Abbreviated Resettlement Action Plan

Size: px
Start display at page:

Download "Abbreviated Resettlement Action Plan"

Transcription

1 August 2018 Abbreviated Resettlement Action Plan REHABILITATION OF MORAGODA ELA CROSS DRAINS PACKAGE B (BOMBE CASTLE AND HIRIBURA) IN GALLE Ministry of Megapolis and Western Development STRATEGIC CITIES DEVELOPMENT PROJECT SETHSIRIPAYA, BATTARAMULLA Rehabilitation of Moragoda Ela Cross Drains - Package B

2 Table of Contents Abbreviations... 4 A. Subproject Description... 6 I. Background... 6 II. Proposed Intervention... 6 III. Significance of the subproject IV. Scope of Proposed Civil Works ) Bombe Castle Drain ) Hiribura Cross Drain V. Socio-Economic Profile B. Legal and Regulatory Framework I. Land Acquisition Act No. 9 of II. Land Acquisition (Payment of Compensation) Regulations of III. National Involuntary Resettlement Policy IV. Involuntary Resettlement Policy (OP/BP 4.12) C. Subprojects Impacts and Mitigations Measures I. Impact of Land Acquisition and Resettlement ) Acquisition of private land ) Transfer of Government land II. Impacts on Residential, Commercial and Auxiliary Structures ) Impact on residential structures ) Impact on commercial structures ) Impact on auxiliary structures ) Impacts on Standing Trees ) Construction related impacts and mitigation measures III. Census of Project Affected Persons D. Eligibility, Compensation and Resettlement Assistance E. Consultations I. Stakeholder Consultations II. Public Consultations on Moragoda Ela Cross Drain Rehabilitation-Package B F. Institutional and Implementation Arrangements I. Dissemination of ARAP II. Maintaining Information Profile III. Grievance Redress Mechanism Rehabilitation of Moragoda Ela Cross Drains - Package B 1

3 1) Grievances redress at field level ) Grievance redresses at PIU level ) Grievance redresses to PMU level ) Independent Grievance Redress Panel (IGP) G. Monitoring and Reporting I. Resettlement database H. Resettlement Budget Annex 1: Proposed Rehabilitation Activities of Cross Drains Annex 2: Inventory of Losses Annex 3: Cabinet Approval for SCDP as Specified Project Annex 4: List of Participants at Individual Consultations Annex 5: List of Participants at Public Consultations Annex 6: Social Impact Mitigation Plan Annex 7: Pictorial representation of Project Impact Area Rehabilitation of Moragoda Ela Cross Drains - Package B 2

4 List of Figures Figure 1: Moragoda Ela and the Cross Drain Packages... 8 Figure 2: Gender composition in the Project Impact Area Figure 3: Income Categories of the households Figure 4: Monthly Incomes of PAHs Figure 5: Structure of the GRM for SCDP Figure 6: Organigram of SCDP Social Safeguard Implementation List of Tables Table 1: Design width of Moragoda Ela cross drains... 9 Table 2: Demographic profile of the GNDs Table 3: Educational levels of the Population Table 4: Livelihood activities of the households in Project Impact Area Table 5: Land Acquisition Process under Land Acquisition Act No. 9 of Table 6: Details of survey plan with number and dates Table 7: Land use pattern of the affected households Table 8: Impact of land acquisition Table 9: Details of the affected private land lots Table 10: Proportion of the loss of land Table 11: Land use pattern of the affected Government institutions Table 12: Auxiliary structures affected due to land acquisition Table 13: Details of affected trees and values Table 14: Socio-economic profile of the PAHs Table 15: Livelihoods of PAHs Table 16: Entitlement Matrix Table 17: Summary of Community Consultation Outcomes on Cross Drains - Package -B Table 18: Agencies responsible for Resettlement Plan Implementation Table 19: Monitoring Indicators of ARAP implementation Table 20: Estimated Budget for Land Acquisition and Resettlement Rehabilitation of Moragoda Ela Cross Drains - Package B 3

5 Abbreviations APs APD ARAP BP CCD CDO CEA CEB DPD DS DSD EAC EIA EM FC FGD GMC GN GOSL GRC GRM IEE IGP IR JMC KMC LA LAA LAR LARC LRC MOM&WD MOU NBRO NEA NIRP NWS&DB PAA PAP PAH PD PIA PIU PMU PPAs RR&R RAP RDA RoW RPF Affected Persons Assistant Project Director Abbreviated Resettlement Action Plan Bank Procedure Coastal Conservation Department Community Development Officer Central Environmental Authority Ceylon Electricity Board Deputy Project Director Divisional Secretariat Divisional Secretariat s Division Entitlement Assessment Committee Environmental Impact Assessment Entitlement Matrix Family Card Focus Group Discussion Galle Municipal Council Grama Niladhari Government of Sri Lanka Grievance Redress Committee Grievance Redness Mechanism Initial Environmental Examinations Independent Grievance Panel Involuntary Resettlement Jaffna Municipal Council Kandy Municipal Council Land Acquisition Land Acquisition Act Land Acquisition Regulation Land Acquisition and Resettlement Committee Local Resettlement Committee Ministry of Megapolis & Western Development Memorandum of Understanding National Building Research Organization National Environment Act National Involuntary Resettlement Policy National Water Supply and Drainage Board Project Approving Agency Project Affected Persons Project Affected Households Project Director Project Implementing Agency Project Implementation Unit Project Management Unit Project Partner Agencies Resettlement, Relocation and Rehabilitation Resettlement Action Plan Road Development Authority Right of Way Resettlement Policy Framework Rehabilitation of Moragoda Ela Cross Drains - Package B 4

6 R&R RSA SA SCDP SCSF SIA SDO SLLRDC SLR SM SSR UDA WB Resettlement and Rehabilitation Rapid Social Assessment Social Assessment Strategic Cities Development Project Strategic Cities Stakeholder Forum Social Impact Assessment Social Development Officer Sri Lanka Land Reclamation & Development Corporation Sri Lanka Rupee Samatha Mandalaya Social Screening Report Urban Development Authority World Bank Rehabilitation of Moragoda Ela Cross Drains - Package B 5

7 A. Subproject Description I. Background 1. The Strategic Cities Development Project under the Ministry of Megapolis and Western Development (MM&WB) has been initiated by the Government of Sri Lanka (GOSL) in response to the current urban problems and the emerging needs of a Middle Income Country. The total project cost amounting to US$ million is co-financed by the GOSL with US$ million and the IDA credit facility of US$ 147 million is managed by the World Bank (Project ID: P130548). The Galle City Region Development and Kandy City Region Development are the initial components of SCDP, and additional financing was provided to support the Jaffna City Region Development. 2. The above objective is to be realized through developing a system of competitive and strategically linked cities of Sri Lanka to improve urban services and public urban spaces contributing to improved livability and investment attractiveness. This concept of systemic urban development underscores triggering strategic or purposive linkages between and among the selected cities towards achieving the stated development outcomes of the project over and above the physical outputs and thereby contributing to cause or reinforce positive impacts. In this connection, the cities are placed within a framework of City Region instead of confining interventions to administrative boundaries of the local government authorities under whose jurisdiction the cities are situated. 3. The Kandy City Region Urban Interventions under SCDP supports priority improvements to relieve traffic congestion and upgrade municipal services to enhance livability and to sustain the world heritage city and its agglomeration areas. This component includes urban services improvements and public urban spaces enhancements of Kandy City Region. Among the interventions undertaken are: (i) traffic improvements, such as the rehabilitation of selected by-pass roads, and establishment and improvement of selected public transport facilities and traffic management measures; (ii) augmentation and rehabilitation of Kandy municipal water supply system; (iii) rehabilitation of major drains; (iv) urban upgrading, including the enhancement of selected streetscapes and public spaces, restoration and adaptive reuse of historic and landmark buildings, and development of an integrated master plan. 4. The Jaffna City Region Urban Intervention aims to expand urban services delivery, improve drainage systems and revival of archaeologically significant sites through key urban interventions. These include: (i) urban upgrading and restoration of important cultural heritage sites, including enhancement of public urban spaces, restoration and adaptive reuse of historic and landmark buildings, (ii) connectivity improvements such as rehabilitation of link roads, public transport and traffic management measures, and (iii) Drainage and stormwater retention ponds improvement to reduce flooding and increase retention of stormwater. Furthermore, the project would support capacity building for project implementation and technical assistance for selected interventions for Jaffna city-region development. 5. The Galle Strategic Cities Development Project focusses on the priority improvements to reduce flooding, and upgrade public urban spaces to improve and sustain the City Region. This component includes: i. Flood reduction measures, including the rehabilitation of selected canals and surface drainage infrastructure; ii. Coastal erosion reduction measures for selected areas; iii. Urban upgrading, including the enhancement of selected streetscapes and public spaces, restoration and adaptive reuse of historic and landmark buildings, and development of an integrated master plan. II. Proposed Intervention Rehabilitation of Moragoda Ela Cross Drains - Package B 6

8 6. The drainage system in Galle municipal area comprises a network of large and small open canals and marshy land. The drainage network of the city consists of three major streams- Moragoda Ela, Moda Ela and Kepu Ela. The drainage network is managed by the Galle Municipal Council except for Moragoda Ela, which is managed by the Provincial Irrigation Department (PID). These streams take the excess stormwater from cross-drains, which are fed by the outflow from roadside drains, into the sea. Water in these streams is polluted, with wastewater and solid and liquid waste coming from the city centre and residential areas. The Galle drainage system is poorly maintained, partially lined and in most of the sections have insufficient capacity to transfer stormwater. The existing rainfall retention areas are disappearing rapidly due to landfill and construction of houses and commercial buildings. 7. Under the proposed sub-project, the following activities have been prioritized: i. Rehabilitation of Moragoda Ela ii. Reconstruction of Bridges across Moragoda Ela iii. Improvement of Moda Ela and Kepu Ela iv. Improvement of Cross Drains connected to Moragoda Ela v. Improvement of Cross drains linked to Moda Ela and Kepu Ela vi. Conservation of eight water retention areas 8. There are 24 cross drains linked to Moragoda Ela. These cross drains have a major role in flood mitigation and drainage improvement in the Moragoda Ela basin as well as in the Galle city. Improvement of Cross Drains connected to Moragoda Ela has been segmented into six separate packages/ sub-projects for the convenience of implementation as well as by considering the engineering and management aspects such as avoiding traffic congestion during construction, easy management of construction and to facilitate for the engagement of local small-scale contractors. Figure 1 shows the Moragoda Ela, and the 24 cross drains connected to Moragoda Ela in package wise. Rehabilitation of Moragoda Ela Cross Drains - Package B 7

9 Figure 1: Moragoda Ela and the Cross Drain Packages 9. The existing drainage system Rehabilitation of Moragoda Ela cross drains-package B of Galle City is an open canal system comprising two cross drains. They are the open drains of Bombe Castle and Hiribura. These two cross drains cut across the Grama Niladhari Divisions (GNDs) of Maitipe, Maligaspe west, and Deddugoda North and Deddugoda South. 10. The two cross drains are laid on a flat ground profile, and the gradient of the cross drains are very low. The drain cross-section survey carried out by design consultant shows that the bed level of Bombe Castle drain varies between 3.2 m to -0.5 m above Mean Sea Level (MSL). The bed level of Hiribura cross drain varies from -0.3m to 1.2m MSL with a low gradient. 11. The Bombe castle drain that starts from Labuduwa road near Karapitiya bus station flows through Maitipe GND of Kadawasathara Divisional Secretariat Division (DSD). The chainage from m to m of the drain section is already constructed with covered concrete drain, and therefore no intervention from the SCDP is required. However, after that, the drain passes through residential areas (0+097 m to m) and paddy fields (0+301 m to m). This paddy land consists of both cultivated and abandoned paddy lands. The two retention areas which are identified to develop under SCDP s Galle drainage components are located within this area. The drain flows through the residential areas in Maligaspe West GND and connects to Hiribura drain at chainage m (near Richmond city). The connecting point of the two drains is a marshy land. One retention area of the Galle drainage component is located at this point. After merging the two drains at Richmond city area, it links to Moragoda Ela near Didiswatta. Therefore, the water flow of both drains is significantly affected by the tidal effects and the water level of Moragoda Ela. This tidal effects and the water level of Moragoda Ela retard the conveyance of the flood flow of both sections of the drains. 12. There are eight pipe culverts across Bombe castle drain of which seven culverts have to be replaced with box culverts. The wastewater and sewerage water of Karapitiya hospital is discharged to the Bombe castle at chainage m which has caused unpleasant environment and health problems to about ten households located in the vicinity. This section of the drain had been rehabilitated as an open concrete drain using government funds by Galle - Kadawathsathara Divisional Secretary s office in July 2016, but it is insufficient for the efficient conveyance of the water flow. The access road and the Rehabilitation of Moragoda Ela Cross Drains - Package B 8

10 drain section have to be rehabilitated for better conveyance of the flow and to minimize inconveniences caused to the community. 13. The Hiribura cross drain starts from Hirubura junction and passes through residential areas of Deddugoda North GND. Thereafter it passes through commercial areas and crosses the Hiribura cross road at chainage m. From m to m, the drain section runs through the residential areas in the Deddugoda South GND and beside the Galle Municipal Council (GMC) road. The drain section from m to m (where it merges with Bombe castle) runs through a marshy land. There are five existing pipe culverts which need to be replaced with box culverts for the smooth flow of water. There is a temporary bridge constructed over the Hiribura drain at chainage m to provide access to Dombagahaliyyadda road which requires improvements to enhance the connectivity. 14. The catchment area of the Bombe castle and the Hiribura drains are changing rapidly due to extensive construction of houses and other commercial buildings. The marshy and low-lying areas, which are unsuitable for construction purposes have been filled up with soil resulting in the loss of water retention capacity of the catchment area. As a result of increasing built-up areas, the infiltration of rainwater is less while the runoff is quick and high. Hence the existing drain becomes incapable of transferring the flood flow, even during a low rainfall resulting in flooding in the area. There is no proper maintenance of the drains. Since the drain flows through areas with high population density and urban areas, the drain also gets easily polluted. Non-decaying pollutants like plastic bags, cans, bottles get entrapped and act as a barrier for free water flow, and further contributes to the deposit of more pollutants. Also, some of the pollutants add nutrients to the water weeds which enhance the trapping of the solid pollutants. It is also observed that vegetation at drain banks affects the smooth flow. Hence, proper maintenance of the drain, preserving the retention areas, improving the drain banks, identifying proper locations for smooth flow conveyance are essential for sustainable flood mitigation. 15. The overall objective of the proposed project is to initiate a sustainable solution for preventing flooding in the area. During flood affected periods, properties and assets of the people get damaged causing not only financial problems but also disturbance to normal lives of the people. Once the flood is gradually drained off, severe health and sanitation issues and water-borne diseases like fever, diarrhoea, Hepatitis, Dengue etc., and many kinds of skin diseases spread over causing a vulnerable situation in the area. According to the Medical Officer of Health (MOH) in GMC, a considerable percentage of dengue prevention costs in GMC area is spent in the surrounding areas of Bombe Castle, and Hiribura drains. The groundwater table is comparatively high in this area, and the overflow of toilet pits creates severe health and environmental problems. 16. The main Project Partner Agency (PPA) of cross drain rehabilitation is the Galle Municipal Council (GMC). The Lanka Hydraulic Institute (LHI) is the design consultant of this subproject. 17. The design width of the rehabilitation of Moragoda Ela cross drains is shown in Table 1. The resettlement impacts were identified in places where the design width exceeds the existing Right of Way (ROW). The design width of the drains is also not consistent and varies as shown in Table 1. Table 1: Design width of Moragoda Ela cross drains Drain Width Design width of the Drain of Bombe Castle 2.5m- 5.0m Design width of the Cross Drain of Hiribura 1.0m- 4.0m Source: SCDP/Galle Cross Drains Design Report Rehabilitation of Moragoda Ela Cross Drains - Package B 9

