Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

Size: px
Start display at page:

Download "Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)"

Transcription

1 Resettlement Plan March 2012 IND: Bihar State Highways II Project Siwan-Siswan Subproject (SH-89) Prepared by Bihar State Road Development Corporation, Government of Bihar for the Asian Development Bank.

2 CURRENCY EQUIVALENTS (as of 9 March 2012) Currency unit Indian rupee (Rs) Rs1.00 = $ $1.00 = Rs ABBREVIATIONS ADB Asian Development Bank ARO Assistant Resettlement Officer BHSP BHSP-II Bihar State Highways Project Bihar State Highways II Project BPL Below Poverty Line BSR Basic Schedule of Rates BSRDC Bihar State Road Development Corporation CPR Common Property Resources CSC Construction Supervision Consultant DC District Collector DGM Deputy General Manager DH Displaced Households DP Displaced Persons DPR Detailed Project Report EA Executing Agency EE Executive Engineer FGD Focus Group Discussion GoI Government of India GRC Grievance Redress Mechanism IA Implementing Agency IP Indigenous Peoples IR Involuntary Resettlement LAA Land Acquisition Act LAP Land Acquisition Plan MD Managing Director NGO Nongovernment Organization NRRP National Rehabilitation and Resettlement Policy, 2007 OBC Other Backward Castes PIU Project Implementation Unit PMU Project Monitoring Unit RC Resettlement Cell R&R Resettlement and Rehabilitation RO Resettlement Officer ROW Right-of-way RP Resettlement Plan SC Scheduled Caste SPS ADB Safeguard Policy Statement ST Scheduled Tribe TOR Terms of Reference

3 iii NOTE In this report, "$" refers to US dollars. This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

4 iv TABLE OF CONTENTS EXECUTIVE SUMMARY vii CHAPTER 1: PROJECT DESCRIPTION General The Project Road and its Location Profile of the Project Area Sub-project Impacts and Benefits Project Components Minimizing Resettlement Scope and Objective of Resettlement Plan Methodology 6 CHAPTER 2:SCOPE OF LAND ACQUISITION AND RESETTLEMENT Scope of land Acquisition Loss of Land Loss of Structure in the Subproject Impact on Private Trees Loss of Livelihoods Loss of Community Property Resources Summary Sub-project Impacts 14 CHAPTER 3: SOCIOECONOMIC INFORMATION AND PROFILE Socio-economic Profile of Project Area Social Categories of the DPs Religious Categories of the DPs Number of DPs Number of DPs of Special Categories Vulnerable Households being Affected in the Sub-project Annual Income Level of the Affected Households Educational Status of DPs Occupational Status of DPs Impact on Indigenous People Gender Impact 19 CHAPTER 4: INFORMATION DISCLOSURE, CONSULTATION, & PARTICIPATION Stakeholders in the Project Public Consultation in the Project Methods of Public Consultation Scope of Consultation and Issues Finding of Focused Group Discussions Consultations with Officials and other Stakeholders Plan for further Consultation in the Project Information Disclosure 23

5 v CHAPTER 5: GRIEVANCE REDRESS MECHANISMS General Grievance Redress Mechanism Constitution and Function of the GRC Operational Mechanisms of GRC 24 CHAPTER 6: LEGAL FRAMEWORK Introduction Land Acquisition Act National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007) Bihar Land Acquisition Resettlement and Rehabilitation Policy Asian Development Bank s (ADB) Policy of Involuntary Resettlement Comparison of National and State Policies with ADB s IR Policy Policy Framework for this Project Methodology for Determination of Valuation of Assets Procedure and Steps of Land Acquisition 36 CHAPTER 7: ENTITLEMENTS, ASSISTANCE AND BENEFITS Definition of DPs and Eligibility Entitlements Entitlement Matrix 40 CHAPTER 8: RELOCATION OF HOUSING AND SETTLEMENTS Basic Provision for Relocation Need for Relocation Magnitude of Physical Displacement in the Sub-project Relocation and Compensation Option by DPs Relocation Strategy 44 CHAPTER 9: INCOME RESTORATION AND REHABILITATION Loss of Livelihoods in the Sub-project Provisions for Loss of Livelihood Income Restoration Measures Additional Support from Ongoing Poverty Reduction Programs 47 CHAPTER 10: RESETTLEMENT BUDGET AND FINANCING PLAN General Compensation Assistance Compensation for Community and Government Property RP Implementation and Support Cost Source of Funding and Fund Flow Management R&R Budget 50

6 vi CHAPTER 11: INSTITUTIONAL ARRANGEMENTS Institutional Requirement Executing Agency Project Management Unit (PMU) Project Implementation Unit (PIU) Non-Government Organization (NGO) Capacity Building on RP in the EA 54 CHAPTER 12: IMPLEMENTATION SCHEDULE Introduction Schedule for Project Implementation R&R Implementation Schedule 56 CHAPTER 13: MONITORING AND REPORTING Need for Monitoring and Reporting Monitoring in the Project Stages of Monitoring Monitoring Indicators Reporting Requirements 60 Appendix-1 Census Survey Questionnaire 61 Appendix-2 ToR for NGO 65 Appendix-3 Findings of the Consultations 75

7 vii EXECUTIVE SUMMARY A. Project Description 1. The Bihar State Road Development Corporation (BSRDC), Government of Bihar is presently implementing Bihar State Highways (BSHP) and BSHP-II Project under Asian Development Bank (ADB) assistance to strengthen and rehabilitate the deteriorated state roads and upgrade some newly declared state roads to provide reliable road transport services in the state. Under BSHP-II (Additional Financing) five subprojects road sections (SH-83, SH-86, SH- 87, SH-88 and SH-89) totaling 291 kilometers are selected for which detailed project reports (DPR) for these road sections are being prepared by BSRDC. This Resettlement Plan1 is prepared for the SH-89 subproject which is considered as Category A as far as Involuntary Resettlement (IR) is concerned. 2. The subproject road section (SH-89) is km road from Siwan Siswan passes through the Siwan district of Bihar. The alignment of the road is proposed as Siwan Laxmipur - Surapur Chapiya Chatta Hassanpura Gopalpur Chainpur - Siswan. The average ROW available in the road section ranges from 18 to 30m. 3. The proposed subproject can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits arising due to the subproject will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace etc which in turn increases the income of the locals, and ultimately elevating their standard of living. Although various positive subproject impacts and benefits are expected from the proposed subproject as mentioned above, there will be some negative impacts on the people living in the immediate project area. 4. The existing ROW is sufficient in substantial portion of the project length which is varies from 18 to 30 meters. This RoW (varies with varying extent of toe line) has been decided based on the embankment toe line due to requirement of comparatively more construction width due to high embankments for significant length. Key activities for sub-project road improvement involves (i) widening/strengthening of the road up to 2-lane configuration (ii) improving road geometry (iii) laying of embankment (iv) rehabilitation and construction of new bridges and other cross drainage structures (v) construction of side drains (vi) Junctions/intersections improvement (vii) provision of service roads, underpasses and way side amenities etc. The brief of all key project activities are described below. Adequate attention has been given during the feasibility and detailed project design phases of the project preparation to minimize the adverse impacts on land acquisition and resettlement impacts. However, technical and engineering constraints were one of the major concerns during exploration of various alternative alignments. With the available options, best engineering solution have been adopted to avoid large scale land acquisition and resettlement impacts. 5. The aim of this Resettlement Plan (RP) is to mitigate all such unavoidable negative impacts caused due to the project and resettle the displaced persons and restore their 1 As per ADB s SPS-2009 and OM Section F-1/OP issued on 4 March 2010, The involuntary resettlement impacts of an ADB-supported project are considered significant if 200 or more persons will experience major impacts, which are defined as (i) being physically displaced from housing, or (ii) losing 10% or more of their productive assets (income generating).

