What To Do With Performance Bonds When Projects Default

Size: px
Start display at page:

Download "What To Do With Performance Bonds When Projects Default"

Transcription

1 What To Do With Performance Bonds When Projects Default By Gary Strong January 18, 2018, 3:12 PM EST In today s economic climate, performance bonds are important for construction contracts. While performance bonds provide some security to subcontractors who are hired by the contractor as well as the owner who pays the contractor, this security is not guaranteed as sureties have surety defenses that provide a surety with an opportunity to disclaim coverage under the performance bond. This article will focus up what are a performance bond surety s options when there is a project default and what types of unique defenses the performance bond surety can use to its benefit. Gary Strong Before one delves into performance bonds, a brief summary of suretyship is necessary. Suretyship is distinguishable from insurance. The suretyship relationship is a three-party relationship (principal, oblige and surety). The principal is the primary obligor who performs contractual obligations (e.g. the contractor on a construction project). The obligee is the entity that enters into a contract with the principal and is the recipient of the obligations (e.g. project owner or governmental unit on a construction project). The surety is the secondary obligor which guarantees the principal s obligations will be performed.[1] Surety s Options During Default Once the project owner, whether it be public or private, has formally issued its declaration holding the principal in default, the surety has several options: 1) fund the principal to completion, 2) perform the work itself, 3) tender a completion contractor, or 4) tender payment to the owner.[2] Option number one (i.e. financing) involves paying the principal s bills to completion. This is

2 typically done when the project is nearing completion. This option saves time and expense of hiring a new construction manager and hopefully will keep the costs within the remaining contract balance. Generally speaking, if there is a project default and a replacement contractor is hired, the costs will increase for the basic reason the completion contractor(s) know full well that the project owner needs the project completed as soon as possible. In the second option, the surety performs the work itself by executing a takeover agreement with the owner and retaining its own completion contractor to complete the work. This option also is typically chosen where the project is close to being completed. This option is sometimes considered more advantageous to the surety because the surety retains more control on the project and gains the additional security of another surety bonding the completion contractor. The third option is for the surety to tender a completion construction manager / contractor to the owner. Here, the surety will obtain independent bids, usually bonded by another surety. The main difference between option two and three is that in the latter the project owner has more involvement. Once the bidder is awarded the contract, the surety allows the owner and any of its representative to direct the replacement contractor. The fourth option is where the surety buys back the bond. Here the surety will tender payment of the cost to complete less remaining contract balance but only up to the penal sum, in return for a fill release by the owner. This is typically done where the net cost to complete exceeds the penal sum of the performance bond. This option is rarer than the others because buying back the bond could affect the surety s indemnification rights against its principal and indemnitor(s). Performance Bond Defenses The liability of a surety under a performance bond is not triggered unless there is a default by the principal.[3] Therefore, the bond duration has been deemed to extend only to the point of substantial completion... at which point the owner is determined to have received performance substantially as bargained for and thus is not legally justified in terminating the bonded contract for default. [4] Upon the owner s termination of the contractor for default and subsequent demand under the surety s performance bond, the surety is entitled to utilize the remaining contract

3 balances to complete the contract work. Alternatively, the surety may use the contract balances to offset an owner s claim for its own completion costs. Essentially, the surety relies upon the bonded contract funds as collateral security against its corresponding loss and expense. Thus, where an owner has prematurely or improperly depleted contract funds prior to involving the surety, the surety can assert a claim for overpayment and/or the related defense of impairment of collateral. Generally, a surety may assert an overpayment claim or defense when the bond obligee has improperly or prematurely depleted the contract balance prior to the surety s involvement. Often, this occurs when a project owner releases payments to the bonded contractor in contravention of an express contractual provision, such as provision requiring the owner to retain a certain percentage of the contract funds pending the contractor s satisfaction of certain conditions.[5] Overpayment may also occur where the obligee pays for patently defective, noncomplaint and incomplete work, including work that has not actually progressed to the extent that progress payments have been made e.g., where 80 percent of the contract funds has been paid to the contractor though only 40 percent of the contract work has been completed.[6] Under the doctrine of impairment, where there has been an overpayment, the surety is generally entitled to a discharge from liability.[7] One way in which a surety may prevail on such defense occurs where it can prove that the obligee has materially modified the bonded contract, increasing the surety s risk. Based upon the nature and extent by which its risk have been increased by such a modification e.g., whether the increased risks are measureable the surety may be entitled to either a complete or pro tanto discharge of its bond obligations.[8] The surety may likewise obtain a pro tanto discharge where it has been prejudiced by the obligee s depletion of contract funds through premature payments or overpayments in contravention of the terms of the bonded contract. When seeking only a discharge from bond liability, the surety asserts overpayment as a defense. Another defense that a performance bond surety can assert is that based upon a material alteration to the contract between obligee and contractor. A material alteration is a nonconsensual increase of the surety s risk by some act of the obligee that changes the bonded contract.[9] Yet not every nonconsensual act qualifies a material alteration. The change must represent a material, substantial departure from the original risk, so that a

