NEP: Energy Access and Efficiency Improvement Project

Size: px
Start display at page:

Download "NEP: Energy Access and Efficiency Improvement Project"

Transcription

1 Resettlement Plan July 2009 NEP: Energy Access and Efficiency Improvement Project Prepared by: Nepal Electricity Connectivity and Energy Efficiency Project I This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. i

2 NEPAL ELECRICITY AUTHORITY Durbarmarg, Kathmandu Draft Final LAND ACQUISITION AND RESETTLEMENT PLAN Prepared For Construction of 132 kv New T/L and Related Sub-station Works in Dumre-Damauli-New Marsyangdi Sub-station Section; Construction of 30 MVA, 132 kv/11 kv Sub-station at Chapali; and Construction of Eight New 33/11 kv, 6/8 MVA Sub-stations; and 3 New 11 kv Switching Sub-stations in Different Districts Prepared By: Nepal Electricity Connectivity and Energy Efficiency Project I NEA/ADB SSTA 7176: NEP Kathmandu, Nepal July 2009 ii

3 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Glossary of the Terms Bigha Chief District Officer (CDO) Dalit (Minor Caste Group) District Development Committee (DDC) Janajati (Ethnic/Indigenous People) There are three major units (Bigha, Kattha, and Dhur) used to measure and keep official record of land in Southern plain of Nepal known as Terai. One Bigha is equivalent to about 6869 sq.m. (Twenty Dhur makes one Kattha, and twenty Kattha makes on Bigha) There are 75 administrative districts in Nepal. Chief District Officers (CDO) are the Chief Administrative Officers of these districts. Among others, the responsibilities of the CDOs also include managing and maintaining district administration, law and order situation in the district, and implementing Land Acquisition and Resettlement Plan for the development projects to be implemented in the districts. Dalit is commonly known as untouchable in traditional Nepalese society. They belong to occupational and artisan group. Dalit Commission has defined dalit as, the community discriminated on the basis of caste and marginalized in terms of social, economic, educational, political and religious sectors. The Dalit caste, has further been divided into different groupings in accordance with socially prescribed type of works. For example, communities traditionally engaged in tailoring, or playing musical instruments, making shoes or communities involved in washing clothes, are given different family names in accordance to the type of traditional occupation they are involved with. There is one District Development Committee in each administrative districts of Nepal to be headed by elected district level political leader. In broad, Nepalese indigenous population consist two major groups, the Indo-Nepalese, whose ancestors migrated into the country from the south and the Tibeto-Nepalese, whose ancestors entered Nepal from the north. There exist cultural, linguistic, and religious differences both between and within the two groups. Differences within the Indo-Nepalese grouped are marked more by caste (a system of social hierarchy) than by ethnicity. The Tibeto- Nepalese group comprises several different ethnic groups including Bhutia, Sherpa, Gurung, Magar, Tamang, Rai, and iii `

4 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Limbu people. The Tibeto-Nepalese are concentrated in hill and mountain and the Indo- Nepalese are concentrated in the Terai plain and inner Terai. Land Acquisition and Compensation Fixation Committee Permanent Acquisition Permanent loss of Crops Restriction to Use of Land Ropani Temporary effect on land Temporary loss of Crops As defined by Nepal indigenous/nationalities/tribal, Act defines; People having their own mother tongue, distinct traditional values, and cultural identities, including social structure and written/non-written history are Indigenous and nationalities population. The committee to be formed under the chairmanship of CDO for acquiring and compensating land and properties based on Land Acquisition Act of Nepal (2034) 1977 and Electricity Rule Land and other assets permanently acquired for the construction of sub-stations, transmission towers and other associated works related to the project in accordance with the prevailing Acts. Permanently acquired land and other assets are paid compensation on replacement cost based on current market rate. All the permanently acquired land are transferred in the name of Executing Agency. Long term loss of crops production in the cultivating land permanently acquired for the project. Land not acquired permanently but used to maintain the RoW of the transmission lines. Ownership of such land will not be transferred and the owners will be allowed to cultivate their land. However, there will be restrictions to construct structures and for plantation of trees within the specified zone of influence of the transmission lines (e.g. 9m both sides for 132 kv T/L) subject to be compensated under the prevailing law as provisioned in Land Acquisition Act 1977 and Electricity Rule Land measurement unit, practices in the hilly regions of the country. One Ropani of land is equivalent to approximately sq. ft. There are three sub-units under the Ropani. They are; (a) Aana ( sq.ft.), (b) paisa (85.56 sq.ft), and (c) Daami (29.39 sq.ft) Land temporarily affected due to use by the contractors during the construction phase. Compensation for the temporary use of land to be paid by the contractors to the land owners in accordance to the agreed terms and conditions to be signed between the two parties. One time loss of crops likely to occur during the iv `

5 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Village Development Committee (VDC) Ward construction period of new transmission line or second circuit stringing on the existing double circuit towers. VDC is the local level administrative unit to be represented by locally elected political leaders in rural areas with certain geographical boundary, number of households and population. Ward is the lowest level administrative unit to be represented by elected local political leaders. As per the existing administrative system, each municipal local administrative area contains up-to 35 numbers of wards whereas the number of ward is only up-to 9 in the case of Village Development Committees (VDC). v`

6 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP ACRONYMS ADB - Asian Development Bank AH - Affected Households AP - Affected Persons CDO - Chief District Officer CFC - Compensation Fixation Committee CRO - Chief Resettlement Officer CRO - Chief Resettlement Officer DDCs - District Development Committee GON - Government of Nepal GRC - Grievance Redress Committees Ha - Hectare Km - Kilometer LARP - Land Acquisition and Resettlement Plan MRM - Management Review Mission NEA - Nepal Electricity Authority NGO - Non Government Organization NRs - Nepalese Rupees PIU - Project Implementation Unit PM - Project Manager PM - Project Manager PO - Project Office/Officer PPTA - Project Preparation Technical Assistance RoW - Right of Way RP - Resettlement Plan S/S - Sub-station SAARC - South Asian Association for Regional Co-operation SLC - Sub-Project Level Committee T/L - Transmission Line VDC - Village Development Committee vi `

7 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP I. The Project Introduction Executive Summary 1. The proposed Nepal Electricity Connectivity and Energy Efficiency Project consist of six investment components and one component on provision of expert services. The Investment component supported by the ADB grant covers six main outputs each consisting of several activities. The first four major investment outputs are; (i) Transmission System Augmentation; (ii) Distribution System Enhancement; (iii) Distribution Loss Reduction; and (iv) Generation Plant Improvement. The investment components have been proposed by Nepal Electricity Authority (NEA) based on its generation and rehabilitation plan, transmission system master plan and short-term distribution augmentation plan. The other two investment outputs are (v) Energy Efficient Lighting and (vi) Solar Power based Street lighting. The final component is to provide (viii) Expert Services assisting Public Private Partnerships (PPP) in distribution. II. Scope of Land Acquisition and Resettlement Planning 2. This Land Acquisition and Resettlement Plan (LARP) has been prepared for (a) Dumre- Damauli-New Marsyangdi Transmission Line (T/L) section under the Middle Marshyangdi - Dumauli Marshyangdi 132 kv transmission line and related Sub-station works, (b) Construction of Chapali Sub-station, and (c) Constructing Distribution and Switching Substations in different ten districts. 3. Land acquisition and resettlement planning however, may not require for; (i) Stringing of 132 kv second circuit between Middle Marsyangdi-Marsyangdi (44 km), (ii) Expansion, reinforcement and construction of new sub-stations at Damauli, Middle- Marsyangdi, and Marsyangdi (Aanbu Khairini) under the Middle Marsyangdi-Damauli-Marsyangdi New Marsyangdi 132 kv transmission line and sub-station construction components, (iii) Second circuit stringing between Butwal-Kohalpur (200 km,), (iv) Construction of distribution substations and switching centers at Swyambhu, Synaja, Mahottari, (v) Expansion of Matatirtha sub-station at Kathmandu, (vi) 66 kv underground cabling from Chabahil to Lainchaur (7.5 km) and associated sub-station upgrading works, and (vi) Installation of 220 MVAR capacitor banks to reactive power compensation at eight transmission existing sub-stations. Project activities under these components will be carried out on the available Government/NEA land or existing RoW. However, taking into account to likely losses of crops and trees during second circuit stringing the LARP has provisioned compensation for the same. Similarly, land acquisition and resettlement plan also may not require for the investment component of (i) clean energy plant development, (ii) supply side energy efficiency improvement, (iii) public private partnership in distribution, and (iv) energy efficiency in lighting, and renewable energy for street-lighting as the activities are basically related to the replacement of available technical equipment/appliances and management aspects. Table 1 provides land acquisition requirement for different investment components under the project. Table 1: Land Acquisition Requirement for the Project S.N Project Component Permanent Acquisition Restriction to Use for RoW Total (in ha) 1, New Transmission Line and Transmission Sub-station Construction 2. Construction of Distribution Sub-station and Switching Centers Total Estimated Area of Affected Land Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design. vii `

