Semi-Annual Social Safeguard Monitoring Report. IND: North-Eastern Region Capital Cities Development Investment Program Kohima, Nagaland

Size: px
Start display at page:

Download "Semi-Annual Social Safeguard Monitoring Report. IND: North-Eastern Region Capital Cities Development Investment Program Kohima, Nagaland"

Transcription

1 Semi-Annual Social Safeguard Monitoring Report Project number: January 2015 Period: July December 2014 IND: North-Eastern Region Capital Cities Development Investment Program Kohima, Nagaland Prepared by State Investment Program Management and Implementation Unit This report has been submitted to ADB by the State Investment Program Management and Implementation Unit, Urban Development Department, Government of Nagaland and is made publicly available in accordance with ADB s public communications policy (2011). It does not necessarily reflect the views of ADB. The social safeguard monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

2 SEMI ANNUAL SOCIAL SAFEGUARD MONITORING REPORT Loan Number: 2528/2834 IND Reporting Period: (July- December 2014) INDIA: North Eastern Region Capital Cities Development Investment Program Project City: Kohima, Nagaland State Implementing Agency: State Investment Program Management and Implementation Unit Executing Agency: Urban Development Department, Government of Nagaland Jan 2015 Kohima

3 ABBREVIATIONS ADB - Asian Development Bank BTA - Bridging Technical Assistance CC - Construction Contractor DOC - Date of Completion DOS - Date of Start DSMC - Design, Supervision and Management Consultant EA - Executing Agency EARP - Environmental Assessment & Review Procedure EIA - Environmental Impact Assessment EO - Environmental Officer GoI - Government of India IA - Implementing Agency IEE - Initial Environmental Examination IPCC - Investment Program Coordination Cell MFF - Multi-tranche Financing Facility MLD - Million Liters per Day mn - Million MoUD - Ministry of Urban Development NEA - National Executing Agency NERCCDIP - North Eastern Region Capital Cities Development Investment Program NSC - National level steering committee PD - Project Director PPTA - Project Preparatory Technical Assistance SEA - State level Executing Agency SIPMIU State Investment Program Management and Implementation Unit UDD - Urban Development Department i

4 Table of Contents 1 Introduction Implementation Arrangements Sub Project Components in Kohima Municipal Council Area Social Safeguard Activities for Tranche -1&2 Sub projects Compliance status of loan covenants Project Impact Policy and Legal Framework Validation and Verifications of APs Public Consultations and Disclosure of RP Grievance Redressal Monitoring and Reporting Issues and Action Plan List of Tables Table 1. Institutional Roles... 4 Table 2. Sub projects &components... 5 Table 3. Status of civil construction and RP implementation in tranche-1 sub projects... 8 Table 4: Summary of Community Development, Public Participation and Gender Sensitization programs conducted during the period from 1 st July to 31 st December, 2014 in kohima Table 5. Status of Loan Covenants List of Appendices Appendix 1: IR screening report for Septage Management works... 2 Appendix 2: Snap shots and minutes of the meetings/fgds Appendix 3: Notification of Grievance Redressal Committee ii

5 1 Introduction 1. The Government of India has obtained a loan from the Asian Development Bank towards financing the North Eastern Region Capital Cities Development Investment Program. The loan is under the Multi Tranche Financing Facility of the Asian Development Bank to improve certain prioritized urban infrastructures mainly in the sectors of water supply, solid waste management and sanitation in 5 North Eastern Region Capital Cities namely, Agartala, Aizwal, Gangtok, Kohima and Shillong. The Program will (i) improve the urban infrastructure (ii) strengthen the urban institutions towards better service delivery, project management and implementation. 2. The NERCCDIP is estimated to be completed in a span of 6 years. The program in Kohima envisages investments in three projects corresponding to three loan tranches of ADB. The State Investment Program Management & Implementation Unit is the implementing agency at State level. M/s CDM Smith India Private Limited (Formerly Wilbur Smith Associates) has been engaged as the Design, Construction Supervision & Management Consultant (DSMC) for this city. 3. Two subprojects are taken up under tranche-1, one in the sector of Water Supply (WS) and another in Solid Waste Management (SWM), are now under implementation in Kohima. The water supply sub project is for the refurbishment of the existing Kohima Water Supply Scheme. The solid waste management sub project focuses in developing a new solid waste management site in the outskirts of Kohima at Lerie. Apart from the above said sub project components certain additional works also proposed in SWM under tranche 1, details of the proposed components are given in table Two subprojects are planned under Tranche-2.The major one is the civil work for providing a new underground water supply distribution pipe system for a total length of 318 km. The contract agreement has been executed in February 2013 and the trenching & laying of pipes was started in January, 2014, around 11.02% of the works has been completed against the targeted progress of 77.65% (as on 31 st December, 2014). The other subproject in Tranche-2 is installation of 21 bulk water meters & 6000 metered connections in the new distribution system. As the works can be started only after the completion of laying the pipe line network, the bidding has been postponed. 5. This is the consolidated report on implementation of Social Safeguard Activities for the period from 1 st July, to 31 st December, 2014, and this is prepared in compliance with the ADB s Safeguard Policy Statement, (SPS 2009). 2 Implementation Arrangements 6. The Ministry of Urban Development (MOUD) is the national-level executing agency (EA) of the program. An IPCC is also established in MOUD incorporating a Social Safeguard Officer. A National Steering Committee (NSC) will monitor the fund use and overall implementation performance of the Investment Program. In each State there will be a State Steering Committee (SSC), an Investment Program Empowered Committee (IPEC) and a State Investment Program Monitoring and Implementation Unit (SIPMIU).The SIPMIU is responsible for overall program implementation, monitoring and supervision in the respective cities. 7. The SIPMIU will have a Social Safeguards Unit headed by a sociologist. Depending on the anticipated volume of resettlement and other related issues, a Resettlement Officer & supporting NGOs may be required as part of the Unit. 3

6 ROs/and NGOs will be responsible for RP implementation. However, in small projects where resettlement issues are is not anticipated or minimal, an extensive staffing in the SSU is not essential. In case any resettlement issues arise during the subsequent stages of implementation, the services of competent personnel/agencies like RO/NGO shall be engaged. The generalized institutional roles of the involved entities are identified in Table 1 as a guide line. The Social Safeguards Unit under SIPMIU will take care of redressing grievances and mitigating negative social impacts caused due to the project with the aid of the existing system and shall request the Program Director for further reinforcement of support staff/ngos if required. Table 1. Institutional Roles Sl no: Activities Agency Responsible Sub-project Initiation Stage 1 Finalization of sites/alignments for sub-projects SIPMIU&DSMC 2 Disclosure of proposed land acquisition and sub-project SIPMIU details by issuing public notice 3 Meetings at community/ house hold level with APs of SSU/&NGO land/property 4 Formation of Valuation Committees SIPMIU RP Preparation Stage 5 Conducting Census of all APs SSU/&NGO 6 Conducting FGDs/ meetings / workshops during SIA SSU/&NGO surveys 7 Computation of Replacement Values of land/properties SSU&DSMC proposed for acquisition and for associated assets 8 Categorization of APs for finalizing entitlements SSU 9 Formulating compensation and rehabilitation measures SIPMIU 10 Conducting discussions/ meetings with all APs and other stake holders SIPMIU/&NGO 11 Fixing compensation for land/property with title holders VC/SIPMIU 12 Finalizing entitlements and rehabilitation packages SIPMIU 13 Disclosure of final entitlements and rehabilitation SIPMIU/&NGO packages 14 Approval of RP IPCC/ADB 15 Sale deed execution and payment of compensation SIPMIU 16 Taking possession of land SIPMIU RP Implementation Stage 17 Implementation of proposed rehabilitation measures SSU/&NGO 18 Consultations with APs during rehabilitation activities SSU/&NGO 19 Grievances redressal SSU/&NGO/GRC 20 Internal monitoring SIPMIU 21 External monitoring External Agency SSU= Social Safeguards Unit AP=affected person, VC=valuation committee, FGD=focus group discussions, GRC = grievance redress committee, NGO = nongovernment organization, SIPMIU = statelevel investment program management and implementation unit, IPCC = investment program coordination cell, RO = resettlement officer, RP=resettlement plan, SIA=social impact assessment. 3 Sub Project Components in Kohima Municipal Council Area 8. Subproject components taken up under various tranches in Kohima Municipal Council is summarized in Table.2 4

