American Bar Association Tort Trial & Insurance Practice Section Fidelity and Surety Law Committee

Size: px
Start display at page:

Download "American Bar Association Tort Trial & Insurance Practice Section Fidelity and Surety Law Committee"

Transcription

1 American Bar Association Tort Trial & Insurance Practice Section Fidelity and Surety Law Committee Calculating the Performing Surety s Additional Time to Complete Tammy N. Giroux, Esq. Shumaker, Loop & Kendrick, LLP Tampa, Florida Doug Dearie Manager-Construction Services Liberty Mutual Surety Seattle, Washington Presented at the 2011 Midwinter Meeting Surety Program January 20-21, 2011 New York, New York The Critical Construction Issues Facing the Performing Surety James Carpenter, Matthew Horowitz and Cindy Rodgers-Waire, Program Chairs

2 I. INTRODUCTION 1 A surety s obligations under the performance bond are generally triggered once an obligee declares the principal in default under the contract. After receiving notice of the default, the surety is entitled to a reasonable period of time to investigate the facts and circumstances surrounding the default. The surety must promptly decide upon a course of action under the performance bond. The surety may deny liability and not perform, or the surety may perform under a reservation of rights. The AIA-A312 bond, for example, expressly lists the options available to the surety. Other bonds, however, do not expressly identify the surety s performance options, and simply commit the surety to perform the obligations undertaken by the principal in its contract with the obligee. As discussed in more detail by other authors presenting papers for this conference, a performance bond is a three-party agreement whereby a surety guarantees the principal s performance of an underlying contract between the principal and the obligee. Once the surety has elected to perform under a reservation of rights, the surety must promptly commence work on the project. The completing surety should analyze its entitlement to any pending claims for time extensions by its principal. In addition, the surety should evaluate its own entitlement to additional contract time for current delays, as well as anticipated future delays. Finally, as the work progresses, the surety must evaluate and timely submit its completing contractor s requests for time extensions. In connection with advancing requests for 1 The authors acknowledge Duane A. Daiker, a partner with Shumaker, Loop & Kendrick, LLP, and Timothy C. Garding, an associate with Shumaker, Loop & Kendrick, LLP, for their assistance with this paper. 1

3 additional time, the surety should simultaneously assess whether the time extensions are compensable or non-compensable, and proceed accordingly. II. THE SURETY S ENTITLEMENT TO TIME EXTENSIONS FROM THE OBLIGEE A surety has the right to select among several courses of action once an obligee has either declared the principal in default or terminated the principal. 2 The surety has the right to mitigate damages that may result from a default or termination, 3 and to limit its liability when satisfying its obligation to make the obligee whole. 4 Whether the surety elects to complete the work itself, support the defaulted principal while the principal completes the work, or enter into a takeover agreement with the obligee and a completion agreement with a replacement contractor, the surety has certain rights. 5 The surety is entitled to investigate the status of the project as of the date of 2 For a more detailed discussion of a surety s performance options, see BRUNER & O CONNOR, JR., BRUNER & O CONNOR ON CONSTRUCTION LAW 12:15-12:22, 12:36, 12:77-12:83 (2009). 3 See, e.g., St. Paul Fire & Marine Ins. v. City of Green River, 93 F.Supp.2d 1170, 1178 (D. Wy. 2000) (holding an obligee s action that deprived a surety of its ability to protect itself pursuant to performance options under a performance bond constituted a material breach that rendered the bond null and void); Dragon Constr., Inc. v. Parkway Bank & Trust, 678 N.E.2d 55, (Ill. App. Ct. 1997) (holding the surety was discharged from any obligation under the performance bond due to the obligee s actions in replacing the contractor without providing notice to the surety); Gen. Accident Ins. Co. of Am. v. Merritt-Meridian Constr. Corp, 975 F.Supp. 511, 516 (S.D.N.Y.1997) ( Sureties enjoy such discretion to settle claims because of the important function they serve in the construction industry, and because the economic incentives motivating them are a sufficient safeguard against payment of invalid claims. ). 4 See, e.g., Seaboard Sur. Co. v. Town of Greenfield, 266 F.Supp.2d 189, (D. Mass. 2003) (acknowledging the tripartite nature of surety contracts and the necessity of granting the surety a commercially reasonable period of time to investigate the circumstances of the default prior to requiring the surety to select one of the various available performance options under the bond); Morrison Assurance Co., Inc. v. United States, 3 Cl.Ct. 626, 632 (1983) (holding a performance bond protects the government obligee by making sure the obligee is not left with a partially completed project); Mass. Bonding and Ins. Co. v. State of New York, 259 F.2d 33, 37 (2d Cir. 1958) ( [I]t is settled law that a surety which undertakes to complete a construction contract after its principal has defaulted and pays laborers and materialmen becomes entitled to payments due the principal from the owner, here the United States, independent of any formal assignment. ). 5 When the contractor (the principal) defaults and the surety pays the claim or completes the contract, the surety steps into three sets of shoes: 2

4 default or termination, pursue all viable claims for time extensions that exist as of the date of default or termination, and pursue all claims for time extensions that arise during the completion of the project. 6 Delays on construction projects result from a variety of causes and circumstances, and critical delays are those that impact the construction schedule for the work. A critical delay is usually a condition precedent to obtaining a time extension. 7 Thus, the surety must evaluate whether the identified critical delays are excusable or non-excusable. 8 An excusable delay, one that was beyond the control of the contractor and unforeseeable, will justify an extension of time for contract completion. 9 In addition, once the determination is made that a particular critical delay is excusable, the surety should determine if it is entitled to compensation for the delay period. 10 An excusable delay will be considered compensable if the delay resulted from actions or inaction of another party, and the surety, as the delayed party, suffered damages as a result of [The Surety] stands in the shoes of the contractor insofar as there are receivables due it; in the shoes of laborers and material men who have been paid by the surety who may have had liens; and, not least, in the shoes of the [owner], for whom the job was completed. Transamerica Ins. Co. v. Barnett Bank, 540 So.2d 113, (Fla. 1989) (citing Nat l Shawmut Bank v. New Amsterdam Cas. Co., 411 F.2d 843, (1st Cir. 1960)). In addition, for a detailed discussion of a surety s rights of subrogation and assignment, see George J. Bachrach & John V. Burch, The Surety s Subrogation Rights, in THE LAW OF SURETYSHIP (Edward G. Gallagher ed., 2d ed. 2000). 6 For a detailed discussion of the process of developing and presenting a request for time extension, see 1 RICHARD K. ALLEN & STANLEY A. MARTIN, CONSTRUCTION LAW HANDBOOK (2d ed. 2009). 7 Id. at 23.03[B]. 8 Id. at 23.03[B] & [D]. 9 Id. 10 Id. at 23.03[C]. 3

5 the delay. 11 As discussed below, the surety must meet its burden of proof and clearly show that the otherwise excusable delay is not a concurrent delay, which renders it non-compensable. 12 A. The Surety May Pursue its Principal s Claims for Time Extensions for Prior Delays The surety may be entitled to pursue its principal s claims for time extensions, even if previously rejected. In situations where (i) the principal complied with the notice provisions of the contract for the submission of claims for time extensions, but the obligee denied the requested time extensions; (ii) the obligee failed to timely respond to the principal s claims for additional time; or (iii) the obligee wrongfully rejected the principal s claims for additional time; the surety, in mitigating its damages and limiting its liability, should re-evaluate every claim for additional time, and further pursue all viable claims that should have been granted by the obligee to the principal. The AIA Standard Form of Agreement 13 and AIA General Conditions 14 address delays, extensions of time, adjustments to the original completion date, and adjustments to the original contract sum. 15 As part of its investigation, the surety should review the previously submitted 11 Id. 12 Id. at 23.03[B], AIA Document A , Standard Form of Agreement between Owner and Contractor Where Basis of Payment Is a Stipulated Sum. 14 AIA Document A , General Conditions of the Contract for Construction. 15 The AIA General Conditions provide: A Change Order is a written instrument prepared by the Architect and signed by the Owner, Contractor and Architect stating their agreement upon all of the following:.1 The change in the Work;.2 The amount of the adjustment, if any, in the Contract Sum; and.3 The extent of the adjustment, if any, in the Contract Time If the Contractor is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or Architect, or of an employee of 4

6 claims for time extensions, the supporting documentation for the claims, the obligee s responses to the claims (if any), and all project documentation related to the claims. The surety must confirm its principal complied with the contractual notice provisions. In addition, the surety must determine if any potential waiver arguments exist, arising out of the principal s failure to timely submit claims for time extensions, or arising out of the principal s submittal of a claim for additional compensation that was silent as to time extensions when it should have included an express reservation of rights to subsequently pursue a claim for time extensions. In situations where the obligee and surety are negotiating a written takeover agreement, the surety should include all unresolved issues in the takeover agreement. As an example, a either, or of a separate contractor employed by the Owner; or by changes ordered in the Work; or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Contractor s control; or by delay authorized by the Owner pending mediation and arbitration; or by other causes that the Architect determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Architect may determine Claims relating to time shall be made in accordance with applicable provisions of Article This section 8.3 does not preclude recovery of damages for delays by either party under other provisions of the Contract Documents Definition. A Claim is a demand or assertion by one of the parties seeking, as a matter of right, payment of money, or other relief with respect to the terms of the Contract. The term Claim also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. The responsibility to substantiate Claims shall rest with the party making the Claim If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor s Claim shall include an estimate of cost and of probably effect of delay on the progress of the Work. In the case of continuing delay, only one Claim is necessary. 5