8 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP 4. As shown in the table above, an estimated area of ha of land is required to implement the project activities. Out of which, about 4.66 ha to be acquired permanently and another ha of land will be restricted to use except for agriculture purpose. As the land restrict for RoW will not be acquired permanently, the cultivator will be allowed to use the land for agriculture purpose. The Land Acquisition and Resettlement Plan (LARP) prepared under the Technical Assistance (TA) ensures; (i) types and extent of losses due to the project (ii) Principles and legal framework applicable for mitigation of losses, (iii) Entitlement matrix for compensation and other assistance based on the inventory of losses, (iv) Provisions for relocation assistance and restoration of house/businesses/income, (v) Budgets, and institutional framework for the implementation of the plan, and (vi) Responsibilities for monitoring of the LARP measures. III. Impacts 5. A total of 314 households and 1654 persons likely to be affected due to the proposed Project. The major impacts include permanent acquisition of land, restriction to use land (except to use for agriculture purpose), and acquisition of residential/commercial structures along the proposed T/L RoW (Table 2). Table 2: Affected Households and APs S.N. Type of Effect Affected HHs (No.) Total A P (No) 1. Effect on Land Effect on Structures Total Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design. 6. Of the total (314) affected households, 22 households likely to have significant impact (2 households due to effect on residential land and 20 households due to effect on their residential/commercial structures). 7. The project may also cause loss of crops in ha of land and private trees in the affected land. 8. The LARP has devised mechanism of addressing likely resettlement issues at local and project levels as much as possible through the Grievance Readdressal Committees (GRC) to ease the LARP implementation before going to the court. 9. All the project-affected households will be paid compensation at full replacement cost (market price) based on prevailing Acts/Rules, ADB Guidelines, and NEA practices. In addition to the compensation, the LARP has also provisioned different types of financial assistance (e.g. shifting, cost, transitional allowance, compensation for loss of business etc). In accordance to the Government s policy, and ADB guidelines at least, one family member from each project affected vulnerable people will also be enrolled in income restoration and improvement program to be implemented as a part of resettlement plan in Dumre-Damauli 132 kv T/L construction section, as the number of vulnerable households is comparatively higher in this project section. IV. Project Locations 10. The Project activities will cover 14 administrative districts of all-five development regions of the country (Table 3). As per the technical design, construction and viii `

9 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP expansion/strengthening of transmission sub-stations (Chapali, Matatirtha, and Lainchaur including underground cabling) and two switching centers (Mulpani and Swyambhu) will be implemented at Kathmandu. The New 132 kv T/L will be implemented in Tanahu and Gorkha districts, and nine distribution sub-stations will be constructed in different districts across the country. Table 3: Locations of Investment Components S.N. Development Region Districts Investment Component Type T/Line and S/S Distribution S/S and S/ Centers 1. Eastern Development Region Jhapa & Siraha 2. Central Development Region Kathmandu, 3. Western Development Region Gorkha, Lamjung, Tanahu, Synaja, Kaski, Parbat 4. Mid-western Development Region Banke & Bardiya 5. Far-western Development Region Kailali and Kanchanpur Source: NEA, Technical Design and Census Survey Feb. 09 Apr V. Resettlement Principles, Policy, and Legal Frameworks 11. Land acquisition principles adopted for this project recognize the Land Acquisition Act 1977, Electricity Act 1992, Electricity Rule 1993, and ADB Policy on Involuntary Resettlement Besides, other relevant Acts, Government policies and applicable NEA practices and experiences will also to be considered, while implementing this Land Acquisition and Resettlement Plan. The resettlement principles adopted in this Project will provide compensation and resettlement assistance to all affected persons and businesses, irrespective of titles and extent of impact, in accordance with ADB s Policy on Involuntary Resettlement and Government s Act. Based on the above policy features, the principles of R&R for this Project will entail the following: Negative impact on persons affected by the Project would be avoided or minimized as much as possible; Where the negative impacts are unavoidable, the Project-affected persons will be assisted in improving or regaining their standard of living. Vulnerable groups will be identified and assisted to improve their standard of living; Land replacement 1 /or cash compensation at replacement costs based on current market rate to the households affected by the loss of land. ; Cash compensation will be paid for residential/commercial/residential-cum-commercial and other structures affected by the Project at current market price; Assistance should be provided to the owners of structures and non-titleholders, who may incur loss of ability to maintain livelihood during relocation and resettlement; 1 There is also provision of land for land compensation to the APs having complete loss of their land only if government land is available in the area (Land Acquisition Act 1977, Clause 14) ix `

10 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Rehabilitation assistance i.e.; compensation for lost business and workdays (including employees) due to relocation and disruption of business enterprise. Before taking possession of the acquired lands and properties, compensation and Resettlement & Rehabilitation (R&R) assistance will be provided in accordance with this policy. Appropriate grievance redress mechanism will be established at the district, and local level to ensure speedy resolution of disputes. All activities related to resettlement planning, implementation, and monitoring would ensure involvement of women, vulnerable groups and APs. VI. Consultation and Stakeholder Participation 12. Stakeholders at different level were consulted during Resettlement Plan preparation process. The consulted stakeholders also include representatives of relevant line agencies (e.g. NEA officials, CDO, Land Measurement Office, District Forest Office, and Local NGOs etc), local people and project-affected families including the vulnerable groups, forest users groups, local level social workers, representatives of political parties, businesspersons, and other resource persons. The stakeholder consultations was found effective on disseminating information about the project, conducting socio-economic and census survey, and soliciting other relevant information/data to prepare the resettlement plan. VII. Institutional Framework 13. NEA will be the Executing Agency (EA) of the project. Managing Director will be the Chief In-charge for the implementation of all components under the project. Under the Managing Director, a project implementation team will be formed for the Transmission and Distributions Departments. NEA will assign Project Managers (PM) for the components under Directors of both Transmission and Distribution Departments. The PM will act as Project Implementation Unit (PMU) and report to the respective Directors (Transmission and System Operation Department and Distribution and Consumer Service Department) of Executing Agency. Technical, administrative and account sections will support in the overall project and LARP implementation activities to be carried out by the Project Office (PO). 14. Four Project Managers (PM) will be assigned under the Transmission and System Operation Department to implement the project activities under: (i) Butwal - Kohalpur Second Circuit Stringing; (ii) Middle-Marsyangdi Damauli Marsyangdi; (iii) Chapali-substation Construction and Chapahil-Lainchaur Underground Cabling and Sub-station Enhancement; and (iv) Expansion of Matatirtha Sub-station. Similarly, two Project Managers (one for eastern and one for central and western districts) will be assigned to implement the distribution components in 10 different districts including Kathmandu. The PM to be assigned for Eastern districts will be stationed at Dhanusha will implement the project in Eastern districts (Jhapa, Siraha, Dhanusha, Mahottari and Sarlahi). The PM to be assigned for Central and Western districts will be stationed at Pokhara and implement project activities in Western (Kathmandu, Kaski, Syanja, Parbat, and Bardiya) districts. These PMs will also be supported by technical, administration and account sections. 15. The PM will regularly update the EA on the progress of LARP implementation activities. The PM will coordinates with the Chief District Officers (CDOs) and formally request for the formation of Land Acquisition and Compensation Fixation Committee (LACFC) for the project. All land acquisition and resettlement related documents prepared for x`

