VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program

Size: px
Start display at page:

Download "VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program"

Transcription

1 Social Monitoring Report Quarterly Report (1 st Quarter 2018) June 2018 VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program Prepared by Management Authority for Urban Railway for the Asian Development Bank Date received by ADB: 12 June 2018

2 NOTE In this report, "$" refers to US dollars. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Some information have been removed as they fall within exceptions to disclosure specified in paragraph 97,(x) of ADB s Public Communications Policy (2011).

3 HO CHI MINH CITY PEOPLE'S COMMITTEE MANAGEMENT AUTHORITY FOR URBAN RAILWAYS HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM METRO LINE2 Project Number: LN 2956 RESETTLEMENT QUARTERLY PROGRESS REPORT QUARTER I May 2018

4 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Than/i Tham Luong Route Resettlement Quarterly Progress Report Updated 1031 Marc/i 2018 HO CHI MINH CITY URBAN MASS RAPID TRANSiT LINE 2 investment PROGRAM BEN TIL4NH THAMLUONG ROUTE Project Number: LN 2956 Prepared by the Management Authority of Urban Railways (MAUR) for the Asian Development Bank (ADB), KfV' and European Investment Bank (EIB) Resettlement Progress Report Quarter IV2O16 P a g e 2

5 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Tham Luong Route TABLE OF CONTENTS I. OVERVIEWS Brief Project Background Land acquisition and resettlement scope Objectives of Internal Monitoring Report Quarter I II. COMPENSARTION, ASSISTANCE AND RESETTLEMENT ACTIVITIES IMPLEMENTED IN QUARTER 1/ Updating number of affected households of the project Updating progress of the Updated Resettlement Plans (URPs) Detailed Measurement Survey (DMS) 1 I 2.4. Arrange the apartments for relocation Announcement of draft compensation unit price and draft compensation plan for affected households Public consultation and information disclosure Complaint and complaint solving Complaints, inquires received and solved Difficulties during implementation 13 III. COMPENSATION, ASSISTANCE AND RESETTLEMENT ACTIVITIES EXPECTED TO BE IMPLEMENTED N QUARTER 11/ Updating the Resettlement Plan of the Project Implementation of compensation, support and resettlement activities of the project Other related activities 16 LIST OF TABLES Table 1 - Project land acquisition scope 4 Table 2 Number of affected households as of 31 March Table 3 - Resettlement Plan Updating activities and agreed time-frame 14 LIST OF FIGURES Figure 1 - Route of Ho Chi Minh City Mass Rapid Transit Line 2 Project 6 Figure 2 The layout of Tham Luong Depot in District No Resettlement Progress Report Quarter 1V2016 P a g e 3

6 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thank Tham Luong Route I. OVERVIEWS 1.1. Brief Project Background The Urban Railway Line 2 (Metro Line 2) is one of eight urban railways in Ho Chi Minh City (HCMC). The Ho Chi Minh City Mass Rapid Transit Line 2 Investment Program (the Metro Line 2 Project or the Project) is one part of the Urban Railway Line 2. The Project involves construction of a depot, ten (10) underground and one (01) elevated stations on the length of 11.3 kilometers (km) of urban dual rail line from Ben Thanh to Tham Luong (including 9.3 km underground, 0.2 km transition and 1.8 km elevated). The Project is implemented in the Districts No.1, No.3, No.10, No.12, and Tan Binh and Tan Phu Districts. 2. In initial plan, the Metro Line 2 Project, Ben Thanh Tham Luong has the total investment cost of 1.37 billions USD in which ADB fund: 540 millions USD, KfW: 313 millions USD, EIB: 195 millions USD and Vietnamese Government: millions USD. However, the Project total investment cost and funding structure are under review and adjustment. 3. The Project has 11 stations including 10 underground stations, 01 elevated station (Tan Binh ) and 2 C&C Sections. According to updated data, the Project land acquisition scope is 249,777.1 m2, of which land acquisition area of households, individuals, organization with compensation an and support: 49,400 m2. Total land acquisition scope of the Project and land acquisition scope of each station are shown in the Table 1 below. Table! - Project land acquisition scope No s - Code District 1 Tao Dan - S2 2 DanChu-S3 Land acquisition scope of the Project Land compensation No. 1 14, , No. 3 1, Total S2 16, , No. 3 13, , No. 10 4, , TotalS3 17, , Hoa Hung S4 No. 3 5, , No. 10 5, , Tota1S4 11, , No. 3 5, , Le Thi Rieng S5 No. 10 8, , Tan Binh To1alS5 14, , Pham Van Hai S6 Tan Binh 11, , TotalS6 11, , Bay Hien S7 Tan Binh 24, , TotalS7 24, , Nguyen Hong Dao S8 Tan Binh 12, , Resettlement Progress Report Quarter 1V2016 Page 4

7 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thank - Tham Luong Route Tota1S8 12, , Tan Binh Ba Queo - S9 Tan Phu 7, Total S9 15, , Tan Binh 28, , Pham Van Bach - SIO - Tan Phu 25, Total Sill 54, , Tan Binh 16, TanBinh-S11 Tan Phu 16, Total Sil 32, Link to Depot No , , Total Link to depot 20, , BT-TD cut-cover section No. 1 11, , Total cut-cover section 11, , II BQ-PVB cut-cover section 6, Total cut-cover section 6, Total 249, , Source: Synthesize from data ofmapping Center and Compensation Board of districts. 4. All underground stations, including the two tunnels of the Project will be constructed under existing city roads, namely Truong Chinh and Cach Mang Thang Tam roads. Except for both ends of the underground stations where escalators will be constructed, the main body of the stations will be built within the existing "planning line" - a demarcated area from both edges of a road which restricts the construction of buildings even on privately-held lands for safety reasons. Each station will be constructed with gate stations and ventilation systems (include fan and ventilation pipes). Most of the land acquisition and resettlement impacts are from these gate stations and ventilation systems. Resettlement Progress Report Quarter 1V2016 P a g e 5

