TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

Size: px
Start display at page:

Download "TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS"

Transcription

1 TWENTY EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Nashville, Tennessee th st APRIL 20 & 21, 2017 TO PAY OR TO PLAY: OPTIONS AVAILABLE TO THE SURETY: FINANCE OR TAKEOVER? PRESENTED BY: G. MATTHEW KEENAN L. GRAVES STIFF, III Starnes Davis Florie, LLP 100 Brookwood Place, 7th Floor Birmingham, Alabama RON WILLS CapSpecialty 1600 Aspen Commons, Suite 300 Middleton, Wisconsin MICHAEL J. SUGAR, JR. Forcon International Corp Oakfield Drive Brandon, FL 33511

2 INTRODUCTION Choosing between financing a principal or taking over a project to remedy a default is a critical question. While it is always good to have the option to choose, the wrong decision could lead to significantly greater losses to the surety and even losses that exceed the penal sum of the bond. This paper will look briefly into how to approach that question and those factors that the surety practitioner should always consider when faced with this choice. I. Surety s Right to Finance or Takeover FINANCING v. TAKEOVER The first question when considering whether to finance a principal or takeover a project is whether the surety has the right to do either. Often, a surety will have the option to choose. The source of the surety s right for either option may be found in the indemnity agreement, bond or both. Accordingly, it is critical to have a good understanding of these agreements as well as evaluating the impact of any state laws or other regulations on the surety s right to advance funds to its principal or take over and complete the project. A. Indemnity Agreement The indemnity agreement between the surety and principal will often provide the surety with the right, but not the obligation, to either finance a principal or takeover the project. In fact, the indemnity agreement is sometimes the only contractual source of such rights. The following is an example of two such provisions: With respect to each bond executed by the Surety in connection with a contract, the Surety is hereby authorized, in its sole discretion, to make or guarantee advances or loans for the purpose of the contract... and the Indemnitors agree both that all such loans and advances... shall be conclusively presumed to be an indemnity obligation of the Indemnitors to the Surety, and that the Surety shall have the absolute right to cease making or guaranteeing advances or loans at any time and without notice to the Indemnitors.... the Surety, in its sole discretion, shall have the right, but not the obligation, to take possession of the work under the contract and any other contract, in connection with which the Surety has issued a bond or bond(s) and, at the expense of the Indemnitors, to complete, to arrange for completion, or... of the contract work. Note that both provisions expressly set forth the continued indemnity obligations with respect to either option taken by the surety. 1 In addition, the assignment rights typically found in the surety s indemnity agreement can be an important tool for a surety who elects to complete a project with a new contractor as all remaining contract funds, equipment, inventory and materials will often be assigned to the surety. 1 In addition to contractual rights, a surety who chooses to finance a principal may also still look to its rights under equitable subrogation or other common law rights to recover any funds advanced to its principal. See 1 Mike F. Pipkin, et al., Bond Default Manual (4th ed. 2015). 1

3 B. Performance Bond Similarly, the performance bond may be a source of such rights. While many different bond forms exist, the AIA Document A Performance Bond is a prime example of a form that clearly provides the surety with the option to choose whether to finance a principal or takeover a project from the principal (along with other options). Under the A312 Bond, provided there has been no owner default and all conditions precedent have been satisfied, the surety enjoys the right to either finance the principal to complete the project: 5.1 Arrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract; or the surety may choose to takeover and complete the project with its own contractor: 5.2 Undertake to perform and complete the Construction Contract itself, through its agents or through independent contractors; or... The AIA Document A311 Performance Bond, on the other hand, does not contain an express option for financing a defaulted principal. Nonetheless, it is commonly understood that the surety has this right under the provision that the Surety may promptly remedy the default or the provision that the surety may [c]omplete the Contract in accordance with its terms and conditions. 2 C. Common Law Finally, some courts have found that a surety enjoys a common law right to take over and complete its principal s project even when the performance bond does not expressly provide for it. 3 Again, it is imperative that the practitioner familiarize himself/herself with all of the sources of the surety s rights before evaluating the surety s options when faced with a principal s default. II. Advantages/Disadvantages of Financing a Principal 4 In theory, there are many good reasons for the surety to choose to advance funds to its principal upon notice of a bond claim by the obligee. In practice, they are much more limited. In fact, the trend for many years has been away from financing a principal due to the many risks associated with it. As more than one treatise has noted, financing a principal is: the most controversial and most maligned of the completion options available to the performance bond surety. This is because financing is not a panacea but a danger-filled mine field which can 2 See, e.g., id. at See id. at 366 and cases cited therein. 4 For a discussion of issues unique to financing and takeover in the context of a federal project, see Gerard P. Sunderland; et al., Tenth Annual Northeast Surety & Fidelity Claims Conference, The Surety and the Federal Government: to Finance, to Takeover, or to do Nothing, That is the Question, (1999). 2

4 lead to disaster... In deciding whether to finance, the surety s natural prejudice should be not to take this step. This prejudice occurs because the arguments in favor of financing are much more persuasive and compelling in theory than they are in practice. 5 Nonetheless, there are advantages for a surety providing financial assistance to a principal, whether directly or through backdoor financing (i.e., payments to subcontractors and suppliers under a payment bond). The most common benefits for the financing surety are: Avoiding the typical problems that arise with the obligee, subcontractors, suppliers and creditors of the principal upon a principal default or when they discover that the principal is in financial trouble; The principal s subcontracts remain enforceable, which means those prices are locked in and are not renegotiated; The principal has a familiarity with the job that a new contractor lacks there is no learning curve on the project when you finance your principal; Avoiding other costs of hiring a new contractor, such as significant mark-ups for various allowances and contingencies; Reduced delays work stoppage and demobilization of the principal can result in liquidated damages; and Keeps your principal interested and motivated to pursue its affirmative claims. Other advantages are that financing can lead to securing collateral security from the principal or indemnitors that it would not otherwise have and insulating of the surety from claims by its principal and indemnitors when the financing agreement includes a release by the principal and indemnitors of any claims they may have against the surety. 6 On the other hand, the disadvantages to providing funds to a principal include: The surety s costs in monitoring the project; Funds advanced by the surety may not reduce the penal sum of the bond; Potential for miscalculating the principal s overhead; Risk of increased costs to complete; Tax issues; Difficulty in achieving substantial completion; Potential claims by the principal when the surety decides to cutoff funding; and Providing the principal with a potential defense to indemnity principals have argued alter ego or domination as a defense to indemnity based upon the surety s advancement of funds. 5 Pipkin, supra note 1, at 210 n.1. 6 Id. at

