Resettlement Planning Document

Size: px
Start display at page:

Download "Resettlement Planning Document"

Transcription

1 Resettlement Planning Document Project Number: May 2015 IND: Rajasthan Urban Sector Development Investment Program - Tranche 2 Submitted by Rajasthan Urban Infrastructure Development Project, Jaipur This report has been submitted to ADB by the Rajasthan Urban Infrastructure Development Project, Jaipur and is made publicly available in accordance with ADB s public communications policy (2011). It does not necessarily reflect the views of ADB. This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area

2

3 Compliances of ADB comments on SRP, for Urban Transport and Roads at Bundi town dated * S.No Comments Compliance (i) On the cover page under documents stage Complied. please mention Updated Resettlement Plan instead of draft for consultation. (ii) Executive Summary, Para 7, page 3: In the sentence stating with As per transect walks. Please clarify which road is referred to when mentioning.12 shops along this road. The road last mentioned in the preceding paragraphs is Muktidham Road which does not have impacted shops; (iii) (iv) (v) (vi) (vii) (viii) (ix) Main text para 9: Please delete the sentence stating with There is no major impact on gender Para 10: Please report the total number of affected persons involved in the consultations referred to and which other stakeholders from government and civil society may have participated: Chapter VIII: Revise title to Temporary Relocation of Small Businesses. This is more appropriate as there is no relocation of housing and settlements. Chapter IX: Please add a sentence or two on the rates applied for compensation of livelihood losses and how these were derived/calculated and clarify how these constitute replacement cost: Please add a new chapter on Common Property Resources and specify their number and types and how losses of these are compensated/rehabilitated, showing that replacement cost was applied. Add current table 6(a) to this new chapter and give it the new number 6,numbering all subsequent tables accordingly(i,e. current table 6 becomes table 7,etc) Page 38: Replace the term transcript with Translation. Annexure 13 and 14: Please provide translations of Hindi text. Complied. Para 7 has been modified and briefly described about the roads, where works will be carried out and the stretch of roads, where kiosks, shops may be affected during construction are mentioned. Complied. Sentence There is no major impact on gender has been deleted in para 10 (renumbered). Complied. Consultation with APs as well as Stakeholders (in quantity) has been added in Para 11 (renumbered). Changed, refer heading of Chapter IX. Complied. Added paragraphs (para 20) as desired to explain rates applied for compensation of livelihood losses and how these were derived/calculated and clarified how these constitute replacement cost in Chapter X. Complied. Chapter-III added in this RP, describing the impacted on CPRs and budgetary provision (table 6a) for restoration/reconstruction of these CPRs added in Chapter XI. Changes made. Complied and translations provided * Comments received in office after wrap up meeting i.e

4 Rajasthan Urban Sector Development Investment Program(RRP IND 40031) Resettlement Plan Document Stage: Updated Resettlement Plan Project Number: DECEMBER 2014 India: Rajasthan Urban Sector Development Investment Program Bundi Urban Transport and Roads Subproject Prepared by Local Self Government Department The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB s Board of Directors, Management, or staff, and may be preliminary in nature.

5

6 ABBREVIATIONS ADB Asian Development Bank BPL Below Poverty Line CBO Community-Based Organization CLC City Level Committees DSC Design and Supervision Consultants GRC Grievance Redress Committee IPIU Investment Program Implementation Unit IPMC Investment Program Management Consultants IPMU Investment Program Project Management Unit LAA Land Acquisition Act LSGD Local Self Government Department MFF Multitranche Financing Facility NGO NoC Non-governmental Organization No Objection Certificate NRRP National Resettlement and Rehabilitation Policy OMC Operations and Maintenance Contractors PAF Project Affected Family PAH Project Affected Household PIU Project Implementation Unit PMU Project Management Unit RoW Right of Way RUIDP Rajasthan Urban Infrastructure Development Project RUSDIP Rajasthan Urban Sector Development Investment Programme SDS Social Development Specialist SRP Short Resettlement Plan STP Sewerage Treatment Plant ULB Urban Local Body WTP Water Treatment Plant

7

8 TABLE OF CONTENTS I. PROJECT DESCRIPTION... 1 II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT... 4 III. IMPACT ON COMMON PROPERTY RESOURCES (CPR)... 8 IV. SOCIO-ECONOMIC INFORMATION/PROFILE... 8 V. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION... 9 VI. GRIEVANCE REDRESS MECHANISMS VII. POLICY AND LEGAL FRAMEWORK VIII. ENTITLEMENTS IX. TEMPORARY RELOCATION OF SMALL BUSINESSES X. INCOME RESTORATION AND REHABILITATION XI. RESETTLEMENT BUDGET AND FINANCIAL PLAN XII. INSTITUTIONAL ARRANGEMENTS XIII. IMPLEMENTATION SCHEDULE XIV. MONITORING AND REPORTING Annexures ANNEXURE 1: SOCIO-ECONOMIC DETAILS OF APS (PREVIOUSLY IDENTIFIED) ANNEXURE 2: SOCIO-ECONOMIC SURVEY DETAILS OF ADDITIONAL APS ANNEXURE 3 SUMMARY DETAILS OF CONSULTATIONS ANNEXURE :4 SUMMARY OF CONSULTATION WITH ADDITIONAL APS ANNEXURE 5 MINUTES OF MEETING ANNEXURE 6 APPROVAL LETTER FOR ADDITIONAL WORKS ANNEXURE 7: SUMMARY ACTIVITIES ON COMMUNITY AWARENESS AND PARTICIPATION PROGRAMME (CAPP) ANNEXURE 8: POLICY FRAMEWORK AND ENTITLEMENTS ANNEXURE 9: COPY OF IDENTITY CARDS ANNEXURE 10 DETAILS OF COMPENSATION DISBURSED TO 23 APS ANNEXURE: 11 REFERENCE OF BOQ ANNEXURE 12 IDENTIFICATION OF MISSING APS ANNEXURE-13 NEWS PAPER CLIP ANNEXURE-14 LETTER OF FOREST DEPARTMENT ANNEXURE 15 COPY OF BPL CARD PROVIDED BY AP (S.NO-2&3) ANNEXURE 16 SITE PHOTOGRAPHS... 46

9

10 1 EXECUTIVE SUMMARY 1. The Local Self Government Department (LSGD) under the Urban Governance Department of Government of Rajasthan (the Government) is executing the Rajasthan Urban Sector Development Investment Program (RUSDIP) in 15 towns namely, Alwar, Baran-Chhabra, Barmer, Bharatpur, Bundi, Chittorgarh, Churu, Dholpur, Jaisalmer, Jhalawar-Jhalarapatan, Karauli, Nagaur, Rajsamand, Sawai Madhopur and Sikar with financial assistance from Asian Development Bank (ADB) under Multi Tranche Financing Facility (MFF). The investment program covers major urban infrastructure works viz., Water Supply, Waste Water Management, Solid Waste Management, Urban Transport and Roads, Social Infrastructure, Support Infrastructure for Cultural Heritage and Urban Drainage. 2. Bundi comprises a road network of km, consisting of km bituminous roads, km cement concrete roads and km WMM road. Municipal Board of Bundi (MBS) and Public Works Department (PWD) both are maintaining the roads. From traffic/safety/environmental point of view, the up gradation and widening of these roads are important for Bundi Town 3. Earlier Short Resettlement Plan (SRP) has been revised for the Bundi Urban Transport and Roads Subproject, due to changes in scope of works. At first, 20 numbers of roads were taken up under this project but due to non-clearance from the Forest Department, 7 roads were dropped and clearance was obtained for only 13 roads (see annexure14). After the minimization of scope of works, the subproject was covered for widening of around 14.8 km of works instead of km of total road lengths which constitute 13 different roads whose length varies from 500 m to 1.5 km. 4. Now again a revision is required in SRP due to change in scope and an additional road proposed and approved through District Collector-Bundi. Additional road namely Mukti Dham Ashram road for widening with length of about 135 mts is proposed. Apart from this, some changes were also made in road number 17 and 3 respectively, in which the length of road (road no. 17) has also increased from 156 M to 756 M (Nainwa link road to Indraprastha colony) and width of road has increased from 10.5 to 14 mtr for the length of 1800 M of road no. 3 (Rotary circle to Petrol Pump by pass) and thus total length is now increased from 14.9 to 15.7.(see annexure 5& 6). 5. Detailed design began in the middle of Year 2010 and was completed by December 2010 and SRP was prepared accordingly ( ) but later on due to change in scope and non clearance given by forest department etc. for some roads, SRP was revised and approved by ADB on and respectively. Now again a revision is required due to changes in scope of works in two street and additional work for Mukti Dham Ashram road. 6. This subproject has been categorized as B for Involuntary Resettlement (IR) impact as per the ADB s Policy on Involuntary Resettlement, Effort was made to avoid land acquisition and resettlement. Overall impacts would be further minimized through careful sitting and alignment during subproject implementation. 7. Summary of Resettlement Impact: Sub-project design minimized land acquisition and resettlement impacts. As per design, civil works will not result in any permanent impacts to structures (both residential and commercial structures), and common properties too. Keeping this in view the construction of the road improvements will be carried out within the existing right-of-way (RoW). As per the latest variation/change in the scope of works, 14 road works will be taken-up, earlier it was 13 roads. As per

11 2 census survey and transect walk done in December 2010 during previous project roads, impact was identified only in 4 roads with temporarily impact on livelihood of 49 APs. These 49 APs are basically roadside mobile venders or mobile/ambulatory hawkers and vendors. After the variation in the scope of works, transect walk was again conducted to study the impacts of road number 3 for widening & additional 600 mtr works of Nainwa road to Indraprasta Colony work in October 2014 and protection wall and widening of new road namely Mukti Dham Road in December 2014 respectively, in all the areas where civil works will be taken-up. In road number 3 from Rotary Circle to Panchganv with length of 1800 M, it is proposed to increase the width of the road from 10.5 M to 14 M, so temporary livelihood impact will be added to 12 more numbers of APs, earlier 22 APs were reported in this section. These 12 APs may experience temporary livelihood impacts as the work will be in front of their shops resulting to possibility of loss of access and thus provision of R&R assistance has been considered for them. Shifting assistance has also considered for 7 numbers of APs. Consultation was made with all of them and they have agreed to shift their kiosks nearby this location As per design and confirmation by the design engineer, none of the residential and commercial structure will be demolished. There is no land acquisition and IR impact in the newly proposed 135 mtr works near Mukti Dham. Although there are two CPR, which are close to the proximity to the project site (near Mukti Dham) will be affected during project execution. One is the temporary ramp, where dead body is kept before interning in to the Mukti Dham and second one is permanent Shelter. Decision was made by the IPIU for up gradation of first one and permanent shelter will be demolished and reconstructed in the available land of Mukti Dham road. Budget provision has been made in the SRP for reconstruction of the shelter.. Detail of APs identified is mentioned in Annexure 2. Thus 61 APs are considered to be affected on a temporary basis. 8. Public Consultations: Consultations were carried out during RP preparation and will continue throughout the subproject cycle. Consultation with newly affected person was done on 28th Oct, 2014 and will continue throughout the project implementation. A grievance redress mechanism has already been formed as the City Level Committee (CLC) acting as grievance redress committee as explained in this RP. 9. Policy Framework and Entitlements: The policy framework and entitlements for the program are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984), and the National Resettlement and Rehabilitation Policy, 2007 (NRRP); ADB s Policy on Involuntary Resettlement, 1995; and the agreed Resettlement Framework. 10. Institutional Arrangements: The LSGD is the executing agency responsible for overall technical supervision and execution of all subprojects funded under the Program. The Implementing Agency is the Investment Program Management Unit (IPMU) of the ongoing Rajasthan Urban Infrastructure Development Project (RUIDP), which has been expanded and assigned as the IPMU, to coordinate construction of subprojects and ensure consistency across the towns. The inter-ministerial Empowered Committee provides LSGD with central policy guidance and coordination. The IPMU is assisted by: Investment Program Management Consultants (IPMC) who manages the Program and assure technical quality of the design and construction; and Design and Supervision Consultants (DSC), who are designing the Infrastructure, managing the tendering of Contractors, and supervising construction. NGO is responsible for assisting in the RP implementation. 11. RP Implementation and Monitoring: All compensation is to be paid prior to start of the civil work. RP implementation will be closely monitored to provide the IPMU with an effective basis for assessing resettlement progress and identifying potential difficulties and problems. Internal monitoring will be undertaken by the IPIU with assistance from the

12 3 IPMU. Monthly progress report will be prepared by the IPIU and will be compiled by the IPMU on a quarterly/bi-annual basis for its due submissions to ADB. 12. RP implementation is going on for this project. Now works has been completed in most of the roads except road no-3 and newly proposed works. R&R assistance have already been disbursed to 23 numbers of APs on dated & (see annexure 10). 2 APs have migrated from the town and one AP has expired, this AP has no one in his family for claiming the amount as confirmed by neighbors during consultation (see annexure 12). APs of Road number-3 were not paid due to delay in laying of sewer pipeline in this section (Ref annexure11).