8 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Tham Luong Route \ NUONU Iutj*J IrAN TIIOI NIIATI > QU4N TAN an QU4N UIZ4Pi Tli4AU J BAQURO Figure! - Route of Ho Chi Minh City Mass Rapid Transit Line 2 Project Resettlement Progress Report Quarter IV2O16 P a g e I 6

9 ---S.- HO CIII MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Them Luong Route 5. The Tham Luong Depot is located in District No. 12. In the long term, the Tham Luong Depot may also be required to serve Metro Line 6 and the proposed extension of Metro Line 2 from Thu Thiem to An Suong. Total land acquisition for construction of the Tham Luong Depot is about 25.7 hectares (ha), and will be divided into 2 phases: (i) phase 1: ha for building the executive office and resettlement area households displaced from the depot area; and (ii) phase 2:7.76 ha for construction of infrastructure and the depot's auxiliary facilities. The layout of the Tham Luong Depot is shown in the Figure 2 below. PLAN OP ThAM LUONG DEPOT- OPTION 2 MT EANG HU DEPOT ThAM LAYONG - PHU'GNG AN 2 Figure2 The layout of Tham Luong Depot in District No As planned, after the project completion, there will be a sustainable urban transport system established in the Districts of the Project and provision of public transport with competitive price along the Project. The Project will reduce the increase of private means of transport, improve urban environment, reduce accident and air/noise pollution and create more friendly environment for pedestrians. The Project also support for the effort of minimizing climate change in the city by applying low carbon transportation and encouraging the change from using private means of transport, which is more energy efficient and emits less greenhouse Land acquisition and resettlement scope 7. According to updated data as at 31 March 2018, the Project implementation will affect 608 households 515 individuals and 93 organizations in 06 Districts of HCMC, including: District 1, 3, 10, Tan Binh, Tan Phu and cases will be totally recovered their land and need to be relocated. Remaining households (497) are partially affected on land, houses and structures. Total permanent land acquisition area for the Project implementation is 249,777.1 m2 (excluding Tham Luong Depot area). For more details, please refer to Item 11 and Table 2 in page 8 below. Resettlement Progress Report Quarter 1V2016 P a g e 7

10 HO CIII MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Tham Luong Route 1.3. Objectives of Internal Monitoring Report Quarter I According to requirements of safeguard policy of the project regulated in ADB SPS 2009, quarterly internal monitoring reports on compensation, support and resettlement activities of the Project will be prepared by MAUR and submitted to HCMC PC and Donors (ADB, EIB and KfW). 9. Main objectives of the quarterly internal monitoring report for Quarter include: (i) Review the implementation progress of all issues related to resettlement activities of the Project in Quarter 1/2018. (ii) Activities expected to be implemented in Quarter Resettlement Progress Report Quarter IV2O16 P a g e 8

11 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thañh Tham Luong Route II. COMPENSARTION, ASSISTANCE AND RESETTLEMENT ACTIVITIES IMPLEMENTED IN QUARTER 1/ Updating number of affected households of the project (PAll) 10. According to the figures updated to 31 March 2018, total affected households of the Project is 608 PAHs, of which 515 households and 93 organizations. Among 608 affected households, 111 households are fully affected and have to be relocated; and the remaining (497) households are partially affected on their houses and structures. Details of number of affected households, classification of affected households are described in Table 2 below. Table2 Number of affected households as of 31 March 2018 No Districts s Households Organizations Total of PAils Partially Fully Total Partially Fully Total Partially Fully Total 1 District Tao Dan BT-TD cutcover section Disc/nt Tao Dan - - DanChu Hoa Hung Le Thi Rieng - I Il District Dan Chu Hoa Hung Le Thi Rieng Tan Binh district Pham Van Hai Bay Hien Nguyen Hong Dao , ii Resettlement Progress Report Quarter IV20 16 Page 19

12 HO CHI MIMI CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Thain Luong Route BaQueo Pham Van Bach - Tan Phu District BaQueo Pham Van Bach - Tan Binh I District Link to Depot TOTAL Source: Reports of the Districts updated to 31 March Therefore, total affected households at the end of March 2018 is 608, changed compared at the end of June 2017 because there are some small affected cases not land acquisition. However, number of affected households may continue change when the District PCs approving the detailed compensation plans. The changes of the total affected households (if any) will be updated in the next resettlement progress reports Updating progress of the Updated Resettlement Plans (URPs) 12. According to the plan agreed with ADB Mission in April 2016, the URP of the Project will be updated and submitted one time for all affected districts of the Project in October However, due to some difficulties during implementation, the implementation progress of related activities in some districts was not ensures. Therefore, ADB and MAUR discussed and agreed the adjustment of updating and submitting plan of the Resettlement Plan for the Project to suit with the actual situation. Accordingly, the URPs will be updated and separately submitted for each district right after finalizing the draft detailed compensation plan and announcing to affected households. 13. The draft version of the URPs for Districts No. 3 and Tan Phu were prepared and submitted to the ADB and the City Compensation and Apraisal Board for review on 15 October After review, ADB provided the comments for the draft URPs on 07 November 2016, accordingly, ADB requested the City Compensation and Apraisal Board review and comment the draft URPs before submission. In December 2016, the MAUR explained to the City Compensation and Apraisal Board the relevant contents of Entitlement Matrix, Greavance Redress Mechanism, income restoration measures which mentioned in the draft URPs for Districts No.3 and Tan Phu. In February 2017, the City Compensation and Apraisal Board had comment. Dated 17/02/20 17, MAUR has revised, supplement the contents as required by ADB, the City Compensation and Apraisal Board and HCMC-PC to finalize the URPs for Districts No.3 and Tan Phu and resubmitted to ADB. On 21/4/2017, ADB has comments from URP District 3 and Tan Resettlement Progress Report Quarter IV2O16 P a g e 110