5 III. Advantages/Disadvantages of a Takeover When a surety elects to take over and complete a project, the surety explicitly assumes the performance obligations of its principal under the latter s contract with the obligee. 7 In other words, the surety steps into the shoes of its principal. The advantages to this option often include: Control over completion and costs; Control over information; Control over the scope of work; Ability to negotiate existing disputes over defects, change orders, extensions of time and liquidated damages; and Establishing of goodwill with the obligee. Conversely, some of the disadvantages for a surety that chooses to takeover its principal s project are: Potential waiver of the penal sum of the bond; Discovery of latent defects in the project; Potential loss of right to recover overpayments made by the obligee to the principal; 8 Undermining the principal s claims against the owner; Losing your goodwill with the principal who then becomes uncooperative and may be more motivated to contest indemnity obligations; and Unforeseen and increased costs due to the inherent risks of taking on any construction project. IV. Evaluating the Options A thorough investigation is key to evaluating whether to finance or takeover. One of the difficulties in conducting a thorough investigation of the principal, the project and other factors, however, is the time constraints placed on the surety given that any delays to the project may lead to additional losses to the surety. Often times, a construction consultant is a key and indispensable component to the surety s investigation as he/she is able to quickly step in and gather the necessary information and documents in a more efficient manner than anyone else. Regardless, the surety will often find that its investigation is hindered by a lack of time. Similarly, there may not always be enough time to fully evaluate the principal s defenses. Accordingly, the surety may decide to remedy the default under a reservation of rights. 7 See, e.g., Travelers Cas. & Sur. Co. v. Dormitory Authority-State of N.Y., 735 F. Supp. 2d 42, 80, n.66 (S.D.N.Y. 2010). 8 See Lumbermens Mut. Cas. Co. v. U.S., 654 F.3d 1305 (Fed. Cir. 2011). 4

6 A. Financing As it did during the underwriting process that took place when the surety first agreed to bond the principal, the surety will want to first obtain certain information and documents from the principal in order to be able to properly evaluate whether the principal is a candidate for financing. This information is commonly known as the four Cs cash, capacity, character and collateral. While the last C, collateral, is not a part of the original underwriting process, it is an obvious necessity when faced with a principal who needs financing. The first C, cash held by or available to the principal, will usually be insufficient and the surety will, thus, be looking for collateral security held by the principal or indemnitors that could be used to mitigate any loss. Capacity represents the principal s ability to perform and complete the project. While the contractor may represent that it is ready, willing and able to finish the job, the surety must investigate further and consider whether the people it has in place can do the job, whether they have the equipment and materials to complete and whether other circumstances exist that may ultimately put the contractor out of business. Character represents the trustworthiness of the principal and indemnitors. The surety must be able to trust the principal that it will diligently perform the work, cooperate, take its indemnity obligations seriously and minimize any loss to the surety. Additionally, other questions to ask are: How much unbonded work does the principal have? Other projects could represent additional financial trouble or they may be a stable source of income that helps to keep the principal solvent. Does the principal have a good relationship with its subcontractors? Financing a principal with deteriorating subcontractor and supplier relationships can lead to more headaches and costs for the surety. Is the project near substantial completion or in its early stages? Financing a principal makes the most sense when a project is near completion. What are the options for finding a completing contractor? If there are no good options for a new contractor that can finish the job at a reasonable cost due to the complexity of the project, the remoteness of the location or some other reason, then financing becomes a more attractive option. A surety may consider financing a design/build/manufacturing contractor that owns patents and copyrights to certain materials or machinery found in the completed structure. For example, the contractor may use a special, patented glass for the curtain wall system, and it is the only entity with a license to use it. To bring another contractor in to complete the job could require an entire redesign of the exterior skin of the building. Thus, financing may be the most reasonable and cost effective option. The reality, however, is that many principals in need of financing will not be in a position to satisfy their surety that advancing funds is the best option to remedy the default or minimize the surety s liability. Capacity and Character are considered by some to be the most important factors in any evaluation. As others have noted, a principal that cannot provide sufficient 5

7 assurance of its capacity to complete the work and of its character regarding its promise to indemnify and hold harmless the surety should not be financed. 9 B. Takeover Many of the same factors mentioned above should also be considered in evaluating whether to take over a project and complete. In both instances these factors will be heavily influenced by the myriad set of facts and circumstances presented by each particular principal and bonded project. For example, it may be determined that it is too expensive to bring in an entirely new contractor to finish a job when the project is near completion at the time of default. Yet, under another set of circumstances, a takeover at such a late stage in the project could be a reasonable option, such as when costs are spiraling out of control. In that situation, the surety may be able to better mitigate its losses by taking over the project and maintaining as much control as possible. At the other end of the spectrum, a default is entered against the principal when the project is still in its early stages. Sureties often find such projects to not be great candidates for a takeover because of the potential for more problems to occur and costs to rise due simply to the length of time remaining to finish the job. Furthermore: [e]arly payments made to the principal under the bonded contract are often for mobilization and other general conditions that do not correspond to actual completion of work on the project. As a result, it is not uncommon that the net exposure to the surety to complete a project in its early stages will approach, if not exceed, the penal sum of the bond. 10 Other key considerations for the surety contemplating a takeover are: Amount of the remaining contract balance compared to the cost to complete the project; Complexity of the project; Location of the project; Whether the completing contractor can finish the job on time; and Potential conflicts or difficulty with the obligee and its design professionals. Finally, it is critically important that all contract documents, plans and specifications are carefully reviewed so that the surety can address any issues related to insurance, warranties, payment of funds, deadlines and related matters during negotiations over the specific terms of the takeover agreement. 9 George J. Bachrach, Eleventh Annual Northeast Surety & Fidelity Claims Conference, Financing the Principal, p. 7 (2000). 10 See Pipkin, supra note 1, at

8 CONCLUSION The question of whether to finance the principal or to takeover and complete the project is extremely important. There will always be risks associated with any course of action taken by a surety to remedy a principal s default. The goal is simply to minimize those risks. Because every situation is different, the practitioner must always conduct a thorough investigation into the facts and in depth analysis of the risks and benefits to the surety in choosing between these two options. 7

