VIE: Song Bung 4 Hydropower Project

Size: px
Start display at page:

Download "VIE: Song Bung 4 Hydropower Project"

Transcription

1 Social Monitoring Report Semestral Report February 2012 VIE: Song Bung 4 Hydropower Project Prepared by Song Bung 4 Hydropower Project Management Board (SB4HPMB) for the Asian Development Bank.

2 SONG BUNG 4 HYDROPOWER PROJECT INDEPENDENT MONITORING REPORT No. 6 RESETTLEMENT AND ETHINIC MINORITY DEVELOPMENT PLAN Prepared by: VICA Consultants International Ltd. February 2012

3 TABLE OF CONTENTS ACRONYMS... III I. EXECUTIVE SUMMARY... 1 I.1. Project s General Introduction... 1 I.2. Implementation Arrangement of the Monitoring No II. METHODOLOGIES... 2 II.1. Scope of Monitoring and Objectives... 2 II.2. Monitoring Methods... 2 II.2.1. Desk study... 2 II.2.2. Field work... 3 III. SUMMARY ON COMPENSATION, RESETTLEMENT AND LIVEHOOD RESTORATION PROGRESS... 4 IV. RESULTS IN MONITORING REMDP IMPLEMENTATION... 5 IV.1. Information Disclosure, Consultations and Community Participation... 5 IV.2. Detailed Measurement Survey (DMS) and Compensation Option Preparation... 6 IV.3. Unit Price and Compensation Pricing... 9 IV.4. Compensation and Assistance Payment IV.5. Site Clearance IV.6. Resettlement Sites Construction IV.7. Income Restoration and Livelihood Development for APs IV.7.1. Changes in social awareness, production capacity and capital utilization of AHs IV.7.2. Changes in effectiveness of livelihood improvement and restoration for AHs IV.8. Gender, Ethnic Minorities and Healthcare Considerations IV.8.1. Gender issues IV.8.2. Ethnic minority considerations IV.8.3. Healthcare considerations IV.9. Complaints and Grievance Redressal IV.10. Coordination among Stakeholders IV.11. SB4HPMB s Internal Monitoring V. CONCLUSIONS AND RECOMMENDATIONS V.1. Conclusions V.1.1. Resettlement and compensation V.1.2. Livelihood restoration, gender, ethnic minority development, healthcare service V.2. Recommendations V.2.1. Compensation and Resettlement VICA Consultants Ltd., Page i

4 V.2.2. Gender, ethnic minorities, and healthcare considerations VI. ANNEXES Annex 1: List of Interviewed Staff and AHs Annex 2: Templates of DMS for AHs in PaDhi and Pa Rum B, Zuoih commune Annex 3: Summary on Compensation and Assistance in PaDhi hamlet, Zuoih commune Annex 4: Acknowledgement Receipts of Compensation and Assistance Payment for AHs Annex 5: Some Fieldwork Photos LIST OF TABLES Table 1: Duration of DMS on affected assets of AHs being resettled and other project components... 7 Table 2: Total amount of compensation payment and assistance to affected hamlets in the project reservoir Table 3: Summary of assistances under SB4HP for resettled AHs Table 4: Site clearance progress under SB4HP Table 5: Revised resettlement sites construction plan agreed among project stakeholders. 16 LIST OF PHOTOS Photo 1: Proceeding of detailed asset inventory for AHs in Pa Rum B hamlet, Administrative Quarter in Zuoih commune... 8 Photo 2: Some photos on compensation and assistance payment for AHs in Ta Poo commune Photo 3: Access roads to Pa Pang, Pa Rum A and Pa Rum B resettlement sites Photo 4: Some photos on Pa Pang RS of Hamlet No.2, Ta Poo commune, Nam Giang, Quang Nam LIST OF BOXES Box 1: Comments of AHs in Hamlet 2 and Pa Pang on Project information Disclosure... 5 Box 2: Procedure of publication of compensation options under Song Bung 4 Hydropower Project... 8 Box 3: Comments of RHs in reservoir area in Vinh hamlet VICA Consultants Ltd., Page ii

5 ACRONYMS ADB Asian Development Bank AHs/APs Affected Households/Persons DMS Detailed Measurement Survey DONRE Department of Natural Resources and Environment DPC District People s Committee EVN Electricity of Vietnam FSL Full Supply Level GOV Government of Vietnam M&E Monitoring and Evaluation PMU Project Management Unit PPC Provincial People s Committee PPTA Project Preparation Technical Assistance PRA Participatory Rapid Assessment REMDP Resettlement and Ethnic Minorities Development Plan RHs Resettled Households RMIU Resettlement Management and Implementation Unit RS Resettlement Site SB4 Song Bung 4 SB4HPMB Song Bung 4 Hydropower Project Management Board SB4HP Song Bung 4 Hydropower Project TA Technical Assistance TOR Terms of Reference USD United State Dollar VND/BVND Vietnam Dong/Billion Vietnam Dong VICA Consultants Ltd., Page iii

6 I. EXECUTIVE SUMMARY I.1. Project s General Introduction 1. Song Bung 4 Hydropower Project (SB4HP) is to be built on Bung River, a tributary of Vu Gia River, some 3km upstream of the confluence with A Vuong River and Bung River. The project is carried out in Zuoih, Ta Poo and Ta Bhing communes of Nam Giang District, Quang Nam Province in Central Vietnam. Song Bung 4 Dam, located on an effluent of Bung River, lies on the boundary of Zuoih and Ta Bhing communes (currently known as Ta Poo commune) of Nam Giang District. The reservoir influences on Zuoih and Ta Poo communes. The project has been commenced since 25 th June The Project works include a dam of 110m high with the length of the dam at the top of 367m, an underground water conveyance system and a Song Bung 4 dam power station. Song Bung 4 Project, located on Bung River some 3km upstream of the confluence with A Vuong River, will create a reservoir with an area of some 15.8 km 2 at the Full Supply Level (FSL) of m and an area reduction of 7.8 km 2 with minimum/ dead water level of +205 m. 3. Water from Song Bung 4 Reservoir will be diverted, via a headrace tunnel and an underground penstock to a power station located on Bung River some 5km downstream of the dam. The difference in elevation between the reservoir and the power station is some 125 m at the FSL. From the power station, the water is conveyed back to Bung River via a short tailrace canal. 4. SB4HP has been approved by ADB for updating REMDP Vol 1; Vol 2 and Vol 3A in 2010 and after reaching an agreement with ADB missions (from 29 th November to 13 th December 2010; from 3 rd March 2011 to 14 th March 2011 and from 13 th December 2011 to 16 th December 2011) the resettlement plan was revised in compliance with new timeline. 5. In accordance with the revised plan on the latest progress, reservoir flood discharge will be approved by ADB once all compensation has been paid to AHs as well as the resettled AHs have been relocated to the Resettlement sites under the approved REMDP. As a result of the adjustment, total investments dramatically increase against initial design. This is mainly because of increased payment for AHs, resulting from the adjustment in compensation/assistance policy and inflation. 6. Under approved REMDP for SB4HP, an amount of some $US 2 millions from Japan Fund for Poverty Reduction (JFPR) is granted for the programs of livelihood rehabilitation and assistance, gender and ethnic minority development as well as healthcare and medical services, and technique assistance undertaken by CHF. The contract was signed at the end of 2008, and will be finished by June According to adjusted construction plan for Resettlement sites, the latest Project s relocation and resettlement activities will be completed on 31 st December Based on the agreement between SB4HPMB with Sino contractor and Mott MacDonald Consultants, key milestones in construction progress approved by EVN are as follows: Construction commencement: 3/9/2010; River backfilling: 16/1/2012; Storing water in the reservoir: 1/6/2014; Operation of the Electricity Generation Unit No. 1: 9/2014; Operation of the Electricity Generation Unit No. 2: 10/2014; Construction completion: Quarter IV/2014. VICA Consultants Ltd., Page 1

