Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It?
|
|
- James Cannon
- 5 years ago
- Views:
Transcription
1 Nevada Supreme Court Declares Pay-If-Paid Clauses Unenforceable Or Did It? by Greg Gledhill, Associate For decades, pay-if-paid and/or pay-when-paid clauses have appeared in typical construction subcontracts. Beginning in the mid-1990s, however, numerous jurisdictions began ruling that such clauses are unenforceable. In 2008, the Nevada Supreme Court followed suit in the case of Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 197 P.3d 1032 (Nev. 2008), and declared that pay-if-paid clauses are unenforceable and against recognized public policy at least that is what we thought. What Are Pay-If-Paid And Pay-When-Paid Clauses? Basically, a pay-if-paid clause makes payment by and owner to a general contractor ( GC ) a condition precedent to the GC s obligation to make payment to a subcontractor ( Sub ). Under a strict interpretation of a pay-if-paid clause, if a GC is never paid by the owner, then the GC would never have a contractual obligation to pay its Sub. A pay-when-paid clause, on the other hand, is a similar, yet less foreboding payment provision. A pay-when-paid clause does not completely relieve a GC from ever making payment; it merely governs the timing of when payment becomes due. Typically, paywhen-paid provisions have been interpreted to allow a GC a reasonable amount of time to wait for owner payment before paying its Sub. Accordingly, even in the event of owner non-payment, a GC would eventually still have an obligation to pay its Sub after a reasonable time. Historically, Such Payment Provisions Have Become Increasingly Limited Even before courts began expressly ruling that pay-if-paid provisions are unenforceable, courts were historically strict in interpreting such provisions. Pay-if-paid provisions were disfavored because potentially substantial credit risks could be unintentionally shifted to an unwary Sub. See, e.g., The Thomas Dyer Co. v. Bishop Int l Eng g Co., 303 F.2d 655 (6 th Cir. 1962). Basically, court saw it as unfair to expect a Sub to bear the risk of an owner s non-payment when the Sub has a contractual relationship only with the GC. Accordingly, in most cases, pay-if-paid provisions were construed by the courts as paywhen-paid provisions. The GC was typically given a reasonable time to recover payment from the owner, particularly where the money was not being withheld by the owner as a result of the Sub s delay or defective workmanship. Yamanishi v. Bleily and Collishaw, Inc., 105 Cal. Rptr. 580 (Ca. 1972); Midland Eng g Co. v. John A. Hall Constr. Co., 398 F. Supp. 981 (D.C. In. 1975). What constitutes a reasonable time has been interpreted differently by the courts depending on the facts and circumstances of the case, but some courts have relied on the
2 limitations period for filing suit indicated in the contract or accompanying bond. Most of the cases seem to suggest that 90 days is the longest time period that would be reasonable. See AESCO Steel, Inc. v. J.A. Jones Constr. Co., 621 F. Supp (D.C. La. 1985); Howard-Green Elec. Co. v. Chaney & James Constr. Co., 182 S.E. 2d 601, 605 (N.C. 1971); John F. Sanchez Plumbing Co. v. Aetna Cas. & Surety Co., 564 So. 2d 1302, (La. Ct. App. 1990); Havens Steel Co. v. Randolph Eng r Co., 613 F. Supp. 514, 539 (D.C. Mo. 1985) ( a three month period (a calendar quarter) would be the maximum reasonable time for delay ); Moore v. Continental Cas. Co., 366 F. Supp. 954, (W.D. Okla. 1973); A.J. Wolfe Co. v. Baltimore Contractors, Inc., 244 N.E.2d 717, 722 (Mass. 1969). The first jurisdictions to declare pay-if-paid provisions absolutely unenforceable (as opposed to general trend of interpreting pay-if-paid clauses as pay-when-paid clauses) were New York and California. In 1995 and 1997, respectively, courts in New York and California voided pay-if-paid provisions as against public policy. See West-Fair Elec. Contractors v. Aetna Cas. & Sur. Co., 661 N.E. 2d 967 (N.Y. 1995) and Wm. R. Clarke Corp. v. Safeco Ins. Co., 938 P.2d 372 (Ca. 1997). The courts both based their decisions principally upon provisions of the particular state s constitution and statutes that rendered unenforceable any provision in a construction contract that purported to waive a subcontractor s rights under the protective mechanic s lien statutes. In both cases, the courts explained that where the Sub s right to receive payment has been indefinitely postponed, the Sub has essentially waived its mechanic s lien rights. Now, numerous jurisdictions across the country have expressly ruled that pay-if-paid provisions are unenforceable typically using the same mechanic s lien public policy justification. Nevada Case Law In the fall of 2008, Nevada became one of the most recent states to expressly rule on the enforceability of pay-if-paid clauses. See Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 197 P.3d 1032 (Nev. 2008). In Bovis, the Nevada Supreme Court upheld the lower court s decision that pay-if-paid provisions are unenforceable based on Nevada s strong public policy favoring a subcontractor s mechanic s lien rights. The Court stated: Because a pay-if-paid provision limits a subcontractor s ability to be paid for work already performed, such a provision impairs the subcontractor s statutory right to place a mechanic s lien on the construction project. As noted above, Nevada s public policy favors securing payment for labor and material contractors. Therefore, we conclude that pay-if-paid provisions are unenforceable because they violate public policy. Id. at 1042 (emphasis added). This straightforward language seems to be beyond interpretation. In an accompanying footnote, however, the Court also stated: FN50. We note that in 2001, the Legislature amended NRS Chapter 624 to include the prompt payment provisions contained in NRS through Pay-if-paid provisions entered into subsequent to the Legislature s amendments are enforceable only in limited