7 surety can include provisions like those in the format below, regarding unresolved time extension issues: Surety. The Owner acknowledges that the Surety will subcontract the performance of the work under the Original Contract to a Completion Contractor. The Owner acknowledges that the Surety is acting in its capacity as a Completion Surety, by virtue of the Surety having issued the Performance Bond for the Original Contractor, in making arrangements for the performance and completion of the Contract, and not as a completing contractor, and that the Surety is not assuming any obligations or liabilities beyond those set forth in the Bond, the Original Contract, any amendments to the Original Contract, and this Agreement. The Surety is entitled to all rights, title and interest of the Original Contractor under the Contract in all respects as if the Surety were the original party to the Contract. No right, promise, benefit or privilege provided to the Owner or the Surety in or by the Contract or Performance Bond shall be waived, reduced, eliminated or released by this Agreement or its terms. All such rights, promises, benefits and privileges shall be and are hereby preserved to the Owner and the Surety. Project Issues. The Surety and the Owner acknowledge that certain issues remain outstanding regarding claims by the Original Contractor and Surety against the Owner and by the Owner against the Original Contractor and Surety, and the Surety and Owner retain any and all rights, with respect to these issues which are as follows: [insert specific issues]. The Surety and Owner agree that the above issues shall be referred to Alternative Dispute Resolution pursuant to this Agreement. Time for Completion. The Surety hereby agrees that it shall cause the remaining Work under the Contract to be complete within not more than calendar days following receipt of the Owner s Notice to Proceed with respect to its completion work ( New Completion Date ), subject only to any time extensions that may otherwise be granted or available to the Surety under the terms of the Contract or by this Agreement. The Owner shall provide the Surety with a punch list of all unfinished work that remains to be completed or corrected within fifteen (15) days of substantial completion. The Owner s failure to provide the foregoing punch list within the fifteen (15) day period will extend the New Completion Date accordingly. Additionally, Owner agrees with Surety that it will not assess against Surety or demand from Surety liquidated damages for the period of time from the date of termination of the project to the execution of this Agreement to the New Completion Date if the Surety or those acting on its behalf have completed all remaining work and obtained Final Completion by the New Completion Date; but if Surety fails to complete all remaining work and obtain final completion by the New Completion Date as provided herein, subject only to any time extensions that may otherwise be granted or available to the Surety under the terms of the 6

8 Contract or by this Agreement, then Owner shall be entitled to liquidated damages as provided under the Contract and Performance Bond for the period from the Completion Date to the date final completion is achieved. In addition, in the absence of a takeover agreement, the surety should submit its claims to the Architect under Section of the AIA General Conditions. The surety should not risk a contractual bar to its claims for time extensions or delay damages due to a failure to satisfy conditions precedent under the contract. Section of the AIA General Conditions provides as follows: The Architect will interpret and decide matters concerning performance under, and requirements of, the Contract Documents on written request of either the Owner or Contractor. The Architect s response to such requests will be made in writing within any time limits agreed upon or otherwise with reasonable promptness. Courts interpreting the above contract language, or modified versions of the above contract language, have barred claims for damages under a conditions precedent argument when a party failed to timely submit a claim, controversy or request for equitable adjustment to the Architect as the initial arbiter of disputes. 16 B. The Surety May Pursue its Own Time Extensions for Current and Anticipated Future Delays Once the surety has elected a course of action under the performance bond, the surety should also analyze and evaluate its own independent basis to seek time extensions and compensation for current delays, as well as known and anticipated future delays. The review of 16 See, e.g., Mayfair Const. Co. v. Waveland Assoc.s Phase I Ltd. P ship, 619 N.E.2d 144, 156, (Ill.App.Ct 1993) (holding the obligee materially breached the contract by failing to bring its claims for construction defects and delays first to the architect for a determination prior to suit, barring the obligee s counterclaims, where the contract expressly required the parties to submit disputes initially to the architect for decision); Commonwealth Const. Co. v. Cornerstone Fellowship Baptist Church, 2006 WL , *21, 23 (Del.Sup.Ct. 2006) (holding the obligee s claims for offsets and credits against the contractor s claims for payment were barred where the obligee failed to submit its claims to the architect as the initial decision maker on such issues). 7

9 the project documents, and the preparation of an after-the-fact schedule analysis, will assist the surety in identifying and pursuing additional claims for time extensions. The surety should focus on proving that delays resulted from the fault of the obligee and its representative. To assist in this analysis, as discussed in more detail below, the surety s professional consultant should conduct a schedule analysis in connection with the project s critical path. 17 The objective is to clearly delineate obligee delay versus contractor delay, and then immediately pursue all viable claims for time extensions. C. The Surety May Pursue the Completing Contractor s Claims for Time Extensions Finally, as the work progresses, the surety should evaluate and timely submit its completing contractor s claims for time extensions. The completing contractor must maintain an accurate schedule. The completing contractor is entitled to submit claims for time extensions upon the discovery of latent defects, the discovery of design errors, or the occurrence of additional obligee or architect delays. 18 In addition, the surety and completing contractor should review the written contract for all applicable provisions authorizing claims for additional time extensions. 19 Events of force majeure, such as hurricanes, floods and earthquakes, also warrant an award of time extensions. 20 Obtaining the time extensions can prove critical in mitigating and minimizing damages arising from the principal s default. 17 For a more detailed discussion of proving and defending time impact claims, see Jon M. Wickwire & Thomas D. Fertitta, Deciding To Litigate: Proving and Defending Time Impact Claims, in MANAGING AND LITIGATING THE COMPLEX SURETY CASE (Philip L. Bruner & Tracey L. Haley eds., 2d ed. 2007) and ALLEN & MARTIN, supra note 6, at , AIA General Conditions. 19 See Wickwire & Fertitta, supra note 17, at ; ALLEN & MARTIN, supra note 6, at See Wickwire & Fertitta, supra note 17, at ; ALLEN & MARTIN, supra note 6, at

10 III. CALCULATION OF TIME EXTENSIONS As discussed in detail by Jon Wickwire and Thomas Fertitta in Deciding To Litigate: Proving and Defending Time Impact Claims, the surety often must prepare an after-the-fact schedule analysis. 21 The surety, directly or through a consultant, should review relevant project documents including, but not limited to, daily reports and job diaries, progress charts, meeting minutes, correspondence, change order files, schedules, cost and budget records, photographs, and requests for information. 22 If supported by the project documents, the surety should resubmit the principal s claims for time extensions arising out of delays caused by the obligee and its representatives. The surety should undertake this analysis whether or not the obligee and surety have entered into a written takeover agreement. When possible, the after-the-fact schedule analysis will assist the surety in pursuing its principal s justifiable claims for time extensions, even if previously rejected. Obtaining approval of its principal s claims for time extensions may be critical to minimizing damages arising from the principal s default on the bonded project. A. The As-Planned or Baseline Schedule With every project, the surety must analyze the nature of the delay described in the claims for time extensions. The prime contract should include the as-planned (or baseline) schedule that establishes the original commencement date and the original substantial completion date. The surety should then identify the as-built critical path(s) by reviewing and analyzing the actual activities in connection with the relationships and events that controlled the progression of the project toward substantial completion. By comparing the as-built start and finish dates of 21 Wickwire & Fertitta, supra note 17, at Id. at ; see also ALLEN & MARTIN, supra note 6, at 23.05; BRUNER & O CONNOR, supra note 2, at

11 critical activities to the originally planned dates, the surety can identify and quantify occurrences of critical delay. In undertaking this analysis, the surety must investigate the causal factors for each of the critical delays and determine the responsible party or parties for each delay. Once that analysis is complete, the surety can then determine the excusable and compensable nature of each delay. The surety will bear the burden of proving the amount of days of contractually recognized time extensions. The surety must review the contract and determine if the contract includes schedule specification sections that set forth a specific methodology the contractor or surety must follow in proving its request for time extensions and related demands for monetary compensation. 23 The above is often referred to as the critical path method ( CPM ) schedule analysis or critical path network analysis. 24 CPM schedules illustrate the construction activities as well as the sequencing of those activities. 25 The critical path model has been defined as: 26 A CPM is a standard construction device used to plan the activities of a construction project in a logical, orderly sequencing manner citing durations for the different activities from the beginning of the job to the end. A CPM is created by dividing the entire project into discrete and quantifiable steps; in turn, each step is allotted an estimated time for completion. Ultimately, each step is arranged into a chronological sequence, thus revealing the anticipated length and structure of the entire construction schedule. In addition to serving as a road map for the contractors to determine when and where their work fits into the overall construction sequence, the CPM also assists contractors in assessing their hiring and material purchasing needs. 23 Wickwire & Fertitta, supra note 17, at For a discussion of using the critical path network analysis to measure critical delay, see ROBERT F. CUSHMAN ET AL., CONSTRUCTION DISPUTES: REPRESENTING THE CONTRACTOR (3d ed. 2001). 25 Id.; see also Wickwire & Fertitta, supra note 17, at ; ALLEN & MARTIN, supra note 6, at See, e.g., Roberts & Schaefer Co. v. Hardaway Co., 152 F.3d 1283, 1287 (11th Cir. 1998), reh'g and suggestion for reh'g en banc denied, 162 F.3d 1179 (11th Cir. 1998). 10