13

14 1 I. PROJECT DESCRIPTION 1. Rajasthan Urban Sector Development Investment Program (RUSDIP) is intended to optimize social and economic development in 15 selected towns in the State, particularly district headquarters and towns with significant tourism potential. This will be achieved through investments in urban infrastructure (water supply; sewerage and sanitation; solid waste management; urban drainage; urban transport and roads), urban community upgrading (community infrastructure; livelihood promotion) and civic infrastructure (art, culture, heritage and tourism; medical services and health; fire services; and other services). RUSDIP will also provide policy reforms to strengthen urban governance, management, and support for urban infrastructure and services. The assistance will be based on the state-level framework for urban reforms, and institutional and governance reforms recommended by the Government of India (the Government) through the Jawaharlal Nehru National Urban Renewal Mission (JNNURM) and Urban Infrastructure Development Scheme for Small and Medium Towns (UIDSSMT). 2. RUIDP Phase II is being implemented over a seven year period beginning in 2008, and being funded by a loan via a Multitranche Financing Facility (MFF) of the Asian Development Bank (ADB). The Executing Agency is the Local Self-Government Department (LSGD) of the Government of Rajasthan; and the Implementing Agency is the Investment Program Management Unit (IPMU) of the Rajasthan Urban Infrastructure Development Project (RUIDP). 3. The subproject is located in town Bundi of District Bundi, in the state of Rajasthan. The existing carriageway varies from 3.5 to 9.0 m for most of the stretch. Due to inadequate carriageway width, the road becomes congested resulting in low speeds for moving vehicles and also the possibility of accidents increase, whereby the traffic passing through this stretch suffers the most. This is fourth revision of Short Resettlement Plan (SRP) for the Bundi Urban Transport and Roads Subproject and the current revision is made due to change in scope of works and inclusion of an additional road. Initially number of roads taken up under this sub project was 20. But later on after getting non-clearance from the Forest Department, 7 numbers of roads were dropped and clearance was obtained for only 13 number of roads (Refer to Annexure 14). After the minimization of scope of works, the subproject covered widening of around 14.8 km of works instead of km of total road lengths which constitute 13 different roads whose length varies from 500m to 1.5 km. 4. Now as per proposal of District Collector Bundi, approval has been given for widening of one additional road, which length is around 135 mtr. The proposed works is adjoining to the Mukti Dham Ashram. In another decision, the length of road no -17 has also increased from 156 mtr. to 756 mtr. (Nainwa link road to Indraprastha colony,) and decision was also made to increase the width from 10.5 to 14 mtr for 1800 mtr length of road number 3 (Rotary circle to Petrol Pump by pass), refer to Annexure 5 & 6.. Thus total length is now increased from 14.9 to 15.7 Kms. Details of proposed roads and its currently proposed works are mentioned in Table 1. The subproject location is illustrated in the map in Figure 1 and 2.

15 2 Sl.No. Road No Table 1: Details of Roads and currently proposed works Name of Road Total Proposed Works length (in mtr) 1 2 Ranjeet Cinema to Mahabir circle via LIC 2 3 Rotary circle to Bihari Circle to Rani ji Babri to Petrol Pump By pass 3 4 Circuit to Dwarika Hotel to Ambedkar Circle to Mandi Tiraha 4 5 Chatrapura Village Bawari to Dwarika hotel to Azad Park 5 6 Construction of CC road Unala Ki Dungri 6 7 Ambedkar Circle to N.H-12 via Rain Basera 7 8 Govt. college Chouraha to S.P office 8 9 S.P office Tiraha to Murti Nandan Colony via Dayanand Colony 9 10 S.P office tiraha to New Tehsil Construction of CC road from Puliya Nainwa Road to Jawahar Colony Tiraha via P.H.E.D office Construction of CC road from Old Mathura Road to Housing Board Colony via Vinus Public School Construction of CC link road to Nianwa Road to Inderprastha Colony Construction of CC Road near Girls.Sr.Secondary School,Vikash Nagar Decision was made to increase the width from 10.5 to 14 mtr for 1800 mtr length from Rotary circle to Panchganv Length has been increased from 156 mtr to 756 mtr. 248 Total Length Additional Road taken up under this project 14 Protection wall and 135 Widening of Road Mukti Dham Total 15695

16 Figure-1: Subproject Location 3

17 4 Figure-2: Subproject Location for the new works Rotary circle to Panchganv 5. This Resettlement Plan (RP) has been updated during December 2014 for the Bundi Urban Transport and Roads Subproject as part of RUIDP Phase II. The RP has been prepared based on the detailed engineering design in 2010 and latest variation/change in scope of works during October 2014 and inclusion of additional road in December This subproject has been categorized as B for Involuntary Resettlement (IR) impact as per the ADB s Policy on Involuntary Resettlement, II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 6. Sub-project design minimized land acquisition and resettlement impacts. As per design chosen, the civil works will not result in any permanent impact on structures (both residential and commercial structures). Keeping this in view the construction of the road improvements will be carried out within the existing Right-of-Way (RoW). As per the latest variation/changes in scope, works will be taken-up in 14 numbers of roads. Initially survey was carried out in all roads which are 20 in number. But later on 13 roads has been taken up instead of 20 roads, because No Objection Certificate (NoC) was not provided by the Forest Department. During survey no APs were identified on these roads, which were dropped due to non-clearance of Forest Department (refer to Table 3). During transect and as per census survey, impact was identified on 49 APs in 4 roads only. These 49 APs with small business activities were identified in December 2010 which are to be temporarily affected (refer to Annexure 1). None of these small business structures are to be demolished. All are basically roadside mobile venders or mobile/ambulatory hawkers and vendors.

18 5 7. After the variation in the scope of works and inclusion of additional road, transect walk was again conducted in the respective road to study the IR impacts. During survey temporary livelihood impact are reported on 12 APs such as vendors, kiosks and small shops during widening of road in the 1800 mtr section of the road (Rotary circle to Panchganv), which is the part of road no 3. In the remaining roads namely additional 600 mtr works of Nainwa road to Indraprasta Colony work and newly proposed 135 mtr works near Mukti Dham, no IR impacts are envisaged. None of the residential and commercial structure will be demolished. As per transect walks and surveys conducted on , these all 12 shops along this road may experience temporary livelihood impacts as the work will be in front of their shops resulting to possibility of loss of access and thus provision of R&R assistance has been considered for them. Shifting assistance has been considered for 7 number of APs. Consultation was made with all of them and they have agreed to shift their kiosks nearby the location. Detail of these 12 APs are mentioned in Annexure 2 separately. In Mukti Dham road, there are two CPRs, which are close to the proximity to the project site (near Mukti Dham) will be affected during project execution. Detail about these CPRs are depicted in separate chapter number 3 namely Impact on Common Property Resources. 8. None of these small business structures are to be demolished due to project activities as construction work will be confined to the existing RoW. Thus these 61 business activities are considered to be affected on a temporary basis. Out of the total 61 small business activities, there are 10 tea shops, 14 pan stalls, 5 marriage band party shops, 5 readymade garments shop, 10 blacksmiths, 6 hair cutting saloons and 1 each as general store, CD shop, furniture shop shoe maker, juice centre, tyre-tube repairing shop, hardware shop, welding shop, tent house etc. Details are given in Table 2. Table 2: Types of Temporary Impacts S.No Type of temporary Impacts Numbers 1 Tea Shops 10 2 Pan Shops 14 3 Marriage Band party Shops 05 4 Readymade garments Shops 05 5 Blacksmiths 10 6 Hair Cutting Saloons 06 7 General Store 01 8 Music CD Shop 01 9 Furniture Shop Shoe Maker Juice centre Tyre-Tube Repairing Hardware Weilding Tent House Cycle repairing 01 Total 61 Source: census and Socio-Economic Survey, December 2010 & October 2014

19 6 Table 3: Subproject Components and its Impact on Land Acquisition and Resettlement S.No Name Of Components Permanent Impact on Land Acquisition and Resettlement 1 Construction of CC road Bhilo Ka Darbaza to Dalalpura Tiraha via Choth Mata Mandir.(677 mtr length) 2 Construction of road from Ranjeet Cinema Tiraha to Mahavir Circle vialic office.(875) mtr length) 3 Widening of Road Rotary circle(n.h-12) to Bihari Circle to Raniji Ki Bawari to Petrol Pump by pass.(4650 mtr).decision was also made to increased the width from 10.5 to 14 mtr for 1800 mtr length from Rotary circle to Panchganv) 4 Widening of Road Circuit to Dwarika Hotel to Ambedkar Circle to Mandi Tiraha (N.H-12) mtr. 5 Widening & Strengthning Chatrapura Village Bawari to Dwarika hotel to Azad Park mtr. 6 Construction of CC road Unala Ki Dungri mtr. 7 Construction of CC road Ambedkar Circle to N.H-12 via Rain Basera-1300 mtr. 8 Construction of CC road from Govt. college Chouraha to S.P office-385 mtr. 9 Widening & Strengthening S.P office Tiraha to Murti Nandan Colony via Dayanand Colony mtr. 10 Widening & Strengthening S.P office tiraha to New Tehsil.-588 mtr. Temporary Impact Remarks NO NO No work proposed due to non-clearance of Forest Department. NO NO No IR impact envisaged. NO YES Temporary impact on loss of income and livelihood of 34 road side small business activities which will be affected during the period of construction. NO YES Temporary impact on loss of income and livelihood of 22 road side small business activities which will be affected during the period of construction.. NO NO No IR impact envisaged. NO NO No IR impact envisaged. NO YES Temporary impact on loss of income and livelihood of 3 road side small business activities which will be affected during the period of construction NO NO No IR impact envisaged. NO YES Temporary impact on loss of income and livelihood of 2 road side small business activities which will be affected during the period of construction. NO NO No IR impact envisaged.

20 7 S.No Name Of Components Permanent Impact on Land Acquisition and Resettlement 11 Construction of CC road from Puliya Nainwa Road to Jawahar Colony Tiraha via P.H.E.D office.-544 mtr. 12 Construction of CC road from Gate no-1 to Gate no-6 backline along community centre mtr. 13 Construction of CC road Rajat Colony branch road to Gate no-2,5,6,7, mtr. 14 Construction of CC road at Nav Jeevan Colony mtr. 15 Construction of CC road Nainwa Road to Sanjay Nagar Basti via Glaxy Model School mtr. 16 Construction of CC road from Old Mathura Road to Housing Board Colony via Vinus Public School.-284 mtr. 17 Construction of CC link road to Nianwa Road to Inderprastha Colony.-156 mtr.and additional 600 mtr. 18 Construction of CC Road Kagzi Dewra at Brahmmo Ki Hatai mtr. 19 Construction of CC Road near Girls.Sr.Secondary School,Vikash Nagar mtr. 20 Construction of CC Road Jail Head Works (Nursury Road).-370 mtr. 21 Protection wall & Widening of Road-Mukti Dham Temporary Impact Remarks NO NO No IR impact envisaged. NO NO No work proposed due to non-clearance of Forest Department NO NO No work proposed due to non-clearance of ForestDepartment NO NO No work proposed due to non-clearance of Forest Department NO NO No work proposed due to non-clearance of Forest Department NO NO No IR impact envisaged. NO NO No IR impact envisaged. NO NO No work proposed due to non-clearance of Forest Department NO NO No IR impact envisaged. NO NO No work proposed due to non-clearance of Forest Department NO Yes Impact reported on 2 numbers of CPRs.

