ORDER (Date of Hearing : 23 rd November, 2010) (Date of Order : 24 th November, 2010)

Similar documents
ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012)

M/s. BLA Power Pvt. Ltd. - Petitioner. 4. M. P. Madhya Kshetra Vidyut Vitaran Co. Ltd., Bhopal -Respondents

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL

MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL. ORDER (Date of Order : 7 th September, 2012)

BIHAR ELECTRICITY REGULATORY COMMISSION

3. M. P. Poorv Kshetra Vidyut Vitaran Co. Ltd. - Respondents Shakti Bhawan, Rampur, Jabalpur

Before the Madhya Pradesh Electricity Regulatory Commission, Bhopal

Case No. 02 of Shri V. P. Raja, Chairman Shri S. B. Kulkarni, Member Shri V. L. Sonavane, Member

The Conditions of distribution license for distribution licensee (including deemed licensee), 2004

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

Order on. Petition No. 58/2013

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. Investigate and to take appropriate action against M/s Torrent and further to cancel the

Order on. Petition No. 38/2013

In the matter of: M/s Rauzagaon Chini Mills (A unit of Balrampur Chini Mills Ltd.) Rauzagaon , District Barabanki (U.P.

Sub: In the matter of representation in compliance to the directions of Hon ble High Court, Jabalpur in Writ Petition no.

Bhopal dated 6th August, 2004

ORDER (Hearing on & )

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH. Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh, Member

Respondents. Present in the Hearing: Respondents

MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL ORDER

THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW

Bhopal, Dated: 23rd July, 2004

Case No.83 of In the matter of Petition under Section 67 of the E.A, 2003 seeking directions upon MSETCL in regard to erection of Tower.

SEVENTH AMENDMENT TO MADHYA PRADESH ELECTRICITY SUPPLY CODE, 2004

Case No. 94 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member

NEW DELHI. Shri M. Deena. to the National Load Despatch e Energy Certificates to

BEFRE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA.

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA

Case No. 68 of Coram. Shri. I. M. Bohari, Member Shri. Mukesh Khullar, Member. M/s RattanIndia Nasik Power Ltd.

MPERC (Procedure of Application for License) REGULATIONS, 2004.

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR **** **** ****

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Notice dated U/s130 of Electricity Act2003.

Case No. 295 of Coram. Anand B. Kulkarni, Chairperson Mukesh Khullar, Member. Adani Power Maharashtra Limited (APML)

ORDER OF THE GRIEVANCE REDRESSAL AUTHORITY, MADHYA PRADESH ORDER OF 11 SEPTEMBER 2004

BEFORE THE H.P. ELECTRICITY REGULATORY COMMISSION AT SHIMLA

THE POPULATION CONTROL BILL, 2016

Case No.139 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW

POWER PURCHASE AGREEMENT FOR WIND ELECTRIC GENERATORS (For sale to Distribution Licensee only)

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

CASE No. 156 of In the matter of

THE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO)

Petition No 973 of 2014 and 1036,1037,1038,1039 &1040 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

SEVENTEENTH AMENDMENT TO MADHYA PRADESH ELECTRICITY SUPPLY CODE, 2004.

Executive Summary Case No 140 of 2017

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

Sri. Alex Soharab. V.F, M/s. Southern Engineering Corporation, V/830-A, Development Area, Edayar, Muppathadom , Aluva.

Case No. 17 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Reliance Infrastructure Ltd., Santacruz (E).

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA NOTIFICATION Shimla, the 21 st September, 2015

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH, BHOPAL. Original Application No. 27/2014 (CZ)

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS OF 2017 M/S LION ENGINEERING CONSULTANTS VERSUS O R D E R

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 211/MP/2012

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai

IN THE SUPREME COURT OF INDIA CRIMINAL APPELLATE JURISDICTION. CRIMINAL APPEAL NO. 171 of 2019 (arising out of SLP (Crl.) No.

ORDER Dated: 11 th August, 2004

CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015

KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION

Case No.3 of Shri P.Subrahmanyam, Chairman Shri Venkat Chary, Member, Shri Jayant Deo, Member.

Draft JSERC (Terms and Conditions for Intra State Open Access) Regulations, 2016

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION NOTIFICATION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2014

Distribution List (WRLDC Letter No. WRLDC/MO/RPS/PG-EPMPL/2018) 1. Executive Director, POWER GRID WRTS-1 2. Executive Director, POWER GRID WRTS-2 3.

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA

M/s. Heer Enterprises - Applicant

Petition No 768 of 2011 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Date of Order :

Case No. 22 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 119/MP/2013. Date of Hearing: Date of Order :

2. Chief Engineer (PPA) UP Power Corporation Limited 14 th Floor, Shakti Bhawan Ext. 14 Ashok Marg, Lucknow.Respondent

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL. Original Application No. 264/2014 (THC) (CZ)

THE NATIONAL SOLAR ENERGY AUTHORITY BILL, 2012

THE NATIONAL FLOOD CONTROL AND REHABILITATION AUTHORITY BILL, 2010

Sangeeta Verma Secretary. No. Secy/ UPERC/Supply Code/ Lucknow: Dated Sir,

M.P. POORV KSHETRA VIDYUT VITRAN COMPANY LIMITD Block No. 7 Shakti Bhawan, Rampur, Jabalpur Phone No , Fax No.