11 III. Significance of the subproject 18. The rehabilitation of the cross drains is necessary because of the following reasons. The existing drainage system of Galle City has not been systematically designed to carry stormwater. Water in these drains is polluted, with wastewater, and solid and liquid waste coming from the city and residential areas. Galle drainage system is poorly maintained, partly lined and at most of the sections have insufficient capacity to transfer stormwater. Available rainfall retention areas are disappearing rapidly due to landfill and construction of houses and commercial buildings. 19. The condition of Bombe Castle and Hiribura drains significantly contribute to flooding near the Karapitiya bus station, Peter Kiringoda road, Dombagahaliyadda area, Hiribura junction and Hiribura crossroad near Galagediya junction during the rainy season. The Galle - Hiribura - Baddegama road which connects some small towns and transportation services between Hiribura-Baddegama, Karapitiya- Kalegana and Karapiptiya-Ambalangoda are disturbed during the flooding of Hiribura cross drain at Hiribura junction and near Karapitiya bus station. The records of the Southern Province Passengers Transport Authority reveal that nearly 60 public transport buses use this road in a day. A considerable number of other types of vehicles also use this road. 20. The Hirbura crossroad also goes under floods at Galagediya junction during heavy rains and significantly impacts on the public transportation on the Hiribura crossroad. The road provides connectivity to Galle town and the following peripheral cities of Galle: Galle to Yakkalamulla, Akuressa Galle to Mapalagama Galle to Yakkalamulla Galle to Waduramba, Baddegama Galle to Waduramba, Yakkalamulla Galle to Thalagaha Galle to Pitigala Galle to Karapitiya via Richmond Kanda 21. The road also provides access to distant areas, such as Kataragama, Tissamaharama, Hambantota etc. In addition, it provides access to important institutions, such as Karapitiya Hospital, Medical Faculty, Labuduwa Agricultural farm, Provincial administrative complex, Agrarian service centre, Labudoowa Siridhamma School and seven other leading schools in the city. According to the records of the Southern Province Passengers Transport Authority, nearly 75 turns of public transport buses drive on this road per day. A considerable number of other types of vehicles also use this road. 22. The Peter Kiringoda road which connects with Anagarika Dharmapala road and Maitipe road get flooded due to the overflow of Bombe Castle drain during heavy rain, and it disturbs the day to day activities of residents of the area. The residential area of Dombagahaliyadda goes under water due to flooding from the two drains. 23. This drainage system is now dilapidated, has failed sections, eroded banks, and bottlenecks due to silting. The tidal effects and the flood level of Moragoda Ela retard the drainage system of Bombe Castle, and Hiribura drains. In addition to stormwater, wastewater and sewerage water are discharged to this drain system by the residents of either side without first being adequately treated for effluents. Frequent floods during the rainy season are a common experience. The drains are highly polluted, prone to floods and a potential health hazard. Rehabilitation of Moragoda Ela Cross Drains - Package B 10

12 IV. Scope of Proposed Civil Works 1) Bombe Castle Drain 24. The rehabilitation of the Bombe castle drain subproject involves: (a) de-silting and deepening, (b) concrete lining of drain bed and walls at identified places, (c) replacing seven pipe culverts with box culverts, (d) reconstruction of damaged common structures up to better condition, and (e) earthen embankment protection for selected drain stretch. 2) Hiribura Cross Drain 25. The rehabilitation works involve: (a) de-silting and deepening, (b) concrete lining of drains beds and walls, (c) construction of house access, (d) reconstruction of damaged boundary walls of project affected persons (APs) at identified places, (e) replacing five existing pipe culverts with box culverts and (d) rehabilitation of temporary bridge at Dombagahaliyadda Road. 26. The estimated cost of the drain rehabilitation is SLRs 144 million and will be implemented by Strategic Cities Development Project under the Ministry of Megapolis and Western Development. The project Partner Agency (PPA) is Galle Municipal Council (GMC). The project is scheduled to be implemented over a period of 12 months beginning November The proposed rehabilitation activities of the cross drains are explained in Annex 1. V. Socio-Economic Profile 27. The project impact area of Moragoda Ela Cross Drains- Package B is the GNDs of Maitipe, Deddugoda South, Deddugoda North, and Maligaspe of Kadawasathara DSD. The population of Maitipe and Maligaspe is predominantly Sinhalese, and the Muslims represent the majority in Deddugoda North. The population of the four GNDs is about 8,520 and the total number of households is 1,857. Table 2 presents the demographic profile of the GNDs that fall within the project impact area. Table 2: Demographic profile of the GNDs GND Sinhalese Tami Muslim Others Total Female Male HH l HH HH HH HH Population Population Total Maitipe ,796 Deddugoda South ,658 1,161 2,819 Deddugoda North ,577 1,348 2,925 Maligaspe Total 1, ,857 4,623 3,897 8,520 Source: Resource Profile 2016, Kadawathsathara Divisional Secretariat Division of Galle 28. The population characteristics of the area reflect a higher percentage of female population compared to their counterpart male population. However, the female population (49%) of Maitipe is lower than the male population. The percentage of the female population (59%) is significantly high in Deddugoda south compared to the other 3 GNDs. Figure 2 shows the gender composition of the population in the project impact area. Rehabilitation of Moragoda Ela Cross Drains - Package B 11

13 Figure 2: Gender composition in the Project Impact Area 60% Female, 49% Female, 59% Female, 54% Female, 53% Female, 54% 50% 40% 30% Male, 51% Male, 41% Male, 46% Male, 47% Male, 46% 20% 10% 0% Maitipe Deddugoda South Deddugoda North Maligaspe Total Female Male 29. The population below five years and non-schooling children constitutes 683 (8%) of the total population. The proportion of the population who had never been to a school is 24 (0.3%). The educational achievements of the rest include: 829 (9.7%) who had studied between Grades 1 to 5, 1,685 (19.8%) between Grades 6 to 10, 2,357 (27.7%) who had completed the General Certificate of Education (Ordinary Level), 2,262 (26.5%) who has reached the General Certificate of Examination (Advanced Level) and 680 (8%) who holds a university degree (Table 3). Table 3: Educational levels of the Population Project Impact Area (n=8,520) Level of Education Persons Percentage No Schooling Child (Age 0-5 Years) Never been to School Grade Grade , Passed GCE O/L 2, Passed GCE A/L 2, Graduates/ Post Graduates Source: DSD Resource Profile Table 4 presents the livelihood activities of the households in the project impact area. The majority of the labour force (58.3%) is employed in government, semi-government and private sector jobs claiming a fixed monthly income. The second highest category of the labour force constitutes people engaged in labour work and comprises 25.8%. People engaged in the agricultural sector (1.9 %) and the industrial sector (1.1%) is only a few. Business activities are the source of income for 4.6% of households whereas another 8.2 % of households are engaged in self-employment. Rehabilitation of Moragoda Ela Cross Drains - Package B 12

14 Table 4: Livelihood activities of the households in Project Impact Area Project Impact Area(n= 1,857) Occupation HHs Percentage Agriculture Labour work Government jobs Semi Government jobs Private Sector jobs Self-Employment Industrial Business Source: DSD Resource Profile Figure 3 presents the income status of the households in the project impact area. Monthly incomes of 9.8% households are more than SLR 50,000/- whereas another 17.1 % of households earn SLR. 25,000/- to SLR. 50,000/-. The monthly household income of 41.3 % range between SLR. 15,000/- to SLR. 25,000/- and they represent the largest income group of the population. About 19.1 % of the households and 11.3 % of the households earn SLR. 10,000/- to SLR. 15,000/- and SLR 5,000/- to SLR. 10,000/- respectively. Nearly 1.5 % of the households earn less than SLR. 5,000/- per month and represent the lowest income 1 group of the population. The resource profile of the Divisional Secretariat Division in 2016 revealed that 15.4% of households in this project impact area receive government s Samurdhi food subsidies given for households living below the poverty line. Figure 3: Income Categories of the households 45.0% 40.0% 35.0% 30.0% 25.0% 20.0% 15.0% 10.0% 5.0% 0.0% < 5,000/- 10,000/- 5,000/- 15,000/- 10,000/- 25,000/- 15,000/- 50,000/- 25,000/- > 50,000/- Income level 1 Source: Resource Profile 2016, Divisional Secretariat Division, Kadawathsathara-Galle Rehabilitation of Moragoda Ela Cross Drains - Package B 13

15 B. Legal and Regulatory Framework 32. The rehabilitation of Moragoda Ela cross drains - Package-B requires the acquisition of private land, partial demolition of a few residential and commercial structures and partial and full demolition of auxiliary structures owned by private households. The land acquisition process will be governed by the Land Acquisition Act No.9 of 1950 while the compensation for acquired properties and loss of other properties will be paid as per the provisions in the Land Acquisition (Payment of Compensation) Regulations of 2013, National Involuntary Resettlement Policy (NIRP) of 2001, the World Bank s Operational Policy 4.12 on Involuntary Resettlement, and the Resettlement Policy Framework prepared for the overall project. These instruments will also help to ensure that the rights of project affected persons (PAPs) are not violated and that they are not impoverished in the course of subproject implementation. This ARAP is prepared in compliance with those policies. I. Land Acquisition Act No. 9 of The Land Acquisition Act (LAA) of 1950 as amended in 1986 provides for the acquisition of private land and servitudes for public purposes. It provides the payment of compensation at market rates for lands, structures and crops. The LAA gives directives for the acquisition of land in the public interest and provides benefits to both titleholders and non-titleholders. (Table 5 for details) Table 5: Land Acquisition Process under Land Acquisition Act No. 9 of 1950 No. Activity Responsibility 1. Conduct land investigation SCDP 2. Prepare application for acquisition of land for a public purpose on behalf SCDP of the Secretary of line ministry (MM&WD) with details of land extent, current situation, boundaries, names & addresses of landowners/claimants, estimated cost & source of payment (Form GAL 29) 3. Apply to the secretary, Ministry of Land (MOL) Secretary, MM&WD 4. Apply with his/her recommendation to the Minister, MOL Secretary, MOL 5. Authorization for acquisition of land under Section 2 of LAA Minister, MOL 6. Produce Section 2 Notice to the acquiring officer indicating the intention MOL of acquisition 7. Exhibit Section 2 Notice in Sinhala, English and Tamil languages in the project area and send copies to claimants DS- Kadawathsathara 8. Request District Superintendent of Surveys to prepare Advance Tracing DS- Kadawathsathara 9. Survey the land and prepare the Advance Tracing Superintendent of Surveys 10. Produce Section 5 Notice to proceed with the acquisition Minister, MOL 11. Exhibit Section 5 Notice in Sinhala, English and Tamil languages in the project area DS- Kadawathsathara 12. Request Superintendent of Surveys to prepare a preliminary plan under Section 6 DS- Kadawathsathara 13. Survey the land, prepare the preliminary plan and submit to the acquiring officer and MOL Superintendent of Surveys 14. Issue the notice of land acquisition under Section 7 in Sinhala, English and Tamil in the Government Gazette, exhibit the Notice in the project area and send copies to MOL and call for submission of claims by interested parties/claimants 15. Conduct inquiries under Section 9 to determine the ownership rights of the land and the compensation payable DS- Kadawathsathara DS- Kadawathsathara 16. Issue the notice of ownership status of the land under Section 10(1)(a) DS- Kadawathsathara Rehabilitation of Moragoda Ela Cross Drains - Package B 14

16 No. Activity Responsibility 17. Request Chief Valuer to determine the compensation for the property to be acquired. DS- Kadawathsathara 18. Conduct the valuation of the land and other properties Valuation Dept 19. Send the valuation report to the acquiring officer Valuation Dept 20. Issue the Section 17 award letter indicating the eligible compensation to PAPs. DS- Kadawathsathara 21. Apply for a Gazetted Ministerial order to take possession of the land Secretary, MM&WD 22. Provide a Ministerial order in Gazette to take possession of the land MOL 23. Take over the possession of the land on behalf of State under Section 38 DS- Kadawathsathara 24 Vesting the possession of the property with the applicant organization by way of a certificate under Section 44 which constitutes a legal title for the land DS- Kadawathsathara Source: SCDP, Land Division 34. Land Acquisition Regulations of 2008, issued under Section 63 (2) (f) of LAA 1950 and came into effect on 17 March 2009 incorporate provisions for statutory payments for compensation. It provides provisions for compensation beyond market value by incorporating: compensation for injurious affection and severance (equivalent to the full cost of damage based on the market value of land acquired), disturbances (in terms of Section 3.11, principle based on the value to owner of the property affected as per the written claims submitted by the AP: Gazette notification No.1596/12 of ), reconstruction costs calculated without depreciation, valuation of the affected plot of land at proportional unit cost, together with compensation for business losses and relocation. II. Land Acquisition (Payment of Compensation) Regulations of The Regulations of 2013 provides for a comprehensive compensation package following the land acquisition. The 2013 Regulations permitted development projects to be designated as specified projects by the Ministry of Lands with the ratification of the Parliament of Sri Lanka. SCDP has been recognized as a specified project by Cabinet Paper Ref. No. 15/0773/614/022 dated 24th June The specified projects qualify to establish Land Acquisition and Resettlement Committees (LARC) in the divisional secretariat divisions where the persons affected by land acquisition can make their representations. Affected parties also have the opportunity to appear before the LARC proceedings and those dissatisfied with LARC decisions on compensation may appeal to the Super LARC established at the national level. 36. The LARC system provides a mechanism for the parties affected by land acquisition to appeal for a higher compensation if they were dissatisfied with the statutory compensation paid to them under the Land Acquisition Act (LAA) of The LAA of 1950 provides only a limited appeal process for aggrieved parties through the Land Acquisition Review Board (LARB) which is hardly accessible to many affected parties (APs) particularly the poor and vulnerable due to cost and time. Instead, the LARC established at divisional secretariat level and chaired by the divisional secretary is easily accessible to APs where he/she will be given an opportunity to make their representations during LARC proceedings. Participation in LARC proceedings has a minimum cost to the APs, and he/she can present their grievances and needs before the LARC committee. The LARC is constituted by the Divisional Secretary or Assistant Divisional Secretary of the relevant Divisional Secretary s Division, the Surveyor General or his nominee, the Chief Valuer or his nominee and an officer not below the rank of the Assistant Secretary nominated by the Minister to whom the subject of the respective specified project has been assigned. LARC offers an exgratia package of compensation which among others include compensation for land, encroached state land, paddy land, buildings and structures, rent-controlled premises under the Rent Act, loss of business and livelihoods, allowances for vulnerable families, loss of wages and employment, ex-gratia payments Rehabilitation of Moragoda Ela Cross Drains - Package B 15

17 for handing over possession of property before the deadline, payments for relocation and self-relocation etc. III. National Involuntary Resettlement Policy The National Involuntary Resettlement Policy (NIRP) 2001 represents a significant milestone in the development of a systematic approach to addressing resettlement issues in Sri Lanka. The Policy thus ensures that (i) project affected persons are adequately compensated, relocated and rehabilitated; (ii) delays in project implementation and cost overruns are reduced; and (iii) better community relations are restored. It aims at ensuring that people affected by development projects are treated in a fair and equitable manner, and ensuring that they are not impoverished in the process. The Policy also enables establishing the framework for project planning and implementation that would meet international best practices in involuntary resettlement. The responsibility for reviewing and approving RAPs is vested with the Ministry of Land and Land Development. 38. The main principles of NIRP that apply to the present project are as follows: Avoid, minimize, and mitigate negative involuntary resettlement impacts by reviewing alternatives to the project Ensure that the affected persons (APs) are fully and promptly compensated and successfully resettled, their livelihoods are re-established, and their standard of living is improved Assist the APs in dealing with psychological, cultural, social, and other impacts caused by compulsory land acquisition and resettlement A commitment to gender equality and equity. Affected persons should be fully involved in the selection of relocation sites, livelihood compensation and development options at the earliest opportunity. Establish an accessible grievance redress mechanism in each development project. Resettlement should be planned and implemented with the full participation of the provincial and local authorities. Participatory measures should be designed and implemented to assist those economically and socially affected to be integrated into the host communities. Resettlement should be planned as a development activity for the affected persons. Affected persons who do not have title deeds to land should receive fair and just treatment. Vulnerable groups should be identified and given appropriate assistance to improve their living standards. Project Executing Agencies should bear the full costs of compensation and resettlement. IV. Involuntary Resettlement Policy (OP/BP 4.12) 39. The World Bank operational policy on Involuntary Resettlement (OP 4.12) seeks to: (a) avoid where feasible or minimize involuntary resettlement, exploring all viable alternative project designs; (b) if not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programmes providing sufficient resources to enable the displaced persons to share in project benefits; (c) ensure that the displaced persons are informed about their options and rights pertaining to resettlement; (d) meaningfully consult the displaced persons and provide them with opportunities to participate in the planning and implementation of resettlement programmes; (e) assist the displaced persons in their efforts to improve their standards of living or at least to restore them, in Rehabilitation of Moragoda Ela Cross Drains - Package B 16

