

83 - CAc ThBng tu chi thi lieri qua khic. + Cu6c hop di d6n k6t l.u$n nhu sau: Dai dicn Dai dien CTCP. TVXD dien :; Dai dien usrjri yp.i~yp~@+~~i.,..,., (3 'li:i.-,-!{;fi.. - * ,=; \ s (r :, by.&. ;'.- \\,,".',,,',..;.z..,. xi..-' cj. ',.,,:. :,,, ;:.,h,., ' :7v a.2...>. L fi!.. 2. ':,.,;. '..;**..._:..-I*-,-.,,, '-, *:...[. <,.!:; :.,:. :.,A,.;,:,;.!,. /' 1 L' Dai dicn T6 chirc xii hoi Dai ditn ~6 chhr hei Dai dien T6 chirc ;uil hei

84 CONG HOA XA HOI CHU NGH~A VIET NAM Doc lap - Tq do - Hanh phuc Du in : Duhg day 220kV QuHng Ninh - Hoinh B8 I H H6m nay, ngi /y- thin A n2m 200 f tai UBND xh... za~,~...&/... Huyen... #WYg'..ta.:.rTinb...,... : Dai dien UBND xh :... G.6q...kh$ Chirc V~I: Chiic vy: Ong (Bi):... C11iic vy:... Ong (BB):... Chirc V~I:... + Dai dien C6ng ty CP. Tir v$n x2y dkrng dien 1. ong (B~):.~.~/~~.~~..&$ZII~C V!:...&:.?T'/(... Ong (BB):... Ct~irc VL!:...:... + Dai dien cic 110 bj in11 hir6ng: (danii sich kkm theo). + Cric ben b2 cimg nhau xem >;kt, thio l~tgn phiratlg in den bi~, g;ii ph6ng m$t bang c6ng trinh: D~rbng day 220kV Quing Ninh - Hohnh Bd. - Dai d.ie11 C6ng ty CP. Tir v$n x2y dlrng dicn 1 dii tl'lnh biy vicc x2y dlmg D~rbng day 220kV Qudng Nirlh - Hoh~ih B6 ciing ~ihir th6ng qua so" lieu khio SBI, dieu t1.a in11 hirhng ci~a tuyg11 d~rbng cliiy d6i v6i clan clr, ctja ph~rang c6 tlrybn dlrb11g clay cli qua, kg hoach vi cic chin11 sach cten bi~, giim thih thi$t hai: + Cric chinh s6ch den bil ctirgc I?p tl-en ca sb phip 19 sau: - Lust dgt dai c6ng bo" ngiy 24/12/ Nghi djnh 22/1998/ND-CP ngay 24/04/1998 quy djnh V/v den bi~ thi$t hai khi Nh2 N~rbc thu h8i ct6 s<r d ~ng vio mllc ctich QLI~"~ phbng, an ni1111, lqi ich c6ng cong. - Nghi djnh sb 106/205/ND-CP vd bio vc an tohn 1~16i ctien cao 5p. - Nghj djnh so" 64/ND-CP ngiy 27/09/1993 quy cljnh V/v giao dgt n6ng cghiep cho cic 118 gia dinh, ci nhan sir dung 611 dinh la11 dhi vio muc ctich SX n6ng nghiep. - Nghi djnh so" 87/ND-CP nghy 17/08/1995 qi~y djnh v$ khung gi5 cac loai. - Th6ng tu 05-BXD / DT nghy 09/02/1993 ve phan c$p nnh 6. - Quy pham trang bj bien, phdn 2 HTD-llTCN do BQ c6ng Nghiep ban hhnh ngiy 11/07/2006

85 .>*, - Cic Th6ng tu chi thi lien qua khic. + CuGc hop di dgn kgt lugn nh~r sau:...,...'...,...,...* <... Dai dicn,, i \!Ci:\;!j x$ -r\i(,;t,'~ Dai 'cli$ri'- '. I, I-r r-! 7-,.- 1 >it!/-' id Sai dien CTCP. TVXD di$n 1, UBND xa/.@f.~,~p,f- ~6 cllicc xs hoi A :.,!.!(..,.! IL 1.t ':-., <:\.,... _.-'..,: ;..._..:--, : /, /-:. :.v : xc,, '->'.,! ; ',... Dai 3ien Dai di$n D+i di$n Td ch$c x5 hei ~6 chdc x5 hgi.... I