8 viii livelihoods. This Resettlement Plan has been prepared on the basis of subproject census survey findings and consultation with various stakeholders. The plan complies with ADB Safeguard Policy Statement-2009 formulated by ADB to protect the rights of the Displaced persons and communities. B. Socio-economic Information and Profile 6. The project area consists of Siwan District. Siwan district is one of the thirty-seven districts of Bihar state, India. Siwan has an area of 2219 Sq. Km with population is 3,318,176 as per 2011 census. The district is densely populated with 1495 person per Sq. km. which is substantially higher than the state average density of 1102 persons per sq km according to 2011 census year. Sex ratio, expressed as number of females per thousand males, of Siwan district (984) is comparable to the state average of 916 as per 2011 census. Bihar does not have any significant number of tribal population, 0.9% of total population, after division of the state into two, the other half being Jharkhand, the home of many scheduled tribes. C Scope of Land Acquisition and Resettlement 7. According to the Land Acquisition Plan (LAP) prepared as a part of Detailed Design Report, acres of land will be acquired for the subproject. The area is excluding the area that already lies with Road Construction Department in terms of existing roads falling in the alignment. A project census survey was carried out to identify the persons who would be affected by the project and to make an inventory of their assets that would be lost to the project, which would be the basis of calculation of compensation. 8. As per findings of the 100% census of affected land and non-land assets, the subproject impacts can be broadly classified as (i) impacts on private land, (ii) impacts on private structures, (iii) impacts on livelihoods due to loss of private properties and (iv) loss of common property resources. From the analysis of impacts it is noted that altogether 131 land units/plots will be affected. As per the survey, in 440 households comprising 245 titleholders and 195 nontitleholders will be affected in the subproject. The details of subproject impacts are discussed in the following section and the summary subproject impacts are presented in the Table E.1. Table E.1: Summary Subproject Impacts Sl. No. Impacts Number 1 Total land acquisition requirements (in Acre) Total private land acquisition requirements (in acre) Total number of land units/plots affected Total number of private land units/plots affected Total number of private structures affected (22 TH + 14 NTH) 36 6 Total number of households affected (245 TH NTH including 14 squatters, 105 agricultural laborers, 44 share 440 croppers, 17 tenants and 15 employees) 7 Total Number of physically displaced households 29 8 Total Number of Vulnerable households affected 53 9 Total number of displaced persons including physical and economic)- (TH and NTH DPs) Total number of CPR affected (Religious Structure) 4 12 Total number of Trees affected 441 Source: Census Survey, BSHP-II Project Additional Financing, 2012

9 ix D. Stakeholders Consultation and Participation 9. Consultations with various stakeholders were carried out during various phases of project preparation. Project related information were disseminated to the APs and based on the findings of consultation with DPs alignment was reviewed and suitably modified to minimize the resettlement impacts. During preparation of RP further consultations with DPs were carried out disseminating information of change of alignment, project entitlement and mitigation measures etc. To keep more transparency in planning and for further active involvement of APs and other stakeholders the project information will be disseminated through disclosure of resettlement planning documents. The EA will submit the following documents to ADB for disclosure on ADB s website: i. the final resettlement plan endorsed by the EA after the census of displaced persons has been completed; ii. a new resettlement plan or an updated resettlement plan, and a corrective action plan prepared during project implementation, if any; and iii. the resettlement monitoring reports. 10. The EA will provide relevant resettlement information, including information from the above mentioned documents in a timely manner, in an accessible place (district magistrate office, office of the PIU and office of the LAO) and in a form and language (Hindi) understandable to affected persons and other stakeholders. A resettlement information leaflet containing information on compensation, entitlement and resettlement management adopted for the sub-project will be made available in local language (Hindi) and distributed to DPs. E. Legal Framework 11. The legal framework and principles adopted for addressing resettlement issues in the Project have been guided by the existing legislation and policies of the GOI, the Government of Bihar and Asian Development Bank and the Entitlement Matrix adopted for the BSHP-II project. Prior to the preparation of the Resettlement Plan, a detailed analysis of the existing national and state policies was undertaken. This RP is prepared based on the review and analysis of all applicable legal and policy frameworks of the country and ADB policy requirements. Based on the analysis of applicable legal and policy frameworks of the country and in consistent with ADB s policy requirements the broad resettlement principle for this project is finalized. F. Entitlements, Assistance and Benefits 12. The project will have three types of displaced persons i.e., (i) persons with formal legal rights to land lost in its entirety or in part; (ii) persons who lost the land they occupy in its entirety or in part who have no formal legal rights to such land, but who have claims to such lands that are recognized or recognizable under national laws; and (iii) persons who lost the land they occupy in its entirety or in part who have neither formal legal rights nor recognized or recognizable claims to such land. The involuntary resettlement requirements apply to all three types of displaced persons 13. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the census survey which is 23rd February DPs who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however, will be given sufficient advance notice, requested to vacate premises and dismantle affected structures prior to project implementation. Their dismantled structures materials will not be confiscated and they

10 x will not pay any fine or suffer any sanction. Compensation for the lost assets to all households will be paid on the basis of replacement cost. Resettlement assistance for lost income and livelihoods will be provided to both title holders and non-title holders. Special resettlement and rehabilitation measures will be made available to the Vulnerable Group as per the Entitlement Matrix formulated for the project. G. Relocation of Housing and Settlements 14. The EA will provide adequate and appropriate replacement land and structures or cash compensation at full replacement cost for lost land and structures, adequate compensation for partially damaged structures, and relocation assistance, according to the Entitlement Matrix. The EA will compensate to the non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land, at full replacement cost. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date. Preference will be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based. These strategies may include resettlement on public land, or on private land acquired or purchased for resettlement. In the case of physically displaced persons, the EA will provide (i) relocation assistance, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, and civic infrastructure and community services as required; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) opportunities to derive appropriate development benefits from the project. H. Income Restoration and Rehabilitation 15. The households losing their livelihoods includes titleholders land, agricultural laborers, agricultural tenants, and sharecroppers, or having commercial structures and employees of the affected structures. In the case of economically displaced persons, regardless of whether or not they are physically displaced, the EA will promptly compensate for the loss of income or livelihood sources at full replacement cost. The EA will also provide assistance such as credit facilities, training, and employment opportunities so that they can improve, or at least restore, their income-earning capacity, production levels, and standards of living to pre-displacement levels. Needs assessments will be conducted to determine the types of training or assistance. The budgetary resources allocated, as per the Entitlement Matrix, will be used to carry out the training. I. Resettlement Budget and Financing Plan 16. The resettlement cost estimate for this subproject includes eligible compensation, resettlement assistance and support cost for RP implementation. The support cost, which includes staffing requirement, monitoring and reporting, involvement of NGO in project implementation, public consultation and other administrative expenses are part of the overall project cost. The unit cost for land and other assets in this budget has been derived through field survey, consultation with affected families, relevant local authorities and reference from old practices. Contingency provisions have also been made to take into account variations from this estimate. The total R&R budget for the proposed subproject RP works out to Rs million.