12 As discussed by Wickwire and Fertitta in Deciding To Litigate: Proving and Defending Time Impact Claims, the focus of the time impact analysis is to evaluate delays on a chronological and cumulative basis. 27 The chronological and cumulative approach allows the executor of the schedule to take into account that the schedule is dynamic and the critical path can change from month to month, and that time is a resource to the executor of the schedule as well as to the schedule stakeholders. 28 The surety must proceed carefully since courts have refused to accept some after-the-fact schedules due to a lack of reliability illustrated in the analysis. 29 B. Preparing the As-Built Critical Path Schedule As stated above, document sources for the as-built critical path schedule analysis include the entire contemporaneous project records, including but not limited to, daily reports and job diaries, meeting minutes, requests for information, progress charts, updates to schedules, change order files, photographs, and weather reports. The focus of the as-built schedule analysis is identifying how a change or delay extends the project s critical path and the project completion date. 30 As succinctly noted by Wickwire and Fertitta, a credible CPM schedule analysis considers the following: 31 the contemporaneous baseline schedule; the amount of float available, if any, of the impacted activities; 27 Wickwire & Fertitta, supra note 17, at Id. at Id. at (citing Chaney & James Construction Co., FAACAP No , 66-2 BCA 6066 (1967) and Mega Constr. Co. v. United States, 29 Fed. Cl. 396, , 434 (1993)). 30 Wickwire & Fertitta, supra note 17, at Id. at

13 a chronological and cumulative accounting of excusable delays for which time extensions may still be pending; the actual job conditions encountered; and the progress achieved up to the point in time when the present delay occurs. In addition, Wickwire and Fertitta provide a comprehensive step-by-step procedure for preparing and documenting delays in their Proof of Delay Procedure Checklist, set forth below: 32 A. Study the scope of the change (alleged or directed), or the extent of the delay encountered. B. Review all reference material, such as appropriate contract clauses, construction drawings, sketches, specifications, vendor data, regulatory and administrative codes, field directives, correspondence, and cost estimates. Prepare an accurate description of the changed condition or the delay encountered. C. Identify all contracting parties who are affected by the direct or indirect delay and request any participation or documentation assistance that may be necessary. D. Determine which activity or activities on the project schedule is or are potentially impacted by the added, delayed, or changed work. E. Review the schedule and determine the scheduled start and finish dates for all affected activities. F. Status the CPM schedule to determine the project s critical path at the inception of the delay. G. From the record-keeping systems and from contacts with key project staff, identify and document the facts associated with the change and/or delay issue. H. Prepare a fragnet analysis illustrating the sequence of delay and define its relationship to the current adjusted schedule. [A fragnet is defined as a sequence of new activities and/or activity revisions that are proposed to be added to the existing schedule to demonstrate (mathematically and graphically) the influence of delay and also the method for incorporating 32 Id. at

14 delay and any impacts into the schedule.] The fragnet should identify the first notice involved and the sequence of activities necessary to mobilize the required work, and it should clearly demonstrate the effect or lack of effect of the alleged delay on the existing schedule and the remaining activities required to be performed. I. Prepare a written narrative of the overall schedule analysis and derive a time impact position to be taken for each delay. Factual references to contract clauses, schedule information, drawings, specifications, sketches, industry standards, and any written or oral communications should be properly identified to support positions and ultimate conclusions. Weekends, holidays, and any recovery periods involved in the calculations should be noted. Also note any use or absorption of available float in the analysis. J. Make sure that any extensions of time for excusable delay is the direct result of the change or delay, and not for any nonexcusable cause. In order to obtain approval of a claim for time extension, the surety must clearly prove the delay was caused by the obligee or its representative. 33 In addition, the surety may obtain time extensions under the contract if the surety shows the delays were caused by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the surety or contractor s control. 34 The surety must anticipate all responses and defenses by the obligee and its representative, including arguments that the purported delay was caused solely by the contractor or constitutes a concurrent delay. Under every scenario, the surety must compute the delay 33 See, e.g., Blinderman Constr. Co. v. United States, 695 F.2d 552, 559 (Fed.Cir. 1982) (observing that [g]enerally, courts will deny recovery where the delays are concurrent or intertwined and the contractor has not met its burden of separating its delays from those chargeable to the Government.); Commerce Int l Co. v. United States, 338 F.2d 81 (Ct.Cl. 1964) (same); S.W. Marshall, Jr. v. United States, 164 F.Supp. 221, (Ct.Cl. 1958) (holding courts cannot grant monetary recovery where the contractor fails to apportion the degree of blame attributable to each party) , AIA General Conditions; see also ALLEN & MARTIN, supra note 6, at 23.03[B], 23.04[E]. 13

15 period and the proposed new completion date. In addition, the surety should simultaneously assess whether the time extensions are compensable, and proceed accordingly. C. Advantages of Using the As-Built Schedule Analysis The as-built schedule analysis, when prepared in a comprehensive and reliable manner, presents proof of not only the fact of a delay, but also the cause of that delay. 35 Pursuant to Section of the AIA Standard Form of Agreement, and Section of the AIA General Conditions, the obligee should grant the surety time extensions, and corresponding monetary compensation resulting from the project delays, if the delays are not contractor-caused or surety-caused. 36 In addition, the surety should pursue, and the obligee should approve, claims for time extensions for concurrent delays, even if the obligee denies claims for additional compensation arising out of the concurrent delays. 37 Thus, the as-built schedule analysis is an effective tool for the surety. IV. DISCUSSION OF POTENTIAL ISSUES WITH COMPENSATION FOR DELAYS The surety will bear the burden of proof associated with proving the existence of damages and then quantifying those damages. 38 As stated above, the surety has the right to pursue not only time extensions, but also the monetary compensation resulting from the project delays, if the delays are not contractor-caused or surety-caused. If the delay that forms the basis 35 Wickwire & Fertitta, supra note 17, at Blinderman Constr. Co., 695 F.2d at 559 (quoting Coath & Goss, Inc. v. United States, 101 Ct.Cl. 702, (1944) and Commerce Int l Co. v. United States, 167 Ct.Cl. 529, 338 F.2d 81, 90 (1964) ( Where both parties contribute to the delay neither can recover damage, unless there is in the proof a clear apportionment of the delay and expense attributable to each party. )). 37 See ALLEN & MARTIN, supra note 6, at 23.03[C] & [D]. 38 For a more detailed discussion of proving and defending construction contract damages, including damages associated with time impact claims, see Julian F. Hoffar, Deciding To Litigate: Proving and Defending Damages, in MANAGING AND LITIGATING THE COMPLEX SURETY CASE (Philip L. Bruner & Tracey L. Haley eds., 2d ed. 2007); see also ALLEN & MARTIN, supra note 6, at

16 of the requests for time extensions involves concurrent causes, or the amount of delay cannot be attributed specifically to the obligee or the obligee s representatives, then the surety may not recover damages. The term concurrent delay indicates a delay to a project s critical path caused by multiple events not exclusively within the control of either the obligee or the contractor. 39 In general, concurrent delay is described as a situation in which two or more delays occur at the same time during all or a portion of the delay periods being considered. 40 In circumstances where the obligee and contractor share responsibility for the delays affecting the critical path (e.g., delays that would affect the overall completion date), the obligee may agree to extend the contract completion date to reflect the period of concurrent delay but simultaneously deny a claim for monetary damages for that period. 41 The concept of concurrent delay has been applied in at least two circumstances: (i) where both parties to a contract are simultaneously at fault for a delay to one activity on the critical path; and (ii) where each party is causing a delay to a separate activity, both of which would affect the overall completion date. 42 As the party seeking recovery, the surety bears the burden of apportioning the delay. A. Concurrent Delay - Joint Fault by Contractor/Surety and Obligee Many courts have recognized the first example of concurrency, which is based upon the notion of joint fault. 43 Generally, courts do not grant delay damages where the contractor (or surety) and obligee both contributed to a delay on the same aspect of the project and the contractor (or surety) fails to meet its burden of segregating its delays from those chargeable to 39 See, e.g., BRUNER & O CONNOR, supra note 2, at 15: CUSHMAN ET AL., supra note 24, at 17.04; ALLEN & MARTIN, supra note 6, at 23.01[D]. 41 CUSHMAN ET AL., supra note 24, at 17.04; ALLEN & MARTIN, supra note 6, at 23.01[D]; JOHN CIBINIC, JR. & RALPH C. NASH, JR., ADMINISTRATION OF GOVERNMENT CONTRACTS 609 (3d ed. 1995). 42 CIBINIC & NASH, supra note 40, at Blinderman Constr. Co., 695 F.2d at