86 PhpSl!ic k2m rheo bikn bdn hop tham vdh ceng 96ng - b60 c6o d211 bil tdi djnh cli Ngdyhff thdng~ n6m 200J. Tqi : &. DANH SACH CAC HO BI ANH HU~NG STT 1 Ho vh t&t.. 1 K$ ten I

87

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Improving grid medium, low voltage NORTH POWER COORATION Electric Network

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN Project Number: Loan 2225-VIE September 2013 VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE Prepared

More information

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

Subproject: Hai Lang Province: Quang Tri

Subproject: Hai Lang Province: Quang Tri Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP299 vol. 4 Ministry of Agriculture and Rural Development The World Bank Natural Disaster

More information

ABBREVIATED RESETTLEMENT ACTION PLAN

ABBREVIATED RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project: Irrigated Agriculture Improvement (IAIP) Subproject 1, Hoa Binh province SOCIALIST

More information

RESETTLEMENT POLICY FRAMEWORK

RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM HO CHI MlNH CITY'S INFRASTRUCTURE DEVELOPMENT FUND ********

More information

Resettlement Due Diligence Report

Resettlement Due Diligence Report Resettlement Due Diligence Report August 2015 VIE: Power Transmission Investment Program, Tranche 2-500kV Pleiku-My Phuoc-Cau Bong Transmission Line Binh Phuoc Province Prepared by Central Vietnam Power

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ------------------------------------------------------------------ SFG1163 V11 Public Disclosure Authorized Public

More information

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft)

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft) Public Disclosure Authorized VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY FRAMEWORK (Final Draft) Table of Contents

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized PEOPLE S COMMITTEE OF PHU YEN PROVINCE PHU YEN PROJECT MANAGEMENT UNIT OF CONSTRUCTION INVESTMENT WORKS FOR AGRICULTURE AND RURAL DEVELOPMENT ----------------o0oo---------------

More information

INVESTMENT CONSTRUCTION FILE

INVESTMENT CONSTRUCTION FILE PlfUMlilJ,Lf THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness ---***--- PHU MINH INVESTMENT AND CONSTRUCTION J.S.C SUBPROJECT: RURAL MIDDLE VOLTAGE POWER NETWORK IN HAl DUONG PROVINCE

More information

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT CAN THO CITY PEOPLE S COMMITTEE CONSTRUCTION & INVESTMENT MANAGEMENT UNIT USING OFFICIAL DEVELOPMENT ASSISTANCE (ODA), CAN THO CITY ***** SFG1562 REV RESETTLEMENT POLICY FRAMEWORK FOR CAN THO URBAN DEVELOPMENT

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

Income and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development

Income and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Income and Livelihood Restoration Plan Income and Livelihood Restoration Plan Document Stage: Final Project Number: 41013 June 2013 Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Prepared

More information

RESETTLEMENT PLAN (RP) TAY HA NOI 500KV SUBSTATION

RESETTLEMENT PLAN (RP) TAY HA NOI 500KV SUBSTATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION Northern Power Projects Management Board -------------------------------

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject

Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject Resettlement Monitoring Report Annual Report October 2012 Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject Prepared by the InvestConsult Group for the Provincial

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant 11 th Independent Monitoring Report November 2014 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT DUE DILIGENCE REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity

More information

ABBREVIATED RESETTLEMENT PLAN

ABBREVIATED RESETTLEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF CONSTRUCTION ADMINISTRATION OF TECHNICAL INFRASTRUCTURE MANAGEMENT BOARD

More information

VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT

VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT Resettlement Framework February 2012 VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT Prepared by the Ministry of Agriculture and Rural Development (MARD), Socialist

More information

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject Social Monitoring Report Corrective Action Plan September 2013 Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject Prepared by the Department of Agriculture

More information

Performance Standard 5 Land Acquisition and Involuntary Resettlement

Performance Standard 5 Land Acquisition and Involuntary Resettlement Introduction Performance Standard 5 1. Involuntary resettlement refers both to physical displacement (relocation or loss of shelter) and to economic displacement (loss of assets or access to assets that

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

Resettlement and Ethnic Minority Development Framework (REMDF)