7 Table 2. Sub projects &components Sl No Name of the Tranche Components subproject 1 Refurbishment of 1 Construction of 18 new RCC Kohima Water reservoirs Supply Scheme Rehabilitation of the water treatment plant at Jotsoma Supply& installation of two electrochlorinators in the water treatment plant 2 Civil Works and 1 Construction of a 2 km long Procurement of approach road. Equipment for Construction of 50 tons/day Sanitary Land Fill, capacity compost plant Compost Plant and Development of a sanitary land fill Approach Road at site of 8000 sqm area Lerie Formation of sqm land for future land fills Installation of a leachate treatment plant to handle lt/day Construction of support facilities like i. Internal roads ii. Dedicated electrical substation with generator back up iii. Service buildings like 3 Supplying and laying of distribution network of 318 km in Kohima Municipal Council area 4 Supply & installation of 21 bulk water administrative block, garages for primary & secondary vehicles, toilet block, security house, weigh bridge control room etc iv. Electrification of the entire buildings and yard lighting of the site iv. Water supply facilities to all buildings including firefighting facilities v. Green belt & landscaping the entire site Development of a new solid waste management site at Lerie vi. Retaining wall to protect the land slips and cross drainages (additional works) 2 Providing a new water supply pipe line distribution network of total length of 318 km Installation of 21 bulk water meters Providing 6000 metered house connections 2 Procurement & installation of 21 bulk water meters at the out lets of 5

8 Sl No Name of the subproject meters and 6000 metered connections Tranche Components 4 Social Safeguard Activities for Tranche -1&2 Sub projects 4.1. Introduction distribution tanks, main storage tank at the water treatment plant and other nodal points Procurement & installation of 6000 domestic water meters and changing over the existing consumer connections from the bunch system to the underground loop system which will be installed under subproject-3 above 9. In order to identify the Resettlement Impacts, if any, due to the subproject implementation, the SIPMIU officials & the DSMC experts have carried out sufficient site visits and consultative inspections in the project areas during the preparation of RP. Based on this and further discussions held with the local public in the city, it has been confirmed that the implementation of the above subprojects would not have any Involuntary Resettlement (IR) impact at any stage. Hence all the sub projects of tranche-1&2 with respect to Involuntary Resettlement impact would be under Category C. However, periodic site visits and discussion with local public will be continuing during the project implementation to confirm that no resettlement issues remain unnoticed or unaddressed Scope of Impact Tranche -1 Sub Projects 10. Solid Waste Management: Permanent land acquisition is not envisaged in both the sub projects taken up under tranche -1. The development of Solid Waste Management Plant at Leire is confined in the land owned by the Kohima Municipal Corporation. The work is in progress and as per the revised program finalized by the civil contractor, on 10th Nov 2014, all works are targeted to be completed by April, As the Leire (SWM) site is surrounded by agricultural lands, three households those who are having agricultural land nearby the SWM site encroached to the area earmarked for SWM (away from construction site as well as green belt area) and constructed cattle shed and shelter for cattle caretakers. This was noticed in the month of September, 2013 and a meeting was arranged by resettlement specialist of DSMC immediately (on 21st September, 2013) to discuss the issues with encroachers. During that meeting they had agreed to vacate the land based on the request of SIPMIU (details of the meeting was illustrated in the semiannual report prepared for the period from July to December, 2013). However this issue was remained unsettled for a long period, further district administration was informed by SIPMIU to intervene in the issue and now it is in the process. District Collector (DC) has inspected the site in the month of June, 2014 and consultations with the encroachers are in progress. 12. Water Supply: 10 tanks out of 18 are commissioned and another 7 are ready for commissioning. The construction work of 7 tanks and the refurbishment of the old water treatment plant at Jotsoma including installation of two new electro chlorinators are in progress. The construction of the remaining 1 tank (Assam 6

9 Rifles HQ) is now proposed under Tr-2 (Construction of storage reservoirs for 9 hydraulic zones ). No IR issues are identified at these project locations during this reporting period Tranche -2 Sub Projects 13. Laying of new water supply distribution network of pipe lines of total length of 318 km in Kohima Municipal Area is the major work planned under water supply sub project of tranche-2. The civil works are proposed to be carried out within the existing RoW and road shoulders. Therefore, no land acquisition is envisaged in this sub project. Digging along the existing right-of ways (RoW) of city roads for laying of these lines will have no impacts as the proposed pipelines will be laid on the edge of the road. The maximum required trench width for laying down of different sizes of pipe lines range between 30cm to 100 cm only and can be accommodated in the road shoulders. At locations where there are permanent structures blocking the alignment of pipe lines, suitable measures to deviate these structures by using appropriate pipe bends are provided at the stage of pipe line design itself. Care is also taken to minimize adverse impacts by selection of appropriate alignment for the pipe lines. The trenching, pipe laying, jointing & pressure testing works etc inside the city will be done in a phased manner & fast pace to minimize the period of disruption. The details of the works have been communicated to the State PWD who is maintaining the PWD& Municipal roads in Kohima. 14. Advance notices (based on the construction plan developed by the civil contractor) to the residents of the area will be given at least 7 days prior to the commencement of the civil works in the respective locality. The community organizers mobilized in SIPMIU under Social Development Officer shall undertake the activities of construction facilitation with the guidance of Community Development and Construction Facilitation expert of DSMC. The COs shall be trained periodically. Sufficient provision is also made in the contract agreement for the repair of roads, providing temporary access across the pipe line trenches (wherever necessary), repair of existing water pipe lines, cables, electric posts, dust prevention, soil erosion and all other similar menaces. 15. The joint site visits carried out by the Resettlement Specialist of DSMC along with water supply design engineers did not identify any IR impact and the presence of IPs. However, in case of any change in locations and scope of work, IR screening and RPs (if required) shall be prepared and disclosed in ADB & EA web sites. 16. Since Nagaland Government is not maintaining any land records, disputes on ROW shall be settled through discussions during the time of project implementation, the service of Community Organizers (appointed under SIPMIU for community participation) shall be utilized for these activities. Social Safeguard Expert of SIPMIU, Resettlement Specialist and Construction Facilitation and Public Awareness Experts of DSMC will play a leading role in addressing the people s concerns during the project implementation Additional Works proposed under Tranche Integrated SWM: Works under this subproject includes the procurement of vehicles, construction of rest rooms and construction of dry waste segregation unit. As construction of rest rooms and dry waste segregation unit is planned within the boundary of existing SWM site, no additional land is required for this sub project. The base line (Involuntary Resettlement Screening) survey conducted on , shows that all the lands earmarked for construction of community toilet block are uninhabited and barren. 7

10 18. Construction of 5 community toilet blocks; The lands earmarked for the two locations are belonging to Kohima Municipal Council (KMC) and one location belongs to the PHED, Government of Nagaland. The remaining two belong to three private individuals. However, all the three land owners have voluntarily surrendered the land required for the project. The base line (Involuntary Resettlement Screening) survey conducted on , shows that all the lands earmarked for construction of community toilet blocks are uninhabited and barren. Based on the above assessments the subproject has been categorized as C for Involuntary Resettlement (IR) impact as per the ADB s Safeguard Policy Statement, Hence no Resettlement Plan (RP) needs to be prepared for this sub project at this stage. A SIA& IR screening report was prepared for this sub project and submitted for ADB s review. The report shall be further modified based on the review comments. 19. Construction of 7 service reservoirs; under this subproject 7 service reservoirs are proposed for 9 hydraulic zones (with multiple compartments at two locations). The lands earmarked for relocating the 6 storage tanks (out of 7) are in possession of the forest department and consent from the department as well as from the traditional land owners (T-Khel ) have been obtained. The 7th land belongs to private individual. The land owner has voluntarily surrendered the land for the project. All the lands are uninhabited. This subproject will not entail any private land acquisition and involuntary resettlement. Based on the above assessments the subproject has been categorized as C for Involuntary Resettlement (IR) impact as per the ADB s Safeguard Policy Statement, Hence no Resettlement Plan (RP) needs to be prepared for this sub project at this stage. A SIA& IR screening report was prepared for this sub project and submitted for ADB s review. The report shall be further modified based on the review comments. 20. Septage Management: The Plant shall be constructed in the land owned by KMC at Dzuruzou (outskirts of the city around 3 Km from habitation), KMC is having around 94 Acres of land in that particular location and the project requires only one hector. The land earmarked for the construction of plant is uninhabited. The approach road is already in place and under use by villagers and vehicles transporting solid waste to dumping site. The IR screening report prepared for this work is attached as appendix -1 of this report Status of RP implementation 21. As discussed above the subprojects taken up under tranche 1 & 2 do not impart any sort of IR and IP impacts and hence the status of RP implementation is not relevant here. However the subproject wise IR impact status is summarized in table.3 below. As part of sensitizing the importance and reviewing the status of safeguard compliance during the subproject implementation periodic meetings have been conducted at construction sites, details are summarized in table 4. The project managers and site engineers of civil contractors and safeguard specialists of SIPMIU and DSMC along with technical staff were attended the work shop and clarified their doubts. Table 3. Status of civil construction and RP implementation in tranche-1 sub projects Sl No Subproject sector & corresponding Tranche Activities Status of RP Implementation 8