21 8 III. IMPACT ON COMMON PROPERTY RESOURCES (CPR) 9. There are two CPRs reported in Mukti Dham road, which are close to the proximity of the project site (near Mukti Dham) will be affected during project execution. One is the temporary ramp, where dead body is kept before interning in to the Mukti Dham, and second one is shelter (permanent). Decision was made by the IPIU for up gradation of first one and permanent shelter will be demolished and reconstructed in the available land of Mukti Dham road. Contractor engaged in the works will rebuild the CPR. Budget provision has been made in the RP for reconstruction of the shelter. Budget has been made after taking measurement of structure and rate has been taken from Schedule of Rates (SoR). Detailed budget costs are provided in Table 6a IV. SOCIO-ECONOMIC INFORMATION/PROFILE 10. A census and socio-economic survey was carried out in the month of December 2010 and October, 2014 all along the subproject area covering each sub components. This was conducted with the help of a predesigned tool. The census survey covered the assessment of detailed impacts and gathered information related to the socio-economic profile of the affected households/persons. Out of the 61 APs, 26 APs come under vulnerable category. These vulnerable APs are further categorized: 3 belong to Women Headed Household, 21 from BPL Category (including 8 from SC) and 1 from Scheduled Tribe (ST) and 1 from SC. However only one indigenous people is impacted but it is confirmed that there will be no impact on Indigenous People. The average household size amongst the surveyed affected households is 5.5. Petty Business is the main source of income of these APs. The average household income of these APs is Rs.5090 per month. Shifting allowances (one time) will be provided to 56 APs including 26 Vulnerable APs. Shifting assistance is not considered for 5 numbers of APs as they are running their shops in the pucca structure and shifting will not require for them. A summary of resettlement impact and the socio-economic details of the APs are given in Table 4 and the detailed socioeconomic profile including the list of APs are given in Annexure 1&2. During consultation two APs (S.No-2 &3) of Annexure 1 informed and provided their proof as BPL Card (see Annexure15.) Table 4: Summary of IR Impacts and Socio-Economic Details of APs Impact Quantity Permanent land aacquisition 0 Temporary land aacquisition Affected Business Activities (Temporary) 0 61 Titled APs 5 Non-titled APs Women -headed household / WHH IP/ST-headed AH 01 BPLPersons/ AH/SC Physically Disabled AH 22 0 Total Vulnerable Households 1 26 Affected trees/crops 0 Affected common property resources 2 Average family size 5.5 Average hhousehold income (per month) Rs 5090 Source: census and Socio-Economic Survey, December 2010& Oct, Vulnerable households consist of households belonging to Scheduled tribe, Women headed, below poverty line and physically disabled

22 9 V. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION 11. Following the model developed for the multitranche financing facility (MFF), a stakeholder consultation workshop was conducted initially (in ), see Annexure 4a and 4b, which provided an overview of the program and subprojects to be undertaken in Bundi and discussed the Government and Asian Development Bank (ADB s) resettlement policies and potential resettlement impacts of the subprojects in Bundi. Representatives of the department (Nagar Nigam, PWD, Forest Dept, Irrigation, Electricity, NGO, NCC etc.) were present during meeting and around 60 in number. During the workshop, Hindi versions of the Resettlement Framework (RF) was also provided to stakeholders to understood the objectives, policy principles and procedures for any land acquisition, compensation and other assistance measures for any affected person. Consultations were held with Affected Persons (49 in number) on at various places in the subproject area such as (i) Circuit House area (ii) Near Lanka Gate ( (iii) Dhan Mandi (iv) Dayanad Colony (v) Nainwa Road (vi) Near S.P office (vii) Near Dwarika Hotel (viii) Near Raniji Ki Bawari. During consultations, key issues raised were: (i) participants expressed satisfaction that there was a subproject taking care of their needs which they have waited for years; (ii) they are not hesitant to move or shift if necessary to accommodate the work; (iii) they are willing to provide labor for the subproject; and (iv) they raised that it is important to repair and widening of roads for free traffic movement. Consultation with newly affected persons (12 in number) was done on 28th Oct, 2014 and will continue throughout the project implementation. Most of the APs attended the consultation personally. Apart from this a meeting was also organized with Nagar Parishad, knowledgeable persons and local inhabitants etc. Consultation records are provided in Annexure 3 & The RP was prepared in consultation with stakeholders. Meetings and individual interviews were held involving stakeholders, particularly with APs on dated Public consultation with primary and secondary stakeholders has been conducted to understand the local issues and public views regarding the possible impact of the subproject. Group Discussion were conducted by RUIDP after advertising in local news papers dt (attached in annexure 13). The issues like awareness about the subproject and extent of the project impact and development components, benefits of project for the economic and social upliftment of community at large, labour availability in the project area or requirement of outside labour, local disturbances due to project construction work, requirement at all of any tree felling etc. at project sites, water logging and drainage problem if any, drinking water problem, existence of forest and any other sensitive area nearby the project site etc. During subproject preparation, consultations were held with the official representatives of the line agencies, apart from the local communities in the project area. 13. Information dissemination and disclosure have been a continuous process since the beginning of the program. An English and Hindi version of the RF has been placed in the office of Urban Local Body (ULB), Investment Program Management Unit (IPMU) office, Investment Program Implementation Unit (IPIU) office and in ADB s website. The revised Resettlement Plan will also be disclosed in ADB s website as well as RUIDP website. The information will also be made available at a convenient place especially in all the relevant offices which will be accessible to the APs. 14. Project information will be continually disseminated through disclosure of resettlement planning documents. The documents will contain information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language (Hindi) and the same will be distributed to APs. The Social Development Specialist (SDS) through its IPIU will keep the APs informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. Additionally, the NGO engaged to implement Community Awareness and Participation Program (CAPP) will continue consultations, information dissemination, and disclosure. The

23 10 NGO has been engaged and it has been working for community consultation and awareness program. A summary of NGO s activities is provided in Annexure 7. The consultation process will be carried out in the entire project cycle. VI. GRIEVANCE REDRESS MECHANISMS 15. Grievances of APs will first be brought to the attention of the implementing NGO or Social Development Specialist (SDS). Grievances not redressed by the NGO or SDS will be brought to the City Level Committees (CLC) set up to monitor project implementation in each town. The CLC, acting as a grievance redress committee (GRC) is chaired by the District Collector with representatives from the ULB, state government agencies, IPIU, communitybased organizations (CBOs) and NGOs. As GRC, the CLC will meet every month. The GRC will determine the merit of each grievance, and resolve grievances within a month of receiving the complaint, failing which the grievance will be addressed by the inter-ministerial Empowered Committee. The Committee will be chaired by the Minister of Urban Development and Local Self Government Department (LSGD), and members will include Ministers, Directors and/or representatives of other relevant Government Ministries and Departments. Grievance not redressed by the GRC will be referred to the IPMU for action failing which grievances will be referred by APs to the appropriate courts of law. The IPIU will keep records of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, and final outcome. The grievance redress process is shown in Figure 3. All costs involved in resolving the complaints will be borne by the IPMU. The GRCs will continue to function throughout the project duration. APs Figure 3: Grievance Redress Process GRC/CLC NGO/SDS/IPIU IPMU CLC = City Level Committee, GRC = Grievance Redress Committee, IPIU=Investment Program Implemetaion Unit, IPMU = Investment Progarm Management Unit, NGO = nongovernmental organization, SDS = Social Development Specialist. VII. POLICY AND LEGAL FRAMEWORK 16. The policy framework and entitlements for the program as well as for this subproject are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984), and the National Resettlement and Rehabilitation Policy, 2007 (NRRP); ADB s Policy on Involuntary Resettlement, 1995; and the agreed Resettlement Framework (RF). Based on these, the core involuntary resettlement principles applicable are: (i) land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring all viable alternative subproject designs; (ii) where unavoidable, time-bound Resettlement Plans will be prepared and APs will be assisted in improving or at least regaining their pre-program standard of living; (iii) consultation with APs on compensation, disclosure of resettlement

24 9. 11 information to APs, and participation of affected persons in planning and implementing subprojects will be ensured; (iv) vulnerable groups will be provided special assistance; (v) payment of compensation to APs including non-titled persons (e.g., informal dwellers/squatters, and encroachers) for acquired assets at replacement rates; (vi) payment of compensation and resettlement assistance prior to the contractor taking physical acquisition of the land and prior to the commencement of any construction activities; (vii) provision of income restoration and rehabilitation; and (viii) establishment of appropriate grievance redress mechanisms. A detailed policy framework including the comparison of national laws and policies with ADB SPS is given in Annexure 8. VIII. ENTITLEMENTS 17. All APs who are identified in the subproject areas on the cut-off date will be entitled to compensation for their affected assets, and rehabilitation measures (as outlined in the entitlement matrix below) sufficient to assist them to improve or at least maintain their preproject living standards, income-earning capacity and production levels. Compensation eligibility is limited by a cut-off date as set for this project on the day of the completion of the census survey which is 10 December 2010 and in this case. APs who settle in the affected areas after the cut-off date will not be eligible for compensation and assistance. They however will be given sufficient advance notice (30 days) and will be requested to vacate premises and dismantle affected structures prior to project implementation. The IPIU and the NGO will provide the identity cards (ID) to each of the APs. A sample copy of the ID card is provided in Annexure 9. The entitlement matrix for the subproject based on the above policies is in Table 5.

25 12 Type of Loss 1 Temporary disruption of livelihood 2 Impacts on vulnerable APs 3 Any other loss not identified 4 Loss and temporary impacts on common resources Application Definition of Entitled Person Legal titleholders, non-titled APs Table 5: Entitlement Matrix Compensation Policy 30 days advance notice regarding construction activities, including duration and type of disruption. Contractor s actions to ensure there is no income/access loss consistent with the IEE. 2 Assistance to mobile vendors/hawkers to temporarily shift for continued economic activity. 3 For construction activities involving unavoidable livelihood disruption, compensation for lost income or a transitional allowance for the period of disruption whichever is greater. All impacts Vulnerable APs Livelihood. Vulnerable households will be given priority in project construction employment. - - nanticipated involuntary impacts will be documented and mitigated based on the principles of the RF Common resources Communities Replacement or restoration of the affected community facilities including public water stand posts, public utility posts, temples, shrines, etc. Implementatio n Issues Identification of alternative temporary sites to continue economic activity. Vulnerable households will be identified during the census. Responsible Agency Valuation Committee will determine income lost. Contractors will perform actions to minimize income/access loss. NGO will verify the extent of impacts through a 100% surveys of APs determine assistance, verify and identify vulnerable households. - NGO will ascertain the nature and extent of such loss. IPMU will finalize the entitlements in line with the RF IPMU Contractor. AP=Affected Person, IEE = initial environmental examination, IPMU = Investment Program Project Management Unit, NGO = nongovernmental organization, RF=Resettlement Framework, and 2 3 This includes: leaving spaces for access between mounds of soil, providing walkways and metal sheets to maintain access across trenches for people and vehicles where required, increased workforces to finish work in areas with impacts on access, timing of works to reduce disruption during business hours, phased construction schedule and working one segment at a time and one side of the road at a time. For example assistance to shift to the other side of the road where there is no construction.