3 circumstances and are subject to the restrictions laid out in these sections. Id. at Note 50 (emphasis added). The seemingly contradictory language in the Bovis decision s main text and its footnote has left the door open for some alternative interpretations. Simplest Interpretation of the Bovis Decision Most of the confusion surrounding the Court s decision in Bovis appears to stem from the Court s failure to distinguish between pay-if-paid and pay-when-paid provisions. In Bovis, the Court refered only to pay-if-paid clauses. In the body of the decision, the Court states that such provisions are unenforceable, while in the subsequent footnote, the Court stated that such provisions are enforceable only in limited circumstances and are subject to the restrictions laid out in [Nevada s Prompt Payment Act]. This apparent inconsistency can be easily reconciled by interpreting the Court s statement in the body of the decision as referring only to pay-if-paid provisions, and the Court s statement in the footnote as referring only to pay-when-paid provisions. Under this interpretation, the Bovis decision stands for the proposition that pay-if-paid provisions are absolutely barred as against public policy, while pay-when-paid provisions may be enforceable in very limited circumstances (i.e., if they comply with the requirements of Nevada s Prompt Payment Act, NRS , and Mechanic s Lien statute, NRS 108). Of course, the restrictions and guidelines governing the timing of payment from a GC to a Sub are strictly spelled out in these statutes, and it would be very difficult to draft a true pay-when-paid provision that allowed for anything more or less than what is set forth in the statutes. Perhaps the best approach for drafters of Nevada contracts is to include a payment provision that simply requires payment in accordance with the Nevada Prompt Payment Act. This seems to be the interpretation, however, held by the majority of Nevada practitioners. Some Nevada lawyers have used an alternative interpretation of the Bovis decision to argue that pay-if-paid provisions remain enforceable in Nevada. Alternative Interpretation of the Bovis Decision Based on the apparent wording discrepancy in the Bovis decision, as well as the somewhat ambiguous wording of Nevada Prompt Payment Act, the argument has been made by at least one Nevada attorney that Bovis did not, in fact, declare pay-if-paid provisions unenforceable. See Leon F. Mead II, Nevada Construction Law, 4:14 (West 2009). This alternative interpretation presumes that the Supreme Court intentionally failed to distinguish between pay-if-paid and pay-when-paid clauses, and intended, to hold that pay-if-paid provisions remain enforceable in Nevada if carefully drafted. First, this alternative argument suggests that a cleverly written pay-if-paid provision
4 could postpone payment to a Sub without necessarily waiving the Sub s statutory mechanic s lien rights, and argues for a case-by-case evaluation of each pay-if-paid clause (similar to the Bovis Court s simultaneous decision regarding lien waiver clauses). It is not clear exactly how such a provision would have to be written, but it seems clear that it could not allow for even the potential of indefinite postponement of payment to the Sub this was precisely the Bovis Court s justification for declaring the particular pay-ifpaid clause at issue, as well as the particular mechanic s lien waiver clause at issue, unenforceable (i.e., under the mechanic s lien statute, if payment never becomes due to the Sub then arguably, the Sub could not file a mechanic s lien against the property). The second main substantive argument supporting this alternative interpretation is that the Nevada Prompt Payment Act expressly references pay-if-paid and pay-when-paid clauses, and provides specific notice and timing requirements for a contractor that stops work in response to non-payment specifically pursuant to such a provision. The Act states in pertinent part: 1. If: (b) A higher-tiered contractor fails to pay the lower-tiered subcontractor within 45 days after the 25th day of the month in which the lower-tiered subcontractor submits a request for payment, even if the higher-tiered contractor has not been paid and the agreement contains a provision which requires the higher-tiered contractor to pay the lower-tiered subcontractor only if or when the higher-tiered contractor is paid; the lower-tiered subcontractor may stop work under the agreement until payment is received if the lower-tiered subcontractor gives written notice to the higher-tiered contractor at least 10 days before stopping work. NRS (1)(b) (emphasis added). The argument that follows is essentially that because the Prompt Payment Act provides a different waiting period for a contractor to stop work when payment is withheld pursuant to a pay-if-paid clause (45 days after the 25 th day of the month during which work was performed, as opposed to the typical day waiting periods set forth under NRS ), the Nevada Legislature must have intended that pay-if-paid clauses remain enforceable. Beyond that, the Prompt Payment Act arguably only gives a contractor the right to stop work and not necessarily any direct affirmative cause of action for payment (the argument being that if withholding payment under a pay-if-paid clause was a breach of contract then the Prompt Payment Act would have specified an immediate cause of action for payment as opposed to simply stopping work). Obviously, the Nevada Legislature s provision of at least one remedy for certain conduct is not necessarily the same as condoning that conduct or excluding other available remedies. The wording of the Prompt Payment Act, however, has left the door open for these arguments. Conclusion
5 The simplest interpretation of the Bovis decision is that pay-if-paid clauses are unenforceable, but pay-if-paid clauses may be enforceable, but only if strictly consistent with Nevada s Prompt Payment Act and Mechanic s Lien Statute. The wording discrepancies in the Bovis decision and the Nevada statutes have left the door open for the alternative argument that pay-if-paid provisions remain enforceable in Nevada. These alternative arguments will likely justify further court consideration and clarification in the future. * Watt, Tieder, Hoffar & Fitzgerald, L.L.P Greensboro Drive, Suite 100 McLean Virginia
Payment Clauses for Subcontractors Vary with States
Payment Clauses for Subcontractors Vary with States Juan A. Franco JD, MSCM and Khalid Siddiqi PHD Kennesaw State University Marietta, Georgia The objective of this study was to identify the contingent
More informationWho Pays for Delay? How Enforceable is a No Damage for Delay Clause?