4 reasonable person would either have not undertaken the risk at all, or would have charged a greater premium.[10] Examples of material alterations include changing the project from building a warehouse to building a residential building or hospital, adding or deleting an entire floor, imposing an inordinate amount of additive and deductive change orders, or failure to obtain lien waivers.[11] Examples of nonmaterial alterations including changing the location of the building by a few inches or feet, adding a basement and failure of the owner to obtain builder s risk insurance.[12] Therefore, given the subjective standard of determining if a material alteration exists, this is a fact dependent inquiry often to be decided by a jury. Conclusion While in many instances, certain defenses can allow the surety to disclaim coverage, this usually would require the surety to go through a long and lengthy litigation to prove its case. When asserting its defenses, the surety needs to sustain its burden of proof both as to the defense itself and also that the event giving rise to that defense caused actual prejudice to the surety. The actual prejudice to the surety is something that differs on a case by case basis. Gary Strong is a partner with Seiger Gfeller Laurie LLP. His practice is focused on the areas of construction defect defense and professional liability defense. The opinions expressed are those of the author(s) and do not necessarily reflect the views of the firm, its clients, or Portfolio Media Inc., or any of its or their respective affiliates. This article is for general information purposes and is not intended to be and should not be taken as legal advice. [1] Restatement (Third) of Suretyship and Guarantee 11, (1996). [2] United States Fid. & Guar. Co. v. Braspetro Oil Servs. Co., 369 F.3d 34, 67 (2nd Cir. 2004); International Fidelity Ins. Co. v. United States, 25 Cl. Ct. 469, 479 (1992); Granite Computer Leasing Corp. v. Travelers Indem. Co., 894 F.2d 547, 552 (2nd Cir. 1990); [3] Marilyn Klinger, et. al., Ch. 6, Contract Performance Bonds, The Law of Suretyship 81,

5 109 (Edward G. Gallagher ed., 2d ed., Am. Bar. Ass n 2000). [4] 4 Philip L. Bruner & Patrick J. O Connor, Jr., Bruner & O Connor on Construction Law 12:9 (West 2002 & Supp. 2008). [5] Nat l Sur. Corp. v. United States, 118 F.3d 1542 (Fed. Cir. 1997). [6] Blackfeet Tribe of the Blackfeet Indian Reservation v. Blaze Constr. Inc., 108 F. Supp.2d 1122 (D. Mont. 2000); United Pacific Insurance Co. v. United States, 16 Cl. Ct. 555 (1989) [7] Restatement (Third) of Suretyship and Guaranty. 37, [8] Walsh Const. Co. v. Egan, 542 N.Y.S.2d 471 (Albany Cty 1989); Transamerica Insurance Co. v. City of Kennewick, 785 F.2d 660 (9th Cir. 1986); American Fidelity Fire Insurance Co. v. Pavia-Byrne Engineering Corp., 393 So. 2d 830 (La. Ct. App. 2d Cir. 1981), writ denied, 397 So. 2d 1362 (La. 1981); William Aupperle & Sons Inc. v. American Indemnity Co., 75 Ill.App.3d 722 (3d Dist. 1979). [9] Midland Steel Warehouse Corp. v. Godinger Silver Art Ltd., 275 A.D.2d 341 (1st Dep t 2000); Hartford Fire Ins. Co. v. Facilities Development Corp., 249 A.D.2d 765 (3d Dep t 1998). [10] Id. [11] The Law of Suretyship, 2d edition at (American Bar Ass n 2000). [12] Id.

You Have to Be Kidding Me!

You Have to Be Kidding Me! You Have to Be Kidding Me! What Is the Extent of the Performance Bond Obligee s Obligations to the Surety? David D. Gilliss Pike & Gilliss LLC 600 Washington Ave Ste 303 Towson, MD 21204 Bruce W. Kahn

More information

TWENTY THIRD ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE SEPTEMBER 20th - 21st, 2012

TWENTY THIRD ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE SEPTEMBER 20th - 21st, 2012 TWENTY THIRD ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE SEPTEMBER 20th - 21st, 2012 OVERPAYMENT CLAIMS IN LIGHT OF RECENT FEDERAL AND STATE DECISIONS: IT'S NOT OVER PRESENTED BY: CHRISTOPHER

More information

INTERNATIONAL FIDELITY INSURANCE COMPANY,

INTERNATIONAL FIDELITY INSURANCE COMPANY, Page 1 2 of 35 DOCUMENTS INTERNATIONAL FIDELITY INSURANCE COMPANY, a foreign corporation, ALLEGHENY CASUALTY COMPANY, a foreign corporation, Plaintiffs-Counter Defendants-Appellees, versus AMERICARIBE-MORIARTY

More information

CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv NKL

CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv NKL Page 1 CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv-04100-NKL UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF MISSOURI, CENTRAL DIVISION

More information

TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015

TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015 TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015 LOSS CONTROL STRATEGIES FOR THE SURETY PRIOR TO FORMAL NOTICE OF DEFAULT OR TERMINATION TAMMY N. GIROUX, ESQUIRE Shumaker,

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS OPINION BY ADMINISTRATIVE JUDGE DICUS ON RESPONDENT S MOTION TO DISMISS FOR LACK OF JURISDICTION

ARMED SERVICES BOARD OF CONTRACT APPEALS OPINION BY ADMINISTRATIVE JUDGE DICUS ON RESPONDENT S MOTION TO DISMISS FOR LACK OF JURISDICTION ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Hackney Group and ) Credit General Insurance Company ) ASBCA No. 51453 ) Under Contract No. N62472-96-C-3237 ) APPEARANCE FOR THE APPELLANT: APPEARANCES

More information

TWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina st nd APRIL 21 & 22, 2016 A SURETY'S RIGHT TO SETTLE CLAIMS OVER A PRINCIPAL'S OBJECTION PRESENTED BY: Amy