11 Sl No Subproject sector & corresponding Tranche 1 Water Supply (Tranche- 1) 2 Solid Waste Management (Tranche- 1) 3 Water Supply (Tranche- 2) Activities Status of RP Implementation Construction of 18 new RCC Reservoirs Renovation of water the treatment Plant at Jotsoma Supply & installation of chlorinators Development of a new solid waste management site with sanitary landfill, leachate treatment plant and all other essential infrastructure at Lerie New water supply distribution pipe line network of total length 318 km in Kohima Municipal Area. No IR Impact No IR Impact No IR Impact. However corrective plan shall be prepared if any issues are identified during the project implementation 4.4. Activities carried out for Public Participation and GAP 22. Various activities conducted in the sector of Community Development, Public Participation and Gender Development during the period from 1st July, 2014 to 31 st December, 2014 is summarized in below table (table 4) and snap shots and minutes of the meetings/fgds are shown in the appendix -2. 9

12 Table 4: Summary of Community Development, Public Participation and Gender Sensitization programs conducted during the period from 1 st July to 31 st December, 2014 in kohima Sl.No Date Name of the Activity Venue Objective Outcome 1 05/05/ /05/ /07/ /07/ /07/ /07/14 Seminar on pilot project and importance of Gender Sensitization Training on safeguards and construction facilitations to Project staff, Community Organizers and contractoers Consultation with community members regarding Solid Waste Management. Consultation with community members regarding Solid Waste Management. Consultation with community members regarding Solid Waste Management School WATSAN( Water & Sanitation) Campaign 7 10/07/14 School WATSAN Campaign SIPMIU hall SIPMIU hall Poterlane Colony Old Ministers Hill Colony Chandmari Colony Govt Middle School Lower Chandmari Mount Sinai Higher Secondary School Create awareness on pilot project, Gender issues and develop action plan for implementation of pilot project with the support of local people. Create awareness on safeguards, importance of construction facilitations in implementation of safeguards in water supply projects and role of community organizers in construction facilitation. To create consensus on waste management and segregation To create consensus on waste management and segregation To create consensus on waste management and segregation Discussion on water related problems and solid waste management. Discussion on water related problems and solid waste management. Prepare draft action plan Got sensitized 16 Got community consensus on waste management segregation Got community consensus on waste management segregation Got community consensus on waste management segregation Participation Male Female Got sensitized Got sensitized /07/14 School WATSAN Campaign Public School Discussion on water related problems and Dzuvuru solid waste management. Got sensitized /07/14 Public meeting Old Minister Hill Public were in full support of Introduction of SWM pilot project. panchayat hall the pilot project /07/14 Meeting at construction site with the Pipeline laying at Sensitize the labours and site engineers of labors Old Ministers Hill contractor on Occupational Health &Safety Sensitization of labors /07/14 Meeting with rag pickers at the present Sensitize labors on safety and segregation Merema Kohima dumping site Merema. on wet & dry waste Sensitization of labors /08/14 School Cleanup campaign and waste Schola Loges Students were sensitized on Sensitized students on waste segregation segregation School. waste segregation /08/14 School Cleanup campaign and waste St Josephs School Students were sensitized on Sensitized students on waste segregation segregation Lower chandmari waste segregation /08/14 Clean School campaign Dainty Buds Sensitized students on waste segregation The students pledge to follow

13 Higher Secondary School and short clipping on waste was shown to students waste segregation in school and at home 15 14/08/14 Waste segregation training at sector Er Hutovi s Demonstration on waste segregation at level at lower Chandmari resident household level Got sensitized /08/14 Meeting with Women group of Old Kopila Awomi s Discussion on waste segregation at They agreed to follow waste Ministers Hill resident household level and on Gender. segregation /08/14 Public meeting with Sector a of Poterlane Poterlane Discussion on waste segregation and colony Panchayat Hall introduction on the ongoing project Got sensitized /08/14 Meeting with Church leaders and Koinonia Baptist members Church(Poterlane) Discussion on SWM Pilot Project Got sensitized /08/14 Clean School campaign Vineyard school Demonstration on waste segregation Got sensitized /08/14 Clean School Campaign Govt Middle School Poterlane Demonstration on Waste segregation Got sensitized /08/14 Joint meeting with panchayat, KMC, Lower Chandmari Discussion on waste segregation and on Wednesday Bazaar women group Panchayat Hall the pilot project Got sensitized /08/14 Meeting with the High way vendors Penuel shop Discussion on waste segregation and the pilot project Got sensitized /08/14 Training on waste segregation with drivers and sweepers of ward no 14 Poterlane panchayat hall Demonstration on waste segregation Agreed to follow waste segregation during waste collection /09/14 Vendors training on waste segreagtion Waiting shed lower Chandmari Demonstration on waste segregation Got sensitized /09/14 Waste segregation training to Immanuel Immanuel Baptist Baptist church youth Church Demonstration on waste segregation Got sensitized /09/14 Combined meeting with sector members of sector B and D Near High court Demonstration on waste segregation Got sensitized /09/14 Meeting with sector B Chairman resident Demonstration on waste segregation Got sensitized /09/14 Vendors training on waste segregation Poterlane Panchayat Hall Demonstration on waste segregation Got sensitized /09/14 SWM pilot project meeting with the Public School sector members Poterlane Demonstration on waste segregation Got sensitized /09/14 Conducted waste segregation with Ao Ao Baptist Church Demonstration on waste segregation and a Baptist church youth Chandmari short film on waste Got sensitized /09/14 Waste segregation with church members Yimchunger Demonstration on waste segregation and a Baptist church short film on waste Got sensitized /09/14 Vendor training on waste segregation T.Khel Market Demonstration on waste segregation Got sensitized /09/14 School clean up campaign Modern College Demonstration on waste segregation and Students pledge to follow Dzuvuru short film on waste waste segregation /09/14 Clean School Campaign Ministers Hill Demonstration and Participation of Students pledge to follow Higher Secondary students in waste segregation waste segregation at all time School /11/14 Meeting with contractors Hotel Japfu Update of all work progress Got sensitized 20 11

14 36 13/11/ /12/14 Meeting with hotel manager, schools administrator, church pastor, hostel warden Meeting with the rag pickers at dumping site Hotel Japfu Merema Discussion on waste and the on going pilot project Discussion on waste segregation and checking on the safety gears and the progress of the pilot project Got sensitized 30 Got sensitized 4 12

15 5 Compliance status of loan covenants 23. The compliance status with respect to loan covenants is presented in table 5 below Table 5. Status of Loan Covenants Sl No Loan Covenant Agency Status of Compliance 1 GOI and the State will ensure that all land and right of way required for the investment program are made available in timely manner. Adequate compensations are provided prior to the signing of relevant civil work contracts, and involuntary resettlement is carried out in accordance with the resettlement frame work (RF) and resettlement plans (RPs) agreed upon between the Government and ADB. An RP will be prepared for each sub project involving land acquisition and resettlement and shall be submitted to ADB for review and approval prior to award of any related civil work contract. 2 GOI and the State will ensure that sub projects will not negatively impact on vulnerable groups, such as indigenous people. In the event of their involvement in any of sub projects, the GOI and the states will ensure the that the sub projects are carried out in accordance with the Indigenous People Development frameworks (IPDF) agreed up on between GOI, the States and the ADB and comply with ADBs policy on Indigenous People (1998) 3 In the event any issues related to indigenous people arise in course of project implementation, the borrower and the state shall ensure to address those issues in accordance with the applicable laws and policies of the borrower, ADB s policy on indigenous Peoples (1998) and the Indigenous Development Framework for the facility as agreed between the Borrower, the State and ADB. In the case of any discrepancy between the Borrower s legislation and ADB s policy, ADB s policy shall prevail. 4 GOI and State will ensure that all civil works contractors comply with all applicable labour laws, including those on occupational Government India Government Nagaland Government India Government Nagaland Government India Government Nagaland Government India Government Nagaland of & of of & of of & of of & of No private land acquisition and resettlement issues are involved under any of the subprojects under the Investment Program. Hence RPs has not been prepared. No negative Impact on vulnerable groups Agreed. However, no issues related to indigenous people are anticipated in the course of execution. Adequate provision has been made in the contract agreements 13