11 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP the project will be handed over to the CDO. The PM to assist CDO on the valuation, verification and finalization affected assets. The PM also to involve local NGO wherever applicable, to implement the LARP. The PM will coordinate with CDO to establish Grievance Redressal Committee in accordance to Clause 11 of Land Acquisition Act 2034 (1977). The PM will update and report the EA on the progress of LARP implementation. VIII. Monitoring and Evaluation 16. The implementation of Land Acquisition and Resettlement activities will be monitored internally and externally. Generally, internal monitoring will be conducted by Project Office and external agencies or independent consultants undertake the task of external monitoring. An external monitoring agency or consultant will be engaged by NEA to carry out independent monitoring on bi-annual basis that also include post Project evaluation. External monitoring will be carried out through outside researcher or consulting agency or NGOs, or through independent consultants. IX. Budget 17. An estimated budget amounting NRs. 425,795,500.7 (US$ 5,322,444)have been calculated to implement the proposed Land Acquisition and Resettlement Plan. xi `

12 Table of Contents Glossary of Terms List of Acronyms Executive Summary I. THE BACKGROUND Introduction Scope of Land Acquisition and Resettlement Plan Projects Benefit and Impact The Benefits The Impacts Measures to Minimize the Impact Objective of the Land Acquisition and Resettlement Plan... 5 II. THE PROJECT LOCATION Locations of Transmission Line /Sub-station Components Middle Marsyangdi Damauli-Marsyangdi Chapali Sub-station Locations of Distribution Components... 7 III. SOCIOECONOMIC SURVEY AND CENSUS Socio-economic Information Affected Families and Assets Effect on Land Ownership Type of the Affected Land Extent of Effect on Land Effect on Structures Ownership of the Affected Structures Loss of Agricultural Crops and Trees Loss of Crops Loss of Provate Trees Impact on Indigenous/Ethnic and Minor Caste Households Impact on Other Socially Vulnerable Groups Loss of Common Property Resources IV. RESETTLEMENT PRINCIPLES, POLICY, AND LEGAL FRAMEWORKS ADB Resettlement Policy Policy and Legal Frameworks Difference between ADB Policy and GON Resettlement Framework NEA Practices on Land Acquisition and Resettlement Resettlement Principles & Assistance of the Proposed Project The Entitlements Compensation for Land Compensation for Loss of Crops and Trees Compensation for Structures (residential/ residential-cum-commercial) Compensation for the Loss of Community Forest Financial Assistance to Tenants Shifting/Transportation Allowance Land Replacement Cost Compensation for Loss of Business and Shifting Allowance xii

13 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Transitional Allowance to the Affected Structures Owners Income Restoration and Improvement V. CONSULTATION AND STAKEHOLDER PARTICIPATION The Approach Disclosure of RP Further Consultation & Community Participation VI. INSTITUTIONAL FRAMEWORK The Setup Transmission and System Operation Department Distribution and System Operation Department Roles and Responsibilities The Executing Agency (EA) The Project Office Grievance Redress Committee (GRC) Non-Government Organizations (NGOs) Role and Responsibilities Implementation Schedule Staff Training on Resettlement Implementation Resettlement Data Bank VII. COMPENSATION ACQUISITION AND RESETTLEMENT BUDGET Valuation of Affected Assests and Fixation of Compensation Rate Valuation Basis of Affected Assets and Associated Costs Valuation of Land Valuation of Structures Valuation of for the Loss of Crops Valuation of Affected Private Trees Valuation of Shifting/Transportation Allowances Valuation of Land Required for Replacement Valuation of Affected Business and Shifting Cost Estimation for Income Restoration and Improvement Activities Cost Estimated for Compensation and Other Financial Assistance VIII. MONITORING AND EVALUATION Need for Monitoring Internal Monitoring External Monitoring Reporting Requirements List of Tables: Table 1-1: Land Acquisition Requirement for the Project... 4 Table 1-2: Affected Households and APs... 5 Table 2-1: Locations of Investment Components... 6 Table 3-1: No of Project Affected Households Interviewed... 9 Table 3-2: Summary of Project Impact Table 3-3: Households Likely to have Significant Impact Table 3-4: Effect on Land by Purpose of Acquisition Table 3-5: Land Ownership Status Table 3-6: Extent of Impact on Land xiii `

14 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Table 3-7: HHs Likely to have Significant Effect on Residential Land..13 Table 3-8: Types of Affected Structures Table 3-9: Ownership Status of the Affected Structures Table 3-10: Estimated Loss of Crops Table 3-11: Loss of Private Trees Table 3-12: Indigenous/Ethnic and Minor Caste HHs Likely to be Affected Table 3-13: Impact on Other Vulnerable and Socially Disadvantaged Households Table 3-14: Community Forest Likely to be Affected in Dumre Damauli Section Table 4-1: Difference between ADB and GON Policy on Resettlement Framework Table 4-3: Vulnerable HHs Requiring Income Restoration & Improvement Activities Table 4-2: Entitlement Matrix Table 6-1: Schedule of Implementing Land Acquisition and Resettlement Plan Table 7-1: Compensation for Land Table 7-2: Compensation for Structures Table 7-3: Compensation for Loss of Crops Table 7-4: Compensation for Loss of Private Trees Table 7-5: Compensation for Loss of Business Table 7-6: Transitional Allowance to APs having Loss of Structures Table 7-7: Shifting Allowances for the Affected Residential/Commercial Structures Table 7-8: Land Replacement Cost Table 7-9: Income Restoration and Improvement Table 7-10: NGO Mobilization Cost Table 7-11: External Monitoring and Evaluation Table 7-12: Summary of Resettlement Budget and Cost Estimate APPENDICES : APPENDIX A-1 : APPENDIX A-2 : APPENDIX B-1 : APPENDIX B-2 : APPENDIX B-3 : APPENDIX C-1 : APPENDIX C-2 : APPENDIX C-3 : APPENDIX C-4 : APPENDIX C-5 : APPENDIX C-6 : APPENDIX D-1 : APPENDIX E-1 : APPENDIX F-1 : APPENDIX G-1 : APPENDIX H-1 : APPENDIX I -1 : Information on land acquisition requirement by investment components Details on land acquisition impact by locations. Key socio-economic characteristics of the project districts A brief descriptions of the locations of each investment component Proposed locations for the distribution sub-stations and switching centers Key socio-economic characteristics of the affected households. Breakdown of the impacts by locations. List of landowners Description of the affected structures by construction types and other details Details on permanent and temporary loss of crops List of Indigenous/Ethnic and Minor Caste HHs likely to have significant impact A synopsis of NEA s practices on implementing resettlement plan consultation matrix The Terms of Reference (ToR) of NGO The current market rate of the affected land at Dumre-Damauli Details on Land Compensation Cost Terms of Reference for External Monitoring Agency xiv `