18 real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. 40. The policy covers both direct economic and social impacts that are caused by involuntary taking of land, resulting in (i) relocation or loss of shelter; (ii) loss of assets or access to assets; or (iii) loss of income sources or means of livelihoods, whether or not the affected persons must move to another location; or (iv) the involuntary restriction of access to legally designated parks and protected areas resulting in adverse impacts on the livelihoods of the displaced persons. 41. In order to address the above impacts, the policy requires the borrower to prepare a resettlement plan that includes measures to ensure that the displaced persons are (i) informed about their options and rights pertaining to resettlement; (ii) consulted on, offered choices among various resettlement options, and provided with technically and economically feasible resettlement alternatives; and (iii) provided prompt and effective compensation at full replacement cost for losses of assets attributable directly to the project. 42. The policy requires that if the impacts include physical relocation, the resettlement plan should include measures to ensure that displaced persons are (i) provided assistance (such as moving allowances) during relocation; and (ii) provided with residential housing, or housing sites, or, as required, agricultural sites for which a combination of productive potential, locational advantages, and other factors are at least equivalent to the advantages of the old site. Furthermore, they should be offered (i) support for a transition period, based on a reasonable estimate of the time likely to be needed to restore their livelihoods and standards of living; and (ii) development assistance in addition to compensation measures such as land preparation, credit facilities, training, or job opportunities. Particular attention should be paid to the needs of vulnerable groups among those displaced, who may not be protected through national land compensation legislation. 43. If land is not the preferred option of the displaced persons, or sufficient land is not available at a reasonable price, non-land based options built around opportunities for employment or self-employment should be provided in addition to cash compensation for land and other assets lost. 44. Payment of cash compensation for lost assets may be appropriate where (i) livelihoods are land based but the land taken for the project is a small fraction of the affected asset and the residual is economically viable; (ii) active markets for land, housing, and labor exist, displaced persons use such markets, and there is sufficient supply of land and housing; or (iii) livelihoods are not land-based. Cash compensation levels should be sufficient to replace the lost land and other assets at full replacement cost in local markets. 45. The policy also requires that compensation and other assistance required for relocation be paid and completed, prior to displacement and provision of resettlement sites with adequate facilities, where required. In particular, taking of land and related assets may take place only after compensation has been paid and, where applicable, resettlement sites and moving allowances have been provided to the displaced persons. 46. Displaced persons eligible for compensation would include (i) those who have formal legal rights to land (including customary and traditional rights recognized under the laws of the country); (ii) those who do not have formal legal rights to land at the time the census begins but have a claim to such land or assets provided that such claims are recognized under the laws of the country or become recognized through a process identified in the resettlement plan; and (iii) those who have no recognizable legal right or claim to the land they are occupying. 47. The Resettlement Policy Framework (RPF) prepared under SCDP is in compliance with both the national regulations as well as World Bank s OP 4.12, and accordingly requires that all social safeguards interventions will follow the guidelines stipulated in the RPF. Accordingly, this Abbreviated Resettlement Rehabilitation of Moragoda Ela Cross Drains - Package B 17

19 Action Plan (ARAP) guided by the RPF, incorporates measures that will be taken to ensure that those affected by the project are informed, consulted and provided compensation and other assistance at full replacement cost for losses attributable to the project. The ARAP includes an Entitlement Matrix (EM) that sets the parameters for providing compensation for persons affected by the project, including compensation for loss of land, structures and other assets at replacement cost as determined by the LARC. 48. Whereas LAA remains the main legal procedure for acquiring private land required for the Project, the affected persons and households will receive compensation and resettlement benefits as per the Entitlement Matrix given in this ARAP irrespective of their title or occupancy status before losing shelter, business, assets, and incomes due to this subproject. Specifically, the EM presents the categories of affected persons eligible for compensation and their corresponding losses. 49. The ARAP was developed based on a census survey conducted with persons/households affected by land acquisitions and consultations conducted with relevant stakeholders. Land acquisition process for this subproject including payment of compensation due to PAPs is scheduled to be completed by 31 st August Rehabilitation of Moragoda Ela Cross Drains - Package B 18

20 C. Subprojects Impacts and Mitigations Measures I. Impact of Land Acquisition and Resettlement 50. This chapter describes the resettlement impacts to be caused by land acquisitions for the subproject. The social impact assessment was conducted based on the surveys described in Table 6. Table 6: Details of survey plan with number and dates Bombe Castle Drain Hiribura Cross Drain Advance Tracing Number: GA/GFG/2017/645 Survey Requisition Number: DA/GFG/L&L/05/90, /33 Advance Tracing Number: GA/GFG/2017/515 Survey Requisition Number: DS/GFG/L&L/05/89, /26 Advance Tracing Number: GA/GFG/2017/826 Survey Requisition Number: DS/GFG/L&L/05/100, /26 Source: Department of Surveys 51. The total extent of the land to be acquired for the subproject is perches (0.367ha) (109 land lots) of which perches (0.253ha) (81 land lots) is owned by 52 households and perches (0.115ha) (28 land lots) by three different government institutions (NHDA, RDA and GMC). 1) Acquisition of private land 52. The land use pattern of the properties to be acquired from households is shown in Table 7. There are 81 land lots owned by 52 private households. Of these 81 lots, 53 lots are used for residential purposes and as home gardens by 39 households. Three other households use their respective 03 land lots for both residential and commercial purposes. Another household uses their land lot for agricultural purposes. There are also another 23 land lots owned by eight households which are vancant/unused plots. The remaining 1 household uses its land lot as access road to their house. Though the land acquisition causes loss of the existing access road to the household, an alternate access road can be established in the remaining portion of the land without any significant change to the existing land use pattern of the remaining land. Table 7: Land use pattern of the affected households Land use No. Lots Land extent (in perches) No. PAPs Residential and home gardens Residential and commercial Vacant and not used for any productive purpose Cultivations Access road Total Source: Survey Plan, July Specifically, the losses incurred by the 52 households (189 persons) from land acquisition includes: (i) partial damages to two residential dwellings; (ii) partial damages to three commercial buildings; and (iii) full damages to 49 auxiliary structures of 24 residential dwellings. Furthermore, land acquisitions will also cause removal of 88 timber and fruit-bearing trees belonging to 23 out of the 52 households and the loss of an access road to one household. In addition, a fish vendor will be temporarily affected due to canal construction work (described later in paragraph 59), whose household comprises 3 Rehabilitation of Moragoda Ela Cross Drains - Package B 19

21 members. All affected households are titleholders. Besides these losses, the acquisition process will not result in physical displacements or relocation of the affected households. 53. Compensation for loss of built structures, livelihoods, trees, and the access road will be determined by LARC at replacement cost as per the Land Acquisition and Payment of Compensation Regulations of 2013 and the RPF prepared for SCDP. Transfer of the government land to the subproject referred to above will not cause any loss of built structures. Table 8 summarizes the impacts of land acquisition on the 52 households. Table 8: Impact of land acquisition Impact No. Units No. Affected households Partial damages to residential structures 2 2 Partial damages to commercial structures 3 3 Full damages to auxiliary structures 45 Partial damages to auxiliary structures 4 24 Loss of standing trees Loss of access road Source: Census survey of PAPs August For the 52 private landowners with ownership of the 81 land lots, the extents of land to be affected by acquisition is less than 11% of the total land owned by the respective landowners which will not have a significant impact on their total land assets. Table 9 presents the impacts of land acquisition on private land (additional details are provided in Annex 2). Of the 52 PAPs, 32 will lose less than one perch 2 of their land; 10 PAPs will lose 1-2 perches; 8 PAPs will lose 2-5 perches, and two PAPs will lose more than five perches. Among the latter, one PAP, however, will lose 22.4 perches of his total land extent of 600 perches which is less than 4% of his total land. The second PAP will lose 5.01 perches of land out of his 220 perches of land which is 2.3% of the total land he owns. Table 9: Details of the affected private land lots The extent of land to No. be acquired PAPs Ownership Impacts of land acquisition Part of home gardens of 29 PAPs < 1 perch 32 Titleholders Part of agriculture land of 01 PAP Part of vacant land of 2 PAPs 1-2 perches 10 Titleholders Part of home gardens of 8 PAPs Part of vacant land of 2 PAPs 2-5 perches 08 Titleholders Part of home gardens of 5 PAPs Part of vacant land of 2 PAPs Part of house access road of 1 PAP > 5 perches 02 Titleholders Part of vacant land of 2 PAPs Total 52 Source: Social Impact assessment, August Table 10 below shows details of land loss to PAPs in proportion to their total land. Accordingly, 14 PAPs will lose less than 3% of their land; 15 PAPs will lose 3%-5% of their land, and 22 PAPs will lose 5% to 8% of their land. One PAP will lose more than 10% of his land (i.e perches out of 28 perches of residential land). A summary of losses is given in Table 10, and details are provided in the inventory of losses in Annex 2. Cash compensation for the acquired land will be paid at replacement cost as per the LAR 2013 and the RPF prepared under the Project. 2 1 perch equals to sq ft. Rehabilitation of Moragoda Ela Cross Drains - Package B 20

22 Table 10: Proportion of the loss of land Percentage of losing land PAPs Less than 3% 14 3% - 5% 15 5% - 8% 22 More than 10% 01 Total 52 Source: Census of PAPs, August ) Transfer of Government land 55. The subproject also requires acquisition of additional 28 land lots (45.38 perches/ 0.115ha) which are vested with three government agencies (Table 11). Of them, 02 land lots (22.9 perches/ 0.058ha) are vested with the National Housing Development Authority (NHDA). This land being marshy remains unused and does not have any built structures within its boundaries. The Road Development Authority (RDA) owns another 2 land lots (0.36 perches) which is used as part of public roads. The Galle Municipal Council (GMC) owns the balance 24 land lots of which 23 lots (19.54 perches/ 0.049ha) are used for public roads and drains while the remaining lot (2.58 perches/ ha) is open land. According to government regulations, the land being vested with state institutions is not required to follow the regular process of land acquisition. Instead, the ownership of the required land will be transferred to the Galle Municipal Council (GMC) through a memorandum of understanding (MoU) signed between GMC and the landowning agencies. Common utilities such as roads and drains built on the land will be affected/damaged during project s construction work. The project will restore these common utilities within the remaining portion of the land to facilitate their uninterrupted functions prior to the commencement of civil works of the subproject. Table 11: Land use pattern of the affected Government institutions NHDA Institute Land use Vacant Land No. of lots The extent of land to be acquired (Perches) RDA Road GMC Road Drain Open Land Total Source: Survey Plan, July 2017 II. Impacts on Residential, Commercial and Auxiliary Structures 1) Impact on residential structures 56. The acquisition of land for Hiribura cross drain will cause partial damages to two residential dwellings. They include damages to the rear extension wall of the house belonging to PAP No. 33 and the staircase of the house belonging to PAP No.38 (See annex 02- IOL). At present, the staircase is outside the main building, and the support column of the staircase and part of the staircase canopy will be damaged under the project. Rehabilitation of Moragoda Ela Cross Drains - Package B 21

23 57. Both these affected parties will be able to remain within their dwellings during construction without relocation. Any construction-related impacts to these two households will be mitigated as per the SIMP designed for the subproject (See Annex 06). Cash compensation for the restoration of the structural damages will be provided at replacement cost as determined by the LARC. The damaged structures will be restored within the remaining portion of the land. The PAPs will be given two months of advance notice to construct the new wall, staircase column and the canopy prior to the demolition of their old structures. The social development officer of PIU in Galle assigned to this subproject will regularly monitor the restoration work. 2) Impact on commercial structures 58. There are three commercial structures which are extensions of the owners respective residential dwellings. Specifically, these commercial structures are owned by three different individuals. The roofs of these three extended commercial structures will be partially damaged under the sub-project. However, these partial damages will not affect the stability of the main structure and the ongoing economic activities will remain intact. All the three PAPs, who run retail outlets in these buildings, can continue to engage in their businesses during the construction period. The damaged sections will be rebuilt within the remaining portion of land after acquisitions. Furthermore, the project will pay compensation for land and the damaged structures at replacement cost. In the event of their business activities being interrupted leading to loss of incomes either during the demolition of the structures or their restoration, the PAPs will be eligible for livelihood assistance as provided in the Entitlement Matrix and the resettlement budget of the ARAP. The livelihood assistance grants will be calculated on the basis of net monthly incomes of the PAPs, (as per their claims made by the PAPs during census and further verified through circumstantial evidence) for a period not exceeding 3 months. The social development officer (SDO) of PIU in Galle assigned to this subproject will closely monitor the impacts of structural demolitions and restoration work on the livelihoods and incomes of the three PAPs. 59. A fish vendor (squatter) occupying road side open space (around 6.0 sqm) at the Galagediya junction of the Hirubura cross drain, will be temporarily affected during civil works of the subproject. The daily net income of the fish vendor is approximately SLR 2,500/- as reported in the census administered as part of this ARAP. During subproject implementation, the vendor has opted for self-relocation within 25 m of his current business location for which the GMC has granted approval. The fish vendor uses a moveable structure made out of wood, which can be easily shifted to the relocation site. Once the rehabilitation work is completed, the fish vendor has the option of continuing his business activities in the same relocated site or to return to his original business location. The social development officer (SDO) of PIU in Galle assigned to this subproject will closely monitor the impacts of relocation on the business and incomes of the fish vendor. In the event of any reported or observed business/income losses of the fish vendor, he will be paid one-time cash grant calculated on the basis of his net daily income of SLR 2,500 for a period not exceeding 20 days, provisions for which are made in the Entitlement Matrix and the resettlement budget of the ARAP. 3) Impact on auxiliary structures 60. Land acquisitions for cross drains will affect another 49 auxiliary structures associated with residential dwellings of 24 project affected households (PAHs). Of the 49 auxiliary structures, 45 would be fully affected, and four would be partially affected. These affected auxiliary structures are summarized in Table 12 while Annex 2 provides details of the affected auxiliary structures of the individual PAPs. Rehabilitation of Moragoda Ela Cross Drains - Package B 22

24 Table 12: Auxiliary structures affected due to land acquisition Type of structure Nos of No. of Affected Impact Structures Households Fully Partially Shed Toilet Toilet Pits Fence Boundary walls House Access Garage Kitchen Bathing Place Water Connection Total 49 ** 45 4 Source: Census of PAPs, August The compensation for the affected auxiliary structures will be provided at replacement cost for which provisions have been included in the resettlement budget. The damaged structures or facilities will be reconstructed by the affected parties within the remaining portion of the land utilizing the cash compensation paid to them. In the event of any vulnerable households being unable to restore their demolished/ damaged structures on their own, they will be assisted by the members of the Local Resettlement Committee (LRC, a committee constituted by the representatives of the PAPs to liaise between the PAPs and the project on resettlement issues) and a mutually agreed course of action will be decided in consultation with those vulnerable households. Since a majority of the affected auxiliary structures such as toilets, toilet pits, kitchens, bathing places, access roads etc. are essential for the daily lives of the PAPs, the project will ensure that those structures are reconstructed and fully restored prior to the commencement of the civil construction work. The old structures will be demolished upon completion of the new structures. The project, having consulted and agreed with the PAPs, will grant sufficient time for the PAPs to reconstruct their structures before the commencement of the civil works. 4) Impacts on Standing Trees 62. The affected private land lots identified as home gardens and agricultural lands contain mixed crops with the characteristic of low country wet zone vegetation. The census survey identified fruit bearing and non-fruit bearing trees with economic value and bushes grown in the affected land. Altogether, 88 trees and bushes will be cut down for drains rehabilitation. All affected trees are located only along the Hiribura cross drain. The common perennial crops are coconut and areca nut. Specifically, 32 coconut trees belonging to eight PAPs and 34 areca nut trees belonging to 12 PAPs will be cut down for the Hirbura cross drain improvement. The total market value of the trees is estimated at SLR 725,500. The details of the affected trees are summarized in Table 13 while Annex 2 presents the details. Cash compensation will be paid for the lost trees based on their replacement cost, which takes into consideration their market value, productivity of the trees, their life cycle, lost incomes from trees and the timber value. The provisions for compensation are included in the EM and the resettlement budget. The compensation will be paid prior to the commencement of civil works. Rehabilitation of Moragoda Ela Cross Drains - Package B 23

