VIE: Northern Power Transmission Expansion Sector Project
|
|
- Hugo Kennedy
- 5 years ago
- Views:
Transcription
1 Resettlement Monitoring Report March 2014 VIE: Northern Power Transmission Expansion Sector Project Prepared by the Local Implementation Consultant (LIC) Social for Viet Nam Electricity (EVN) Northern Power Project Management Board (NPPMB). The Resettlement Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB s Board of Directors, Management, or Staff and may be preliminary in nature.
2 NORTHERN POWER TRANSMISSION EXPANSION PROJECT ADB LOAN No VIE (SF) 8 th REPORT (1 st QUARTERLY, 2014) Submitted to: Northern Power Project Management Board No.1111D, Hong Ha Street, Ha Noi city, Vietnam Prepared by: LOCAL IMPLEMENTATION CONSULTANT (LIC)- RESETTLEMENT Hanoi, March 2014
3 Northern Power Project Management Board And Asian Development Bank Dear Sir/Madam Subject: VIE I am pleased to submit to you the 1 st Quarterly Report, 2014 covering through January to March Yours truly, Nguyen Thi Ngoc Anh Local Implementation Consultant- Resettlement
4 TABLE OF CONTENT A. OVERVIEW 5 A.1. Project background 5 A.2. Objectives of 1 st, 2014 Quarterly report 5 A3. METHODOLOGY 6 B. IMPLEMENTED ACTIVITIES 6 C. FINDINGS AND EVALUATION OF 1 st QUARTERLY REPORT, D. WORK PLAN FOR PREPARING EVALUATION REPORT 11 E. ANNEX 12 Annex 1: Final Corrective Action Plan under the Due Diligence Review (Son La- Hiep Hoa T/L) 13 Annex 2: Final Corrective Action Plan under the Due Diligence Review (Hiep Hoa substation) 16 Page 3
5 ACRONYMS ADB AP CPC DMS DCARB EM LIC GoV PPCs RPF ROW RP RS NPPMB VND TNA T/L Asian Development Bank Affected Person Commune People s Committee Detailed Measurement Survey District Compensation and Resettlement Board Ethnic Minorities Local implementation consultant Government of Viet Nam Provincial People s Committees Resettlement Policy Framework Right of Way Resettlement Plan Resettlement site Northern Power Project Management Board Viet Nam Dong Training need assessment Transmission line Page 4
6 A. OVERVIEW A.1. Project background 1. Project Northern Power Transmission expansion sector represents a 5- year time slice of Electricity of Viet Nam s (EVN) transmission expansion program, covering 500kV and 220kV transmission lines, and associated substations. The project covers the northern part of Viet Nam which is relatively poor. The project will enable power to be supplied to the planned industrial zones in the region, thereby facilitating employment and income generating opportunities. Thus it will benefit the poor and ethnic minorities living in the project area. The project will also create the potential for power interconnection between Vietnam and the People s Republic of China. 2. The Project is to (i) strengthen the northern transmission network to improve system s reliability and quality of supply, (ii) facilitate power transmission by removing transmission bottlenecks, (iii) reduce transmission losses, and (iv) facilitate efficient utilization of existing and planned power plants. 3. Under the loan VIE-2225 framework, there are 12 subprojects namely (i) Son La Hoa Binh Nho Quan 500kVTransmission Line, (ii) 220kV Thanh Hoa Vinh T/L; (iii) Son La - Hiep Hoa 500 kv Transmission Line; (iv) Expansion of 500kV Thuong Tin; (v) Extension 220kV Van Tri Substation; (vi) Hiep Hoa 500 kv substation; (vii) 220kV Bim Son substation; (viii) 220kV Tuyen Quang substation; (ix) Extension 500kV Nho Quan substation 2nd transformer; (x) Kim Dong 220kV s/s; (xi) Thuong Tin-Kim Dong 220kV T/L; and (xii) Hai Duong KV s/s A.2. Objectives of 1 st, 2014 Quarterly report 4. This report mentions following issues: Syntheses shortcoming mentioned in 4 th evaluation; quarterly report, solution and The progress rate of compensation and resettlement of subprojects: Findings and evaluation of LIC (updated data at the end of ) To develop the report, the Consultant Team has worked with the NPPMB, VICA, contractors and local authorities in subproject area to update the resettlement Page 5
7 compliance of the subprojects and conducted spot check site visit and public consultation in Son La- Hiep Hoa T/L; Hiep Hoa substation, Kim Dong substation and 220kv Thuong Tin Kim Dong T/L. A3. METHODOLOGY 5. The employed methodology consisted of the following: Review of project documents: Loan Agreement, Project Documents, Resettlement Plan, Updated resettlement plan, Due Diligence reports, Memorandum of understanding from ADB s missions, ADB s SES 2009, ADB s Guideline on resettlement assessment. Maintain close dialogue with ADB Safeguard Specialists, NPPMP, CPPMP, Vica and LIC social, contractors and local authorities. Site visit: several visits have been paid to spot check the activities of compensation and resettlement compliance in the subprojects ( Hiep Hoa substation, Kim Dong substation and Thuong Tin- Kim Dong substation). B. IMPLEMENTED ACTIVITIES 6. Up to March 2014, LIC consultant has completed the implementation activities as following: B.1. Review the project documents 7. LIC has reviewed the project documents like Loan Agreement, Project Documents, Resettlement Plan, Updated resettlement plan, Due Diligence reports, Memorandum of understanding from ADB s missions, ADB s SES 2009, ADB s Guideline on resettlement assessment. 8. In addition to that, the RP of two core subprojects (Thuong Tin- Kim Dong T/L, Kim Dong substation) and Due Diligence report of 500K V Hiep Hoa have also been reviewed. 9. LIC has continued to review the environmental compliance reports prepared by contractors. The capacity of the contractors has been significantly increased with the support and guidance from LIC. Page 6