9 BIOS Ron Wills is surety claims counsel for Capitol Indemnity Corporation. Before that he was surety claims counsel with Fireman s Fund. He has over 20 years of experience in the industry. Ron has a degree in Information Systems from the University of Georgia and was a Sr. Systems Analyst in software development for about 10 years before going to law school. He graduated with a J.D. from Georgia State University and is admitted to the practice of law in Georgia and Florida. After receiving his law degree, he worked in private practice for about three years with a firm that primarily practiced in the surety defense arena. Ron Wills CAPITOL INDEMNITY CORPORATION 1600 Aspen Commons, Suite 300 Middleton, WI (770) rwills@capspecialty.com Mike Sugar - is the president and founder of Forcon International Corp [1984]. Surety & Fidelity underwriter for The Hartford. Claims attorney/manager for Fidelity and Deposit Company of Maryland. Mr. Sugar graduated from the University of Buffalo in 1967 Bachelor of Arts. Juris Doctor from the University of Buffalo in He is a member of the Washington D.C., Pennsylvania (inactive) and Florida Bars (active). Mr. Sugar is the founder of the Southern Surety & Fidelity Claims Conference and the Northeast Surety & Fidelity Claims Conference. After law school, he moved to Paris, France and taught English at the School of Berlitz while growing a full red beard. Michael J. Sugar, Jr. FORCON INTERNATIONAL CORP Oakfield Dr. Brandon, FL (813) mjsugar@forcon.com Gray Stiff is a Senior Partner at Starnes Davis Florie LLP in Birmingham, Alabama. He has extensive experience in construction litigation, including representation of owners, contractors, and sureties, design professional defense and prosecution and defense of business and commercial claims. Gray was named Lawyer of the Year for Birmingham Litigation Construction in the 2016 edition of Best Lawyers in America, and he has been regularly selected by his peers for inclusion in Best Lawyers in America, In addition, Gray has been named to "Who's Who in Construction, Architecture & Engineering 2009" by the Birmingham Business Journal, which recognized him as one of the top construction litigation attorneys in Birmingham. He obtained a J.D. from Cumberland School of Law, Samford University (1978) and a B.A. from the University of Virginia (1973). Luther Graves Stiff, III STARNES DAVIS FLORIE LLP 100 Brookwood Place, 7th Floor Birmingham, Alabama

10 (205) Matt Keenan is a partner with Starnes Davis Florie LLP in Birmingham, Alabama. Matt's practice is focused on the representation of sureties and other entities in the defense and prosecution of business and commercial claims. He has been named a Rising Star for the State of Alabama by Alabama Super Lawyers in 2014 and Matt received his J.D. from the University of Alabama School of Law (2005) where he served on the Alabama Law Review. He is a graduate of Texas Christian University (1993). G. Matthew Keenan STARNES DAVIS FLORIE LLP 100 Brookwood Place, 7th Floor Birmingham, Alabama (205) gmk@starneslaw.com 9

SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996

SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996 SEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE OCTOBER 24-25, 1996 BID PACKAGES DETERMINING THE REMAINING SCOPE OF WORK TO COMPLETE AREAS OF CONCERN PRESENTED BY: William H. Ver Eecke,

More information

ELEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE

ELEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE ELEVENTH ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE Financing the Principal - Panel Discussion (including an analysis of the circumstances under which a surety would consider financing a principal,

More information

What You Should Know About General Agreements of Indemnity and Why You Should Know It

What You Should Know About General Agreements of Indemnity and Why You Should Know It What You Should Know About General Agreements of Indemnity and Why You Should Know It Summary When a contractor (for purposes of this discussion, contractor includes subcontractor) first seeks surety credit,

More information

EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 EXONERATION BASICS: ENFORCING THE SURETY'S RIGHTS

EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 EXONERATION BASICS: ENFORCING THE SURETY'S RIGHTS EIGHTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 3-4, 1997 EXONERATION BASICS: ENFORCING THE SURETY'S RIGHTS PRESENTED BY: L. GRAVES STIFF, III, ESQ. STARNES & ATCHISON Seventh Floor,

More information

CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I???

CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I??? CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS Or I don't want no ConsensusDOCS bond form or do I??? Deborah S. Griffin Gina A. Fonte Holland & Knight LLP Boston, MA 02116 Presented at

More information

KNOW YOUR BOND BEFORE YOU SIGN

KNOW YOUR BOND BEFORE YOU SIGN by Mark H. McCallum and Robert J. Duke...an important part of the surety underwriting process is to know and understand the terms of the construction contract. KNOW YOUR BOND BEFORE YOU SIGN A contractor

More information

In the United States Court of Federal Claims

In the United States Court of Federal Claims In the United States Court of Federal Claims No. 14-84C (Filed: November 19, 2014 FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, et al. v. Plaintiffs, THE UNITED STATES OF AMERICA, Defendant. Tucker Act;

More information

SURETY TODAY PRESENTATION. Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD December 11, 2017

SURETY TODAY PRESENTATION. Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD December 11, 2017 SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD December 11, 2017 Bankruptcy: The Debtor s and the Surety s Rights to the Bonded

More information

What To Do With Performance Bonds When Projects Default

What To Do With Performance Bonds When Projects Default What To Do With Performance Bonds When Projects Default By Gary Strong January 18, 2018, 3:12 PM EST In today s economic climate, performance bonds are important for construction contracts. While performance

More information

CONTRACTOR INFORMATION - Attach most recent company year-end financial statement or tax return.