7 I.2. Implementation Arrangement of the Monitoring No.6 8. VICA Independent Consultant Team (the Consultants) arrived in the field in December 2011 to implement the sixth monitoring mission. The main purposes of the monitoring mission include: (i) collecting information, confirming the actual results of the implementation of the of SB4HP. (ii) Analyzing and evaluating different aspects of REMDP implementation in terms of resettlement, livelihood development, gender and ethnic minority; (iii) providing crucial recommendations to improve the REMDP implementation. 9. The Consultants (i) met with SB4HPMB to discuss and collect data on the implementation progress of the project components, (ii) worked with and interviewed the staff of SB4HPMB and Nam Giang District Resettlement Management and Implementation Unit (RMIU Nam Giang), Center for Land Fund Development in Nam Giang District to affirm the results of settling complaints and grievances during the compensation process; (iii) discussed the staff in Vinh hamlet and staff of Pa Pang hamlet, staff of hamlet 2 - Ta Poo commune, staff of Pa Rum A hamlet Zuoih commune to affirm the compensation, assistance and income restoration progress for the Affected Households (AHs); (iv) questionnaires and in-depth based interviewed and consulted with AHs of all project components, (v) Group discussion on gender and ethnic minority issues with the AHs. II. METHODOLOGIES II.1. Scope of Monitoring and Objectives 10. The previous REMDP Independent monitoring reports were in full of the objectives, contents and monitoring methods at the request of SB4HPMB. This section summarizes the main objectives and scopes of the monitoring as below: II.2. General objective: To strengthen the efficiency of project activities (progress and quality of activities, compliance level with requirements prescribed in REMDP). Specific objectives: o o o o o Studying the implementation status of REMDP in the three project areas namely the reservoir, the upstream/downstream areas of the reservoir and the land-acquisition area (for construction) of the project. Checking the implementation of DMS/ILO and the accuracy of the data from Pa Rum A, Pa Rum B, PaDhi, Cong Don hamlets and the reservoir area of Vinh hamlet. Independently monitoring the compensation and assistance, and site clearance for all project components which include: i) resettlement site in Hamlet No. 2; ii) Administrative Quarter in Zuoih commune; Monitoring the activities related to livelihood restoration for AHs, issues of gender, ethnic minority and healthcare services. Evaluating results as well as the implementation of internal monitoring activities for conclusions and recommendations on REMDP implementation. Monitoring Methods II.2.1. Desk study 11. The Consultants started with studying and reviewing relevant documents available in office as usual to collect qualitative information and quantitative data to capture the general progress of compensation, assistance and resettlement of the project to date. The documents VICA Consultants Ltd., Page 2

8 scrutinized by the Consultants include: (i) submitted monitoring reports; (ii) Updated REMDPs (especially Chapter 6, 7, and 8 of updated REMDP Vol 2); (iii) internal monitoring report of SB4HPMB; (iv) MOU of ADB Mission from 13/12/2011 to 16/12/2011. The Consultants, additionally, regularly update new policies of ADB and GoV for ensuring efficiency of monitoring activities. II.2.2. Field work 12. During the field trip, different methods were used and combined to obtain the best monitoring results, including the followings: Document analysis 13. The Consultants reviewed the documents related to safeguard policies, legal documents, internal reports and other documents on the results of compensation, assistance and resettlement activities to diversify information sources, which could be enable to collect and analyze relevant matters during REMDP implementation. The Consultants had conducted random checks on records and documents relating to the implementation of compensation, assistance and resettlement of SB4HPMB, RMIU and reports of JFPR s consultant (CHF). In-depth interview 14. The Consultants carried out in-depth interviews with project affected persons (APs), project staff and those responsible for REMDP implementation by a prepared list of questions. This will provide more information in addition to the ones collected from questionnaires and document analysis. During this monitoring mission, in-depth interviews were conducted with the following: SB4HPMB s staff: 4 persons CHF s staff: 3 persons RMIU s staff: 3 persons Staff of Ta Poo hamlet: 3 persons Staff of Pa Pang hamlet: 2 persons Staff of hamlet No. 2: 4 persons AHs in hamlet No. 2 and Pa Rum B: 15 persons Questionnaire Interview 15. During the monitoring process, this method is used as a main tool to assess the resettlement implementation. The Consultants had distributed questionnaires to 55 AHs during this monitoring. Group discussion 16. The group discussions were conducted with hamlet officials and representatives of the AHs at hamlet No. 2, and Pa Pang (Ta Poo commune) to collect information on the advantages, difficulties and solutions during the project implementation and re-evaluate project framework as well as policy framework. This method, moreover, was carried out with a focus on evaluating other issues related to benefits/entitlements of APs, community participation, efficiency of construction investment, and capacity of project staff. The Consultants carried out 2 groups discussions, most of which were conducted at local community houses, and the hamlet head s house). There were 6-8 participants in each discussion. Observation 17. During the field trip, the Consultants visited and interviewed some AHs to observe their living conditions and facilities. The Consultants, also, interviewed APs how they used their VICA Consultants Ltd., Page 3

9 compensation as well as assistance measurements for AHs livelihood rehabilitation after the project implementation. III. SUMMARY ON COMPENSATION, RESETTLEMENT AND LIVEHOOD RESTORATION PROGRESS 18. Implementation progress of the main project components was basically in line with the schedule approved by EVN under the Decision No. 1579/QD-EVN dated 14/11/2008. The items of the main works were commenced on 25 th June By the monitoring time, compensation payment has been made and completed under 12 items of the main works. The remained key item (reservoir) has been implemented as follows: (i) compensation and assistance payment were made for AHs in Hamlet No. 2, and 04 AHs in Vinh Hamlet, Ta Poo commune; (ii) approval decision on compensation and assistance payment options for AHs in PaDhi, Zouih commune was issued; (iii) approval decision on compensation options for works in administrative quarter of Zuoih commune was issued; (iv) compensation and assistance options for AHs in Pa RumA, Pa RumB, Zuoih commune was submitted. Compensation payment was completed for 25 AHs in Pa Pang resettlement site (RS). CHF is currently providing technical assistance for livelihood restoration and development for AHs under a contract signed with ADB. 20. Construction site survey and design for project RSs are lagging 8 months behind the revised construction plan due to limited experiences of local consultants which caused difficulties for updating REMDP. By the monitoring time, resettlement site construction plan had been adjusted per request of ADB s Mission during their field trip from 13/12/2011 to 16/12/ The construction of access roads to Pa RumA and Pa RumB RS (in combination with the temporary road for SB2HP construction) had been completed and put into use since Second Quarter of Song Bung Bridge was put into use, which facilitated transportation among hamlets and Pa RumA and Pa RumB RS. Currently, the access road to Pa Pang RS has been technically opened for traffic in June Construction contractors and local people can access Pa Pang RS through the bridge and the road (at the connecting section with National Highway 14D). By the monitoring time, the construction of drainage culverts on route, diaphragm wall and foundation excavation for slab bridge construction were completed and it is expected to finish the construction of the whole road to PaDhi RS by the end of July of At Resettlement sites such as Pa Pang, Pa Pum A, Pa Rum B, and PaDhi, the landmarking activity in field had been completed with the participation of PMU staff, JFPR consultants (CHF) and local people. In Pa Pang RS, road serving production, house foundation, drinking water reservoir and water pipe installation for AHs have been conducted. Construction of internal roads in the hamlet had been completed. By the monitoring time, land allocation for resettled HHs in Hamlet No. 2 had been completed and most of AHs are building houses on their allocated land plots in Pa Pang RS (48 out of 53 houses were completed). 22kV medium voltage transmission line was completed and expected to supply electricity before 20 th January Some project activities (construction of RSs, access roads to RSs) had been lagging behind the schedule (for about 8 months) due to some subjective reasons/causes (such as the cooperation among local authorities to reach agreements on procedures, delays in granting license and making decisions, and delays in contractor s construction) as well as objective reasons/causes (natural disasters, floods, changes in compensation and assistance policies), which were out of PMU s control. 24. Co Tu APs were assisted in accordance with the Project Policy Framework (PPF) and GoV s policies on ethnic minorities. The compensation and assistance amount had been paid in VICA Consultants Ltd., Page 4