26 13 IX. TEMPORARY RELOCATION OF SMALL BUSINESSES 18. APs will be provided 30 days advance notice to ensure no or minimal disruption in livelihood. If required, they will also be assisted to temporarily shift for continued economic activity. For example they will be assisted to shift to the other side of the road where there is no construction. Ensuring there is no income or access loss during subproject construction is the responsibility of contractors. Consistent with the initial environmental examination, contractors will ensure: leaving spaces for access between mounds of soil, providing walkways and metal sheets to maintain access across trenches for people and vehicles where required, increased workforces to finish work in areas with impacts on access, timing of works to reduce disruption during business hours, phased construction schedule and working one segment at a time and one side of the road at a time. 56 APs will be shifted to a nearby location. During the shifting, they will be provided shifting allowance and livelihood assistance for the period of disruption. X. INCOME RESTORATION AND REHABILITATION 19. Should construction activities result in unavoidable livelihood disruption, compensation for lost income or a transitional allowance for the period of disruption whichever is greater will be provided. Vulnerable APs will be given priority in project construction employment. Compensation and assistance to affected persons must be made prior to possession of land/assets and prior to the award of civil works contracts. Now works has been completed in most of the roads except road no-3 and newly proposed works. R&R assistance have already been disbursed to 23 numbers of APs on dated & (see Annexure 10.). 2 numbers of APs have been migrated from the town and one has expired and there is no one in his family for claiming the amount as confirmed by his neighborhood during consultation (see Annexure 12). Remaining APs are in road number-3, where works has not started and it will take time. As per BOQ these roads are to be constructed after laying of sewer pipeline, (see annexure11) which is still awaited. 20. Under approved RP, an estimated Budget provision for Livelihood assistance for all and shifting assistance for kiosks/vendors for marginal shifting (other side of the road, if required). Mainly RP includes Three types of compensation 1) Livelihood assistance, 2) Shifting assistance, 3) Vulnerability assistance.. A Micro Plan will be prepared to constitute the Replacement Cost on the basis of economic data provided by the APs during survey. These Micro Plans help out to identify the APs which are below minimum wage rate at the time of disbursement to ensure additional compensation to these APs. It also takes care of the time lags, minimum wages, escalation etc. Micro Plan considers the real impact on APs and also ensured that all the APs are compensated for time over run and entire period of disturbance. For loss of structure Budget has been made (without considering the depreciation cost) after taking measurement of structure and rate has been taken from Schedule of Rates (SoR) XI. RESETTLEMENT BUDGET AND FINANCIAL PLAN 21. The resettlement cost estimate for the Bundi Roads subproject includes resettlement assistance, as outlined in the entitlement matrix, support cost for RP implementation and contingency provision amounting to be 5% of the total cost. The state government will be responsible for releasing the funds for resettlement in a timely manner. The total resettlement cost for the subproject is INR The resettlement cost items and estimates are outlined in Table 6.

27 14 Table 6: Resettlement Costs Sl. No Item Unit Quan tity Unit Cost Amount 14 Days Assistance for Relocation & Transfer Shifting assistance Lump sum Loss of Income Livelihood 4 14 Days Additional assistance to Vulnerable groups 5 Sub Total Item Replacement value of CPR (Ref table 6a) 3 Administrative & Implementation costs Implementing NGO Lump Sum 1,00,000 4 Total Contingency 5% Grand Total Note: Based on assessment made during the socio-economic survey. Please Note: Any Structure which gets affected partially or fully due to the project implementation would be restored /re-constructed again by the contractor/in charge of the sub-project. This has been included in the TOR of the contractor and RUIDP will ensure that this gets done. S. No. Table 6(a): Replacement value for structure to be dismantled 1 CPR Item Unit No Length Width Height Total Qty Rate as per SOR Amount (Rs.) 1 Excavation Cum PCC Cum R/R foundation up Cum to plinth 4 R/R in S/S Cum RCC slab Cum Flooring Sqm kg/cum Kg Sub-total Contingency (10%) Grand Total XII. INSTITUTIONAL ARRANGEMENTS 22. The Local Self Government Department (LSGD) is the executing agency responsible for overall technical supervision and execution of all subprojects funded under the Program. The Implementing Agency is the Investment Program Management Unit (IPMU) of the ongoing Rajasthan Urban Infrastructure Development Project (RUIDP), which has been expanded and assigned as the IPMU, to coordinate construction of subprojects and ensure consistency across the towns. The inter-ministerial Empowered Committee provides LSGD with central policy guidance and coordination. The IPMU is assisted by: Investment Program 4 5 The amount is based on the average per day income as derived from the census and socio economic survey. It will be further ensured that APs are at least paid minimum wages as compensation against livelihood loss at the time of disbursement. Additional Assistance to Vulnerable Vendors/Shop Owners for loss of Livelihood: Less than 3 days Rs 500/- per day, Between 4 to 7 days impact-@ Rs 400/-per day, Between 8 to 15 days impact-@ Rs 350/-per day, Between 16 to 31 days impact-@ Rs 300/-per day, More than 31 days impact- A lump sum of Rs 10000/- which is based on assessment made during the census andsocio-economic survey.

28 15 Management Consultants (IPMC) who manages the Program and assure technical quality of the design and construction; and Design and Supervision Consultants (DSC), who are designing the infrastructure, managing the tendering of Contractors, and supervising construction. 23. IPIUs have already been established in the project town, Bundi to manage implementation of subprojects in their area. City Level Committee (CLC) will monitor subproject implementation in each town. They will appoint Construction Contractors to build elements of the infrastructure in a particular town (supervised by DSC). Once the infrastructure begins to operate, responsibility will be transferred to the appropriate state or local Government Agency, who will be given training, support and financial assistance through the Program where necessary to enable them to fulfill their responsibilities. They will employ local Operations and Maintenance Contractors (OMC) to maintain and repair the infrastructure as required. 24. Resettlement issues are coordinated by a Social Development Specialist (IPMU SDS) within the IPMU, who ensures that all subprojects comply with involuntary resettlement safeguards. A Resettlement Specialist who is part of the IPMC team assists the SDS. SDS, as part of the DSC, have been appointed to work with each IPIU to update the Resettlement Plan in the detailed design stage, and to prepare Resettlement Plans for new subprojects, where required to comply with the Government and ADB policies. NGO is appointed to assist the implement Resettlement Plans with close coordination with IPIU. Various institutional roles and responsibilities are described in Table 7. Table 7: Institutional Roles and Responsibilities Activities Agency Responsible Subproject Initiation Stage Finalization of sites/alignments for subprojects IPMU Issuance of Public Notice IPMU Meetings at community/household level with affected persons of land/property IPMU/IPIU Formation of Valuation Committees IPMU Resettlement Plan Preparation Stage Conducting Census of all affected persons IPMU/IPIU/NGO Conducting FGDs/meetings/workshops during SIA surveys IPIU/NGO Computation of replacement values of land/properties proposed for acquisition and for VC/IPIU associated assets Categorization of affected persons for finalizing entitlements IPIU/IPMU Formulating compensation and rehabilitation measures IPIU/IPMU Conducting discussions/meetings/workshops with all affected persons and other IPIU/NGO stakeholders Fixing compensation for land/property with titleholders VC/IPMU/IPIU Finalizing entitlements and rehabilitation packages IPIU/IPMU/IPIU Disclosure of final entitlements and rehabilitation packages IPIU/NGO Approval of Resettlement Plan IPMU/ADB Sale Deed execution and payment IPMU Taking possession of land Resettlement Plan Implementation Stage Implementation of proposed rehabilitation measures NGO/SDS/IPIU Consultations with affected persons during rehabilitation activities NGO/SDS/IPIU Grievances redressal NGO/SDS/GRC/CLC Monitoring IPIU/IPMU ADB = Asian Development Bank, FGD = focus group discussions, GRC = Grievance Redress Committee, LSGD= Local Self Government Department, NGO = nongovernmental organization, IPMU = investment program management unit, IPIU = investment program implementation unit, SDS = Social Development Specialist, SIA = social impact assessment, VC = Valuation Committee.

29 16 XIII. IMPLEMENTATION SCHEDULE 25. All the compensation and assistance will be completed prior to the start of the civil work at each specific stretch. Disbursement of compensation, assistance and relocation of APs cannot commence until the RP has been cleared by ADB. All entitlements are to be paid prior to displacement. Written confirmation is required by the IPMU to ADB stating that all compensation has been paid to APs. Only then can construction works begin on sections where compensation has been paid. A tentative implementation schedule is given in Table 8. Activity Table 8: Implementation Schedule Appointment of NGOs Briefing of the CLC on GRC functions Census and socio-economic surveys (issuance of identification cards) Consultations and disclosure Confirmation of government land to be used and transfer from other departments Resettlement Plan updating if required Resettlement Plan review and approval (IPMU and ADB) Issue notice to APs Compensation and resettlement assistance Relocation as required Takeover possession of acquired property Monitoring Handover land to contractors Start of civil works Rehabilitation of temporarily occupied lands Months Immediately after construction XIV. MONITORING AND REPORTING 26. RP implementation will be closely monitored to provide the IPMU with an effective basis for assessing resettlement progress and identifying potential difficulties and problems Monitoring will be undertaken by the IPIU with assistance from the IPMU.The extent of monitoring activities, including their scope and periodicity, will be commensurate with the project s risks and impacts. Monitoring will involve: (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; (ii) socioeconomic monitoring during and after any resettlement impact utilizing baseline information established through the socio-economic survey of APs undertaken during project subpreparation; and (iii) overall monitoring to assess AP s status. The EA is required to implement safeguard measures and relevant safeguard plans, as provided in the legal agreements, and to submit periodic monitoring reports on their implementation performance. ADB will require the EA to: Establish and maintain procedures to monitor the progress of implementation of safeguard plans, Verify the compliance with safeguard measures and their progress toward intended outcomes, Document and disclose monitoring results and identify necessary corrective and preventive actions in the periodic monitoring reports, Follow up on these actions to ensure progress toward the desired outcomes,(v) retain qualified and experienced external expert to verify monitoring information for projects with significant impacts and risks, Submit periodic monitoring reports on safeguard measures as agreed with ADB.

30 27. The IPMU monitoring will include daily planning, implementation, feedback and trouble shooting, individual AP file maintenance, community relationships, dates for consultations, number of appeals placed and progress reports. The IPIU will provide monthly monitoring report to the IPMU and the IPMU will compile the IPIU report and will submit to ADB on a quarterly basis on the intial two years and thereafter would submit monitoring reports bi-annually as per the agreed RF. Executing Agency will appoint the external monitoring agency/expert and the external monitor will monitor sub-projects twice a year and submit reports directly to the EA (IPMU). The EA will submit external monitoring reports on bi annually basis for another two years to ADB for review. Further details are in the RF. 17

31 18 SOCIO-ECONOMIC DETAILS of Aps (Previously Identified) ANNEXURE 1: S.No Location Name of Shop Vulnerability Monthly Type of Structure Occupation/Business Nature of Impact Owner Income 1 Nanakpura Circle, Bundi Road Ganeshlal Saini NA Tea Stall Tea Vendor Temporary 2 Near,Sarkari Godam,Bundi Road 3 Near,Sarkari Godam,Bundi Road 4 Near Gurudwara,Devpura,B undi 5 Near Gokul Palace,Devpura Bundi 6 Near Gokul Palace,Devpura Bundi 7 Near Gokul Palace,Devpura Bundi 8 Near Gokul Palace,Devpura Bundi 9 Near Gokul Palace,Devpura Bundi 10 Near Gokul Palace,Devpura Bundi 11 Near Gokul Palace,Devpura Bundi 12 Near Khamb ki Chatri,Bundi 13 Near Khamb ki Chatri,Bundi 14 Near Khamb ki Chatri,Bundi 15 Near Khamb ki Chatri,Bundi 16 Near Khamb ki Chatri,Bundi 17 Near Khamb ki Chatri,Bundi Sheoji Nath BPL Tea Stall Tea Vendor Temporary Ganeshlal Saini BPL Pan Stall Pan Vendor Temporary Lokesh Jain NA Pan Stall Pan Vendor Temporary Satyanarayan Sen NA Hair Cutting Saloon (Stall) Barber Temporary Banwari Rana BPL(SC) Marriage Band Party Marriage Band Party Temporary Shop Kamlesh Rana BPL(SC) Marriage Band Party Marriage Band Party Shop Temporary Mukesh Rana BPL(SC) Marriage Band Party Marriage Band Party Shop (Stall) Temporary Babulal BPL(SC) Marriage Band Party Marriage BandParty Shop (Stall) Temporary Pappulal Rana BPL(SC) Marriage Band Party Marriage Band Party Shop (Stall) Temporary Babulal Sen NA Hair Cutting Saloon (Stall) Barber Temporary Ramesh Chandra NA Pan Stall Pan Vendor Temporary Modi Rakesh Saini NA Pan Stall Pan Vendor Temporary Raj Kumar NA Pan Stall Pan Vendor Temporary Gochar Lokesh Suman NA Pan Stall Pan Vendor Temporary Shyam Prakash Modi Mahavir Prasad Gochar NA Pan Stall Pan Vendor Temporary NA Pan Stall Pan Vendor Temporary