CONTRACTOR INFORMATION - Attach most recent company year-end financial statement or tax return. This program is not intended for use on the following types of contracts; Subdivision Completion Multi-year Terms Indefinite Quantity Service Contracts Design Build Efficiency Guarantees Software Programs

More information

TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015

TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015 TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015 LOSS CONTROL STRATEGIES FOR THE SURETY PRIOR TO FORMAL NOTICE OF DEFAULT OR TERMINATION TAMMY N. GIROUX, ESQUIRE Shumaker,

More information

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017 SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017 SURETY CASE LAW UPDATE WHAT WE HAVE FOUND INTERESTING OVER THE

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS OPINION BY ADMINISTRATIVE JUDGE DICUS ON RESPONDENT S MOTION TO DISMISS FOR LACK OF JURISDICTION

ARMED SERVICES BOARD OF CONTRACT APPEALS OPINION BY ADMINISTRATIVE JUDGE DICUS ON RESPONDENT S MOTION TO DISMISS FOR LACK OF JURISDICTION ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Hackney Group and ) Credit General Insurance Company ) ASBCA No. 51453 ) Under Contract No. N62472-96-C-3237 ) APPEARANCE FOR THE APPELLANT: APPEARANCES

More information

TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013

TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013 TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013 DON T BE PUT OFF BY SETOFF PRESENTED BY: Toby Pilcher The Hanover Insurance Group

More information

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD January 8, 2018

SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD January 8, 2018 SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD January 8, 2018 Bankruptcy: The Surety s Proof of Claim (MIKE) This is the third

More information

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF ASH EQUIPMENT CO., INC. D/B/A AMERICAN HYDRO; AND ASH EQUIPMENT CO., INC., A

More information

INTERNATIONAL FIDELITY INSURANCE COMPANY,

INTERNATIONAL FIDELITY INSURANCE COMPANY, Page 1 2 of 35 DOCUMENTS INTERNATIONAL FIDELITY INSURANCE COMPANY, a foreign corporation, ALLEGHENY CASUALTY COMPANY, a foreign corporation, Plaintiffs-Counter Defendants-Appellees, versus AMERICARIBE-MORIARTY

More information

FIDELITY AND GUAR. INS. UNDERWRITERS

FIDELITY AND GUAR. INS. UNDERWRITERS FIDELITY AND GUAR. INS. UNDERWRITERS v. U.S. Cite as 119 Fed.Cl. 195 (2014) 4. United States O113.12(2) FIDELITY AND GUARANTY INSUR- ANCE UNDERWRITERS, et al., Plaintiffs, v. The UNITED STATES of America,

More information

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM MERCHANTS BONDING COMPANY (MUTUAL) MERCHANTS NATIONAL BONDING INC. P.O. Box 14498 Des Moines iowa 50306-3498 Phone (800) 678-8171 FAX (515) 243-3854 GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS

More information

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM

GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS FORM MERCHANTS BONDING COMPANY (MUTUAL) MERCHANTS NATIONAL BONDING, INC. P.O. Box 14498, Des Moines, iowa 50306-3498 Phone (800) 678-8171 FAX (515) 243-3854 GENERAL APPLICATION AND AGREEMENT OF INDEMNITY CONTRACTORS

More information

CONTRACT FOR ROOF REMOVAL AND REPLACEMENT - Milford Middle School

CONTRACT FOR ROOF REMOVAL AND REPLACEMENT - Milford Middle School CONTRACT FOR ROOF REMOVAL AND REPLACEMENT - Milford Middle School THIS AGREEMENT made this day of, 2013 between the Milford School District, a New Hampshire school district having a usual place of business

More information

(01/31/13) Principal Name /PIA No. PAYMENT AND INDEMNITY AGREEMENT No.

(01/31/13) Principal Name /PIA No. PAYMENT AND INDEMNITY AGREEMENT No. PAYMENT AND INDEMNITY AGREEMENT No. THIS PAYMENT AND INDEMNITY AGREEMENT (as amended and supplemented, this Agreement ) is executed by each of the undersigned on behalf of each Principal (as defined below)

More information

TWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina st nd APRIL 21 & 22, 2016 A SURETY'S RIGHT TO SETTLE CLAIMS OVER A PRINCIPAL'S OBJECTION PRESENTED BY: Amy

More information

SOURCE ONE SURETY, LLC.

SOURCE ONE SURETY, LLC. SOURCE ONE SURETY, LLC. 15233 VENTURA BOULEVARD, SUITE 500 SHERMAN OAKS, CA 91403 GENERAL INDEMNITY AGREEMENT THIS General Agreement of Indemnity (hereinafter called Agreement ), is made and entered into

More information

FIRST INDEMNITY OF AMERICA INSURANCE COMPANY INDEMNITY AGREEMENT

FIRST INDEMNITY OF AMERICA INSURANCE COMPANY INDEMNITY AGREEMENT FIRST INDEMNITY OF AMERICA INSURANCE COMPANY Agreement Number: Execution Date: Click here to enter text. Click here to enter text. INDEMNITY AGREEMENT DEFINITIONS: Surety: First Indemnity of America Insurance

More information

The Law of Payment Bonds

The Law of Payment Bonds The Law of Payment Bonds Second Edition KEVIN L. LYBECK, WAYNE D. LAMBERT, AND JOHN E. SEBASTIAN, EDITORS Defending Liberty Pursuing Justice The Law of Payment Bonds, 2d Ed. Contents Chapter 1 - Introduction

More information

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater, Florida th st APRIL 30 & MAY 1, 2009 BACK TO THE FUTURE: HAS BRAMBLE REVIVED THE A311 BONDS AND DO WE REALLY WANT TO GO THERE?

More information

THIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002

THIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002 THIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002 JEWELS IN THE INDEMNITY AGREEMENT, AND A LUMP OF COAL PRESENTED BY: JOHN V. BURCH, ESQ. BOVIS, KYLE & BURCH,

More information

By James D. Fullerton

By James D. Fullerton By James D. Fullerton Contract Note Personal Guaranty Bond Mortgage Mechanic s Lien Signed by Contract Debtor Allows CR to sue DR and obtain judgment Signed by 2 nd DR, Bonding Co., Bonding Principal

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS

ARMED SERVICES BOARD OF CONTRACT APPEALS ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of -- ) ) ASBCA Nos. 56895, 56987, 56988, Thorington Electrical and ) 56989, 56990, 56991, Construction Company ) 56992, 56993, 56994, ) 56995, 56996, 56997,

More information

EXHIBIT CONSTRUCTION CONTRACT BOND

EXHIBIT CONSTRUCTION CONTRACT BOND Bond Number: Bond Number: EXHIBIT CONSTRUCTION CONTRACT BOND This Agreement made the day of, 20, between, a corporation organized and existing under the laws of the State of Florida, with its principal

More information

The Troubled Public Construction Project: When is it Time to Call in the Surety?