25 Type Fruit-Bearing Trees Non-Fruit Bearing Trees Table 13: Details of affected trees and values Age of the Number of trees affected Tree tree Bombe Hiribura (Years) Total Castle CD Coconut Areca Nut Mango Unit Value 3 (SLRs) Value (SLRs) , , , , ,000 64, , , ,500 52,000 < ,000 20,000 > ,000 75,000 Jack ,000 30,000 Amberella ,000 4,000 Naminang ,500 1,500 Goraka ,000 5,000 Rose Apple/Jambu ,000 2,000 Bakini ,500 1,500 Erabadu ,000 1,000 Godapara ,000 Kanda Bamboo Bushes ,000 40,000 Total ,500 Source: Census of PAPs, August Furthermore, the Environment Screening Report (ESR) prepared for this subproject has allocated funds to replant the trees of same varieties on PAPs remaining land as a special environmental program in addition to the compensation paid for the affected trees. 5) Construction related impacts and mitigation measures 64. Temporary impacts from construction-related civil works of the rehabilitation of Moragoda Ela Cross Drains - (Package B) are also anticipated. Such construction-related impacts may include access difficulties, the safety of pedestrians, traffic congestion, disturbances to common utilities, dust, noise and labour influx and management. A Social Impact Mitigation Plan (SIMP) prepared by the project (see Annex 06) to address those civil works related impacts will be implemented by the contractor. The SIMP will form a part of the contractual agreement. Both SCDP and GMC will closely monitor the effective and efficient implementation of the SIMP and the compliance of the contractor and the staff involved. 3 The estimation of the value of coconut trees is based on the rates provided by the Coconut Cultivation Board and the valuation of other fruit bearing trees is done with the guidance issued by Department of Agriculture concerning the timber value of trees as well as age and yield of trees. The rates provided by the Timber Corporation are used to estimate the value of the non-fruit bearing trees on its timber value. Rehabilitation of Moragoda Ela Cross Drains - Package B 24

26 III. Census of Project Affected Persons 65. The census survey covered 53 project affected households (PAHs) which included 52 titleholder household and one squatter, who is a fish vendor. The Inventory of Losses (IOL) was prepared based on the results of the census. No government institutions were included in the census survey. 66. Table 14 presents a socio-demographic profile of the project affected persons. The total population of the 53 PAHs is 192 with 56% males and 44% females. The age structure of the household population indicates that 62% of the population fall in the years of age category, followed by 25.5% between 0-15 years and 12.5% over and above 60 years. Except for the population below five years, adult population is literate. More than half the population had attained GCE Ordinary Level, GCE Advanced Level or higher education. 67. There are 7 families supported by women and not having able bodied male members who can earn; therefore these 7 families are considered as vulnerable families among the project affected persons. Of them, three households will be affected by the damages caused to their auxiliary structures. The Entitlement matrix of the ARAP provides for special assistance for the affected vulnerable households. Sex Age Education Table 14: Socio-economic profile of the PAHs Project Affected Area (n=192) Category Criteria PAPs no. Percentage Female Male > Children below five years Grade Grade O/L A/L Undergraduate Graduate Post Graduate Women Headed HH Female-Headed HH Source: Census of PAPs, August Almost 58% of the households population is employed in the public sector, private sector or foreign employment, and receive a regular monthly income. Labour work is the main income source for 18.6%. Business activities are conducted by 17% of the households, and 3.8% are engaged in agriculturerelated activities. Table 15 presents the livelihood activities of the PAPs. Rehabilitation of Moragoda Ela Cross Drains - Package B 25

27 Occupation Table 15: Livelihoods of PAHs Percentage (n=53) PAPs no. % Labour work Government jobs Private Sector jobs Foreign Employment Business Agriculture Carpenter (Skilled Labor) Source: Census of PAPs, August Tweleve affected households receive government s Samurdhi subsidies granted to poor households living below the official poverty line. The beneficiary households of this subsidy scheme are those dependent on labour work and agriculture-related work. 70. The monthly incomes of 17% of the project affected households are less than SLR.10, 000/- per month. The monthly earnings of 20.7% households are between SLR. 10,000/ to SLR.25, 000/-. Another 41.5% households receive monthly incomes ranging from SLR.25, 000/- to SLR. 50,000/. The rest 20.8% earns more than SLR. 50,000/- a month. More than 60% of the households are dependent on monthly fixed incomes exceeding SLR. 25,000/-. There are seven households (13.2%) headed by women. Figure 4 illustrates the income levels of the PAHs. Figure 4: Monthly Incomes of PAHs 45.0% 41.2% 40.0% 35.0% 30.0% 25.0% 20.0% 17.6% 21.6% 19.6% 15.0% 10.0% 5.0% 0.0% SLR. 5,000/- to SLR. 10,000/- SLR. 10,000/- to SLR. 25,000/- SLR. 25,000/- to SLR. 50,000/- More than SLR. 50,000/- Source: Census of PAPs, August 2017 Rehabilitation of Moragoda Ela Cross Drains - Package B 26

28 D. Eligibility, Compensation and Resettlement Assistance 71. The Entitlement Matrix provided in the Resettlement Policy Framework (RPF) outlines various types of losses resulting from land acquisition and provides for compensation and resettlement & rehabilitation (R & R) assistance for various categories of affected people. The Matrix applies to all subprojects entailing involuntary resettlement impacts irrespective of the size of the sub-project and the extent of the impact. The A-RAP incorporates the provisions from the entitlement matrix which are relevant for the proposed subproject. If at any stage of the sub-project, additional resettlement impacts are identified, the A-RAP will be updated by the SCDP to make provisions for mitigating such impacts with compensation and R&R assistance in line with the Entitlement Matrix and the updated ARAP will be submitted for Bank s approval before its implementation. 72. This Matrix has been prepared considering various categories of losses and impacts identified during the social assessment, which is summarized in Table 16 below. This Matrix is based on applicable Sri Lankan laws, the NIRP and complies with the World Bank s safeguard principles of OP 4.12, the RPF prepared for the Project. The Entitlement Matrix offers compensation at replacement cost for loss of land, built structures, livelihoods and incomes, and standing trees, as well as for the restoration of community facilities, and provisions for mitigating project related temporary impacts. 73. Parties entitled for compensation under the project can be individuals, households, families or communal groups. The Entitlement Matrix of this ARAP considers affected categories of persons/households to determine their entitlements. If more than one person claims legal or customary ownership to the same property or resources, the compensation for such properties or resources will be shared between owners, as specified in the RPF for the Project. 74. Any person or household, or community who suffers the loss of land, shelter, business, and incomes because of the project impact is eligible for receiving compensation and/or R&R assistance at replacement cost to offset such losses enabling restoration of living conditions to a state better or equal to the pre-project situation. The eligibility is determined by social impact assessment conducted while preparing the A-RAP and approved by the PMU. In case of titleholders, eligibility is determined by reviewing the title deeds or other ownership documents recognized under the law. 75. The cut-off date for eligibility for entitlements is the first day of the census survey conducted based on the detailed measurement survey and/or the Date of Notification under the Section 2 of LAA for the titleholders. The cut-off date will be publicly announced, and widely disseminated. Persons who encroach on the area after the cut-off-date are not entitled to claim compensation or any other form of resettlement assistance. Fixed assets such as built structures or planted trees after this date will not be covered and compensated. The census survey for this subproject was completed on 31 st August 2017, and only one non-titleholder was identified. The cut-off date for titleholders was 27 th April 2017, the date on which Section 2 notice under LAA was issued. The land acquisition process gets initiated soon after the Section 2 of the LAA is triggered. This largely serves an administrative purpose of identifying the landowners. However, acquisitions will be finalized only after receiving clearance for the ARAP and cash compensation at replacement cost is paid in full together with other resettlement assistance 76. All involuntary land acquisitions will be compensated at replacement cost as per the LAA-1950, and LA Regulations of 2013 that include cost of replacing assets calculated based on market value, transaction costs, interest accrued, transitional and restoration costs, and any other applicable payments. The PAPs will be assisted to reestablish their living standards (affected shelter and incomes) to a level higher or better than their living conditions before the project. 77. The auxiliary structures to be demolished such as toilets, toilet pits, house accesses etc. are essential parts of the daily lives of people. Therefore, it is necessary that these auxiliary structures are replaced with new structures before the demolition of the old/existing structures. The PAPs will be Rehabilitation of Moragoda Ela Cross Drains - Package B 27

29 allowed 2 months after the full payment of their due compensation to re-construct their auxiliary structures in the remaining portion of the land. Table 16: Entitlement Matrix Sr. No. Type of Loss/Disturbance Definition of AP Entitlement 1. Private Land without Structures 1.1 Partial loss of land due to land acquisition Legal title holders/ affected parties with land use rights recognized under the law Compensation at replacement cost Standing trees - Do- Ex-gratia payments as livelihood assistance 2. Loss of Residential Structures Details Compensation for affected land lots at replacement costs based on market value, injurious value, severance, disturbances and transaction cost as per LAA 1950, and nonstatutory and ex-gratia payments as per LAR Applicable interest on compensation amount for the delay in payment of compensation calculated from the date of taking over possession of land as per LAA of 1950 & LAR APs who hand over the possession of land before the date specified by the acquiring officer shall be entitled to an ex-gratia payment determined by LARC as per LAR Compensation for trees affected at replacement cost based on the the current market price of the threes depending on their type, age, productivity, lost income and life cycle of the trees as determined by LARC as per LAR APs allowed to retain felt trees 2.1 Permanent and partial loss of residential structures 2.2 Permanent Loss of auxiliary structures associated with residential dwellings Owner occupants with a title deed or other ownership documents recognized under the law Compensation at replacement cost Compensation for the damaged structures based on replacement cost determined through market value, injurious value, severance, disturbances and transaction cost (without depreciation) as per LAA of 1950 & LAR Right to salvage material from the demolished structure. -Do- -Do Compensation for the auxiliary structures at replacement costs based on market value, injurious value, severance, disturbances and transaction cost (without depreciation) after the acquisition as per LAA of 1950 & LAR If the APs hand over the possession of structures and land before the date specified by the acquiring officer they shall be entitled 4 Replacement cost means the cost involved in replacing an asset at the time of acquisition and includes fair market value, transaction cost, interest accrued, transitional and restoration cost and any other applicable payments. The depreciation value of the assets and structures shall not be taken in to account. Where there are no active market condition, replacement cost is equivalent to delivered cost of all building materials, labor cost for construction and any transaction or relocation cost. Rehabilitation of Moragoda Ela Cross Drains - Package B 28

30 Sr. No. Type of Loss/Disturbance Definition of AP Women headed households (Vulnerable HH) Entitlement Details to an ex-gratia payment determined by LARC as per LAR Right to salvage material from the demolished structure Mutually agreed upon time frame for reconstruction of auxiliary structures before their demolition Payment of special allowance of LKR 15,000/- to be paid for a vulnerable household as determined by the LARC as per LAR In the event of any vulnerable households being unable to restore their demolished/ damaged structures on their own, mutually agreed additional support (agreed between LRC, vulnerable HH and PMU/PIA) 3.0 Commercial Land and Structures 3.1 Permanent and partial loss of commercial land and structures 4. Loss of business income Owner occupants with a title deed or other ownership documents recognized under the law Compensation at replacement cost Compensation for the damaged structures at replacement cost based on market value, injurious value, severance, disturbances and transaction cost (without depreciation) after the acquisition as per LAA of 1950 & LAR Ex-gratia payment determined by LARC as per LAR 2013 if the APs hand over the possession of structures and land before the date specified by the acquiring officer Full compensation for the structures/properties before taking over the physical possession based on replacement cost (without depreciation) as per LAA of 1950 & LAR Right to salvage material from the demolished structure Mutually agreed upon time frame for reconstruction of auxiliary structures before their demolition 4.1 Loss/ disturbances for business income Titleholder s and Nontitleholders Livelihood assistance Cash grants in case of loss of business income during the construction period as determined by LARC considering the type and scale of the business and period of business losses as per LAA of 1950 & LAR Alternative business site to be allocated by GMC to the fish vendor and one-month notice for the relocation of his business 5. Unanticipated Impacts 5.1 Unanticipated Impacts PAPs Compensation at If unanticipated damages caused to the structures due to subproject activities, Rehabilitation of Moragoda Ela Cross Drains - Package B 29

31 Sr. No. Type of Loss/Disturbance Definition of AP Source: Entitlement Metrix, RPF, SCDP Entitlement replacement cost Details restoration of such structures through the insurance policy of the contractor. (a mandatory requirement to be complied by the contractor throughout the contract period) Rehabilitation of Moragoda Ela Cross Drains - Package B 30

32 E. Consultations I. Stakeholder Consultations 78. During project planning stage and in the preparation of the ARAP, the Ministry of Megapolis and Western Development, and the staff of SCDP (Both at PMU and PIU) conducted several stakeholder consultations since the year II. Public Consultations on Moragoda Ela Cross Drain Rehabilitation-Package B 79. Stakeholder consultations for the Galle drainage component including cross drains rehabilitation were carried out with the political authority (Parliament members of Galle district, cabinet ministers, provincial council members and GMC members), government officers and community members and PAPs both at individual and group level. A summary of the consultation outcomes is presented in Table 17. Individual consultations were conducted with 66 persons who included among others the PAPs. The number of participants at the two community consultations was 31 (see Annex 5 & 6 for lists of participants). Community coordinators (representatives of the community) were nominated during the consultations by the participants for coordination and liaison with the community, SCDP and PPA during the implementation of the subproject. Table 17: Summary of Community Consultation Outcomes on Cross Drains - Package -B SN Issue Discussed Participants comments Response from the project 1 Increase of flooding Hiribura junction gets frequently flooded during the rainy season. Participants requested to improve the roadside drains and divert excess water to Moragoda Ela (near Kahaduwawatta bridge) and not to connect roadside drains to Hiribura drain. Subproject designers decided to delink the connection of roadside drains from Hiribura drain 2 Land acquisition for drain widening 3 Public inconveniences 4 Public properties would be damaged with drain improvement 5 Proper maintenance system 6 Unanticipated damages for private properties during construction When widening the drain, acquire equal width of land strips from both sides of the canal for development purposes. Cover the drain near the residential areas (0+097m to m) for safety and to prevent bad odour from Bombe castle canal. Improve the access road adjacent to Bombe castle drain (0+197 m to m) Need a mechanism for drains maintenance Will civil works impact on adjoining private properties during the construction period? The participants were informed that the design had taken the community views into consideration and the hydrological requirements. Subproject s design includes the covered drain section for the chainage (0+097m to 0+297m) Improvements to the road section have been included in the design SCDP will facilitate GMC to prepare a strategy for the canal and drains maintenance under its capacity development component - Community members will be informed about the construction activities after finalizing the design. - Third party insurance will be a part of contractor s agreement and it will cover any unanticipated damages and accidents to both structures and people. Affected parties will be compensated if such damages occurred Rehabilitation of Moragoda Ela Cross Drains - Package B 31

33 SN Issue Discussed Participants comments Response from the project 7 Dumping of debris on private land 8 Damages to public properties 9 Reconstruction of damaged private structures During the previous canal rehabilitation work, debris was dumped into private land and not removed after the construction work. It created severe environmental and health issues. Participants requested not to dump the debris into private land. Canal improvement should not affect the width of the access roads. Will the damaged structures have to be reconstructed by the affected parties? Temporary dumping site on government land at Maligaspe and a permanent dumping site at Kehelhena 10km away from the site were identified. Proposed development activities will improve the road width and surface of the road adjoining the canals. Damaged structures will be reconstructed by the PAHs with cash compensation provided to them. Any vulnerable households who are unable to attend to the restoration work will be assisted by LRC. Compensation for damaged structures will be paid at replacement cost as determined by the LRAC. Rehabilitation of Moragoda Ela Cross Drains - Package B 32