32 19 S.No Location Name of Shop Owner Vulnerability Monthly Income Type of Structure Occupation/Business Nature of Impact 18 Near Khamb ki Md. Islam NA Readymade garments Readymade garments Temporary Chatri,Bundi Shop (Stall) Trading 19 Near Khamb ki Nur Mohamad NA Readymade garments Readymade garments Chatri,Bundi Shop (Stall) Trading Temporary 20 Near Khamb ki Ratan Lal NA Readymade garments Readymade garments Chatri,Bundi Agrawal Shop (Stall) Trading Temporary 21 Near Khamb ki Hanish Kumar NA Readymade garments Readymade garments Chatri,Bundi Shop (Stall) Trading Temporary 22 Near Khamb ki Mohmad NA Readymade garments Readymade garments Chatri,Bundi Shop (Stall) Trading Temporary 23 Near Lanka Heera Bai Female BlacksmithStall Blacksmith Gate,,Dhan Mandi Headed Temporary Road Household 24 Near Lanka Ram Prasad BPL Blacksmith Stall Blacksmith Gate,,Dhan Mandi Temporary Road 25 Near Lanka Sada Ram BPL Blacksmith Stall Blacksmith Temporary Gate,,Dhan Mandi Road 26 Near Lanka Khana Ram BPL Blacksmith Stall Blacksmith Temporary Gate,,Dhan Mandi Road 27 Near Lanka Ram Lal BPL Blacksmith Stall Blacksmith Temporary Gate,,Dhan Mandi Road 28 Near Lanka Dave Bai Female Blacksmith Stall Blacksmith Temporary Gate,,Dhan Mandi Headed 29 Road Household Near Lanka Ramesh BPL Gate,,Dhan Mandi Blacksmith Stall Blacksmith Temporary Road 30 Near Lanka Shyama BPL Blacksmith Stall Blacksmith Temporary Gate,,Dhan Mandi Road 31 Near Lanka Tola Bai Female Blacksmith Stall Blacksmith Temporary Gate,,Dhan Mandi Headed 32 Road Household Dhan Mandi Road Md.Aslam Nagori BPL Furniture Stall Furniture Vendor Temporary

33 20 S.No Location Name of Shop Owner 33 Dhan Mandi Road Nand Bihari Suman 34 Dhan Mandi Road Chandra Prakash Suman Vulnerability Monthly Type of Structure Occupation/Business Nature of Impact Income BPL Pan Stall Pan Vendor Temporary BPL Tea Stall Tea Vendor Temporary 35 Dhan Mandi Road Jagdish Meena ST Tea Stall Tea Vendor Temporary 36 Dhan Mandi Road Om Prakash BPL Pan Stall Pan Vendor Temporary Saini 37 Dhan Mandi Road Jitendra Singh BPL Blacksmith Stall Blacksmith Temporary 38 Dhan Mandi Road Man Singh NA Music CD Stall Music CD Vendor Temporary 39 Dhan Mandi Road Rakesh Nayak BPL(SC) Pan Stall Pan Vendor Temporary 40 Dhan Mandi Road Lal Bahadur NA Pan Stall Pan Vendor Temporary 41 Dhan Mandi Road Rajesh Ahirwal BPL(SC) Shoe Stall Cobbler Temporary 42 Dhan Mandi Road Satyanarayan NA Pan Stall Pan Vendor Temporary Sharma 43 Dhan Mandi Road Punam Chandra NA Tea Stall Tea Vendor Temporary 44 Dhan Mandi Road Shambhu Raj NA Hair Cutting Saloon (Stall) Barber Temporary Sen 45 Dayanand Colony Mahabir BPL(SC) General Store General items vendor Temporary 46 Dayanand Colony Bansi Saini NA Tea Stall Tea Vendor Temporary 47 Kota Road Ganesh Suman NA Tea Stall Tea Vendor Temporary Chauraha,near Lanka Gate 48 Kota Road Chauraha,near Lanka Gate 49 Kota Road Chauraha, near Lanka Gate Rambharosi Goswami NA Pan Stall Pan Vendor Temporary Mangilal Sen NA Hair Cutting Saloon (Stall) Barber Temporary

34 21 ANNEXURE 2: Socio-Economic Survey Details of APs identified for the additional works of the road from Kota by pass to Panchganv. Sl. No Location/ Name of the Road 1. Near Rotary circle, Bundi Name of AP Md. Ajmuddin 2 -D0- Laturlal Meghwal Cutoff Date Typology of Structure Specificbeing SHOP/ Kiosk/ Mobile Kiosk Kiosk Ownership Title Holder / non-title Holder Non-Tittle holder Non-Tittle holder Type of Busines s Cycle Repairing Tea Shop Social Category Vulnera bility No. of Family Members Daily Income (in Rs.) Impact Temporary / Permanent Rehabilitation Option/Remarks (Lively hood (comp) / Shifting (SA) / Vulnerability (VA) specify which ever is applicable GEN NA Temporary Livelihood impact on compensation & livelihood Shifting assistance provided for them. SC SC do- -do- 3 -D0- Ramchar an Sen Kiosk Non-Tittle holder Hair cutting OBC NA do- -do- 4 Near Sant Nirankari Satsang,Devpura Bundi Hemraj Mali Kiosk Non-Tittle holder Tea Shop OBC NA do- -do- 5 -D0- Tejpal Saini Kiosk Non-Tittle holder Juice Centre OBC NA do- -do- 6 Near Old Petrol Pump,Devpura, Bundi Md.Khalil Khan 7. -D0- Aashutos h Sringi 8 -D0- Md. Jenuddin Kiosk Non-Tittle holder Tyre- Tube Repairing Shop Tittle holder Hardwar e(cemen t) Shop Tittle holder Hardwar e GEN NA do- -do- GEN NA do- Only livelihood assistance provision made for them. Shifting will not require. GEN NA do- -do- 9 -D0- Md.Moie uddin Shop Tittle holder Wielding GEN NA do- -do-

35 22 Sl. No Location/ Name of the Road Name of AP 10 -D0- Giriraj Arora Cutoff Date Typology of Structure Specificbeing SHOP/ Kiosk/ Mobile Ownership Title Holder / non-title Holder Type of Busines s Shop Tittle holder Tent House Social Category Vulnera bility No. of Family Members Daily Income (in Rs.) Impact Temporary / Permanent GEN NA do- -do- Rehabilitation Option/Remarks (Lively hood (comp) / Shifting (SA) / Vulnerability (VA) specify which ever is applicable 11 Near Old Petrol Pump,Devpura, Bundi 12 Near Old Petrol Pump,Devpura, Bundi Radhesh yam Arora Rajesh Kumar Sen Shop Tittle holder Tea Snacks Kiosk Non-Tittle holder Hair cutting GEN NA Temporary impact on livelihood OBC NA Temporary impact on livelihood Only livelihood assistance provision made for them. Shifting will not require. Livelihood compensation & Shifting assistance provided for them.

36 23 Location Near Lanka Gate,,Dhan Mandi Road Date of Consultatio ns SUMMARY DETAILS OF CONSULTATIONS Public Consultation- Social Survey Time of Number of Names of the Consultation participants Participants :30 pm 4 Sada Ram, Ramlal, Dave Bai Ramesh ANNEXURE 3: Photographs Dayanand Colony :30 pm 3 Mahabir Bansi Saini Ram Prasad Dayanand Colony :50 pm 4 Ramji Lal Suresh Suman Ved Prakash Near S.P office pm 2 Ram Chandra Seela Bai

37 24 PUBLIC CONSULTATION Issues discussed Awareness about the subproject and extent of the project impact and development components Benefits of the subproject for the economic and social upliftment of community at large Labour availability in the Project area or requirement of outside labour Possibility of Local disturbances due to Project Construction Work Water logging and drainage problem if any Drinking water problem Other problems, encountered, if any Sr. No. Key Issues/Demands 1 Have you heard about RUSDIP (Rajasthan Urban Sector Development Investment Program. 2 General perception about the project and the awareness about the proposed project. 3 In what way they may be associated with the project. Issues of the Public Consultation- Design phase Perception of community Some participants have heard about RUSDIP because of water supply work is going on in this town. People are aware of the upcoming project.dsc/capp representatives briefly described about this project. Majority of people told that the existing road is very poor and congested and it is inaccessible during rainy season. Employment to local skilled and unskilled labors will be preferred during construction work. 4 Loss of community life like any Market Places No loss of market places and no disturbance to local or community activities to be affected normal activities are expected as all works will be done within available ROW 5 Loss of residential/commercial structures, if No loss is predicted, any due to the project 6 What kind of R&R assistance they would Monetary assistance will be provided for those whose require. income/livelihood will be temporarily disturbed due to construction work. 7 What is the economic status of the local Economic status of the local people is of average/ medium people level, majority belongs to lower middle class. The major findings of the consultations held at various locations are summarized as follows. Most of the people are aware of the subproject and are willing to render the support whenever required. Most of the APs were aware that the commercial activities that they were engaged in along the road are mostly on encroached government land and are considered to be squatters. They are willing to shift from present location but at the same time the people expected that the authorities should be little considerate towards their problem and they seek some assistance to restore their livelihood. The people also suggested a proper compensation package to be granted, for those, whose business will be affected temporarily during construction. People suggested that the adequate safety measures should be provided for uninterruptednormal social life.

38 25 ANNEXURE : 4 SUMMARY OF CONSULTATION WITH ADDITIONAL APS DATED Consultation was made with all the APs regarding proposed work and its impact on their businesses and provision of R& R under this project. They have happy to know that compensation provision is made in case business is interrupted. All APs appreciated this work and suggested that infrastructure development of the town is very much required so that tourist inflow can be increased. As tourist inflow will be increased, business will definitely be improve. DSC and CAPP person also informed about the Grievance Redress System under this project. Consultations were also conducted in Mukti Dham areas and nearby household have appreciated this works.

39 26 ANNEXURE 5 Minutes of Meeting under Chairmanship of Project Director Dated Change of Alignment/Scope (Ref point no. 4)

40 27 Approval letter for Additional works ANNEXURE 6

41 28 ANNEXURE 7: SUMMARY ACTIVITIES ON COMMUNITY AWARENESS AND PARTICIPATION PROGRAMME (CAPP) 1. Appreciating the fact that the long term success of the project dependence on the willingness of local communities to sustain improved services and facilities provided by the project, Community awareness and participation program (CAPP) has been designed as an integral part of RUIDP with objective of fostering greater awareness and involvement of the communities for participation in all aspects of project decision making. The objectives of CAPP are to: Promote participatory community involvement in the project and to contribute to the delivery of sustainable urban service. Cover community awareness, participation, and education with respect to implementation and management of the project facilities, and to educate communities about environmental sanitation and health linkages. Inform the project beneficiaries about implications to the community in terms of benefits and responsibilities, including the need to pay for sustainable urban and civic amenities. Stimulate civic concern about environmental quality and responsibility. Ensure that the communities develop a sense of ownership of the new and rehabilitated infrastructure and services. Ensure community involvement during planning and implementation of all components of the project activities 2. To mobilize, motivate, participation and awareness of community a COMMUNITY ACTION PARTICIPATION PROGRAM (CAPP) is taken under the RUSDIP. M/s Indian Institute of Rural Management, Jaipur has been engaged as CAPP consultant from August, Community mobilization will be activated through various Public Meetings, Campaign and media means. CAPP will be undertaken to make the public aware of the short-term inconveniences and long-term benefits of the project in order to gain full support of the beneficiaries for the Project. CAPP will be helpful to make beneficiaries aware of preventive care to avoid environmental health-related hazards and of their responsibilities to avoid the wastage of water, including issues such as water rates, user charges and property tax reform, etc. for achieving the goals of the Project. In addition, it will provide feedback to the IPMU with a view to adjusting the work program based on the impact of the campaign and concerns raised by the beneficiaries 3. In order to achieve desired goal several awareness campaigns, seminars, orientations, trainings, sewer and water connectivity camps have been organized at different levels on various facets health, hygiene, water and sanitation, solid waste management, sewerage, property connection, road safety and other RUIDP related sector. IEC material is also being brought out on the above issues. The programs are designed to help enhance the understanding of the project and through people s participation ensure sustainability of the assets/services provided. Overview of CAPP Activities Formation of Groups PublicMeeting at the community level Jajam baithaks Individual contact Site visits