8 10. Provide input on the resettlement safeguard compliance for Quarterly Progress report for NPPMB 11. LIC has been requested by ADB and NPPMB to provide input on the resettlement safeguard compliance for the quarterly progress report in 1 st Quarterly of This input has just only the summary of the resettlement compliance of whole VIE 2225 Loan in every three month. More detail will be presented in this quarterly report as well as semi-annual reports prepared by LIC. Resettlement compliance monitoring samples for subprojects have been prepared by LIC. B.2. Meeting 12. Maintaining close dialogue with ADB Safeguard Specialists, NPPMP, CPPMP, Vica and LIC social, environment, CMC, contractors and local authorities.is quite important to identify and solve the issue in the timely manner. In addition to that, the and direct phone exchange are useful and effective tools among LIC with NPPMP, ADB Safeguard Specialists, VICA 13. Particularly, close dialogue and working with contractors especially those are doing civil works was prioritized and implemented frequently. B.3. Site visit 14. During this quarter, the LIC has conducted spot check visit to some subprojects are under construction like 220KV Kim Dong substation and 220kV Thuong Tin-Kim Dong substation which are under construction to further provide guidance on how to monitor and control the implementation of resettlement activities. Page 7
9 C. FINDINGS AND EVALUATION OF 1 st QUARTERLY REPORT, In 1 st quarterly report () LIC carries out monitoring and evaluating the implementation of compensation and resettlement for 02 subprojects of 500KV Son La- Hiep Hoa transmission line and 500kV Hiep Hoa substation. Besides, LIC also assists NPPMB to review RP reports of 220 kv Kim Dong substation and 220kV Thuong Tin- Kim Dong T/L subprojects. 16. Son La- Hiep Hoa T/L Son La- Hiep Hoa T/L has operated at the end of March, Up to now, there are some existing problems, including: Issuance of Land Use right Certificate (LURC), which serves as ownership document for the new plot of land, in a resettlement site or for individual plot has not been provides to all relocated household. The progress of rate is quite slow. Main reason leading this problem is that slow progress of payment of land use fee. Table 1: Status of Issuance LURC No List of Resettlement site No of plot I/ PHU THO 71 Status of issuance of LURC 1 Hien Quan, Tam Nong district 11 Completed 2 Phu Tho town 23 Not completed 3 Phu Loc commune, Phu Ninh dis 6 Not completed 4 Phu Nham commune Phu Ninh dis 6 Not completed 5 Phu Ninh commune, Phu Ninh dis 14 Not completed 6 Tien Du commune, Phu Ninh dis 5 Not completed 7 Tu Da commune, Phu Ninh dis 6 Not completed II/ VINH PHUC Yen Thạch Song Lo dis 13 Completed 9 Đồng Thịnh 1, Song Lo dis 12 Not completed 10 Đồng Thịnh 2, Song Lo dis 20 Not completed 11 Xuan Loi commune, Tam Duong dis 13 Completed 12 Tiên Lu commune, Tam Duong dis 5 Completed 13 Dong Ích commune, Tam Duong dis 2 Completed 14 An Hoà commune Tam Duong dis 6 Completed Page 8
10 No List of Resettlement site No of plot 15 Khu TĐC Nội Bài - Lào Cai Status of issuance of LURC Mặt đường 2C Tam Duong dis 11 Not completed Thôn Lẻ, Tam Duong dis 1 Not completed Kim Long, Tam Duong dis 2 Not completed 16 Đồng Bắn, Tam Duong dis 7 Not completed 17 Long Sơn Tam Duong dis 2 Not completed 18 2C street Not completed 19 Gô village Tam Duong dis 45 Not completed 20 Village No 8 Tam Duong dis 16 Not completed 21 Trai Khooong, Tam Dao dis 24 Completed 22 Trung My commune, Binh Xuyen dis 8 Completed III/ THAI NGUYEN Trung Thanh, Pho Yen dis 7 Not completed 24 Thuan Thanh, Pho Yen dis 5 Not completed Compensation of Mr. xxxx xxxxx xxxx, 12 Zone, Phu Tho Town: Mr. xxxx xxxxx xxxx moved to live in a tea plantation area of land managed by communes (total area 3,078 m 2 ) from 1987, without land ownership documents. He builds a 4 th level house here. His family has 3 children, 2 boys, 1 girl in that 2 married children (son and daughter). In the fact, after the cut off date, in 2011 Mr. xxxx xxxxx xxxx separates his household into 3 small household (including: (i) his wife, his smallest son and him, (ii) his son and (iii) his daughter). Mr. xxxx xxxxx xxxx required for 3 plot is resettlement site. The CRC of Phu Tho refused. Thus, Mr. xxxx xxxxx xxxx lodged a complaint to the Phu Tho Town court (September, 2012) which was dismissed. In April, 2013 he lodged a complaint to the Phu Tho province Court which was also rejected. Now, he is living under the operated line since 1 year. Page 9
11 Mr. xxxx xxxxx xxxx is living under the operated line His wife and son are living in a hutch Out of RoW) Slow completion of Infrastructure in Thuan Thanh RS, Pho Yen district, Thai Nguyen. Working with Pho Yen Construction and Investment PMU, it is said that slow disbursement of NPPMB leads slow of construction activities here. Thuan Thanh RS has 13 resettlement plot, however, the number of Son La- Hiep Hoa T/L is only 5 plots. District Construction and Investment PMU proposed NPPMB to invest infrastructure for overall plots. However, NPPMB refused and required to only pay for 5 plots of Son La- Hiep Hoa T/L. In the fact, There are meetings between District Construction and Investment PMU and NPPPMB to discuss about this issues. In Jan, 2014, District Construction and Investment PMU agreed with proposal of NPPMB and at the end of Feb, 2014, NPPMB pay in advance for District Construction and Investment PMU to implement construction activities in Thuan Thanh RS. 17. Hiep Hoa substation subproject Hiep Hoa DDR approved by ADB and CPPMB carry out additional compensation payment according to approved corrective action plan. Currently, VICA carry out to check list of vulnerable household (the poor, female-headed household with Page 10