10 full to them (with the presence of both husband and wife) after they signed (or finger printed) on the List of Acknowledgement Receipts. 25. SB4HP was funded with USD 2 million from JFPR Fund of Japan to restore livelihood for AHs. CHF is a technical assistance organization recruited to conduct technical assistance, livelihood restoration measures for AHs, especially those under project s resettlement plan. Generally, livelihood restoration activities under the Project has been conducted by CHF in the whole project. However, despite some achievement, there are some certain outstanding issues mentioned in section IV In general, compensation and resettlement progress was behind the approved schedule due to various reasons (updating data on AHs under REMDP took times; compensation option approval also took a lot of time; land measurement and cadastral activities were faced number of difficulties resulted from the large area; limited capacity of local authorities in land management which led local people encroach forest land for compensation and assistance etc). However, according to the consultant s estimation compensation and assistance payment for AHs was implemented in compliance with approved REMDP s regulations by RMIU and SB4HPMB. During the DMS process, some arisen affected assets (mostly the trees) had caused some claims/grievances from AHs. These queries/complaints have been jointly settled by CPCs, RMIU Nam Giang, and Center for Land Fund Development in Nam Giang District, CHF and SB4HPMB. IV. IV.1. RESULTS IN MONITORING REMDP IMPLEMENTATION Information Disclosure, Consultations and Community Participation 27. The information disclosure is often conducted under a consultation meeting among stakeholders such as project staff, RMIU, CHF s staff, resettlement team in representing AHs and AHs. Most of AHs fully participated in the community consultation meetings to grasp information of the project. 28. Before implementing DMS, compensation payment and site clearance, information about APs benefits, project policies, environmental impacts, implementation arrangement, responsibilities of stakeholders and grievance mechanism, etc. were all made known to AHs by local authorities at all levels (SB4HPMB, RMIU, local staff, CHF ). 29. There are a lot of resettled HHs in Pa Pang and hamlet no. 2, Pa RumA and Pa RumB and PaDhi, information disclosure and consultation, therefore, are paid special attention by stakeholders. Most of consultation meetings were held in community house or village header s house and participated by all AHs. 30. By the monitoring time, it is learned by IMC that most of AHs were aware of project s impacts, their entitlements, responsibilities and the adjusted resettlement plan in order to stabilize their life and restore livelihood. They also said that the Project had positively changed their life. However, many people supposed that their livelihood development in future will meet difficulties as cultivation land area was narrowed and livelihood assistance activities will end upon the project completion, which would create significant impacts on their future life. Box 1: Comments of AHs in Hamlet 2 and Pa Pang on Project information Disclosure Bnuoch Chup, AH in Hamlet 2, Ta Poo commune, Nam Giang, Quang Nam: It is difficult for resettlement households without man like us. We have to hire labor to take woods and build houses. Almost households have moved here except some who stay to take care of the old one. If having money, we will complete houses before thinking of planting rice or earn living from forest. The soil and land in the new hamlet is not as good and large as in the old one. We might have to go into the forest to earn living. At present, although being guided how to develop models, we do not pay much attention as we are busy on building houses. VICA Consultants Ltd., Page 5

11 A Viet Duoc, AH in Pa Pang, Ta Poo commune, Nam Giang, Quang Nam: In Pa Pang, money was paid a long time ago, products from rice plantation models developed were shared equally to all at several tens of kilos per household. Some of chickens and pigs brought here died. Since land area is limited, we have to reclaim more. At the moment, we still have money to fix house and spend but in future perhaps there s no choice but earn living from forest as before. Source: In-depth interview, IMC, 12/ Apart from consultation meetings, stakeholders mobilized AHs to participate in training models to understand production procedures on site and hang posters with images at community house for AHs to follow. 32. In each resettled hamlet, the resettlement and supervision groups were established to support community consultation, project information dissemination. There are 9 members in each resettlement group, including (i) the group head (chief of hamlet); (ii) 2 healthcare staff; (iii) 2 facilitators; (iv) 2 veterinary staff; (v) 2 extension staff. Members of supervision group include 15 persons (i) 9 members of hamlet resettlement group; (ii) representatives of hamlet Youth union, Women s Union and Fatherland Front; (iii) representatives of AHs. The establishment of these organizations is to ensure conveying AH s feedbacks to project stakeholders to reach agreements and reduce interest conflicts, which helps the PMU adjust resettlement plans suitable to actual project activities. 33. At the monitoring time, information disclosure, consultation were conducted regularly, depending on each phase under the project via suitable methods with AHs at different locations. Co-operation between stakeholders and AHs helped to smooth consultation and information disclosure as scheduled. General Comments 34. Community consultation had been carried out satisfactorily by SB4HPMB, CHF s staff in collaboration with Nam Giang RMIU, and CPCs. During consultation meetings, AHs were informed about the project s basic information, benefits of AHs, grievance redressal procedure and livelihood restoration by project s staff. 35. AHs were all aware of impacts of the project on their life. There is a fact that BAH only knew the total sum of money but not care about each sum of compensation and assistance item. 36. Resettlement and Community Supervision Groups established in hamlets should have included all AHs. However, due to poor education level of AHs and members of hamlet resettlement group, the effectiveness of group s activities is not as good as expected. Most of representatives of AHs in consultation meetings were not active to grasp information. Therefore, it is necessary to provide capacity building training for this group; otherwise, it can not fully utilize all functions during the project implementation. 37. In general, project information disclosure by monitoring time brought quite good results. However, there were some certain shortcomings originating from large affected area, poor education level etc which caused obstacles to consultation and information disclosure activities. IV.2. Detailed Measurement Survey (DMS) and Compensation Option Preparation 38. DMS was carried out for all AHs under different project components and followed the schedule. 39. By the monitoring time, in the reservoir area, PMU in collaboration with stakeholders have carried out the DMS for AHs in: (i) the reservoir area( Pa Rum A, Pa Rum B, Hamlet No. 2, PaDhi hamlet, 4 AHs in Vinh Hamlet); (ii) access roads to resettlement sites (PaDhi, Pa Rum A, Pa Rum B); (iii) Administrative Quarter in Zuoih commune. Inventory duration was as follows: VICA Consultants Ltd., Page 6

12 Table 1: Duration of DMS on affected assets of AHs being resettled and other project components Components/Items Starting date Ending date No. of AHs (household) Hamlet No The first time 05/01/ /01/2011 The second time 15/02/ /02/2011 The third time 22/03/ /03/2011 Pa Rum A hamlet 05/04/ /04/ Pa Dhi hamlet 01/03/ /03/ Pa Rum B hamlet 21/06/ /07/ Road to PaDhi 21/10/ /11/ Road to Pa Rum A and Pa Rum B Administrative Quarter in Zuoih commune Source: PMU, 12/ /10/ /05/ /05/ /05/ The list of AHs to be resettled was updated under REMDP Vol. 2, which was approved by the ADB. At present, some AHs claimed for additional inventory of property, which was handled with collaboration between PMU and other stakeholders. 41. The DMS was implemented with participation of stakeholders including (i) Provincial consulting unit (Natural Resources and Environment Technique Center - Quang Nam DONRE); (ii) Nam Giang RMIU s members and Center for Land Fund Development in Nam Giang district; (iii) Commune cadastral staff; (iv) representative of the Investor; (v) representative of communal authority; (vi) village resettlement groups; (vii) CHF s representative; and (viii) representatives of AHs. 42. The DMS was carried out under following steps: Step 1. SB4HPMB in coordination with Nam Giang RMIU, Center for Land Fund Development in Nam Giang district distribute the affected asset declaration sheets for households and introduce the way to fill in the sheet by themselves. Step 2. RMIU staff together with SB4HPMB staff, communal and hamlet staff and AHs conducted site inspection and verified actual affected properties of each household and compare them with the declaration sheets. Step 3. When the DMS was over, representative of AHs (normally the household s head) co-signed and certified in the minutes/proceeding. 43. A summary table of DMS s results was then publicized at the hamlet community houses. Any complaints on affected assets (land area, structures, trees, crops and other properties) were checked and verified by members of Compensation Board. The records of additional DMS (if any) will be made after reaching an agreement and the signature of AH s representative. - VICA Consultants Ltd., Page 7