17 the obligee. 44 The concurrent delays are thus said to be intertwined. 45 In such circumstances, courts deny recovery of damages on the grounds that delays attributable to both parties are commingled and the court cannot ascertain the measure of the contractor s damages without speculating. 46 For example, in F.M. Hargrave v. United States, 47 the plaintiff contractor, Hargrave Construction Company ( Hargrave ), and the government each caused delays to compaction work during the performance of a contract for grading, paving, construction of drainage facilities and construction of an additional runway on a military airport. 48 Hargrave asserted the government s inspectors prevented proper compaction by requiring excessive wetting of the subgrade. 49 The court agreed, finding the government s inspectors required the use of an excessive amount of water and the government s inspectors provided improper instructions during the work. 50 However, the court also faulted Hargrave for its lack of sufficient equipment, inability to handle the drainage, and inability to prevent ponding on the project site. 51 In ruling, the court found that although Hargrave incurred extra costs as a result of the government s improper direction, the court could not determine the extent to which Hargrave s damages were the direct result of the actions of the government. 52 Citing the concurrency rule, which denies recovery where the parties are jointly at fault for the delay, the court denied Hargrave s claim 44 Id. 45 Id. 46 Id. 47 F.M. Hargrave v. United States, 130 F.Supp. 598 (Ct.Cl. 1955). 48 Id. at Id. 50 Id. 51 Id. 52 Id. at

18 since Hargrave failed to meet its burden of proving to the court that its additional costs and expenses were directly caused by the actions of the government. 53 B. Concurrent Delay - Separate and Distinct Activities on the Scheduling Critical Path (Offsetting Delays) The second type of concurrency occurs when delay is simultaneously caused by the contractor (or surety) and the obligee, but arises from two separate and distinct activities identified on the scheduled critical path. Courts and governing boards have recognized that concurrent delay also exists where a project would have been delayed by one cause, notwithstanding another delay caused by either party. 54 Generally, courts do not grant delay damages where the contractor and obligee are simultaneously causing delay relating to two separate activities. 55 Stated differently, courts are denying claims for delay damages where the contractor or surety cannot show that Party A delayed the project s completion date by a delay to Activity X when the completion date would also have been extended by a separate delay to Activity Y caused by Party B. 53 Id. at William F. Klingensmith, Inc. v. United States, 731 F.2d 805 (Fed. Cir. 1984) (holding that although the contractor caused some delay in the installation of extra caissons, the contractor could recover damages if it showed the obligee caused concurrent delays arising out of the separate issue of the smoke tunnel, and if the contractor proved how much of that concurrent delay was caused by the obligee); Chas. I. Cunningham Co., IBCA No. 60, 57-2 BCA 1541, at 5483 (1957) (holding contractor should not be held responsible for delays in the completion of the project caused by the issuance of government purchase orders that necessitated deferment of the completion until certain items could be procured and installed); Young Enterprises of Ga., Inc. v. Gen. Serv. Admin., GSBCA No , 00-2 BCA 31, 148 (2000) (considering the concurrent delays of the contractor and the government, the board rejected the contractor s claims for recovery for delay damages on the grounds the contractor failed to carry its burden of proof and failed to show the delays were caused solely by the government where the delays purportedly caused by the government were too intertwined with the delays attributable to the contractor). 55 Id. 17

19 For example, in The Tuller Constr. Co. v. United States, 56 the court denied delay damages upon a finding that independent delays to separate activities resulted in concurrent delay. In Tuller, the government delayed more than two months before supplying shop drawings for the equipment the government was furnishing, and the contractor was also delayed while waiting for approvals from the War Production Board. 57 In addition, during construction, the contractor s method for building an intake pipe in a river bed proved to be impracticable, and the work was delayed while the contractor employed an alternative method. 58 Despite finding the government and contractor-caused delays were separable, the court denied the contractor s claim for recovery of delay damages because, the evidence show[ed] that there would have been substantially the same delay in the completion of the job, if the government had been prompt in supplying the materials and drawings. 59 Even in light of the above case law, the surety should pursue all viable claims for time extensions, even if the surety will not receive additional monetary compensation resulting from the delays. As stated above, the surety is best positioned to mitigate and minimize damages if all time extensions are sought and granted. C. Brief Comparison of the Concurrent Delay Analysis to Changing Trends in the Case Law on Liquidated Damages The concurrent delay analysis discussed above has some similarities to the changing trends in the case law on liquidated damages. 60 Historically, contractors argued the rule against 56 The Tuller Constr. Co. v. United States, 118 Ct. Cl. 509 (1951). 57 Id. at Id. at Id. at For a more detailed discussion, see BRUNER & O CONNOR, supra note 2, at 15:70. 18

20 apportionment to defeat government claims for liquidated damages. 61 When employed by courts, the rule against apportionment prohibited the government from recovering under a contract s liquidated damages clause if the government was responsible for any delay to the project. 62 More recently, however, courts have criticized the rule against apportionment as harsh and outdated. 63 Courts are now moving toward the clear apportionment rule, an approach that permits the award of liquidated damages to obligees where the party seeking recovery can clearly apportion responsibility for delays to the critical path. 64 V. EVIDENTIARY ISSUES WITH A TERMINATED PRINCIPAL By the time the obligee declares a default, the principal is often out of business. The principal s office may be closed. The principal may have released its employees. The project documents may not be readily available for review. The surety is often faced with a situation where it does not have access to key project documentation or key personnel of the principal. Sometimes the principal s business is still a going concern, but the key employees of the principal are uncooperative. The surety will experience difficulty proving its principal s claims for time extensions, pursuing monetary damages for delays or damages arising during the 61 See, e.g., Acme Process Equip. v. United States, 347 F.2d 509 (Ct.Cl. 1965), rev d on other grounds, 385 U.S. 138 (1966) (holding that foregoing enforcement of the liquidated damages provision does not deprive the government of damages for the contractor s delay, rather, the government merely loses its right to insist on an artificial measure of damages when it is also responsible for the delay); Schmoll v. United States, 91 Ct.Cl. 1, 16 (1940) (annulling a liquidated damages provision because delays were attributable to both parties). 62 Id. 63 See, e.g., PCL Constr. Servs., Inc. v. United States, 53 Fed. Cl. 479, 485 (2002). 64 Id.; see also Cumberland Cas. & Sur. Co. v. United States, 82 Fed.Cl. 500 (2008) (citing Sauer, Inc. v. Danzig, 224 F.3d 1340 (Fed. Cir. 2000) and Essex Electro Eng rs v. Danzig, 224 F.3d 1283 (Fed. Cir. 2000) (holding that liquidated damages for delay should be parsed by responsibility between the parties)). 19

21 principal s tenure on the project, or pursuing the surety s and completing contractor s claims for time extensions and damages. If the surety anticipates litigation on any issue related to the default and termination, the surety will have to overcome multiple evidentiary obstacles. If not addressed upon the surety s election of its performance option under the bond, the surety may not position itself to prevail in subsequent litigation. The surety should seek the cooperation of the principal, and record the testimony of key personnel through recorded statements. If a key witness later proves to be unavailable for trial, or testifies but is unable to recall critical facts, the surety may be able to offer the prior recorded testimony as evidence. 65 Ultimately, the court is tasked with determining the competency, relevancy and admissibility of proffered evidence. 66 Since courts have exclusive power to determine the technical competency of evidence 67 and the personal knowledge of the witness, 68 courts have broad discretion to deny a motion to admit speculative evidence, unauthenticated evidence, or incomplete evidence. Authentication or identification of evidence is required as a condition precedent to its admissibility. 69 In situations where the surety has no cooperation from the principal, the surety will have to find alternate ways to authenticate and introduce the principal s business records to support the 65 FED. R. EVID. 613, 804(b)(1); see also, Walker v. Pepsi-Cola Bottling Co., 2000 WL at *5 (D.Del. August 10, 2000) (holding previously recorded testimony given as a witness at another hearing or in a deposition is admissible if the party or its predecessor in interest against whom the evidence is being offered was present). 66 See, e.g., FED. R. EVID , , FED. R. EVID. 601; see also, Bourjaily v. United States, 483 U.S. 171, 172 (1987) (holding that while the Rules of Evidence require the court to determine preliminary questions on the admissibility of evidence, the Rules of Evidence do not define the standard of proof). 68 FED. R. EVID FED. R. EVID. 901; see also, JOHN W. STRONG, MCCORMICK ON EVIDENCE 222 (5th ed. 1999) ( [P]roof of any circumstances which will support a finding that the writing is genuine will suffice to authenticate the writing. ). 20