42 29 School campaign Street Play, Nukkad Natak and Puppet Shows Observance of Important National / International Day Road Safety Programs Cultural Event Exhibitions Jhanki Display Women Participation and Income Generation Activities Organization Camps IEC Activities o Print Media o Display of Posters o RUIDP Calendar o Preparation of Brochure and Folders o Preparation of Pamphlets o Stickers o Preparation and release of Nav Aakar o Release of News Letter o Release of News and Appeals Electronic Media o Interactive Phone in program through AIR o Display of film on Water Conservation o Film Show for Environment Improvement o Display of Cinema Slides o Documentary Film on RUIDP Pragati Path o Display of Scroll Messages o Display of Banners / Flexes o Press Conference Training Programme and Workshops

43 30 POLICY FRAMEWORK AND ENTITLEMENTS ANNEXURE 8: A. Policy and Legal Framework The policy framework and entitlements for the Program are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984) the National Resettlement and Rehabilitation Policy, 2007 (NRRP); and ADB s Policy on Involuntary Resettlement, The salient features of Government and ADB polices are summarized below. 1. Government Policy a. National Resettlement and Rehabilitation Policy, 2007 The NRRP stipulates the minimum facilities to be ensured for persons displaced due to the acquisition of land for public purposes. The objectives of the Policy are: (i) (ii) (iii) (iv) to minimize displacement and to identify non-displacing or least displacing alternatives; to plan resettlement and rehabilitation of project affected families (PAFs) or project affected households (PAHs), including tribal and vulnerable households; to provide improved standard of living to PAFs or PAHs; and to facilitate a harmonious relationship between the requiring body and PAFs. Though NRRP is applicable for projects where over 400 PAFs in the plains or 200 PAFs in hilly or tribal areas are displaced, the basic principles can be applied to resettling and rehabilitating PAFs regardless of the number affected. NRRP s provisions are intended to mitigate adverse impacts on PAFs. While key principles of NRRP are similar, and for some items go beyond ADB s Policy on Involuntary Resettlement (1995), NRRP excludes linear projects (which acquire only narrow strips of land). Linear impacts and temporary linear impacts (which is the likely impact of the Program) are not covered by NRRP. Further, there is no law on resettlement in the country. The law relating to the acquisition of privately owned immoveable property is the Land Acquisition Act of 1894 (LAA, amended 1984) discussed in the following section. b. Land Acquisition Act, 1894 The LAA provides a framework for facilitating land acquisition in India. LAA enables the State Government to acquire private land for public purposes. LAA ensures that no person is deprived of land except under LAA and entitles APs to a hearing before acquisition. The main elements of LAA are: (i) (ii) (iii) Land identified for the purpose of a project is placed under Section 4 of the LAA. This constitutes notification. Objections must be made within 50 days to the District Collector (DC, the highest administrative officer of the concerned District). The land is then placed under Section 6 of the LAA. This is a declaration that the Government intends to acquire the land. The DC is directed to take steps for the acquisition, and the land is placed under Section 9. Interested parties are then invited to state their interest in the land and the price. Under Section 11, the DC will make an award within one year of the date of publication of the declarations. Otherwise, the acquisition proceedings shall lapse. In case of disagreement on the price awarded, within 6 weeks of the award, the parties (under Section 18) can request the DC to refer the matter to the Courts to make a final ruling on the amount of compensation.

44 31 (iv) (v) (vi) Once the land has been placed under Section 4, no further sale or transfer is allowed. Compensation for land and improvements (such as houses, wells, trees, etc.) is paid in cash by the project authorities to the State Government, which in turn compensates landowners. The price to be paid for the acquisition of agricultural land is based on sale prices recorded in the District Registrar's office averaged over the three years preceding notification under Section 4. The compensation is paid after the area is acquired, with actual payment by the State taking about two or three years. An additional 30 percent is added to the award as well as an escalation of 12 percent per year from the date of notification to the final placement under Section 9. For delayed payments, after placement under Section 9, an additional 9 percent per annum is paid for the first year and 15 percent for subsequent years. 2. ADB s Policy on Involuntary Resettlement, 1995 The three important elements of ADB s involuntary resettlement policy are (i) compensation to replace lost assets, livelihood, and income; (ii) assistance for relocation, including provision of relocation sites with appropriate facilities and services; and (iii) assistance for rehabilitation to achieve at least the same level of well-being with the project as without it. For any ADB operation requiring involuntary resettlement, resettlement planning is an integral part of project design, to be dealt with from the earliest stages of the project cycle, taking into account the following basic principles: (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) Involuntary resettlement will be avoided whenever feasible. Where population displacement is unavoidable, it should be minimized. All lost assets acquired or affected will be compensated. Compensation is based on the principle of replacement cost. Each involuntary resettlement is conceived and executed as part of a development project or program. APs need to be provided with sufficient resources to re-establish their livelihoods and homes with time-bound action in co-ordination with civil works. APs are to be fully informed and closely consulted. APs are to be assisted to integrate economically and socially into host communities so that adverse impacts on the host communities are minimized and social harmony is promoted. The absence of a formal title to land is not a bar to ADB policy entitlements. APs are to be identified and recorded as early as possible to establish their eligibility, through a census which serves as a cut-off date, and prevents subsequent influx of encroachers. Particular attention will be paid to vulnerable groups including those with out legal title to land or other assets; households headed by women; the elderly or disabled; and indigenous groups. Assistance must be provided to help them improve their socio-economic status. The full resettlement costs will be included in the presentation of project costs and benefits. C. Comparison of Borrower s Policy with the RF The NRRP represents a significant milestone in the development of a systematic approach to address resettlement issues in India. LAA, 1894 however gives directives for acquisition of land in public interest and provides benefits only to titleholders. Table 1

45 32 presents a comparison of Government polices (LAA and NRRP) in comparison with the RF which is consistent with ADB s involuntary resettlement policy. Table 1: Comparison Between the Borrower s and ADB s Involuntary Resettlement Policy Policy Principles LAA NRRP Remarks 1. Involuntary resettlement should be avoided where feasible. 2. Where population displacement is unavoidable, it should be minimized by exploring viable project options. 3. If individuals or a community must lose their land, means of livelihood, social support systems, or way of life in order that a project might proceed, they should be compensated and assisted so that their economic and social future will generally be at least as favorable with the project as without it. Appropriate land, housing, infrastructure, and other compensation, comparable to the without project situation, should be provided to the adversely affected population, including indigenous groups, ethnic minorities, and pastoralists who may have usufruct or customary rights to the land or other resources taken for the project. 4. Any involuntary resettlement should, as far as possible, be conceived and executed as a part of a development project or program and resettlement plans should be prepared with appropriate timebound actions and budgets. Resettlers should be provided sufficient resources and opportunities to reestablish their homes and livelihoods as LAA is applicable wherever private land is to be acquired by Government for public purpose. LAA is applicable wherever private land is to be acquired by Government for public purpose. According to the ADB s IR policy full RP is required when 200 or more people will experience major impacts. A Short RP is required when resettlement is insignificant when less than 200 people will experience major impacts. According to the NRRP, RP should be prepared when it involves resettlement of more than 500 families (roughly about 2,000 persons) in plain areas and 200 families (roughly about 1,000 people) in hilly areas, Desert Development Programme (DDP) blocks, areas mentioned in Schedule V and Schedule VI of the Constitution of India. According to the ADB s IR policy full RP is required when 200 or more people will experience major impacts. A Short RP is required when resettlement is insignificant when less than 200 people will experience major impacts. According to the NRRP, RP should be prepared when it involves resettlement of more Compliance of proposed RF with ADB s IR Policy This is addressed in the RF. The locations for project components have been identified in such a manner that IR is avoided to the extent possible. These IR impacts shall be further minimized during detailed designs. This is addressed in the RF. The locations for project components have been identified in such a manner that IR is avoided to the extent possible. These IR impacts shall be further minimized during detailed designs. The RF addresses the IR impacts. The entitlements to the APs are outlined in the Entitlement Matrix. The RF addresses the IR impacts. The entitlements to the APs are outlined in the Entitlement Matrix.

46 33 Policy Principles LAA NRRP Remarks soon as possible. 5. The affected people should be fully informed and closely consulted on resettlement and compensation options. Where adversely affected people are particularly vulnerable, resettlement and compensation decisions should be preceded by a social preparation phase to build up the capacity of the vulnerable people to deal with the issues. 6. Appropriate patterns of social organization should be promoted, and existing social and cultural institutions of resettlers and their hosts should be supported and used to the greatest extent possible. Resettlers should be integrated economically and socially into host communities so that adverse impacts on host communities are minimized. One of the effective ways of achieving this integration may be by extending development benefits to host communities. 7. The absence of formal legal title to land some affected groups should not be a bar to compensation. Affected persons entitled to compensation and rehabilitation should be identified and recorded as early as possible, preferably at the project identification stage, in order to prevent an influx of illegal encroachers, squatters, and other nonresidents who wish to take advantage of such benefits. Particular attention should be paid to the needs of the poorest affected persons including those without legal title to assets,, than 400 families (roughly about 2,500 persons) in plain areas and 250 families (roughly about 1,250 people) in hilly areas, Desert Development Programme (DDP) blocks, areas mentioned in Schedule V and Schedule VI of the Constitution of India. LAA does not provide for resettlement. However, it specifies the time limit for acquisition, though the project / program for which it is conceived need not necessarily be time-bound. LAA recognizes only titleholders, who are to be notified prior to acquisition. - LAA provides for every affected person to receive a notification prior to acquisition and for a hearing in case of any objection. Acquisition under the Act is permitted within one year from the date of declaration of intent to acquire, failing which, the process has to start again. LAA does not regard nontitleholders as APs. The Rajasthan Urban Housing and Habitat Policy, 2006 aims to provide tenurial rights to urban slum dwellers with Compliance of proposed RF with ADB s IR Policy A time-bound action plan and implementation schedule for the IR activities is outlined. The key RP activities are identified and the responsibilities for the same outlined. Consultations have been carried out with APs. This will be further consolidated by the RP implementing NGO. The plan for information disclosure in the project, including the RF. This is addressed in the Entitlement Matrix. The process for verification of impacts and establishing the eligibility of the APs is outlined in the RF.

47 34 Policy Principles LAA NRRP Remarks female-headed households and other vulnerable groups, such as indigenous peoples, and appropriate assistance provided to help them improve their status. 8. The full costs of resettlement and compensation, including the costs of social preparation and livelihood programs as well as the incremental benefits over the without project situation, should be included in the presentation of Project costs and benefits. 9. To better assure timely availability of required resources and to ensure compliance with involuntary resettlement procedures during implementation, eligible cots of resettlement and compensation may be considered for inclusion in Bank loan financing for the project, if requested. special emphasis on persons belonging to scheduled castes, scheduled tribes, weaker sections, physically handicapped and widows. This is consistent with recognizing those without legal titles and the vulnerable. According to the ADB s IR policy full RP is required when 200 or more people will experience major impacts. A Short RP is required when resettlement is insignificant when less than 200 people will experience major impacts. According to the NRRP, RP should be prepared when it involves resettlement of more than 500 families (roughly about 2,500 persons) in plain areas and 250 families (roughly about 1,250 people) in hilly areas, Desert Development Programme (DDP) blocks, areas mentioned in Schedule V and Schedule VI of the Constitution of India. The NRRP s concept of replacement cost is not clearly defined. However, the NRRP does consider various compensation packages to substitute the losses of APs. - Compliance of proposed RF with ADB s IR Policy The RF addresses the IR impacts. The entitlements to the APs are outlined in the Matrix. Entitlement This is addressed in the Entitlement Matrix The impacts have been assessed and RP costs according to the entitlement matrix have been worked out. These costs are included in the Project Costs..