13 Photo 1: Proceeding of detailed asset inventory for AHs in Pa Rum B hamlet, Administrative Quarter in Zuoih commune Source: PMU, 12/ The compensation and assistance options were established on the basis of project policy framework (outlined in REMDP 1 ), which was approved by ADB and under related Decisions of Quang Nam PPC. The losses and damages on trees, structures, and assets would be compensated in cash, equal to the value of the affected assets. The households eligible for resettlement would be compensated land-for-land together with various assistances to restore their living standards. In addition, because AHs were the ethnic minority ones, the compensation and assistance options had been adopted the policies for ethnic minority people in accordance with project policy framework and GoV s regulations. Box 2: Procedure of publication of compensation options under Song Bung 4 Hydropower Project As contents of investment projects and works, the priority order, implementation schedules, compensation and assistance options for site clearance and resettlement related to projects and works in communal-level localities, detailed land use plans and adjusted options and local residential area master plan in commune should be posted publicly at Commune People s Council s and Commune People s Committee s Office within two days from the date the documents were adopted and signed for promulgation, for matters falling under the deciding competence of communal-level administrations, or from the date the documents were received, for matters falling under the deciding competence of superior state bodies. The duration for posting up will be at least thirty consecutive days from the date of post-up. Source: Article 7 in Ordinance on Exercise of Democracy in communes, wards and townships, Quang Nam PPC had stipulated and assigned responsibilities to local departments to appraise the compensation options prepared by RMIU Nam Giang. During the compensation option preparation, SB4HPMB and RMIU Nam Giang had coordinated with CPCs to conduct public consultation on the compensation pricing and calculation of compensation for affected assets of AHs. The compensation options can only be finalized and submitted for approval after obtaining the consent/agreement of local people. 46. In general, DMS and compensation option preparation under SB4HP were conducted following the procedures. By the monitoring time, DMS and compensation option preparation in 1 Chapter 6, REMDP Vol 2, updated. VICA Consultants Ltd., Page 8

14 most of project works were carried out. Although the DMS and compensation option preparation were done in a transparent manner, DMS in some work items was delayed (due to limited number of staff, coincidence with rainy season in Central Region, large affected area etc). However, most of AHs had their assets/properties inventoried except some AHs complained on affected assets, which then handled by PMU and stakeholders to adjust compensation and assistance option. IV.3. Unit Price and Compensation Pricing 47. Based on DMS s records agreed and signed by AHs, SB4HPMB in collaboration with RMIU Nam Giang conducted the compensation pricing and assistance entitling based on the provisions on compensation, assistance and resettlement issued by Quang Nam PPC. 48. By the monitoring time, the compensation value for AHs in hamlet 2, Pa Rum A, Parum B PaDhi, Administrative Quarter in Zuoih commune, access road to PaDhi was applied based on the unit price of Compensation option approved by Nam Giang DPC was presented in the detailed summary table on value of compensation, assistance and resettlement for each construction item and affected asset (such as houses, land, trees, crops and assistance for each AH). 50. Legal bases for compensation pricing for AHs in hamlets and other work items include: Decision No. 23/2010/QD-UBND dated 30/09/2010 by Quang Nam PPC on regulating compensation, assistance and resettlement when the State acquires land in Quang Nam in Decision No. 33/2010/QD-UBND dated 17/12/2010 by Quang Nam PPC on regulating methods to identify prices of all land types within Quang Nam province in Decision No. 1711/QD-UBND dated 27/12/2010 by Nam Giang DPC on approving prices of agricultural lands in 2011 in Nam Giang District. 51. For resettled AHs, two compensation and assistance options were prepared by PMU and Nam Giang RMIU as follows: (i) One option was to compensate and assist in constructing houses and auxiliary structures; (ii) One option was to compensate and assist in resettlement for other affected assets (land, trees, crops and civil structures). Based on actual resettlement plan, compensation payment would be made by PMU according to approved compensation option in order to timely support AHs during their construction of new houses and living stabilization. 52. Within 3 days after having approval decision of authorized agencies, the detailed compensation option was posted at CPC s office and hamlet community houses. The publicized compensation option included detailed calculation on the value of affected assets, total compensation and assistance for each AH. 53. According to the IMC s records, there were some AHs not satisfied with the compensation unit price for their affected assets. However, after consulting with project stakeholders, these complaints were not reasonable. For example, APs requested compensation for trees/crops planted after the cut-off date; or compensation for protection forest/natural reserve and natural production forest. This caused difficulties and delays in applying compensation unit price and preparing compensation option as well as the overall project implementation. 54. During the interview and field observation, it was learned that together with publicly posting compensation options, PMU s staff in collaboration with local authority also informed AHs details on time, location, method and procedures of compensation and assistance payment. AH s complaints and grievances were satisfactorily addressed by PMU in collaboration with Nam Giang RMIU prior to make compensation payment. In general, compensation unit price application under the Project was complied with the regulations. VICA Consultants Ltd., Page 9

15 IV.4. Compensation and Assistance Payment 55. SB4HPMB began making compensation and site clearance from May At the time of monitoring, for the reservoir area, 25 AHs in Pa Pang hamlet, 64 AHs in hamlet 2, 04 AHs in Vinh hamlet of Ta Poo commune (former hamlet 2 of Zuoih commune) and the Administrative Quarter of Zuoih commune had received assistance and compensation payments. For access roads to PaDhi, Pa Rum A and Pa Rum B resettlement sites, the compensation option for AHs was approved. For the other hamlets, namely, Pa Rum A, Pa Rum B, PaDhi, the compensation and assistance option was submitted for appraisal and approval. On the basis of the compensation option approved by Quang Nam PPC, PMU s staff in coordination with Nam Giang RMIU and local governments made compensation payments directly to AHs. 56. As mentioned above, SB4HPMB and Nam Giang RMIU had prepared 2 separate compensation and assistance options for AHs in resettled hamlets as follows: (i) Compensation and assistance option for constructing houses and auxiliary structures; and (ii) Compensation and assistance option for land, trees and crops. As for other RSs of Pa Rum A, Pa Rum B, PaDhi, there would be a common compensation options for houses, property and assistance amounts for AHs. However, the compensation payment was split into several times because of on-going house reconstruction plan and livelihood rehabilitation program. Table 2: Total amount of compensation payment and assistance to affected hamlets in the project reservoir Commune Ta Poo Zuoih Hamlet Hamlet No.2 (new) Total Compensation Payment (VND) 9,334,689, ,090,697,000 Pa Pang 12,579,793,167 Vinh hamlet (04 resettled households) Pa Rum A Pa Rum B 6,837,851,300 Uncompleted approval Uncompleted approval PaDhi 54,397,962,481 Access road to PaDhi resettlement site Administrative Quarter, commune Source: PMU, December 2011 Zuoih 4,392,872,941 1,477,611,000 Type of assistance/compensation Assistance for constructing house and auxiliary structure Compensation and other types of assistance Compensation, assistance for constructing house and auxiliary structure and other types of assistance Compensation, assistance for constructing house and auxiliary structure and other types of assistance Compensation, assistance for constructing house and auxiliary structure and other types of assistance Compensation and other types of assistance Compensation and other types of assistance 57. By the time of monitoring, only AHs being resettled in Hamlet No.2 have received compensation payment and assistance. Because AH s relocation and construction have not been completed, SB4HPMB cooperating with Nam Giang RMIU, Agribank of Nam Giang district and VICA Consultants Ltd., Page 10