Who Pays for Delay? How Enforceable is a No Damage for Delay Clause? Eugene Polyak Associate Fort Lauderdale, Florida T: 954.769.5335 E: gpolyak@smithcurrie.com Delays are an all too common occurrence
More informationRe: JES Commercial, Inc. v. The Hanover Insurance Company Roanoke City Case No. CL16-108
TWENTY-THIRD JUDICIAL CIRCUIT OF VIRGINIA WILLIAM D. BROADHURST, JUDGE ROANOKE C ITY COURTHOUSE 315 C H URCH AVENUE. S.W. P.O. BOX 211 ROANOKE. VIRGINIA 24002-02ll (540) 853-2051 FAX (540) 853-1040 COMMONWEALTH
More informationContingent Payment Clauses in the 50 States
Contingent Clauses in the 50 s Published by: Foundation of the American Subcontractors Association, Inc. 1004 Duke Street Alexandria, VA 22314-3588 Telephone: (888) 374-3133 Fax: (888) 374-3133 E-mail:
More informationCRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I???
CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS Or I don't want no ConsensusDOCS bond form or do I??? Deborah S. Griffin Gina A. Fonte Holland & Knight LLP Boston, MA 02116 Presented at
More informationContingent Payment Clauses in the 50 States
Contingent Clauses in the 50 s Published by: Foundation of the American Subcontractors Association, Inc. 1004 Duke Street Alexandria, VA 22314-3588 Telephone: (888) 374-3133 Fax: (888) 374-3133 e-mail:
More informationExhibit A. Anti-Advance Waiver Of Lien Rights Statutes in the 50 States and DC
Exhibit A Anti-Advance Waiver Of Lien Rights Statutes in the 50 States and DC STATE ANTI- ADVANCE WAIVER OF LIEN? STATUTE(S) ALABAMA ALASKA Yes (a) Except as provided under (b) of this section, a written
More informationV.C. Vitanza Sons, Inc. v Liberty Mut. Ins. Co NY Slip Op 31616(U) August 24, 2016 Supreme Court, New York County Docket Number: /2015
V.C. Vitanza Sons, Inc. v Liberty Mut. Ins. Co. 2016 NY Slip Op 31616(U) August 24, 2016 Supreme Court, New York County Docket Number: 650307/2015 Judge: Ellen M. Coin Cases posted with a "30000" identifier,
More informationDISPUTES AND CLAIM RESOLUTION
1 DISPUTES AND CLAIM RESOLUTION August 14-16, 2017 Presented by: www.watttieder.com Robert M. Fitzgerald rfitzgerald@watttieder.com Carter B. Reid creid@watttieder.com 1765 Greensboro Station Place Suite
More informationConcurrent Delay The Owner s Newest Defense 1
Concurrent Delay The Owner s Newest Defense 1 James G. Zack, Jr., CCM, CFCC, FAACEI, FRICS, PMP 2 Emily R. Federico, PSP 3 ABSTRACT When owners impose liquidated damages at the end of a delayed project
More information1:14-cv LJO-GSA UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF CALIFORNIA U.S. Dist. LEXIS 57467
Page 1 AMERICAN CONSTRUCTION & ENVIRONMENTAL SERVICES., a Nevada Corporation, Plaintiff, v. TOTAL TEAM CONSTRUCTION SERVICES, INC., a California corporation; TRAVELERS CASUALTY & SURETY COMPANY OF AMERICA,
More informationYoung Electrical Contractors, Inc. v. Dustin Construction, Inc. No. 8, September Term 2017
Young Electrical Contractors, Inc. v. Dustin Construction, Inc. No. 8, September Term 2017 Contracts Interpretation Construction Contracts Conditional Payment Provisions. A contract between a general contractor
More informationIndependent Temperature Control Servs., Inc. v Alps Mech. Inc NY Slip Op 31563(U) June 1, 2011 Sup Ct, Queens County Docket Number: 1338/11
Independent Temperature Control Servs., Inc. v Alps Mech. Inc. 2011 NY Slip Op 31563(U) June 1, 2011 Sup Ct, Queens County Docket Number: 1338/11 Judge: Orin R. Kitzes Republished from New York State Unified
More informationELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE
ELEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE LIQUIDATED DAMAGES REVISITED Responses Available to the Surety Robert A. Koenig SHUMAKER, LOOP & KENDRICK, LLP 1000 Jackson Avenue Toledo,
More informationIN THE COURT OF APPEALS OF TENNESSEE WESTERN SECTION AT JACKSON
IN THE COURT OF APPEALS OF TENNESSEE WESTERN SECTION AT JACKSON FILED THE TIPTON COUNTY DEPARTMENT OF PUBLIC INSTRUCTION BY TIPTON COUNTY BOARD OF April 7, 1998 EDUCATION, Cecil Crowson, Jr. Appellate
More informationDistrict Court, Suffolk County New York, People v. NYTAC Corp.