15 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP I. THE BACKGROUND 1.1 Introduction 1. Government of Nepal aims to expand electricity to rural areas by providing quality services at a low cost, to adopt hydro-electricity as the foundation of overall economic development, and develop it as an exportable item. 2 The proposed Nepal Electricity Connectivity and Energy Efficiency Project consist of six investment components and one component on provision of expert services. The investment component supported by the ADB grant covers six main outputs each consisting of several activities. The first four major investment outputs are; (i) Transmission System Augmentation; (ii) Distribution System Enhancement; (iii) Distribution Loss Reduction; and (iv) Generation Plant Improvement. NEA proposed investment components based on its generation and rehabilitation plan, transmission system master plan and short-term distribution augmentation plan. The other two investment outputs are (v) Energy Efficient Lighting and (vi) Solar Power based Street lighting. The final component is to provide (vii) Expert Services assisting Public Private Partnerships (PPP) in distribution (i) Facilitation of Access to Clean Energy (Component 1): The following activities have been included under this components: a. Middle Marshyangdi - Dumauli Marshyangdi 132 kv transmission line and related substation works: This component is to improve the security of power evacuation from the newly constructed 70 MW Middle Marshyangdi hydropower station, and will provide general reinforcement through the important Damauli sub-station. Work will include construction of 19 km new double circuit 132 kv transmission line in Dumre-Damauli-New marsyangdi section, second circuit stringing on an existing 44 km 132 kv transmission line from Middle Marsynagdi to Marsyangdi, construction of a new 15 MVA, 132 kv/33 kv sub-station at Marshyandi, reinforcement of Damauli sub-station with construction of two 132 kv line bays, and extension of 132 kv line bays at Middle Marshyandi and Marshyandi switchyards. b. Butwal-Kohalpur 132 kv second circuit transmission line: This 200 km line is used to transfer power imported from India to Mahendranagr to the west and centre of the country. The project involves stringing of the second circuit of an existing 132 kv line built on double circuit towers, increasing the power import capacity by up to 100MW. c. Construction of Chapali Substation: This sub-project includes construction of a new 30 MVA, 132 kv/11 kv sub-station, installation of 15 km of underground 11 kv distribution line for 6 feeders at Chapali, and extension of two 66 kv GIS line bays at Lainchaur sub-station and installation of 7.5 km, 66 kv underground cable form Lainchaur to Chabahil. d. Expansion of Matatirtha Substation: The western part of Kathmandu Valley is relatively well served with 132 kv transformer capacity. However, the area experiences poor power supply due to the loading imposed on and length of 2 Three Year Interim Plan, Approach Paper (2064/ /67), National Planning Commission, July `

16 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP 11 kv feeders, resulting in frequent feeder tripping and high losses. The project will reduce average 11 kv feeder length by converting the Matatirtha 132 kv switching station into a full 132 kv sub-station. It involves constructing additional 132 kv bays, installing two transformers, and constructing 33 kv and 11 kv lines to connect to existing circuits. e. Installation of Capacitor Banks: This project involves installation of approximately 220 MVAR of capacitor banks for reactive power compensation at eight transmission sub-stations. (ii) (iii) (iv) (v) (vi) Energy Access Quality Enhancement (Component 2): In order to improve distribution system reliability, quality of supply, and reduction of technical losses, NEA has proposed to construct eight new 33/11 kv, 6/8 MVA sub-stations at (i) Kusma, (ii) Burahathwa, (iii) Mainapokhar, (iv) Dhanusha/Dharampani, (v) Paraul; (vi) Baniyani; (vii) Mirchaiya; (viii) Dhikurpokhari/Banskot, and three new 11 kv switching substations at (i) Swoyambhu, (ii) Mulpani, and (iii) Mirmi, taking into account the technical urgency and optimization of revenue generation. This will reduce the incidence of scheduled and unscheduled supply interruptions, reduce losses, and improve supply quality. Clean Energy Plant Improvement (Component 3): Under this component Marsyangdi (69 MW) Gandak (15 MW) hydropower plants will be partially rehabilitated. This work will increase availability at both power stations and will reduce self-consumption at Lower Marshyangdi, providing an estimated additional 4 GWh of energy per year. This component is composed of (a) replacement of weir control system and modernization of excitation system at Marshyangdi; and (b) installation of trash rack cleaning system at Gandak for the improvement of plant availability. NEA is contemplating engagement of individual consultants to support it during the bidding process. Supply-side Energy Efficiency Improvement (Component 4): This component is proposed to address high technical and non-technical losses in medium voltage and low voltage distribution networks in Kathmandu Valley. A series of pilot project have been prepared by NEA; kv feeders and downstream low voltage networks with unacceptably high losses have been identified and are to be rebuilt from the 11 kv feeder circuit breaker down to the customer service connection and revenue meter. These pilot projects will become model networks that can be replicated across Nepal. They will incorporate best international practice with respect to design, construction and commercial operation. To ensure that best practice is adopted, Individual consultants will be engaged to provide technical advice and support NEA for detailed design and implementation. Public Private Partnership in Distribution (Component 5): NEA is committed for introducing a franchising modality for the management and operation of selected distribution areas. NEA will identify three cities in which it will form strategic partnerships with private sector entities for management and operation of the urban electricity supply systems. ADB is presently supporting development of a franchising model, bidding guidelines, and related legal and bidding documentation. Loan proceeds will be used for expert services required to support the bidding process. Energy Efficiency in Lighting (Component 6): Presently NEA has a pilot CFL program targeting about 250,000 domestic consumers within 21 identified areas. This 2`

17 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP investment component involves scaling-up of this program to nationwide program with an estimated 1 million high quality CFLs of capacities 9W, 12W and 20W. The Project will target phase-wise domestic consumers in all electrified areas with emphasis on high impact areas. It is expected that this program will free up a minimum of 10MW of power plant and a potential reduction of 23 GWh of consumption. Also, assistance will be provided for a public awareness campaign and for an implementation consultant (local) and other resources required for the Demand-side Management (DSM) cell to be established by NEA. (vii) Renewable Energy for Street-Lighting (Component 7): This component will facilitate the promotion of solar-powered street lighting in urban areas of Nepal and will fund a pilot project involving Bhaktapur, Kathmandu and Lalitpur areas. The identified areas are durbar squares in all three municipalities, areas around Pashupati Nath temple, Swyambhu and Boudha Nath Stupas, Thamel and New Road/Indra Chowk. The Project includes purchase of solar-powered street lighting systems, replacement/installation and setting up a system to ensure proper maintenance system. It is estimated that around 1,200 street lights will be replaced with solar which will reduce peak load demand of about 0.2 MW and save about 700 MWh per year. 1.2 Scope of Land Acquisition and Resettlement Plan 2. Resettlement-planning document is required to both Government and ADB in the development projects having scope of affecting and acquiring individuals/ community assets. In line with the policy guidelines of the Asian Development Bank (ADB), and Government s Land Acquisition Act (LAA) 1977, this Land Acquisition and Resettlement Plan (LARP) has been prepared for the project activities under the investment components of (a) Dumre- Damauli-New Marsyangdi Transmission Line (T/L) section under the Middle Marshyangdi - Dumauli Marshyangdi 132 kv transmission line and related Sub-station works, (b) Construction of Chapali Sub-station, and (c) Constructing Distribution and Switching Substations in different nine districts (Fig 1). Figure 1: Scope of Land Acquisition Resettlement Planning Dumre-Damauli- Marsyangdi 132 kv T/L Construction Construction of 30 MVA Chapali Substation Distribution and Switching Substation Construction 3. Land acquisition and resettlement planning however, may not require for (i) Stringing 132 kv second circuit between Middle Marsyangdi-Marsyangdi (44 km), (ii) Expansion, reinforcement and construction of new sub-stations at Damauli, Middle, Marsyangdi, and Marsyangdi (Aanbu Khairini),(iii) 132 kv second circuit stringing between Butwal-Kohalpur (aprox 200 km,), and (iv) Construction of distribution sub-stations and switching centers at Swyambhu, Synaja, Mahottari, (v) Expansion of Matatirtha sub-station at Kathmandu, and (vi) Installation of 220 MVAR of capacitor banks for reactive power compensation at eight existing transmission sub-stations. 3`