34 F. Institutional and Implementation Arrangements 80. The Executive Agency (EA) of the Project is the Ministry of Megapolis & Western Development (MoM&WD) which is responsible for overall project coordination. The PMU under the EA will manage and coordinate project implementation. The Project Implementation Unit (PIU) established in Galle is responsible for the implementation of the ARAP. The PIU will carry out necessary social assessments and consultations for the project, and provide required technical assistance and consultancy services. Roles and responsibilities of agencies involved in A-RAP preparation and implementation are explained in Table 18. Table 18: Agencies responsible for Resettlement Plan Implementation No. Stages of Land Acquisition Process Time Frame Responsibility 1 Submission of request application to MOL to acquire the land Completed SCDP, DS 2 Issue Section 2 of LAA -Intention to acquire land Completed DS 3 Preparation of advanced tracing (Amended) Completed SD 4 Establish Grievance Redress Committee (GRC) Completed SCDP, GMC, DS 5 Conducting Census Survey Completed SCDP Reserve the land for development intervention (Section 38 A of LAA) Assessment of land use and preparation of Condition report Informing PAPs on the decision to acquire the land (Section 5 of LAA) Request Surveyor General to prepare the preliminary plans (Section 6 of LAA) Inform PAPs to submit claims (if any) for ownership and compensation (Section 7 of LAA) Orientation for PAPs to prepare relevant documents for ownership inquiries 12 Holding inquiries on ownership (Section 9 of LAA) Completed Completed Completed Completed Completed Completed ongoing and to be completed by 15/04/2018 MOL, DS VD, SCDP, DS DS, SCDP SD, SCDP, DS DS GMC, DS, SCDP 13 Preparation of ARAP 10/08/2018 SCDP 14 WB s clearance for ARAP 15/08/2018 WB, SCDP 16 Public Disclosure -ARAP 20/08/2018 SCDP 17 Ownership determination and request for valuation (Section 10.1.A of LAA) Completed 18 Preparation of valuation reports Completed VD Issuing award letters indicating compensation amount to PAPs (Section 17 of LAA) Aggrieved PAPs submit their appeals for higher compensation through DS/LARC Completed DS DS, VD DS 15/08/2018 PAPs 21 Award of compensation (Section 17 of LAA) 31/08/2018 LARC Facilitating the fish vendor to shift his business activities to a relocation site with GMC assistance Signing MoUs with government institutions to transfer the required land to GMC for drain rehabilitation 24 Restore the damaged auxiliary structures of the PAPs 31/08/2018 SCDP, GMC 31/08/2018 LARC, GMC, NHDA From 01/09/2018 to 31/10/2018 GMC, DS, SCDP, PAPs 25 Handing over the site to the contractor 01/11/2018 SCDP/GMC/DS Rehabilitation of Moragoda Ela Cross Drains - Package B 33

35 No. Stages of Land Acquisition Process Time Frame Responsibility 26 Implementation of EMP and SIMP Completion of common infrastructures affected (Roads, Drains) Developing an institutional mechanism for canal maintenance From 01/11/2018 to 30/10/2019 Before 31/12/ /11/2018 SCDP, GMC, Construction Contractor SCDP, GMC, Construction Contractor SCDP, GMC and Community 29 Section 44-Issue vesting order to the Ministry 15/09/2018 DS, GMC, SCDP 30 Monitoring safeguards compliance 31 Continue grievances redress mechanism Source: SCDP/Land Division From 01/11/2018 to 31/10/2019 Started and continue up to 31/10/2019 SCDP SDO, GRC, PD, IGP I. Dissemination of ARAP 81. The ARAP will be disclosed in local languages (Sinhala and Tamil) as required by the safeguard policies of the WB and the GOSL and disseminated to the public. The ARAP will be disclosed at SCDP s website ( as well as World Bank InfoShop after getting clearances from WB and links will be published on public media. II. Maintaining Information Profile 82. The PIU/Galle collected information from PAPs through census survey and during the community consultations and developed a database including maps and photographs. The database will be updated by the PIU in periodic intervals and will be used for implementation and monitoring of the ARAP. III. Grievance Redress Mechanism 83. Grievance Redress Mechanisms (GRMs) are institutions, instruments, methods and processes by which a resolution to a grievance is sought and provided. Grievances are inevitable when complex projects are implemented, and PAPs or groups should be provided with an institutionalized GRM for them to submit their grievances and obtain redress. A project-specific GRM has already been established at four levels to resolve the issues raised by the PAPs. All PAPs will be informed of the availability and functioning of the GRM through leaflets printed in local languages and handed over to individual households, and through the members of the LRC and during community consultations. 1) Grievances redress at field level 84. A Social Development Officer of SCDP will be responsible for addressing the grievances at the field level, i.e., at the sub-project site. All grievances can be lodged both verbally and in written form. A log book will be maintained at the construction site and the Grama Niladari offices of both Deddugoda North and South to record grievances. A verbal grievance can also be communicated to the social development officer and the GNs of Deddugoda North and South. The project also welcomes grievances communicated in anonymity, and these will be recorded and addressed accordingly. Wherever required, the social development officer (SDO) and the GNs will retain the anonymity of the aggrieved parties. The social development officer will be located at 2 nd Floor, Middle Shopping Complex, Talbert Town, Galle. The telephone and other contact details of the SDO will be shared with community members and displayed at construction sites. The SDO will take immediate action to resolve the issues raised by the Rehabilitation of Moragoda Ela Cross Drains - Package B 34

36 PAPs. If the SDO is unable to resolve the grievances within one week, it will be forwarded to the next level, which is Project Implementation Unit (PIU) of Strategic Cities Development Project. 2) Grievance redresses at PIU level 85. The GRC at PIU level will comprise a representative from GMC, two community representatives of PAPs, Grama Niladaries of the subproject impact area, contractor s engineer and APD/SDO who will function as Secretary to GRC. The GRC will meet bi-monthly or more frequently, depending on the number of grievances received from the site level. The PIU level GRC is responsible for solving grievances within one week. The PIU level grievance committee is located on the 2 nd floor, Middle Shopping Complex, Talbert Town, Galle. 3) Grievance redresses to PMU level 86. If a PAP was not satisfied with GRC s decision or else PIU level GRC is unable to solve the problem at their level, the grievance could be submitted to the Project Director (PD). The PD, in consultation with the PPAs/PIU concerned at PMU level will decide on the resolution for the grievance. The PMU is located on the 4th floor, Sethsiripaya, Stage 01, Battaramulla. The PD will give his/her decision within one week of receiving the grievance. 4) Independent Grievance Redress Panel (IGP) 87. If the PD s decision is not acceptable to a PAP or PD is unable to resolve the grievance, PAPs can appeal to the Independent Grievance Panel (IGP) established at national level. The meetings of the IGP will be held at MM &WD. The IGP comprises representatives from the Land Ministry, Department of Valuation, a lawyer, a retired senior government officer, and a representative of a recognized Civil Society Organization and/or a person representing the PAPs. The IGP will be chaired by the Secretary to MM & WD. IGP will give the decision for grievance within two weeks of receiving the grievance. Thus, the PAPs have four project-based grievance redress mechanisms to resolve their grievances. The PAPs will not be charged any fees related to grievance redress by the Project based GRM. If the PAPs were not satisfied with the project based GRM or any of its levels, the PAPs could approach the Mediation Boards (Samatha Mandala [SM]), established under the Ministry of Justice to seek redress. The PAPs will also have the option of resorting to legal action via the court system. 88. Figure 5 shows the structure and the flow of the GRM of SCDP. Rehabilitation of Moragoda Ela Cross Drains - Package B 35

37 Figure 5: Structure of the GRM for SCDP 89. The contact information of PIU, GMC and PMU is given below Mr M.R.S. Kumara Social Officer Strategic Cities Development Project 2 nd Floor, Middle Shopping Complex, Talbert Town, Galle skumara36@gmail.com Galle Municipal Council Mrs. Wasana Gunarathne Municipal Commissioner Galle Municipal Council Galle mcgalle@sltnet.lk Project Management Unit Mr Pradeep Hettiarachchi Deputy Project Director (social) Strategic Cities Development Project 4 th Floor, Sethsiripaya -Stage 1, Battaramula pradeepscdp@gmail.com Project Implementation Unit Mr K.M.S.D.P.Konara Assistant Project Director (Social) Strategic Cities Development Project 2 nd Floor, Middle Shopping Complex, Talbert Town, Galle konarascdp@gmail.com Mr Anura Dissanayake Project Director Strategic Cities Development Project 4 th Floor, Sethsiripaya -Stage 1, Battaramula pdscdp14@gmail.com Rehabilitation of Moragoda Ela Cross Drains - Package B 36

38 G. Monitoring and Reporting 88. The monitoring and reporting system is integral to social safeguards, and the project will establish a monitoring and reporting system for ensuring efficient and effective management of social safeguards. The social development officer (SDO) assigned to the subproject will make weekly monitoring visits to the subproject sites. The SDO will also function as the community liaison officer for the subproject and communicate any community concerns and issues to the Deputy Project Director at PIU, Galle and the Deputy Project Director (Social) at PMU. The DPD (Social) will also conduct monthly meetings at PIU to review the progress of ARAP implementation and report the status to the Project Director. 89. An organigram of the social safeguards implementation team is given in Figure 6. Figure 6: Organigram of SCDP Social Safeguard Implementation Project Director External Independent Monitor (Social Safeguards) Deputy Project Director (Social) PMU Level PIU Level Assistant Project Director (Social) Social Development Officer 90. The following indicators will be used to monitor the progress of ARAP implementation while covering the processes, outputs, outcomes and impacts. Rehabilitation of Moragoda Ela Cross Drains - Package B 37

39 Monitoring Level Processes & inputs Outputs Outcomes Impacts Table 19: Monitoring Indicators of ARAP implementation Monitoring Area Indicators Source of information Acquisition of land Consultations Grievance redress Compensation paid at replacement cost Rehabilitation of damaged residential structures Rehabilitation of damaged commercial structures Rehabilitation of damaged auxiliary structures Assistance to restore livelihoods Implementation of EMP Functional GRM Canal Rehabilitation works Improving the home gardens Maintenance works of Canals Flood reduction Cleaner environment Completion of LA process by 31/08/2018. Completion of signing MoUs to transfer the government land to GMC for canal rehabilitation by 31/08/2018 Public and individual consultations for resettlement planning completed by 15/04/2018 Establishment and functioning of GRM (Completed) Payment of both statutory and exgratia compensation Completion of the restoration of damaged structures by 31/10/2018 Completion of the restoration of damaged structures by 31/10/2018 Completion of the restoration of damaged structures by 31/10/2018 Relocation of the business activities of the fish vendor to in an alternate site with GMC approval Distribution of trees to PAPs under replantation program The number of grievances reported and resolved. Completion of Canal rehabilitation works Improving home gardens and planting trees by PAPs using their compensation and with additional support from the project Desilting and rehabilitation of drains once in six months Reduced flooding in the Galle city area due to improvements to the Moragoda Ela cross drains by Cleaner environment of subproject impact area after rehabilitation works Progress report from Land Division Progress report from Land Division Meeting minutes and list of participants GRC meeting minutes Progress report of Land division Internal Monitoring report of SCDP Internal Monitoring report of SCDP Internal Monitoring report of SCDP -Do- Progress report of Environmental Division Report of GRC Contractor s report Project completion report Rehabilitation of Moragoda Ela Cross Drains - Package B 38

40 I. Resettlement database 91. All information related to land acquisition, socioeconomic information of the PAPs, inventory of losses of individual PAPs, compensation & entitlements and payments and reconstruction-related activities will be collected and computerized by the PIU. This database will be the baseline for monitoring and safeguards management. The External Monitor of social safeguard will also monitor the implementation of ARAP with a specific focus on the following. i. Review and monitor the overall implementation progress and performance of the Abbreviate Resettlement Action Plan (ARAP). ii. Determine the level of compliance of the implementation of ARAP with the policies of the World Bank and the Government as defined in the project s RPF, and recommend corrective actions to improve implementation and management, as required. iii. Monitor the progress of land acquisitions, payment of compensation and resettlement processes and its compliance with both RPF and the ARAP. iv. Assess the overall adequacy and the effectiveness of the safeguard measures adopted to restore and improve the livelihoods, living standards and the overall wellbeing of the project affected persons, households and communities and provide recommendations on additional safeguard measures required. Rehabilitation of Moragoda Ela Cross Drains - Package B 39

41 H. Resettlement Budget 92. The Department of Valuation is responsible for the valuation of land and structures and to decide on the statutory compensation. The compensation for all losses will be based on replacement cost. However, the following benchmarks have been used for preliminary assessments. Compensation for all structural damages is based on the rates provided by the Building Department whereas the land values are calculated at the current market values. The estimation of the value of coconut trees is based on the rates provided by the Coconut Cultivation Board. The rates provided by the Timber Corporation are used to estimate the value of the timber trees. The valuation of other trees has been assessed with the guidance received from the Department of Agriculture. 93. The total compensation for acquired land, structural damages, trees, livelihood support, progress monitoring etc. is SLR million which is equivalent to the US $ million (at an exchange rate of 1US $= SLR. 150). Table 20: Estimated Budget for Land Acquisition and Resettlement Item No. Unit SLR/unit Total SLR Total US$ Compensation for Lands Compensation for structures Residential land, agricultural lands and vacant lands Perch 350,000 34,167, ,780 Commercial Land 2.3 Perch 500,000 1,150,000 7,667 Residential (Partial- 2 houses) 200 3, ,000 4,667 Commercial (Partial- 3 commercial ft , ,000 4,667 premises) Shed 3 15,000 45, Toilet 4 50, ,000 1,333 Toilet pits 5 40, ,000 1,333 Fence 2 15,000 30, Boundary walls ,000 2,400,000 16,000 No s House access 9 10,000 90, Garage 1 15,000 15, Kitchen 3 25,000 75, Bathing place 3 5,000 15, Water connections 3 5,000 15, Compensation for Tress Livelihood & Resettlement Assistance Details of affected trees and values are given in Table 12 Business income assistance for fish vendor - onetime grant based on the daily net income of LKR 2500*20 days (if required) Livelihood assistance for 3 commercial units if unforeseen impacts occur (Net average monthly income of 3 months period) 1 No s 725, ,500 4,837 1 No s 50,000 50, PAPs 300, ,000 6,000 Vulnerable allowances for women headed households 7 PAPs 15, , Rehabilitation of Moragoda Ela Cross Drains - Package B 40

42 Consultation & Information Dissemination Item No. Unit SLR/unit Total SLR Conducting consultations ( During subproject the construction period) Information Dissemination (Leaflets, Posters, Display Boards) Internal progress monitoring of ARAP and documentation Document preparation charges to PAPs in LA process Total US$ 4 No s 25, , Mont hs 15, , , PAPs 10, ,000 3,533 Sub Total 42,347, ,317 Administration Cost 0.5% Lump 211,738 1,412 Contingency 2.5% sum 1,058,688 7,058 Grand Total 43,617, ,786 Rehabilitation of Moragoda Ela Cross Drains - Package B 41

43 Annex 1: Proposed Rehabilitation Activities of Cross Drains No. Description of Proposed Civil Works Quantity Bombe Castle 1 Total Length 1,647 m 2 Length proposed to rehabilitate 399 m (from m to m and m to 1+637m) 3 Width of Drain 2.5 m 5.0 m 4 Proposed bed level 1.6 m m (MSL) 5 De-silting 399 m 6 Concrete lining 209 m 7 Earthen Drain Improvement 190 m 8 Construction of Culverts 07 Nos (@ m, m, m, m, m, m and m) Hiribura Cross Canal 1 The total length of Drain 1,250 m 2 Width of Drain 1.0 m to 4.0 m 3 Height of Drain 1.1 m m 4 De-silting and deepening 1,250 m 5 Concrete lining 940 m (0+000 m to m) 6 Construction of Culverts 05 Nos (@0+470 m, m, m, m and m) 7 Bridge Rehabilitation Chainage m for Dombagahaliyadda Road) Source: Design report of Moragoda Ela cross drains Rehabilitation of Moragoda Ela Cross Drains - Package B 42