13 HO CIII MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Tham Luong Route Phu. On 31/5/2017, MAUR has revised URP District 3 and resubmitted to ADB. On 12/6/2017, ADB approved URP District Draft version of URPs for Districts No.1, No. 10, No.12 were prepared and submitted to ADB in December On 09/6/2017, MAUR updated and supplemented the relevant contents as comments of ADB, City Compensation and Apraisal Board, HCMC-PC for the URPs for Districts No.1, No. 10, No.12, Tan Phu, Tan Binh and resubmitted to ADB.On 23/6/2017, ADB approved these URPswith condition that MAUR shall finalize these URPs according comments ADB. 15. Then, MAUR had completed contents, re-submitted and on 28th February 2018, ADB had Fax letter to approve URPs of 6 districts. However, HCMC PC has still concerned about performance of AM in URP so that they have not yet considered and approved IJRPs Detailed Measurement Survey (DMS) 16. The DMS includes many different activities and can be divided into 02 main activities groups: (i) investigation, survey, measurement of affected land area, houses and structures; and (ii) legal verification of affected land, houses, structures. As of 31 December 2016, all districts completed the work of DMS Arrange the apartments for relocation 17. In preparing for relocation of the relocating households, District Compensation and Site Clearance Boards havearranged the fund of apartments for reloation. Accordingly, 142 apartments for relocation have been prepared in District 4 including District No. 1, No. 3, No. 10 and Tan Binh with the number of arranged apartments: (i) District No. 1: 09 flats in apartment building 203 Nguyen Trai District No. 1; (ii) District No. 3: 16 flats in SCREC apartment building Ward No. 12 District 3 and 30 flats in apartment building No. 4 Phan Chu Trinh Ward No. 12 Binh Thanh District; (iii) District No. 10: 33 flats in Nguyen Kim apartment building Ward No. 7 District No. 10; and Tan Binh District: 38 flats in Lot A, Tan Tru apartment building Ward No. 15 and 19 flat in Lot J Bau Cat 2 apartment building Ward No. 10 Tan Binh District. 18. Apartment price for relocation will be also defined according to market price. Consultants will appraise the price and propose price for each apartment and DOC will issue letter announcing official selling price. Information on resettlement flat selling price will be noticed to affected households together with Ti price during the announcement of the draft detailed compensation plans by the District Compensation and Site Clearance Boards. 19. As of 31 December 2016, DOC has issued the apartment price for relocation in Districts No.10, No. 1 and No.3. Apartment price for relocation in Tan Binh district has issued in February 2017 by the DOC Announcement of the Ti price and draft detailedcompensation plan to the PAils 20. Up to 31 December 2016, based to land price appraised by the Independent Land Price Apraisal Consultant, DONRE has announced the d proposed compensation price-frame (Ti) in all affected districts. The Ti prices have also been publicly announced by the Resettlement Progress Report Quarter 1V20 16 P a g e 11

14 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Thom Luong Route District Compensation and Site Clearance Boardsduring consultation and listing the draft detailed compensation plans. 21. By the end of February 2017, District PCs will summarize the PAHs' comments on the TI price and propose the final price for compensation (T2) to the HCMC-PC for review and approval. The T2 price will be the legal basis for District PCs issuing the compensation decisions for the PAHs. 22. On October, November 2017, HCMC PC had considered, approved land price adjustment coefficient to calculate compensation, support of the Project in districts: 1, 3, 10, 12, Tan Binh and Tan Phu (T2 price). Currently, PC of districts drafted decision of land acquisition, decision of resettlement plan approval for each affected case. After HCMC PC consider and approve URP, PC of districts will issue the above-mentioned decisions Public consultation and information disclosure 23. Project information Booklets (PIB) has been prepared for providing to affected households during the implementation of compensation, support and resettlement activities. This is a document briefing the policy on entitlement of affected households based on the Resettlement Framework of the Project (2010) and Resettlement Plan (2012) accepted by HCMC and ADB. 24. Main information in PIB include: Brief on the Project: (i) Project's impacts; (ii) Project owner and Implementation agency; (iii) stages and implementation time frame; (iv) Expected Project Total Cost Estimate; (v) Donors' name and investment amount for the Project. Compensation, support and resettlement policy for affected households by the Project: (i) compensation, support and resettlement principle of the Project; (ii) compensation, support policy for affected houses, structures, architectural items; and (iv) other support policies. Grievance Redress Mechanism. - Contact address: provision of name, address, phone number of the agencies related to the Project compensation. 25. During the announcement of draft TI price in affected wards of all affected districts (06), MAUR coordinated with the District Compensation and Site Clearance Boards to provide information and conduct consultation with affected people and agencies/organizations affected in land acquisition, resettlement and issues related to the construction of stations in the Districts. 26. Consultation activities were conducted in Districts No.1, No. 3, No.10, No.12, Tan Binh anh Tan Phu from October 2016 to February 2017 with the participation of the representatives from local government, communist party organizations and households affected by the Project. Main issues consulted with affected households and organization include: (i) affected scope of stations according to DMS result; (ii) legal condition and entitlement of compensation, support and resettlement; (iii) implementation plan and participation of affected people and communication; (iv) Grievance Redress Mechanism; and (v) How were comments and recommendations Resettlement Progress Report Quarter IV2O16 P a g e 12

15 HO CIII MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben T/sanh Tham Luong Route from affected people and community in the first consultation solved by authorities. Pifi was also provided to affected people and posted at offices of residential group and offices of WPCs. 27. During consultation, affected households expressed their concerns on issues related to compensation, support and resettlement policy of the Project. Issues related to impacts to income of business households during construction, compensation unit price, grievance redress mechanism... were also raised by households. Questions from affected households were responded by representatives from District Compensation and Site Clearance Boards and MAUR. Detailed information on consultation will be also updated into the Updated Resettlement Plans of the districts Complaint and complaint solving 28. As mentioned in the previous progress report, the Grievance Redress Mechanism set up in RP 2012 is not consistent with actual condition of the Project. Therefore, a procedure of complaint solving was set up and proposed to be applied for Line 2 Project. The established procedure was based on ADB requirements and Vietnamese legal procedures on complaint solving and the provisions of the HCMC-PC on the settlement of complaints. 29. Summary of the procedures for settlement of complaints which was proposed for the Metro Line 2 Project as followings: The PAHs, who disagrees with any content related to the activities of compensation, assistance and resettlement of the Metro Line 2 project may send their inquiries or complaints to the competent authorities for review and resolve in accordance with the following steps; and the aggrieved affected person will not have to pay any fee for his/her case. 30. MAUR is responsible for recording and documentation of the complaints and grievances related to land acquisition and resettlement and present the progress of grievance redress in the quarterly reports submitting to HCMC-PC and ADB. 31. In January 2017, HCMC-PC has send the official document to the ADB to propose the procedures for settlement of complaints of the Metro Line 2 Proejct as mentioned above and the procedures has been updated in the URPs of the districts Complaints, inquires received and solved 32. According to Vietnamese legal regulation, complaint related to compensation, support and resettlement of the Project will only start when authorities issue administrative decisions such as land acquisition decision and compensation, support and resettlement decisions. Therefore, as of31 March 2018, no complaint related compensation, support and resettlement of the Project was received. 33. During implementation of related activities such as DMS, announcement of draft Ti price, compensation plan drafting... related questions from affected households will be reviewed and solved by People Committee of Wards anddistrict Compensation and Site Clearance Boards Difficulties during implementation 34. In Tan Binh district, due to the large number of affected households and more than 50% of total AHs of the project, the implementation of DMS activities, legal documentation Resettlement Progress Report Quarter 1V2016 P a g e 113