48 35 COPY OF IDENTITY CARDS ANNEXURE 9:

49 36 ANNEXURE 10 Details of compensation disbursed to 23 numbers of APs on dated &

50 37

51 38 ANNEXURE: 11 Reference of BOQ where it was mentioned that road no-3 works will be start after laying of sewer pipeline

52 39 IDENTIFICATION OF MISSING APS ANNEXURE 12 Consultation with nearby household for the availability of Mr.Ramprasad (S.No-24 - Annexure 1) Translation Consultation was made with local public on dated 8 th July 14 regarding the Availability of Mr.Ramkumar,so that compensation can be disbursed to him. The local public informed that he has shifted to Kota along with his family 2 years back and no one in his family is in Bundi.

53 40 Consultation with nearby household for the availability of Md.Islam(S.No-18) of Annexure 1 Translation Consultation was made with local public on dated 18 th Jun 14 regarding the Availability of Md.Islam,so that details can be collected from them for disbursement of compensation. The local public informed that he has shifted to Kota along with his family 2 years back and no one in his family is in Bundi.

54 41 Consultation with nearby household for the availability of Lal Bahadur (S.No-40) of Annexure 1 Translation Consultation was made with local public on dated 18 th Jun 14 regarding the Availability of Lal Bahadur and his kin,so that details can be collected from them for disbursement of compensation..the local public informed that he expired 1 years back and he was alone.

55 42 ANNEXURE-13 NEWS PAPER CLIP Highlights of the news New Cutting Published in Bundi Bhasker New Paper (17 th Jan 2011) Position of present roads which are in bad conditions and require overall improvement RUIDP taking up work of up gradation of 18 Roads in Bundi City 16 CC roads (350mm) and 2 BT roads may be taken up Work will be executed in 1.5 years Tenders already initiated Available ROW of Road varies from 7mtr to 14 mtr etc.

56 43 LETTER OF FOREST DEPARTMENT ANNEXURE-14 Translation of letter issued by Forest Department To EE, IPIU, Bundi Sub: Regarding road restoration works being executed by project Ref: IPIU letter no. dated Please find enclose list of roads out of century area, there is no objection for up gradation of these roads. Divisional Forest Officer Bundi

57 44 List of 13 roads for which NoC issued by Divisional Forest Office

58 45 ANNEXURE 15 COPY OF BPL CARD PROVIDED BY AP (S.NO-2&3) OF ANNEXURE 1 S.No-3(Ganesh Lal Saini) S.NO-2 (SHEOJI NATH)

59 46 SITE PHOTOGRAPHS View of Proposed road from Rotary circle to Panchganv ANNEXURE 16 View of proposed works near Mukti Dham

60 PHOTOS OF AFFECTED CPR NEAR MUKTI DHAM 47

IND: Rajasthan Urban Sector Development Investment Program

IND: Rajasthan Urban Sector Development Investment Program Social Monitoring Report Project Number: 40031 September 2009 IND: Rajasthan Urban Sector Development Investment Program Prepared by Local Self Government Department This report has been submitted to ADB

More information

Resettlement Plan. IND: Rajasthan Urban Sector Development Investment Program - Rajsamand Urban Transport and Roads Subproject

Resettlement Plan. IND: Rajasthan Urban Sector Development Investment Program - Rajsamand Urban Transport and Roads Subproject Resettlement Plan Document Stage: Draft for Consultation Project Number: 40031 Revised: January 2014 Package No. RUSDIP/TR-3/ RSM/ ST -01 This SRP has been redrafted for inclusion of three numbers of additional

More information

India: Rajasthan Urban Sector Development Investment Program Barmer Urban Transport and Roads Subproject

India: Rajasthan Urban Sector Development Investment Program Barmer Urban Transport and Roads Subproject Resettlement Plan Document Stage: Draft for Consultation Project Number: 40031 April 2012 India: Rajasthan Urban Sector Development Investment Program Barmer Urban Transport and Roads Subproject Prepared

More information

India: Rajasthan Urban Sector Development Investment Program Chittorgarh Heritage Subproject

India: Rajasthan Urban Sector Development Investment Program Chittorgarh Heritage Subproject Resettlement Plan Document Stage: Draft for Consultation Project Number: 40031 October 2010 India: Rajasthan Urban Sector Development Investment Program Chittorgarh Heritage Subproject Prepared by Local

More information

IND: Rajasthan Urban Sector Development Investment Program

IND: Rajasthan Urban Sector Development Investment Program Social Monitoring Report Project Number: 40031 December 2009 IND: Rajasthan Urban Sector Development Investment Program Prepared by Local Self Government Department This report has been submitted to ADB

More information

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

IND: Railway Sector Investment Program

IND: Railway Sector Investment Program Resettlement Framework Document Stage: Final March 2011 IND: Railway Sector Investment Program Prepared by Ministry of Railways for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 16 March 2011)

More information

Resettlement Plan. IND: Rajasthan Urban Sector Development Program (RUSDP) Sri Ganganagar Water Supply and Sewerage Works

Resettlement Plan. IND: Rajasthan Urban Sector Development Program (RUSDP) Sri Ganganagar Water Supply and Sewerage Works Resettlement Plan Document stage: Draft for consultation Project Number: 42267 September 2014 IND: Rajasthan Urban Sector Development Program (RUSDP) Sri Ganganagar Water Supply and Sewerage Works This

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan February 2012 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Rehabilitation and Channelization of Storm Water Drains at Channi Himmat in Jammu City Prepared

More information

Resettlement Planning Document

Resettlement Planning Document Resettlement Planning Document Project Number: 40031-033 April 2015 IND: Rajasthan Urban Sector Development Investment Program - Tranche 2 Submitted by Rajasthan Urban Infrastructure Development Project,

More information

India: Jammu & Kashmir Urban Sector Development Project

India: Jammu & Kashmir Urban Sector Development Project Resettlement Planning Document Full Resettlement Plan- Improvements to B.C Road from Shakuntala Crossing to Children s Hospital Including pedestrian subway Document Stage: Final Project Number: 41116 October

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

Resettlement Plan. IND: Rajasthan Urban Sector Development Program (RUSDP) Pali Water Supply and Sewerage Works

Resettlement Plan. IND: Rajasthan Urban Sector Development Program (RUSDP) Pali Water Supply and Sewerage Works Resettlement Plan Document stage: Draft for consultation Project Number: 42267 September 2014 IND: Rajasthan Urban Sector Development Program (RUSDP) Pali Water Supply and Sewerage Works This resettlement

More information

IND: Rajasthan Urban Sector Development Investment Program

IND: Rajasthan Urban Sector Development Investment Program Social Monitoring Report Project Number: 40031 March 2010 IND: Rajasthan Urban Sector Development Investment Program Prepared by Local Self Government Department This report has been submitted to ADB by

More information

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP)

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) Resettlement Planning Document Resettlement Framework Document Stage: Draft for Consultation Project Number: 42486 June 2016 India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) The resettlement

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

India: Uttarakhand State Road Investment Program

India: Uttarakhand State Road Investment Program Resettlement Planning Document Resettlement Plan for Kirti Nagar New Tehri Road Subproject Document Stage: Final Project Number: 38255 May 2008 India: Uttarakhand State Road Investment Program Prepared

More information

India: Rajasthan Urban Sector Development Investment Program Chittorgarh Water Supply Subproject

India: Rajasthan Urban Sector Development Investment Program Chittorgarh Water Supply Subproject Resettlement Plan Document Stage: Draft for Consultation Project Number: 40031 December 2011 India: Rajasthan Urban Sector Development Investment Program Chittorgarh Water Supply Subproject Prepared by

More information

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT Resettlement and Rehabilitation (R&R) Entitlement Framework RP297 Under

More information

MON: Urban Development Sector Project Bulgan Subproject

MON: Urban Development Sector Project Bulgan Subproject Resettlement Completion Report Annual Report 24 December 2012 MON: Urban Development Sector Project Bulgan Subproject Prepared by Purevsuren Dorjnamjil, Resettlement Specialist, Project Management Unit

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

Land Acquisition and Resettlement Due Diligence Report

Land Acquisition and Resettlement Due Diligence Report Land Acquisition and Resettlement Due Diligence Report Document stage: Draft for consultation Project Number: 48434 Loan and/or Grant Number(s): {LXXXX; GXXXX; TAXXXX} March 2016 India: Visakhapatnam-Chennai

More information

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Resettlement Implementation Plan Project Number: 37381-013 September 2012 Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Prepared by SMEC Consultants for Dry Zone Urban

More information

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project Internal Monitoring Report 37231-023 March 2016 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein do not

More information

IND: Mumbai Metro Rail Systems Project

IND: Mumbai Metro Rail Systems Project Social Due Diligence Report October 2018 IND: Mumbai Metro Rail Systems Project Prepared by Mumbai Metropolitan Region Development Authority, Government of India for the Asian Development Bank. ABBREVIATION

More information

Resettlement Plan. October Prepared by the Government of Jammu and Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu and Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan October 2013 IND: Jammu and Kashmir Urban Sector Development Investment Program (JKUSDIP) - Construction of Mechanized Automated Multi Level Parking Facility at Super Bazaar, Jammu (Tranche

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan October 2013 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Construction of Storm Water Drains in the Adjoining Areas of NH Bypass (Rawalpora Chowk Chanapora

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

IND: Uttarakhand Emergency Assistance Project

IND: Uttarakhand Emergency Assistance Project Resettlement Planning Document Project Number: 47229-001 March 2015 IND: Uttarakhand Emergency Assistance Project Prepared by: Uttarakhand Jal Santhan, Jal Bhawan, Dehradun, Uttarakhand This report has

More information

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89) Resettlement Plan March 2012 IND: Bihar State Highways II Project Siwan-Siswan Subproject (SH-89) Prepared by Bihar State Road Development Corporation, Government of Bihar for the Asian Development Bank.

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan November 2012 IND: Chhattisgarh State Road Sector Project Dhamdha Khairagarh Road Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

IND: Northeastern Region Capital Cities Development Investment Program Aizawl Water Supply and Sewerage Subproject

IND: Northeastern Region Capital Cities Development Investment Program Aizawl Water Supply and Sewerage Subproject Resettlement Plan December 2011 IND: Northeastern Region Capital Cities Development Investment Program Aizawl Water Supply and Sewerage Subproject Prepared by State Investment Program Management and Implementation

More information

BAN: Railway Sector Investment Program

BAN: Railway Sector Investment Program Resettlement Planning Document Resettlement Framework Document Stage: Final Project Number: 32234 June 2006 BAN: Railway Sector Investment Program Prepared by Bangladesh Railway, Dhaka, Bangladesh The

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

India: Infrastructure Development Investment Program for Tourism

India: Infrastructure Development Investment Program for Tourism Infrastructure Development Investment Program for Tourism (RRP IND 40648) Resettlement Framework Document Stage: Draft for Consultation Project Number: P40648 July 2010 India: Infrastructure Development

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector

India: Preparing the Energy Efficiency Enhancement Project in the Assam Power Sector Resettlement Planning Document Short Resettlement Plan for Tranche-2 Components Document Stage: Draft for Consultation Project Number: TA 7096-IND April 2010 India: Preparing the Energy Efficiency Enhancement

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Appendix 13 Resettlement Framework Dec 2011 SRI: Local Government Enhancement Project CURRENCY EQUIVALENTS (as of 27 June 2011) Currency Unit = Sri Lankan Rupee/s (SLR/Rs) Rs1.00 = $0.0091 $1.0 = Rs 109.8700

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

Revised Resettlement Plan Tibar-Gleno Road

Revised Resettlement Plan Tibar-Gleno Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING PROJECT February 2012 Democratic Republic of Timor-Leste REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS

More information

IND: Railway Sector Investment Program Tranche 3

IND: Railway Sector Investment Program Tranche 3 Resettlement Due Diligence Report September 2017 IND: Railway Sector Investment Program Tranche 3 Prepared by the Ministry of Railways for the Republic of India and the Asian Development Bank. CURRENCY

More information

IND: Uttarakhand Emergency Assistance Project

IND: Uttarakhand Emergency Assistance Project Resettlement Planning Document Project Number: 47229-001 July 2016 IND: Uttarakhand Emergency Assistance Project Sub Project : Supplementary Due Diligence Report (social) internal roads of Dehradun district