12 dependents). Based on updated DMS provided by VICA, CPPMB will cooperate with Hiep Hoa district CRC to prepare a additional compensation plan KV Kim Dong substation subproject Kim Dong 220kV substation is located in Toan Thang commune, Kim Dong district, Hung Yen province. In Jan, 2013, VICA consultant carried community consultation meetings, socio-economic and asset inventory survey in subproject and submitted a draft RP to NPPMB and ADB. ADB had NOL for this RP. LIC had a short field trip at Kim Dong, Hung Yen province. It is known that, there is no complaint related to compensation activities. The contractor promptly completed construction activities. 19. Thuong Tin - Kim Dong T/L subproject VICA consultant prepared 03 districts RP for this subproject in December, 2012 and submitted a draft version to NPPMB and ADB for approval. ADB had NOL for three RP. Up to now, 23 out of 81 foundation has not completed compensation payment due to adjustment of line D. WORK PLAN FOR PREPARING EVALUATION REPORT 20. LIC proposes to carry our following activities: - Monitoring and evaluating the implementation corrective action plan of Son La- Hiep Hoa T/L, Hiep Hoa substation according to proposed DDR prepared by ADB consultant; - Cooperate with stakeholder to solve existing problems of Thuong Tin- Kim Dong T/L; - Prepare a evaluation report for 4 subprojects Page 11
13 E. ANNEX Annex 1: Final Corrective Action Plan under the Due Diligence Review Annex 2: Project booklet Page 12
14 4 th quarterly report LIC resettlement September, 2013 Annex 1: Final Corrective Action Plan under the Due Diligence Review (Son La- Hiep Hoa T/L) Issue Corrective Action By whom By when Restoration of livelihoods. Along TL few HH is losing more than 10% of their total productive land. No specific income restoration measures have been implemented. The number of HH losing more than 10% of their affected productive land is unknown. - Identify through DMS list, the number of AH losing more than 10% of their productive land in each/district/town/city; - Assess trough monitoring if these HH could restore their livelihoods. - Prepare adapted income restoration measures if required. NPT/NPPMB in coordination with DCRB 30 April 2014 Completion of Infrastructures in Thuan Thanh Resettlement Site In Thuan Thanh RS (Thai Nguyen Province, Pho Yen District), drainage, inner roads and electricity are not completed; no activity occurred on this RS. - Contractor to prepare disbursement to DPC - DPC to send disbursement documents to NPPMB for review and approval - NPPMB to disburse funds - Install remaining infrastructures - Inform regularly HH of the schedule of work - Extend allowance for renting houses until completion of RS - NPT/NPPMB in coordination with Contractor Dong Ban, PMU Construction & Investment Pho Yen District, DRCB Pho Yen/Contractor, DRCB Pho Yen, DCRB Pho Yen - 30 April 2014 Vulnerable Except poor, no other vulnerable have been identified Check the DMS list and with local organization (Farmer s Union, Women s Union) if potential vulnerable HHs are ((i) female headed HH with dependents, (ii) disabled HH heads, (iv) children and the elderly HH who are landless and with no other means of support, and (v) landless HH. This will determine what type of allowances are necessary to be provided. NPT/NPPMB in coordination with respective DRCBs and consultation with - Women s Union - Farmer s Union - Relevant civil society organizations - District and people committees - 30 April 2014 Issuance of Land Use Right Certificate The Land Use Right Certificate (LURC), which serves as ownership document for the new plot of land, in a resettlement site or for individual plot, has not been provided to all relocated HH due to slow process. The LURC is issued by the - Issuance of LURC latest by 31 May 2014 for HHs which have already been allocated a plot of land and which have paid their land use fees. - NPT/NPPMB in coordination with District People s Committee - 31 May 2014 Page 13