44 Annex 2: Inventory of Losses Inventory of Losses (IOL), Moragoda Ela Cross Drains- Package B SN Name of Affected Person Land Entitlement (Deed/ Permit) Loss of land due to the acquisition Present Land Use Total Land (Perches) Affected land extent (Perches) % Partial Damage of permanent Building Due to LA Residential Commercial Shed Toilet Loss of auxiliary structures due to LA Toilet Pit Fence Boundary Wall House Access Part of Garage Part of Kitchen Bathing Place Water Connection Coconut Arecanut Mango Loss of crops & trees due to LA Fruit Bearing Trees Jack Amberella Naminang Goraka Rose Apple/Jambu Bakini Non-fruit bearing trees Erabadu Godapara Kanda Bamboo Bush 1 M.G.S.Amarasena Yes R % P. S.Danthanarayana Yes R % D.Abewikrama Yes R % 4 V.A.Nilam Asanka Yes R % 5 P.K.Sumanaweera Yes R % 6 E.V.G.Mallika Yes R % M.T.Indrapala Yes R % S.A.S.Lorensuhewa Yes R % 1 9 L.K.Hirimburegama Yes V % H.Munasingha Yes R % K.H.W.I. Seenevirathna Yes R % A.S.Ahamad Yes V % M.K.I. Amarasiri Yes V % M.G.Thamara Yes R % 15 N.M Nissanka Nelson Yes R % A.H. Fathima Riyas Yes R % M.S.Noor Amsiya Yes V % Mohomed Rifki Yes R % 1 1 Rehabilitation of Moragoda Ela Cross Drains - Package B 43

45 Inventory of Losses (IOL), Moragoda Ela Cross Drains- Package B SN Name of Affected Person Land Entitlement (Deed/ Permit) Loss of land due to the acquisition Present Land Use Total Land (Perches) Affected land extent (Perches) % Partial Damage of permanent Building Due to LA Residential Commercial Shed Toilet Loss of auxiliary structures due to LA Toilet Pit Fence Boundary Wall House Access Part of Garage Part of Kitchen Bathing Place Water Connection Coconut Arecanut Mango Loss of crops & trees due to LA Fruit Bearing Trees Jack Amberella Naminang Goraka Rose Apple/Jambu Bakini Non-fruit bearing trees Erabadu Godapara Kanda Bamboo Bush 19 A.A.Abudool Salam Yes R % A.S.M.Sali Yes R % 1 21 N.S.K.Sarina Yes R % 1 22 M.S.M.Wikrama Yes V % 23 M.S.U.Silmiya Yes Ro % 1 24 M.F.Niloja Yes R % A,H.Siththi Irosha Yes R&C % 1 26 M.H.M.Noice Yes R % 27 M.H.F.Fasla Yes R&C % M.H.M. Ikbal Yes V % 29 M.J.S.Nuwaira Yes R % 1 30 M.M.Fathima Mafla Yes R % M.R.N.Masiha Yes R % 1 32 M.A.M.Afker Yes R&C % 1 33 M.A.N.Affara Yes R % M.J.F. Sihara Yes R % M.J.M.Nahas Piyas Yes R % 36 U.Marshula Yes R % Rehabilitation of Moragoda Ela Cross Drains - Package B 44

46 Inventory of Losses (IOL), Moragoda Ela Cross Drains- Package B SN Name of Affected Person Land Entitlement (Deed/ Permit) Loss of land due to the acquisition Present Land Use Total Land (Perches) Affected land extent (Perches) % Partial Damage of permanent Building Due to LA Residential Commercial Shed Toilet Loss of auxiliary structures due to LA Toilet Pit Fence Boundary Wall House Access Part of Garage Part of Kitchen Bathing Place Water Connection Coconut Arecanut Mango Loss of crops & trees due to LA Fruit Bearing Trees Jack Amberella Naminang Goraka Rose Apple/Jambu Bakini Non-fruit bearing trees Erabadu Godapara Kanda Bamboo Bush 37 Fathima Farida Yes R % M.S.C.Rishmina Yes R % H.M.F.Hashira Yes R % J.P. Sriyani Yes R % 2 41 A.K.Rohini Yes R % W.R.W.I.Dilukshi Yes R % 43 G.H.Ariyathilaka Yes R % 2 44 A.G.David Yes R % K.M.Karunapala Yes A % 5 46 D.L.T.Pushpakumari Yes R % 2 47 R.Norman Yes R % 48 Chaminda Liyanage Yes R % 49 Pandu Pathmalal Yes V % P.K.Deweka Yes V % 51 Suwathil Jenna Yes R % I.A.Umma Shamila Yes R % 1 1 Total 1, Land Use- R-Residential, R&C- Residential and Commercial-Commercial, A-Agricultural, V-Vacant, Ro-Road Source: Census survey-august 2017 Rehabilitation of Moragoda Ela Cross Drains - Package B 45

47 Annex 3: Cabinet Approval for SCDP as Specified Project Rehabilitation of Moragoda Ela Cross Drains - Package B 46

48 Annex 4: List of Participants at Individual Consultations SN Name GND Address Contact No 1 D.D.Vidanapathige Deddugoda North 28/6,Hirimbura Cross Road,Gamagewatta,Galle A.G.David Deddugoda North 36/28-D,Hirimbura Cross Road,Galle G.K.Dimuthu Deddugoda North 36/28-A,Yasodarawatta,Hirimbura Cross, Hirimbura, Galle Ikbal Deddugoda North 5 G.K.Dewaka Deddugoda North 6 D.Kodithuwakku Deddugoda North 33/9,Anagarika Dharmapala Mawatha, Galle K.G.Sumanawathi Deddugoda North 36/28E,Yasodarawatta,Hirimbura Cross Road, Galle K.M.Karunapala Deddugoda North 36/28C,Hirimbura Cross, Daham Sevena Mw, Galle D.L.T.Pushpakumari Deddugoda North 36/28N,Hirimbura,Deddugoda,Galle S.Rashmia Deddugoda North 34/3,Hirimbura Cross,Galle 11 J.A.Laxman Deddugoda North 28/1A,Hirimbura Cross,Galle Fathima Sihara Deddugoda North 34/B-2,Hirimbura Cross,Galle Fathima Farida Deddugoda North 34/3-A,Hirimbura Cross,Galle U.Marshula Deddugoda North 34/31, Hirimbura Cross,Galle M.J.M.Rayas Deddugoda North 34-B,Hirimbura Cross,Galle H.M.F.Hashira Deddugoda North 34/04, Hirimbura Cross, Galle M.A.N.A.Fara Deddugoda North 36,Hirimbura Cross,Galle B.P.Weerawicrama Deddugoda North 40,National House,3rd Lane,Kajugahaliyadda,Galle P.D.M.Kumara Deddugoda North 28/6,Hirimbura Cross,Gamagewatta,Galle 20 Premarathana Deddugoda North Bimbawatta,Richmond City 21 Siddik Deddugoda North 22 M.F.Niloja Deddugoda North 47/20,Hirimbura Cross,Galle 23 M.G.M.Pawas Deddugoda North 47/17,Hirimbura Cross, Galle C.B.Jayasundara Deddugoda North 47/3,Pasal Mawatha,Hirimbura,Galle A.R.N.Masina Deddugoda North 4,Pasal Mawatha,Hirimbura Cross,Galle Fathima Mifla Deddugoda North 3,Pasal Mawatha,Hirimbura Cross, Galle Rehabilitation of Moragoda Ela Cross Drains - Package B 47

49 27 Green City Hardware Deddugoda North 28 A.R.N.Fasina Deddugoda North 4B,Pasal Mawatha,Hirimbura Cross,Galle Mohomed Rifki Deddugoda North 47/11A,Pasal Mawatha,Hirimbura Cross, Galle Shuremsia Deddugoda North 47/12A,Pasal Mawatha,Hirimbura Fathima Riyas Deddugoda North 47/6C,Pasal Mawatha,Hirimbura,Galle I.L.M.Silmia Deddugoda North 47/ M.S.M.Aslim Deddugoda North 13/5,Deddugoda Lane,Hirimbura Cross,Galle N.S.K.Sarina Deddugoda North 47/10,Hirimbura Cross,Pasal Mawatha,Galle M.Nilabdeen Deddugoda North 23A/6,Hirimbura,Pasal Mawatha, Galle C.Kodithuwakku Deddugoda North 37 Madanayake Deddugoda North H.Munasinghe Deddugoda North Bank officer House Deddugoda North 38/7Hirimbura Lane, Galle 40 N.Nelson Deddugoda North 16/27,Hirimbura Cross,Galle A.S.M.Sali Deddugoda North 24/3,Siththiya Lane,Halamitiya,Galle A.S.Salam Deddugoda North 48/12, New School MW,Hirimbura, Galle 43 A.K.I.Amarasiri Deddugoda North 16/20-A,Shanthi Pedesa,Hirimbura Cross,Galle S.A.S.Lorensuhewa Deddugoda North 38/5,Hirimbura Cross, Galle S.Danthanarayana Deddugoda North 38/1-C,Hirimbura Cross,Galle 46 S.Jagoda Deddugoda North 47 N.Harischandra Deddugoda North 516,Hirimbura,Galle M.J.M.Nuwaira Deddugoda North 3B,Hirimbura Pasal Mawatha, Galle 49 M.J.S.Nuwaira Deddugoda North 1B,Hirimbura Pasal Mawatha,Galle M.H.F.Fasla Deddugoda North 1/65,Hirimbura Cross, Galle A.A.F.Rasmia Deddugoda South 72/2A,Anagarika Dharmapala Mw,Karapitiya M.I.S.Aseen Deddugoda South 134/3B,Anagarika Dharmapala Mw,Karapitiya 53 M.B.M.Falil Jifri Deddugoda South 14/100,Anagarika Dharmapala Mw,Karapitiya M.R.Piyadasa Deddugoda South 12/100,Bombe Casel Watta,Karapitiya A.G.Sirikumara Deddugoda South 11/100,Anagarika Dharmapala Mw,Galle Rehabilitation of Moragoda Ela Cross Drains - Package B 48

50 56 A.G.Karunadasa Deddugoda South 11/100,Anagarika Dharmapala Mw,Karapitiya,Galle 57 A.G.Somalatha Deddugoda South 11/100,Bombe casel Watta,Karapitiya 58 I.Amitha Shamila Deddugoda South 134/3A,Anagarika Dharmapala Mw,Karapitiya,Galle 59 M.Kadar Deddugoda South 10/100,Karapitiya,Hirimbura Cross,Galle 60 A.H.N.Fathima Deddugoda South 112, Hirimbura Cross,Karapitiya,Galle 61 M.Makil Deddugoda South 116,Hirimbura Stores,Karapitiya,Galle Kodithuwakku Deddugoda South 63 M.S.Kumara Deddugoda South MACO filling Station,Beligaha Junction, Galle A.I.Seiniya Deddugoda South 100/7,Hirimbura Cross,Karapitiya V. Abeywicrama Deddugoda South 66 S.Jentha Deddugoda South 6/100 A,Hirimbura Cross,Karapitiya Rehabilitation of Moragoda Ela Cross Drains - Package B 49

51 Annex 5: List of Participants at Public Consultations Date: 2016/09/28 Place: Dahamsevana Temple, Richmond City Time: 3.00pm List of Participants: No Name Address Tel. Phone 01 J.A. Luxman 28/1 A, Hiribura Cross Rd., Galle M.S.M. Suhail 34/4, Hiribura Cross Rd., Galle T.G. Weerawickrama Deddugoda M.S.F. Jifran 34/3, Hiribura Rd., Galle A.L.M. Auff 36, Hiribura Rd., Galle 06 M.J.M. Nuwiar 1 C, Hiribura Second Lane, Galle M.W.M. Jusan 34B2, Hiribura Cross Road, Galle A.S.F. Fareeda 34, Hiribura Road, Galle M.A. lushan 36/28 A, Hiribura Rd., Galle K.M. Karunapala 36/28 C Hiribura Cross Rd., Galle P.L.T. Pushpa Kumari 36/28 N, Hiribura Cross Rd., Galle S.Kumara Date: 2016/09/29 Place: Mr.D.K.S.Amarasiri s Place, Deddogoda North Time: 3.00pm List of Participants: No Name Address Tel. Phone 01 D.K.S. Amarasiri 16/14, Shanthi Pedesa, Hiribura lane, Galle A.A.A. Salam 47/12, School Lane, Hiribura, Galle P. Madanayake 16/25, Hiribura Lane, Galle M.T. Indrapala 3/38, Siriviman Pedesa, Hiribura Patumaga, Galle P.P.S. Sumanaweera 6/38, Siriviman Pedesa, Hiribura Patumaga, Galle M.F.M. Fairuz 20/47, Hiribura Cross Rd., Galle M.U.S. Amarasena 516, Hiribura Junction, Galle N.M. Galison 16/27, Hiribura Lane, Galle M.S.K. Sreena. 47/10, School Lane, Hiribura A.H.F. Riyaza 47/6 C, School Lane, Hiribura M.S. Noor Amziya 47/12 A, School Lane, Hiribura M.Z.F. Nilofa 23A / 6, School Lane, Hiribura M.S.M. Saal 29/3, School Lane, Hiribura, Galle Noorul Mazeeha No 03A, School Lane, Hiribura Cross Rd., Galle Noorul Fazeeha No 04B, School Lane, Hiribura Cross Rd., Galle Fathima Mifla 03, School Lane, Hiribura cross Rd., Galle M.B.I. Ahamed 1 B, School Lane, Hiribura Cross Rd., Galle M.S. Bishuruclea 47/11 A, School Lane, Hiribura Cross Rd., Galle M.H.F. Fazla 65/1, Hiribura cross Rd., Galle Rehabilitation of Moragoda Ela Cross Drains - Package B 50

52 Annex 6: Social Impact Mitigation Plan No Adverse Social Impacts Mitigation Measures Location/ Place 01 Access disturbances -Temporary Impact Households/Businesses/i nstitutions will have difficulties in access during rehabilitation works Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for reporting any complaints. Provide walkways and metal sheets were required to maintain access for people Special care will be taken wherever the community sensitive areas are located (specified in the EMP) and accelerate the civil works in front of critical areas such as institutions, places of worship, business establishment, hospitals, and schools Bombe castle drain- near Karapitiya Bus stand (Chainage 0+097m), Hiribura Galagediya junction (Chainage 0+679m) Six houses in Hiribura drain and two houses in Bombe castle drain Bombe castle drain near Karapitiya hospital (Chainage 0+097m to 0+301m) Implementing Cost Contractor s cost -Do- -Do- Responsibility Construction Contractor/ RDA/ SCDP/ GMC Construction Contractor/ SCDP/ GMC -Do- Time Frame During Construction -Do- -Do- Consult business and institutions regarding operating hours and factoring this into work schedules Surrounding area of Sites -Do- -Do- -Do- Propose alternative access roads during construction period. -Do- -Do- -Do- -Do- Do not damage or block the existing access road for residential areas during construction Bombe castle drain near Karapitiya hospital (Chainage 0+097m to 0+301m) -Do- -Do- -Do- Contractor to use small excavating equipment as much as possible to avoid unanticipated damages. Site -Do- -Do- -Do- In case of complete loss of motorable access leading to loss of business over a day, financial SLR 1000/ per day per business owner from the 1 st day of such interruptions until ease of access has been restored by the contractor. When needed Contractor cost -Do- -Do- Rehabilitation of Moragoda Ela Cross Drains - Package B 51