The Troubled Public Construction Project: When is it Time to Call in the Surety? City Attorneys Department League of California Cities Annual Conference October 6, 2005 The Troubled Public Construction Project: When is it Time to Call in the Surety? Michael N. Conneran, Esq. Hanson,

More information

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 SURETY LOSS: METHODS FOR SEEKING REIMBURSEMENT PRESENTED BY: Jeffrey S. Price Manier

More information

Conditions of Contract for Purchase of Goods and Services

Conditions of Contract for Purchase of Goods and Services Conditions of Contract for Purchase of Goods and Services DOCUMENT GOVERNANCE Policy Owner Head of Procurement Effective date 1 March 2017 This policy will be reviewed every six months. CONTENTS 1. DEFINITIONS

More information

SureQuick Express Bond Application

SureQuick Express Bond Application SureQuick Express Bond Application General Information Contractor Company Name Business Phone No. ( ) Mobile ( ) Home ( ) E-mail address Type of work done? Operates as Proprietorship Partnership Corporation

More information

2002 Report to the Legislature: Proposed Mechanics Lien Reforms. Submitted by: The New York State Law Revision Commission

2002 Report to the Legislature: Proposed Mechanics Lien Reforms. Submitted by: The New York State Law Revision Commission 2002 Report to the Legislature: Proposed Mechanics Lien Reforms Submitted by: The New York State Law Revision Commission I. Introduction This report is the result of the Commission s study of certain inefficiencies

More information

Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE

Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE 1 Contract Formation: These Terms and Conditions of Purchase (the "Terms and Conditions") apply to any purchases by Prufrex USA, Inc., its subsidiaries,

More information

QUOTE DOCUMENTS FOR CALLANAN GYM FLOOR REPLACEMENT center Street. Des Moines, Iowa QUOTE # Q7088

QUOTE DOCUMENTS FOR CALLANAN GYM FLOOR REPLACEMENT center Street. Des Moines, Iowa QUOTE # Q7088 QUOTE DOCUMENTS FOR CALLANAN GYM FLOOR REPLACEMENT 3010 center Street Des Moines, Iowa 50312 QUOTE # Q7088 Owner Des Moines Independent Community School District 1917 Dean Avenue Des Moines, IA 50316 DES

More information

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014

TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 TWENTY FIFTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 10 TH & 11 TH, 2014 WHAT IS A DEFAULT AND WHY DOES IT MATTER PRESENTED BY: Jarrod W. Stone, Esquire Manier

More information

CITY OF RICHMOND PERFORMANCE BOND

CITY OF RICHMOND PERFORMANCE BOND KNOW ALL MEN BY THESE PRESENTS: That place of business is located at CITY OF RICHMOND PERFORMANCE BOND, the Contractor ( Principal ) whose principal and ( Surety ) whose address for delivery of Notices

More information

I, Accept this proposal and make a payment of $ to confirm my commitment.

I, Accept this proposal and make a payment of $ to confirm my commitment. This Solar Home Improvement Agreement (this Agreement ) is between Golden Gate Green Finance dba Golden Gate Power, California General and Electrical Contractor license number 1002922 ( Golden Gate Power,

More information

TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater Beach, Florida RD TH APRIL 23 & 24, 2015 HANOVER V. ATLANTIS DRYWALL & FRAMING, et al: ARE INDEMNITY CLAIMS SUBJECT TO ARBITRATION?

More information

DEVELOPMENT CONTRACT FOR PUBLIC IMPROVEMENTS. WHEREAS,, (the Developer ), whose. business address is, is the owner and developer of

DEVELOPMENT CONTRACT FOR PUBLIC IMPROVEMENTS. WHEREAS,, (the Developer ), whose. business address is, is the owner and developer of PROJECT NO. CONTRACT TYPE DEVELOPMENT CONTRACT FOR PUBLIC IMPROVEMENTS WHEREAS,, (the Developer ), whose business address is, is the owner and developer of real property located in the corporate limits

More information

AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE) AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE) EJCDC C-520, Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Deletions by Engineer

More information

IBEW LOCAL 701 CONTRACTOR S WAGE AND FRINGE BENEFIT BOND

IBEW LOCAL 701 CONTRACTOR S WAGE AND FRINGE BENEFIT BOND IBEW LOCAL 701 CONTRACTOR S WAGE AND FRINGE BENEFIT BOND AGREEMENT dated this day of, 20, hereinafter called the agreement, by and between IBEW Local 701, being organized and existing under the laws of

More information

QUOTE DOCUMENTS FOR KING PARKING EXPANSION Forest Avenue. Des Moines, Iowa QUOTE # Q6747. Owner

QUOTE DOCUMENTS FOR KING PARKING EXPANSION Forest Avenue. Des Moines, Iowa QUOTE # Q6747. Owner QUOTE DOCUMENTS FOR KING PARKING EXPANSION 1849 Forest Avenue Des Moines, Iowa QUOTE # Q6747 Owner Des Moines Independent Community School District 1917 Dean Avenue Des Moines, Iowa 50316 DES MOINES PUBLIC

More information

QUICKPOLE.CA TERMS OF SERVICE. Last Modified On: July 12 th, 2018

QUICKPOLE.CA TERMS OF SERVICE. Last Modified On: July 12 th, 2018 1. PRELIMINARY PROVISIONS: QUICKPOLE.CA TERMS OF SERVICE Last Modified On: July 12 th, 2018 1.1 Introduction. Welcome to our website's Terms and Conditions ("Agreement"). The provisions of this Agreement

More information

Cont Casualty Co v. Fleming Steel Co

Cont Casualty Co v. Fleming Steel Co 2011 Decisions Opinions of the United States Court of Appeals for the Third Circuit 7-25-2011 Cont Casualty Co v. Fleming Steel Co Precedential or Non-Precedential: Non-Precedential Docket No. 10-4524

More information

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules

More information

Third Circuit Holds That Claims Are Disallowable Under Section 502(d) of the Bankruptcy Code No Matter Who Holds Them

Third Circuit Holds That Claims Are Disallowable Under Section 502(d) of the Bankruptcy Code No Matter Who Holds Them CLIENT MEMORANDUM Third Circuit Holds That Claims Are Disallowable Under Section 502(d) of the Bankruptcy Code No November 22, 2013 AUTHORS Paul V. Shalhoub Marc Abrams In a recent opinion, the United

More information

GENERAL TERMS AND CONDITIONS 1. Term: This Contract will apply from the Commencement Date and will continue until further notice unless this Contract

GENERAL TERMS AND CONDITIONS 1. Term: This Contract will apply from the Commencement Date and will continue until further notice unless this Contract GENERAL TERMS AND CONDITIONS 1. Term: This Contract will apply from the Commencement Date and will continue until further notice unless this Contract is terminated in accordance with its terms. 2. Supply:

More information

TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013

TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013 TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013 DRAFTING TAKEOVER AGREEMENTS TO MINIMIZE SURETY'S RISK PRESENTED BY: Rachel Walsh

More information

SURETY TODAY PRESENTATION. Given by Michael A. Stover Wright, Constable & Skeen, LLP Baltimore, MD May 14, 2018 THE SURETY S RESERVATION OF RIGHTS

SURETY TODAY PRESENTATION. Given by Michael A. Stover Wright, Constable & Skeen, LLP Baltimore, MD May 14, 2018 THE SURETY S RESERVATION OF RIGHTS SURETY TODAY PRESENTATION Given by Michael A. Stover Wright, Constable & Skeen, LLP Baltimore, MD May 14, 2018 THE SURETY S RESERVATION OF RIGHTS We all do it. It s practically instinctive. We don t even

More information

Guarantor additionally represents and warrants to Obligee as

Guarantor additionally represents and warrants to Obligee as GUARANTY THIS GUARANTY ( Guaranty ) is made as of the day of, 20, by, a corporation /limited liability company (strike whichever is inapplicable) formed under the laws of the State of and having a principal

More information

ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE

ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE SEVEN MYTHS ABOUT EQUITABLE SUBROGATION J. Michael Franks MANIER & HEROD First Union Tower 150 4th Avenue North Suite 2200 Nashville, TN 37219

More information

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF TEXAS MARSHALL DIVISION O R D E R

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF TEXAS MARSHALL DIVISION O R D E R IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF TEXAS MARSHALL DIVISION DATATREASURY CORP., Plaintiff, v. WELLS FARGO & CO., et al. Defendants. O R D E R 2:06-CV-72-DF Before the Court

More information

ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE

ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE LIQUIDATED DAMAGES REVISITED Responses Available to the Surety Robert A. Koenig SHUMAKER, LOOP & KENDRICK, LLP 1000 Jackson Avenue Toledo,

More information

SECTION INSTRUCTIONS TO BIDDERS

SECTION INSTRUCTIONS TO BIDDERS SECTION 00200 INSTRUCTIONS TO BIDDERS PARAGRAPH TITLE PAGE NO. 1. FORMAT 3 2. SPECIFICATION LANGUAGE 3 3. GENERAL DESCRIPTION OF THE PROJECT 3 4. QUALIFICATION OF CONTRACTORS 3 5. DOCUMENT INTERPRETATION

More information

EXHIBIT WARRANTY BOND. (Address), hereinafter called Principal, and

EXHIBIT WARRANTY BOND. (Address), hereinafter called Principal, and EXHIBIT WARRANTY BOND ITEMS MDX PROCUREMENT/CONTRACT NO.: Bond No.: KNOW ALL PERSONS BY THESE PRESENTS: That we, (Name) of (Address), hereinafter called Principal, and (Name) of (Address), hereinafter

More information

COUNSEL JUDGES OPINION

COUNSEL JUDGES OPINION ELECTRIC SUPPLY CO. V. UNITED STATES FID. & GUAR. CO., 1969-NMSC-003, 79 N.M. 722, 449 P.2d 324 (S. Ct. 1969) ELECTRIC SUPPLY CO., Inc., a New Mexico corporation, Plaintiff-Appellant, vs. UNITED STATES

More information

FORM OF AGREEMENT BETWEEN CONSTRUCTOR AND OWNER

FORM OF AGREEMENT BETWEEN CONSTRUCTOR AND OWNER FORM OF AGREEMENT BETWEEN CONSTRUCTOR AND OWNER This AGREEMENT made the Day day of MONTH in the year Two Thousand Fourteen BY AND BETWEEN CONSTRUCTOR, hereinafter called the, and the Board of Regents,

More information

GIA # Execution Date:

GIA # Execution Date: GIA # Execution Date: INDEMNITY AGREEMENT This Indemnity Agreement ( Agreement ) is made as of the Execution Date set forth above by Indemnitors for the purpose of indemnifying Surety in connection with

More information

THE SERVICE INSURANCE COMPANY, INC. 80 MAIN STREET, SUITE 330, WEST ORANGE, NJ INDEMNITY AGREEMENT READ CAREFULLY

THE SERVICE INSURANCE COMPANY, INC. 80 MAIN STREET, SUITE 330, WEST ORANGE, NJ INDEMNITY AGREEMENT READ CAREFULLY THE SERVICE INSURANCE COMPANY, INC. 80 MAIN STREET, SUITE 330, WEST ORANGE, NJ 07052 INDEMNITY AGREEMENT READ CAREFULLY We, the Indemnitor(s), together with the Principal(s) named below (individually and

More information

Case 2:17-cv DB Document 48 Filed 07/12/17 Page 1 of 14 IN THE UNITED STATES COURT FOR THE DISTRICT OF UTAH CENTRAL DIVISION

Case 2:17-cv DB Document 48 Filed 07/12/17 Page 1 of 14 IN THE UNITED STATES COURT FOR THE DISTRICT OF UTAH CENTRAL DIVISION Case 2:17-cv-00207-DB Document 48 Filed 07/12/17 Page 1 of 14 IN THE UNITED STATES COURT FOR THE DISTRICT OF UTAH CENTRAL DIVISION HOMELAND MUNITIONS, LLC, BIRKEN STARTREE HOLDINGS, CORP., KILO CHARLIE,

More information

Dispute resolution. Construction Law Survival Manual. Credit Management Fair Credit Reporting Act Equal Credit Opportunity Act

Dispute resolution. Construction Law Survival Manual.  Credit Management Fair Credit Reporting Act Equal Credit Opportunity Act Dispute resolution Presented by James D. Fullerton 1 www.fullertonlaw.com JFullerton@FullertonLaw.com James D. Fullerton Fullerton & Knowles, P.C. 12642 Chapel Rd. Clifton, VA 20124 (703) 818-2600, Ext.

More information

SPECIFICATIONS. Renovations and Additions to the Coffee Springs Senior Center. Coffee Springs, Alabama. CDBG Project No.