11 xi J. Grievance Redress Mechanisms 17. In the subproject RP implementation there is a need for an efficient grievance redressal mechanism that will assist the affected persons in resolving their queries and complaints. Therefore, formation of Grievance Redressal Committee (GRC) will be most important for grievance redressal and it is anticipated that most, if not all grievances, would be settled by the GRC. The GRC will be established at the district level with the primary objective of providing a mechanism to mediate conflict and cut down on lengthy litigation. It will also provide people, who might have objections or concerns about their assistance, a public forum to raise their objections and through conflict resolution, address these issues adequately. The GRCs will continue to function, for the benefit of the DPs, during the entire life of the subproject including the defects liability periods. K. Institutional Arrangements 18. The Executing Agency (EA) for the Project is BSRDC, Government of Bihar. The existing BSRDC has already set up a Project Management Unit (PMU) headed by a Managing Director (MD) with General Managers and Deputy General Managers (DGM) assisted by Managers. This office will be functional for the whole Project duration. The EA, headed by MD will have overall responsibility for implementation of loan and will also be responsible for the overall coordination among ADB, Government of Bihar and PIU. For resettlement activities, PMU will do the overall coordination, planning, implementation, and financing. Project Implementation Unit (PIU) will be established at subproject level for the implementation of subprojects. Keeping in view the sensitivity R&R matters an experienced and well-qualified NGO in this field will be engaged to assist the PIUs in the implementation of the RP. L. Implementation Schedule 19. Implementation of RP mainly consists of compensation to be paid for affected structures and rehabilitation and resettlement activities. The time for implementation of resettlement plan will be scheduled as per the overall project implementation. All activities related to the land acquisition and resettlement must be planned to ensure that compensation is paid prior to displacement and commencement of civil works. Public consultation, internal monitoring and grievance redress will be undertaken intermittently throughout the project duration. However, the schedule is subject to modification depending on the progress of the project activities. The civil works contract for each subproject will only be awarded after all compensation and relocation has been completed for subproject and rehabilitation measures are in place. M. Monitoring and Reporting 20. Monitoring and reporting are critical activities in involuntary resettlement management in order to ameliorate problems faced by the APs and develop solutions immediately. RP implementation for the subproject will be closely monitored by the EA through it s PIU and implementing NGO. Additionally, the EA will engage expert for monitoring of the subproject RP implementation and will submit biannual reports to determine whether resettlement goals have been achieved, more importantly whether livelihoods and living standards have been restored/ enhanced and suggest suitable recommendations for improvement. All the resettlement monitoring reports will be disclosed to APs as per procedure followed for disclosure of resettlement plans by the EA.

12 CHAPTER 1: PROJECT DESCRIPTION 1.1 General 1. The Bihar State Road Development Corporation (BSRDC), Government of Bihar is presently implementing Bihar State Highways (BSHP) and BSHP-II Project under Asian Development Bank (ADB) assistance to strengthen and rehabilitate the deteriorated state roads and upgrade some newly declared state roads to provide reliable road transport services in the state. Under BSHP-II - Additional Financing, five subprojects road sections (SH-83, SH-86, SH- 87, SH-88 and SH-89) totaling 291 kilometers are selected for which detailed project reports (DPR) for these road sections are being prepared by BSRDC. 2. This Resettlement Plan 2 is prepared for the SH-89 subproject which is considered as Category A as far as Involuntary Resettlement (IR) is concerned. 1.2 The Project Road and its Location 3. The subproject road section (SH-89) is located in the in Siwan district of western Bihar. The Location map of Bihar state Highway Projects-II and sub-project is given in Figure: 1. Figure: 1 Subproject Location Map SH 89 2 As per ADB s SPS-2009 and OM Section F-1/OP issued on January 2010, The involuntary resettlement impacts of an ADB-supported project are considered significant if 200 or more persons will experience major impacts, which are defined as (i) being physically displaced from housing, or (ii) losing 10% or more of their productive assets (income generating).

13 2 4. The subproject road section (SH-89) is km road from Siwan to Siswan passes through the Siwan district of Bihar. The alignment of the road is proposed as Siwan Laxmipur - Surapur Chapiya Chatta Hassanpura Gopalpur Chainpur - Siswan. The ROW available in the road section ranges from 4.5 to 6m. 5. Soft shoulders are generally in fair to good condition. However, at a few locations especially on high embankment sections the width is reduced to only 1 m. Edge drop and undulation are also observed at a few locations. Rain cuts are also observed at major locations mainly on high embankment stretches like approaches to the structures due to lack of protection works and chute drains. 6. The horizontal alignment of the existing road has several sub-standard and sharp curves including right angle turn especially in initial stretch. Also, there is no proper transition length for several horizontal curves to provide for required super elevation reversal for riding safety and comfort. These deficiencies have been corrected in fixing the horizontal alignment for the entire subproject road to conform to MOSRTH standards. The vertical alignment of the road is at a flat grade with the height of embankment generally varying from 0.50 to m, except for the approaches to major bridges. 1.3 Profile of the Project Area 7. The project area consists of Siwan district. Siwan district is one of the thirty-seven districts of Bihar state, India. Siwan has an area of 2219 Sq. Km with population is 3,318,176 as per 2011 census. The district is densely populated with 1495 person per Sq. km. which is substantially higher than the state average density of 1102 persons per sq km according to 2011 census year. Sex ratio, expressed as number of females per thousand males, of Siwan district (984) is comparable to the state average of 916 as per 2011 census. Bihar does not have any significant number of tribal population, 0.9% of total population, after division of the state into two, the other half being Jharkhand, the home of many scheduled tribes. 1.4 Subproject Impacts and Benefits 8. The proposed subproject can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits arising due to the subproject will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace etc which in turn increases the income of the locals, and ultimately elevating their standard of living. The possible direct and indirect positive impacts of the subproject are listed below. The immediate benefits of road construction and improvement will come in the form of direct employment opportunities for the roadside communities and specially those who are engaged as wage laborers, petty contractors and suppliers of raw materials. Improved road network will provide for improved linkages between the village communities and urban center, which provides wider marketing facilities. Road network will not only link the village communities to better markets, but also open up wider work opportunities in distant places. People can shuttle to distant work sites and towns and engage in construction, factories, business as well as domestic works. Improved road network will encourage urban entrepreneurs to invest in far and remote areas in commercial farming and industrial activities.