More information

LUCKNOW METRO RAIL PROJECT

LUCKNOW METRO RAIL PROJECT LUCKNOW METRO RAIL PROJECT RESETTLEMENT POLICY FRAMEWORK (Final) LUCKNOW METRO RAIL CORPORATION LTD. Contents SECTION-1... 1 INTRODUCTION... 1 1.1 INTRODUCTION... 1 1.2 THE PROJECT... 1 Table 1.1: Route

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

TRIBAL DEVELOPMENT PLAN

TRIBAL DEVELOPMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Rehabilitation, Upgradation and Strengthening of Nuapada-Bango Munda Section of NH-217

More information

Resettlement and Indigenous Peoples Plan. IND: North Eastern State Roads Investment Program

Resettlement and Indigenous Peoples Plan. IND: North Eastern State Roads Investment Program Resettlement and Indigenous Peoples Plan February 2013 IND: North Eastern State Roads Investment Program Udaipur Melaghar Subproject (TR02) Prepared by Ministry of Development of North Eastern Region for

More information

India: Infrastructure Development Investment Program for Tourism

India: Infrastructure Development Investment Program for Tourism Infrastructure Development Investment Program for Tourism (RRP IND 40648) Resettlement Framework (Updated) Project Number: P40648 Approved: July 2010 Revised: October 2010 India: Infrastructure Development

More information

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems Technical Assistance Consultant s Report Project Number: 44140 Date: April 2014 TA 7566-REG: Strengthening and Use of Country Safeguard Systems Subproject: Supporting and Strengthening National-Level Capacity

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan August 2012 IND: Chhattisgarh State Road Sector Project Nandghat Gidhoury Road Section Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

MLD - Kulhudhuffushi Harbor Expansion Project

MLD - Kulhudhuffushi Harbor Expansion Project Kulhudhuffushi Harbor Expansion Project (RRP MLD 36111-013) Due Diligence Report on Involuntary Resettlement and Indigenous Peoples March 2016 MLD - Kulhudhuffushi Harbor Expansion Project Prepared by

More information

Resettlement Plan Dili-Tibar-Liquica Road

Resettlement Plan Dili-Tibar-Liquica Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING SECTOR PROJECT November 2011 REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK

More information

BAN: City Region Development Project for Shakhari Bazaar Urban Renewal Subproject

BAN: City Region Development Project for Shakhari Bazaar Urban Renewal Subproject Resettlement Plan Document Stage: Draft for Consultation Project Number: 39298 July 2010 BAN: City Region Development Project for Shakhari Bazaar Urban Renewal Subproject Prepared By: Local Government

More information

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project Resettlement Plan (Draft) November 2013 IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project Prepared by, Government of Madhya Pradesh through MP Transco, DISCOM C, DISCOM-E

More information

IND: Rajasthan State Highway Investment Program

IND: Rajasthan State Highway Investment Program Resettlement Plan April 2016 IND: Rajasthan State Highway Investment Program Package-4 1. Singhana - Buhana - Haryana Border Road (SH-13B) 2. Ajeetgarh - Chala Road (SH-13) 3. Sikar-Ganeri-Jaswantgarh

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Resettlement Planning Document Project Number: 40648-034 March 2016 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Sub Project : Conservation and Adaptive Reuse of Town Hall,

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING Road Development Agency 1 5 6 2 3 4 RESETTLEMENT POLICY FRAMEWORK FINAL REPORT Consultancy Services for the Design and Preparation of Bidding Documents for a Countrywide Roll-out of the Output and Performance

More information

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT DRAFT COMPARATIVE ANALYSIS OF NEPAL s LEGAL FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT Note: The following is based

More information

IND: Uttarakhand State Roads Investment Program (Project 3)

IND: Uttarakhand State Roads Investment Program (Project 3) Resettlement Plan November 2011 IND: Uttarakhand State Roads Investment Program (Project 3) Pauri Bend Magnesite Factory Road Subproject Prepared by Public Works Department, Government of Uttarakhand for

More information

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field

2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas Gas Field Draft Safeguards Monitoring Report Project No. 38164-013 Draft Semi Annual Report December 2015 2622-BAN: Natural Gas Access Improvement Project, Part B: Safety and Supply Efficiency Improvement in Titas

More information

Final Monitoring Report to the Board of Directors. on the. Implementation of Remedial Actions. for the

Final Monitoring Report to the Board of Directors. on the. Implementation of Remedial Actions. for the Final Monitoring Report to the Board of Directors on the Implementation of Remedial Actions for the Integrated Citarum Water Resources Management Investment Program Project 1 in the Republic of Indonesia

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

Indigenous Peoples Development Planning Document. IND: Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program

Indigenous Peoples Development Planning Document. IND: Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Draft for Consultation Project Number: 38412 June 2009 IND: Assam Integrated Flood and Riverbank

More information

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives Page 1 of 9 Involuntary Resettlement 1. Bank 1 experience indicates that involuntary resettlement under development projects, if unmitigated, often gives rise to severe economic, social, and environmental

More information

Rehabilitation & Resettlement (R&R) Policy for Kochi Metro Rail Project March 2015

Rehabilitation & Resettlement (R&R) Policy for Kochi Metro Rail Project March 2015 Rehabilitation & Resettlement (R&R) Policy for Kochi Metro Rail Project March 2015 AARVEE Associates Architects Engineers & Consultants Private Limited 8-2-5, Ravula Residency Srinagar Colony Hyderabad

More information

INDIA: Tsunami Emergency Assistance (Sector) Project

INDIA: Tsunami Emergency Assistance (Sector) Project Resettlement Planning Document Short Resettlement Plan Document Stage: Final Project Number: 39114 March 2007 INDIA: Tsunami Emergency Assistance (Sector) Project Prepared by Public Works Department, Government

More information

Involuntary Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook Draft Working Document

Involuntary Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook Draft Working Document Involuntary Resettlement Safeguards A Planning and Implementation Good Practice Sourcebook Draft Working Document November 2012 This working document was prepared by staff of Asian Development Bank. It

More information

IND: Uttarakhand Emergency Assistance Project

IND: Uttarakhand Emergency Assistance Project Resettlement Planning Document Project Number: 47229-001 May 2016 IND: Uttarakhand Emergency Assistance Project Sub Project : DDR for Roads of Dehradun District Submitted by Uttarakhand Emergency Assistance

More information

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Resettlement Planning Document Project Number: 40648-034 March 2016 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Sub Project : Eco Tourism Development at Ropar and Harike

More information

IND: Second Jharkhand State Road Project

IND: Second Jharkhand State Road Project Resettlement Plan March 2015 IND: Second Jharkhand State Road Project Khunti - Tamar Road Prepared by State Highways Authority of Jharkhand (SHAJ), Government of India for the Asian Development Bank. ADB

More information

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE

More information

Indonesia: Enhanced Water Security Investment Project

Indonesia: Enhanced Water Security Investment Project Initial Poverty and Social Analysis March 2018 Indonesia: Enhanced Water Security Investment Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy

More information

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia)

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Republic of Sakha (Yakutia) of the Russian Federation Innovative Development of Preschool

More information

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007 Involuntary Resettlement - Overview Transport Forum Washington, D.C. March 30, 2007 OP 4.12 - Triggers Trigger: acquisition of land which displaces people physically and / or economically. Policy applies

More information

IND: Infrastructure Development Investment Program for Tourism (IDIPT)- Tranche 2

IND: Infrastructure Development Investment Program for Tourism (IDIPT)- Tranche 2 Social Monitoring Report Project Number: 40648-033 November 2017 Period: July 2016 December 2016 IND: Infrastructure Development Investment Program for Tourism (IDIPT)- Tranche 2 Submitted by Program Management

More information

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF)

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) World Bank-financed Project World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

IND: Second Jharkhand State Road Project

IND: Second Jharkhand State Road Project Resettlement Plan March 2015 IND: Second Jharkhand State Road Project Dumka Hansdiha Road Prepared by State Highways Authority of Jharkhand (SHAJ), Government of India for the Asian Development Bank. ADB

More information

Timor-Leste: Baucau to Viqueque Highway Project

Timor-Leste: Baucau to Viqueque Highway Project Resettlement Plan Project Number: 51115 June 2017 Timor-Leste: Baucau to Viqueque Highway Project Prepared by the Government of Timor-Leste for the Asian Development Bank. Table of Contents CHAPTER 1

More information

The Disaster Management Act, 2005

The Disaster Management Act, 2005 GOVERNMENT OF HIMACHAL PRADESH DEPARTMENT OF REVENUE The Disaster Management Act, 2005 (National Act, Rules and Notifications) Alongwith State DM Rules and Notifications HP STATE DISASTER MANAGEMENT AUTHORITY

More information

IND: Bihar State Highways II Project Additional Financing

IND: Bihar State Highways II Project Additional Financing Resettlement Plan November 2011 IND: Bihar State Highways II Project Additional Financing Roonisaidpur Bhiswa Subproject (SH-87) Prepared by Bihar State Road Development Corporation, Government of Bihar

More information

Involuntary Resettlement Due Diligence Report. IND: Infrastructure Development Investment Program for Tourism Tranche 2

Involuntary Resettlement Due Diligence Report. IND: Infrastructure Development Investment Program for Tourism Tranche 2 Involuntary Resettlement Due Diligence Report Project Number: 40648-033 June 2014 IND: Infrastructure Development Investment Program for Tourism Tranche 2 Submitted by Department of Tourism, Government

More information

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS ENVIRONMENTAL SAFEGUARDS Objectives To ensure the environmental soundness and sustainability of projects and to support the integration

More information

IND: Visakhapatnam to Chennai Industrial Corridor Development Program (VCICDP)

IND: Visakhapatnam to Chennai Industrial Corridor Development Program (VCICDP) Resettlement Framework Document stage: Draft for Consultation Project Number: 48434 March 2016 IND: Visakhapatnam to Chennai Industrial Corridor Development Program (VCICDP) Prepared by the Department

More information

REVIEW AND ASSESSMENT REPORT OF THE SPECIAL PROJECT FACILITATOR ON THE INTEGRATED CITARUM WATER RESOURCES MANAGEMENT INVESTMENT PROGRAM INDONESIA

REVIEW AND ASSESSMENT REPORT OF THE SPECIAL PROJECT FACILITATOR ON THE INTEGRATED CITARUM WATER RESOURCES MANAGEMENT INVESTMENT PROGRAM INDONESIA 1 REVIEW AND ASSESSMENT REPORT OF THE SPECIAL PROJECT FACILITATOR ON THE INTEGRATED CITARUM WATER RESOURCES MANAGEMENT INVESTMENT PROGRAM INDONESIA LOANS 2500/2501(SF) INO (13 Nov 2008) March 2011 2 ABBREVIATIONS

More information

BAN: Secondary Education Sector Investment Program

BAN: Secondary Education Sector Investment Program Secondary Education Sector Investment Program (RRP BAN 44213) Resettlement Framework September 2013 BAN: Secondary Education Sector Investment Program Prepared by Directorate of Secondary and Higher Education

More information

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project Initial Poverty and Social Analysis May 2018 People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project This document is being disclosed to the public in accordance

More information

India. Public Works Department. DETAILED PROJECT REPORT Volume - IX: Resettlement Action Plan. July 2015 GOVERNMENT OF UTTAR PRADESH

India. Public Works Department. DETAILED PROJECT REPORT Volume - IX: Resettlement Action Plan. July 2015 GOVERNMENT OF UTTAR PRADESH Public Disclosure Authorized GOVERNMENT OF UTTAR PRADESH Public Works Department Uttar Pradesh Core Road Network Development Program Part A: Project Preparation DETAILED PROJECT REPORT Volume - IX: Resettlement

More information

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the CENTRAL

More information

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program Indigenous Peoples Planning Framework Document Stage: Draft for Consultation Project Number: 47101 (IND) September 2013 India: Assam Power Sector Investment Program Prepared by Assam Power Generation Corporation

More information

India: Delhi Meerut Regional Rapid Transit System Project

India: Delhi Meerut Regional Rapid Transit System Project Initial Poverty and Social Analysis October 2018 India: Delhi Meerut Regional Rapid Transit System Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project

PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project (RRP PAK 47360-003) Resettlement Plan August 2018 PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement

More information