53 No Adverse Social Impacts Mitigation Measures Location/ Place 02 Pedestrians Safety Issues- Temporary Impact Safety issues to the pedestrians, vehicles and workers during drains rehabilitation using heavy equipment s & machinery Comply with the provisions of Health and Safety regulations under the Factory Ordinance with regards to provisions of health and safety measures, amenities at workplaces. Alarm warning to the pedestrian, vehicle and workers using sign boards, fence, band tape, etc. Ensure appropriate safety equipment, tools and protective clothing are provided to workers, and that safe working method are applied. A safety inspection checklist should be prepared to take into consideration what the workers are expected to be wearing and monitored during specific construction activities. Whole length of drain section & contractor s vehicle yard -Do- -Do- Implementing Cost N/A Contractor s Cost -Do- Responsibility Time Frame Construction During Contractor/ SCDP/ Construction GMC -Do- Construction Contractor/ SCDP -Do- N/A -Do- -Do- -Do- During construction/ Periodic monitoring Ensure prevention of risks from electrocution by regular inspection and maintenance of all electric power-driven machines used on the construction site. They must be kept away from permanent/ temporary pedestrian walkways. A temporary fence will be erected on crossroad stretch near the bridge to avoid contact with the public and workers. Entire drain section & contractor s vehicle yard Bombe castle drain near Karapitiya hospital (Chainage 0+097m to 0+301m) Hiribura drain-section 0+679m to 0+960m N/A Contractor s Cost -Do- -Do- During Construction -Do- Ensure basic emergency aid service is in place in the work site as well as in labour camps Sites, contractor s vehicle yard & labor camps -Do- -Do- -Do- Ensure training of basic health and safety are provided to the workforce before the commencement of construction work where all the above critical factors are emphasized N/A -Do- -Do- Before starting construction Clear work camp sites after use and reinstate with vegetation Labour camps -Do- -Do- After construction Rehabilitation of Moragoda Ela Cross Drains - Package B 52

54 No Adverse Social Impacts Mitigation Measures Location/ Place 03 viii. Traffic Congestion- Temporary Impacts 04 Traffic congestion would be aggravated due to drains rehabilitation works Phase out the construction of existing culverts to minimize traffic congestion. Special traffic management plan and deploying additional traffic police should be put in place. Shifting of Common and Private Utilities- Permeant Impact Bombe castle drain- near Karapiyi Bus stand (Chainage 0+097m) Hiribura Galagediya junction (Chainage 0+679m Implementing Cost Contractor s Cost Responsibility Construction Contractor/ RDA/ SCDP/ GMC Time Frame During Construction -Do- -Do- -Do- -Do- Shifting of Common and Private Utility Services If the relocation of common utility services anticipated, prepare an inventory of utilities at proposed sites with the assistance of service providers Prepare relocation plans with service providers for utilities to be shifted. Liaise with NWS&DB, CEB, and SLT to obtain utility plans & shifting arrangement, machine operator awareness about utilities and plan rehabilitation routes and facility sites to avoid existing utilities wherever possible. Arrange for service providers to attend to the site immediately to deal with any accidental damage to utilities. Site N/A -Do- -Do- N/A -Do- Project Planning Stage Designing stage -Do- N/A -Do- -Do- When needed Contractor cost -Do- -Do- 05 Ensure the compensation for unexpected structural damages due to construction activities by Third Party Insurance Coverage Entire drains Section Project Cost -Do- If any public or private structures are damaged (including due to vibration), replace the structures or compensate owners. Siting of construction camps, labour camps, stockyards and managing the risk of adverse impacts on communities from temporary project induced labour influx - Temporary Impact If construction camps, labour camps, stockyards, vehicle refuelling areas etc. are Care will be taken not to disturb the sensitive areas and avoid highly residential areas when selecting sites to locate labour camps, stockyards, vehicle refuelling areas etc. and their layout of such place should be approved by subproject supervision -Do- Camps/Yards Insurance Coverage N/A -Do- Construction Contractor/ SCDP/ GMC Before start the construction During construction During construction Rehabilitation of Moragoda Ela Cross Drains - Package B 53

55 No Adverse Social Impacts Mitigation Measures Location/ Place located near sensitive areas such as wetlands, conservation zones and places of scenic beauty or recreational value, or any water body, those areas may be adversely affected. The risks of adverse impacts on communities from temporary project induced labour influx. consultant Accumulation of water due to blocking of drains during construction activities should be mitigated by removal of soil and debris to the dumping yards to avoid potential flooding. Maintain the sound waste management system within the camps and the site and do not allow to dispose of the garbage, wastewater as well as sewerage water to open places/land Make the contractors aware of advantages in giving priority to selecting labour from project influenced areas/local communities to minimize the need for erecting labour camps and minimize labour influx. Introduce Worker Code of Conduct as part of employment and sanctions/penalties for non-compliance Strengthen law enforcement activities around worker camps and work sites Establish a grievance redress mechanism for workers and host communities Frequent supervision of labourers activities, labour welfare activities, basic needs provided for labours, hygienic condition of the camps/ sites Avoid illegal lodging arrangements by workers of contractors Avoid social conflicts or tension and prevalence of genderbased violence. Conduct awareness programs to labourers on hygienic status including sexually transmitted diseases Rehabilitation of Moragoda Ela Cross Drains - Package B 54 Entire drains section Camps/ Yards/ Site N/A Implementing Cost Contractor Cost -Do- N/A Responsibility -Do- construction Contractor/ GMC/ PMU/ MOH/LAs Contractor/ GMC/PMU Time Frame -Do- -Do- -Do- N/A Contractor Cost -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- Camps/ Yards/ Sites Camps/ Yards/ Sites and project impact area N/A N/A GMC/ PMU/ MOH Contractor/ SCDP/GMC -Do- -Do- -Do- N/A -Do- -Do- Camps/Yards Contractor s Cost Contractor/ GMC/ PMU/ MOH Conduct cultural sensitization programs for workers regarding engagement with local communities -Do- -Do- -Do- -Do- Receive timely feedback from local/host communities -Do- -Do- -Do- -Do- -Do-

56 No Adverse Social Impacts Mitigation Measures Location/ Place The contractor should adopt formal recruitment procedures to avoid ad-hoc recruitment of labourers Mandatory and continuous awareness raising for workers to refrain from unacceptable conduct of behaviour Keep a complaints/ grievances box and establish a labour GRM to report their grievances Prepare an inventory (including names/ National ID numbers/ addresses etc.) of the entire labour force employed by contractor, and share with PIU. This inventory shall be regularly updated. 06 Dust, Noise and Vibration- Temporary Impact Dust, Noise and Vibration during construction and night work will cause inconveniences/ disturbances to the residents Follow guidelines stipulated in the Environmental Management Plan (EMP) Disallow worker exposure to noise level greater than 85 dba for the duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced effectively Use the temporary and permanent dumping site as directed in contract document with Engineer supervision and guided by EMP 07 Parking of Contractor s vehicles along the Road- Temporary Impact Parking of vehicles along Contractor shall rent out suitable places for parking of the road especially in vehicles used for rehabilitation works to avoid inconveniences residential areas. to communities Implementing Cost Responsibility Time Frame -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- Sites Contractor s Cost Contractor/ SCDP/GMC During construction -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- 08 x. Social Mobility Issues- Temporary Impact Social mobility issues (community integration sensitivities) Safeguard Officer (Environment & Social) appointed by the contractor need to liaise with stakeholders and build up the community integration. 09 Occupational Health and Safety- Temporary Impact Occupational hazards which can arise from working in subproject Develop and implement site-specific Health and Safety (H&S) plan which will include measures: (a) excluding public from the site; (b) ensuring all workers are provided with and use personal N/A -Do- -Do- -Do- -Do- -Do- -Do- -Do- Rehabilitation of Moragoda Ela Cross Drains - Package B 55

57 No Adverse Social Impacts Mitigation Measures Location/ Place Implementing Cost Responsibility Time Frame protective equipment (PPE); (c) H&S Training for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; Ensure that qualified first-aid can be provided at all times. Equipped first-aid stations shall be easily accessible -Do- -Do- -Do- -Dothroughout the site Provide medical insurance coverage for workers -Do- -Do- -Do- -Do- Secure all installations from unauthorized intrusion and accident risks -Do- -Do- -Do- -Do- Provide suppliers of potable water and clean eating place where workers are not exposed to hazardous or noxious substances -Do- -Do- -Do- -Do- Provide H&S training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protection, and preventing injuring to fellow workers Ensure that visitor/s are escorted if it is required them to enter areas where hazardous conditions or substances are present. Ensure moving equipment is outfitted with audible backup alarms Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall abide by international standards and be familiar to, and easily understood by the workers, visitors, and the general public as appropriate 10 Lack awareness & gender base issues of workers - Temporary Impact -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- The absence of adequate sanitary facilities for female workers, child labour, wage disparity, entitlements for leave, Provide water and sanitation facilities for employees/ labourers as per IFC 2009 standards (1 toilet/15 persons) and separate facilities for men and women. Equal participation of women wokers shall be encouraged and ensure wage parity during the implementation of subprojects -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- Rehabilitation of Moragoda Ela Cross Drains - Package B 56

58 No Adverse Social Impacts Mitigation Measures Location/ Place lack of awareness for workers, encouraging local community for works. according to GOSL s labour policy; women are given equal pay for work of equal value. (This will be included in the contractual agreements) Prevent employing children under 16 years of age and young persons in the age group of 16 and 18 years; Equal opportunities should be given to both males and females in work assignments and depending on the type of work, underground works can be carried out regardless of gender. Train employees in the storage and handling of materials which can potentially cause soil contamination. Precaution should be followed during construction The contractor is expected to select the labour force from the local community as much as possible if the skilled people are available. Before recruiting the labour, the Contractor should inform the people in the surrounding area at least five days before the selection takes place by announcing through a public announcement system and by displaying posters in public places of the relevant villages. Entitlement of Leave for workers according to the Shop and Office Employees (Regulation of Employment and Remuneration) Act Implementing Cost Responsibility Time Frame -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- -Do- N/A -Do- -Do- 11 Handling complains from the community - Temporary Impact Pedestrians, vehicles, Conduct GRC and LRC meetings once a month or when needed residential & commercial with community representatives from site impact area N/A Contractor Cost -Do- -Docommunity and workers of construction site make complaints regarding Keep complaint registry at site office as well as at LRC office N/A -Do- -Do- -Doinconveniences due to construction works. PMU- Project Management Unit, - RDA- Road Development Authority, MOH- Medical Officer Health, LA- Local Authority, N/A- Not Applicable, A-RAP- Abbreviated Resettlement Action Plan, GMC- Galle Municipal Council, GOSL- Government of Sri Lanka, LRC- Local Resettlement Committee. Rehabilitation of Moragoda Ela Cross Drains - Package B 57

59 Annex 7: Pictorial representation of Project Impact Area Bombe Castle Canal - Rehabilitation starting point at m Damaged Access Road - Residential Area of Bombe Castle Rehabilitation of Moragoda Ela Cross Drains - Package B 58

60 Access road and canal section of Bombe Castle near Karapitiya hospital Bombe Castle Canal at chainage m Rehabilitation of Moragoda Ela Cross Drains - Package B 59

61 The starting point of Hiribura Canal (Near Hiribura Junction) Hiribura Canal crossing point at Hiribura crossroad. Rehabilitation of Moragoda Ela Cross Drains - Package B 60

62 Bombe Castle and Hiribura Canal Merging Point near Richmond City area. Community consultation for Hiribura drain Development Rehabilitation of Moragoda Ela Cross Drains - Package B 61

63 Hiribura & Bombe Castle Drain Development Consultation Rehabilitation of Moragoda Ela Cross Drains - Package B 62

RESETTLEMENT POLICY PFRAMEWORK FOR STRATEGIC CITIES DEVELOPMENT PROJECT

RESETTLEMENT POLICY PFRAMEWORK FOR STRATEGIC CITIES DEVELOPMENT PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized pg. 1 Contents Abbreviations... vii Glossary... ix Executive Summary... xiii 1. Introduction...

More information

SOCIAL MANAGEMENT FRAMEWORK

SOCIAL MANAGEMENT FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STRATEGIC CITIES DEVELOPMENT PROJECT (SCDP) SOCIAL MANAGEMENT FRAMEWORK October 2014

More information

Resettlement Action Plan (RAP): Colombo Light Rail Transit (LRT) Project July 2018

Resettlement Action Plan (RAP): Colombo Light Rail Transit (LRT) Project July 2018 Contents CHAPTER 1 Introduction... 1-1 1.1 Background of the Project... 1-1 1.1.1 Background of the Project... 1-1 1.2 Project Justification... 1-3 1.3 Objectives of the proposed Project... 1-3 1.4 Objectives

More information

SRI: Additional Financing for National Highway Sector Project

SRI: Additional Financing for National Highway Sector Project Resettlement Plan May 2011 Document Stage: Draft SRI: Additional Financing for National Highway Sector Project Hikkaduwa Baddegama Section of Hikkaduwa Baddegama Nilhena Road (B153) Prepared by Road Development

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

EBRD Performance Requirement 5

EBRD Performance Requirement 5 EBRD Performance Requirement 5 Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or loss of

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Appendix 13 Resettlement Framework Dec 2011 SRI: Local Government Enhancement Project CURRENCY EQUIVALENTS (as of 27 June 2011) Currency Unit = Sri Lankan Rupee/s (SLR/Rs) Rs1.00 = $0.0091 $1.0 = Rs 109.8700

More information

SOCIAL MANAGEMENT FRAMEWORK

SOCIAL MANAGEMENT FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Social Management Framework 2012 METRO COLOMBO URBAN DEVELOPMENT PROJECT (MCUDP) SOCIAL

More information

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems Technical Assistance Consultant s Report Project Number: 44140 Date: April 2014 TA 7566-REG: Strengthening and Use of Country Safeguard Systems Subproject: Supporting and Strengthening National-Level Capacity

More information

Sri Lanka: Northern Road Connectivity Project Additional Financing

Sri Lanka: Northern Road Connectivity Project Additional Financing Resettlement Plan June 2012 Sri Lanka: Northern Road Connectivity Project Additional Financing Prepared by the Road Development Authority, Ministry of Ports and Highways for the Asian Development Bank.