16 Sl No Loan Covenant Agency Status of Compliance health and safety, and do not employ child labour as defined in national legislation for construction and maintenance activities. Priority work will be given to people from the area where the works are implemented and men and women will receive equal pay for work of equal value. 5 Within six months of the Effective Government of Notification dated Date, the State shall have Nagaland 18 th January 2013 is established a grievance reporting attached as and redressal mechanism Appendix -4 6 Project Impact 24. The subprojects now being taken up in Kohima under the investment program in the sector of water supply & solid waste management as well as the efforts for the capacity building of Kohima Municipal Council will speed up the pace of the socio economic development of the City by substantially improving the urban environment and living standards of the citizens. The implementation of the subprojects will not create any major adverse impact on community. 7 Policy and Legal Framework 25. The policy framework and entitlements for all the subprojects of the investment program under tranche 1&2 are based on the National Resettlement and Rehabilitation Policy, 2007 (NRRP) and ADB s Safeguard Policy Statement, (SPS) Validation and Verifications of APs 26. Since the subprojects are falling in the C category as per ADB Policy on Involuntary Resettlement (1995) for Tranche-1 and ADB Safeguards Policy Statement (2009) for Tranche-2, no RP was prepared. 9 Public Consultations and Disclosure of RP 27. Public consultation and information dissemination are treated as a two way process through which the information is passed on to public and their feedback is sought to understand their issues. In addition to the discussion of specific issues, details about the safeguard policies and GRC of the project are broadcasting in all public meetings. The consultative process shall be continued throughout the project period. The activities conducted during the current reporting period is summarized in table.4 10 Grievance Redressal 28. A Grievance Redressal Committee has been constituted as per the guideline of EMP. The same is attached as Appendix Monitoring and Reporting 29. As part of streamlining the collection and segregation of household solid wastes before commissioning the SW plant at Leire, a pilot project has been developed and the same is under implementation at two wards of KMC, this activity plan shall be updated frequently based on the feedback from the field. Gender sensitisation activities and plan for inclusive (gender) development shall also be discussed throughout the program. 14

17 12 Issues and Action Plan 30. The pilot project (for streamlining source segregation, collection and transportation) now being implemented in two wards of KMC shall be implemented in other wards also. 15

18 APPENDICES 1

19 Appendix 1: IR screening report for Septage Management Scheme Social Impact Assessment & IR Screening Report Septage Management Scheme for Kohima (Sub project taken up under Tranche -2) Loan Number: 2528 IND INDIA: North Eastern Region Capital Cities Development Investment Program Project City: Kohima, Nagaland State Implementing Agency: State Investment Program Management and Implementation Unit Executing Agency: Urban Development Department, Government of Nagaland Date of Submission: January

20 ABBREVIATIONS ADB - Asian Development Bank DSMC - Design, Supervision and Management Consultant EA - Executing Agency GoI - Government of India IA - Implementing Agency KMC Kohima Municipal Council MFF - Multi-tranche Financing Facility MoUD - Ministry of Urban Development NERCCDIP - North Eastern Region Capital Cities Development Investment Program PD - Project Director PIU Project Implementation Unit SIPMIU State Investment Program Management and Implementation Unit UDD - Urban Development Department i

21 Table of Contents 1 Introduction Existing Sanitation and Septage Management Infrastructure in Kohima Project Description Scope of Land Acquisition and Resettlement Impact Conclusion... 6 List of Appendices Appendix 1: Location of project site (Google Image)... 7 Appendix 2: Land ownership details... 8 ii

22 1 Introduction 1 The NERCCDIP envisages achieving sustainable urban development in the project cities of Agartala, Aizawl, Kohima, Gangtok and Shillong through investments in urban infrastructure sectors. The urban infrastructure and service improvements targeted in Kohima under the program are in the following sectors (i) water supply, (ii) solid waste management (iii) sewerage and sanitation and (iv) capacity development of the stake holders. The expected impact of the NERCCDIP in this city is some of the increased basic amenities, reduced poverty and social & financial imbalances. The expected outcome of the program will be an improved urban environment and living standards for the people expected to be living in Kohima till the end of the design period of the program which is apparently the year The program will provide support to (i) improve and expand the few of the prioritized urban infrastructure and its subsequent services in Kohima (ii) strengthen the institutional, management, and the financing of KMC. The program of Kohima will be implemented over a six year period beginning in 2009, and will be funded by a loan via the MFF of the ADB. The SIPMIU of Kohima is the Project Implementation Unit (PIU). The program in Kohima is now under implementation under the tranche-1& 2 loan support of the ADB. 2 The following are the major deficiencies in basic amenities in the City in the sector of water supply, garbage disposal and sanitation. The PHED water supply system is connected to only one fifth of the households of the City and that too limited to certain areas. The water supply is limited to once in three to seven days in the lean season. The present water sources are inadequate to meet the water requirement. The garbage collection is not satisfactory. Collection from households is twice in a week. Garbage is not segregated at its source. There is no sewerage system in the City. Human waste is disposed into pits or septic tanks. 3 Except for a sewerage system for the City, efforts are being taken to rectify the above deficiencies through the subprojects now being implemented undertranche1& 2 as well as the subprojects proposed under variations in Tranche -2 4 This Social Impact Assessment and Involuntary Resettlement (IR) screening report discuss about the Septage Management Scheme for Kohima Municipal Council This subproject proposed to be taken up under tranche -2 in sanitation sector. 2 Existing Sanitation and Septage Management Infrastructure in Kohima 5 At the present, sanitation infrastructure is looked after by Kohima Municipal Council (KMC). The City is divided into 19 wards, each having a sanitation committee that helps citizens in improving the sanitation in their premises. The Sanitation committees are also monitoring the functioning of existing sanitation mechanism. There is no sewerage system in the City. Household Sanitary wastewater is discharged into Septic tanks for treatment and disposal into soak pits or in surface drains. Sludge in the wastewater gets accumulated in the septic tanks and get anaerobically digested. This sludge is periodically removed and disposed. Normally Septic tanks are designed for a cleaning frequency of two years. However, In Kohima, because of space constrains and other reasons, the septic tanks provided are not of correct design and capacity; most of them are under sized. These septic tanks are required to be cleaned more frequently; also accumulated septage is not getting fully stabilized. Disposal of this septage without further treatment is an 3

23 environment hazard. Citizens awareness about hygiene is good and there is preparedness for improvements in the existing system. 6 Toilets & Septic Tanks: Almost all houses are having lavatories and about 95 % are connected to septic tanks and the remaining to open dug pits covered at top. Lavatories are pour- flush/cistern type. Septic tanks have not been constructed in a scientific way. They have been provided as per the availability of land, finances of the house owner as well as mason s skill. Major problem in many cases is the volume of the tank. Because of space constraints, soak pits have been provided for very few tanks only. Other septic tanks are discharging the effluent into storm water drains. The septage accumulated in the tanks is collected by vacuum tankers and disposed off untreated at the waste dumping site belonging to KMC at Dzuruzou, about 12 km from Kohima. This practice of collecting and transportation to dumping site was started in 2006 after KMC acquired a 3000 lit capacity Vacuum tanker. Prior to this, septic tanks were emptied in to the adjacent storm water drains through a bottom outlet during rainy season. This practice is still continuing, but to a lesser extent, as KMC s infrastructure is not adequate to provide vacuum tanker service to all the dwellings. Because of insufficient volume and poor maintenance, the septic tanks get filled up with septage with in short durations, resulting in short circuiting & overflow of sullage of improper quality into storm water drains. Thus more frequent emptying of septic tanks is required in Kohima 7 Collection and Transport of Septage; As pointed out, till the year 2006, there was no mechanized arrangement for cleaning and emptying of the septic tanks. It is still a practice still in Kohima to drain the septic tanks in to the steep storm water drains during rainy season taking advantage of the torrent flow and steep gradient. KMC acquired its first vacuum tanker in the year Second vacuum tanker arrived in 2009 and third one is procured in the year Out of these three, one acquired during 2009 is out of service. Thus only two vacuum tankers are in operation and in a week of 5 working days, 20 to 30 tanks are emptied. 8 Treatment and Disposal: At the present there is no arrangement for the treatment of septage. Untreated Septage is disposed off at the disposal site at Dzuruzou without treatment, causing serious environmental pollution at Dzuruzou. 9 Administrative Mechanism: In the present, operating mechanism, citizens submit request to KMC for the removal of septage from their septic tank as and when septage accumulates to full level. The KMC shall inform the date of convenience after collecting the service charge. The tariff is Rs per trip for the 3000 lit capacity vacuum tanker and Rs 4500 for the 5000 lit capacity vacuum tanker. The ward level sanitation committees monitors the malfunctioning septic tanks as well as illegal draining of septic tanks in to storm water drains. There is provision in KMC to penalize illegal draining of septic tanks. 3 Project Description 10 Since Kohima is not having sewerage system, City s sanitation is fully dependent on proper functioning of septic tanks as well as proper collection, transportation, treatment and safe disposal of septage. This situation will remain to significant extent, even after the introduction of a sewerage scheme in future. This is because of the topography of the City and narrowness of some roads; it will not be possible to cover the entire City under sewerage scheme. Thus providing a good septage management system and replacement of existing septic tanks with scientifically designed septic tanks is a necessity for safeguarding City s environment. 4