14 3 Improved road will also help people building strong institutional network with outside agencies. Essential and emergency services like schools, health center, public distribution system etc can be availed faster. Increased frequency of interaction with outsiders will increase the awareness level of the people in the village with regard to their health and nutrition, living style, value of education and proper utilization of available resources. Interaction with the government, non-government and other development agents will help people gain new knowledge on improved farming, land development, development and maintenance of natural resources through the formation of various economic and social development groups. 9. Although various positive subproject impacts and benefits are expected from the proposed subproject as mentioned above, there will be some negative impacts on the people living in the immediate project area. The summary details of project profile including affected villages, households, and land acquisition are presented in the Table: 1.1 below; Name of District SIWAN Name of Villages Mapur Siwan Surapur Chhapiya khurd Chhapiya buzurg Chhata Hathauri Bindwal Bararam Harihans Gopalpur Shauli Aranda Tanrila Hasanpura Jalallpur Samri Rajanpuria Kathtal Madhwapur Nawada Nayagaon Mariwan Rampur Bhangwanpur Gharghat Tilauta Chandanpura Gangapur Table: 1.1 Summary of Affected Area Affected Households Displaced Persons 3 Affected Land (in Acres) No. of Affected Trees No. of Affected CPR In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

15 4 1.5 Project Components 10. As the existing ROW is sufficient in substantial portion of the project length which is varies from 18 to 30 meters. This RoW (varies with varying extent of toe line) has been decided based on the embankment toe line due to requirement of comparatively more construction width due to high embankments for significant length. Key activities for sub-project road improvement involves (i) widening/strengthening of the road up to 2-lane undivided carriageway configuration (ii) improving road geometry (iii) laying of embankment (iv) construction of new bridges and other cross drainage structures (v) construction of side drains (vi) Junctions/intersections improvement (vii) provision of service roads and way side amenities etc. The brief of all key project activities are described below. 11. Road Configuration: It is proposed to construct/widen the road to 2 lane standard undivided carriageways of 7.0 m width with earthen shoulders width of 1.5 m either side are proposed. Structures 2 Lane standard configuration with independent 7.0 m carriageways (total width 10.5m) is proposed. However, in the first phase to be taken up now civil road works for two lane facility and two-lane structures are proposed for construction with two lanes. 12. Realignment/Bypasses: Two bypasses are proposed for the subproject from KM 0.00 to KM Siwan and from Km to Km at Chhata. Only some realignments are proposed in some locations totalling a length of about 1.1 kilometres only due to (i) poor road geometry and pavement & embankment conditions (ii) inadequate ROW (iii) identification of bridges at suitable locations (iv) drainage & road side water body problems (v) cutting of large no. of trees (vi) interference with religious structures at a couple of locations and many other bottlenecks. 13. Bridges and other Cross Drainage Structures: One major bridge (on river Daha) and 6 minor bridges are proposed on this project corridor. There are 48 numbers of culverts along the project corridor in which the existing alignment has been followed. All pipe culverts, arch culverts and slab culvert are replaced by a new box culvert of different size. There is proposal for construction of 95 number of box culverts. There will be approximately 3 balancing culverts per Km of the road to allow the free passage of the water through the embankment. 14. Road side Drainage: There is no proper drainage along the existing alignment. The provision of catch water drain in cut sections, meter drain or out fall drain will be constructed to avoid outside water coming in and disposal of storm water at frequent intervals to prevent soil erosion. 15. Junctions/intersections Improvement: There are 5 major intersections (with NHs, SH & MDRs) in this project corridor. All major intersections will be improved for free and uninterrupted flow of traffic. As per the traffic analysis during feasibility study grade separation is not required at any of the intersection. 1.6 Minimizing Resettlement Impact 16. Adequate attention has been given during the feasibility and detailed project design phases of the project preparation to minimize the adverse impacts on land acquisition and resettlement impacts. However, technical and engineering constraints were one of the major concerns during exploration of various alternative alignments. With the available options, best engineering solution have been adopted to avoid large scale land acquisition and resettlement impacts. Following are the general criteria adopted for the selection of the alignment: It should serve as uninterrupted flow of traffic;

16 5 It should provide linkage to other link roads in the region; It should take in to account the future traffic growth and management; It should be coordinated with local and national development plans, It should minimize environment impact along the corridor; It should take in to consideration the opinions of local people in selection of alignment. 17. The specific measures adopted for minimizing the resettlement impacts for the sub project are as follows: Exploration of several alternate alignments in consultation with engineering team, concerned government departments and local community; Avoiding highly productive agricultural land to minimize the adverse economic displacement; Diverting the alignment towards the available unused government land to minimize impact on private property. 18. The preliminary project design of the project was conceptualized with 30 meter uniform ROW for the project. During detailed design stage, the following steps were taken to minimize land acquisition and resettlement impacts. The proposed ROW was fixed with the designed toe line + 2 meters additional width on each side only. Avoiding proposed realignments for minor curve improvements and widening the existing road by suggesting proper safety measures such as reducing the design speed, providing crash barrier, providing retaining wall, providing proper signage etc. Avoiding proposed junctions at small intersections by providing underpasses with service roads as per requirement. 19. Due to the above minimization efforts, the land acquisition requirement was reduced from acres to Acres and minimized the R&R impacts from Displaced Households (DH) to 2073 DPs. 1.7 Scope and Objective of Resettlement Plan (RP) 20. The aim of this Resettlement Plan (RP) is to mitigate all such unavoidable negative impacts caused due to the project and resettle the displaced persons and restore their livelihoods. This Resettlement Plan has been prepared on the basis of subproject census survey findings and consultation with various stakeholders. The plan complies with ADB Safeguard Policy Statement-2009 designed by ADB to protect the rights of the displaced persons and communities. The issues identified and addressed in this document are as follows: Type and extent of loss of land/ non-land assets, loss of livelihood, loss of common property resources and social infrastructure; Impacts on indigenous people, vulnerable groups like poor, women and other disadvantaged sections of society Public consultation and peoples participation in the project; Existing legal and administrative framework and formulation of resettlement policy for the project; Preparation of entitlement matrix, formulation of relocation strategy and restoration of businesses/income;

17 6 R&R cost estimate including provision for fund and; Institutional framework for the implementation of the plan, including grievance redress mechanism and monitoring reporting. 1.8 Methodology 21. The RP has been prepared by adopting flowing steps and methodologies Resettlement Screening 22. A social screening exercise was performed through a reconnaissance survey to gather first hand information on impact on land acquisition and resettlement with specific attention on land use, presence of legal and/or illegal housing, traffic patterns, cultural resources, urban settlements and other sensitive areas. The aim of reconnaissance survey was to assess the scope of land acquisition and resettlement study and accordingly the detailed plan of action was prepared for the preparation of land acquisition planning and resettlement plan Land Acquisition Planning 23. The alignment was finalized as per the detailed engineering design. Initially, the numbers of affected villages were identified as per the alignment. All the village maps were collected from the local revenue offices. The village maps were digitized by the detailed design consultant. Following the digitization of village maps, the engineering design of the alignment was superimposed in the digitized cadastral map in order to identify the number of land parcels and their demarcation including the quantification. The superimposition of alignment on the village map provided all the plot numbers. A Land Acquisition Plan (LAP) has been prepared accordingly. Based on the identified land plots, a team of local enumerators were hired and local revenue officials were consulted to collect the names of owners of each plot Census Survey and Inventory of Assets 24. Following finalization of the road alignment and identification of the land parcels, crosssections design and land acquisition requirements, census of all displaced persons (DPs) was carried in the subproject. The objective of the project census survey was to identify the persons who would be displaced by the project and to make an inventory of their assets that would be lost to the project, which would be the basis of calculation of compensation. A structured census questionnaire (refer Appendix: 1) was used to collect detailed information on affected households/ properties for a full understanding of impacts in order to develop mitigation measures and resettlement plan for the DPs. The survey team was trained by the resettlement specialist and the survey was closely monitored on a regular basis. Additionally, socioeconomic data was also collected as part of the Social Impact Assessment (SIA) study. The census survey includes the following: Inventory of the 100% land and non land assets Categorization and measurements of potential loss Physical measurements of the affected assets/structures Identification of trees and crops Household characteristics, including social, economic and demographic profile

18 7 Identification of non titleholders Assessment of potential economic impact Public Consultation 25. To ensure peoples participation in the planning phase and aiming at promotion of public understanding and fruitful solutions of developmental problems such as local needs of road users and problem and prospects of resettlement, various sections of Displaced persons (DPs) and other stakeholders were consulted through focus group discussions, individual interviews and formal and informal consultations. The vulnerable sections of DPs and women were also included in this consultation process.