16 CHF advised AHs in Hamlet No. 2 to open saving accounts in the Bank after receiving compensation payment. Both husband and wife would be the owners of the saving accounts. Compensation payment has been made for AHs in hamlet 2 three times. Based on the progress of site clearance, construction in RS and actual AH s relocation, compensation payment was made as schedule. Photo 2: Some photos on compensation and assistance payment for AHs in Ta Poo commune. Source: PMU, IMC 12/ The assistance payments for resettled AHs in reservoir area were in line with the project policy framework and REMDP. The types of assistance are presented in following table: Table 3: Summary of assistances under SB4HP for resettled AHs No Type of Assistance Beneficiaries Assistance Mode 2 1 Healthcare assistance Households in hamlet no. 2, Pa Rum A, Pa Rum B, PaDhi hamlets 2 Relocation assistance Both male and female in all resettled hamlets 3 Relocation bonus Resettled households 4 Relocation of hamlet community house 5 Assistance for house warming ceremony 6 Assistance for study tours Project hamlet Resettled households Resettled households Constructing/upgrading Healthcare Station and improving healthcare services in affected hamlets Healthcare assistance: VND 30,000 per head of AH All resettled AHs; each AH received an amount of VND 4,000,000 as relocation assistance amount. All HHs resettled themselves are entitled to receive relocation bonus: + Within district: VND 200,000 per HH; + Out of district, within province: VND 400,000 per HH; + Out of province, within Central provinces: VND 800,000 per HH; + Relocate in Northern and Southern provinces: VND 1,000,000 per HH. In cash: VND 5,000,000 per hamlet In cash: VND 1,000,000 per HH In cash: VND 500,000 per HH 2 From EVN/PMU VICA Consultants Ltd., Page 11

17 No Type of Assistance Beneficiaries Assistance Mode 2 7 Assistance for exhuming and moving the graves 8 Assistance for moving graves 9 Assistance for house construction 10 Assistance for food security during the transitional period (assisting once for HHs losing all affected land) 11 Assistance for medical care during transitional period 12 Assistance for education 13 Assistance for connecting electricity grid 14 Assistance for developing production technique, occupation and business 15 Allowance for vulnerable households Resettled households Resettled households Resettled households Resettled households All resettled households (in any) All resettled households (if any) All resettled households (if any) All resettled households (if any) Poorest HHs, female or elderly headed HHs 16 Wage for workers Resettled households (with/without family book registration in the hamlet) 17 Income restoration Resettled households Source: REMDP Vol 2 and SB4HPMB, 7/2011. In cash: VND 400,000 per HH In cash: VND 350,000 per grave (i) Households having 1-4 persons are assisted with VND 147,288,952 per HH; (ii) Households having 5-7 persons are assisted with VND 161,576,185 per HH. In cash: (i) food: 300,000 VND/month/person within 48 months after moving; (ii) nutrition foods in equivalent of 100,000 VND/person/month in 6 months. An amount of VND 100,000 per household as medical allowance. Households having children attending primary school will be supported with textbooks during 3 years, free of charge. In cash: 15,000 VND/month/person in 3 months In cash: VND 1,000,000 per HH to develop/ improve production technique, occupation and business. In cash: 150,000 VND/person/month in 60 months Each labor (male or female) will receive rice and/or cash as wage for building resettlement sites, building their own houses and infrastructure in the sites and livelihood development. (i) assistance for varieties, pesticide and fertilizer: VND 2000 per m 2, VND 200,000 per 500 m 2 per year x 5 crops; (ii) assistance for extension: VND 500,000 per HH; (iii) assistance for improvement of occupation, services and trade: VND 1,000,000 per HH; (iv) assistance for implementing required procedures, including: VND 300,000 per HH for moving old houses and VND 1,000,000 per HH for ceremony in new houses; (v) assistance for poverty reduction in line with MOLISA: VND 150,000 per head in 60 months; (vi) assistance for business suspension: minimum salary rate x 6 months. VICA Consultants Ltd., Page 12

18 59. Households out of resettlement scale were paid compensation for affected properties. In addition, they received assistance for job seeking, livelihood settlement; engrave moving, income restoration and incentive for transfer on time. General Comments 60. The Consultants learnt that AHs after receiving compensation and assistance, had deposited in Nam Giang Agribank. At the time of paying compensation, Bank s officials had directly instructed AHs to open saving accounts. The interview results showed that these AHs only kept some 20% of total compensation amount to do shopping and solve the immediate difficulties/problems of the family. The technical staff of CHF had consulted and advised AHs how to use the compensation amount in a proper and effective manner to stabilize and restore their livelihoods 3. Box 3: Comments of RHs in reservoir area in Vinh hamlet Bnuoch A Chop, hamlet 2, Ta Poo, Nam Giang, Quang Nam RHs in hamlet 2 has received compensation payment and assistance twice for their resettled houses in former hamlet. They only spend a small amount of money on buying items and hiring workers for house construction so the remaining money was deposited in the bank. People can periodically draw returns and hold their saving accounts. On 27/12 and 29/12, all RHs in the hamlet will receive the remaining compensation payment and assistance that is will be also deposited in the bank. Po Long Le, hamlet 2, Nam Giang, Quang Nam Staff of SB4HPMB and bank inform us about relevant procedures for drawing money. My wife and I both drew money and signed in two previous times. We are going to spend a small amount of money on paying workers. The remaining is drawn latter. Staff of bank had given us detailed guidance. Source: In-depth interview, IMC 12/ Through interviewing, the Consultants realized that in the period from being informed about the project until being received compensation and assistance, AHs were provided with following documents by SB4HPMB s staff: (i) Results of the detailed land measurements; (ii) Compensation and assistance for resettlement option/plan; (iii) The attachment on compensation unit price for houses, structures and assets under Decision No. 78/QD-UBND dated 20/1/2011 by Nam Giang DPC; (iv) Minutes of inventory and calculation on compensation; (v) Documents on compensation policies and mechanisms for AHs resided in the reservoir area and Pa Pang RS (Chapter 6 in REMDP-Vol 2); (vi) Receipt of compensation, assistance and resettlement; and (vii) Plan on utilizing compensation and livelihood assistance. 62. In general, compensation and assistance payments for AHs was made as the project schedule. There was no problem during the compensation payment thanks to successful consultation and advanced negotiation with AHs. In addition, some arising problems might make compensation payments lag behind the schedule. In detail, the most notable problem was that some AHs in Pa Pang hamlet were requested to co-use the land. Some AHs did not bring relevant procedures for receiving compensation payments or wanted to receive all compensation payment one time, etc. These may affect approved disbursement progress. IV.5. Site Clearance 63. According to project schedule, site clearance activity would be done once AHs received their compensation. SB4HP s site clearance activity started since May Upon site clearance, the land was handed over to construction units, which was implemented by stakeholders in compliance with the procedures set forth in REMDP. 3 CHF s consultation minutes were distributed to all AHs in Pa Pang, Hamlet No. 2, Pa Rum A, Pa Rum B and PaDhi hamlets. VICA Consultants Ltd., Page 13

19 Photo 3: Access roads to Pa Pang, Pa Rum A and Pa Rum B resettlement sites Source: the IMC and PMU, 12/ At the time of compensation payment and assistance, compensation and assistance statement was signed between asset owners and PMU, including: (i) not encroach the handedover site under any circumstances; (ii) not cause any delay toward construction activities in the handed-over site; (iii) bonus will be entitled upon early-handing over the site. 65. All acquired land items under the Project mentioned in REMDP Vol 3 (110kV Transmission line, camps, rock quarry and operation house ) were cleared and handed over to contractors after completing compensation payments. 66. For AHs in the reservoir area (resettled hamlets, access road to resettlement sites and Administrative Quarter of Zuoih commune), site clearance was implemented as the actual schedule. At the time of monitoring, site clearance in the new reservoir area was only implemented to 04 households of Vinh hamlet, former hamlet 2, Pa Pang hamlet and access road to resettlement area. Site clearance for the remaining resettled hamlets has not implemented due to uncompleted approval of the compensation and assistance option. Table 4: Site clearance progress under SB4HP No. Items Progress 1 Access road to Parum B and Pa Rum A RSs Completed 2 Access road to Pa Pang RS Completed 3 Access road to Padhi RS Completed 4 Pa Pang RS Completed 5 Hamlet No. 2 RS Completed 6 Reservoir in Hamlet No. 2 Completed 7 Administrative Quarter of Zuoih commune Completed 8 PaDhi RS and its reservoir Compensation and assistance option submitted 9 Reservoir in Pa Rum B hamlet Compensation and assistance option submitted 10 Pa Rum A, B RS and Pa Rum A Reservoir Source: SB4HPMB, 12/2011. Compensation and assistance option submitted VICA Consultants Ltd., Page 14