15 4 th quarterly report LIC resettlement District People s Committee. Issue Corrective Action By whom By when Slow Process of disbursement of Funds. Delays in transfer of funds from NPPMB to DCRB have been observed in most of the districts. These delays hamper the resettlement activities and especially the completion of RS. Disbursement documents are prepared first by the contractor and then sent at the District level by the PMU of Construction and Investment and sent to NPPMB for review approval and disbursement. According to NPPMB, contractors don t send documents to DPC. - NPPMB to continue assisting contractors and DPC (PMU of Construction and Investment) to prepare acceptable disbursement document; - NPPMB to transfer remaining funds - NPT/NPPMB in coordination with Contractors, PMU for Investment & Construction at District level - 30 April 2014 Compensation of Mr. xxxx xxxxx xxxx (Phu Tho Province, Phu Tho Town) Mr. xxxx xxxxx xxxx refused compensation and didn t hand over his land to the project. He is still living under the transmission line. According to legal documents, Mr. xxxx is living on forest land. He considers that he is living stably and wants to be compensated as for residential land. Compensation for forest land is 35,000 VND/m 2, while compensation for residential land in RS is 70,000/m 2. He required 3 plots of land free in the RS. NPPMB/DCRB proposed to provide free one plot of land in the RS of 400 m 2 but he refused. AH have usually to buy the plot of land. He lodged a complaint to the Phu Tho Town Court which was dismissed. He is living under the operated line since 1 year. - NPPMB to ensure that the the offer to allocate a plot of land of 400 m 2 in the RS for free is maintained. - NPPMB to compensate for all other assets (trees, crops, structures) at replacement costs. - NPT/ NPPMB in coordination with DPC Phu Tho Town - 30 April 2014 In April, 2013 he lodged a complaint to the Province Court which was also rejected. Page 14
16 4 th quarterly report LIC resettlement Issue Corrective Action By whom By when Phu Ninh RS (Phu Tho Province, Phu Ninh District) In Phu Ninh RS, there is risk of landslide due to steep slope without erosion protection. Landslide could affect properties and infrastructures (drainage ditch). Grievance Process The grievance process is followed; there is however some delays in the information to APs who made complaints Monitoring External monitoring to be conducted by LIC - NPPMB to study options to protect slope against erosion and implement these protective measures. - NPPMB to review complaints in all affected districts/town/city and review how grievances were addressed and resolve any residual grievances. All grievances must be addressed within the time regulated by the law (30-45 days after receiving the official complaints). - NPPMB to ensure APs raising complaints are informed about the results of the decision within the timeframe indicated in the RP - NPPMB to work with LIC to ensure that all monitoring activities are conducted as stipulated in the agreed RF; - NPPMB to ensure that LIC pays special attention ton the needs of women and ethnic minority people and that LIC ensures that all consultation and participation processes with affected people are coordinated in a participatory manner. - NPT/NPPMB with DCRB - 31 May NPT/ NPPMB in coordination with DCRB - 30 June NPPMB/LIC - Evidence to be documented in each quarterly report Page 15
17 4 th quarterly report LIC resettlement September, 2013 Annex 2: Final Corrective Action Plan under the Due Diligence Review (Hiep Hoa substation) Issue Corrective Action By whom By when Only some HH were identified during DMS and received assistance. Other vulnerable HH were not identified Following construction, drainage is not adequate and led to frequent flooding to the cultivation area of Ha Noi, dai Mao and Huong Ninh hamlets despite some work (drainage channel, dyke done to reduce flooding ) During operation. Lights from the substation attracts butterfly and worms at right affecting crop productivity As per agreed RPF all poor and vulnerable APs, even if not severely affected, should receive a cash allowance equivalent to 30kg of roce per family member per month for a minimum period of six months (amount to be determined by Hiep Hoa district PC) LFDC to check in the DMS list and through local organization (Farmer s Union, Women s Union) if potential vulnerable HH: (i) femaleheaded HH with dependent; (ii) disabled HH heads; (iii) poor Hh; (iv) HH without with no means of support; and (v) HH without security of tenure; are present and provide the agreed allowance NPT/ CPPMB to ensure that support to localities for drainage installation and pumping stations in the areas affected by flooding is provided NPT/ CPPMB to coordinate with various stakeholders and ensure that a solution for the buteerfly and worms attracted by the light from the substation is found. CPPMB ensure that the protective measures are implemented immediately BPT/ CPPMB in coordination with Hiep Hoa DPC NPT/ CPPMB in coordination with Hiep Hoa DPC, local authorities in affected hamlets/ communes NPT/ CPPMB in coordination with Hiep Hoa DPC, local authorities in affected hamlets/ communes 20th May 15 th April 15 th April Page 16
DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE
DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN Project Number: Loan 2225-VIE September 2013 VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE Prepared
More informationVIE: Northern Power Transmission Expansion Sector Project
Resettlement Monitoring Report June 2013 VIE: Northern Power Transmission Expansion Sector Project Subprojects: 1) 500kV Hiep Hoa substation 2) 500kV Son La- Hiep Hoa Transmission Line 3) 220 kv Thuong
More informationVIE: Northern Power Transmission Expansion Sector Project
Resettlement Monitoring Report July 2013 VIE: Northern Power Transmission Expansion Sector Project Subprojects: 1) 500 kv Transmission line Son La- Nho Quan- Hoa Binh (2) 220 kv Transmission line Thanh
More informationVIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project
RESETTLEMENT DUE DILIGENCE REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity
More informationVIE: Northern Power Transmission Expansion (Sector) Project
Social Monitoring Report Post-Evaluation Report April 2016 VIE: Northern Power Transmission Expansion (Sector) Project Prepared by the Northern Power Project Management Board for the Asian Development
More informationSOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness No. 182/2013/ND-CP Hanoi, November 14, 2013 DECREE
THE GOVERNMENT ------- SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness --------- No. 182/2013/ND-CP Hanoi, November 14, 2013.. DECREE STIPULATING REGION-BASED MINIMUM WAGE LEVELS FOR LABORERS
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education
More informationResettlement and Ethnic Minorities Monitoring Report
Resettlement and Ethnic Minorities Monitoring Report Semi-annual Report August 2013 Viet Nam: Sustainable Rural Infrastructure Development Project in Northern Mountain Provinces Subprojects in Dien Bien,
More informationSocial Monitoring Report
Social Monitoring Report #4 Report November GMS: Kunming-Hai Phong Transport Corridor - Noi Bai - Lao Cai Highway Project Vinh Phuc Province Prepared by Scientific Technological Center and Environment
More informationResettlement Due Diligence Report
Resettlement Due Diligence Report August 2015 VIE: Power Transmission Investment Program, Tranche 2-500kV Pleiku-My Phuoc-Cau Bong Transmission Line Binh Phuoc Province Prepared by Central Vietnam Power
More informationSOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness No. 107/2010/ND-CP Hanoi, October 29, 2010 DECREE
THE GOVERNMENT ------- SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness --------- No. 107/2010/ND-CP Hanoi, October 29, 2010 DECREE STIPULATING REGION-BASED MINIMUM WAGE LEVELS FOR VIETNAMESE
More informationVIE: Yen Vien-Lao Cai Railway Upgrading Project
Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project External Monitoring Report on RP Implementation Yen Bai Province Prepared by Railway Projects Management
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry
More informationRESETTLEMENT ACTION PLAN
Public Disclosure Authorized Public Disclosure Authorized PEOPLE S COMMITTEE OF PHU YEN PROVINCE PHU YEN PROJECT MANAGEMENT UNIT OF CONSTRUCTION INVESTMENT WORKS FOR AGRICULTURE AND RURAL DEVELOPMENT ----------------o0oo---------------
More informationVIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line
Social Monitoring Report Semi-Annual Report January-June 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam Power Projects
More informationVIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project
RESETTLEMENT PLAN Project Number: 46391-001 December 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education
More informationViet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject
Social Monitoring Report Corrective Action Plan September 2013 Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject Prepared by the Department of Agriculture
More informationVIE: Mong Duong 1 Thermal Power Plant
Resettlement Monitoring Report Quarterly Report July September 2013 VIE: Mong Duong 1 Thermal Power Plant Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1. Internal
More informationDANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT
DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT (Loan No. 5233-VN) SFG2443 V2 RESETTLEMENT PLAN FOR THE ADJUSTMENT
More informationVIE: Yen Vien-Lao Cai Railway Upgrading Project
Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project Resettlement Monitoring Report Prepared by Railway Projects Management Unit of Viet Nam Railway for
More informationVIE: Mong Duong 1 Thermal Power Plant
11 th Independent Monitoring Report November 2014 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project
More informationVIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section
Social Due Diligence Report Document Stage: Second Draft Project Number: 40080 May 2013 VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section Prepared by Hanoi Metro Railway Board for
More informationIndigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project
Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary
More informationInternal Monitoring Report. VIE: Second Greater Mekong Subregion Corridor Towns Development Project. Semestral Report (From July to December 2017)
Internal Monitoring Report Semestral Report (From July to December 2017) VIE: Second Greater Mekong Subregion Corridor Towns Development Project Prepared by: PMUs Bac Giang, Lao Cai and Mong Cai for Asian
More informationVIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project
Social Monitoring Report 2nd Semi-annual Report January 2018 VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project Prepared by Development Research and Consultancy Centre
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of
More informationVIE: Yen Vien-Lao Cai Railway Upgrading Project
Social Monitoring Report Semi-Annual Report July December 2015 VIE: Yen Vien-Lao Cai Railway Upgrading Project Resettlement Monitoring Report Prepared by CDM Smith DBI Joint Venture for the Ministry of
More informationVIE: Central Mekong Delta Region Connectivity Project
Social Monitoring Report Quarterly Report No. 3 April 2014 VIE: Central Mekong Delta Region Connectivity Project Prepared by Joint Venture: CDM Smith, Inc., WSP Finland Limited & Yooshin Engineering Corporation