18 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP 4. These project activities will be carried out on the available Government/NEA land or existing RoW. However, taking into account to likely losses of crops and trees the LARP has also provisioned compensation for the same. Similarly, land acquisition and resettlement plan also may not require for the investment component of (i) clean energy plant development, (ii) supply side energy efficiency improvement, (iii) public private partnership in distribution, and (iv) energy efficiency in lighting, and renewable energy for street-lighting as the activities are basically related to the replacement of available technical equipment/appliances and management aspects. Table 1-1 provides land acquisition requirement to implement the project activities. Detailed information on land acquisition and restriction requirement by investment components is included in Appendix A-1. Table 1-1: Land Acquisition and Restriction Requirement for the Project S.N Project Components Permanent Acquisition (in ha) 1, New Transmission Line and Transmission Substation Construction 2. Construction of Distribution Sub-station and Switching Centers Restriction to Use for RoW (in ha) Total (in ha.) Total Estimated Area of Affected Land Source: NEA, Technical Design and Census Survey Feb-Apr, 09 and census, Feb-Mar, 2009 Note A: One Bigha = sq.m., 1 ropani= sq.m, 1 ha = sq.m. Note B: The data presented in the table is based on preliminary census data which need to be updated during detail Design 5. As shown in the table above an estimated area of ha of land is required to implement the project activities. Out of which, about 4.66 ha to be acquired permanently and another ha of land will be restricted to use except for agriculture purpose. The land restrict for RoW will not be acquired permanently, and the cultivator will be allowed to use the land within the RoW only for agriculture purpose. The LAND Acquisition and Resettlement Plan is to ensure; (i) Types and extent of losses due to the project (ii) Principles and legal framework applicable for mitigation of losses, (iii) Entitlement matrix for compensation and other assistance based on the inventory of losses, (iv) Provisions for relocation assistance and restoration of house/businesses/income, (v) Budgets, and institutional framework for the implementation of the plan, and (vi) Responsibilities for monitoring of the LARP measures. 1.3 Projects Benefit and Impact The Benefits 6. Opportunity for hydropower development, reduction of outage in the distribution network, and total network loss, supply of efficient and reliable energy are some of the key expected benefits of the Project. Implementation of the Project may also bring several positive impacts in the socio-economic scenario of the Project districts thereby contributing towards poverty reduction through enhancing economic activities in the area through creation of employment opportunities in the production sectors due to reliable and efficient electricity supply, and even employment opportunity during construction period The Impacts 7. A total of 314 households and 1654 persons likely to be affected by the proposed Project. The major impacts include permanent acquisition of land, restriction to use land (except to use for agriculture purpose), and acquisition of residential/commercial structures 4`

19 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP along the proposed T/L RoW (Table 1-2). Appendix A-2 provides details on land acquisition and resettlement impact by investment component and locations. Table 1-2: Affected Households and APs S.N. Type of Effect Affected HHs (No.) Total Affected Persons (No) 1. Effect on Land Effect on Structures Total Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design. 1.4 Measures to Minimize Impact 8. Appropriate measures have been taken by the project design in order to minimize acquisition and resettlement impact by using the available Government/NEA lands, wherever feasible and even by changing alignment route of the 132 kv new transmission lines. NEA has changed its design drawing of 132 kv new Middle Marsyangdi-Dumre-Damauli section from Angle Point 0 7 in order to avoid the settlement area and valuable land. 3 Likewise, Government/NEA land have also been identified and proposed for the implementation of some distribution sub-stations and switching centers in different districts (e.g. construction of switching stations at Mirmi- Syanja, Swyambu-kathmandu, and distribution sub-stations at Mahottari, Dhanusha, Mainapokhar, and transmission sub-station at Marsyangdi). NEA further aims to minimize the alignment route of the transmission line in critical sections based on community demand 4 as far as technically feasible and carrying out the constructionerection of towers and stringing transmission lines during off seasons. 1.5 Objective of the Land Acquisition and Resettlement Plan 9. The Resettlement Plan (RP) also mentioned in this document as Land Acquisition and Resettlement Plan (LARP), is guided by ADB Policy on Involuntary Resettlement, Land Acquisition Act of Nepal 1977, and other relevant Acts, Rules (e.g. Electricity Act 1992, Electricity Rule 1993) and Government policies, and guidelines related T/L construction. The main objective of LARP is to identify impact and to plan measures for mitigating various losses likely to occur due to the Project. It further aims to provide guidelines to address the identified acquisition and resettlement impact and to ensure compensation and other assistances to the affected households and people under the prevailing legal norms of GON in keeping with the ADB guidelines. The LARP is based on the general findings of field reconnaissance, socio-economic, and census survey of the Project affected household and their affected assets. The plan to be up-dated and finalized during the detailed design based on changes in technical design and verification of affected persons and their assets. 3 Transmission and System Operation, Transmission Line/Sub-station Construction Department, Project Development Department (i) Final Report on Detailed Feasibility of Dumre-Damauli 132 kv Transmission line February 2006, and (ii) Dumre- Damauli 132 kv Transmission Line (Alternative Route Alignment No.III) 4 In Dumre-Damauli Section, some of the community forest users groups, and local community have requested NEA to consult with them while fixing the alignment route during detail design and construction phase in order to further minimize the impact. 5`

20 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP II. THE PROJECT LOCATION 10. The proposed Project activities will cover 14 administrative districts of all-five development regions of the country (Table 2-1). Key socio-economic characteristics of the project districts are included in Appendix B Construction and expansion/strengthening of transmission sub-stations (Chapali, Matatirtha, and Lainchaur including underground cabling) and two switching centers (Mulpani and Swyambhu) will be implemented at Kathmandu. The New 132 kv T/L will be implemented in Tanahu and Gorkha districts, and nine distribution sub-stations will be constructed in different districts across the country. A brief descriptions on the locations of each investment component is given in Appendix B-2. Table 2-1: Locations of Investment Components S.N. Development Region Districts Investment Component Type T/Line and S/S Construction Distribution S/S and Switching Centers 1. Eastern Development Region Jhapa & Siraha 2. Central Development Region Kathmandu, 3. Western Development Region Gorkha, Lamjung, Tanahu, Synaja, Kaski, Parbat 4. Mid-western Development Region Banke & Bardiya 5. Far-western Development Region Kailali and Kanchanpur Source: NEA, Technical Design and Census Survey Feb. 09 Apr Locations of Transmission Line /Sub-station Components Middle Marsyangdi Damauli-Marsyangdi 12. New 132 kv T/L will be constructed in Dumre-Damauli (18 km) section and for New Marsyangdi Sub-station (1 km) under Middle Marsyangdi-Damauli-Marsyangdi T/L and substation construction component. The proposed Dumre-Damauli T/L starts at Angle Point (AP) 0, located inside the compound of Damauli sub-station and passes through ward No. 1,3.5,6, and 11 of Vyas Municipality, ward No. 1 and 9 of Barbhanjyang VDC, Ward No. 1,2,3,4,6,7, and 8 of Ghansikuwa VDC (Tanahu District), and get connected with the tapping point (known as AP 39 of MMHEP T/L tower) located at Ward No. 8 of Chynagli VDC in Gorkha district. As per the technical design, most of the alignment route of Dumre-Damauli new T/L covers Tanahu district except from AP 21 to the tapping point (known as AP 39) located in Chyangli VDC of Gorkha. The proposed T/L mostly passes through the community forest and cultivating land. Similarly, the new T/L for proposed New Marsyangdi sub-station (approx 1 km) starts from the proposed sub-station location at Markichowck, Ward No. 3 of Aanbu Khairini VDC (Tanahu district) and crosses the agricultural land towards south and get connected at existing Marsyangdi Tower near Raudi Khola Chapali Sub-station 13. Chapali sub-station site is located at Chapali Bhadrakali VDC; ward No. 8, Bhangal, approximately 10 km north from the center of Kathmandu. As per the National Census 2001, 6`