20 67. Beside advantages of resettlement, there are some difficulties due to lagging behind the approved project schedule: recovery of forest products within the clearance sites could not be completed on schedule due to prolonged duration, and coincide with the rainy season in central region, which delayed the overall progress; inventory and identification of sold status also met some difficulties due to large area; some AHs were confused about inventory of assets that were required to be re-carried out; there are some difficulties in change in land using due to the prolonged duration in terms of approval, review and limited capacity of local staff. 68. In general, there were no problems in implementation of resettlement thanks to the agreement among stakeholders. At the time of monitoring, in all cleared sites, construction works were carried out as scheduled. IV.6. Resettlement Sites Construction 69. Resettlement sites were constructed to relocate 04 hamlets of 02 communes to another sites replacing flooded hamlets of PaDhi, Pa Rum A, Pa Rum B hamlets in Zuoih commune; hamlet 2 of Ta Poo commune 4. Despite the adjustment in administrative border, 04 resettlement sites in communes of Zuoih and Ta Poo in Nam Giang district remain to be constructed under the project. 70. It is expected to construct the Zuoih administrative office in Cong Dong hamlet and 3 RSs in the commune, including: PaDhi RS with 63 households; Parum A RS with 44 households; Parum B RS with 64 households; 71. Pa Pang RS (Ta Poo commune) for 53 resettled HHs from former Hamlet No. 2 is being constructed under the project. 72. In resettlement sites, expected cultivation land area to be allocated to RHs include: (i) 400m 2 of residential land; (ii) 600m 2 of garden land; (iii) agricultural production land: 1.5 ha of terrain land and about 8-10ha of agro-forestry land (forest land allocated for hamlet community). Besides, it was estimated that the rice cultivation land area in project hamlets will be reclaimed with a total of about 24 ha, of which, Pa Pang hamlet has about 12ha, Pa Rum A and Hamlet No. 2 have about 4ha and 7ha respectively. 73. RS construction plan was prepared upon the agreement with AHs and prescribed in the updated REMDP Vol1 and Vol2, which was also the legal basis for PMU s compliance and implementation. 74. The construction progress of resettlement sites can be summarized as follows: PaPang resettlement site for households in hamlet 2: Compensation payment for AHs had been completed since December The landmark in Pa Pang resettlement site had been completed with participation of AHs, SB4HPMB and JFPR Consultants (CHF). The option of handing-over forest land access rights to AHs in Hamlet No. 2 was approved by Nam Giang DPC in September At the moment, this option had been approved by ADB s officer and updated into REMDP Vol2. The actual handover is expected to be implemented in 8/2011. By the monitoring time, the contractor had commenced the construction works since April Currently, base road for production activities, construction of foundation and dam, and backfilling of inter-hamlet road and bridge have been done. Water supply system installation is being implemented. In 4 Decree No. 03/NQ-CP dated 10/01/2011 by the Government on adjustment to communal administrative border, establishment of Nam Giang (commune/district), Quang Nam. VICA Consultants Ltd., Page 15

21 addition, the contractors have constructed public works, wet-rice reclamation and water supply system for production activities. During July 2011, milpa land was handed over to AHs in Hamlet 2 and Pa Pang. Currently, the house foundations have been handed over to AHs to build houses. Most of them have completed the main structures of the houses and their houses are being completed. ParumA, ParumB and PaDhi resettlement sites: Landmarking had been completed with participation of local people, SB4HPMB's staff, JFPR Consultant (CHF). By the time of monitoring, resettlement site designs had been completed and disclosed to AHs since 2/2011. Procurement of RS construction was carried out in 12/2011. At present, contractor selection is being carried out and the construction activities will start in the first quarter of Photo 4: Some photos on Pa Pang RS of Hamlet No.2, Ta Poo commune, Nam Giang, Quang Nam Source: IMC, December The option on handing-over forest land access rights to the community in resettlement sites had been approved by Nam Giang DPC since early September 2010, endorsed by ADB s officer and updated into REMDP Vol 2. The landmarking to hand over to local community in RSs was carried out in 8/ In the meeting with IMC on 21/12/2011, PMU confirmed that RS construction progress would be in line with the approved progress agreed by PMU and ADB Missions during the missions from 29/11/2010 to 13/12/2010; the mission from 03/03/2011 to 14/03/2011 and the latest mission from 13/12/2011 to 16/12/2011 based on the adjusted plan. The adjusted plan for RS construction progress is presented in the following table: Table 5: Revised resettlement sites construction plan agreed among project stakeholders 1. Pa Pang resettlement site Items - Proceed compensation and assistance for site clearance: residential area construction, public works, and production land for Pa Pang hamlet. Starting date Timeline Completion date 15/12/ /12/ Screen bomb/mine in the whole project area. 04/09/ /10/ Bid/Procure and award construction contracts. 15/12/ /03/ Implement construction execution. 20/03/ /05/ : Abbreviation for 2010, similar for years VICA Consultants Ltd., Page 16

VIE: Song Bung 4 Hydropower Project

VIE: Song Bung 4 Hydropower Project Social Monitoring Report Semestral Report January 2011 VIE: Song Bung 4 Hydropower Project Prepared by Song Bung 4 Hydropower Project Management Board (SB4HPMB) for the Asian Development Bank. SONG BUNG

More information

VIE: Song Bung 4 Hydropower Project

VIE: Song Bung 4 Hydropower Project Social Monitoring Report Final Report July 2015 VIE: Song Bung 4 Hydropower Project Prepared by Song Bung 4 Hydropower Project Management Board (SB4HPMB) for the Vietnam Electricity and the Asian Development

More information

Resettlement Due Diligence Report

Resettlement Due Diligence Report Resettlement Due Diligence Report August 2015 VIE: Power Transmission Investment Program, Tranche 2-500kV Pleiku-My Phuoc-Cau Bong Transmission Line Binh Phuoc Province Prepared by Central Vietnam Power

More information

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject Social Monitoring Report Corrective Action Plan September 2013 Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject Prepared by the Department of Agriculture

More information

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN Project Number: Loan 2225-VIE September 2013 VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE Prepared

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT DUE DILIGENCE REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant 11 th Independent Monitoring Report November 2014 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Resettlement Monitoring Report March 2014 VIE: Northern Power Transmission Expansion Sector Project Prepared by the Local Implementation Consultant (LIC) Social for Viet Nam Electricity (EVN) Northern

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Improving grid medium, low voltage NORTH POWER COORATION Electric Network

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

Resettlement and Ethnic Minorities Monitoring Report

Resettlement and Ethnic Minorities Monitoring Report Resettlement and Ethnic Minorities Monitoring Report Semi-annual Report August 2013 Viet Nam: Sustainable Rural Infrastructure Development Project in Northern Mountain Provinces Subprojects in Dien Bien,

More information

VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project

VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project Social Monitoring Report 2nd Semi-annual Report January 2018 VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project Prepared by Development Research and Consultancy Centre

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

Viet Nam: University of Science and Technology of Hanoi (New Model University) Project

Viet Nam: University of Science and Technology of Hanoi (New Model University) Project Social Monitoring Report Quarterly Report December 2017 Viet Nam: University of Science and Technology of Hanoi (New Model University) Project Prepared by the Viet Nam Academy of Science and Technology

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

ABBREVIATED RESETTLEMENT ACTION PLAN

ABBREVIATED RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project: Irrigated Agriculture Improvement (IAIP) Subproject 1, Hoa Binh province SOCIALIST

More information

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Yen Vien-Lao Cai Railway Upgrading Project Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project External Monitoring Report on RP Implementation Yen Bai Province Prepared by Railway Projects Management

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT PLAN Project Number: 46391-001 December 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

Vietnam: GMS Sustainable Tourism Development Project

Vietnam: GMS Sustainable Tourism Development Project December 2010 Vietnam: GMS Sustainable Tourism Development Project Prepared by Quang Binh Provincial Implementation Unit for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 17 August 2010) Currency

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized PEOPLE S COMMITTEE OF PHU YEN PROVINCE PHU YEN PROJECT MANAGEMENT UNIT OF CONSTRUCTION INVESTMENT WORKS FOR AGRICULTURE AND RURAL DEVELOPMENT ----------------o0oo---------------