More informationVIE: GMS Ben Luc - Long Thanh Expressway
Social Monitoring Report Inception Report May 2013 VIE: GMS Ben Luc - Long Thanh Expressway Prepared by Thanglong Infrastructure Development for Vietnam Expressway Corporation and the Asian Development
More informationSubproject: Hai Lang Province: Quang Tri
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP299 vol. 4 Ministry of Agriculture and Rural Development The World Bank Natural Disaster
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of
More informationResettlement Plan. Stage of the document: Final Project number: June 2017
1 Resettlement Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang Tri Provinces Sector Project-Water
More informationExternal Resettlement Monitoring Report
External Resettlement Monitoring Report Semi-annual Report Mission 3 October, 2013 VIE - STRENGTHENING WATER MANAGEMENT AND IRRIGATION SYSTEMS REHABILITATION PROJECT Subproject: The Water Resources University
More informationVIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project
Resettlement Plan Updated Resettlement Plan for Nghi Xuyen pumping station Sub-project October 2012 VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Prepared by CPMO for
More informationViet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject
Resettlement Monitoring Report Annual Report October 2012 Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject Prepared by the InvestConsult Group for the Provincial
More informationNH21/1 NAM DINH - LAC QUAN RESETTLEMENT ACTION PLAN
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK
More informationNH18: CUA ONG MONG DUONG RESETTLEMENT ACTION PLAN
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK
More informationVIE: Transport Connections in Northern Mountainous Provinces Project
Quarterly Report on Gender action and ethnic minority Development Plan Loan 2789 April 2014 VIE: Transport Connections in Northern Mountainous Provinces Project QUARTERLY REPORT ON GENDER ACTION AND ETHNIC
More informationVIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------
More informationIncome and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development
Income and Livelihood Restoration Plan Income and Livelihood Restoration Plan Document Stage: Final Project Number: 41013 June 2013 Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Prepared
More informationViet Nam: Central Region Rural Water Supply and Sanitation Sector Project
Resettlement Plan July 2015 Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF THANH TRACH COMMUNE, BO TRACH DISTRICT, QUANG BINH PROVINCE Prepared
More informationRESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE
RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the CENTRAL
More informationVIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT
Resettlement Framework February 2012 VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT Prepared by the Ministry of Agriculture and Rural Development (MARD), Socialist
More informationVIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Project (GMS1)
Resettlement Monitoring Report #1 Semestral Report August 2015 VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Prepared by Vietnam Water, Sanitation and Environment joint
More informationResettlement Plan. September 2016
Resettlement Plan September 2016 VIE: GMS Flood and Drought Risk Management and Mitigation Project - Upgrading and Rehabilitation of Four Primary Canals in Plain of Reeds, Dong Thap Province - Cai Cai
More informationL3173-VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN THE CENTRAL PROVINCES (Additional Financing)
INTERNAL SOCIAL SAFEGUARDS MONITORING REPORT ON RESETTLEMENT (From July 2017 to December 2017) Document stage: Final report Loan Number: 3173 January, 2018 L3173-VIE: INTEGRATED RURAL DEVELOPMENT SECTOR
More informationVIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION
Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ------------------------------------------------------------------ SFG1163 V11 Public Disclosure Authorized Public
More informationUpdated Resettlement and Ethnic Minority Development Plan
Updated Resettlement and Ethnic Minority Development Plan Project Number: 46293-005 May 2018 Viet Nam: Greater Mekong Sub-Region Tourism Infrastructure for Inclusive Growth Project Subproject: Lao Cai
More informationVIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft)
Public Disclosure Authorized VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY FRAMEWORK (Final Draft) Table of Contents
More informationNH21/2 LAC QUAN THINH LONG RESETTLEMENT ACTION PLAN
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK
More informationViet Nam: Central Region Rural Water Supply and Sanitation Sector Project
Resettlement Plan September 2015 Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF THACH BANG-THACH KIM-THINH LOC COMMUNES LOC HA DISTRICT, HA TINH
More informationResettlement and Ethnic Minority Development Plan (REMDP)
Resettlement and Ethnic Minority Development Plan (REMDP) Document Stage: Final 20 July 2010 GMS: Kunming-Hai Phong Transport Corridor - Noi Bai- Lao Cai Highway Project Bao Thang District, Lao Cai Province
More informationVIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project. EVN HCMC: 220kV Tan Cang Substation
Resettlement Due Diligence Report Stage of the document: Final Loan number: 3163-VIE October 2016 VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project EVN HCMC: 220kV Tan Cang Substation