16 HO CHI MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Them Luong Route verification, and drafting of long-term compensation plans. By 3 1/12/2016, the detailed compensation plan has been finalized. Detailed compensation plan was publicly listed and opinions of affected households in Tan Binh were implemented in February Summary of activities related to compensation, support an resettlement of the Project by 31 March 2018 and comparison of milestones agreed in MOU dated December 2016 is shown in Table 3 below. Activity Consultation Activities DMS URP Table3 - Resettlement Plan Updating activities and agreed time-frame Agreed content and implementation time-frame Implementation of additional public consultation after announcing TI price for households' comments. DMS will be completed: - All DMS works have completed by Districts, - Verification of legal ity for use of land, houses and landattached assets for Tan Binh District is expected to be completed in December Draft URP for Tan Binh District is expected to be completed in December ADB Project Division provided comments on the Draft URPs of District 3 and Tan Phu, and MAUR submitted the revised Draft URPs to ADB. ADB requested that the revised URP of District 3 and Tan Phu should be reviewed by HCMC PC (Compensation Appraisal Council). After the HCMC PC comments on and finalizes the revised URPs, ADB will forward these documents to its Safeguard Department for comment. After comments from the Safeguard Department are given to MAUR, HCMC PC will implementation progress as of3l March 2018 MAUR coordinated with the District Compensation and Site Clearance Boards of Districts No. 1, No.3, No. 10, No. 12, Tan Phu and Tan Binh to implement consultation activities from October 2016 to February 2017 combining with the announcement of Ti price. Verification of legal ity for use of land, houses and land-attached assets for Tan Birth District is expected to be completed in February URPs for districts No.3 and Tan Phu have been prepared and submitted to the Compensation Apraisal Council and ADB for review in October and November In February 2017, MAUR submitted the revised URP of District 3 and Tan Phu (including Compensation Appraisal Council reviewed). In April 2017, ADB had comments the revised URP of District 3 and Tan Phu. In May 2017, MAUR submitted URPs for Districts 1,3,10,12, Tan Binh and Tan Phu. In June 2017, ADB approved of URP for District 3. ADB approves URP for districts 1,10,12, Tan Binh and Tan Phu provided that MAUR will complete these URPs in ADB opinion. Then, MAUR had completed contents, resubmitted and on 28th February 2018, ADB had Fax letter to approve URPs of 6 districts. However, HCMC PC has still concerned about 'Source: MOU of the ADB's Mission in December Resettlement Progress Report Quarter 1V2016 Page 14

17 Activity Price T2 Payment of compensation and resettlement for affected households2 HO CIII MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thank Them Luong Route - Agreed content and implementation time-frame1 submit final URPs to ADB and ADB will accept the final URPs. MAUR will revise other Districts' URPs based on the Safeguard Department's comments. Likewise, HCMC PC will submit the final URPs for other Districts to ADB for acceptance. Price T2 is expected to be approved by HCMC PC in February Districts PC will issue the Approval Decision on Detailed Compensation Plan and Compensation work will be implemented from February to June Implementation progress as of 31 Maróh 2018 performance of AM in URP so that they have not yet considered and approved URPs. On October, November 2017, HCMC PC had considered, approved land price adjustment coefficient to calculate compensation, support of the Project in districts: 1, 3, 10, 12, Tan Binh and Tan Phu (Price T2) Payment of compensationand resettlement for affectedhouseholds will be implemented after HCMC PC approval URPs. 2lncome restoration activities can still be continued even when compensation and resettlement activities are completed. Resettlement Progress Report Quarter 1V2016 P a g e 15

18 HO CIII MINH CITY URBAN MASS RAPID TRANSIT LINE 2 INVESTMENT PROGRAM Ben Thanh Tham Luong Route III. COMPENSATION, ASSISTANCE AND RESETTLEMENT ACTIVITIES EXPECTED TO BE IMPLEMENTED IN QUARTER Updating the Resettlement Plan of the Project 35. In June 2017, ADB approved URP. for districts 1,3,10,12, Tan Birth and Tan Phu provided that MAUR will complete these URPs in ADB opinion. 36. Currently, MAUR had completed contents, re-submitted and on 28th February 2018, ADB had Fax letter to approve URPs of 6 districts. 37. Currently, HCMC PC has still concerned performance of AM in URPs so that they have not yet approved URPs. In June 2018, MAUR continuously report HCMC PC relating to AM after ADB responded on concerns of HCMC Appraisal Compensation Committee relating to AM Implementation of compensation, support and resettlement activities of the project 38. Activities of compensation, support and resettlement payment of the Project will be commenced after ADB and HCMC PC agreed and approved URPs of districts Other related activities a. Relocation Muslim Cemetary at 360C CMTT District No. 3: 39. Further to information provided in the Quarterly Report 11/2017. To date, the Muslim Community has had Management Board. The activities related to compensation, assistance and reloction of the Muslim Cemetery will be performed by the new Management Board. Currently, the new Management Board is coordinating with the Compensation Board of District 3 to complete the legal documents prepared for the relocation work. b. Compensation, assistance and relocation for the PAHs at the Tham Luong Depot in District No. 12: 40. For Area ha: Up to 31 March 2018, the compensation, assistance were paid for 90 PAHs in a total of 92 PAHs. The remaining PAl-Is (Ms. Nguyen Thi Mong Thuy HH and Mr. Nguyen Van Truong HH) have complaints on the land using right and these cases are being reviewed by the Court, therefore the amount of compensation, assistance for these HHs has been transferred to the accounts in State Treasury of District No. 12. District 12 Compensation Board continues to work with Ms. Thuy and Truong to soon not hand over the site for the project. 41. For the Area ha: There are 18 affected households due to land acquisition of Area II. To date, there are 12 households received compensation, support and handed over their land for the project. The Compensation and Site Clearance Board of District No. 12 is deploying the preparation the compensation plans for 06 PAHs. Resettlement Progress Report Quarter IV2O16 P a g e 16

VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project

VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project Resettlement Plan July 2012 VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project Prepared by Ho Chi Minh City People s Committee Management Authority Of Urban Railway for the Asian Development

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT DUE DILIGENCE REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity

More information

VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section

VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section Social Due Diligence Report Document Stage: Second Draft Project Number: 40080 May 2013 VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section Prepared by Hanoi Metro Railway Board for

More information

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Yen Vien-Lao Cai Railway Upgrading Project Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project External Monitoring Report on RP Implementation Yen Bai Province Prepared by Railway Projects Management

More information

VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project. EVN HCMC: 220kV Tan Cang Substation

VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project. EVN HCMC: 220kV Tan Cang Substation Resettlement Due Diligence Report Stage of the document: Final Loan number: 3163-VIE October 2016 VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project EVN HCMC: 220kV Tan Cang Substation

More information

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section)

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Safeguards Monitoring Report External Social Safeguards Monitoring Report October 2017 VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Prepared by External Resettlement Monitor

More information

VIE: Ben Luc-Long Thanh Expressway Project

VIE: Ben Luc-Long Thanh Expressway Project Social Monitoring Report 3rd Quarterly Report December 2017 VIE: Ben Luc-Long Thanh Expressway Project Prepared by the Viet Nam Expressway Corporation for the Asian Development Bank. NOTE This social monitoring

More information

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN Project Number: Loan 2225-VIE September 2013 VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE Prepared

More information

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT (Loan No. 5233-VN) SFG2443 V2 RESETTLEMENT PLAN FOR THE ADJUSTMENT

More information

VIE: GMS Ben Luc - Long Thanh Expressway

VIE: GMS Ben Luc - Long Thanh Expressway Social Monitoring Report Inception Report May 2013 VIE: GMS Ben Luc - Long Thanh Expressway Prepared by Thanglong Infrastructure Development for Vietnam Expressway Corporation and the Asian Development

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant 11 th Independent Monitoring Report November 2014 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project

More information

VIE: Central Mekong Delta Region Connectivity Project

VIE: Central Mekong Delta Region Connectivity Project Social Monitoring Report Quarterly Report No. 3 April 2014 VIE: Central Mekong Delta Region Connectivity Project Prepared by Joint Venture: CDM Smith, Inc., WSP Finland Limited & Yooshin Engineering Corporation

More information

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section)

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Safeguards Monitoring Report Quarterly Resettlement Monitoring Report (July September 2018) November 2018 VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Prepared by TPF Getinsa-Eurostudios,

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant Resettlement Monitoring Report Quarterly Report July September 2013 VIE: Mong Duong 1 Thermal Power Plant Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1. Internal

More information

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Yen Vien-Lao Cai Railway Upgrading Project Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project Resettlement Monitoring Report Prepared by Railway Projects Management Unit of Viet Nam Railway for

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT PLAN Project Number: 46391-001 December 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian

More information

Income and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development

Income and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Income and Livelihood Restoration Plan Income and Livelihood Restoration Plan Document Stage: Final Project Number: 41013 June 2013 Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Prepared

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Social Monitoring Report Semi-Annual Report January-June 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam Power Projects

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Resettlement Monitoring Report March 2014 VIE: Northern Power Transmission Expansion Sector Project Prepared by the Local Implementation Consultant (LIC) Social for Viet Nam Electricity (EVN) Northern

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject

Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject Resettlement Monitoring Report Annual Report October 2012 Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject Prepared by the InvestConsult Group for the Provincial

More information

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Yen Vien-Lao Cai Railway Upgrading Project Social Monitoring Report Semi-Annual Report July December 2015 VIE: Yen Vien-Lao Cai Railway Upgrading Project Resettlement Monitoring Report Prepared by CDM Smith DBI Joint Venture for the Ministry of

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

PROJECT SUMMARY. Improving health for immigrant women in difficult circumstances 3. LEGAL NAME OF THE ORGANIZATION PROPOSING ITS PROJECT

PROJECT SUMMARY. Improving health for immigrant women in difficult circumstances 3. LEGAL NAME OF THE ORGANIZATION PROPOSING ITS PROJECT ABOUT US PROJECT SUMMARY *GENERAL INFORMATION OF THE PROJECT 1. PROJECT TITLE Improving health for immigrant women in difficult circumstances 2. PROJECT LOCATION TAN PHU DISTRICT 3. LEGAL NAME OF THE

More information

Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project

Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project Resettlement Planning Document Resettlement Plan Document Stage: Revised Project Number: 41013-013 March 2012 Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project Prepared by Provincial

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness No. 107/2010/ND-CP Hanoi, October 29, 2010 DECREE

SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness No. 107/2010/ND-CP Hanoi, October 29, 2010 DECREE THE GOVERNMENT ------- SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness --------- No. 107/2010/ND-CP Hanoi, October 29, 2010 DECREE STIPULATING REGION-BASED MINIMUM WAGE LEVELS FOR VIETNAMESE

More information

Internal Monitoring Report. VIE: Second Greater Mekong Subregion Corridor Towns Development Project. Semestral Report (From July to December 2017)