More information

STRATEGIC CITIES DEVELOPMENT PROJECT (SCDP) Resettlement Action Plan. Greater Galle City Development Project

STRATEGIC CITIES DEVELOPMENT PROJECT (SCDP) Resettlement Action Plan. Greater Galle City Development Project STRATEGIC CITIES DEVELOPMENT PROJECT (SCDP) Resettlement Action Plan of Greater Galle City Development Project Funded By World Bank and Ministry of Defense and Urban Development Government of Sri Lanka

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

SRI: Southern Road Connectivity Project

SRI: Southern Road Connectivity Project Resettlement Plan January 2016 SRI: Southern Road Connectivity Project Kesbewa to Pokunuwita Section of Pamankada Horana (B084) Road Prepared by Ministry of University Education & Highways, Government

More information

Guidance Note 5 Land Acquisition and Involuntary Resettlement

Guidance Note 5 Land Acquisition and Involuntary Resettlement This Guidance Note 5 corresponds to Performance Standard 5. Please also refer to the Performance Standards 1-4 and 6-8 as well as the corresponding Guidance Notes for additional information. Bibliographical

More information

RESETTLEMENT ACTION PLAN (RAP)

RESETTLEMENT ACTION PLAN (RAP) Public Disclosure Authorized RESETTLEMENT ACTION PLAN (RAP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Management Unit Metro Colombo Urban Development

More information

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives Page 1 of 9 Involuntary Resettlement 1. Bank 1 experience indicates that involuntary resettlement under development projects, if unmitigated, often gives rise to severe economic, social, and environmental

More information

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT DRAFT COMPARATIVE ANALYSIS OF NEPAL s LEGAL FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT Note: The following is based

More information

RESETTLEMENT POLICY FRAMEWORK. NATURAL GAS CONNECTION PROJECT IN 11 GOVERNORATES IN EGYPT (March 2014)

RESETTLEMENT POLICY FRAMEWORK. NATURAL GAS CONNECTION PROJECT IN 11 GOVERNORATES IN EGYPT (March 2014) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Submitted to : Egyptian Natural Gas Holding Company Prepared by: EcoConServ Environmental

More information

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Resettlement Implementation Plan Project Number: 37381-013 September 2012 Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Prepared by SMEC Consultants for Dry Zone Urban

More information

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007 Involuntary Resettlement - Overview Transport Forum Washington, D.C. March 30, 2007 OP 4.12 - Triggers Trigger: acquisition of land which displaces people physically and / or economically. Policy applies

More information

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING Road Development Agency 1 5 6 2 3 4 RESETTLEMENT POLICY FRAMEWORK FINAL REPORT Consultancy Services for the Design and Preparation of Bidding Documents for a Countrywide Roll-out of the Output and Performance

More information

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia)

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Republic of Sakha (Yakutia) of the Russian Federation Innovative Development of Preschool

More information

Performance Standard 5 Land Acquisition and Involuntary Resettlement

Performance Standard 5 Land Acquisition and Involuntary Resettlement Introduction Performance Standard 5 1. Involuntary resettlement refers both to physical displacement (relocation or loss of shelter) and to economic displacement (loss of assets or access to assets that

More information

Resettlement Policy Framework

Resettlement Policy Framework Urban Transport Improvement Project of Tianjin by Using the World Bank Loan Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT Resettlement and Rehabilitation (R&R) Entitlement Framework RP297 Under

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF)

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) World Bank-financed Project World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

Resettlement Policy Framework (RPF)

Resettlement Policy Framework (RPF) Sri Lanka: Local Development Support Project (LDSP) Resettlement Policy Framework (RPF) Ministry of Provincial Councils and Local Governments and Sports (MPCLGS) September 2018 Public Disclosure Authorized

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

Sri Lanka: Northern Province Sustainable Fisheries Development Project: Pesalai Fisheries Harbor Mannar

Sri Lanka: Northern Province Sustainable Fisheries Development Project: Pesalai Fisheries Harbor Mannar Resettlement Plan July 2018 Sri Lanka: Northern Province Sustainable Fisheries Development Project: Pesalai Fisheries Harbor Mannar Prepared by the Ministry of Fisheries and Aquatic Resources Development

More information

ABBREVIATED RESETTLEMENT ACTION PLAN

ABBREVIATED RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project: Irrigated Agriculture Improvement (IAIP) Subproject 1, Hoa Binh province SOCIALIST

More information

CONSTRUCTION OF PROPOSED MULTIPURPOSE BUILDING AT PAHALA KARAGAHAMUNA

CONSTRUCTION OF PROPOSED MULTIPURPOSE BUILDING AT PAHALA KARAGAHAMUNA Ministry of Provincial Councils and Local Government Local Government Enhancement Sector Project (Asian Development Bank Funded) Loan No. 3431 SRI DUE DILIGENCE REPORT (Social Safeguards) March 2017 CONSTRUCTION

More information

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement This document should be read in conjunction with the proposed World Bank Policy to understand the proposed responsibilities of the World Bank (in the Policy) and the Borrowing Country (in the Standards).

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Sri Lanka: Puttalam Housing Project

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Sri Lanka: Puttalam Housing Project Project Name Region Sector Project ID Borrower(s) Implementing Agency PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Sri Lanka: Puttalam Housing Project Report No.: AB2595 SOUTH ASIA Housing Reconstruction

More information

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014 Work plan of Independent Agency and Implementation of IFC Performance Standards Green Goal Ltd., 17 February 2014 Content IFC performance standards Legal grounds of Cambodia Resettlement planning process

More information

Project Information Document (PID)

Project Information Document (PID) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name: Region: Project Information Document (PID) Sri Lanka: Puttalam Housing

More information

Public Disclosure Authorized SFG3015 V1. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized SFG3015 V1. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized SFG3015 V1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Resettlement Policy Framework Karachi Neighborhood Improvement Project February,

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

SFG3481 V1 REPUBLIC OF RWANDA. Final Report

SFG3481 V1 REPUBLIC OF RWANDA. Final Report Public Disclosure Authorized REPUBLIC OF RWANDA SFG3481 V1 Public Disclosure Authorized LOCAL ADMINISTRATIVE ENTITIES DEVELOPMENT AGENCY (LODA) IKIGO GISHINZWE GUTEZA IMBERE IBIKORWA BY ITERAMBERE MU NZEGO

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

Resettlement Policy Framework

Resettlement Policy Framework Public Disclosure Authorized The World Bank SFG3873 REV Public Disclosure Authorized Hezhou Urban Water Infrastructure and Environment Improvement Project Public Disclosure Authorized Resettlement Policy

More information

Social Management Policy Framework

Social Management Policy Framework Appendix 1-2 SFG1851 GEF Mainstreaming Integrated Water and Environment Management Project Social Management Policy Framework (Amended) Public Disclosure Authorized Public Disclosure Authorized Public

More information

Sri Lanka: Northern Province Sustainable Fisheries Development Project: Point Pedro Harbor Jaffna

Sri Lanka: Northern Province Sustainable Fisheries Development Project: Point Pedro Harbor Jaffna Resettlement Plan July 2018 Sri Lanka: Northern Province Sustainable Fisheries Development Project: Point Pedro Harbor Jaffna Prepared by the Ministry of Fisheries and Aquatic Resources Development and

More information

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT (Loan No. 5233-VN) SFG1981 V2 RESETTLEMENT PLAN Public Disclosure

More information

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RPF of Additional Financing for Fujian Highway Sector Investment Project Contents RP1032

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized PEOPLE S COMMITTEE OF PHU YEN PROVINCE PHU YEN PROJECT MANAGEMENT UNIT OF CONSTRUCTION INVESTMENT WORKS FOR AGRICULTURE AND RURAL DEVELOPMENT ----------------o0oo---------------

More information

Revised Resettlement Plan Tibar-Gleno Road

Revised Resettlement Plan Tibar-Gleno Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING PROJECT February 2012 Democratic Republic of Timor-Leste REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS

More information

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS ENVIRONMENTAL SAFEGUARDS Objectives To ensure the environmental soundness and sustainability of projects and to support the integration

More information

DUE DILIGENCE REPORT IHALAGAMA WATER TREATMENT PLANT IMPROVEMENT PROJECT

DUE DILIGENCE REPORT IHALAGAMA WATER TREATMENT PLANT IMPROVEMENT PROJECT MINISTRY OF PROVINCIAL COUNCILS AND LOCAL GOVERNMENT LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT (ASIAN DEVELOPMENT BANK FUNDED) Loan No. 3431 SRI DUE DILIGENCE REPORT (SOCIAL SAFEGUARDS) JUNE 2017 IHALAGAMA

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft)

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft) Public Disclosure Authorized VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY FRAMEWORK (Final Draft) Table of Contents

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA PROPOSED SECOND NEW KELANI BRIDGE PROJECT A PROJECT FOR TRAFFIC IMPROVEMENT AROUND EXISTING NEW KELANI BRIDGE RESETTLEMENT ACTION PLAN (Final Report) October

More information

Subproject: Hai Lang Province: Quang Tri

Subproject: Hai Lang Province: Quang Tri Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP299 vol. 4 Ministry of Agriculture and Rural Development The World Bank Natural Disaster

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TRANSPORT NOTES TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP THE WORLD BANK,

More information

IND: Railway Sector Investment Program

IND: Railway Sector Investment Program Resettlement Framework Document Stage: Final March 2011 IND: Railway Sector Investment Program Prepared by Ministry of Railways for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 16 March 2011)

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Resettlement Action Plan

Resettlement Action Plan SFG1865 Resettlement Action Plan For TRANSPORT CONNECTIVITY AND ASSET MANAGEMENT PROJECT Road Development Authority Ministry of Higher Education and Highways SRI LANKA 2016 Resettlement Action Plan FOR

More information

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems Technical Assistance Consultant s Report Project Number: 44140 Date: April 2013 TA 7566-REG: Strengthening and Use of Country Safeguard Systems Subproject: Strengthening Involuntary Resettlement Safeguard

More information

Resettlement Plan Dili-Tibar-Liquica Road

Resettlement Plan Dili-Tibar-Liquica Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING SECTOR PROJECT November 2011 REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK

More information

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE

More information

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT CAN THO CITY PEOPLE S COMMITTEE CONSTRUCTION & INVESTMENT MANAGEMENT UNIT USING OFFICIAL DEVELOPMENT ASSISTANCE (ODA), CAN THO CITY ***** SFG1562 REV RESETTLEMENT POLICY FRAMEWORK FOR CAN THO URBAN DEVELOPMENT

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

India: Jammu & Kashmir Urban Sector Development Project

India: Jammu & Kashmir Urban Sector Development Project Resettlement Planning Document Full Resettlement Plan- Improvements to B.C Road from Shakuntala Crossing to Children s Hospital Including pedestrian subway Document Stage: Final Project Number: 41116 October

More information

Draft Resettlement Policy Framework

Draft Resettlement Policy Framework Republic of Tajikistan Ministry of Transport Central Asia Road Links Project Republic of Tajikistan Draft Resettlement Policy Framework Date: July 5, 2014 Draft Resettlement Policy Framework for Central

More information

FEDERAL REPUBLIC OF ETHIOPIAN MINISTRY OF MINES

FEDERAL REPUBLIC OF ETHIOPIAN MINISTRY OF MINES Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FEDERAL REPUBLIC OF ETHIOPIAN MINISTRY OF MINES Volume II: Resettlement Policy Framework

More information

Social Impact Assessment For TRANSPORT CONNECTIVITY AND ASSET MANAGEMENT PROJECT

Social Impact Assessment For TRANSPORT CONNECTIVITY AND ASSET MANAGEMENT PROJECT Public Disclosure Authorized SFG1866 i Public Disclosure Authorized Social Impact Assessment For TRANSPORT CONNECTIVITY AND ASSET MANAGEMENT PROJECT Public Disclosure Authorized JaEla to Puttalam Section

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY OFFICE OF OIL, GAS, AND MINERALS FERROUS MINERAL MINING

DEPARTMENT OF ENVIRONMENTAL QUALITY OFFICE OF OIL, GAS, AND MINERALS FERROUS MINERAL MINING DEPARTMENT OF ENVIRONMENTAL QUALITY OFFICE OF OIL, GAS, AND MINERALS FERROUS MINERAL MINING (By authority conferred on the environmental quality by section 63103 of 1994 PA 451, MCL 324.63103) PART 1.

More information

Environmental and Social Management Framework

Environmental and Social Management Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Pacific Aviation Investment Program Environmental and Social Management Framework Technical

More information

India: Infrastructure Development Investment Program for Tourism

India: Infrastructure Development Investment Program for Tourism Infrastructure Development Investment Program for Tourism (RRP IND 40648) Resettlement Framework (Updated) Project Number: P40648 Approved: July 2010 Revised: October 2010 India: Infrastructure Development

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

SRI: Integrated Road Investment Program

SRI: Integrated Road Investment Program Resettlement Due Diligence Report April 2017 SRI: Integrated Road Investment Program Improvement, Rehabilitation and Maintenance of Maradankadawala - Habarana section of Maradankadawela - Habarana Tirikkondiadimadu

More information

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89) Resettlement Plan March 2012 IND: Bihar State Highways II Project Siwan-Siswan Subproject (SH-89) Prepared by Bihar State Road Development Corporation, Government of Bihar for the Asian Development Bank.

More information

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the CENTRAL

More information

MINISTRY OF COMMERCE, TRADE AND INDUSTRY

MINISTRY OF COMMERCE, TRADE AND INDUSTRY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Zambia SFG2542 MINISTRY OF COMMERCE, TRADE AND INDUSTRY Project ID: No. P156492

More information

An Innovative Participatory Development Induced Involuntary Resettlement Experience in Sri Lanka

An Innovative Participatory Development Induced Involuntary Resettlement Experience in Sri Lanka An Innovative Participatory Development Induced Involuntary Resettlement Experience in Sri Lanka -Setting the Stage for Making Involuntary Resettelers Voluntary Project Partners and Beneficiaries - By

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

Ministry of Energy and Mining. Development Bank of Jamaica. Energy Security and Efficiency Enhancement Project

Ministry of Energy and Mining. Development Bank of Jamaica. Energy Security and Efficiency Enhancement Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Ministry of Energy and Mining Development Bank of Jamaica FINAL (JANUARY 21, 2011) Energy

More information

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP)

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) Resettlement Planning Document Resettlement Framework Document Stage: Draft for Consultation Project Number: 42486 June 2016 India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) The resettlement

More information

Resettlement Policy Framework

Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Tajikistan Ministry of Transport Central Asia Road Links Project Republic

More information

MLD - Kulhudhuffushi Harbor Expansion Project

MLD - Kulhudhuffushi Harbor Expansion Project Kulhudhuffushi Harbor Expansion Project (RRP MLD 36111-013) Due Diligence Report on Involuntary Resettlement and Indigenous Peoples March 2016 MLD - Kulhudhuffushi Harbor Expansion Project Prepared by

More information

THE WORLD BANK INSPECTION PANEL S EARLY SOLUTIONS PILOT APPROACH: THE CASE OF BADIA EAST, NIGERIA

THE WORLD BANK INSPECTION PANEL S EARLY SOLUTIONS PILOT APPROACH: THE CASE OF BADIA EAST, NIGERIA THE WORLD BANK INSPECTION PANEL S EARLY SOLUTIONS PILOT APPROACH: THE CASE OF BADIA EAST, NIGERIA In July 2014 the World Bank Inspection Panel, the Bank s complaints mechanism for people who believe that

More information

MATARBARI PORT ACCESS ROAD DEVELOPMENT PROJECT

MATARBARI PORT ACCESS ROAD DEVELOPMENT PROJECT Government of the People s Republic of Bangladesh Ministry of Road Transport and Bridges Roads and Highways Department Land Acquisition and Resettlement Action Plan Submitted by: November 2018 BETS Consulting

More information

Resettlement Policy Framework

Resettlement Policy Framework SFG3184 Public Disclosure Authorized GOVERNMENT OF TAMIL NADU PUBLIC WORKS DEPARTMENT WATER RESOURCES ORGANISATION Environmental & Social Assessment and Preparation of Environmental & Social Management

More information

2017 RESETTLEMENT PLAN SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT SFG2836 V7 REV

2017 RESETTLEMENT PLAN SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT SFG2836 V7 REV SFG2836 V7 REV PEOPLE S COMMITTEE OF VINH LONG PROVINCE VINH LONG DEPARTMENT OF PLANNING & INVESTMENT SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT Public Disclosure Authorized Public Disclosure

More information

SRI: Greater Colombo Wastewater Management Project

SRI: Greater Colombo Wastewater Management Project Resettlement Plan Document Stage: Updated Project Number: 36173-013 October 2017 SRI: Greater Colombo Wastewater Management Project (Sub Component: M26 Sewer Line Railway Quarters Rd in Maligawatta East)

More information

Resettlement Work Plan (RWP) for. Development of Phase 1 Area. Thilawa Special Economic Zone (SEZ)

Resettlement Work Plan (RWP) for. Development of Phase 1 Area. Thilawa Special Economic Zone (SEZ) Yangon Region Government Resettlement Work Plan (RWP) for Development of Phase 1 Area Thilawa Special Economic Zone (SEZ) November 2013 Table of Content Abbreviations CHAPTER 1 INTRODUCTION......1 1.1

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field Draft Safeguards Monitoring Report Project No. 38164-013 Draft Semi Annual Report December 2015 2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas

More information

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project Internal Monitoring Report 37231-023 March 2016 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein do not

More information

Irrigation Rules, 2056 (2000)

Irrigation Rules, 2056 (2000) Irrigation Rules, 2056 (2000) Date of publication in Nepal Gazette 2056.9.19 (2000.1.3) Amendment Irrigation (First Amendment) Rules, 2060 (2004) 2060.11.11(2004.2.23) Preamble: In exercise of the power

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

India: Infrastructure Development Investment Program for Tourism

India: Infrastructure Development Investment Program for Tourism Infrastructure Development Investment Program for Tourism (RRP IND 40648) Resettlement Framework Document Stage: Draft for Consultation Project Number: P40648 July 2010 India: Infrastructure Development

More information

SALDANHA BAY MUNICIPALITY SOLID WASTE DISPOSAL BY-LAW

SALDANHA BAY MUNICIPALITY SOLID WASTE DISPOSAL BY-LAW SALDANHA BAY MUNICIPALITY SOLID WASTE DISPOSAL BY-LAW Under of section 156 of the Constitution of the Republic of South Africa, 1996 (Act 108 of 1996), the Saldanha Bay Municipality, enacts as follows:-

More information