More informationABBREVIATED RESETTLEMENT ACTION PLAN
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project: Irrigated Agriculture Improvement (IAIP) Subproject 1, Hoa Binh province SOCIALIST
More informationRESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the
RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education
More informationVIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project
Final Resettlement Monitoring Report Post Evaluation Document stage: Final Project number: 42080 December 2016 VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Subproject:
More informationInvoluntary Resettlement Due Diligence Report
Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Cao Bang Province Prepared by the Ministry of Education
More informationVietnam: GMS Sustainable Tourism Development Project
December 2010 Vietnam: GMS Sustainable Tourism Development Project Prepared by Quang Binh Provincial Implementation Unit for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 17 August 2010) Currency
More informationViet Nam: Secondary Cities Development Project. Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province
Resettlement Plan Resettlement Plan Document Stage: Revised Project Number: 45198 June 2016 Viet Nam: Secondary Cities Development Project Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province
More informationVIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province)
Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province) Prepared by Central Vietnam Power Projects
More informationVIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)
Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian
More informationVIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project
Final Resettlement Monitoring Report Post Evaluation Report Document stage: Final Project number: 42080 December 2016 VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Subproject:
More informationViet Nam: University of Science and Technology of Hanoi (New Model University) Project
Social Monitoring Report Quarterly Report December 2017 Viet Nam: University of Science and Technology of Hanoi (New Model University) Project Prepared by the Viet Nam Academy of Science and Technology
More informationResettlement and Ethnic Minority Development Plan (REMDP)
Resettlement and Ethnic Minority Development Plan (REMDP) Stage of the document: Final Project number: 49026-002 April 2017 VIE: Basic Infrastructure for Inclusive Growth in the Northeastern Provinces
More informationViet Nam: Water Sector Investment Program Tranche 3. Constructing New Water Treatment Plant, Phuc Triu Commune, Thai Nguyen City, Thai Nguyen Province
Resettlement Plan Resettlement Plan Document Stage: Revised Project Number: 41456-043 January 2019 Viet Nam: Water Sector Investment Program Tranche 3 Constructing New Water Treatment Plant, Phuc Triu
More informationRESETTLEMENT PLAN (Final draft)
SFG3898 V1 REV HA TINH PROVINCIAL PEOPLE S COMMITTEE WORLD BANK RESETTLEMENT PLAN (Final draft) DYNAMIC CITIES INTEGRATED DEVELOPMENT PROJECT KY ANH TOWN SUBPROJECT HA TINH PROVINCE Public Disclosure Authorized
More informationVIE: Song Bung 4 Hydropower Project
Social Monitoring Report Semestral Report February 2012 VIE: Song Bung 4 Hydropower Project Prepared by Song Bung 4 Hydropower Project Management Board (SB4HPMB) for the Asian Development Bank. SONG BUNG
More informationSocialist Republic of Viet Nam: Second Greater Mekong Subregion Corridor Towns Development Project. Bac Giang Subproject
Resettlement Plan June 2015 Socialist Republic of Viet Nam: Second Greater Mekong Subregion Corridor Towns Development Project Bac Giang Subproject Prepared by Bac Giang Provincial People s Committee for
More informationViet Nam: Central Region Urban Environmental Improvement Project
Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 34355 June 2008 Viet Nam: Central Region Urban Environmental Improvement Project Prepared by Project Coordination
More informationVIE: Phuoc Hoa Water Resources Project
Resettlement Plan Loan: 2025/2747 Document stage: updated Dec 2013 VIE: Phuoc Hoa Water Resources Project Component: Tan Bien Irrigation Area Five drainage canals in Chau Thanh District, Tay Ninh Province
More informationViet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project
Resettlement Planning Document Resettlement Plan Document Stage: Revised Project Number: 41013-013 March 2012 Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project Prepared by Provincial
More informationOverview of arbitration in Vietnam
Overview of arbitration in Vietnam Arbitration in Vietnam: Understanding the Process and Making It Work for your Business Pham D Nghia Ways to resolve business disputes Article 317 Commercial Law 2005:
More informationVIE: Central Mekong Delta Region Connectivity Project
Social Monitoring Report Quarterly Report No. 8 November 2015 VIE: Central Mekong Delta Region Connectivity Project Prepared by Joint Venture: CDM Smith, Inc., WSP Finland Limited & Yooshin Engineering
More informationVIE: Second Health Care in the Central Highlands Project in Dak Nong Province
Due Diligence Report March 2016 VIE: Second Health Care in the Central Highlands Project in Dak Nong Province Prepared by the Ministry of Health, Socialist Republic of Viet Nam, for Asian Development Bank.