Resettlement and Ethnic Minority Development Framework (REMDF) Resettlement and Ethnic Minority Development Framework (REMDF) Stage of the document: FINAL Project number: 49026-002 April 2017 VIE: Basic Infrastructure for Inclusive Growth in the Northeastern Provinces

More information

NH18: CUA ONG MONG DUONG RESETTLEMENT ACTION PLAN

NH18: CUA ONG MONG DUONG RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Social Monitoring Report Semi-Annual Report January-June 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam Power Projects

More information

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014 Work plan of Independent Agency and Implementation of IFC Performance Standards Green Goal Ltd., 17 February 2014 Content IFC performance standards Legal grounds of Cambodia Resettlement planning process

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT PLAN Project Number: 46391-001 December 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian

More information

Guidance Note 5 Land Acquisition and Involuntary Resettlement

Guidance Note 5 Land Acquisition and Involuntary Resettlement This Guidance Note 5 corresponds to Performance Standard 5. Please also refer to the Performance Standards 1-4 and 6-8 as well as the corresponding Guidance Notes for additional information. Bibliographical

More information

NH21/1 NAM DINH - LAC QUAN RESETTLEMENT ACTION PLAN

NH21/1 NAM DINH - LAC QUAN RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

EBRD Performance Requirement 5

EBRD Performance Requirement 5 EBRD Performance Requirement 5 Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or loss of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the CENTRAL

More information

DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT PLAN

DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Resettlement Monitoring Report March 2014 VIE: Northern Power Transmission Expansion Sector Project Prepared by the Local Implementation Consultant (LIC) Social for Viet Nam Electricity (EVN) Northern

More information

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT (Loan No. 5233-VN) SFG1981 V2 RESETTLEMENT PLAN Public Disclosure

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province) Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province) Prepared by Central Vietnam Power Projects

More information

Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Plan December 2013 Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (EVN HANOI: 110 kv Noi Bai Airport Substation and Associated 110 kv Transmission Line) Prepared

More information

NH21/2 LAC QUAN THINH LONG RESETTLEMENT ACTION PLAN

NH21/2 LAC QUAN THINH LONG RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK

More information

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives Page 1 of 9 Involuntary Resettlement 1. Bank 1 experience indicates that involuntary resettlement under development projects, if unmitigated, often gives rise to severe economic, social, and environmental

More information

Vietnam: GMS Sustainable Tourism Development Project

Vietnam: GMS Sustainable Tourism Development Project December 2010 Vietnam: GMS Sustainable Tourism Development Project Prepared by Quang Binh Provincial Implementation Unit for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 17 August 2010) Currency

More information

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RPF of Additional Financing for Fujian Highway Sector Investment Project Contents RP1032

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Resettlement Plan. Stage of the document: Final Project number: June 2017

Resettlement Plan. Stage of the document: Final Project number: June 2017 1 Resettlement Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang Tri Provinces Sector Project-Water

More information

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement This document should be read in conjunction with the proposed World Bank Policy to understand the proposed responsibilities of the World Bank (in the Policy) and the Borrowing Country (in the Standards).

More information

Resettlement Policy Framework

Resettlement Policy Framework Urban Transport Improvement Project of Tianjin by Using the World Bank Loan Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant Resettlement Monitoring Report Quarterly Report July September 2013 VIE: Mong Duong 1 Thermal Power Plant Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1. Internal

More information

VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Plan VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project (EVN HANOI: Mo Lao 110kV Substation and 110kV Connection) Prepared by Ha Noi Power Corporation for the Asian Development

More information

Viet Nam: Central Region Urban Environmental Improvement Project

Viet Nam: Central Region Urban Environmental Improvement Project Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 34355 June 2008 Viet Nam: Central Region Urban Environmental Improvement Project Prepared by Project Coordination

More information

Decree on Compensation and Resettlement Management in Development Projects

Decree on Compensation and Resettlement Management in Development Projects Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity The Government No. 84 Vientiane Capital, Date: 05 / 04 / 2016 Decree on Compensation and Resettlement Management in Development

More information

SOCIAL SAFEGUARD MANUAL

SOCIAL SAFEGUARD MANUAL Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM HO CHI MlNH CITY'S INFRASTRUCTURE DEVELOPMENT FUND ********

More information

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE

More information

Viet Nam: Water Sector Investment Program Tranche 3. Constructing New Water Treatment Plant, Phuc Triu Commune, Thai Nguyen City, Thai Nguyen Province