Touro Law Review Volume 21 Number 1 New York State Constitutional Decisions: 2004 Compilation Article 15 December 2014 District Court, Suffolk County New York, People v. NYTAC Corp. Maureen Fitzgerald
More informationForeign Contractor And Subcontractor Claims Against The United States Government Part One
Foreign Contractor And Subcontractor Claims Against The United States Government Part One by John B. Tieder, Jr., Senior Partner, Paul A. Varela, Senior Partner, and David B. Wonderlick, Partner Watt Tieder
More information11/4/2015. Notice Provisions: Does Colorado Require Strict Compliance? Colorado Construction Law Update
Colorado Construction Law Update Trip DeMuth Faegre Baker Daniels Notice Provisions: Does Colorado Require Strict Compliance? 2 Notice provisions require that contractors give immediate notice of claims
More informationTORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA. Great American Insurance Company v. General Builders, Inc.
TORTIOUS BAD FAITH CLAIMS AGAINST SURETIES - NOT IN NEVADA by Sharon A. Parker, Associate* Construction in Las Vegas is booming. There are currently over 100 major construction projects at various stages
More informationInternational Construction Arbitration Alert
International Construction Arbitration Alert Concurrent Delay Is the English Court of Appeal s Clarification Conclusive? September 13, 2018 Key Points The Court of Appeal has held that a clause denying
More informationRecent Case: Sales - Limitation of Remedies - Failure of Essential Purpose [Adams v. J.I. Case Co., 125 Ill. App. 2d 368, 261 N.E.
Case Western Reserve Law Review Volume 22 Issue 2 1971 Recent Case: Sales - Limitation of Remedies - Failure of Essential Purpose [Adams v. J.I. Case Co., 125 Ill. App. 2d 368, 261 N.E.2d 1 (1970)] Case
More informationPast Due. Appellate courts appear to be limiting the reach of construction prompt payment laws. By Barbara Reeves Neal And Kenneth C.
Past Due Appellate courts appear to be limiting the reach of construction prompt payment laws By Barbara Reeves Neal And Kenneth C. Gibbs With private construction at its slowest pace in years and public
More informationUnited States v. John C. Grimberg Co.
No Shepard s Signal As of: October 23, 2017 2:19 PM Z United States v. John C. Grimberg Co. United States District Court for the Eastern District of Virginia, Alexandria Division October 19, 2017, Filed
More informationSURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017
SURETY TODAY PRESENTATION Given by Michael A. Stover and George J. Bachrach Wright, Constable & Skeen, LLP Baltimore, MD February 13, 2017 SURETY CASE LAW UPDATE WHAT WE HAVE FOUND INTERESTING OVER THE
More informationCURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv NKL
Page 1 CURTISS-MANES-SCHULTE, INC., Plaintiff, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant. No. 2:14-cv-04100-NKL UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF MISSOURI, CENTRAL DIVISION
More informationILE. Cṗr. rtettei c7.-3ocis. 132 Nev., Advance Opinion IA SEP IN THE SUPREME COURT OF THE STATE OF NEVADA
132 Nev., Advance Opinion IA IN THE THE STATE CASHMAN EQUIPMENT COMPANY, A CORPORATION, Appellant, vs. WEST EDNA ASSOCIATES, LTD., D/B/A MOJAVE ELECTRIC, A CORPORATION; WESTERN SURETY COMPANY, A SURETY;
More informationKBW ASSOCIATES, INC., Plaintiff, vs. JAYNES CORPORATION, INC., et al., Defendants. Case No. 2:13-cv GMN-CWH
Page 1 KBW ASSOCIATES, INC., Plaintiff, vs. JAYNES CORPORATION, INC., et al., Defendants. Case No. 2:13-cv-01771-GMN-CWH UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEVADA 2015 U.S. Dist. LEXIS 18220
More informationBell Prods. v. Hosp. Bldg. & Equip. Co.
No Shepard s Signal As of: January 26, 2017 12:14 PM EST Bell Prods. v. Hosp. Bldg. & Equip. Co. United States District Court for the Northern District of California January 23, 2017, Decided; January
More informationCONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT (CALIFORNIA)
CONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT (CALIFORNIA) TYPE 1 FORM - Pursuant to Civil Code 8132 (Effective 7/1/2012) NOTICE: THIS DOCUMENT WAIVES THE CLAIMANT'S LIEN, STOP PAYMENT NOTICE, AND
More informationRecent Developments in Federal and State Arbitration Law
Recent Developments in Federal and State Arbitration Law by Shelly L. Ewald, Senior Partner Watt Tieder Newsletter, Winter 2005-2006 Despite the extensive history and widespread adoption of arbitration
More informationIN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA ASHEVILLE DIVISION CIVIL CASE NO. 1:16-cv MR-DLH
IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF NORTH CAROLINA ASHEVILLE DIVISION CIVIL CASE NO. 1:16-cv-00030-MR-DLH TRIBAL CASINO GAMING ) ENTERPRISE, ) ) Plaintiff, ) ) vs. ) MEMORANDUM
More informationVolume 54, Fall 1979, Number 1 Article 13
St. John's Law Review Volume 54, Fall 1979, Number 1 Article 13 GOL 17-103(1): Contractual Provision Agreed Upon Before Cause of Action Accrued May Not Extend Statute of Limitations Notwithstanding Contrary
More informationCont Casualty Co v. Fleming Steel Co
2011 Decisions Opinions of the United States Court of Appeals for the Third Circuit 7-25-2011 Cont Casualty Co v. Fleming Steel Co Precedential or Non-Precedential: Non-Precedential Docket No. 10-4524
More informationARBITRATOR DISCLOSURE: STANDARDS AND GROWING CHALLENGES
ARBITRATOR DISCLOSURE: STANDARDS AND GROWING CHALLENGES "Do I believe in arbitration? I do. But not in arbitration between the lion and the lamb, in which the lamb is in the morning found inside the lion."