More informationResettlement and Ethnic Minorities Development Plan. VIE: Support to Border Areas Development Project
Resettlement and Ethnic Minorities Development Plan Document stage: Final Project Number: 48189-002 July 2016 VIE: Support to Border Areas Development Project Subproject: Upgarading provincial road 756
More informationRESETTLEMENT PLAN (RP) TAY HA NOI 500KV SUBSTATION
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION Northern Power Projects Management Board -------------------------------
More informationABBREVIATED RESETTLEMENT PLAN
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF CONSTRUCTION ADMINISTRATION OF TECHNICAL INFRASTRUCTURE MANAGEMENT BOARD
More informationINVESTMENT CONSTRUCTION FILE
PlfUMlilJ,Lf THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness ---***--- PHU MINH INVESTMENT AND CONSTRUCTION J.S.C SUBPROJECT: RURAL MIDDLE VOLTAGE POWER NETWORK IN HAl DUONG PROVINCE
More informationViet Nam: Central Region Rural Water Supply and Sanitation Sector Project
Resettlement Plan July 2015 Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF THACH BANG-THACH KIM-THINH LOC COMMUNES LOC HA DISTRICT, HA TINH PROVINCE
More informationResettlement and Ethnic Minority Development Plan
Resettlement and Ethnic Minority Development Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang
More informationVIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project
Resettlement Plan VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project (EVN HANOI: Mo Lao 110kV Substation and 110kV Connection) Prepared by Ha Noi Power Corporation for the Asian Development
More informationDANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT
DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT (Loan No. 5233-VN) SFG1981 V2 RESETTLEMENT PLAN Public Disclosure
More informationVIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing
Resettlement Plan March 2017 VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing Subproject: Upgrading Dai Giang River Dike system, Thua Thien Hue province Prepared
More informationNORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Improving grid medium, low voltage NORTH POWER COORATION Electric Network
More informationInternal Migration in Vietnam: The Current Situation
UNFPA, the United Nations Population Fund, is an international development agency that promotes the right of every woman, man and child to enjoy a life of health and equal opportunity. UNFPA supports countries
More informationViet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project
Resettlement Plan December 2013 Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (EVN HANOI: 110 kv Noi Bai Airport Substation and Associated 110 kv Transmission Line) Prepared
More informationLao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005
Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project
More informationResettlement Plan Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project
Resettlement Plan Project Number: 46391-001 December 2015 Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project EVN HCMC: 220-110kV Cau Bong Binh Tan Transmission Line Prepared by
More informationVIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project
Resettlement Plan July 2012 VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project Prepared by Ho Chi Minh City People s Committee Management Authority Of Urban Railway for the Asian Development
More informationNOTIONS OF MIGRANT WORKERS TO INDUSTRIAL ZONES IN BACNINH PROVINCE OF VIETNAM
ISSAAS 2016 International Congress and General Meeting National and Global Good Agricultural Practices (GAPs) in Southeast Asia NOTIONS OF MIGRANT WORKERS TO INDUSTRIAL ZONES IN BACNINH PROVINCE OF VIETNAM
More informationResettlement and Ethnic Minority Development Plan (REMDP)
Resettlement and Ethnic Minority Development Plan (REMDP) Stage of the document: Final Project number: 49026-002 April 2017 VIE: Basic Infrastructure for Inclusive Growth in the Northeastern Provinces
More informationCivil Society Partnership
CARE Civil Partnership CIVIL ACTION FOR SOCIO-ECONOMIC INCLUSION (CASI) Civil Society Partnership Civil Action for Socio-economic Inclusion(CASI) GOAL: Sustainable improvements in livelihood security for
More informationCAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT
CAN THO CITY PEOPLE S COMMITTEE CONSTRUCTION & INVESTMENT MANAGEMENT UNIT USING OFFICIAL DEVELOPMENT ASSISTANCE (ODA), CAN THO CITY ***** SFG1562 REV RESETTLEMENT POLICY FRAMEWORK FOR CAN THO URBAN DEVELOPMENT
More informationVIE: Viet Nam Water Sector Investment Program (Tranche 2) - Thua Thien Hue Water Supply Subproject Phase I
Land Acquisition and Resettlement Due Diligence Report August 2017 VIE: Viet Nam Water Sector Investment Program (Tranche 2) - Thua Thien Hue Water Supply Subproject Phase I Prepared by Watech Construction
More informationDIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT PLAN
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT
More informationProtocol to the Agreement on Ending the War and Restoring Peace in Vietnam Concerning the International Commission of Control and Supervision
Protocol to the Agreement on Ending the War and Restoring Peace in Vietnam Concerning the International Commission of Control and Supervision The parties participating in the Paris Conference on Vietnam,
More informationVIE: GMS Ben Luc Long Thanh Expressway Project
Internal Monitoring Report Quarterly Report October-December 2015 VIE: GMS Ben Luc Long Thanh Expressway Project Prepared by Dasan Consultants Co. Ltd., in joint venture with Kunhwa Engineering & Consulting
More information