22 surety s claims. The surety may have to authenticate the principal s business records through the adverse party. Alternatively, the surety may try to introduce key documentation through experts who have independently confirmed and authenticated the contents of the business records. 70 Generally, the surety can overcome these evidentiary hurdles; however, the surety must anticipate the time and costs to do so. VI. CONCLUSION A surety s entitlement to time extensions, and additional monetary compensation arising from those time extensions, are important for the surety to investigate and pursue. Upon takeover, the surety should conduct a thorough review and analysis of the project documentation, initial scope of work, scheduling analysis, approved change orders, pending change orders and remaining contract balances. By pursuing pending or wrongfully rejected claims for time extensions, the surety may be able to lessen financial loss arising from the principal s termination. In addition, by pursuing claims for time extensions discovered by the completing contractor, the surety can continue to mitigate the potential loss. Furthermore, the surety should always evaluate whether the identified claims for time extensions are compensable. 70 FED. R. EVID , 705; see also, Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579, 597 (1993) (holding expert testimony must rest[] on a reliable foundation and [be] relevant to the task at hand. ); United States v. Firishchak, 468 F.3d 1015, 1022 (7th Cir. 2006) (holding trial court did not abuse its discretion in permitting an Ukrainian Auxiliary Police historian to testify as to the authenticity of UAP documents). 21

23 About the Authors Tammy N. Giroux is a partner in the Surety & Fidelity Practice Group at Shumaker, Loop & Kendrick, LLP in Tampa, Florida. Ms. Giroux obtained her B.S. in Finance (cum laude) from Florida State University, and her J.D. (cum laude) from Stetson University College of Law. Ms. Giroux practices extensively in the area of surety and fidelity claims and commercial litigation. Doug Dearie is the Manager-Construction Services for Liberty Mutual Surety in Seattle, Washington. Mr. Dearie obtained his B.S. in Civil Engineering from Newark College of Engineering (NJIT), and has lectured widely in the area of surety bond litigation. 22

TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015

TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015 TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015 LOSS CONTROL STRATEGIES FOR THE SURETY PRIOR TO FORMAL NOTICE OF DEFAULT OR TERMINATION TAMMY N. GIROUX, ESQUIRE Shumaker,

More information

TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013

TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013 TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013 DON T BE PUT OFF BY SETOFF PRESENTED BY: Toby Pilcher The Hanover Insurance Group

More information

Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE

Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE 1 Contract Formation: These Terms and Conditions of Purchase (the "Terms and Conditions") apply to any purchases by Prufrex USA, Inc., its subsidiaries,

More information

INTERNATIONAL FIDELITY INSURANCE COMPANY,

INTERNATIONAL FIDELITY INSURANCE COMPANY, Page 1 2 of 35 DOCUMENTS INTERNATIONAL FIDELITY INSURANCE COMPANY, a foreign corporation, ALLEGHENY CASUALTY COMPANY, a foreign corporation, Plaintiffs-Counter Defendants-Appellees, versus AMERICARIBE-MORIARTY

More information

SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996

SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996 SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996 BID PACKAGES DETERMINING THE REMAINING SCOPE OF WORK TO COMPLETE AREAS OF CONCERN PRESENTED BY: William H. Ver Eecke,

More information

Time Extension Requests A Checklist 1

Time Extension Requests A Checklist 1 Time Extension Requests A Checklist 1 James G. Zack, Jr., CCM, CFCC, FAACEI, FRICS, PMP 2 Navigant Consulting, Inc. Mark A. Sgarlata 3 Watt Tieder Hoffar & Fitzgerald Joseph S. Guarino 4 Watt Tieder Hoffar

More information

What To Do With Performance Bonds When Projects Default

What To Do With Performance Bonds When Projects Default What To Do With Performance Bonds When Projects Default By Gary Strong January 18, 2018, 3:12 PM EST In today s economic climate, performance bonds are important for construction contracts. While performance

More information

CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I???

CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I??? CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS Or I don't want no ConsensusDOCS bond form or do I??? Deborah S. Griffin Gina A. Fonte Holland & Knight LLP Boston, MA 02116 Presented at

More information

Streamlined Arbitration Rules and Procedures

Streamlined Arbitration Rules and Procedures RESOLUTIONS, LLC s GUIDE TO DISPUTE RESOLUTION Streamlined Arbitration Rules and Procedures 1. Scope of Rules The RESOLUTIONS, LLC Streamlined Arbitration Rules and Procedures ("Rules") govern binding

More information

SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE St. Pete Beach, Florida th th MAY 4-5, 2006 PURSUIT AND PRESERVATION OF PRE AND POST DEFAULT CLAIMS AGAINST THE UNITED STATES GOVERNMENT

More information

Consolidated Arbitration Rules

Consolidated Arbitration Rules Consolidated Arbitration Rules THE LEADING PROVIDER OF ADR SERVICES 1. Applicability of Rules The parties to a dispute shall be deemed to have made these Consolidated Arbitration Rules a part of their

More information

CITY OF RICHMOND PERFORMANCE BOND

CITY OF RICHMOND PERFORMANCE BOND KNOW ALL MEN BY THESE PRESENTS: That place of business is located at CITY OF RICHMOND PERFORMANCE BOND, the Contractor ( Principal ) whose principal and ( Surety ) whose address for delivery of Notices

More information

PROSECUTION AND PROGRESS

PROSECUTION AND PROGRESS PROSECUTION AND PROGRESS 1.01 SUBLETTING OR ASSIGNMENT OF CONTRACT A. Work by Contractor: 1. The Contractor shall perform, with its own organization and forces, work amounting to no less than 30% of the

More information

National Patent Board Non-Binding Arbitration Rules TABLE OF CONTENTS

National Patent Board Non-Binding Arbitration Rules TABLE OF CONTENTS National Patent Board Non-Binding Arbitration Rules Rules Amended and Effective June 1, 2014 TABLE OF CONTENTS Important Notice...3 Introduction...3 Standard Clause...3 Submission Agreement...3 Administrative

More information

ARBITRATION RULES. Arbitration Rules Archive. 1. Agreement of Parties

ARBITRATION RULES. Arbitration Rules Archive. 1. Agreement of Parties ARBITRATION RULES 1. Agreement of Parties The parties shall be deemed to have made these rules a part of their arbitration agreement whenever they have provided for arbitration by ADR Services, Inc. (hereinafter

More information

NO. COA NORTH CAROLINA COURT OF APPEALS. Filed: 4 December Appeal by defendants from Amended Judgment entered 8 March

NO. COA NORTH CAROLINA COURT OF APPEALS. Filed: 4 December Appeal by defendants from Amended Judgment entered 8 March NO. COA12-636 NORTH CAROLINA COURT OF APPEALS Filed: 4 December 2012 SOUTHERN SEEDING SERVICE, INC., Plaintiff, v. Guilford County No. 09 CVS 12411 W.C. ENGLISH, INC.; LIBERTY MUTUAL INSURANCE COMPANY;

More information

Concurrent Delay The Owner s Newest Defense 1

Concurrent Delay The Owner s Newest Defense 1 Concurrent Delay The Owner s Newest Defense 1 James G. Zack, Jr., CCM, CFCC, FAACEI, FRICS, PMP 2 Emily R. Federico, PSP 3 ABSTRACT When owners impose liquidated damages at the end of a delayed project

More information

City of Malibu Request for Proposals (RFP) for Government Relations and Lobbying Services

City of Malibu Request for Proposals (RFP) for Government Relations and Lobbying Services City of Malibu Request for Proposals (RFP) for Government Relations and Lobbying Services INTRODUCTION The City of Malibu (City) is requesting proposals from firms to provide contracting services for government

More information

Graciano Corp. v Lanmark Group, Inc NY Slip Op 33388(U) December 28, 2018 Supreme Court, New York County Docket Number: /14 Judge: Eileen

Graciano Corp. v Lanmark Group, Inc NY Slip Op 33388(U) December 28, 2018 Supreme Court, New York County Docket Number: /14 Judge: Eileen Graciano Corp. v Lanmark Group, Inc. 2018 NY Slip Op 33388(U) December 28, 2018 Supreme Court, New York County Docket Number: 652750/14 Judge: Eileen Bransten Cases posted with a "30000" identifier, i.e.,

More information

ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE

ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE LIQUIDATED DAMAGES REVISITED Responses Available to the Surety Robert A. Koenig SHUMAKER, LOOP & KENDRICK, LLP 1000 Jackson Avenue Toledo,

More information

SOUTHERN CALIFORNIA EDISON COMPANY ENERGY SERVICE PROVIDER SERVICE AGREEMENT

SOUTHERN CALIFORNIA EDISON COMPANY ENERGY SERVICE PROVIDER SERVICE AGREEMENT Agreement Number: This Energy Service Provider Service Agreement (this Agreement ) is made and entered into as of this day of,, by and between ( ESP ), a organized and existing under the laws of the state

More information

Case 0:14-cv JIC Document 48 Entered on FLSD Docket 01/29/15 11:03:44 Page 1 of 9 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA

Case 0:14-cv JIC Document 48 Entered on FLSD Docket 01/29/15 11:03:44 Page 1 of 9 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA Case 0:14-cv-60963-JIC Document 48 Entered on FLSD Docket 01/29/15 11:03:44 Page 1 HILL YORK SERVICE CORPORATION, d/b/a Hill York, v. Plaintiff, CRITCHFIELD MECHANICAL, INC., Defendant. / UNITED STATES

More information

Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes)

Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes) Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes) Rules Amended and Effective October 1, 2013 Fee Schedule Amended and Effective June 1,

More information

ADR CODE OF PROCEDURE

ADR CODE OF PROCEDURE Last Revised 12/1/2006 ADR CODE OF PROCEDURE Rules & Procedures for Arbitration RULE 1: SCOPE OF RULES A. The arbitration Rules and Procedures ( Rules ) govern binding arbitration of disputes or claims

More information

AGREEMENT FOR PROFESSIONAL SERVICES

AGREEMENT FOR PROFESSIONAL SERVICES AGREEMENT FOR PROFESSIONAL SERVICES This Agreement is made and entered into as of [date] by and between the City of Malibu (hereinafter referred to as the "City"), and (hereinafter referred to as "Consultant").