More information

In the United States Court of Federal Claims

In the United States Court of Federal Claims In the United States Court of Federal Claims No. 14-84C (Filed: November 19, 2014 FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, et al. v. Plaintiffs, THE UNITED STATES OF AMERICA, Defendant. Tucker Act;

More information

2. Bond amount expressed as the financial limit of that obligation;

2. Bond amount expressed as the financial limit of that obligation; 12:13 BRUNER & O CONNOR ON CONSTRUCTION LAW 2. Bond amount expressed as the financial limit of that obligation; 3. Duration of the bond obligation; 4. Stated trigger of the surety s performance bond liability;

More information

TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013

TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013 TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013 DON T BE PUT OFF BY SETOFF PRESENTED BY: Toby Pilcher The Hanover Insurance Group

More information

INTERNATIONAL MUNICIPAL LAWYERS ASSOCIATION IMLA. Construction Law and Claims for. The Municipal Lawyer. Tuesday. January 7,2008

INTERNATIONAL MUNICIPAL LAWYERS ASSOCIATION IMLA. Construction Law and Claims for. The Municipal Lawyer. Tuesday. January 7,2008 INTERNATIONAL MUNICIPAL LAWYERS ASSOCIATION IMLA Program: Construction Law and Claims for The Municipal Lawyer Tuesday. January 7,2008 Title: Defaults/Surety/Termination Issues By Presenter: John P. Markovs

More information

TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Nashville, Tennessee th st APRIL 20 & 21, 2017 TO PAY OR TO PLAY: OPTIONS AVAILABLE TO THE SURETY: FINANCE OR TAKEOVER? PRESENTED BY:

More information

TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater Beach, Florida RD TH APRIL 23 & 24, 2015 PRE-LOSS RECOVERY STRATEGIES PRESENTED BY: T. Bennett Acuff Erik P. Raines Hill Ward

More information

Case No UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF MICHIGAN, SOUTHERN DIVISION U.S. Dist.

Case No UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF MICHIGAN, SOUTHERN DIVISION U.S. Dist. Page 1 THE LASALLE GROUP, INC., Plaintiff, v. JST PROPERTIES, L.L.C., d/b/a GULF COAST CONSTRUCTION, L.L.C., and AMERICAN CONTRACTORS INDEMNITY COMPANY, Defendants. Case No. 10-14380 UNITED STATES DISTRICT

More information

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD January 8, 2018

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD January 8, 2018 SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD January 8, 2018 Bankruptcy: The Surety s Proof of Claim (MIKE) This is the third

More information

TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013

TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013 TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013 DRAFTING TAKEOVER AGREEMENTS TO MINIMIZE SURETY'S RISK PRESENTED BY: Rachel Walsh

More information

CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I???

CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I??? CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS Or I don't want no ConsensusDOCS bond form or do I??? Deborah S. Griffin Gina A. Fonte Holland & Knight LLP Boston, MA 02116 Presented at

More information

FIDELITY AND GUAR. INS. UNDERWRITERS

FIDELITY AND GUAR. INS. UNDERWRITERS FIDELITY AND GUAR. INS. UNDERWRITERS v. U.S. Cite as 119 Fed.Cl. 195 (2014) 4. United States O113.12(2) FIDELITY AND GUARANTY INSUR- ANCE UNDERWRITERS, et al., Plaintiffs, v. The UNITED STATES of America,

More information

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017 SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017 SURETY CASE LAW UPDATE WHAT WE HAVE FOUND INTERESTING OVER THE

More information

Chapter 8. Bond Requirements. Marilyn Klinger Shannon J. Briglia Kevin P. Gilliland. I. Introduction

Chapter 8. Bond Requirements. Marilyn Klinger Shannon J. Briglia Kevin P. Gilliland. I. Introduction Chapter 8 Bond Requirements Marilyn Klinger Shannon J. Briglia Kevin P. Gilliland Lauren P. McLaughlin I. Introduction Construction project owners, particularly public owners, desire performance guarantees

More information

SURETY TODAY PRESENTATION. Given by Michael A. Stover Wright, Constable & Skeen, LLP Baltimore, MD May 14, 2018 THE SURETY S RESERVATION OF RIGHTS

SURETY TODAY PRESENTATION. Given by Michael A. Stover Wright, Constable & Skeen, LLP Baltimore, MD May 14, 2018 THE SURETY S RESERVATION OF RIGHTS SURETY TODAY PRESENTATION Given by Michael A. Stover Wright, Constable & Skeen, LLP Baltimore, MD May 14, 2018 THE SURETY S RESERVATION OF RIGHTS We all do it. It s practically instinctive. We don t even

More information

THIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002

THIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002 THIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002 JEWELS IN THE INDEMNITY AGREEMENT, AND A LUMP OF COAL PRESENTED BY: JOHN V. BURCH, ESQ. BOVIS, KYLE & BURCH,

More information

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater, Florida th st APRIL 30 & MAY 1, 2009 BACK TO THE FUTURE: HAS BRAMBLE REVIVED THE A311 BONDS AND DO WE REALLY WANT TO GO THERE?

More information

6 of 75 DOCUMENTS. RLI INSURANCE COMPANY, Plaintiff, v. INDIAN RIVER SCHOOL DISTRICT, EDIS COMPANY, and BECKER MORGAN GROUP, Defendants.