More informationIN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA SECOND APPELLATE DISTRICT DIVISION ONE B207453
Filed 4/8/09; pub. order 4/30/09 (see end of opn.) IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA SECOND APPELLATE DISTRICT DIVISION ONE RENE FLORES et al., Plaintiffs and Respondents, v. B207453 (Los
More informationTWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015
TWENTY-SIXTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE APRIL 23-24, 2015 LOSS CONTROL STRATEGIES FOR THE SURETY PRIOR TO FORMAL NOTICE OF DEFAULT OR TERMINATION TAMMY N. GIROUX, ESQUIRE Shumaker,
More informationIN THE SUPREME COURT OF THE STATE OF KANSAS. No. 113,037 SYLLABUS BY THE COURT
IN THE SUPREME COURT OF THE STATE OF KANSAS No. 113,037 WAGNER INTERIOR SUPPLY OF WICHITA, INC., Appellant, v. DYNAMIC DRYWALL, INC., et al., Defendants, (PUETZ CORPORATION and UNITED FIRE & CASUALTY COMPANY),
More informationUnited States Court of Appeals For the Eighth Circuit
United States Court of Appeals For the Eighth Circuit No. 12-1857 Southern Wine and Spirits of Nevada, A Division of Southern Wine and Spirits of America, Inc. lllllllllllllllllllll Plaintiff - Appellant
More informationSonic-Denver T, Inc., d/b/a Mountain States Toyota, and American Arbitration Association, Inc., JUDGMENT AFFIRMED
COLORADO COURT OF APPEALS Court of Appeals No. 10CA0275 Adams County District Court No. 09CV500 Honorable Katherine R. Delgado, Judge Ken Medina, Milton Rosas, and George Sourial, Plaintiffs-Appellants,
More informationBullet Proof Guaranties
Bullet Proof Guaranties David M. Mannion, Esq. DMannion@BlakeleyLLP.com Blakeley LLP 54 W. 40th Street New York, NY 10018 V. (917) 472-9587 F. (949) 260-0613 www.blakeleyllp.com New York Los Angeles Orange
More informationNOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED
NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED IN THE DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT KEL HOMES, LLC, ) ) Appellant, ) ) v. ) Case No. 2D05-3547 ) MICHAEL
More informationSecuring the Delinquent Account & Alternative Legal Theories to Collect on Delinquent Accounts
Securing the Delinquent Account & Alternative Legal Theories to Collect on Delinquent Accounts David M. Mannion, Esq. DMannion@BlakeleyLLP.com Blakeley LLP 54 W. 40th Street New York, NY 10018 V. (917)
More informationAbandonment and Cardinal Change on State and Local Construction Pro j e c t s
Abandonment and Cardinal Change on State and Local Construction Pro j e c t s AA R O N P. SI L B E R M A N Contracts for state and local public construction projects typically contain clauses stating how
More informationIN THE UNITED STATES DISTRICT COURT
W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP et al Doc. 36 IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA LYNCHBURG DIVISION W.C. ENGLISH, INC., v. Plaintiff, CASE NO. 6:17-CV-00018
More informationTWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS
TWENTY SEVENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina st nd APRIL 21 & 22, 2016 A SURETY'S RIGHT TO SETTLE CLAIMS OVER A PRINCIPAL'S OBJECTION PRESENTED BY: Amy
More informationCase 1:14-cv RJS-DBP Document 47 Filed 11/22/17 Page 1 of 12 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF UTAH NORTHERN DIVISION
Case 1:14-cv-00134-RJS-DBP Document 47 Filed 11/22/17 Page 1 of 12 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF UTAH NORTHERN DIVISION HOPE ZISUMBO, Plaintiff, MEMORANDUM DECISION AND ORDER
More informationVIRGINIA: IN THE CIRCUIT COURT OF SOUTHWESTERN COUNTY 1
VIRGINIA: IN THE CIRCUIT COURT OF SOUTHWESTERN COUNTY 1 SMOOTH RIDE, INC., Plaintiff, v. Case No.: 1234-567 IRONMEN CORP. d/b/a TUFF STUFF, INC. and STEEL-ON-WHEELS, LTD., Defendants. PLAINTIFF SMOOTH
More informationFILED. 130 Nev., Advance Opinion 57 IN THE SUPREME COURT OF THE STATE OF NEVADA AUG
130 Nev., Advance Opinion 57 IN THE THE STATE SIMMONS SELF-STORAGE PARTNERS, LLC, A LIMITED LIABILITY COMPANY; ANTHEM MINI-STORAGE, LLC, A LIMITED LIABILITY COMPANY; HORIZON MINI-STORAGE, LLC, A LIMITED
More informationAn Essential Brick and Its Chip: A Refresher on Payment Bond Claims Under the Miller Act and the "Little Miller Act"
An Essential Brick and Its Chip: A Refresher on Payment Bond Claims Under the Miller Act and the "Little Miller Act" Written By Jason T. Strickland (jtstrickland@wardandsmith.com) May 24, 2011 Introduction
More informationTWENTY SECOND ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE
TWENTY SECOND ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE nd rd SEPTEMBER 22-23, 2011 PAY-WHEN-PAID & PAY-IF-PAID CLAUSES AND THE SURETY PRESENTED BY: DARREN GRZYB, ESQUIRE Wolff & Samson PC
More informationTHIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002
THIRTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, SC April 25-26, 2002 JEWELS IN THE INDEMNITY AGREEMENT, AND A LUMP OF COAL PRESENTED BY: JOHN V. BURCH, ESQ. BOVIS, KYLE & BURCH,
More informationWhat To Do With Performance Bonds When Projects Default
What To Do With Performance Bonds When Projects Default By Gary Strong January 18, 2018, 3:12 PM EST In today s economic climate, performance bonds are important for construction contracts. While performance
More informationPritchett Controls, Inc. v. Hartford Accident & Indem. Co.