More information

Purchase Agreement TERMS AND CONDITIONS PRICES PAYMENT AND PAYMENT TERMS. Bright Ideas. Better Solutions. Benchmark is Branch Automation.

Purchase Agreement TERMS AND CONDITIONS PRICES PAYMENT AND PAYMENT TERMS. Bright Ideas. Better Solutions. Benchmark is Branch Automation. Purchase Agreement The following terms and conditions shall apply to the sale of goods or products ( goods or products ) associated with your invoice: TERMS AND CONDITIONS The obligations and rights of

More information

CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv NKL

CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv NKL Page 1 CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv-04100-NKL UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF MISSOURI, CENTRAL DIVISION

More information

STATE OF MICHIGAN COURT OF APPEALS

STATE OF MICHIGAN COURT OF APPEALS STATE OF MICHIGAN COURT OF APPEALS NORTHLINE EXCAVATING, INC., Plaintiff-Appellee, FOR PUBLICATION October 15, 2013 9:05 a.m. v No. 304964 Livingston Circuit Court COUNTY OF LIVINGSTON LIVINGSTON LC No.

More information

COMPREHENSIVE JAMS COMPREHENSIVE ARBITRATION RULES & PROCEDURES

COMPREHENSIVE JAMS COMPREHENSIVE ARBITRATION RULES & PROCEDURES COMPREHENSIVE JAMS COMPREHENSIVE ARBITRATION RULES & PROCEDURES Effective October 1, 2010 JAMS COMPREHENSIVE ARBITRATION RULES & PROCEDURES JAMS provides arbitration and mediation services from Resolution

More information

AAA Healthcare. Payor Provider Arbitration Rules and Mediation Procedures. Available online at adr.org/healthcare

AAA Healthcare. Payor Provider Arbitration Rules and Mediation Procedures. Available online at adr.org/healthcare AAA Healthcare Payor Provider Arbitration Rules and Mediation Procedures Available online at adr.org/healthcare Rules Amended and Effective November 1, 2014 Rules Amended and Effective November 1, 2014.

More information

FIRST INDEMNITY OF AMERICA INSURANCE COMPANY INDEMNITY AGREEMENT

FIRST INDEMNITY OF AMERICA INSURANCE COMPANY INDEMNITY AGREEMENT FIRST INDEMNITY OF AMERICA INSURANCE COMPANY Agreement Number: Execution Date: Click here to enter text. Click here to enter text. INDEMNITY AGREEMENT DEFINITIONS: Surety: First Indemnity of America Insurance

More information

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ]

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ] EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT IRREVOCABLE STANDBY DESIGN-BUILD LETTER OF CREDIT ISSUER PLACE FOR PRESENTATION OF DRAFT APPLICANT BENEFICIARY [ ] [Name and address of banking institution

More information

INSTRUCTIONS TO BIDDERS Medical Center

INSTRUCTIONS TO BIDDERS Medical Center Revisions: Revisions were made to these Instructions to Bidders to conform to recent changes to the Code of Virginia and to changes in policy. Revised paragraphs are indicated by a vertic al line in the

More information

Purchase Agreement (Goods)

Purchase Agreement (Goods) Purchase Agreement (Goods) SLS SAMPLE DOCUMENT 06/30/17 This is a Purchase Agreement ( Agreement ), dated as of [month day, year] ( Effective Date ), between [ ] ( Client ) and ( Vendor ). BACKGROUND Client

More information

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS ICON DRILLING ABN 75 067 226 484 PURCHASE ORDER TERMS & CONDITIONS Acceptance of this offer is subject to the terms and conditions of this Agreement. Acceptance of materials, work or services, payment

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS OPINION BY ADMINISTRATIVE JUDGE DICUS ON RESPONDENT S MOTION TO DISMISS FOR LACK OF JURISDICTION

ARMED SERVICES BOARD OF CONTRACT APPEALS OPINION BY ADMINISTRATIVE JUDGE DICUS ON RESPONDENT S MOTION TO DISMISS FOR LACK OF JURISDICTION ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Hackney Group and ) Credit General Insurance Company ) ASBCA No. 51453 ) Under Contract No. N62472-96-C-3237 ) APPEARANCE FOR THE APPELLANT: APPEARANCES

More information

FORM 32 PERFORMANCE BOND UNDER SECTION 85.1 OF THE ACT Construction Act

FORM 32 PERFORMANCE BOND UNDER SECTION 85.1 OF THE ACT Construction Act FORM 32 PERFORMANCE BOND UNDER SECTION 85.1 OF THE ACT Construction Act No. (the Bond ) Bond Amount $ (name of the contractor*) as a principal, hereinafter [collectively] called the Contractor, and, THE

More information

International Construction Arbitration Alert

International Construction Arbitration Alert International Construction Arbitration Alert Concurrent Delay Is the English Court of Appeal s Clarification Conclusive? September 13, 2018 Key Points The Court of Appeal has held that a clause denying

More information

Guarantor additionally represents and warrants to Obligee as

Guarantor additionally represents and warrants to Obligee as GUARANTY THIS GUARANTY ( Guaranty ) is made as of the day of, 20, by, a corporation /limited liability company (strike whichever is inapplicable) formed under the laws of the State of and having a principal

More information

SETTLEMENT AGREEMENT AND RELEASE. This settlement agreement was executed by and between Plaintiffs Amelia Thompson

SETTLEMENT AGREEMENT AND RELEASE. This settlement agreement was executed by and between Plaintiffs Amelia Thompson SETTLEMENT AGREEMENT AND RELEASE I. Recitals. A. Introduction. This settlement agreement was executed by and between Plaintiffs Amelia Thompson and Monique Glenn-Leufroy (collectively, Named Plaintiffs

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) 1. Scope of Application and Interpretation 1.1 Where parties have agreed to refer their disputes

More information

Construction Industry Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Construction Disputes)

Construction Industry Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Construction Disputes) Construction Industry Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Construction Disputes) Rules Amended and Effective October 1, 2009 Fee Schedule Amended and Effective

More information

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION EDITION

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION EDITION [JURISDICTION] S AMENDMENTS TO AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION - 1997 EDITION This document modifies portions of the General Conditions of the Contract for Construction

More information

AGREEMENT FOR PHYSICIAN SERVICES RECITALS. B. The District owns and operates Hospital in, Washington (the "Hospital");

AGREEMENT FOR PHYSICIAN SERVICES RECITALS. B. The District owns and operates Hospital in, Washington (the Hospital); AGREEMENT FOR PHYSICIAN SERVICES This Agreement for Physician Services (the "Agreement") is made and entered into as of, by and between Public Hospital District No. of County, Washington (the "District"),

More information

General Terms of Contract

General Terms of Contract APPENDIX III General Terms of Contract GENERAL CONDITIONS OF CONTRACT 1. GENERAL PROVISIONS 1. 1 Definitions Unless the context otherwise requires, the following terms whenever used in this Contract have

More information

PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C.

PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C. PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C. Design-Build Institute of America Contract Documents LICENSE AGREEMENT

More information

SEMINOLE TRIBE OF FLORIDA

SEMINOLE TRIBE OF FLORIDA SEMINOLE TRIBE OF FLORIDA Tribal Court Small Claims Rules of Procedure Table of Contents RULE 7.010. TITLE AND SCOPE... 3 RULE 7.020. APPLICABILITY OF RULES OF CIVIL PROCEDURE... 3 RULE 7.040. CLERICAL

More information

TOHOPEKALIGA WATER AUTHORITY WATER, REUSE, AND WASTEWATER SYSTEM DEVELOPER'S SERVICE AGREEMENT

TOHOPEKALIGA WATER AUTHORITY WATER, REUSE, AND WASTEWATER SYSTEM DEVELOPER'S SERVICE AGREEMENT This Document Prepared by: David Thomas After Recording Return to: Theresa Hunter 951 Martin Luther King Blvd. Kissimmee, FL 32741 Parcel ID Number: TOHOPEKALIGA WATER AUTHORITY WATER, REUSE, AND WASTEWATER

More information

AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE) AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE) EJCDC C-520, Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Deletions by Engineer

More information

I, Accept this proposal and make a payment of $ to confirm my commitment.