24 11 Existing Septage management Infrastructure is unscientific and also inadequate even to serve the present population. The infrastructure requires improvement and expansion to make it suitable for the expected future increase in population. There are two major short comings in the existing system Inadequate collection & transportation arrangements Unscientific disposal of septage 12 As the present system is not adequate to serve entire City, many households are draining their septic tanks into storm water drains. Disposal of untreated septage and sullage is cause of several concerns. 13 Considering the present practice of septage collection,3 nos 3 cubic metre capacity and 5 nos of 5 cubic metre capacity vacuum tankers are proposed for septage transportation from the City. The septage will be unloaded in a collection chamber from where it will flow through a de-gritting channel to Equalization cum conditioning tank. In the de-gritting channel, heavy particles like sand, grit etc will settle down, which will be removed periodically. Two grit channels one working and one standby will be provided with isolation gates. 14 In equalization tank, water will be aerated and stirred with air flowing through it. Here lime will be added for correcting the ph as well as for conditioning of the water for better solid liquid separation. By addition of lime, release of hydrogen sulfide which causes odor will be arrested. Septage is expected to have suspended solid in the range of 1 to 2 %. In order to increase this concentration to 5 to 7 % for economical mechanical dewatering, sludge from Equalization tank will be feed to Sludge Thickeners. 15 In Sludge Thickener, solid liquid separation will take place by gravity separation process. Underflow from thickener will be collected in the sludge storage tank and over flow will be taken to biological treatment section (Activated Sludge process). 16 Sludge from Sludge Storage Tank will be fed to mechanical sludge drying equipment. Solid Bowl Centrifuge/Filter press will be used for this purpose. Sludge cake form mechanical dewatering will have 30 to 40 % solids and will be of spadable consistency. It shall be stored in a shed for further drying and packed & disposed off for use as farm manure. 17 The liquid from dewatering machine will be sent back to an equalization tank for re processing. Polyelectrolyte will be added for improving solid liquid separation in thickener and in mechanical dewatering. Separated Liquid will be treated for removal of biological matter by activated sludge process. The effluent from the activated sludge process will be disinfected and disposed off into inland surface water. Following are the project components (a) (b) (c) (d) (e) (f) (g) (h) Procurement of 3 cum capacity vacuum tankers -3 nos Procurement 5 cum capacity vacuum tankers -5 nos Construction of Plant buildings Installation of machineries & equipment s in the plant Developing approach road to Plant site & internal road Substation including generator back up for Plant Yard lighting of Plant site Water supply system for Plant site 4 Scope of Land Acquisition and Resettlement Impact 18 The Plant shall be constructed in the land owned by KMC at Dzuruzou (outskirts of the city around 3 Km from habitation), KMC is having around 94 Acres of land in that particular location and the project requires only one hector. The land earmarked for 5

25 the construction of plant is uninhabited. The approach road is already in place and under use by villagers and vehicles transporting solid waste to dumping site. The location map of the project location is shown in the google imagery attached as appendix -1, further the land ownership details of the land earmarked for the project is attached as appendix The subproject will not entail any private land acquisition and involuntary resettlement. This was confirmed during the field reconnaissance conducted on 9th December, 2014 by the Resettlement Specialist of DSMC and Assistant Engineers of SIPMIU along with KMC officials. 5 Conclusion 20 Based on the above assessments the subproject has been categorized as C for Involuntary Resettlement (IR) impact as per the ADB s Safeguard Policy Statement, Hence no Resettlement Plan (RP) needs to be prepared for this sub project at this stage. 6

26 Appendix 1: Location of project site (Google Image) 7

27 Appendix 2: Land ownership details 8

28 9

29 10

30 Appendix 2: Snap shots and minutes of the meetings/fgds. Meeting with Immanuel & Ao Baptist Youth Church Meeting with Koinona Baptist Church Members. Meeting with Yimchunger Baptist Church members Meeting with vendors Meeting with T Khel Market 11

31 Clean School Campaign at Schola Lojes WATSAN Campaign at Public School Dzuvuru Clean School Campaign at Govt Middle School Poterlane Clean School Campaign at Minister s Hill Baptist Higher Secondary School Kohima WATSAN Campaign At Mount Sinai Higher Secondary School Clean School Campaign At Modern College 12

32 Meeting with Chandmari Sector Meeting with Women group of Lower chandmari Meeting with Women group of Old Ministers Hill Colony 13

33 14

34 15

35 16

36 17

37 18

38 19

39 20

40 21

41 22

42 23

43 24

44 . 25

45 Appendix 3: Notification of Grievance Redressal Committee 26

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

Land Acquisition and Resettlement Due Diligence Report

Land Acquisition and Resettlement Due Diligence Report Land Acquisition and Resettlement Due Diligence Report Document stage: Draft for consultation Project Number: 48434 Loan and/or Grant Number(s): {LXXXX; GXXXX; TAXXXX} March 2016 India: Visakhapatnam-Chennai

More information

IND: Northeastern Region Capital Cities Development Investment Program Aizawl Water Supply and Sewerage Subproject

IND: Northeastern Region Capital Cities Development Investment Program Aizawl Water Supply and Sewerage Subproject Resettlement Plan December 2011 IND: Northeastern Region Capital Cities Development Investment Program Aizawl Water Supply and Sewerage Subproject Prepared by State Investment Program Management and Implementation

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

IND: Railway Sector Investment Program

IND: Railway Sector Investment Program Resettlement Framework Document Stage: Final March 2011 IND: Railway Sector Investment Program Prepared by Ministry of Railways for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 16 March 2011)

More information

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Resettlement Implementation Plan Project Number: 37381-013 September 2012 Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Prepared by SMEC Consultants for Dry Zone Urban

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

2. PLAN ADMINISTRATION

2. PLAN ADMINISTRATION 2. PLAN ADMINISTRATION 2.1 SECTION INTRODUCTION 2.1.1 This section gives an overview of District Plan administration. It discusses the sections of the Act that directly relate to the planning and resource

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

IND: Mumbai Metro Rail Systems Project

IND: Mumbai Metro Rail Systems Project Social Due Diligence Report October 2018 IND: Mumbai Metro Rail Systems Project Prepared by Mumbai Metropolitan Region Development Authority, Government of India for the Asian Development Bank. ABBREVIATION

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

13 LC S A BILL TO BE ENTITLED AN ACT

13 LC S A BILL TO BE ENTITLED AN ACT House Bill 199 (COMMITTEE SUBSTITUTE) By: Representatives Lindsey of the 54 th and Smith of the 70 th A BILL TO BE ENTITLED AN ACT 1 2 3 4 5 6 7 8 9 10 11 To amend Part 2 of Article 1 of Chapter 23 of

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

MON: Urban Development Sector Project Bulgan Subproject

MON: Urban Development Sector Project Bulgan Subproject Resettlement Completion Report Annual Report 24 December 2012 MON: Urban Development Sector Project Bulgan Subproject Prepared by Purevsuren Dorjnamjil, Resettlement Specialist, Project Management Unit

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

MLD - Kulhudhuffushi Harbor Expansion Project

MLD - Kulhudhuffushi Harbor Expansion Project Kulhudhuffushi Harbor Expansion Project (RRP MLD 36111-013) Due Diligence Report on Involuntary Resettlement and Indigenous Peoples March 2016 MLD - Kulhudhuffushi Harbor Expansion Project Prepared by

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan November 2012 IND: Chhattisgarh State Road Sector Project Dhamdha Khairagarh Road Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP)