No Shepard s Signal As of: December 4, 2017 8:19 PM Z Pritchett Controls, Inc. v. Hartford Accident & Indem. Co. United States District Court for the District of Maryland November 21, 2017, Decided; November
More informationYou Have to Be Kidding Me!
You Have to Be Kidding Me! What Is the Extent of the Performance Bond Obligee s Obligations to the Surety? David D. Gilliss Pike & Gilliss LLC 600 Washington Ave Ste 303 Towson, MD 21204 Bruce W. Kahn
More informationReginella Construction Company v. Travelers Casualty & Surety Co
2014 Decisions Opinions of the United States Court of Appeals for the Third Circuit 6-11-2014 Reginella Construction Company v. Travelers Casualty & Surety Co Precedential or Non-Precedential: Non-Precedential
More informationA Second Bite At The Arbitration Apple: The AAA s New Optional Appellate Arbitration Rules
A Second Bite At The Arbitration Apple: The AAA s New Optional Appellate Arbitration Rules by Nathan W. Lambeth, Associate Watt, Tieder, Hoffar & Fitzgerald, L.L.P.* Introduction A construction contractor
More informationTWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013
TWENTY FOURTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina April 18th & 19th, 2013 DON T BE PUT OFF BY SETOFF PRESENTED BY: Toby Pilcher The Hanover Insurance Group
More informationIN THE DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FIFTH DISTRICT JANUARY TERM v. Case No. 5D
IN THE DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FIFTH DISTRICT JANUARY TERM 2004 SERETTA CONSTRUCTION, INC., Appellant, v. Case No. 5D03-1562 GREAT AMERICAN INSURANCE CO., ET AL., Appellee. Opinion
More informationRad & D'Aprile, Inc. v Arnell Constr. Corp NY Slip Op Decided on March 28, Appellate Division, Second Department
Rad & D'Aprile, Inc. v Arnell Constr. Corp. 2018 NY Slip Op 02156 Decided on March 28, 2018 Appellate Division, Second Department Published by New York State Law Reporting Bureau pursuant to Judiciary
More informationAlternative Dispute Resolution in the Employment Context
Alternative Dispute Resolution in the Employment Context By Joshua M. Javits Special to the national law journal During the last year and half, the legal environment surrounding the use of alternative
More informationIN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA ROANOKE DIVISION ) ) ) ) ) ) ) ) ) )
IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA ROANOKE DIVISION SULEYMAN CILIV, d/b/a 77 CONSTRUCTION CONTRACTING AND TRADING COMPANY, v. Plaintiff, UXB INTERNATIONAL, INC., Defendant.
More information1 of 1 DOCUMENT. CLIPPER PIPE & SERVICE, INC., Appellee v. THE OHIO CASUALTY INSURANCE CO.; CONTRACTING SYSTEMS, INC. II, Appellant. No.
Page 1 1 of 1 DOCUMENT CLIPPER PIPE & SERVICE, INC., Appellee v. THE OHIO CASUALTY INSURANCE CO.; CONTRACTING SYSTEMS, INC. II, Appellant No. 59 EAP 2014 SUPREME COURT OF PENNSYLVANIA 2015 Pa. LEXIS 1275
More information2010 CUMULATIVE SUPPLEMENT Chapter 11: Georgia Construction and Design Law
2010 CUMULATIVE SUPPLEMENT Chapter 11: Georgia Construction and Design Law IX Construction Liens Replace the first paragraph with the following: Mechanics and materialmen s liens are established by Code
More informationThird District Court of Appeal State of Florida
Third District Court of Appeal State of Florida Opinion filed June 7, 2017. Not final until disposition of timely filed motion for rehearing. No. 3D16-4 Lower Tribunal No. 15-17911 Travelers Casualty and
More informationThe Jacobs Case: Pennsylvania Contract Bond Law Goes Modern
Volume 11 Issue 1 Article 2 1965 The Jacobs Case: Pennsylvania Contract Bond Law Goes Modern Daniel Mungall Jr. Follow this and additional works at: http://digitalcommons.law.villanova.edu/vlr Part of
More informationROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE
ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE THE FOLLOWING TERMS AND CONDITIONS, AND THOSE SPECIFIED ON THE FACE OF THIS PURCHASE ORDER, SHALL EXCLUSIVELY GOVERN THE PURCHASE OF ALL MATERIALS
More informationOF FLORIDA THIRD DISTRICT JULY TERM, NORTH AMERICAN SPECIALTY ** LOWER INSURANCE COMPANY, TRIBUNAL NO ** Appellee.
NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DISPOSED OF. IN THE DISTRICT COURT OF APPEAL OF FLORIDA THIRD DISTRICT JULY TERM, 2005 WMS CONSTRUCTION, INC., ** Appellant, ** vs.