6 of 75 DOCUMENTS. RLI INSURANCE COMPANY, Plaintiff, v. INDIAN RIVER SCHOOL DISTRICT, EDIS COMPANY, and BECKER MORGAN GROUP, Defendants. Page 21 6 of 75 DOCUMENTS RLI INSURANCE COMPANY, Plaintiff, v. INDIAN RIVER SCHOOL DISTRICT, EDIS COMPANY, and BECKER MORGAN GROUP, Defendants. Civil Action No. 05-858-JJF UNITED STATES DISTRICT COURT

More information

Cont Casualty Co v. Fleming Steel Co

Cont Casualty Co v. Fleming Steel Co 2011 Decisions Opinions of the United States Court of Appeals for the Third Circuit 7-25-2011 Cont Casualty Co v. Fleming Steel Co Precedential or Non-Precedential: Non-Precedential Docket No. 10-4524

More information

KNOW YOUR BOND BEFORE YOU SIGN

KNOW YOUR BOND BEFORE YOU SIGN by Mark H. McCallum and Robert J. Duke...an important part of the surety underwriting process is to know and understand the terms of the construction contract. KNOW YOUR BOND BEFORE YOU SIGN A contractor

More information

In these difficult economic times, well-drafted guaranties are a hedge against a

In these difficult economic times, well-drafted guaranties are a hedge against a WINNING GUARANTIES In these difficult economic times, well-drafted guaranties are a hedge against a borrower s bankruptcy filing or the return of damaged collateral. Under a properly crafted guaranty,

More information

Section: FN (Finance) Effective Date: July 1, 2011

Section: FN (Finance) Effective Date: July 1, 2011 Section: FN (Finance) Effective Date: July 1, 2011 Policy Type: Company Wide Revision Date(s): POLICY:. The Rural/Metro Corporation Surety Bond Policy and Procedure has been developed by the Chief Financial

More information

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM MERCHANTS BONDING COMPANY (MUTUAL) MERCHANTS NATIONAL BONDING INC. P.O. Box 14498 Des Moines iowa 50306-3498 Phone (800) 678-8171 FAX (515) 243-3854 GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS

More information

TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Nashville, Tennessee th st APRIL 20 & 21, 2017 RISKY BUSINESS: IMPAIRMENT OF SURETYSHIP, AND THE RESTATEMENT PRESENTED BY: GREGORY R.

More information

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM MERCHANTS BONDING COMPANY (MUTUAL) MERCHANTS NATIONAL BONDING, INC. P.O. Box 14498, Des Moines, iowa 50306-3498 Phone (800) 678-8171 FAX (515) 243-3854 GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS

More information

Bullet Proof Guaranties

Bullet Proof Guaranties Bullet Proof Guaranties David M. Mannion, Esq. DMannion@BlakeleyLLP.com Blakeley LLP 54 W. 40th Street New York, NY 10018 V. (917) 472-9587 F. (949) 260-0613 www.blakeleyllp.com New York Los Angeles Orange

More information

Surety Bad Faith after PSE Consulting: An Implicit Bar to Indemnification

Surety Bad Faith after PSE Consulting: An Implicit Bar to Indemnification Surety Bad Faith after PSE Consulting: An Implicit Bar to Indemnification By Frederick E. Hedberg and Nicole E. Liguori Frederick E. Hedberg In the construction industry, parties to general agreements

More information

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 29, 2012 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 29, 2012 Session IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 29, 202 Session ERIE INSURANCE EXCHANGE v. GARY ROSE, INDIVIDUALLY AND D/B/A AMERICAN MASONRY AND CAPITAL BUILDERS, LLC Appeal from the Chancery Court

More information

Assembly Bill No. 125 Committee on Judiciary

Assembly Bill No. 125 Committee on Judiciary - Assembly Bill No. 125 Committee on Judiciary CHAPTER... AN ACT relating to constructional defects; enacting provisions governing the indemnification of a controlling party by a subcontractor for certain

More information

Availability of Surety and Insurance Upon Completion and Beyond

Availability of Surety and Insurance Upon Completion and Beyond American Bar Association Forum on the Construction Industry Availability of Surety and Insurance Upon Completion and Beyond F. Malcolm Cunningham, Jr. Cunningham Law Firm, P.A. 400 Australian Avenue, Suite

More information

SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996

SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996 SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996 BID PACKAGES DETERMINING THE REMAINING SCOPE OF WORK TO COMPLETE AREAS OF CONCERN PRESENTED BY: William H. Ver Eecke,

More information

SOURCE ONE SURETY, LLC.

SOURCE ONE SURETY, LLC. SOURCE ONE SURETY, LLC. 15233 VENTURA BOULEVARD, SUITE 500 SHERMAN OAKS, CA 91403 GENERAL INDEMNITY AGREEMENT THIS General Agreement of Indemnity (hereinafter called Agreement ), is made and entered into

More information

S17G1472. IN RE: ESTATE OF GLADSTONE. This appeal stems from the Forsyth County Probate Court s finding that

S17G1472. IN RE: ESTATE OF GLADSTONE. This appeal stems from the Forsyth County Probate Court s finding that In the Supreme Court of Georgia Decided: May 5, 2018 S17G1472. IN RE: ESTATE OF GLADSTONE. BOGGS, Justice. This appeal stems from the Forsyth County Probate Court s finding that Emanuel Gladstone breached

More information

Construction Law Newsletter

Construction Law Newsletter Construction Law Newsletter Published by the Section on Construction Law of the Oregon State Bar ISSUE No. 17 December, 2000 SURETY BONDS AND INDEMNITY AGREEMENTS: ARE YOU STILL ON THE HOOK? Howard W.