I, Accept this proposal and make a payment of $ to confirm my commitment. This Solar Home Improvement Agreement (this Agreement ) is between Golden Gate Green Finance dba Golden Gate Power, California General and Electrical Contractor license number 1002922 ( Golden Gate Power,

More information

Differing Site Conditions

Differing Site Conditions Chapter Seven Differing Site Conditions Melissa A. Beutler and Christopher M. Burke 7.01 Introduction...114 7.02 Differing Site Condition Explained (Type I and Type II)...115 7.03 Claim for Extra Work

More information

CALIFORNIA CIVIL CODE SECTION

CALIFORNIA CIVIL CODE SECTION CALIFORNIA SECTION 8000-8848 8000. Unless the provision or context otherwise requires, the definitions in this article govern the construction of this part. 8002. "Admitted surety insurer" has the meaning

More information

Agreement to UOB Banker s Guarantee Terms and Conditions

Agreement to UOB Banker s Guarantee Terms and Conditions Agreement to UOB Banker s Guarantee Terms and Conditions In consideration of United Overseas Bank Limited (the Bank ) agreeing at the Applicant s request to issue the Banker s Guarantee, the Applicant

More information

JAMS International Arbitration Rules & Procedures

JAMS International Arbitration Rules & Procedures JAMS International Arbitration Rules & Procedures Effective September 1, 2016 JAMS INTERNATIONAL ARBITRATION RULES JAMS International and JAMS provide arbitration and mediation services from Resolution

More information

Request for Proposals for Homeless Outreach Services

Request for Proposals for Homeless Outreach Services Request for Proposals for Homeless Outreach Services Date Issued: March 4, 2019 Proposals must be received no later than 4:00 p.m. on Friday, April 12, 2019 at the following address: Attention: Susan Duenas

More information

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 WHAT IS A DEFAULT AND WHY DOES IT MATTER PRESENTED BY: Jarrod W. Stone, Esquire Manier

More information

Small Claims rules are covered in:

Small Claims rules are covered in: Small Claims rules are covered in: CCP 116.110-116.950 CHAPTER 5.5. SMALL CLAIMS COURT Article 1. General Provisions... 116.110-116.140 Article 2. Small Claims Court... 116.210-116.270 Article 3. Actions...

More information

SUBDIVISION IMPROVEMENT AGREEMENT. (Date of Subdivision Map Recordation: )

SUBDIVISION IMPROVEMENT AGREEMENT. (Date of Subdivision Map Recordation: ) SUBDIVISION IMPROVEMENT AGREEMENT Tract Map No.: (Date of Subdivision Map Recordation: ) THIS AGREEMENT is between the City of Fontana, a municipal corporation, County of San Bernardino, State of California

More information

ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL

ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL TABLE OF CONTENTS I. THE RULES AS PART OF THE ARBITRATION AGREEMENT PAGES 1.1 Application... 1 1.2 Scope... 1 II. TRIBUNALS AND ADMINISTRATION 2.1 Name

More information

TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Nashville, Tennessee th st APRIL 20 & 21, 2017 TO PAY OR TO PLAY: OPTIONS AVAILABLE TO THE SURETY: FINANCE OR TAKEOVER? PRESENTED BY:

More information

STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT )

STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT ) STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT ) 1. BASIS OF SALE 1.1 EXION Asia Pte Ltd ( EXION ) shall sell and the Purchaser shall purchase the Goods and/or Services in accordance with

More information

SETTLEMENT AGREEMENT AND RELEASE

SETTLEMENT AGREEMENT AND RELEASE SETTLEMENT AGREEMENT AND RELEASE This Settlement Agreement and Release ("Agreement"), effective as of the last date of execution below ("Effective Date"), is made by and between California River Watch,

More information

M. Stephen Turner, P.A., and J. Nels Bjorkquist, of Broad and Cassel, Tallahassee, for Appellant.

M. Stephen Turner, P.A., and J. Nels Bjorkquist, of Broad and Cassel, Tallahassee, for Appellant. IN THE DISTRICT COURT OF APPEAL FIRST DISTRICT, STATE OF FLORIDA TWIN OAKS AT SOUTHWOOD, LLC, v. Appellant, NOT FINAL UNTIL TIME EXPIRES TO FILE MOTION FOR REHEARING AND DISPOSITION THEREOF IF FILED CASE

More information

Wills and Trusts Arbitration RULES

Wills and Trusts Arbitration RULES Wills and Trusts Arbitration RULES Effective September 15, 2005 Introduction Standard Arbitration Clause Administrative Fees Wills and Trusts Arbitration Rules 1. Incorporation of These Rules into a Will

More information

Purchase Agreement (Services)

Purchase Agreement (Services) Purchase Agreement (Services) SLS SAMPLE DOCUMENT 06/30/17 This is a Purchase Agreement ( Agreement ), dated as of [month day, year] ( Effective Date ), between [ ] ( Client ) and ( Vendor ). BACKGROUND

More information

IC Chapter 3. Adjudicative Proceedings

IC Chapter 3. Adjudicative Proceedings IC 4-21.5-3 Chapter 3. Adjudicative Proceedings IC 4-21.5-3-1 Service of process; notice by publication Sec. 1. (a) This section applies to: (1) the giving of any notice; (2) the service of any motion,

More information

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT Case: 15-60683 Document: 00513486795 Page: 1 Date Filed: 04/29/2016 IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT Summary Calendar EDWARDS FAMILY PARTNERSHIP, L.P.; BEHER HOLDINGS TRUST,

More information

AGREEMENT FOR PROFESSIONAL SERVICES Contract No.

AGREEMENT FOR PROFESSIONAL SERVICES Contract No. AGREEMENT FOR PROFESSIONAL SERVICES Contract No. This AGREEMENT FOR PROFESSIONAL SERVICES ( AGREEMENT ) is made and entered into effective as of the day of, 20, by and between the CITY OF ALHAMBRA, a charter

More information

Rule 26. General Provisions Governing Discovery; Duty of Disclosure [ Proposed Amendment ]

Rule 26. General Provisions Governing Discovery; Duty of Disclosure [ Proposed Amendment ] Rule 26. General Provisions Governing Discovery; Duty of Disclosure [ Proposed Amendment ] (a) Required Disclosures; Methods to Discover Additional Matter. (1) Initial Disclosures. Except to the extent

More information

Re: JES Commercial, Inc. v. The Hanover Insurance Company Roanoke City Case No. CL16-108

Re: JES Commercial, Inc. v. The Hanover Insurance Company Roanoke City Case No. CL16-108 TWENTY-THIRD JUDICIAL CIRCUIT OF VIRGINIA WILLIAM D. BROADHURST, JUDGE ROANOKE C ITY COURTHOUSE 315 C H URCH AVENUE. S.W. P.O. BOX 211 ROANOKE. VIRGINIA 24002-02ll (540) 853-2051 FAX (540) 853-1040 COMMONWEALTH

More information

STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES

STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES JAMS STREAMLINED ARBITRATION RULES & PROCEDURES Effective JULY 15, 2009 STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES JAMS provides arbitration and mediation services from Resolution Centers

More information

ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES

ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES APPENDIX 3.8 ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES (Rules Amended and Effective June 1, 2009) (Fee Schedule Amended and Effective June 1, 2010) Article 1 a. Where parties have

More information

AVK UK LIMITED CONDITIONS OF SALE OF GOODS FROM WEBSITE

AVK UK LIMITED CONDITIONS OF SALE OF GOODS FROM WEBSITE General AVK UK LIMITED CONDITIONS OF SALE OF GOODS FROM WEBSITE PLEASE READ THESE TERMS CAREFULLY AND MAKE SURE THAT YOU UNDERSTAND THEM, BEFORE ORDERING ANY GOODS FROM OUR SITE. BECAUSE OF THE NATURE

More information

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules

More information

CHAPTER 4 ENFORCEMENT OF RULES

CHAPTER 4 ENFORCEMENT OF RULES 400. GENERAL PROVISIONS CHAPTER 4 ENFORCEMENT OF RULES 401. THE CHIEF REGULATORY OFFICER 402. BUSINESS CONDUCT COMMITTEE 402.A. Jurisdiction and General Provisions 402.B. Sanctions 402.C. Emergency Actions

More information

ALABAMA A&M UNIVERSITY Carter and Chambers Fire Alarm System(s) A. Project Identification: New Fire Alarm system(s) Carter/Chambers

ALABAMA A&M UNIVERSITY Carter and Chambers Fire Alarm System(s) A. Project Identification: New Fire Alarm system(s) Carter/Chambers ALABAMA A&M UNIVERSITY Carter and Chambers Fire Alarm System(s) SUMMARY PART 1 GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Work covered by the Contract Documents. 2. Time of Completion

More information

Warehouse Agreement. WHEREAS, Warehouse Operator is in the business of warehousing and storing goods; and

Warehouse Agreement. WHEREAS, Warehouse Operator is in the business of warehousing and storing goods; and Warehouse Agreement This Warehouse Agreement, dated as of [DATE] (this Agreement ), is entered into between [WAREHOUSE OPERATOR NAME], a [STATE OF ORGANIZATION] [TYPE OF ENTITY] ( Warehouse Operator )