19 8 CHAPTER 2: SCOPE OF LAND ACQUISITION AND RESETTLEMENT 2.1 Scope of Land Acquisition 26. Since the existing ROW is adequate in the sub-project and land acquisition is not required for widening of the existing road. Except the takeoff point there is no other realignment/ bypass is envisaged during the detail engineering. A project census survey was carried out to identify the persons who would be displaced by the project and to make an inventory of their assets that would be lost due to the project, which would be the basis of calculation of compensation. Initially the Census survey for Siwan to Siswan was carried out during 2011 and the updated census survey was carried out from 18th February 2012 to 23rd February The major findings in terms of magnitude of impacts are discussed in the following sections. 2.2 Loss of land 27. According to the Land Acquisition Plan (LAP) prepared as a part of Detailed Design Report, acres of land will be acquired for the subproject. The area is excluding the existing ROW. Some DPs will be losing their land to the project and their livelihoods. Dwellings will also be affected. The detail impact of subproject on land and associated losses are discussed in this section Ownership of Land Being Acquired for the Subproject 28. Out of acres, acres (95.96%) land is privately owned and 1.05 acres (4.04%) is owned by various Government departments such as District Board, Irrigation department, Agriculture department and Central Government etc. The details of land acquisition requirement are summarized in the Table 2.1. Table 2.1: Details of Land being acquired for the Subproject Sl. No. Type of Land No. of Plots Area of land (in acres) %Age 1 Private Land Government Land Total Land Acquisition Plan, Detailed Design Report, Type of the Land Being Acquired for the Subproject 29. The land being acquired for the sub-project is of various types such as irrigated land acres (72.50%), non-irrigated land 6.05 acres (23.27%), other type including various government land acres (2.23%). Various types of land area with number of plots are presented in the Table 2.2. Table 2.2: Type of the Land being acquired for the Subproject Sl. No. Type of Land No. of Plots Area (in Acre) %Age 1 Irrigated Non-Irrigated Other Total Source: Census Survey, BSHP II Project Additional Financing, 2012

20 Use of Land Being Acquired for the Subproject 30. The current land use pattern of land to be acquired for the sub-project shows that acres (72.50%) of land are being used for cultivation. Among other land use, residential land is 3.81 acres (14.65%), commercial use is 1.42 acres (5.46%) and residential cum commercial use is 0.82 acres (3.15%). Others accounts to 4.23% of total land to be acquired which is basically government land being used for different purpose. There are 259 households being affected including 245 titleholders in 125 plots and 14 non-titleholders in 6 government plots. Details of land use pattern including number of plots are given in the Table 2.3. Table 2.3: Use of Land Being Acquired for the Subproject Sl. Land Usage No. of No of No. of Area (in %Age No. Plots Structures Households Acre) 1 Cultivation Residential Commercial Residential & Commercial Other (Government) Total Source: Census Survey, BSHP II Project Additional Financing, Ownership Pattern of Private Land 31. All the private land being acquired for the sub-project is owned by titleholders only. Out of 125 private plots, 105 (84.00%) plots are owned by single household whereas 14 (11.20%) plots are owned by two or more households. It was not possible to ascertain the ownership pattern of 8 (32.00%) plots. The ownership pattern of private land is summarized in the Table 2.4 Table 2.4: Ownership Pattern of Private Land Sl. No. Ownership Pattern No. of land Unit/ Plot %Age 1 Single Joint Other/not specified Total Source: Census Survey, BSHP II Project Additional Financing, Scale of Impact on Affected Private Land Units/ Plots 32. The analysis of data on scale of impacts on private land reveals that 35 (14.29%) households are losing less than 10% of their land. Among others, 96 (39.18%) households are losing between 10% to 25% followed by 78 (31.84%) households losing between 25% to 50%, 21 (8.57%) households losing between 50% and 75% and 15 (6.12%) households losing between 75% to 100% of their plot areas. The details of scale of impacts on private plots are presented in the Table 2.5.

21 10 Table 2.5: Scale of Impact on Affected Private Land Units/ Plots Sl. No. Scale of Impact No. of land Number of Unit/ Plot Households %Age 1 Up to 10% Above 10% and Below 25% Above 25% and Below 50% Above 50% and Below 75% Above 75% and up to 100% Total Source: Census Survey, BSHP II Project Additional Financing, Indirect Impacts due to Loss of Private Land 33. In terms of indirect impacts on DPs due to loss of private land, 44 sharecroppers and 105 agricultural laborers will be affected. The details are summarized in Table 2.6 Table 2.6: Indirect Impact on DPs by Loss of Private Land Sl. No. Category of Impact No. of Household %Age 1 Sharecroppers Agricultural Laborer Total Source: Census Survey, BSHP II Project Additional Financing, Loss of Structure in the Affected Private Land 34. Out of 125 private land units/ plots affected in the subproject, 102 plots are only land and 23 plots are land with structure. Within these 125 plots, there are 40 structures of various types such as private (36), religious (4) structure. The details of these structures are presented in the Table: 2.7. Table 2.7: Loss of Structure Sl. No. Type of Properties No. of affected structure Percentage 1 Private Religious Total Source: Census Survey, BSHP II Project Additional Financing, Type of Structures Affected in the Subproject 35. The number of structures that will be affected due to proposed acquisition of land is enumerated as 40. Among these 22 are titleholders while number of squatters is found 18. The usage of the structures that belongs to title-holders is further classified as residential (77.27%), commercial (13.64%) and both commercial cum residential (9.09%). The details of structures are presented in the Table: 2.8.

22 11 Table 2.8: Type of Structures Affected in the Subproject Sl. No Type of Structure Title Holder Squatter Total 1 Residential Structure Commercial Structure Residential cum Commercial Structure Religious Structure Total Source: Census Survey, BSHP II Project Additional Financing, Scale of Impact on Structure 36. The scale of impact is assessed on the basis of detailed measurement of the portion of the structures falling within the proposed ROW through census survey. Based on this survey data, the range of impact is grouped into five sub-categories, from a minimal range of up to 10% to a maximum of 100%. It is found that within the 40 affected structures there are 64 households will be affected. Out of 64 households, 11 (17.19%) households will be losing only 10% of their structures. There are 21 households, who will be losing between 10% and 25% of their structures. 25 (39.06%) households are losing between 25% and 50% and the rest of the 7 households are losing above 50 and below 75%. The details of scale of impacts on structures are presented in the Table 2.9. Table 2.9: Scale of Impact on Structure Sl. No. Scale of Impact No. of Structure Number of Households %Age 1 Up to 10% Above 10% and Below 25% Above 25% and Below 50% Above 50% and Below 75% Above 75% Total Source: Census Survey, BSHP II Project Additional Financing, Type of Construction of Affected Structure 37. The structures being affected in the subproject are of various types by construction such as temporary, semi-permanent and permanent nature. Out of 40 structures, 21 (52.50%) structures are of permanent nature, 17 (42.50%) structures are of semi-permanent nature and 2 (5.0%) structures are of temporary nature. The details of type of constructions of the affected structures are summarized in the Table 2.10.