More information

Should the Surety Stand on Its Equitable Subrogation Rights or File Its Indemnity Agreement under the Uniform Commercial Code?

Should the Surety Stand on Its Equitable Subrogation Rights or File Its Indemnity Agreement under the Uniform Commercial Code? Nebraska Law Review Volume 69 Issue 3 Article 4 1990 Should the Surety Stand on Its Equitable Subrogation Rights or File Its Indemnity Agreement under the Uniform Commercial Code? Richard W. Smith Woods

More information

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 SURETY LOSS: METHODS FOR SEEKING REIMBURSEMENT PRESENTED BY: Jeffrey S. Price Manier

More information

FORM 32 PERFORMANCE BOND UNDER SECTION 85.1 OF THE ACT Construction Act

FORM 32 PERFORMANCE BOND UNDER SECTION 85.1 OF THE ACT Construction Act FORM 32 PERFORMANCE BOND UNDER SECTION 85.1 OF THE ACT Construction Act No. (the Bond ) Bond Amount $ (name of the contractor*) as a principal, hereinafter [collectively] called the Contractor, and, THE

More information

-against- C. RYAN EBCOM/H&G LLC SHORT FORM ORDER

-against- C. RYAN EBCOM/H&G LLC SHORT FORM ORDER ---------------------------------------------------------------------------------- s; SHORT FORM ORDER SUPREME COURT STATE OF NEW YORK Present: HON. JOHN P. DUNNE. Justice TRIAL/lAS, PART 8 C. RYAN EBCOM/H&G

More information

TORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA. Great American Insurance Company v. General Builders, Inc.

TORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA. Great American Insurance Company v. General Builders, Inc. TORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA by Sharon A. Parker, Associate* Construction in Las Vegas is booming. There are currently over 100 major construction projects at various stages

More information

CONTRACT FOR ROOF REMOVAL AND REPLACEMENT - Milford Middle School

CONTRACT FOR ROOF REMOVAL AND REPLACEMENT - Milford Middle School CONTRACT FOR ROOF REMOVAL AND REPLACEMENT - Milford Middle School THIS AGREEMENT made this day of, 2013 between the Milford School District, a New Hampshire school district having a usual place of business

More information

ELEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE

ELEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE ELEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE Financing the Principal - Panel Discussion (including an analysis of the circumstances under which a surety would consider financing a principal,

More information

SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE St. Pete Beach, Florida th th MAY 4-5, 2006 PURSUIT AND PRESERVATION OF PRE AND POST DEFAULT CLAIMS AGAINST THE UNITED STATES GOVERNMENT

More information

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION Case: 4:18-cv-00203-CDP Doc. #: 48 Filed: 08/28/18 Page: 1 of 13 PageID #: 788 UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION LIBERTY MUTUAL INSURANCE ) COMPANY, ) ) Plaintiff,

More information

What You Should Know About General Agreements of Indemnity and Why You Should Know It

What You Should Know About General Agreements of Indemnity and Why You Should Know It What You Should Know About General Agreements of Indemnity and Why You Should Know It Summary When a contractor (for purposes of this discussion, contractor includes subcontractor) first seeks surety credit,

More information

The Law of Construction Bonds in Arkansas: A Review

The Law of Construction Bonds in Arkansas: A Review University of Arkansas at Little Rock Law Review Volume 9 Issue 2 Article 4 1986 The Law of Construction Bonds in Arkansas: A Review David G. Paul Follow this and additional works at: http://lawrepository.ualr.edu/lawreview

More information

The Troubled Public Construction Project: When is it Time to Call in the Surety?

The Troubled Public Construction Project: When is it Time to Call in the Surety? City Attorneys Department League of California Cities Annual Conference October 6, 2005 The Troubled Public Construction Project: When is it Time to Call in the Surety? Michael N. Conneran, Esq. Hanson,

More information

Case MFW Doc 120 Filed 08/29/18 Page 1 of 11 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE.

Case MFW Doc 120 Filed 08/29/18 Page 1 of 11 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE. Case 18-11795-MFW Doc 120 Filed 08/29/18 Page 1 of 11 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE In re: RM Holdco LLC, et al., 1 Debtors. Chapter 11 Case No. 18-11795 (MFW Jointly

More information

UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA CHARLOTTE DIVISION CIVIL ACTION NO: 3:07-CV DCK

UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA CHARLOTTE DIVISION CIVIL ACTION NO: 3:07-CV DCK United States Surety v. Hanover R.S. Limited Partnership et al Doc. 27 UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA CHARLOTTE DIVISION CIVIL ACTION NO: 3:07-CV-00381-DCK UNITED

More information

Strickland v. Arch Ins. Co.

Strickland v. Arch Ins. Co. Neutral As of: January 16, 2018 3:34 PM Z Strickland v. Arch Ins. Co. United States Court of Appeals for the Eleventh Circuit January 9, 2018, Decided No. 17-10610 Non-Argument Calendar Reporter 2018 U.S.