Viet Nam: Water Sector Investment Program Tranche 3. Constructing New Water Treatment Plant, Phuc Triu Commune, Thai Nguyen City, Thai Nguyen Province Resettlement Plan Resettlement Plan Document Stage: Revised Project Number: 41456-043 January 2019 Viet Nam: Water Sector Investment Program Tranche 3 Constructing New Water Treatment Plant, Phuc Triu

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

Resettlement Policy Framework

Resettlement Policy Framework Public Disclosure Authorized The World Bank SFG3873 REV Public Disclosure Authorized Hezhou Urban Water Infrastructure and Environment Improvement Project Public Disclosure Authorized Resettlement Policy

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project

VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Resettlement Plan Updated Resettlement Plan for Nghi Xuyen pumping station Sub-project October 2012 VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Prepared by CPMO for

More information

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING Road Development Agency 1 5 6 2 3 4 RESETTLEMENT POLICY FRAMEWORK FINAL REPORT Consultancy Services for the Design and Preparation of Bidding Documents for a Countrywide Roll-out of the Output and Performance

More information

NUI PHAO MINING PROJECT DAI TU DISTRICT THAI NGUYEN PROVINCE RESETTLEMENT ACTION PLAN

NUI PHAO MINING PROJECT DAI TU DISTRICT THAI NGUYEN PROVINCE RESETTLEMENT ACTION PLAN The Provincial People s Committee of Thai Nguyen Nui Phao Mining Joint Venture Company NUI PHAO MINING PROJECT DAI TU DISTRICT THAI NGUYEN PROVINCE RESETTLEMENT ACTION PLAN Prepared by Nui Phao Mining

More information

Viet Nam: University of Science and Technology of Hanoi (New Model University) Project

Viet Nam: University of Science and Technology of Hanoi (New Model University) Project Social Monitoring Report Quarterly Report December 2017 Viet Nam: University of Science and Technology of Hanoi (New Model University) Project Prepared by the Viet Nam Academy of Science and Technology

More information

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project Resettlement Plan July 2015 Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF THANH TRACH COMMUNE, BO TRACH DISTRICT, QUANG BINH PROVINCE Prepared

More information

SOCIALIST REPUBLIC OF VIET NAM CONSTRUCTION. Independence - Freedom Happiness

SOCIALIST REPUBLIC OF VIET NAM CONSTRUCTION. Independence - Freedom Happiness THE MINISTRY OF SOCIALIST REPUBLIC OF VIET NAM CONSTRUCTION Independence - Freedom Happiness -------- ---------------- No.: 13/2013/TT-BXD Hanoi, August 15, 2013 CIRCULAR PRESCRIBING VERIFICATION, APPRAISAL

More information

THE GOVERNMENT SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom - Happiness No. 164/2013/ND-CP Hanoi, November 12, 2013 DECREE

THE GOVERNMENT SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom - Happiness No. 164/2013/ND-CP Hanoi, November 12, 2013 DECREE THE GOVERNMENT SOCIALIST REPUBLIC OF VIET NAM ------- Independence - Freedom - Happiness ---------- No. 164/2013/ND-CP Hanoi, November 12, 2013 DECREE AMENDING AND SUPPLEMENTING A NUMBER OF ARTICLES OF

More information

VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project

VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project Resettlement Plan July 2012 VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project Prepared by Ho Chi Minh City People s Committee Management Authority Of Urban Railway for the Asian Development

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Resettlement Monitoring Report June 2013 VIE: Northern Power Transmission Expansion Sector Project Subprojects: 1) 500kV Hiep Hoa substation 2) 500kV Son La- Hiep Hoa Transmission Line 3) 220 kv Thuong

More information

Resettlement and Ethnic Minority Development Plan (REMDP)

Resettlement and Ethnic Minority Development Plan (REMDP) Resettlement and Ethnic Minority Development Plan (REMDP) Stage of the document: Final Project number: 49026-002 April 2017 VIE: Basic Infrastructure for Inclusive Growth in the Northeastern Provinces

More information

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT Resettlement and Rehabilitation (R&R) Entitlement Framework RP297 Under

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project

Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project Resettlement Planning Document Resettlement Plan Document Stage: Revised Project Number: 41013-013 March 2012 Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project Prepared by Provincial

More information

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF)