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) Resettlement Planning Document Resettlement Framework Document Stage: Draft for Consultation Project Number: 42486 June 2016 India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) The resettlement

More information

FIRST READING: SECOND READING: PUBLISHED: PASSED: TREATMENT AND DISPOSAL OF WASTEWATER BY LAND APPLICATION

FIRST READING: SECOND READING: PUBLISHED: PASSED: TREATMENT AND DISPOSAL OF WASTEWATER BY LAND APPLICATION FIRST READING: SECOND READING: PUBLISHED: PASSED: TREATMENT AND DISPOSAL OF WASTEWATER BY LAND APPLICATION A RESOLUTION TO DELETE IN ITS ENTIRETY CHAPTER 13.30 ENTITLED TREATMENT AND DISPOSAL OF WASTEWATER

More information

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS ENVIRONMENTAL SAFEGUARDS Objectives To ensure the environmental soundness and sustainability of projects and to support the integration

More information

Indigenous Peoples Development Planning Document. IND: Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program

Indigenous Peoples Development Planning Document. IND: Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Draft for Consultation Project Number: 38412 June 2009 IND: Assam Integrated Flood and Riverbank

More information

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT Resettlement and Rehabilitation (R&R) Entitlement Framework RP297 Under

More information

Assessing the sanitation situation in a resettlement colony in Delhi

Assessing the sanitation situation in a resettlement colony in Delhi 8 August 2018 Assessing the sanitation situation in a resettlement colony in Delhi Using IRC's Faecal Waste Flow Calculator in India Shiny Saha and Ruchika Shiva Supporting water sanitation and hygiene

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

Definitions: (1) Administrator, The Administrator of the Callaway County Health Department or the designee of the Administrator;

Definitions: (1) Administrator, The Administrator of the Callaway County Health Department or the designee of the Administrator; Callaway County Sewer Ordinance Adapted from Missouri Revised Statutes Chapter 701 State Standards sections as numbered Below, changes reflect a higher stringency Effective Date March 1, 2006 Section 701.025

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

District of Chilliwack. Bylaw No A bylaw to provide for the regulation of holding tanks

District of Chilliwack. Bylaw No A bylaw to provide for the regulation of holding tanks District of Chilliwack Bylaw No. 1984 A bylaw to provide for the regulation of holding tanks The Council of the District of Chilliwack in open meeting assembled enacts as follows: 1. This bylaw may be

More information

TITLE 17 REFUSE AND TRASH DISPOSAL 1 REFUSE

TITLE 17 REFUSE AND TRASH DISPOSAL 1 REFUSE 17-1 TITLE 17 REFUSE AND TRASH DISPOSAL 1 CHAPTER 1. REFUSE. CHAPTER 1 REFUSE SECTION 17-101. Premises to be kept clean. 17-102. Definitions. 17-103. Storage of refuse generally. 17-104. Confiscation of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

Final Monitoring Report to the Board of Directors. on the. Implementation of Remedial Actions. for the

Final Monitoring Report to the Board of Directors. on the. Implementation of Remedial Actions. for the Final Monitoring Report to the Board of Directors on the Implementation of Remedial Actions for the Integrated Citarum Water Resources Management Investment Program Project 1 in the Republic of Indonesia

More information

HENRY COUNTY HEALTH CENTER REGULATION NO WASTEWATER TREATMENT SYSTEMS REGULATION

HENRY COUNTY HEALTH CENTER REGULATION NO WASTEWATER TREATMENT SYSTEMS REGULATION HENRY COUNTY HEALTH CENTER REGULATION NO. 89-1 WASTEWATER TREATMENT SYSTEMS REGULATION PURPOSE: A regulation governing the construction, modification, installation and operation of wastewater treatment

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Appendix 13 Resettlement Framework Dec 2011 SRI: Local Government Enhancement Project CURRENCY EQUIVALENTS (as of 27 June 2011) Currency Unit = Sri Lankan Rupee/s (SLR/Rs) Rs1.00 = $0.0091 $1.0 = Rs 109.8700

More information

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector Resettlement Planning Document Short Resettlement Plan for Tranche-2 Components Document Stage: Draft for Consultation Project Number: TA 7096-IND April 2010 India: Preparing the Energy Efficiency Enhancement

More information

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan February 2012 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Rehabilitation and Channelization of Storm Water Drains at Channi Himmat in Jammu City Prepared

More information

Monthly Progress Report

Monthly Progress Report Monthly Progress Report 1 st December 31 st December, 2013 Submitted by: RAY State Level Technical Cell, Gangtok - Sikkim Submitted to: State Level Nodal Agency, RAY - Sikkim TABLE OF CONTENT A. MONTHLY

More information

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project Internal Monitoring Report 37231-023 March 2016 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein do not

More information

13 Environmental Regulations

13 Environmental Regulations 13 Environmental Regulations 13.1 Hazardous Materials 13.1.1 Permits Required. All uses associated with the bulk storage of over two thousand (2,000) gallons of oil or motor oil, shall require a Conditional

More information

MISSISSIPPI LEGISLATURE REGULAR SESSION 2013 COMMITTEE SUBSTITUTE FOR HOUSE BILL NO. 719

MISSISSIPPI LEGISLATURE REGULAR SESSION 2013 COMMITTEE SUBSTITUTE FOR HOUSE BILL NO. 719 MISSISSIPPI LEGISLATURE REGULAR SESSION 2013 By: Representative Mims To: Public Health and Human Services COMMITTEE SUBSTITUTE FOR HOUSE BILL NO. 719 AN ACT TO REENACT SECTIONS 41-67-1 THROUGH 41-67-29

More information

India: Jammu & Kashmir Urban Sector Development Project

India: Jammu & Kashmir Urban Sector Development Project Resettlement Planning Document Full Resettlement Plan- Improvements to B.C Road from Shakuntala Crossing to Children s Hospital Including pedestrian subway Document Stage: Final Project Number: 41116 October

More information

THE STUDY ON SOLID WASTE MANAGEMENT IN THE MUNICIPALITY OF PHNOM PENH IN THE KINGDOM OF CAMBODIA. Final Report Summary

THE STUDY ON SOLID WASTE MANAGEMENT IN THE MUNICIPALITY OF PHNOM PENH IN THE KINGDOM OF CAMBODIA. Final Report Summary JAPAN INTERNATIONAL COOPERATION AGENCY (JICA) MUNICIPALITY OF PHNOM PENH KINGDOM OF CAMBODIA NO. THE STUDY ON SOLID WASTE MANAGEMENT IN THE MUNICIPALITY OF PHNOM PENH IN THE KINGDOM OF CAMBODIA Final Report

More information

Shanxi Small Cities and Towns Development Demonstration Sector Project

Shanxi Small Cities and Towns Development Demonstration Sector Project Involuntary Resettlement Due Diligence Report Project Number: 42383 September, 2012 Shanxi Small Cities and Towns Development Demonstration Sector Project Qingxu: Urban Surface Water Improvement Subproject

More information

ON-SITE INDIVIDUAL WASTEWATER TREATMENT SYSTEMS LAW CHAPTER 56 TOWN OF GORHAM ARTICLE 1 INTRODUCTORY PROVISIONS ARTICLE 2 DEFINITIONS

ON-SITE INDIVIDUAL WASTEWATER TREATMENT SYSTEMS LAW CHAPTER 56 TOWN OF GORHAM ARTICLE 1 INTRODUCTORY PROVISIONS ARTICLE 2 DEFINITIONS ON-SITE INDIVIDUAL WASTEWATER TREATMENT SYSTEMS LAW CHAPTER 56 TOWN OF GORHAM 56.101 Title 56.102 Applicability 56.103 Purpose 56.104 Authority 56.201 Words and Terms ARTICLE 1 INTRODUCTORY PROVISIONS

More information

SOIL REMOVAL AND DEPOSITION BYLAW

SOIL REMOVAL AND DEPOSITION BYLAW City of Vernon SOIL REMOVAL AND DEPOSITION BYLAW #5259 BYLAW NO. THE CORPORATION OF THE CITY OF VERNON ADOPTION BYLAW NUMBER 5259 AMENDMENTS AMENDMENT 5670 February 26, 2018 Regulatory Updates as follows:

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

Project Information Document (PID)

Project Information Document (PID) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name: Region: Project Information Document (PID) Sri Lanka: Puttalam Housing

More information

TITLE 17 REFUSE AND TRASH DISPOSAL 1 REFUSE

TITLE 17 REFUSE AND TRASH DISPOSAL 1 REFUSE 17-1 TITLE 17 REFUSE AND TRASH DISPOSAL 1 CHAPTER 1. REFUSE. CHAPTER 1 REFUSE SECTION 17-101. Definitions. 17-102. Premises to be kept clean. 17-103. Storage. 17-104. Location of containers. 17-105. Disturbing

More information

Public Water Supply and Sewerage Act

Public Water Supply and Sewerage Act Issuer: Riigikogu Type: act In force from: 01.01.2015 In force until: 30.06.2017 Translation published: 05.02.2015 Amended by the following acts Passed 10.02.1999 RT I 1999, 25, 363 Entry into force 22.03.1999

More information

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89) Resettlement Plan March 2012 IND: Bihar State Highways II Project Siwan-Siswan Subproject (SH-89) Prepared by Bihar State Road Development Corporation, Government of Bihar for the Asian Development Bank.