More information

LOCAL RULES SUPERIOR COURT of CALIFORNIA, COUNTY of ORANGE DIVISION 3 CIVIL RULES

LOCAL RULES SUPERIOR COURT of CALIFORNIA, COUNTY of ORANGE DIVISION 3 CIVIL RULES DIVISION 3 CIVIL RULES Rule Effective Chapter 1. Civil Cases over $25,000 300. Renumbered as Rule 359 07/01/09 301. Classification 07/01/09 302. Renumbered as Rule 361 07/01/09 303. All-Purpose Assignment

More information

Information or instructions: Combined discovery requests, admissions, production of documents and interrogatories

Information or instructions: Combined discovery requests, admissions, production of documents and interrogatories Information or instructions: Combined discovery requests, admissions, production of documents and interrogatories 1. The practitioner may desire to combine Request for Admissions, Interrogatories and Request

More information

EXHIBIT WARRANTY BOND. (Address), hereinafter called Principal, and

EXHIBIT WARRANTY BOND. (Address), hereinafter called Principal, and EXHIBIT WARRANTY BOND ITEMS MDX PROCUREMENT/CONTRACT NO.: Bond No.: KNOW ALL PERSONS BY THESE PRESENTS: That we, (Name) of (Address), hereinafter called Principal, and (Name) of (Address), hereinafter

More information

INTERNATIONAL DISPUTE RESOLUTION PROCEDURES

INTERNATIONAL DISPUTE RESOLUTION PROCEDURES INTERNATIONAL DISPUTE RESOLUTION PROCEDURES (Including Mediation and Arbitration Rules) Rules Amended and Effective June 1, 2014 available online at icdr.org Table of Contents Introduction.... 5 International

More information

DEVELOPMENT AGREEMENT

DEVELOPMENT AGREEMENT DEVELOPMENT AGREEMENT THIS DEVELOPMENT AGREEMENT (this Agreement ), is made and entered into this day of, 2010 by and between the CITY OF WICHITA, KANSAS, a municipal corporation duly organized under the

More information

Home Foundation Subcontractor Services Agreement

Home Foundation Subcontractor Services Agreement Home Foundation Subcontractor Services Agreement This Packet Includes: 1. General Information 2. Instructions and Checklist 3. Step-by-Step Instructions 4. Home Foundation Subcontractor Services Agreement

More information

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS 1. Applicability. (a) These terms and conditions of sale (these "Terms") are the only terms which govern the sale of the goods ("Goods") by Tecogen Inc.

More information

PN /19/2012 DISPUTE RESOLUTION BOARD PROCESS

PN /19/2012 DISPUTE RESOLUTION BOARD PROCESS PN 108 10/19/2012 DISPUTE RESOLUTION BOARD PROCESS The Department s Dispute Resolution Board Process is based upon the partnering approach to construction administration and must be followed by the Contractor

More information

SEVES USA INC. PPC Insulators Division North America Purchase Order Terms & Conditions. Title and risk of loss. Governing Terms & Conditions.

SEVES USA INC. PPC Insulators Division North America Purchase Order Terms & Conditions. Title and risk of loss. Governing Terms & Conditions. SEVES USA INC. PPC Insulators Division North America Purchase Order Terms & Conditions Governing Terms & Conditions This Purchase Order ( Order ) constitutes the offer of Seves USA Inc. USA, Inc. ( Seves

More information

General Contractor shall provide their own dumpster. Dumpster shall be located in parking lot behind Gymnasium. Coordinate location with Owner.

General Contractor shall provide their own dumpster. Dumpster shall be located in parking lot behind Gymnasium. Coordinate location with Owner. ADDENDUM No. 1 Project: Carpet Replacement South Ripley Elementary Versailles, Indiana Project No: 1839.01 Date: October 12, 2018 This addendum is a part of the bid documents. Acknowledge receipt on the

More information

PROPOSAL BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 610 First Edition, 2015 Design-Build Institute of America Washington, D.C.

PROPOSAL BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 610 First Edition, 2015 Design-Build Institute of America Washington, D.C. PROPOSAL BOND FOR DESIGN-BUILD PROJECTS Document No. 610 First Edition, 2015 Design-Build Institute of America Washington, D.C. Design-Build Institute of America Contract Documents LICENSE AGREEMENT By

More information

GUARANTY OF PERFORMANCE AND COMPLETION

GUARANTY OF PERFORMANCE AND COMPLETION EXHIBIT C-1 GUARANTY OF PERFORMANCE AND COMPLETION This GUARANTY OF PERFORMANCE AND COMPLETION ( Guaranty ) is made as of, 200, by FLUOR CORPORATION, a Delaware corporation (the Guarantor ), to the VIRGINIA

More information

Bid Addendum #1 Bid # 13/14-01FA: Furniture and Equipment Bid Issued March 19, 2014

Bid Addendum #1 Bid # 13/14-01FA: Furniture and Equipment Bid Issued March 19, 2014 Bid Addendum #1 Bid # 13/14-01FA: Issued March 19, 2014 *This addendum forms a part of the Agreement documents and modifies the original bid documents. The following revisions, clarifications, deletions

More information

Federal Rules of Civil Procedure

Federal Rules of Civil Procedure 1 of 7 10/10/2005 11:14 AM Federal Rules of Civil Procedure collection home tell me more donate search V. DEPOSITIONS AND DISCOVERY > Rule 26. Prev Next Notes Rule 26. General Provisions Governing Discovery;

More information

CLEARING MEMBERSHIP AGREEMENT DATED LCH.CLEARNET LIMITED. and. ("the Firm") Address of the Firm

CLEARING MEMBERSHIP AGREEMENT DATED LCH.CLEARNET LIMITED. and. (the Firm) Address of the Firm CLEARING MEMBERSHIP AGREEMENT DATED LCH.CLEARNET LIMITED and ("the Firm") Address of the Firm THIS AGREEMENT is made on the date stated above BETWEEN the Firm and LCH.CLEARNET LIMITED ("the Clearing House"),

More information

TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013

TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013 TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013 DRAFTING TAKEOVER AGREEMENTS TO MINIMIZE SURETY'S RISK PRESENTED BY: Rachel Walsh

More information

Spark Energy, LLC RESIDENTIAL AND SMALL COMMERCIAL CUSTOMER DISCLOSURE STATEMENT

Spark Energy, LLC RESIDENTIAL AND SMALL COMMERCIAL CUSTOMER DISCLOSURE STATEMENT Spark Energy, LLC RESIDENTIAL AND SMALL COMMERCIAL CUSTOMER DISCLOSURE STATEMENT Price Plan Fixed Rate 8.80 per kwh PRICE PROTECT INSTANT 12 Monthly Administrative Fee $0.0 Term of Agreement Customer Rescind

More information

1:14-cv LJO-GSA UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF CALIFORNIA U.S. Dist. LEXIS 57467

1:14-cv LJO-GSA UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF CALIFORNIA U.S. Dist. LEXIS 57467 Page 1 AMERICAN CONSTRUCTION & ENVIRONMENTAL SERVICES., a Nevada Corporation, Plaintiff, v. TOTAL TEAM CONSTRUCTION SERVICES, INC., a California corporation; TRAVELERS CASUALTY & SURETY COMPANY OF AMERICA,

More information

SCHOOL FACILITIES MITIGATION AGREEMENT

SCHOOL FACILITIES MITIGATION AGREEMENT SCHOOL FACILITIES MITIGATION AGREEMENT This ( Agreement ) is made effective as of October 25, 2016 ( Effective Date ) by and between the Redlands Unified School District ( District ), a public school district

More information

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS 1. Applicability. 2. Delivery. GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS a. These terms and conditions of sale (these "Terms") are the only terms which govern the sale of the goods ("Goods") by

More information

UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA CHARLOTTE DIVISION CIVIL ACTION NO: 3:07-CV DCK

UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA CHARLOTTE DIVISION CIVIL ACTION NO: 3:07-CV DCK United States Surety v. Hanover R.S. Limited Partnership et al Doc. 27 UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA CHARLOTTE DIVISION CIVIL ACTION NO: 3:07-CV-00381-DCK UNITED

More information

STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AND BOARD OF TRUSTEES OF THE INTERNAL IMPROVEMENT TRUST FUND OF THE STATE OF FLORIDA

STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AND BOARD OF TRUSTEES OF THE INTERNAL IMPROVEMENT TRUST FUND OF THE STATE OF FLORIDA STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AND BOARD OF TRUSTEES OF THE INTERNAL IMPROVEMENT TRUST FUND OF THE STATE OF FLORIDA STATE OF FLORIDA DEPARTMENT ) IN THE OFFICE OF THE OF ENVIRONMENTAL

More information

-against- C. RYAN EBCOM/H&G LLC SHORT FORM ORDER

-against- C. RYAN EBCOM/H&G LLC SHORT FORM ORDER ---------------------------------------------------------------------------------- s; SHORT FORM ORDER SUPREME COURT STATE OF NEW YORK Present: HON. JOHN P. DUNNE. Justice TRIAL/lAS, PART 8 C. RYAN EBCOM/H&G

More information