23 12 Table 2.10: Type of Construction of Affected Structure Sl. No. Construction Type No. of Structure %Age 1 Temporary Semi-Permanent Permanent Total Source: Census Survey, BSHP II Project Additional Financing, Indirect Impacts on DPs by Loss of Private Structure 38. In terms of indirect impacts on DPs due to loss of private structures, 17 tenants and 15 employees will be affected as a result of impact on their residential structures. The details are summarized in Table 2.11 Table 2.11: Indirect Impact on DPs by Loss of Private Structure Sl. No. Category of Impact No. of Household %Age 1 Commercial Tenant Residential cum Commercial Tenant Employee in Commercial Structure Employee in Residential cum Commercial Structure Total Source: Census Survey, BSHP II Project Additional Financing, Magnitude of Displacement in the Project 39. The finding of census survey was further analyzed to know the magnitude of displacement terms of both physical and economical displacement. According to the magnitude of impact, both physical and economic displacement is divided into three sub-categories. In case of physical displacement, households losing less than 10% of their residential structures are categorized as marginal displacement, households losing more than 10% and up to 25% of their residential structures are categorized as partial displacement and those households losing more than 25% of their residential structures are categorized as fully displaced. In case of economic displacement, households losing less than 10% of their productive assets are categorized as marginal displacement, households losing more than 10% and up to 75% of their productive assets are categorized as partial displacement and those households losing more than 75% of their productive assets are categorized as fully displaced. The breakup of 259 displaced households in terms of their magnitude is presented in the Table: Table 2.12: Magnitude of Displacement in the Project Sl. No. Magnitude of Displacement Physical Economical Displacement Displacement Total 1 Marginally Displaced Household Partially Displaced Household Fully Displaced Household Total Source: Census Survey, BSHP II Project Additional Financing, 2012

IND: Bihar State Highways II Project Additional Financing

IND: Bihar State Highways II Project Additional Financing Resettlement Plan November 2011 IND: Bihar State Highways II Project Additional Financing Roonisaidpur Bhiswa Subproject (SH-87) Prepared by Bihar State Road Development Corporation, Government of Bihar

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan November 2012 IND: Chhattisgarh State Road Sector Project Dhamdha Khairagarh Road Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan August 2012 IND: Chhattisgarh State Road Sector Project Nandghat Gidhoury Road Section Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

IND: Railway Sector Investment Program

IND: Railway Sector Investment Program Resettlement Framework Document Stage: Final March 2011 IND: Railway Sector Investment Program Prepared by Ministry of Railways for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 16 March 2011)

More information

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT Resettlement and Rehabilitation (R&R) Entitlement Framework RP297 Under

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan October 2013 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Construction of Storm Water Drains in the Adjoining Areas of NH Bypass (Rawalpora Chowk Chanapora

More information

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP)

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) Resettlement Planning Document Resettlement Framework Document Stage: Draft for Consultation Project Number: 42486 June 2016 India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) The resettlement

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

India: Jammu & Kashmir Urban Sector Development Project

India: Jammu & Kashmir Urban Sector Development Project Resettlement Planning Document Full Resettlement Plan- Improvements to B.C Road from Shakuntala Crossing to Children s Hospital Including pedestrian subway Document Stage: Final Project Number: 41116 October

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

Revised Resettlement Plan Tibar-Gleno Road

Revised Resettlement Plan Tibar-Gleno Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING PROJECT February 2012 Democratic Republic of Timor-Leste REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Appendix 13 Resettlement Framework Dec 2011 SRI: Local Government Enhancement Project CURRENCY EQUIVALENTS (as of 27 June 2011) Currency Unit = Sri Lankan Rupee/s (SLR/Rs) Rs1.00 = $0.0091 $1.0 = Rs 109.8700

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

Resettlement Plan Dili-Tibar-Liquica Road

Resettlement Plan Dili-Tibar-Liquica Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING SECTOR PROJECT November 2011 REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK

More information

IND: Mumbai Metro Rail Systems Project

IND: Mumbai Metro Rail Systems Project Social Due Diligence Report October 2018 IND: Mumbai Metro Rail Systems Project Prepared by Mumbai Metropolitan Region Development Authority, Government of India for the Asian Development Bank. ABBREVIATION

More information

Resettlement and Indigenous Peoples Plan. IND: North Eastern State Roads Investment Program

Resettlement and Indigenous Peoples Plan. IND: North Eastern State Roads Investment Program Resettlement and Indigenous Peoples Plan February 2013 IND: North Eastern State Roads Investment Program Udaipur Melaghar Subproject (TR02) Prepared by Ministry of Development of North Eastern Region for

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

IND: Second Jharkhand State Road Project

IND: Second Jharkhand State Road Project Resettlement Plan March 2015 IND: Second Jharkhand State Road Project Dumka Hansdiha Road Prepared by State Highways Authority of Jharkhand (SHAJ), Government of India for the Asian Development Bank. ADB

More information

Resettlement Plan. October Prepared by the Government of Jammu and Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu and Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan October 2013 IND: Jammu and Kashmir Urban Sector Development Investment Program (JKUSDIP) - Construction of Mechanized Automated Multi Level Parking Facility at Super Bazaar, Jammu (Tranche

More information

Land Acquisition and Resettlement Due Diligence Report

Land Acquisition and Resettlement Due Diligence Report Land Acquisition and Resettlement Due Diligence Report Document stage: Draft for consultation Project Number: 48434 Loan and/or Grant Number(s): {LXXXX; GXXXX; TAXXXX} March 2016 India: Visakhapatnam-Chennai

More information

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Indigenous People Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP October 2013 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

More information

MLD - Kulhudhuffushi Harbor Expansion Project

MLD - Kulhudhuffushi Harbor Expansion Project Kulhudhuffushi Harbor Expansion Project (RRP MLD 36111-013) Due Diligence Report on Involuntary Resettlement and Indigenous Peoples March 2016 MLD - Kulhudhuffushi Harbor Expansion Project Prepared by

More information

IND: Second Jharkhand State Road Project

IND: Second Jharkhand State Road Project Resettlement Plan March 2015 IND: Second Jharkhand State Road Project Khunti - Tamar Road Prepared by State Highways Authority of Jharkhand (SHAJ), Government of India for the Asian Development Bank. ADB

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

SRI: Additional Financing for National Highway Sector Project

SRI: Additional Financing for National Highway Sector Project Resettlement Plan May 2011 Document Stage: Draft SRI: Additional Financing for National Highway Sector Project Hikkaduwa Baddegama Section of Hikkaduwa Baddegama Nilhena Road (B153) Prepared by Road Development

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field Draft Safeguards Monitoring Report Project No. 38164-013 Draft Semi Annual Report December 2015 2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas

More information

Indigenous Peoples Development Planning Document. IND: Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program

Indigenous Peoples Development Planning Document. IND: Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Draft for Consultation Project Number: 38412 June 2009 IND: Assam Integrated Flood and Riverbank

More information

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan February 2012 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Rehabilitation and Channelization of Storm Water Drains at Channi Himmat in Jammu City Prepared

More information

BAN: Railway Sector Investment Program

BAN: Railway Sector Investment Program Resettlement Planning Document Resettlement Framework Document Stage: Final Project Number: 32234 June 2006 BAN: Railway Sector Investment Program Prepared by Bangladesh Railway, Dhaka, Bangladesh The

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

Performance Standard 5 Land Acquisition and Involuntary Resettlement

Performance Standard 5 Land Acquisition and Involuntary Resettlement Introduction Performance Standard 5 1. Involuntary resettlement refers both to physical displacement (relocation or loss of shelter) and to economic displacement (loss of assets or access to assets that

More information

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE

More information

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Resettlement Implementation Plan Project Number: 37381-013 September 2012 Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Prepared by SMEC Consultants for Dry Zone Urban

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

Guidance Note 5 Land Acquisition and Involuntary Resettlement

Guidance Note 5 Land Acquisition and Involuntary Resettlement This Guidance Note 5 corresponds to Performance Standard 5. Please also refer to the Performance Standards 1-4 and 6-8 as well as the corresponding Guidance Notes for additional information. Bibliographical

More information

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement This document should be read in conjunction with the proposed World Bank Policy to understand the proposed responsibilities of the World Bank (in the Policy) and the Borrowing Country (in the Standards).