More information

CITY OF KAMLOOPS BY-LAW NO (AS AMENDED)

CITY OF KAMLOOPS BY-LAW NO (AS AMENDED) This is a consolidated by -law prepared by the City of Kamloops for convenience only. The City does not w arrant that the information contained in this consolidation is current. It is the responsibility

More information

Appendix 1 of this report contains definitions of terms and expressions referred to within the search result.

Appendix 1 of this report contains definitions of terms and expressions referred to within the search result. INTERPRETATION of Drainage and Water Search Appendix 1 of this report contains definitions of terms and expressions referred to within the search result. ENQUIRIES AND RESPONSES The search report on the

More information

IND: North Eastern Region Capital Cities Development Investment Program (NERCCDIP) T1 & T2 (Meghalaya)

IND: North Eastern Region Capital Cities Development Investment Program (NERCCDIP) T1 & T2 (Meghalaya) Social Monitoring Report Project Number: 35290-023 / 35290-033 March 2017 Period: July 2016 December 2016 IND: North Eastern Region Capital Cities Development Investment Program (NERCCDIP) T1 & T2 (Meghalaya)

More information

Environmental Protection Act

Environmental Protection Act Page 1 of 9 Français Environmental Protection Act ONTARIO REGULATION 224/07 SPILL PREVENTION AND CONTINGENCY PLANS Consolidation Period: From June 6, 2007 to the e-laws currency date. No amendments. This

More information

Village of Suamico. Chapter 9 SEWER UTILITY

Village of Suamico. Chapter 9 SEWER UTILITY Chapter 9 SEWER UTILITY 9.01 General... 1 9.02 Intent and Purpose... 1 9.03 Administration... 2 9.04 Definition... 2 9.05 Wastewater Rules and Regulations... 3 9.06 Sewer Service Charge System... 5 9.07

More information

AN ORDINANCE CONCERNING THE LAND APPLICATION OF SEWER SLUDGE IN BUCKINGHAM COUNTY ARTICLE ONE NAME

AN ORDINANCE CONCERNING THE LAND APPLICATION OF SEWER SLUDGE IN BUCKINGHAM COUNTY ARTICLE ONE NAME AN ORDINANCE CONCERNING THE LAND APPLICATION OF SEWER SLUDGE IN BUCKINGHAM COUNTY ARTICLE ONE NAME The name of the ordinance shall be The Sewer Sludge Land Application Ordinance for Buckingham County.

More information

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject)

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Updated Land Acquisition and Compensation Plan April 2018 LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Part 2 Prepared by the Department of Water Supply,

More information

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia)

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Republic of Sakha (Yakutia) of the Russian Federation Innovative Development of Preschool

More information

CHAPTER 3 GARBAGE AND REFUSE

CHAPTER 3 GARBAGE AND REFUSE 4-3-1 4-3-1 CHAPTER 3 GARBAGE AND REFUSE SECTION: 4-3-1: Definitions 4-3-2: Collection and Pickup of Garbage 4-3-3: Service Charges 4-3-4: Regulations 4-3-5: Vehicles and Equipment 4-3-6: Inspections 4-3-7:

More information

DEPARTMENT OF THE ENVIRONMENT. Instrument of Appointment by. the Secretary of State for the Environment. of Yorkshire Water Services Limited

DEPARTMENT OF THE ENVIRONMENT. Instrument of Appointment by. the Secretary of State for the Environment. of Yorkshire Water Services Limited DEPARTMENT OF THE ENVIRONMENT Instrument of Appointment by the Secretary of State for the Environment of Yorkshire Water Services Limited as a water and sewerage undertaker under the Water Act 1989 Department

More information

DONEGAL COUNTY COUNCIL PLANNING AND DEVELOPMENT ACTS,

DONEGAL COUNTY COUNCIL PLANNING AND DEVELOPMENT ACTS, DONEGAL COUNTY COUNCIL PLANNING AND DEVELOPMENT ACTS, 2000-2004 Manager's Order No: 2005PG1653 Reference Number: 05/2371 Name of Applicant: Address: MR HUGH KENNEDY C/O FERGUS C MURRAY CRONKERRIN ARDARA

More information

Gender Equality and Development

Gender Equality and Development Overview Gender Equality and Development Welcome to Topic 3 of the e-module on Gender and Energy. We have already discussed how increased access to electricity improves men s and women s lives. Topic Three

More information

Indonesia: Enhanced Water Security Investment Project

Indonesia: Enhanced Water Security Investment Project Initial Poverty and Social Analysis March 2018 Indonesia: Enhanced Water Security Investment Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy

More information

SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY

SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project (RRP CAM46293) SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY Country: Cambodia Project Title: Greater Mekong Subregion Tourism

More information

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program Indigenous Peoples Planning Framework Document Stage: Draft for Consultation Project Number: 47101 (IND) September 2013 India: Assam Power Sector Investment Program Prepared by Assam Power Generation Corporation

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Sri Lanka: Puttalam Housing Project

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Sri Lanka: Puttalam Housing Project Project Name Region Sector Project ID Borrower(s) Implementing Agency PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Sri Lanka: Puttalam Housing Project Report No.: AB2595 SOUTH ASIA Housing Reconstruction

More information

BOROUGH OF BUENA WORKSHOP AGENDA APRIL 8, 2019 PAGE 1

BOROUGH OF BUENA WORKSHOP AGENDA APRIL 8, 2019 PAGE 1 PAGE 1 MEETING CALLED TO ORDER: P.M. MEETING ADJOURNED: P.M. CALL MEETING TO ORDER: Flag Salute ROLL CALL OF ATTENDANCE: SUNSHINE LAW: MAYOR S REPORT: PUBLIC HEARING: This meeting is being held in compliance

More information

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT DRAFT COMPARATIVE ANALYSIS OF NEPAL s LEGAL FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT Note: The following is based

More information

BAN: Railway Sector Investment Program

BAN: Railway Sector Investment Program Resettlement Planning Document Resettlement Framework Document Stage: Final Project Number: 32234 June 2006 BAN: Railway Sector Investment Program Prepared by Bangladesh Railway, Dhaka, Bangladesh The

More information

TOWN OF PELHAM Office of the Selectmen

TOWN OF PELHAM Office of the Selectmen TOWN OF PELHAM Office of the Selectmen Town Hall Tel: (603) 635-8233 6 Village Green Fax: (603) 635-8274 Pelham, NH 03076 selectmen@pelham-nh.com BOARD OF HEALTH WASTE DISPOSAL SYSTEMS REGULATIONS CHAPTER

More information

Physical Planning CAP

Physical Planning CAP LAWS OF Physical Planning CAP. 8.03 43 [Subsidiary] PHYSICAL PLANNING REGULATIONS SECTION 64 (S.R.O. 67 of 1996) Commencement [1 October 1996] Short title 1. These Regulations may be cited as the Physical

More information

MINUTES OF THE REGULAR MEETING OF THE MOUNT LAUREL TOWNSHIP MUNICIPAL UTILITIES AUTHORITY

MINUTES OF THE REGULAR MEETING OF THE MOUNT LAUREL TOWNSHIP MUNICIPAL UTILITIES AUTHORITY MINUTES OF THE REGULAR MEETING OF THE MOUNT LAUREL TOWNSHIP MUNICIPAL UTILITIES AUTHORITY May 21, 2015 Vice Chairman Francescone called the regular meeting of the Mount Laurel Township Municipal Utilities

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Resettlement Planning Document Project Number: 40648-034 March 2016 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Sub Project : Conservation and Adaptive Reuse of Town Hall,