Internal Monitoring Report. VIE: Second Greater Mekong Subregion Corridor Towns Development Project. Semestral Report (From July to December 2017) Internal Monitoring Report Semestral Report (From July to December 2017) VIE: Second Greater Mekong Subregion Corridor Towns Development Project Prepared by: PMUs Bac Giang, Lao Cai and Mong Cai for Asian

More information

Overview of arbitration in Vietnam

Overview of arbitration in Vietnam Overview of arbitration in Vietnam Arbitration in Vietnam: Understanding the Process and Making It Work for your Business Pham D Nghia Ways to resolve business disputes Article 317 Commercial Law 2005:

More information

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT (Loan No. 5233-VN) SFG1981 V2 RESETTLEMENT PLAN Public Disclosure

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY

PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY SFG2836 V2 REV SCALING UP URBAN UPGRADING PROJECT SUBPROJECT OF BEN TRE CITY, BEN TRE PROVINCE RESETTLEMENT PLAN (Final Version)

More information

VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Plan VIE: Hanoi and Ho Chi Minh City Power Grid Development Sector Project (EVN HANOI: Mo Lao 110kV Substation and 110kV Connection) Prepared by Ha Noi Power Corporation for the Asian Development

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Resettlement Monitoring Report June 2013 VIE: Northern Power Transmission Expansion Sector Project Subprojects: 1) 500kV Hiep Hoa substation 2) 500kV Son La- Hiep Hoa Transmission Line 3) 220 kv Thuong

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

Protocol to the Agreement on Ending the War and Restoring Peace in Vietnam Concerning the International Commission of Control and Supervision

Protocol to the Agreement on Ending the War and Restoring Peace in Vietnam Concerning the International Commission of Control and Supervision Protocol to the Agreement on Ending the War and Restoring Peace in Vietnam Concerning the International Commission of Control and Supervision The parties participating in the Paris Conference on Vietnam,

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

MINUTES OF THE ANNUAL GENERAL MEETING OF SHAREHOLDERS 2017 OF DHG PHARMACEUTICAL JOINT STOCK COMPANY

MINUTES OF THE ANNUAL GENERAL MEETING OF SHAREHOLDERS 2017 OF DHG PHARMACEUTICAL JOINT STOCK COMPANY DHG PHARMACEUTICAL JSC No.: 004/2018/BB.ĐHĐCĐ SOCIALIST REPUBLIC OF VIETNAM Independence Freedom Happiness Cantho, 28 th March, 2018 MINUTES OF THE ANNUAL GENERAL MEETING OF SHAREHOLDERS 2017 OF DHG PHARMACEUTICAL

More information

VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project

VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project Social Monitoring Report 2nd Semi-annual Report January 2018 VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project Prepared by Development Research and Consultancy Centre

More information

SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness No. 182/2013/ND-CP Hanoi, November 14, 2013 DECREE

SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness No. 182/2013/ND-CP Hanoi, November 14, 2013 DECREE THE GOVERNMENT ------- SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness --------- No. 182/2013/ND-CP Hanoi, November 14, 2013.. DECREE STIPULATING REGION-BASED MINIMUM WAGE LEVELS FOR LABORERS

More information

Viet Nam: Water Sector Investment Program Tranche 3. Constructing New Water Treatment Plant, Phuc Triu Commune, Thai Nguyen City, Thai Nguyen Province

Viet Nam: Water Sector Investment Program Tranche 3. Constructing New Water Treatment Plant, Phuc Triu Commune, Thai Nguyen City, Thai Nguyen Province Resettlement Plan Resettlement Plan Document Stage: Revised Project Number: 41456-043 January 2019 Viet Nam: Water Sector Investment Program Tranche 3 Constructing New Water Treatment Plant, Phuc Triu

More information

Viet Nam: University of Science and Technology of Hanoi (New Model University) Project

Viet Nam: University of Science and Technology of Hanoi (New Model University) Project Social Monitoring Report Quarterly Report December 2017 Viet Nam: University of Science and Technology of Hanoi (New Model University) Project Prepared by the Viet Nam Academy of Science and Technology

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Resettlement Due Diligence Report

Resettlement Due Diligence Report Resettlement Due Diligence Report August 2015 VIE: Power Transmission Investment Program, Tranche 2-500kV Pleiku-My Phuoc-Cau Bong Transmission Line Binh Phuoc Province Prepared by Central Vietnam Power

More information

RESETTLEMENT PLAN DANANG PEOPLE'S COMMITTEE PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG CITY SUSTAINABLE DEVELOPMENT PROJECT

RESETTLEMENT PLAN DANANG PEOPLE'S COMMITTEE PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG CITY SUSTAINABLE DEVELOPMENT PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized, DANANG PEOPLE'S COMMITTEE PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT

More information

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject Social Monitoring Report Corrective Action Plan September 2013 Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject Prepared by the Department of Agriculture

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

VIE: Viet Nam Water Sector Investment Program (Tranche 2) - Thua Thien Hue Water Supply Subproject Phase I

VIE: Viet Nam Water Sector Investment Program (Tranche 2) - Thua Thien Hue Water Supply Subproject Phase I Land Acquisition and Resettlement Due Diligence Report August 2017 VIE: Viet Nam Water Sector Investment Program (Tranche 2) - Thua Thien Hue Water Supply Subproject Phase I Prepared by Watech Construction

More information

Building Capacity to Make Transport Work for Women and Men in Vietnam

Building Capacity to Make Transport Work for Women and Men in Vietnam 67980 EAST ASIA AND PACIFIC REGION Social Development Notes I N N O VATI O N S, LE S S O N S, A N D B E ST P R A CTI C E Building Capacity to Make Transport Work for Women and Men in Vietnam Gender and

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized PEOPLE S COMMITTEE OF PHU YEN PROVINCE PHU YEN PROJECT MANAGEMENT UNIT OF CONSTRUCTION INVESTMENT WORKS FOR AGRICULTURE AND RURAL DEVELOPMENT ----------------o0oo---------------

More information

Subproject: Hai Lang Province: Quang Tri

Subproject: Hai Lang Province: Quang Tri Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP299 vol. 4 Ministry of Agriculture and Rural Development The World Bank Natural Disaster

More information

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft)