21 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP there are 903 households in the VDC with the total population of 4544 (comprising 2278 male and 2268 female). Over the last few years, urbanization within this vicinity has been increasing rapidly. Many new residential buildings have come up in this area and this area is of potential importance from distribution expansion viewpoint. The likely impacts associated with this sub-station construction appears to be less as the proposed sub-station area is already occupied with 132 kv and 66 kv transmission line Right of Way (ROW). About 35 ropani (approx 1.79 ha) of land will be required for the proposed sub-station and about 500 meters of existing access road from main road to the substation site shall be improved. 14. Another three project activities under the transmission components (expansion of existing Matatirtha S/S and Improvement of existing Chabahil sub-station and 33 kv underground cabling) will be implemented in Kathmandu. 2.2 Locations of Distribution Components 15. Project activities under the distribution component covers 10 administrative districts of the country. Out of them, two distribution switching center (Swyambhu and Mulpani) will be implemented in Kathmandu and rest of the project activities will be implemented in different nine districts. For this component, NEA had identified locations prior to the mobilization of the TA team. However, some of the locations were confirmed during the project preparation phase. While doing so, it was also approached to identify alternative locations for some of the sub-stations. NEA will construct distribution sub-stations in one of the proposed locations of each project district. Information on the proposed locations for the distribution sub-stations and switching centers is given in Appendix B-3. 7`

22 8 ` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

NEP: Road Connectivity Sector I Project

NEP: Road Connectivity Sector I Project Resettlement Planning Document Revised Resettlement Plan Bhaktapur Changunarayan Subproject Document Stage: Final Project December: 37266-3 September 2008 NEP: Road Connectivity Sector I Project Prepared

More information

Combined Resettlement and Indigenous Peoples Plan (Transmission Components)- Draft

Combined Resettlement and Indigenous Peoples Plan (Transmission Components)- Draft Combined Resettlement and Indigenous Peoples Plan (Transmission Components)- Draft Document Stage: Draft Project Number: P44219 (NEP) April 2014 NEP: South Asia Subregional Economic Cooperation (SASEC)

More information

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

Earthquake Emergency Assistance Project

Earthquake Emergency Assistance Project Government of Nepal Ministry of Federal Affairs and Local Development Central Level Project Implementation Unit Earthquake Emergency Assistance Project (ADB Loan 3260-NEP) Section IV: Gender Equality and

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

Nepal: Rural Reconstruction and Rehabilitation Sector Development Project

Nepal: Rural Reconstruction and Rehabilitation Sector Development Project Resettlement Planning Document Resettlement Plan Grant Number: 0093 December 2010 Nepal: Rural Reconstruction and Rehabilitation Sector Development Project Kushma-Durlung-Salija Road Sub-Project, Kusma-Parbat

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Indigenous People Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP October 2013 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

Gender Equality and Development

Gender Equality and Development Overview Gender Equality and Development Welcome to Topic 3 of the e-module on Gender and Energy. We have already discussed how increased access to electricity improves men s and women s lives. Topic Three

More information

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector Resettlement Planning Document Short Resettlement Plan for Tranche-2 Components Document Stage: Draft for Consultation Project Number: TA 7096-IND April 2010 India: Preparing the Energy Efficiency Enhancement

More information

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems Technical Assistance Consultant s Report Project Number: 44140 Date: April 2013 TA 7566-REG: Strengthening and Use of Country Safeguard Systems Subproject: Strengthening Involuntary Resettlement Safeguard

More information

Resettlement Plan: Solar-LED Streetlights. BAN: Power System Efficiency Improvement Project

Resettlement Plan: Solar-LED Streetlights. BAN: Power System Efficiency Improvement Project Resettlement Plan: Solar-LED Streetlights Document Stage: Draft Project Number: 37113 April 2011 BAN: Power System Efficiency Improvement Project Prepared by: Bangladesh Power Development Board (BPDB),

More information

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

Garma-Nele-Bogal Subproject, Solukhumbu Chainage: (O )

Garma-Nele-Bogal Subproject, Solukhumbu Chainage: (O ) Government of Nepal Ministry of Federal Affairs and Local Development Central Level Project Implementation Unit Earthquake Emergency Assistance Project Lalitpur, Nepal (ADB Loan 3260-NEP) Gender Equality

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

IND: Railway Sector Investment Program

IND: Railway Sector Investment Program Resettlement Framework Document Stage: Final March 2011 IND: Railway Sector Investment Program Prepared by Ministry of Railways for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 16 March 2011)

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT DRAFT COMPARATIVE ANALYSIS OF NEPAL s LEGAL FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT Note: The following is based

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

Earthquake Emergency Assistance Project

Earthquake Emergency Assistance Project Government of Nepal Ministry of Federal Affairs and Local Development Central Level Project Implementation Unit Earthquake Emergency Assistance Project (ADB Loan 3260-NEP) Section IV: Gender Equality and

More information

IND: Mumbai Metro Rail Systems Project

IND: Mumbai Metro Rail Systems Project Social Due Diligence Report October 2018 IND: Mumbai Metro Rail Systems Project Prepared by Mumbai Metropolitan Region Development Authority, Government of India for the Asian Development Bank. ABBREVIATION

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Quarterly Social Monitoring Report (1 st Submission)

Quarterly Social Monitoring Report (1 st Submission) 2 x 100 MW CEBU POWER PLANT Quarterly Social Monitoring Report (1 st Submission) 2010.04 KEPCO SPC Power Corporation Construction Office Table of Contents I. Social Monitoring Report (as of 31 March 2010)

More information

Land Acquisition and Resettlement Due Diligence Report

Land Acquisition and Resettlement Due Diligence Report Land Acquisition and Resettlement Due Diligence Report Document stage: Draft for consultation Project Number: 48434 Loan and/or Grant Number(s): {LXXXX; GXXXX; TAXXXX} March 2016 India: Visakhapatnam-Chennai

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project Internal Monitoring Report 37231-023 March 2016 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein do not

More information

Indonesia: Enhanced Water Security Investment Project

Indonesia: Enhanced Water Security Investment Project Initial Poverty and Social Analysis March 2018 Indonesia: Enhanced Water Security Investment Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy

More information

MON: Urban Development Sector Project Bulgan Subproject

MON: Urban Development Sector Project Bulgan Subproject Resettlement Completion Report Annual Report 24 December 2012 MON: Urban Development Sector Project Bulgan Subproject Prepared by Purevsuren Dorjnamjil, Resettlement Specialist, Project Management Unit

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project Resettlement Plan (Draft) November 2013 IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project Prepared by, Government of Madhya Pradesh through MP Transco, DISCOM C, DISCOM-E

More information

EBRD Performance Requirement 5

EBRD Performance Requirement 5 EBRD Performance Requirement 5 Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or loss of

More information

Flagship Capital Corporation

Flagship Capital Corporation Resettlement Planning Document Resettlement Framework Project Number: 39906 June 2005 REG: Proposed Equity Investment Flagship Capital Corporation Prepared by Flagship Capital Corporation (Singapore) Ltd.