More information

INDIA: Tsunami Emergency Assistance (Sector) Project

INDIA: Tsunami Emergency Assistance (Sector) Project Resettlement Planning Document Short Resettlement Plan Document Stage: Final Project Number: 39114 March 2007 INDIA: Tsunami Emergency Assistance (Sector) Project Prepared by Public Works Department, Government

More information

Prepared by Road Construction Department, Government of Jharkhand.

Prepared by Road Construction Department, Government of Jharkhand. Resettlement Planning Document Resettlement Plan for Dumka Barhet Section Document Stage: Draft Project Number: 40005 May 2009 India: Jharkhand State Roads Project Prepared by Road Construction Department,

More information

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014 Work plan of Independent Agency and Implementation of IFC Performance Standards Green Goal Ltd., 17 February 2014 Content IFC performance standards Legal grounds of Cambodia Resettlement planning process

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

Land Acquisition and Resettlement Framework. PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project

Land Acquisition and Resettlement Framework. PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project Land Acquisition and Resettlement Framework Document Stage: Draft September 2017 PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project Prepared by Khyber Pakhtunkhwa Highways Authority, Communications

More information

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS ENVIRONMENTAL SAFEGUARDS Objectives To ensure the environmental soundness and sustainability of projects and to support the integration

More information

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007 Involuntary Resettlement - Overview Transport Forum Washington, D.C. March 30, 2007 OP 4.12 - Triggers Trigger: acquisition of land which displaces people physically and / or economically. Policy applies

More information

LUCKNOW METRO RAIL PROJECT

LUCKNOW METRO RAIL PROJECT LUCKNOW METRO RAIL PROJECT RESETTLEMENT POLICY FRAMEWORK (Final) LUCKNOW METRO RAIL CORPORATION LTD. Contents SECTION-1... 1 INTRODUCTION... 1 1.1 INTRODUCTION... 1 1.2 THE PROJECT... 1 Table 1.1: Route

More information

MLD: Greater Malé Environmental Improvement and Waste Management Project

MLD: Greater Malé Environmental Improvement and Waste Management Project Resettlement Framework Document Stage: Draft for Consultation Project Number: 51077-002 March 2018 MLD: Greater Malé Environmental Improvement and Waste Management Project Prepared by Ministry of Environment

More information

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector Resettlement Planning Document Short Resettlement Plan for Tranche-2 Components Document Stage: Draft for Consultation Project Number: TA 7096-IND April 2010 India: Preparing the Energy Efficiency Enhancement

More information

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING Road Development Agency 1 5 6 2 3 4 RESETTLEMENT POLICY FRAMEWORK FINAL REPORT Consultancy Services for the Design and Preparation of Bidding Documents for a Countrywide Roll-out of the Output and Performance

More information

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives Page 1 of 9 Involuntary Resettlement 1. Bank 1 experience indicates that involuntary resettlement under development projects, if unmitigated, often gives rise to severe economic, social, and environmental

More information

India: Uttarakhand State Road Investment Program

India: Uttarakhand State Road Investment Program Resettlement Planning Document Resettlement Plan for Kirti Nagar New Tehri Road Subproject Document Stage: Final Project Number: 38255 May 2008 India: Uttarakhand State Road Investment Program Prepared

More information

TRIBAL DEVELOPMENT PLAN

TRIBAL DEVELOPMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Rehabilitation, Upgradation and Strengthening of Nuapada-Bango Munda Section of NH-217

More information

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems Technical Assistance Consultant s Report Project Number: 44140 Date: April 2013 TA 7566-REG: Strengthening and Use of Country Safeguard Systems Subproject: Strengthening Involuntary Resettlement Safeguard

More information

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT DRAFT COMPARATIVE ANALYSIS OF NEPAL s LEGAL FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT Note: The following is based

More information

Resettlement Plan: Solar-LED Streetlights. BAN: Power System Efficiency Improvement Project

Resettlement Plan: Solar-LED Streetlights. BAN: Power System Efficiency Improvement Project Resettlement Plan: Solar-LED Streetlights Document Stage: Draft Project Number: 37113 April 2011 BAN: Power System Efficiency Improvement Project Prepared by: Bangladesh Power Development Board (BPDB),

More information

MON: Urban Development Sector Project Bulgan Subproject

MON: Urban Development Sector Project Bulgan Subproject Resettlement Completion Report Annual Report 24 December 2012 MON: Urban Development Sector Project Bulgan Subproject Prepared by Purevsuren Dorjnamjil, Resettlement Specialist, Project Management Unit

More information

IND: Uttarakhand Emergency Assistance Project

IND: Uttarakhand Emergency Assistance Project Resettlement Planning Document Project Number: 47229-001 July 2016 IND: Uttarakhand Emergency Assistance Project Sub Project : Supplementary Due Diligence Report (social) internal roads of Dehradun district

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project Internal Monitoring Report 37231-023 March 2016 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein do not

More information

Involuntary Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook Draft Working Document

Involuntary Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook Draft Working Document Involuntary Resettlement Safeguards A Planning and Implementation Good Practice Sourcebook Draft Working Document November 2012 This working document was prepared by staff of Asian Development Bank. It

More information

EBRD Performance Requirement 5

EBRD Performance Requirement 5 EBRD Performance Requirement 5 Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or loss of

More information

India: Delhi Meerut Regional Rapid Transit System Project

India: Delhi Meerut Regional Rapid Transit System Project Initial Poverty and Social Analysis October 2018 India: Delhi Meerut Regional Rapid Transit System Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

RESETTLEMENT POLICY FRAMEWORK. NATURAL GAS CONNECTION PROJECT IN 11 GOVERNORATES IN EGYPT (March 2014)

RESETTLEMENT POLICY FRAMEWORK. NATURAL GAS CONNECTION PROJECT IN 11 GOVERNORATES IN EGYPT (March 2014) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Submitted to : Egyptian Natural Gas Holding Company Prepared by: EcoConServ Environmental

More information

TIM: Road Network Upgrading Sector Project

TIM: Road Network Upgrading Sector Project Resettlement Plan August 2013 TIM: Road Network Upgrading Sector Project Prepared by the Government of {complete and accurate name of government agency or private sector project sponsor} for the Asian

More information

Indonesia: Enhanced Water Security Investment Project

Indonesia: Enhanced Water Security Investment Project Initial Poverty and Social Analysis March 2018 Indonesia: Enhanced Water Security Investment Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy

More information

Involuntary Resettlement Assessment and Measures. IND: Karnataka State Highway Improvement Project