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft) Public Disclosure Authorized VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY FRAMEWORK (Final Draft) Table of Contents

More information

VIE: Phuoc Hoa Water Resources Project

VIE: Phuoc Hoa Water Resources Project Resettlement Plan Sept 212 VIE: Phuoc Hoa Water Resources Project Component: Duc Hoa main canal Cu Chi section Prepared by Project Management Unit for Investment and Construction of Cu Chi District for

More information

Social Monitoring Report

Social Monitoring Report Social Monitoring Report #4 Report November GMS: Kunming-Hai Phong Transport Corridor - Noi Bai - Lao Cai Highway Project Vinh Phuc Province Prepared by Scientific Technological Center and Environment

More information

Resettlement Plan. September 2016

Resettlement Plan. September 2016 Resettlement Plan September 2016 VIE: GMS Flood and Drought Risk Management and Mitigation Project - Upgrading and Rehabilitation of Four Primary Canals in Plain of Reeds, Dong Thap Province - Cai Cai

More information

Resettlement and Ethnic Minorities Monitoring Report

Resettlement and Ethnic Minorities Monitoring Report Resettlement and Ethnic Minorities Monitoring Report Semi-annual Report August 2013 Viet Nam: Sustainable Rural Infrastructure Development Project in Northern Mountain Provinces Subprojects in Dien Bien,

More information

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT CAN THO CITY PEOPLE S COMMITTEE CONSTRUCTION & INVESTMENT MANAGEMENT UNIT USING OFFICIAL DEVELOPMENT ASSISTANCE (ODA), CAN THO CITY ***** SFG1562 REV RESETTLEMENT POLICY FRAMEWORK FOR CAN THO URBAN DEVELOPMENT

More information

VIE: GMS Ben Luc - Long Thanh Expressway Project

VIE: GMS Ben Luc - Long Thanh Expressway Project Updated Resettlement Plan Can Giuoc district province November 2013 VIE: GMS Ben Luc - Long Thanh Expressway Project Prepared by the Vietnam Expresssway Corporation for the Asian Development Bank. This

More information

VIE: GMS Southern Coastal Corridor Project

VIE: GMS Southern Coastal Corridor Project Social Monitoring Report 2nd Report September 2014 VIE: GMS Southern Coastal Corridor Project Prepared by External Monitor, Romeo Cleto, for the Ministry of Transport of Viet Nam and the Asian Development

More information

NH21/2 LAC QUAN THINH LONG RESETTLEMENT ACTION PLAN

NH21/2 LAC QUAN THINH LONG RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

Resettlement Plan. Stage of the document: Final Project number: June 2017

Resettlement Plan. Stage of the document: Final Project number: June 2017 1 Resettlement Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang Tri Provinces Sector Project-Water

More information

ABBREVIATED RESETTLEMENT PLAN

ABBREVIATED RESETTLEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF CONSTRUCTION ADMINISTRATION OF TECHNICAL INFRASTRUCTURE MANAGEMENT BOARD

More information

Intra-urban mobilities in Ho Chi Minh City and Hanoi (Vietnam)

Intra-urban mobilities in Ho Chi Minh City and Hanoi (Vietnam) Intra-urban mobilities in Ho Chi Minh City and Hanoi (Vietnam) Le Thi Huong, IER Ho Chi Minh City, lehuongloc@hotmail.com Nguyen Thi Thieng, Population Centre Hanoi, thiengnt@neu.edu.vn Patrick Gubry,

More information

Intra-urban mobilities in Ho Chi Minh City and Hanoi (Vietnam)

Intra-urban mobilities in Ho Chi Minh City and Hanoi (Vietnam) Intra-urban mobilities in Ho Chi Minh City and Hanoi (Vietnam) Le Thi Huong, IER Ho Chi Minh City, lehuongloc@hotmail.com Nguyen Thi Thieng, Population Centre Hanoi, thiengnt@neu.edu.vn Patrick Gubry,

More information

Prepared by Project Coordination Unit, Management Board for Surveying and Planning Investment Projects, Ministry of Constructions.

Prepared by Project Coordination Unit, Management Board for Surveying and Planning Investment Projects, Ministry of Constructions. Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 34355-01 May 2008 VIE: Central Region Urban Environmental Improvement Prepared by Project Coordination Unit, Management

More information

Resettlement and Ethnic Minorities Development Plan. VIE: Support to Border Areas Development Project

Resettlement and Ethnic Minorities Development Plan. VIE: Support to Border Areas Development Project Resettlement and Ethnic Minorities Development Plan Document stage: Final Project Number: 48189-002 July 2016 VIE: Support to Border Areas Development Project Subproject: Upgarading provincial road 756

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province) Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province) Prepared by Central Vietnam Power Projects

More information

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Improving grid medium, low voltage NORTH POWER COORATION Electric Network

More information

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the CENTRAL

More information

VIE: Phuoc Hoa Water Resources Project

VIE: Phuoc Hoa Water Resources Project Resettlement Plan Loan: 2025/2747 Document stage: updated Dec 2013 VIE: Phuoc Hoa Water Resources Project Component: Tan Bien Irrigation Area Five drainage canals in Chau Thanh District, Tay Ninh Province

More information

Viet Nam: Secondary Cities Development Project. Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province

Viet Nam: Secondary Cities Development Project. Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province Resettlement Plan Resettlement Plan Document Stage: Revised Project Number: 45198 June 2016 Viet Nam: Secondary Cities Development Project Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province

More information

VIE: Ho Chi Minh City-Long Thanh-Dau Giay Expressway Project

VIE: Ho Chi Minh City-Long Thanh-Dau Giay Expressway Project Social Monitoring Report May 2010 VIE: Ho Chi Minh City-Long Thanh-Dau Giay Expressway Project Prepared by EPC Co., Ltd. for the Viet Nam Expressway Corporation under the Ministry of Transport and the

More information

NH21/1 NAM DINH - LAC QUAN RESETTLEMENT ACTION PLAN

NH21/1 NAM DINH - LAC QUAN RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK

More information

Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Plan December 2013 Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (EVN HANOI: 110 kv Noi Bai Airport Substation and Associated 110 kv Transmission Line) Prepared