More information

NIGERIAN ELECTRICITY REGULATORY COMMISSION REGULATIONS FOR EMBEDDED GENERATION 2012

NIGERIAN ELECTRICITY REGULATORY COMMISSION REGULATIONS FOR EMBEDDED GENERATION 2012 NIGERIAN ELECTRICITY REGULATORY COMMISSION REGULATIONS FOR EMBEDDED GENERATION 2012 1 P a g e REGULATION NO: 0112 NIGERIAN ELECTRICITY REGULATORY COMMISSION In exercise of its powers to make Regulations

More information

Resettlement Planning Document. PHI: Visayas Base Load Power Development Project

Resettlement Planning Document. PHI: Visayas Base Load Power Development Project Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 43906 February 2010 PHI: Visayas Base Load Power Development Project Prepared by KEPCO SPC Power Corporation The

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

PAK: MFF II Power Transmission Enhancement Program (PTEIP II)

PAK: MFF II Power Transmission Enhancement Program (PTEIP II) Social Document stage: Draft 16 May, 2017 PAK: 48078-002 MFF II Power Transmission Enhancement Program (PTEIP II) Social Due Diligence Review of Upgradation/ Extension of NTDC s Telecommunication & SCADA

More information

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field Draft Safeguards Monitoring Report Project No. 38164-013 Draft Semi Annual Report December 2015 2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas

More information

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP)

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) Resettlement Planning Document Resettlement Framework Document Stage: Draft for Consultation Project Number: 42486 June 2016 India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) The resettlement

More information

RESETTLEMENT POLICY FRAMEWORK. NATURAL GAS CONNECTION PROJECT IN 11 GOVERNORATES IN EGYPT (March 2014)

RESETTLEMENT POLICY FRAMEWORK. NATURAL GAS CONNECTION PROJECT IN 11 GOVERNORATES IN EGYPT (March 2014) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Submitted to : Egyptian Natural Gas Holding Company Prepared by: EcoConServ Environmental

More information

Nepal: Rural Reconstruction and Rehabilitation Sector Development Project

Nepal: Rural Reconstruction and Rehabilitation Sector Development Project Resettlement Planning Document Resettlement Plan Grant Number: 0093 October 2010 Nepal: Rural Reconstruction and Rehabilitation Sector Development Project Sunkhani-Kanpa Road Sub-Project, Lapilang-Kanpa

More information

India: Jammu & Kashmir Urban Sector Development Project

India: Jammu & Kashmir Urban Sector Development Project Resettlement Planning Document Full Resettlement Plan- Improvements to B.C Road from Shakuntala Crossing to Children s Hospital Including pedestrian subway Document Stage: Final Project Number: 41116 October

More information

Guidance Note 5 Land Acquisition and Involuntary Resettlement

Guidance Note 5 Land Acquisition and Involuntary Resettlement This Guidance Note 5 corresponds to Performance Standard 5. Please also refer to the Performance Standards 1-4 and 6-8 as well as the corresponding Guidance Notes for additional information. Bibliographical

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT DUE DILIGENCE REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity

More information

Resettlement Due Diligence Report

Resettlement Due Diligence Report Resettlement Due Diligence Report August 2015 VIE: Power Transmission Investment Program, Tranche 2-500kV Pleiku-My Phuoc-Cau Bong Transmission Line Binh Phuoc Province Prepared by Central Vietnam Power

More information

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT Resettlement and Rehabilitation (R&R) Entitlement Framework RP297 Under

More information

Revised Resettlement Plan Tibar-Gleno Road

Revised Resettlement Plan Tibar-Gleno Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING PROJECT February 2012 Democratic Republic of Timor-Leste REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS

More information

The economic and social basis for state-restructuring in Nepal

The economic and social basis for state-restructuring in Nepal R 2013: 1 The economic and social basis for state-restructuring in Nepal Magnus Hatlebakk Charlotte Ringdal Chr. Michelsen Institute (CMI) is an independent, non-profit research institution and a major

More information

MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE NEPAL: POWER DEVELOPMENT PROJECT (P043311)

MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE NEPAL: POWER DEVELOPMENT PROJECT (P043311) MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE NEPAL: POWER DEVELOPMENT PROJECT (P043311) Management has reviewed the Request for Inspection of the Nepal: Power Development Project (P043311)

More information

Report No NP NEPAL: Power Development Project (P043311) Investigation Report. February 12, The Inspection Panel

Report No NP NEPAL: Power Development Project (P043311) Investigation Report. February 12, The Inspection Panel Report No. 93722-NP NEPAL: Power Development Project (P043311) Investigation Report February 12, 2015 The Inspection Panel Acknowledgements The preparation of this Report would not have been possible

More information

MFF 0021-PAK: Power Distribution Enhancement Investment Program Proposed Tranche 3

MFF 0021-PAK: Power Distribution Enhancement Investment Program Proposed Tranche 3 Resettlement Plan October 2012 MFF 0021-PAK: Power Distribution Enhancement Investment Program Proposed Tranche 3 Prepared by Multan Electric Power Company for the Asian Development Bank. ASIAN DEVELOPMENT

More information

Regional Cooperation and Integration Assessment (Summary)

Regional Cooperation and Integration Assessment (Summary) Regional Cooperation and Integration Assessment (Summary) 1 Country Partnership Strategy: Nepal, 2013-2017 REGIONAL COOPERATION AND INTEGRATION ASSESSMENT (SUMMARY) A. Current State of Regional Cooperation

More information

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89) Resettlement Plan March 2012 IND: Bihar State Highways II Project Siwan-Siswan Subproject (SH-89) Prepared by Bihar State Road Development Corporation, Government of Bihar for the Asian Development Bank.

More information

BAN: Railway Sector Investment Program

BAN: Railway Sector Investment Program Resettlement Planning Document Resettlement Framework Document Stage: Final Project Number: 32234 June 2006 BAN: Railway Sector Investment Program Prepared by Bangladesh Railway, Dhaka, Bangladesh The

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems Technical Assistance Consultant s Report Project Number: 44140 Date: April 2014 TA 7566-REG: Strengthening and Use of Country Safeguard Systems Subproject: Supporting and Strengthening National-Level Capacity

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the CENTRAL

More information

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TRANSPORT NOTES TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP THE WORLD BANK,

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

Donated for a Cause: Land Transfers in DRILP

Donated for a Cause: Land Transfers in DRILP Overview The Decentralized Rural Infrastructure and Livelihood Project (DRILP) has been successful in bringing much needed road and community infrastructure to Nepal's hill and mountain districts. An additional

More information

SRI: Additional Financing for National Highway Sector Project

SRI: Additional Financing for National Highway Sector Project Resettlement Plan May 2011 Document Stage: Draft SRI: Additional Financing for National Highway Sector Project Hikkaduwa Baddegama Section of Hikkaduwa Baddegama Nilhena Road (B153) Prepared by Road Development

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan November 2012 IND: Chhattisgarh State Road Sector Project Dhamdha Khairagarh Road Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1

RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1 RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1 Prepared for: CLRP-AF Project Monitoring Unit, Ministry of Environment and Spatial Planning Prepared by: replan Inc.

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

Resettlement Plan Dili-Tibar-Liquica Road

Resettlement Plan Dili-Tibar-Liquica Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING SECTOR PROJECT November 2011 REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK

More information

India: Delhi Meerut Regional Rapid Transit System Project

India: Delhi Meerut Regional Rapid Transit System Project Initial Poverty and Social Analysis October 2018 India: Delhi Meerut Regional Rapid Transit System Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

Ethnic Minorities Development Framework. PRC: Guiyang Integrated Water Resources Management Sector Project

Ethnic Minorities Development Framework. PRC: Guiyang Integrated Water Resources Management Sector Project Ethnic Minorities Development Framework Ethnic Minorities Development Framework Document Stage: Draft Project Number: P38594 September 2006 PRC: Guiyang Integrated Water Resources Management Sector Project

More information

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2019 Start Date (first day) 1 April 2019 Templates for Schedules 11a 13 (Asset Management Plan)

More information

NEP: Third Small Towns Water Supply and Sanitation Sector Project Suda Town (now Bedkot Municipality) (Kanchanpur District) Subproject

NEP: Third Small Towns Water Supply and Sanitation Sector Project Suda Town (now Bedkot Municipality) (Kanchanpur District) Subproject Resettlement Plan Project Number: 35173-013 January 2017 NEP: Third Small Towns Water Supply and Sanitation Sector Project Suda Town (now Bedkot Municipality) (Kanchanpur District) Subproject Prepared