More information

Annex I: SIP Rules and Regulations Industrial Area. A. Work Permit

Annex I: SIP Rules and Regulations Industrial Area. A. Work Permit Annex I: SIP Rules and Regulations Industrial Area A. Work Permit Sohar Industrial Port Company SAOC Sultanate of Oman May 25, 2014 Table of Contents 1 Definitions... 2 2 General... 4 2.1 Purpose of this

More information

Minnesota Pollution Control Agency

Minnesota Pollution Control Agency Minnesota Pollution Control Agency STATE OF MINNESOTA Minnesota Pollution Control Agency MUNICIPAL DIVISION PUBLIC NOTICE OF INTENT TO REISSUE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES)/ STATE

More information

Ethnic Minorities Development Framework. PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program

Ethnic Minorities Development Framework. PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program Ethnic Minorities Development Framework Project Number: 50050-002 September 2016 PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program Prepared by the Government of the People

More information

Host and refugee population cooperation: case of Dumse water supply and sanitation project, Damak-5, Nepal

Host and refugee population cooperation: case of Dumse water supply and sanitation project, Damak-5, Nepal 40 th WEDC International Conference, Loughborough, UK, 2017 LOCAL ACTION WITH INTERNATIONAL COOPERATION TO IMPROVE AND SUSTAIN WATER, SANITATION AND HYGIENE SERVICES Host and refugee population cooperation:

More information

CHAPTER 60 HEALTH AND SANITATION GARBAGE SERVICE GARBAGE DISPOSAL AT CITY DUMP. Disposal of garbage, trash and waste matter

CHAPTER 60 HEALTH AND SANITATION GARBAGE SERVICE GARBAGE DISPOSAL AT CITY DUMP. Disposal of garbage, trash and waste matter CHAPTER 60 HEALTH AND SANITATION SECTION 60.02 SECTION 60.03 SECTION 60.04 SECTION 60.24 Garbage Service Garbage Disposal at City Dump Refuse Penalties GARBAGE SERVICE SECTION 60.02.010 SECTION 60.02.220

More information

SCHEDULE "13" Gravel License. "BCBC Improvements" means any Premises or Building Equipment existing on the Gravel Pits at any time during the Term;

SCHEDULE 13 Gravel License. BCBC Improvements means any Premises or Building Equipment existing on the Gravel Pits at any time during the Term; SCHEDULE "13" Gravel License 1. Definitions 1.1 In this Gravel License, unless the context otherwise requires: (c) "BCBC Improvements" means any Premises or Building Equipment existing on the Gravel Pits

More information

JOHNSON COUNTY CODE OF REGULATIONS FOR PRIVATE INFILTRATION AND INFLOW 2010 EDITION

JOHNSON COUNTY CODE OF REGULATIONS FOR PRIVATE INFILTRATION AND INFLOW 2010 EDITION JOHNSON COUNTY CODE OF REGULATIONS FOR PRIVATE INFILTRATION AND INFLOW 2010 EDITION Johnson County Wastewater 11811 S. Sunset Drive, Suite 2500 Olathe, KS 66061-7061 (913) 715-8500 INDEX CHAPTER 1 POLICY

More information

DOCKET NO. D CP-3 DELAWARE RIVER BASIN COMMISSION

DOCKET NO. D CP-3 DELAWARE RIVER BASIN COMMISSION DOCKET NO. D-1993-068 CP-3 DELAWARE RIVER BASIN COMMISSION Lower Bucks County Joint Municipal Authority Wastewater Treatment Plant Bristol Township, Bucks County, Pennsylvania PROCEEDINGS This docket is

More information

ABBREVIATED RESETTLEMENT ACTION PLAN RP285 V.

ABBREVIATED RESETTLEMENT ACTION PLAN RP285 V. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ABBREVIATED RESETTLEMENT ACTION PLAN RP285 V. 3 For the North Septage Treatment Plant

More information

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan October 2013 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Construction of Storm Water Drains in the Adjoining Areas of NH Bypass (Rawalpora Chowk Chanapora

More information

Non-Stormwater Discharge Ordinance

Non-Stormwater Discharge Ordinance Non-Stormwater Discharge Ordinance 1. Purpose. The purpose of this Ordinance is to provide for the health, safety, and general welfare of the citizens of the Town of York through regulation of non-stormwater

More information

UNHCR WASH MANUAL WASH PROGRAMME MANAGEMENT 319

UNHCR WASH MANUAL WASH PROGRAMME MANAGEMENT 319 WASH programmes in refugee settings often require large numbers of staff, vehicles, equipment and materials especially in the first few months of an emergency. It is essential that these resources are

More information

FILLMORE COUNTY FEEDLOT ORDINANCE

FILLMORE COUNTY FEEDLOT ORDINANCE FILLMORE COUNTY FEEDLOT ORDINANCE Amended November 25, 2003 Amended May 20, 2014 Table of Contents SECTION 1 Statutory Authority........................ 1 SECTION 2 Policy..................................

More information

DISTRICT OF LAKE COUNTRY BYLAW DEVELOPMENT APPLICATION PROCEDURES BYLAW CONSOLIDATED VERSION

DISTRICT OF LAKE COUNTRY BYLAW DEVELOPMENT APPLICATION PROCEDURES BYLAW CONSOLIDATED VERSION DISTRICT OF LAKE COUNTRY BYLAW 99-240 DEVELOPMENT APPLICATION PROCEDURES BYLAW CONSOLIDATED VERSION (Includes amendments as of July 4, 2017) This is a consolidated copy to be used for convenience only.

More information

ASSEMBLY, No STATE OF NEW JERSEY. 208th LEGISLATURE INTRODUCED MAY 17, 1999

ASSEMBLY, No STATE OF NEW JERSEY. 208th LEGISLATURE INTRODUCED MAY 17, 1999 ASSEMBLY, No. STATE OF NEW JERSEY 0th LEGISLATURE INTRODUCED MAY, Sponsored by: Assemblyman JOHN E. ROONEY District (Bergen) Assemblyman DAVID C. RUSSO District 0 (Bergen and Passaic) SYNOPSIS Requires

More information

HUU-AY-AHT FIRST NATIONS

HUU-AY-AHT FIRST NATIONS HUU-AY-AHT FIRST NATIONS COMMUNITY PLANNING AND DEVELOPMENT ACT OFFICIAL CONSOLIDATION Current to December 18, 2014 The Huu-ay-aht Legislature enacts this law to provide a fair and effective system for

More information

Chapter 22 UTILITIES* ARTICLE I. IN GENERAL ARTICLE II. SEWERS*

Chapter 22 UTILITIES* ARTICLE I. IN GENERAL ARTICLE II. SEWERS* Chapter 22 UTILITIES* Art. Art. I. In General II. Sewers Div. 1. Generally Div. 2. Use of Sanitary Sewer System Div. 3. Sewer User Charges Art. III. Water Secs. 22-1--22-20. Reserved. DIVISION 1. GENERALLY

More information

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Indigenous People Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP October 2013 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

More information

SEWERAGE ACT CHAPTER Ⅰ GENERAL PROVISIONS

SEWERAGE ACT CHAPTER Ⅰ GENERAL PROVISIONS SEWERAGE ACT Wholly Amended by Act No. 8014, Sep. 27, 2006 Amended by Act No. 8338, Apr. 6, 2007 Act No. 8352, Apr. 11, 2007 Act No. 8371, Apr. 11, 2007 Act No. 8819, Dec. 27, 2007 Act No. 8820, Dec. 29,

More information

SUBCHAPTER 22. TREATMENT WORKS APPROVALS, SEWER BANS, SEWER BAN EXEMPTIONS

SUBCHAPTER 22. TREATMENT WORKS APPROVALS, SEWER BANS, SEWER BAN EXEMPTIONS SUBCHAPTER 22. TREATMENT WORKS APPROVALS, SEWER BANS, SEWER BAN EXEMPTIONS 7:14A-22.1 General policy and purpose (a) It is the purpose of this subchapter to: 1. Establish when a treatment works approval

More information

LONDON GROVE TOWNSHIP CHESTER COUNTY, PENNSYLVANIA ORDINANCE NO. 172

LONDON GROVE TOWNSHIP CHESTER COUNTY, PENNSYLVANIA ORDINANCE NO. 172 LONDON GROVE TOWNSHIP CHESTER COUNTY, PENNSYLVANIA ORDINANCE NO. 172 AN ORDINANCE AMENDING CHAPTER 18 OF THE CODIFIED ORDINANCES OF LONDON GROVE TOWNSHIP TO INSERT A NEW PART 3 GOVERNING MUNICIPAL MANAGEMENT

More information