More information

Resettlement and Ethnic Minority Development Framework (REMDF)

Resettlement and Ethnic Minority Development Framework (REMDF) Resettlement and Ethnic Minority Development Framework (REMDF) Stage of the document: FINAL Project number: 49026-002 April 2017 VIE: Basic Infrastructure for Inclusive Growth in the Northeastern Provinces

More information

VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT

VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT Resettlement Framework February 2012 VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT Prepared by the Ministry of Agriculture and Rural Development (MARD), Socialist

More information

Internal Monitoring Report. VIE: Second Greater Mekong Subregion Corridor Towns Development Project. Semestral Report (From July to December 2017)

Internal Monitoring Report. VIE: Second Greater Mekong Subregion Corridor Towns Development Project. Semestral Report (From July to December 2017) Internal Monitoring Report Semestral Report (From July to December 2017) VIE: Second Greater Mekong Subregion Corridor Towns Development Project Prepared by: PMUs Bac Giang, Lao Cai and Mong Cai for Asian

More information

Socialist Republic of Viet Nam: Second Greater Mekong Subregion Corridor Towns Development Project. Bac Giang Subproject

Socialist Republic of Viet Nam: Second Greater Mekong Subregion Corridor Towns Development Project. Bac Giang Subproject Resettlement Plan June 2015 Socialist Republic of Viet Nam: Second Greater Mekong Subregion Corridor Towns Development Project Bac Giang Subproject Prepared by Bac Giang Provincial People s Committee for

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant Resettlement Monitoring Report Quarterly Report July September 2013 VIE: Mong Duong 1 Thermal Power Plant Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1. Internal

More information

VIE: Mong Duong 1 Thermal Power Project

VIE: Mong Duong 1 Thermal Power Project Social Monitoring Report Final Independent Monitoring Report December 2017 VIE: Mong Duong 1 Thermal Power Project Prepared by the Development and Research & Consultancy Centre for Vietnam Electricity

More information

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft)

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft) Public Disclosure Authorized VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY FRAMEWORK (Final Draft) Table of Contents

More information

Resettlement and Ethnic Minority Development Plan (REMDP)

Resettlement and Ethnic Minority Development Plan (REMDP) Resettlement and Ethnic Minority Development Plan (REMDP) Stage of the document: Final Project number: 49026-002 April 2017 VIE: Basic Infrastructure for Inclusive Growth in the Northeastern Provinces

More information

VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Project (GMS1)

VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Project (GMS1) Resettlement Monitoring Report #1 Semestral Report August 2015 VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Prepared by Vietnam Water, Sanitation and Environment joint

More information

Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject

Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject Resettlement Monitoring Report Annual Report October 2012 Viet Nam: Central Region Small and Medium Towns Development Cam Ranh (Khanh Hoa) Subproject Prepared by the InvestConsult Group for the Provincial

More information

Income and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development

Income and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Income and Livelihood Restoration Plan Income and Livelihood Restoration Plan Document Stage: Final Project Number: 41013 June 2013 Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Prepared

More information

Key Words: Song Hinh Multipurpose Project, Resettlement, Project Management Board

Key Words: Song Hinh Multipurpose Project, Resettlement, Project Management Board IEA Hydropower Implementing Agreement Annex VIII Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 07-02: Resettlement Song Hinh Multipurpose Project, Vietnam Key Issues:

More information

Subproject: Hai Lang Province: Quang Tri

Subproject: Hai Lang Province: Quang Tri Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP299 vol. 4 Ministry of Agriculture and Rural Development The World Bank Natural Disaster

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Social Monitoring Report Semi-Annual Report January-June 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam Power Projects

More information

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT (Loan No. 5233-VN) SFG1981 V2 RESETTLEMENT PLAN Public Disclosure

More information

Gender Equality and Development

Gender Equality and Development Overview Gender Equality and Development Welcome to Topic 3 of the e-module on Gender and Energy. We have already discussed how increased access to electricity improves men s and women s lives. Topic Three

More information

VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section

VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section Social Due Diligence Report Document Stage: Second Draft Project Number: 40080 May 2013 VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section Prepared by Hanoi Metro Railway Board for

More information

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

Resettlement and Income Restoration in Thilawa SEZ

Resettlement and Income Restoration in Thilawa SEZ Resettlement and Income Restoration in Thilawa SEZ Lessons from the first & second phases and emerging good practices Thilawa SEZ Management Committee (TSMC) Yangon Region Government (YRG) 20 February

More information

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ------------------------------------------------------------------ SFG1163 V11 Public Disclosure Authorized Public

More information

VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing

VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing Resettlement Plan March 2017 VIE: INTEGRATED RURAL DEVELOPMENT SECTOR PROJECT IN CENTRAL PROVINCES - Additional Financing Subproject: Upgrading Dai Giang River Dike system, Thua Thien Hue province Prepared

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project

VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Resettlement Plan Updated Resettlement Plan for Nghi Xuyen pumping station Sub-project October 2012 VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project Prepared by CPMO for

More information

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT CAN THO CITY PEOPLE S COMMITTEE CONSTRUCTION & INVESTMENT MANAGEMENT UNIT USING OFFICIAL DEVELOPMENT ASSISTANCE (ODA), CAN THO CITY ***** SFG1562 REV RESETTLEMENT POLICY FRAMEWORK FOR CAN THO URBAN DEVELOPMENT

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the CENTRAL

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province) Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Dak Nong Province) Prepared by Central Vietnam Power Projects

More information

VIE: GMS Ben Luc - Long Thanh Expressway

VIE: GMS Ben Luc - Long Thanh Expressway Social Monitoring Report Inception Report May 2013 VIE: GMS Ben Luc - Long Thanh Expressway Prepared by Thanglong Infrastructure Development for Vietnam Expressway Corporation and the Asian Development

More information

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project Resettlement Plan July 2015 Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF THANH TRACH COMMUNE, BO TRACH DISTRICT, QUANG BINH PROVINCE Prepared

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Plan December 2013 Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (EVN HANOI: 110 kv Noi Bai Airport Substation and Associated 110 kv Transmission Line) Prepared

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

Viet Nam: Central Region Urban Environmental Improvement Project

Viet Nam: Central Region Urban Environmental Improvement Project Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 34355 June 2008 Viet Nam: Central Region Urban Environmental Improvement Project Prepared by Project Coordination

More information

Decree on Compensation and Resettlement Management in Development Projects

Decree on Compensation and Resettlement Management in Development Projects Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity The Government No. 84 Vientiane Capital, Date: 05 / 04 / 2016 Decree on Compensation and Resettlement Management in Development

More information

VIE: Phuoc Hoa Water Resources Project

VIE: Phuoc Hoa Water Resources Project Resettlement Plan Sept 212 VIE: Phuoc Hoa Water Resources Project Component: Duc Hoa main canal Cu Chi section Prepared by Project Management Unit for Investment and Construction of Cu Chi District for

More information

VIE: Phuoc Hoa Water Resources Project

VIE: Phuoc Hoa Water Resources Project Resettlement Plan Loan: 2025/2747 Document stage: updated Dec 2013 VIE: Phuoc Hoa Water Resources Project Component: Tan Bien Irrigation Area Five drainage canals in Chau Thanh District, Tay Ninh Province

More information

VIE: Central Mekong Delta Region Connectivity Project

VIE: Central Mekong Delta Region Connectivity Project Social Monitoring Report Quarterly Report No. 3 April 2014 VIE: Central Mekong Delta Region Connectivity Project Prepared by Joint Venture: CDM Smith, Inc., WSP Finland Limited & Yooshin Engineering Corporation

More information

Viet Nam: Water Sector Investment Program Tranche 3. Constructing New Water Treatment Plant, Phuc Triu Commune, Thai Nguyen City, Thai Nguyen Province

Viet Nam: Water Sector Investment Program Tranche 3. Constructing New Water Treatment Plant, Phuc Triu Commune, Thai Nguyen City, Thai Nguyen Province Resettlement Plan Resettlement Plan Document Stage: Revised Project Number: 41456-043 January 2019 Viet Nam: Water Sector Investment Program Tranche 3 Constructing New Water Treatment Plant, Phuc Triu

More information

RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1

RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1 RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1 Prepared for: CLRP-AF Project Monitoring Unit, Ministry of Environment and Spatial Planning Prepared by: replan Inc.