More informationBy: Professor Jean R. Sternlight University of Nevada Las Vegas Boyd School of Law
The Ultimate Arbitration Update: Examining Recent Trends in Labor and Employment Arbitration in the Context of Broader Trends with Respect to Arbitration By: Professor Jean R. Sternlight University of
More informationConsumer Class Action Waivers Post-Concepcion
Portfolio Media. Inc. 860 Broadway, 6th Floor New York, NY 10003 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Consumer Class Action Waivers Post-Concepcion Law360,
More informationCHOICE OF LAW ISSUES IN FRANCHISE AND DEALERSHIP AGREEMENTS 1. Gary W. Leydig
GARY W. LEYDIG ADVOCATE COUNSELOR TRIAL LAWYER CHOICE OF LAW ISSUES IN FRANCHISE AND DEALERSHIP AGREEMENTS 1 Gary W. Leydig The enforceability of choice of law provisions in franchise and dealer agreements
More informationSUPERIOR COURT OF THE DISTRICT OF COLUMBIA CIVIL DIVISION MICHELLE MCCRAE, et al., * * * * * * * * * ORDER
SUPERIOR COURT OF THE DISTRICT OF COLUMBIA CIVIL DIVISION MICHELLE MCCRAE, et al., v. Plaintiffs, DISTRICT OF COLUMBIA, Defendant. ORDER This attorney s fee dispute is before the court on defendant the
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 14-84C (Filed: November 19, 2014 FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, et al. v. Plaintiffs, THE UNITED STATES OF AMERICA, Defendant. Tucker Act;
More informationUTAH PARENT MAY NOT WAIVE CHILD'S NEGLIGENCE CLAIM
UTAH PARENT MAY NOT WAIVE CHILD'S NEGLIGENCE CLAIM HAWKINS v. PEART No. 01AP-422 (Utah 10/30/2001) SUPREME COURT OF THE STATE OF UTAH October 30, 2001 KEYWORDS: Utah, horse ride, waiver, child, parent,
More informationSTATE RULE(S) STATUTE(S) CASE(S) AND CLAUSES ADDRESSED
Alabama James E. Watts & Sons Contractors v. Nabors, 484 So. 2d 373 (Al. Civ. App. 1985). - Court enforces agreement whereby payment of the contractor by the owner was a condition precedent to payment
More informationCommittee Opinion October 31, 2005 PROVISION ALLOWING FOR ALTERNATIVE FEE ARRANGEMENTS SHOULD CLIENT TERMINATE REPRESENTATION MID-CASE WITHOUT CAUSE.
LEGAL ETHICS OPINION 1812 CAN LAWYER INCLUDE IN A FEE AGREEMENT A PROVISION ALLOWING FOR ALTERNATIVE FEE ARRANGEMENTS SHOULD CLIENT TERMINATE REPRESENTATION MID-CASE WITHOUT CAUSE. You have presented a
More informationTHE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL
PRIOR PRINTER'S NO. 1 PRINTER'S NO. 1 THE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL No. Session of 01 INTRODUCED BY SANTORA, DRISCOLL, SOLOMON, THOMAS, McNEILL, PASHINSKI, DUNBAR, GALLOWAY, W. KELLER,
More informationTWENTY THIRD ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE SEPTEMBER 20th - 21st, 2012
TWENTY THIRD ANNUAL NORTHEAST SURETY AND FIDELITY CLAIMS CONFERENCE SEPTEMBER 20th - 21st, 2012 OVERPAYMENT CLAIMS IN LIGHT OF RECENT FEDERAL AND STATE DECISIONS: IT'S NOT OVER PRESENTED BY: CHRISTOPHER
More informationIllinois Legal Update. Patrick M. Miller, Partner
Illinois Legal Update Patrick M. Miller, Partner ILLINOIS Legal Update Case Law Update: Limitations periods applicable to construction related and indemnification claims Strict application of affidavit
More informationFollow this and additional works at: Part of the Law Commons
Brigham Young University Law School BYU Law Digital Commons Utah Court of Appeals Briefs 2008 Miller Family Real Estate, LLC, a Utah limited liability company v. Saied Hajizadeh, an individual, and Exclusive
More informationAPPENDIX G MODEL FORM OF SMALL DIVERSE AND SMALL BUSINESS SUBCONTRACTOR AGREEMENT RECITALS
APPENDIX G MODEL FORM OF SMALL DIVERSE AND SMALL BUSINESS SUBCONTRACTOR AGREEMENT This Subcontractor Agreement ("Subcontract") is made effective as of, 20, by and between, ("Contractor") and, a Small Diverse
More information6:14-cv KEW Document 26 Filed in ED/OK on 06/17/14 Page 1 of 10 IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF OKLAHOMA
6:14-cv-00182-KEW Document 26 Filed in ED/OK on 06/17/14 Page 1 of 10 IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF OKLAHOMA (1) CHOCTAW NATION OF ) OKLAHOMA, ) ) Plaintiff, ) ) Case
More informationCONSTRUCTION DEFECT CLAIM PROCEDURES INTRODUCTION. In 1999, in response to intense lobbying by builders and builders trade organizations
CONSTRUCTION DEFECT CLAIM PROCEDURES I. INTRODUCTION In 1999, in response to intense lobbying by builders and builders trade organizations who were concerned about an increase in the costs associated with
More informationIN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT
Case: 16-30496 Document: 00513899296 Page: 1 Date Filed: 03/06/2017 IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit FILED March 6, 2017 Lyle W.