SPECIFICATIONS. Renovations and Additions to the Coffee Springs Senior Center. Coffee Springs, Alabama. CDBG Project No. SPECIFICATIONS Renovations and Additions to the Coffee Springs Senior Center Coffee Springs, Alabama G Mark Pepe Architect 307 West Adams Street Dothan, Alabama 36303 (334) 712-9721 (334) 699-2028 Facsimile

More information

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater, Florida th st APRIL 30 & MAY 1, 2009 KNOWING WHEN TO SAY "WHEN" - PURSUING INDEMNIFICATION CLAIMS IN DIFFICULT ECONOMIC TIMES

More information

Assembly Bill No. 125 Committee on Judiciary

Assembly Bill No. 125 Committee on Judiciary - Assembly Bill No. 125 Committee on Judiciary CHAPTER... AN ACT relating to constructional defects; enacting provisions governing the indemnification of a controlling party by a subcontractor for certain

More information

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE THE FOLLOWING TERMS AND CONDITIONS, AND THOSE SPECIFIED ON THE FACE OF THIS PURCHASE ORDER, SHALL EXCLUSIVELY GOVERN THE PURCHASE OF ALL MATERIALS

More information

License Agreement. 1.4 Named User License A Named User License is a license for one (1) Named User to access the Software.

License Agreement. 1.4 Named User License A Named User License is a license for one (1) Named User to access the Software. THIS AGREEMENT is between Salient Corporation, a New York corporation with its principal office and place of business located at 203 Colonial Drive, Horseheads, NY 14845 ( Salient ) and any party that

More information

TENDER OF COMPLETION CONTRACTOR TO CITY AND RELEASE AGREEMENT. This TENDER OF COMPLETION CONTRACTOR TO CITY AND RELEASE

TENDER OF COMPLETION CONTRACTOR TO CITY AND RELEASE AGREEMENT. This TENDER OF COMPLETION CONTRACTOR TO CITY AND RELEASE TENDER OF COMPLETION CONTRACTOR TO CITY AND RELEASE AGREEMENT This TENDER OF COMPLETION CONTRACTOR TO CITY AND RELEASE AGREEMENT ( Agreement ), dated the 24th day of August, 2016, is entered into by and

More information

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION EDITION

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION EDITION [JURISDICTION] S AMENDMENTS TO AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION - 1997 EDITION This document modifies portions of the General Conditions of the Contract for Construction

More information

NAPA SANITATION DISTRICT

NAPA SANITATION DISTRICT IMPROVEMENT AGREEMENT SANITARY SEWER IMPROVEMENTS NAPA CREEK CONDOMINIUMS THIS AGREEMENT is made as of this day of, 20 by and between NCCH 103 Napa, LP, a Delaware limited partnership (" DEVELOPER ) and

More information

( ) SAP Vendor: AGREEMENT FOR INSTALLATION OF UTILITY FACILITY ON STRUCTURE

( ) SAP Vendor: AGREEMENT FOR INSTALLATION OF UTILITY FACILITY ON STRUCTURE BRIDGE D-401 AGRMT No: (8.12.2005) SAP Vendor: AGREEMENT FOR INSTALLATION OF UTILITY FACILITY ON STRUCTURE THIS AGREEMENT, numbered in COMMONWEALTH files, made and entered into this day of, by and between

More information

SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE St. Pete Beach, Florida th th MAY 4-5, 2006 PURSUIT AND PRESERVATION OF PRE AND POST DEFAULT CLAIMS AGAINST THE UNITED STATES GOVERNMENT

More information

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ]

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ] EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT IRREVOCABLE STANDBY DESIGN-BUILD LETTER OF CREDIT ISSUER PLACE FOR PRESENTATION OF DRAFT APPLICANT BENEFICIARY [ ] [Name and address of banking institution

More information

CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv NKL

CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv NKL Page 1 CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv-04100-NKL UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF MISSOURI, CENTRAL DIVISION

More information

AUBURN UNIVERSITY OFFICE OF INNOVATION ADVANCEMENT AND COMMERCIALIZATION. Ready To Sign non-exclusive licensing program

AUBURN UNIVERSITY OFFICE OF INNOVATION ADVANCEMENT AND COMMERCIALIZATION. Ready To Sign non-exclusive licensing program AUBURN UNIVERSITY OFFICE OF INNOVATION ADVANCEMENT AND COMMERCIALIZATION Ready To Sign non-exclusive licensing program Instructions for Execution 1. Save this license agreement file to your hard drive.

More information

TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS

TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS TWENTY SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater Beach, Florida RD TH APRIL 23 & 24, 2015 PRE-LOSS RECOVERY STRATEGIES PRESENTED BY: T. Bennett Acuff Erik P. Raines Hill Ward

More information

END USER LICENSE AGREEMENT FOR FOUNDRY PRODUCTS VIA ATHERA

END USER LICENSE AGREEMENT FOR FOUNDRY PRODUCTS VIA ATHERA END USER LICENSE AGREEMENT FOR FOUNDRY PRODUCTS VIA ATHERA 1. INTRODUCTION 1.1 We operate the Athera Platform ("Athera"). We are The Foundry Visionmongers Ltd., a company registered in England and Wales

More information

Precoplat GmbH General Terms and Conditions of Sale and Supply for goods and services. Revision

Precoplat GmbH General Terms and Conditions of Sale and Supply for goods and services. Revision Precoplat GmbH General Terms and Conditions of Sale and Supply for goods and services. Revision 1 28.03.2002 1 GENERAL 1.1 These General Terms and Conditions of Business or General Terms and Conditions

More information

IN THE SUPREME COURT OF THE STATE OF FLORIDA. Appellant, Case No. SC Lower Tribunal No

IN THE SUPREME COURT OF THE STATE OF FLORIDA. Appellant, Case No. SC Lower Tribunal No IN THE SUPREME COURT OF THE STATE OF FLORIDA DAVID BOLAND, INCORPORATED, vs. Appellant, Case No. SC02-2210 Lower Tribunal No. 01-17246 INTERCARGO INSURANCE COMPANY, Appellee. / ON A QUESTION CERTIFIED

More information

ANSWER TO COUNTERCLAIM BUSINESS DISPUTE

ANSWER TO COUNTERCLAIM BUSINESS DISPUTE ANSWER TO COUNTERCLAIM BUSINESS DISPUTE "Redacted" Case Document 98 Filed 09/15/10 Page 1 of 7 IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF ALABAMA SOUTHERN DIVISION v. v.,.,, Plaintiffs,

More information

ANNOTATION SDK/ACTIVEX DEVELOPMENT LICENSE AGREEMENT

ANNOTATION SDK/ACTIVEX DEVELOPMENT LICENSE AGREEMENT ANNOTATION SDK/ACTIVEX DEVELOPMENT LICENSE AGREEMENT This Software Development License Agreement ( Agreement ) is made and entered into by and between ( Licensee ), a corporation having its principal place

More information

PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C.

PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS SAMPLE. Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C. PERFORMANCE BOND FOR DESIGN-BUILD PROJECTS Document No. 620 First Edition, 2015 Design-Build Institute of America Washington, D.C. Design-Build Institute of America Contract Documents LICENSE AGREEMENT

More information

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT Case: 15-60683 Document: 00513486795 Page: 1 Date Filed: 04/29/2016 IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT Summary Calendar EDWARDS FAMILY PARTNERSHIP, L.P.; BEHER HOLDINGS TRUST,

More information

Trócaire General Terms and Conditions for Procurement

Trócaire General Terms and Conditions for Procurement Trócaire General Terms and Conditions for Procurement Version 1 February 2014 1. Contractors Obligations 1.1 The Contractor undertakes to perform its obligations arising from this Agreement with due care,

More information

2D BARCODE SDK/ACTIVEX SERVER APPLICATION DEVELOPMENT LICENSE AGREEMENT

2D BARCODE SDK/ACTIVEX SERVER APPLICATION DEVELOPMENT LICENSE AGREEMENT 2D BARCODE SDK/ACTIVEX SERVER APPLICATION DEVELOPMENT LICENSE AGREEMENT This Software Development License Agreement ( Agreement ) is made and entered into by and between ( Licensee ), a corporation having

More information

Case 1:05-cr EWN Document 295 Filed 03/22/2007 Page 1 of 12

Case 1:05-cr EWN Document 295 Filed 03/22/2007 Page 1 of 12 Case 1:05-cr-00545-EWN Document 295 Filed 03/22/2007 Page 1 of 12 Criminal Case No. 05 cr 00545 EWN IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO Judge Edward W. Nottingham UNITED STATES

More information

Settling the Hard-Fought Case

Settling the Hard-Fought Case FIDELITY AND SURETY Multiple Questions to Consider By John W. Dreste and Thomas K. O Gara Settling the Hard-Fought Case What happens when the surety compromises after the sheen fades from the principal

More information

COLOR PRINTER DRIVER FOR WINDOWS 10/8/7/Vista 32-bit and 64-bit LICENSE AGREEMENT

COLOR PRINTER DRIVER FOR WINDOWS 10/8/7/Vista 32-bit and 64-bit LICENSE AGREEMENT COLOR PRINTER DRIVER FOR WINDOWS 10/8/7/Vista 32-bit and 64-bit LICENSE AGREEMENT This Software Development License Agreement ( Agreement ) is made and entered into by and between ( Licensee ), a corporation

More information

RHODE ISLAND MECHANIC S LIEN LAW

RHODE ISLAND MECHANIC S LIEN LAW RHODE ISLAND MECHANIC S LIEN LAW 2018-2019 Go to: Rhode Island Mechanics Lien Forms: More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When

More information

MOTION OF RLI INSURANCE COMPANY TO LIFT THE AUTOMATIC STAY TO CANCEL SURETY BONDS THAT ARE FINANCIAL ACCOMMODATIONS

MOTION OF RLI INSURANCE COMPANY TO LIFT THE AUTOMATIC STAY TO CANCEL SURETY BONDS THAT ARE FINANCIAL ACCOMMODATIONS IN THE UNITED STATES BANKRUPTCY COURT FOR THE SOUTHERN DISTRICT OF NEW YORK In re: ) Chapter 11 Case No. REPUBLIC AIRWAYS HOLDINGS, INC. ) et al., ) 16-10429 (SHL) ) Debtors. ) Jointly Administered ) MOTION

More information

Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It?

Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It? Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It? by Greg Gledhill, Associate For decades, pay-if-paid and/or pay-when-paid clauses have appeared in typical construction subcontracts.

More information

Advisory. Seventh Circuit Rejects Bond Indenture and Its Waiver of Tribal Sovereign Immunity, But Allows Leave to Amend for Equitable Claims

Advisory. Seventh Circuit Rejects Bond Indenture and Its Waiver of Tribal Sovereign Immunity, But Allows Leave to Amend for Equitable Claims Advisory Insolvency & Restructuring Finance October 31, 2011 Seventh Circuit Rejects Bond Indenture and Its Waiver of Tribal Sovereign Immunity, But Allows Leave to Amend for Equitable Claims by Blaine

More information

incorporate, or which are implied by trade, custom, practice or course of dealing.

incorporate, or which are implied by trade, custom, practice or course of dealing. CUSTOMER TERMS AND CONDITIONS 1. INTERPRETATION 1.1 Definitions. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Conditions: the terms

More information

CONSTRUCTION LEGAL EDGE FALL 2008

CONSTRUCTION LEGAL EDGE FALL 2008 CONSTRUCTION LEGAL EDGE FALL 2008 This newsletter is informational only and should not be construed as legal advice. 2008, Pietragallo Gordon Alfano Bosick & Raspanti, LLP. All rights reserved. Articles

More information

Assembly Amendment to Assembly Bill No. 125 (BDR 3-588) Title: No Preamble: No Joint Sponsorship: No Digest: Yes

Assembly Amendment to Assembly Bill No. 125 (BDR 3-588) Title: No Preamble: No Joint Sponsorship: No Digest: Yes 0 Session (th) A AB Amendment No. Assembly Amendment to Assembly Bill No. (BDR -) Proposed by: Assembly Committee on Judiciary Amends: Summary: No Title: No Preamble: No Joint Sponsorship: No Digest: Yes

More information

Supplement to Report on Legal Opinions to Third Parties in Georgia Real Estate Secured Transactions

Supplement to Report on Legal Opinions to Third Parties in Georgia Real Estate Secured Transactions Supplement to Report on Legal Opinions to Third Parties in Georgia Real Estate Secured Transactions This Supplement to Report on Legal Opinions to Third Parties in Georgia Real Estate Secured Transactions

More information

TORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA. Great American Insurance Company v. General Builders, Inc.

TORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA. Great American Insurance Company v. General Builders, Inc. TORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA by Sharon A. Parker, Associate* Construction in Las Vegas is booming. There are currently over 100 major construction projects at various stages

More information