More information

SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 1998

SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 1998 SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 1998 PERFORMANCE BOND DECLARED NULL AND VOID! SURETY'S DEFENSE ARISING FROM OBLIGEE'S FAILURE TO ALLOW SURETY TO EXERCISE PERFORMANCE BOND OPTIONS

More information

Case KG Doc 266 Filed 06/14/17 Page 1 of 27

Case KG Doc 266 Filed 06/14/17 Page 1 of 27 Case 17-10828-KG Doc 266 Filed 06/14/17 Page 1 of 27 UNITED STATES BANKRUPTCY COURT DISTRICT OF DELAWARE In re: Venoco, LLC, et al., Debtors. 1 Chapter 11 Case No. 17-10828 (KG) (Jointly Administered)

More information

X : : : : : : : : : : : : X. JOHN F. KEENAN, United States District Judge: Plaintiff, Federal Insurance Company ( Federal ) has moved

X : : : : : : : : : : : : X. JOHN F. KEENAN, United States District Judge: Plaintiff, Federal Insurance Company ( Federal ) has moved Federal Insurance Company v. Metropolitan Transportation Authority et al Doc. 33 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK ------------------------------ FEDERAL INSURANCE COMPANY, -against-

More information

FIRST INDEMNITY OF AMERICA INSURANCE COMPANY INDEMNITY AGREEMENT

FIRST INDEMNITY OF AMERICA INSURANCE COMPANY INDEMNITY AGREEMENT FIRST INDEMNITY OF AMERICA INSURANCE COMPANY Agreement Number: Execution Date: Click here to enter text. Click here to enter text. INDEMNITY AGREEMENT DEFINITIONS: Surety: First Indemnity of America Insurance

More information

Settling the Hard-Fought Case

Settling the Hard-Fought Case FIDELITY AND SURETY Multiple Questions to Consider By John W. Dreste and Thomas K. O Gara Settling the Hard-Fought Case What happens when the surety compromises after the sheen fades from the principal

More information

SureQuick Express Bond Application

SureQuick Express Bond Application SureQuick Express Bond Application General Information Contractor Company Name Business Phone No. ( ) Mobile ( ) Home ( ) E-mail address Type of work done? Operates as Proprietorship Partnership Corporation

More information

SURETY TODAY PRESENTATION. Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD December 11, 2017

SURETY TODAY PRESENTATION. Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD December 11, 2017 SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD December 11, 2017 Bankruptcy: The Debtor s and the Surety s Rights to the Bonded

More information

NINETEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 10 TH & 11 TH, 2008

NINETEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 10 TH & 11 TH, 2008 NINETEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 10 TH & 11 TH, 2008 NAVIGATING THE LABYRINTH: PRACTICAL ISSUES ARISING WHEN LITIGATING AIA A312 PERFORMANCE

More information

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF ASH EQUIPMENT CO., INC. D/B/A AMERICAN HYDRO; AND ASH EQUIPMENT CO., INC., A

More information

MEMORANDUM OF LAW IN SUPPORT OF DEFENDANT S CROSS-MOTION FOR SUMMARY JUDGMENT AND IN OPPOSITION TO PLAINTIFF S MOTION FOR SUMMARY JUDGMENT

MEMORANDUM OF LAW IN SUPPORT OF DEFENDANT S CROSS-MOTION FOR SUMMARY JUDGMENT AND IN OPPOSITION TO PLAINTIFF S MOTION FOR SUMMARY JUDGMENT FILED: NEW YORK COUNTY CLERK 03/23/2016 04:12 PM INDEX NO. 650806/2013 NYSCEF DOC. NO. 29 RECEIVED NYSCEF: 03/23/2016 SUPREME COURT OF THE STATE OF NEW YORK COUNTY OF NEW YORK -------------------------------------------------------------------x

More information

Assembly Amendment to Assembly Bill No. 125 (BDR 3-588) Title: No Preamble: No Joint Sponsorship: No Digest: Yes

Assembly Amendment to Assembly Bill No. 125 (BDR 3-588) Title: No Preamble: No Joint Sponsorship: No Digest: Yes 0 Session (th) A AB Amendment No. Assembly Amendment to Assembly Bill No. (BDR -) Proposed by: Assembly Committee on Judiciary Amends: Summary: No Title: No Preamble: No Joint Sponsorship: No Digest: Yes

More information

AIA Document A101 TM 1997

AIA Document A101 TM 1997 AIA Document A101 TM 1997 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM AGREEMENT made as of the day of in the year of (In words, indicate day,

More information

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA. VERSUS NO NEW ORLEANS CITY, et al. Defendants

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA. VERSUS NO NEW ORLEANS CITY, et al. Defendants UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA WALTER POWERS, JR., et al. Plaintiffs CIVIL ACTION VERSUS NO. 13-5993 NEW ORLEANS CITY, et al. Defendants SECTION "E" FINDINGS OF FACT & CONCLUSIONS

More information

EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 EXONERATION BASICS: ENFORCING THE SURETY'S RIGHTS

EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 EXONERATION BASICS: ENFORCING THE SURETY'S RIGHTS EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 EXONERATION BASICS: ENFORCING THE SURETY'S RIGHTS PRESENTED BY: L. GRAVES STIFF, III, ESQ. STARNES & ATCHISON Seventh Floor,

More information

SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 8-K CURRENT REPORT

SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 8-K CURRENT REPORT SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 8-K CURRENT REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 DATE OF REPORT August 7, 2003 (Date of Earliest

More information

IN THE DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FIFTH DISTRICT JULY TERM 2007

IN THE DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FIFTH DISTRICT JULY TERM 2007 IN THE DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FIFTH DISTRICT JULY TERM 2007 HUBBARD CONSTRUCTION COMPANY, v. Appellant, Case No. 5D06-3640 JACOBS CIVIL, INC., Appellee. / Opinion filed October