More information

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject)

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Updated Land Acquisition and Compensation Plan April 2018 LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Part 2 Prepared by the Department of Water Supply,

More information

INDIA: Tsunami Emergency Assistance (Sector) Project

INDIA: Tsunami Emergency Assistance (Sector) Project Resettlement Planning Document Short Resettlement Plan Document Stage: Final Project Number: 39114 March 2007 INDIA: Tsunami Emergency Assistance (Sector) Project Prepared by Public Works Department, Government

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Appendix 13 Resettlement Framework Dec 2011 SRI: Local Government Enhancement Project CURRENCY EQUIVALENTS (as of 27 June 2011) Currency Unit = Sri Lankan Rupee/s (SLR/Rs) Rs1.00 = $0.0091 $1.0 = Rs 109.8700

More information

Resettlement Policy Framework

Resettlement Policy Framework Urban Transport Improvement Project of Tianjin by Using the World Bank Loan Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

MLD - Kulhudhuffushi Harbor Expansion Project

MLD - Kulhudhuffushi Harbor Expansion Project Kulhudhuffushi Harbor Expansion Project (RRP MLD 36111-013) Due Diligence Report on Involuntary Resettlement and Indigenous Peoples March 2016 MLD - Kulhudhuffushi Harbor Expansion Project Prepared by

More information

2009 Bill 50. Second Session, 27th Legislature, 58 Elizabeth II THE LEGISLATIVE ASSEMBLY OF ALBERTA BILL 50 ELECTRIC STATUTES AMENDMENT ACT, 2009

2009 Bill 50. Second Session, 27th Legislature, 58 Elizabeth II THE LEGISLATIVE ASSEMBLY OF ALBERTA BILL 50 ELECTRIC STATUTES AMENDMENT ACT, 2009 2009 Bill 50 Second Session, 27th Legislature, 58 Elizabeth II THE LEGISLATIVE ASSEMBLY OF ALBERTA BILL 50 ELECTRIC STATUTES AMENDMENT ACT, 2009 THE MINISTER OF ENERGY First Reading.......................................................

More information

Advantages of hydro generation: Resettlement of Indigenous Bote (Fisherman) families: A Case Study of Kali Gandaki "A" Hydroelectric Project of Nepal

Advantages of hydro generation: Resettlement of Indigenous Bote (Fisherman) families: A Case Study of Kali Gandaki A Hydroelectric Project of Nepal Advantages of hydro generation: Resettlement of Indigenous Bote (Fisherman) families: A Case Study of Kali Gandaki "A" Hydroelectric Project of Nepal Rajendra P. Thanju Environmental and Social Studies

More information

Involuntary Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook Draft Working Document

Involuntary Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook Draft Working Document Involuntary Resettlement Safeguards A Planning and Implementation Good Practice Sourcebook Draft Working Document November 2012 This working document was prepared by staff of Asian Development Bank. It

More information

Key Issues: Climate Zone: As: Tropical humid. Subjects: - Restoration of livelihood and Rebuilding of Resettled Communities

Key Issues: Climate Zone: As: Tropical humid. Subjects: - Restoration of livelihood and Rebuilding of Resettled Communities IEA Hydropower Implementing Agreement Annex VIII Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 07-01: Resettlement - Chiew Larn Multipurpose Project, Thailand Key

More information

Ministry of Energy and Mining. Development Bank of Jamaica. Energy Security and Efficiency Enhancement Project

Ministry of Energy and Mining. Development Bank of Jamaica. Energy Security and Efficiency Enhancement Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Ministry of Energy and Mining Development Bank of Jamaica FINAL (JANUARY 21, 2011) Energy

More information

Deutscher Tropentag Berlin, 5-7 October Conference on International Agricultural Research for Development

Deutscher Tropentag Berlin, 5-7 October Conference on International Agricultural Research for Development Deutscher Tropentag 2004 - Berlin, 5-7 October 2004 Conference on International Agricultural Research for Development Hydropower Development in Nepal: Local Responses to Technology and Formal Institutions

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

Resettlement and Income Restoration in Thilawa SEZ

Resettlement and Income Restoration in Thilawa SEZ Resettlement and Income Restoration in Thilawa SEZ Lessons from the first & second phases and emerging good practices Thilawa SEZ Management Committee (TSMC) Yangon Region Government (YRG) 20 February

More information

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF)

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) World Bank-financed Project World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014 Work plan of Independent Agency and Implementation of IFC Performance Standards Green Goal Ltd., 17 February 2014 Content IFC performance standards Legal grounds of Cambodia Resettlement planning process

More information

Economic and Social Council

Economic and Social Council United Nations E/C.19/2010/12/Add.5 Economic and Social Council Distr.: General 16 February 2010 Original: English Permanent Forum on Indigenous Issues Ninth session New York, 19-30 April 2010 Items 3

More information

PROCEDURES AND GUIDELINES FOR APPLYING SERVICE CONNECTION AT 11 KV / 33 KV HIGH TENSION (HT) & 132 KV EXTRA HIGH TENSION (EHT)

PROCEDURES AND GUIDELINES FOR APPLYING SERVICE CONNECTION AT 11 KV / 33 KV HIGH TENSION (HT) & 132 KV EXTRA HIGH TENSION (EHT) PROCEDURES AND GUIDELINES FOR APPLYING SERVICE CONNECTION AT 11 KV / 33 KV HIGH TENSION (HT) & 132 KV EXTRA HIGH TENSION (EHT) Note. The procedures and guidelines mentioned herein are in accordance with

More information

India: Infrastructure Development Investment Program for Tourism

India: Infrastructure Development Investment Program for Tourism Infrastructure Development Investment Program for Tourism (RRP IND 40648) Resettlement Framework Document Stage: Draft for Consultation Project Number: P40648 July 2010 India: Infrastructure Development

More information

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement This document should be read in conjunction with the proposed World Bank Policy to understand the proposed responsibilities of the World Bank (in the Policy) and the Borrowing Country (in the Standards).

More information

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project Initial Poverty and Social Analysis May 2018 People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project This document is being disclosed to the public in accordance

More information

Resettlement Framework

Resettlement Framework i Resettlement Framework Resettlement Framework Document Stage: Draft for Consultation September 2007 Cambodia: Tonle Sap Lowland Stabilization Sector Project The Resettlement Framework is a document of

More information

Resettlement Framework. BHU: Urban Infrastructure Project. October Prepared by the Royal Government of Bhutan for the Asian Development Bank.

Resettlement Framework. BHU: Urban Infrastructure Project. October Prepared by the Royal Government of Bhutan for the Asian Development Bank. Resettlement Framework October 2011 BHU: Urban Infrastructure Project Prepared by the Royal Government of Bhutan for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 5 October 2011) Currency unit

More information

REF: Appeal to Consider Alternatives for the Nepal Power Development Project in Sindhuli District

REF: Appeal to Consider Alternatives for the Nepal Power Development Project in Sindhuli District 18 February 2013 To, Dr. Jim Yong Kim President, World Bank 18 H Street, NW Washington, DC 20433 USA REF: Appeal to Consider Alternatives for the Nepal Power Development Project in Sindhuli District Dear

More information

NEPAL ELECTRICITY AUTHORITY

NEPAL ELECTRICITY AUTHORITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NEPAL ELECTRICITY AUTHORITY (A GOVERNMENT OF NEPAL UNDERTAKING) TRANSMISSION LINE/SUBSTATION

More information

Cambodia: Agriculture Sector Development Program

Cambodia: Agriculture Sector Development Program Resettlement Planning Document Resettlement Plan (Boeung Ket) Document Stage: Final Project Number: 34380 May 2009 Cambodia: Agriculture Sector Development Program Prepared by National Divestment Committee

More information

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ------------------------------------------------------------------ SFG1163 V11 Public Disclosure Authorized Public

More information