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) World Bank-financed Project World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

VIE: Greater Mekong Subregion Southern Coastal Corridor

VIE: Greater Mekong Subregion Southern Coastal Corridor Resettlement Plan March 2012 VIE: Greater Mekong Subregion Southern Coastal Corridor Updated Resettlement Plan of Xa Xia Ha Tien Section Prepared by Cuu Long Corporation for Investment, Development and

More information

Resettlement Plan Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Resettlement Plan Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Plan Project Number: 46391-001 December 2015 Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project EVN HCMC: 220-110kV Cau Bong Binh Tan Transmission Line Prepared by

More information

ABBREVIATED RESETTLEMENT ACTION PLAN

ABBREVIATED RESETTLEMENT ACTION PLAN Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT ==================== Public Disclosure Authorized Mekong Delta Integrated Climate Resilience and

More information

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia)

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Republic of Sakha (Yakutia) of the Russian Federation Innovative Development of Preschool

More information

EVN PO\VER CORPORATION CENTRAL POWER NETWORK PROJECT MANAGEMENT UNIT. Add: 4 Hoar 78A DuyTan, Da Nang city Tel: : Fax: 0511.

EVN PO\VER CORPORATION CENTRAL POWER NETWORK PROJECT MANAGEMENT UNIT. Add: 4 Hoar 78A DuyTan, Da Nang city Tel: : Fax: 0511. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized / ffi EVNCPC NPMU EVN PO\VER CORPORATION CENTRAL POWER NETWORK PROJECT MANAGEMENT UNIT

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY

PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY SFG2836 V2 REV SCALING UP URBAN UPGRADING PROJECT SUBPROJECT OF BEN TRE CITY, BEN TRE PROVINCE RESETTLEMENT PLAN (Final Version)

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Cao Bang Province Prepared by the Ministry of Education

More information

Income and Livelihood Restoration Program Report. VIE: Mong Duong 1 Thermal Power Plant

Income and Livelihood Restoration Program Report. VIE: Mong Duong 1 Thermal Power Plant Income and Livelihood Restoration Program Report February 2014 VIE: Mong Duong 1 Thermal Power Plant Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1. EVN GENCO

More information

Resettlement Plan. September 2016

Resettlement Plan. September 2016 Resettlement Plan September 2016 VIE: GMS Flood and Drought Risk Management and Mitigation Project - Upgrading and Rehabilitation of Four Primary Canals in Plain of Reeds, Dong Thap Province - Cai Cai

More information

NIGERIAN URBAN AND REGIONAL PLANNING ACT

NIGERIAN URBAN AND REGIONAL PLANNING ACT The Complete Laws of Nigeria Home NIGERIAN URBAN AND REGIONAL PLANNING ACT ARRANGEMENT OF SECTIONS PART I Plan preparation and administration A: Types and levels of Physical Development Plans SECTION 1.

More information

Resettlement and Ethnic Minority Development Plan

Resettlement and Ethnic Minority Development Plan Resettlement and Ethnic Minority Development Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang

More information

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT DRAFT COMPARATIVE ANALYSIS OF NEPAL s LEGAL FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT Note: The following is based

More information

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Yen Vien-Lao Cai Railway Upgrading Project Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project External Monitoring Report on RP Implementation Yen Bai Province Prepared by Railway Projects Management

More information

1 of 24 3/9/2017 8:19 AM

1 of 24 3/9/2017 8:19 AM 1 of 24 3/9/2017 8:19 AM Independent Clearing House for Nigeria's Justice Sector Home Rules of Court Treaties Law Firms Court Judgments About Us NIGERIAN URBAN AND REGIONAL PLANNING ACT SUPPORTED BY ARRANGEMENT

More information

RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1

RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1 RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1 Prepared for: CLRP-AF Project Monitoring Unit, Ministry of Environment and Spatial Planning Prepared by: replan Inc.

More information

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TRANSPORT NOTES TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP THE WORLD BANK,

More information

2017 RESETTLEMENT PLAN SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT SFG2836 V7 REV

2017 RESETTLEMENT PLAN SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT SFG2836 V7 REV SFG2836 V7 REV PEOPLE S COMMITTEE OF VINH LONG PROVINCE VINH LONG DEPARTMENT OF PLANNING & INVESTMENT SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT Public Disclosure Authorized Public Disclosure

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information