More information

ABBREVIATED RESETTLEMENT PLAN

ABBREVIATED RESETTLEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF CONSTRUCTION ADMINISTRATION OF TECHNICAL INFRASTRUCTURE MANAGEMENT BOARD

More information

VIE: Greater Mekong Subregion Southern Coastal Corridor

VIE: Greater Mekong Subregion Southern Coastal Corridor Resettlement Plan March 2012 VIE: Greater Mekong Subregion Southern Coastal Corridor Updated Resettlement Plan of Xa Xia Ha Tien Section Prepared by Cuu Long Corporation for Investment, Development and

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project Internal Monitoring Report 37231-023 March 2016 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein do not

More information

Resettlement and Ethnic Minority Development Plan

Resettlement and Ethnic Minority Development Plan Resettlement and Ethnic Minority Development Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang

More information

Key Issues: Climate Zone: As: Tropical humid. Subjects: - Restoration of livelihood and Rebuilding of Resettled Communities

Key Issues: Climate Zone: As: Tropical humid. Subjects: - Restoration of livelihood and Rebuilding of Resettled Communities IEA Hydropower Implementing Agreement Annex VIII Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 07-01: Resettlement - Chiew Larn Multipurpose Project, Thailand Key

More information

Resettlement Plan. Stage of the document: Final Project number: June 2017

Resettlement Plan. Stage of the document: Final Project number: June 2017 1 Resettlement Plan Stage of the document: Final Project number: 49026-003 June 2017 VIE: Basic Infrastructure for Inclusive Growth in Nghe An, Ha Tinh, Quang Binh and Quang Tri Provinces Sector Project-Water

More information

Resettlement Plan. September 2016

Resettlement Plan. September 2016 Resettlement Plan September 2016 VIE: GMS Flood and Drought Risk Management and Mitigation Project - Upgrading and Rehabilitation of Four Primary Canals in Plain of Reeds, Dong Thap Province - Cai Cai

More information

Resettlement and Ethnic Minority Development Plan (REMDP)

Resettlement and Ethnic Minority Development Plan (REMDP) Resettlement and Ethnic Minority Development Plan (REMDP) Stage of the document: Final Project number: 49026-002 April 2017 VIE: Basic Infrastructure for Inclusive Growth in the Northeastern Provinces

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

Due Diligence Report and Corrective Action Plan. VIE: Productive Rural Infrastructure Sector Project in the Central Highlands Provinces

Due Diligence Report and Corrective Action Plan. VIE: Productive Rural Infrastructure Sector Project in the Central Highlands Provinces Due Diligence Report and Corrective Action Plan Document stage: final Project Number: 40238 November 2017 VIE: Productive Rural Infrastructure Sector Project in the Central Highlands Provinces Subproject:

More information

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Yen Vien-Lao Cai Railway Upgrading Project Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project Resettlement Monitoring Report Prepared by Railway Projects Management Unit of Viet Nam Railway for

More information

Tenke Fungurume Mining An affiliate of Freeport-McMoRan Copper & Gold

Tenke Fungurume Mining An affiliate of Freeport-McMoRan Copper & Gold Tenke Fungurume Mining An affiliate of Freeport-McMoRan Copper & Gold Tenke Fungurume Mining (TFM), an affiliate of Freeport-McMoRan Copper & Gold, is the largest private foreign investment in the DRC,

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Resettlement Monitoring Report June 2013 VIE: Northern Power Transmission Expansion Sector Project Subprojects: 1) 500kV Hiep Hoa substation 2) 500kV Son La- Hiep Hoa Transmission Line 3) 220 kv Thuong

More information

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section)

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Safeguards Monitoring Report External Social Safeguards Monitoring Report October 2017 VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Prepared by External Resettlement Monitor

More information

SFG1095 V4 SUBPROJECT: Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

SFG1095 V4 SUBPROJECT: Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized SFG1095 V4 Public Disclosure Authorized SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Binh Dinh, May 2015 SUBPROJECT: PROJECT OWNER THE CONSULTANT Binh

More information

PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY

PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY SFG2836 V2 REV SCALING UP URBAN UPGRADING PROJECT SUBPROJECT OF BEN TRE CITY, BEN TRE PROVINCE RESETTLEMENT PLAN (Final Version)

More information

Vulnerability of livelihoods in flood-prone areas: A case study in Kandal of Cambodia and An Giang of Vietnam

Vulnerability of livelihoods in flood-prone areas: A case study in Kandal of Cambodia and An Giang of Vietnam Vulnerability of livelihoods in flood-prone areas: A case study in Kandal of Cambodia and An Giang of Vietnam Nguyen Duy Can¹, S. Sophat² and S. Khom³ ¹ Cantho University, Vietnam ² Royal University of

More information

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project Resettlement Plan September 2015 Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF THACH BANG-THACH KIM-THINH LOC COMMUNES LOC HA DISTRICT, HA TINH

More information

Article 2These Regulations apply to the residents-resettlement for the Three Gorges Project construction.

Article 2These Regulations apply to the residents-resettlement for the Three Gorges Project construction. Regulations on Residents-Resettlement for the Yangtze River Three Gorges Project Construction (Adopted at the 35th Executive Meeting of the State Council on February 15, 2001, promulgated by Decree No.

More information

Guidance Note 5 Land Acquisition and Involuntary Resettlement

Guidance Note 5 Land Acquisition and Involuntary Resettlement This Guidance Note 5 corresponds to Performance Standard 5. Please also refer to the Performance Standards 1-4 and 6-8 as well as the corresponding Guidance Notes for additional information. Bibliographical

More information

THE GOVERNMENT SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom - Happiness No. 164/2013/ND-CP Hanoi, November 12, 2013 DECREE

THE GOVERNMENT SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom - Happiness No. 164/2013/ND-CP Hanoi, November 12, 2013 DECREE THE GOVERNMENT SOCIALIST REPUBLIC OF VIET NAM ------- Independence - Freedom - Happiness ---------- No. 164/2013/ND-CP Hanoi, November 12, 2013 DECREE AMENDING AND SUPPLEMENTING A NUMBER OF ARTICLES OF

More information

FINAL ETHNIC MINORITY POLICY FRAMEWORK

FINAL ETHNIC MINORITY POLICY FRAMEWORK SOCIALIST REPUBLIC OF VIETNAM Independence Freedom Happiness ******** SFG2829 REV FINAL ETHNIC MINORITY POLICY FRAMEWORK SCALING-UP URBAN UPGRADING PROJECT PROJECT S LOCATION BEN TRE (BEN TRE PROVINCE),

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

Viet Nam: Secondary Cities Development Project. Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province

Viet Nam: Secondary Cities Development Project. Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province Resettlement Plan Resettlement Plan Document Stage: Revised Project Number: 45198 June 2016 Viet Nam: Secondary Cities Development Project Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province

More information

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

Social Monitoring Report

Social Monitoring Report Social Monitoring Report #4 Report November GMS: Kunming-Hai Phong Transport Corridor - Noi Bai - Lao Cai Highway Project Vinh Phuc Province Prepared by Scientific Technological Center and Environment

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Cao Bang Province Prepared by the Ministry of Education

More information

ABBREVIATED RESETTLEMENT ACTION PLAN

ABBREVIATED RESETTLEMENT ACTION PLAN Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT ==================== Public Disclosure Authorized Mekong Delta Integrated Climate Resilience and

More information

RESETTLEMENT POLICY FRAMEWORK

RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM HO CHI MlNH CITY'S INFRASTRUCTURE DEVELOPMENT FUND ********

More information

External Resettlement Monitoring Report

External Resettlement Monitoring Report External Resettlement Monitoring Report Semi-annual Report Mission 3 October, 2013 VIE - STRENGTHENING WATER MANAGEMENT AND IRRIGATION SYSTEMS REHABILITATION PROJECT Subproject: The Water Resources University

More information