Involuntary Resettlement Assessment and Measures. IND: Karnataka State Highway Improvement Project Involuntary Resettlement Assessment and Measures Resettlement Plan for AEP 5: 48A (Padubidri Belmane Karkala) Document Stage: Draft for Consultation Project Number: 42513 August 2010 IND: Karnataka State

More information

IND: Uttarakhand State Roads Investment Program (Project 3)

IND: Uttarakhand State Roads Investment Program (Project 3) Resettlement Plan November 2011 IND: Uttarakhand State Roads Investment Program (Project 3) Pauri Bend Magnesite Factory Road Subproject Prepared by Public Works Department, Government of Uttarakhand for

More information

IND: Railway Sector Investment Program Tranche 3

IND: Railway Sector Investment Program Tranche 3 Resettlement Due Diligence Report September 2017 IND: Railway Sector Investment Program Tranche 3 Prepared by the Ministry of Railways for the Republic of India and the Asian Development Bank. CURRENCY

More information

Resettlement Policy Framework

Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Tajikistan Ministry of Transport Central Asia Road Links Project Republic

More information

Draft Resettlement Policy Framework

Draft Resettlement Policy Framework Republic of Tajikistan Ministry of Transport Central Asia Road Links Project Republic of Tajikistan Draft Resettlement Policy Framework Date: July 5, 2014 Draft Resettlement Policy Framework for Central

More information

IND: Rajasthan State Highway Investment Program

IND: Rajasthan State Highway Investment Program Resettlement Plan April 2016 IND: Rajasthan State Highway Investment Program Package-4 1. Singhana - Buhana - Haryana Border Road (SH-13B) 2. Ajeetgarh - Chala Road (SH-13) 3. Sikar-Ganeri-Jaswantgarh

More information

India: Infrastructure Development Investment Program for Tourism

India: Infrastructure Development Investment Program for Tourism Infrastructure Development Investment Program for Tourism (RRP IND 40648) Resettlement Framework (Updated) Project Number: P40648 Approved: July 2010 Revised: October 2010 India: Infrastructure Development

More information

Timor-Leste: Baucau to Viqueque Highway Project

Timor-Leste: Baucau to Viqueque Highway Project Resettlement Plan Project Number: 51115 June 2017 Timor-Leste: Baucau to Viqueque Highway Project Prepared by the Government of Timor-Leste for the Asian Development Bank. Table of Contents CHAPTER 1

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

India. Public Works Department. DETAILED PROJECT REPORT Volume - IX: Resettlement Action Plan. July 2015 GOVERNMENT OF UTTAR PRADESH

India. Public Works Department. DETAILED PROJECT REPORT Volume - IX: Resettlement Action Plan. July 2015 GOVERNMENT OF UTTAR PRADESH Public Disclosure Authorized GOVERNMENT OF UTTAR PRADESH Public Works Department Uttar Pradesh Core Road Network Development Program Part A: Project Preparation DETAILED PROJECT REPORT Volume - IX: Resettlement

More information

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program Indigenous Peoples Planning Framework Document Stage: Draft for Consultation Project Number: 47101 (IND) September 2013 India: Assam Power Sector Investment Program Prepared by Assam Power Generation Corporation

More information

NEP: Road Connectivity Sector I Project

NEP: Road Connectivity Sector I Project Resettlement Planning Document Revised Resettlement Plan Bhaktapur Changunarayan Subproject Document Stage: Final Project December: 37266-3 September 2008 NEP: Road Connectivity Sector I Project Prepared

More information

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia)

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Republic of Sakha (Yakutia) of the Russian Federation Innovative Development of Preschool

More information

Rehabilitation & Resettlement (R&R) Policy for Kochi Metro Rail Project March 2015

Rehabilitation & Resettlement (R&R) Policy for Kochi Metro Rail Project March 2015 Rehabilitation & Resettlement (R&R) Policy for Kochi Metro Rail Project March 2015 AARVEE Associates Architects Engineers & Consultants Private Limited 8-2-5, Ravula Residency Srinagar Colony Hyderabad

More information

PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project

PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project (RRP PAK 47360-003) Resettlement Plan August 2018 PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement

More information

Nepal: Rural Reconstruction and Rehabilitation Sector Development Project

Nepal: Rural Reconstruction and Rehabilitation Sector Development Project Resettlement Planning Document Resettlement Plan Grant Number: 0093 December 2010 Nepal: Rural Reconstruction and Rehabilitation Sector Development Project Kushma-Durlung-Salija Road Sub-Project, Kusma-Parbat

More information

India: Infrastructure Development Investment Program for Tourism

India: Infrastructure Development Investment Program for Tourism Infrastructure Development Investment Program for Tourism (RRP IND 40648) Resettlement Framework Document Stage: Draft for Consultation Project Number: P40648 July 2010 India: Infrastructure Development

More information

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project Resettlement Plan (Draft) November 2013 IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project Prepared by, Government of Madhya Pradesh through MP Transco, DISCOM C, DISCOM-E

More information

BAN: South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2

BAN: South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2 Resettlement Due Diligence Report May 2017 BAN: South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2 Prepared by the Roads and Highways Department, Government of the

More information

SECOND TAMIL NADU ROAD SECTOR PROJECT (TNRSP-II) Final Resettlement Plan

SECOND TAMIL NADU ROAD SECTOR PROJECT (TNRSP-II) Final Resettlement Plan SECOND TAMIL NADU ROAD SECTOR PROJECT (TNRSP-II) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Final Resettlement Plan for 3 Roads under PPP Public Disclosure Authorized

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Cao Bang Province Prepared by the Ministry of Education

More information

SRI: Southern Road Connectivity Project

SRI: Southern Road Connectivity Project Resettlement Plan January 2016 SRI: Southern Road Connectivity Project Kesbewa to Pokunuwita Section of Pamankada Horana (B084) Road Prepared by Ministry of University Education & Highways, Government

More information

Resettlement Policy Framework

Resettlement Policy Framework Urban Transport Improvement Project of Tianjin by Using the World Bank Loan Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

PAK: Sindh Provincial Road Improvement Project (SPRIP)

PAK: Sindh Provincial Road Improvement Project (SPRIP) SOCIAL SAFEGUARD DUE DILIGENCE REPORT Social Safeguard Due Diligence Report for proposed Additional Road Sections (Sindh Provincial Road Improvement Project SPRIP) (September 2018) PAK: Sindh Provincial

More information

IND: Uttarakhand Emergency Assistance Project

IND: Uttarakhand Emergency Assistance Project Resettlement Planning Document Project Number: 47229-001 May 2016 IND: Uttarakhand Emergency Assistance Project Sub Project : DDR for Roads of Dehradun District Submitted by Uttarakhand Emergency Assistance

More information

Resettlement Framework. BHU: Urban Infrastructure Project. October Prepared by the Royal Government of Bhutan for the Asian Development Bank.

Resettlement Framework. BHU: Urban Infrastructure Project. October Prepared by the Royal Government of Bhutan for the Asian Development Bank. Resettlement Framework October 2011 BHU: Urban Infrastructure Project Prepared by the Royal Government of Bhutan for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 5 October 2011) Currency unit

More information

GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS NATIONAL HIGHWAYS INTERCONNECTIVITY IMPROVEMENT PROJECTS (NHIIP)

GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS NATIONAL HIGHWAYS INTERCONNECTIVITY IMPROVEMENT PROJECTS (NHIIP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS NATIONAL HIGHWAYS INTERCONNECTIVITY

More information