More information

The seventh Vietnam Economist Annual Meeting (VEAM 2014) on 24 th 25 th, June 2014 University of Economics Ho Chi Minh City, Vietnam PROGRAMME

The seventh Vietnam Economist Annual Meeting (VEAM 2014) on 24 th 25 th, June 2014 University of Economics Ho Chi Minh City, Vietnam PROGRAMME The seventh Vietnam Economist Annual Meeting (VEAM 2014) on 24 th 25 th, June 2014 University of Economics Ho Chi Minh City, Vietnam PROGRAMME Welcome reception: 18:30-20:00, Monday, June 23 rd 2014 Victory

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

ABBREVIATED RESETTLEMENT ACTION PLAN

ABBREVIATED RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project: Irrigated Agriculture Improvement (IAIP) Subproject 1, Hoa Binh province SOCIALIST

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

L3173-VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN THE CENTRAL PROVINCES (Additional Financing)

L3173-VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN THE CENTRAL PROVINCES (Additional Financing) INTERNAL SOCIAL SAFEGUARDS MONITORING REPORT ON RESETTLEMENT (From July 2017 to December 2017) Document stage: Final report Loan Number: 3173 January, 2018 L3173-VIE: INTEGRATED RURAL DEVELOPMENT SECTOR

More information

DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT PLAN

DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT

More information

VIE: Phuoc Hoa Water Resources Project

VIE: Phuoc Hoa Water Resources Project Resettlement Plan April 2012 VIE: Phuoc Hoa Water Resources Project Prepared by Project Management Board for Investment and Construction of Agriculture and Rural Development of Tay Ninh Province for the

More information

Viet Nam: Central Region Urban Environmental Improvement Project

Viet Nam: Central Region Urban Environmental Improvement Project Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 34355 June 2008 Viet Nam: Central Region Urban Environmental Improvement Project Prepared by Project Coordination

More information

VIE: Central Mekong Delta Region Connectivity Project

VIE: Central Mekong Delta Region Connectivity Project Social Monitoring Report Quarterly Report No. 8 November 2015 VIE: Central Mekong Delta Region Connectivity Project Prepared by Joint Venture: CDM Smith, Inc., WSP Finland Limited & Yooshin Engineering

More information

RESETTLEMENT PLAN (Final draft)

RESETTLEMENT PLAN (Final draft) SFG3898 V1 REV HA TINH PROVINCIAL PEOPLE S COMMITTEE WORLD BANK RESETTLEMENT PLAN (Final draft) DYNAMIC CITIES INTEGRATED DEVELOPMENT PROJECT KY ANH TOWN SUBPROJECT HA TINH PROVINCE Public Disclosure Authorized

More information

Resettlement Plan. Stage of the document: Final Project number: June 2017

Resettlement Plan. Stage of the document: Final Project number: June 2017 Resettlement Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang Tri Provinces Sector Project-Improving

More information

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject)

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Updated Land Acquisition and Compensation Plan April 2018 LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Part 2 Prepared by the Department of Water Supply,

More information

VIE: Second Health Care in the Central Highlands Project in Dak Nong Province

VIE: Second Health Care in the Central Highlands Project in Dak Nong Province Due Diligence Report March 2016 VIE: Second Health Care in the Central Highlands Project in Dak Nong Province Prepared by the Ministry of Health, Socialist Republic of Viet Nam, for Asian Development Bank.

More information

NH18: CUA ONG MONG DUONG RESETTLEMENT ACTION PLAN

NH18: CUA ONG MONG DUONG RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT 18 ROAD NETWORK

More information

VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Project (GMS1)

VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Project (GMS1) Resettlement Monitoring Report #1 Semestral Report August 2015 VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Prepared by Vietnam Water, Sanitation and Environment joint

More information

MON: Urban Development Sector Project Bulgan Subproject

MON: Urban Development Sector Project Bulgan Subproject Resettlement Completion Report Annual Report 24 December 2012 MON: Urban Development Sector Project Bulgan Subproject Prepared by Purevsuren Dorjnamjil, Resettlement Specialist, Project Management Unit

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN HO CHI MINH CITY PEOPLE S COMMITTEE SUPPORT FOR AUTONOMUS HIGHER EDUCATION PROJECT (SAHEP) SFG2785 REV RESETTLEMENT ACTION PLAN (for the new campus of the Industrial University of Ho Chi Minh City in Tan

More information

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ------------------------------------------------------------------ SFG1163 V11 Public Disclosure Authorized Public

More information

VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing

VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing Resettlement Plan March 2017 VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing Subproject: Upgrading Dai Giang River Dike system, Thua Thien Hue province Prepared

More information

Resettlement Policy Framework

Resettlement Policy Framework Urban Transport Improvement Project of Tianjin by Using the World Bank Loan Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

Resettlement Plan Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Resettlement Plan Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Plan Project Number: 46391-001 December 2015 Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project EVN HCMC: 220-110kV Cau Bong Binh Tan Transmission Line Prepared by

More information

VIE: GMS Ben Luc Long Thanh Expressway Project

VIE: GMS Ben Luc Long Thanh Expressway Project Internal Monitoring Report Quarterly Report October-December 2015 VIE: GMS Ben Luc Long Thanh Expressway Project Prepared by Dasan Consultants Co. Ltd., in joint venture with Kunhwa Engineering & Consulting

More information

VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project

VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Final Resettlement Monitoring Report Post Evaluation Document stage: Final Project number: 42080 December 2016 VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Subproject:

More information

Vietnam. Restrictions on Freedom of Expression JANUARY 2018

Vietnam. Restrictions on Freedom of Expression JANUARY 2018 JANUARY 2018 COUNTRY SUMMARY Vietnam Vietnam s human rights situation seriously deteriorated in 2017. Police arrested at least 21 people for sweeping national security offenses that are used to punish

More information

VIE: Mong Duong 1 Thermal Power Project

VIE: Mong Duong 1 Thermal Power Project Social Monitoring Report Final Independent Monitoring Report December 2017 VIE: Mong Duong 1 Thermal Power Project Prepared by the Development and Research & Consultancy Centre for Vietnam Electricity

More information