More information

FORM OF AGREEMENT BETWEEN CONSTRUCTOR AND OWNER

FORM OF AGREEMENT BETWEEN CONSTRUCTOR AND OWNER FORM OF AGREEMENT BETWEEN CONSTRUCTOR AND OWNER This AGREEMENT made the Day day of MONTH in the year Two Thousand Fourteen BY AND BETWEEN CONSTRUCTOR, hereinafter called the, and the Board of Regents,

More information

SURETY BAD FAITH: TORT RECOVERY FOR BREACH OF A CONSTRUCTION PERFORMANCE BOND

SURETY BAD FAITH: TORT RECOVERY FOR BREACH OF A CONSTRUCTION PERFORMANCE BOND SURETY BAD FAITH: TORT RECOVERY FOR BREACH OF A CONSTRUCTION PERFORMANCE BOND ARON J. FRAKES This note examines tort recovery for breaches of performance bonds. In the construction industry, it is customary

More information

Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It?

Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It? Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It? by Greg Gledhill, Associate For decades, pay-if-paid and/or pay-when-paid clauses have appeared in typical construction subcontracts.

More information

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 WHAT IS A DEFAULT AND WHY DOES IT MATTER PRESENTED BY: Jarrod W. Stone, Esquire Manier

More information

CONTRACTOR INFORMATION - Attach most recent company year-end financial statement or tax return.

CONTRACTOR INFORMATION - Attach most recent company year-end financial statement or tax return. This program is not intended for use on the following types of contracts; Subdivision Completion Multi-year Terms Indefinite Quantity Service Contracts Design Build Efficiency Guarantees Software Programs

More information

Chapter Three. Bidding. Patrick M. Miller and Molly Moss

Chapter Three. Bidding. Patrick M. Miller and Molly Moss Chapter Three Bidding Patrick M. Miller and Molly Moss 3.01 Introduction...24 3.02 Mutual Mistake...24 3.03 Unilateral Mistake before Award of Contract...27 3.04 Unilateral Mistake after Award of Contract...28

More information

EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997

EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 THE "CARDINAL CHANGE" DOCTRINE AS A DEFENSES TO SURETY BOND CLAIMS: A PRACTICAL GUIDE TO THE FEDERAL CASE LAW PRESENTED BY:

More information

An Essential Brick and Its Chip: A Refresher on Payment Bond Claims Under the Miller Act and the "Little Miller Act"

An Essential Brick and Its Chip: A Refresher on Payment Bond Claims Under the Miller Act and the Little Miller Act An Essential Brick and Its Chip: A Refresher on Payment Bond Claims Under the Miller Act and the "Little Miller Act" Written By Jason T. Strickland (jtstrickland@wardandsmith.com) May 24, 2011 Introduction

More information

United States Court of Appeals for the Federal Circuit

United States Court of Appeals for the Federal Circuit United States Court of Appeals for the Federal Circuit K-CON, INC., Appellant v. SECRETARY OF THE ARMY, Appellee 2017-2254 Appeal from the Armed Services Board of Contract Appeals in Nos. 60686, 60687,

More information

Illinois Legal Update. Patrick M. Miller, Partner

Illinois Legal Update. Patrick M. Miller, Partner Illinois Legal Update Patrick M. Miller, Partner ILLINOIS Legal Update Case Law Update: Limitations periods applicable to construction related and indemnification claims Strict application of affidavit

More information

Illinois Case Law Updates. Melissa Economy Faegre Baker Daniels

Illinois Case Law Updates. Melissa Economy Faegre Baker Daniels Illinois Case Law Updates Melissa Economy Faegre Baker Daniels 2 Overview Legislative Updates: 770 ILCS 60/38.1 - Bonding over Mechanics Liens 765 ILCS 605/1 - Condominium Property Act Amendments Case

More information

IN THE SUPREME COURT OF FLORIDA TALLAHASSEE, FLORIDA CASE NO. SC

IN THE SUPREME COURT OF FLORIDA TALLAHASSEE, FLORIDA CASE NO. SC IN THE SUPREME COURT OF FLORIDA TALLAHASSEE, FLORIDA CASE NO. SC02-2210 DAVID BOLAND, INCORPORATED, : : Appellant, : : vs. : : INTERCARGO INSURANCE COMPANY, : : Appellee. : : QUESTION OF LAW CERTIFIED

More information

Securing the Delinquent Account & Alternative Legal Theories to Collect on Delinquent Accounts

Securing the Delinquent Account & Alternative Legal Theories to Collect on Delinquent Accounts Securing the Delinquent Account & Alternative Legal Theories to Collect on Delinquent Accounts David M. Mannion, Esq. DMannion@BlakeleyLLP.com Blakeley LLP 54 W. 40th Street New York, NY 10018 V. (917)

More information

TENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 21-22, 1999

TENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 21-22, 1999 TENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 21-22, 1999 NAMED OBLIGEE S RIGHTS UNDER THE PAYMENT BOND (ARE THERE ANY?); RIGHTS AND LIMITATIONS ON THE OBLIGEE S RIGHTS ON EXHAUSTION

More information

The Jacobs Case: Pennsylvania Contract Bond Law Goes Modern

The Jacobs Case: Pennsylvania Contract Bond Law Goes Modern Volume 11 Issue 1 Article 2 1965 The Jacobs Case: Pennsylvania Contract Bond Law Goes Modern Daniel Mungall Jr. Follow this and additional works at: http://digitalcommons.law.villanova.edu/vlr Part of

More information

PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C.

PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C. PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C. Design-Build Institute of America Contract Documents LICENSE AGREEMENT

More information

The Real Estate Finance Opinion Report of 2012

The Real Estate Finance Opinion Report of 2012 The Real Estate Finance Opinion Report of 2012 History and Summary By Edward J. Levin Edward J. Levin is a partner in the Baltimore, Maryland, office of Gordon Feinblatt LLC and the chair of the Real Property

More information

UNITED STATES COURT OF APPEALS

UNITED STATES COURT OF APPEALS Case: 12-1553 Document: 35-2 Page: 1 Filed: 12/21/2012 No. 2012-1553 UNITED STATES COURT OF APPEALS FOR THE FEDERAL CIRCUIT FLUOR INTERCONTINENTAL, INC., Plaintiff-Appellant, v. HILLARY RODHAM CLINTON,

More information

(01/31/13) Principal Name /PIA No. PAYMENT AND INDEMNITY AGREEMENT No.

(01/31/13) Principal Name /PIA No. PAYMENT AND INDEMNITY AGREEMENT No. PAYMENT AND INDEMNITY AGREEMENT No. THIS PAYMENT AND INDEMNITY AGREEMENT (as amended and supplemented, this Agreement ) is executed by each of the undersigned on behalf of each Principal (as defined below)

More information

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater, Florida th st APRIL 30 & MAY 1, 2009 KNOWING WHEN TO SAY "WHEN" - PURSUING INDEMNIFICATION CLAIMS IN DIFFICULT ECONOMIC TIMES

More information

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF OREGON

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF OREGON Yarbrough v. First American Title Insurance Company et al Doc. 50 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF OREGON JACK R. YARBROUGH, Plaintiff, 3:14-cv-01453-BR OPINION AND ORDER v. FIRST

More information

PROPOSAL BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 610 First Edition, 2015 Design-Build Institute of America Washington, D.C.

PROPOSAL BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 610 First Edition, 2015 Design-Build Institute of America Washington, D.C. PROPOSAL BOND FOR DESIGN-BUILD PROJECTS Document No. 610 First Edition, 2015 Design-Build Institute of America Washington, D.C. Design-Build Institute of America Contract Documents LICENSE AGREEMENT By

More information

ENGINEERING, PROCUREMENT, CONSTRUCTION SURETY PAYMENT BOND Page 1 of 10

ENGINEERING, PROCUREMENT, CONSTRUCTION SURETY PAYMENT BOND Page 1 of 10 Page 1 of 10 Bond Type Surety Bond Form and Version Number ENGINEERING, PROCUREMENT, CONSTRUCTION SURETY PAYMENT BOND 2018 03-04 XBRL-CET ENGINEERING, PROCUREMENT, CONSTRUCTION SURETY PAYMENT BOND Principal

More information

Case 0:14-cv JIC Document 48 Entered on FLSD Docket 01/29/15 11:03:44 Page 1 of 9 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA

Case 0:14-cv JIC Document 48 Entered on FLSD Docket 01/29/15 11:03:44 Page 1 of 9 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA Case 0:14-cv-60963-JIC Document 48 Entered on FLSD Docket 01/29/15 11:03:44 Page 1 HILL YORK SERVICE CORPORATION, d/b/a Hill York, v. Plaintiff, CRITCHFIELD MECHANICAL, INC., Defendant. / UNITED STATES

More information

1:14-cv LJO-GSA UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF CALIFORNIA U.S. Dist. LEXIS 57467

1:14-cv LJO-GSA UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF CALIFORNIA U.S. Dist. LEXIS 57467 Page 1 AMERICAN CONSTRUCTION & ENVIRONMENTAL SERVICES., a Nevada Corporation, Plaintiff, v. TOTAL TEAM CONSTRUCTION SERVICES, INC., a California corporation; TRAVELERS CASUALTY & SURETY COMPANY OF AMERICA,

More information

Reginella Construction Company v. Travelers Casualty & Surety Co

Reginella Construction Company v. Travelers Casualty & Surety Co 2014 Decisions Opinions of the United States Court of Appeals for the Third Circuit 6-11-2014 Reginella Construction Company v. Travelers Casualty & Surety Co Precedential or Non-Precedential: Non-Precedential

More information

TWENTY SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE

TWENTY SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE TWENTY SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE SEPTEMBER 22nd - 23rd, 2016 PRACTICAL DEFENSES TO PROBATE BOND CLAIMS PRESENTED BY: JEFFREY M. FRANK, ESQUIRE Alber Crafton 2301 W.

More information

IN THE SUPREME COURT OF THE STATE OF FLORIDA. CASE NO. Lower Tribunal Case No. 09-CA

IN THE SUPREME COURT OF THE STATE OF FLORIDA. CASE NO. Lower Tribunal Case No. 09-CA IN THE SUPREME COURT OF THE STATE OF FLORIDA CASE NO. Lower Tribunal Case No. 09-CA-001404 VILA & SON LANDSCAPING CORPORATION, Petitioner vs. POSEN CONSTRUCTION, INC., Respondent PETITIONER'S JURISDICTIONAL

More information

STATE OF MICHIGAN COURT OF APPEALS

STATE OF MICHIGAN COURT OF APPEALS STATE OF MICHIGAN COURT OF APPEALS MACDONALD LAW OFFICE, PLLC, Plaintiff-Appellant, UNPUBLISHED June 24, 2010 v No. 289167 Hillsdale Circuit Court TED JANSEN and PENNY JANSEN, LC No. 08-000624-CK Defendants-Appellees.

More information