More informationBank of America frames its actions demanding that one of its customers breach a four
STATE OF NORTH CAROLINA WAKE COUNTY IN THE GENERAL COURT OF JUSTICE SUPERIOR COURT DIVISION 09-CVS-003654 MICHAEL L. TORRES, Plaintiff, v. THE STEEL NETWORK, INC., EDWARD DIGIROLAMO, BANK OF AMERICA N.A.,
More informationChicken or Egg: Applying the Age- Old Question to Class Waivers in Employee Arbitration Agreements
Chicken or Egg: Applying the Age- Old Question to Class Waivers in Employee Arbitration Agreements By Bonnie Burke, Lawrence & Bundy LLC and Christina Tellado, Reed Smith LLP Companies with employees across
More informationTWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS
TWENTIETH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Clearwater, Florida th st APRIL 30 & MAY 1, 2009 BACK TO THE FUTURE: HAS BRAMBLE REVIVED THE A311 BONDS AND DO WE REALLY WANT TO GO THERE?
More informationRobinson Bradshaw & Hinson, P.A., by Adam K. Doerr, Esq. and Stephen M. Cox, Esq., for Plaintiff.
Talisman Software, Sys. & Servs., Inc. v. Atkins, 2016 NCBC 1. STATE OF NORTH CAROLINA IN THE GENERAL COURT OF JUSTICE SUPERIOR COURT DIVISION COUNTY OF DURHAM 14 CVS 5834 TALISMAN SOFTWARE, SYSTEMS &
More informationTWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013
TWENTY FORTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE Charleston, South Carolina APRIL 18 TH & 19 TH, 2013 DRAFTING TAKEOVER AGREEMENTS TO MINIMIZE SURETY'S RISK PRESENTED BY: Rachel Walsh
More informationM. Stephen Turner, P.A., and J. Nels Bjorkquist, of Broad and Cassel, Tallahassee, for Appellant.
IN THE DISTRICT COURT OF APPEAL FIRST DISTRICT, STATE OF FLORIDA TWIN OAKS AT SOUTHWOOD, LLC, v. Appellant, NOT FINAL UNTIL TIME EXPIRES TO FILE MOTION FOR REHEARING AND DISPOSITION THEREOF IF FILED CASE
More informationETHICS OF PREPARING AGREEMENTS FOR JOINTLY REPRESENTED CLIENTS IN LITIGATION TO MAKE COLLECTIVE SETTLEMENT DECISIONS Adopted January 4, 2018
Formal Opinions Opinion 134 134 ETHICS OF PREPARING AGREEMENTS FOR JOINTLY REPRESENTED CLIENTS IN LITIGATION TO MAKE COLLECTIVE SETTLEMENT DECISIONS Adopted January 4, 2018 Question Under the Colorado
More informationSTATE OF MINNESOTA IN SUPREME COURT A Court of Appeals Wright, J. Took no part, Lillehaug, J. Safety Signs, LLC,
STATE OF MINNESOTA IN SUPREME COURT A12-0370 Court of Appeals Wright, J. Took no part, Lillehaug, J. Safety Signs, LLC, Appellant, vs. Filed: December 4, 2013 Office of Appellate Courts Niles-Wiese Construction
More informationSEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS
SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE St. Pete Beach, Florida th th MAY 4-5, 2006 PURSUIT AND PRESERVATION OF PRE AND POST DEFAULT CLAIMS AGAINST THE UNITED STATES GOVERNMENT
More informationUsing A Contractual Consequential Damage Limitation
Portfolio Media. Inc. 860 Broadway, 6th Floor New York, NY 10003 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Using A Contractual Consequential Damage Limitation
More informationINTERNATIONAL FIDELITY INSURANCE COMPANY,
Page 1 2 of 35 DOCUMENTS INTERNATIONAL FIDELITY INSURANCE COMPANY, a foreign corporation, ALLEGHENY CASUALTY COMPANY, a foreign corporation, Plaintiffs-Counter Defendants-Appellees, versus AMERICARIBE-MORIARTY
More informationPERFORMANCE & PAYMENT BONDS
310 C H A P T E R 1 3 PERFORMANCE & PAYMENT BONDS What is a Bond? INTRODUCTION The term bond can be confusing, because it has so many different meanings in various commercial contexts. A municipal bond
More informationARMED SERVICES BOARD OF CONTRACT APPEALS
ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- Tele-Consultants, Inc. Under Contract No. 000000-00-0-0000 APPEARANCES FOR THE APPELLANT: ) ) ) ) ) ASBCA No. 58129 Thomas 0. Mason, Esq. Francis E.
More informationGarnishment - State vs. Federal Procedures
Cleveland State University EngagedScholarship@CSU Cleveland State Law Review Law Journals 1971 Garnishment - State vs. Federal Procedures Timothy M. Flanagan Lawrence G. Smith Follow this and additional
More informationIN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE AUGUST 7, 2003 Session
IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE AUGUST 7, 2003 Session DEBORAH CLARK v. SUE RHEA d/b/a SURPRISE PARTIES Direct Appeal from the Chancery Court for Wilson County No. 99488 C. K. Smith,
More informationLitigation Avoidance
Litigation Avoidance 101 Thinking Through the Use of Boilerplate Provisions for Arbitration, Mediation, and Attorney Fees in Real Estate Contracts By Michael F. Donner Attorneys frequently copy standard
More informationConstruction Law Survival Manual. Reviewing and Revising Construction Contracts
Reviewing and Revising Construction Contracts Presented by James D. Fullerton 1 www.fullertonlaw.com JFullerton@FullertonLaw.com James D. Fullerton Fullerton & Knowles, P.C. 12642 Chapel Rd. Clifton, VA
More information