Draft Supplementary Power Purchase Agreement

क द र य व द य त न य मक आय ग CENTRAL ELECTRICITY REGULATORY COMMISSION नई द ल ऱ NEW DELHI

National Electric Power Regulatory Authority Islamic Republic of Pakistan

ELECTRICITY GENERATION LICENCE GRANTED TO INSERT NAME HERE INSERT GEN REF NUMBER HERE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION SPECIAL LEAVE PETITION (CIVIL) NO OF G. Sundarrajan.

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

Case No. 61 of In the matter of. Petition of Wardha Power Company Ltd. for Review of Order dated 17 January, 2014 in Case No.

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL. Original Application No. 129/2013 (CZ)

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

REQUEST FOR PROPOSAL

NIGERIAN ELECTRICITY REGULATORY COMMISSION REGULATIONS FOR EMBEDDED GENERATION 2012

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL. Misc. Application No. 557/2014 and Original Application No. 118/2014 (THC) (CZ)

THE PLAY SCHOOLS (REGULATION) BILL, 2015

CASE No. 337 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member ORDER

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR INJUNCTION Date of Judgment: RSA No.55/2009 & CM No.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE Date of Judgment: FAO (OS) 298/2010

Case No. 2 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : DELHI WATER BOARD ACT, Date of decision: 4th February, 2011.

MYT PETITION FOR THIRD CONTROL PERIOD FY TO FY

Please read the following instructions carefully before you proceed to execute the Service Agreement-cum-Surety Bond:

M/s. Neelsidhi Developers - Complainant The Emerald, 2 nd floor, Plot No. 195 B, Besides, Neelsidhi Towers, Sector -12, Vashi, Navi Mumbai

Transcription:

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION, BHOPAL Sub : In the matter of petition for approval of cost sharing scheme by prospective EHT ORDER (Date of Hearing : 23 rd November, 2010) (Date of Order : 24 th November, 2010) Petition No. 68/2010 MP Power Transmission Co. Ltd., - Petitioner No.1 Block No.2, Shakti Bhawan, Vidyut Nagar, Jabalpur (MP). MP Poorv Kshetra Vidyut Vitaran Co. Ltd., - Petitioner No.2 Block No.7, Shakti Bhawan, Vidyut Nagar, Jabalpur (MP) V/s M/s Reliance Cementation (P) Ltd., - Respondent No. 1 Maihar. M/s KJS Cement Ltd., - Respondent No. 2 Maihar Shri D.P. Saxena, Consultant, Shri V.D Souza, EE and, Shri Sanjay Okhade, EE appeared on behalf the Petitioners. 2. The petition is in the matter of approval of cost sharing scheme by prospective EHT consumers for conversion of 132 KV Substation to 220 KV Substation Maihar under the provisions of Section 43 and 46 of the Electricity Act, 2003 and under the principles laid down in the Madhya Pradesh Electricity Regulatory Commission (Recovery of Expenses and other charges for providing electric line or plant used for the purpose of giving supply) (Revision-I) Regulations, 2009 {RG- 31(I) of 2009}. The case was listed for motion hearing on 26.10.2010. 3. During the motion hearing, the representatives of Petitioner No. 1 and 2 have submitted that Respondent No. 1 (M/s Reliance Cementation (P) Ltd., Maihar) has proposed to setup a 5.08 MTPA Cement Plant at Village Bharauli Tehsil Maihar, District Satna for which request was made for sanction of 30 MVA load at 132 KV. The sanction was accorded and conveyed vide letter No. 1670 dated 16.02.2010. The supply was proposed to be catered by laying a 132 KV DCSS line from 220 KV substation, Katni up to consumer plant for a route length of about 50 KM. The tentative cost of the work was estimated to around 18.5 Crores. Respondent No. 2 (M/s KJS Cement Ltd.) has also proposed to setup a 1.50 MTPA Clinker, OPC/PPC 2.25 MTPS Cement

Plant at Village Amlai, Tehsil Maihar District Satna for which request was made for sanction of 10 MVA load at 132 KV. The sanction was accorded and conveyed vide letter no. 1705 dated 24.02.2010. The supply was proposed to be catered by laying a 132 KV DCSS line from 220 KV substation, Kotar (under construction) or Katni for a route length of about 60 KM. The tentative cost of the work was estimated to be around 20 Crores. 4. The Petitioners have submitted that since the extension of 132 KV line from 220 KV substations, Katni or Kotar involves long patches of forest land, work of laying 132 KV line was likely to be delayed, hence, Respondents requested for an alternate supply arrangement. Thereafter, discussions were held between the parties on 20 th May, 2010 at Jabalpur, wherein it was agreed that: (c) 132 KV Maihar substation can be converted to 220 KV substation so that 132 KV supply to both the consumers could be provided from 220 KV Maihar substation. The total cost of conversion of 132 KV Maihar substation into 220 KV Maihar substation was worked out by the MPPTCL (Petitioner no. 1) as The cost of 220 KV line and other costs will be borne by MPPTCL. 20.02 Crores. (d) Petitioners would share the cost of conversion which is 20.00 Crores on 50:50 (e) ratio because basically this work will be solely organized for them. Their final contribution for the purpose of conversion of substation would therefore be 10.00 Crores each. It was also agreed that the payment shall be made in the following manner: (i) 1 st installment by 30 th June, 2010-4.00 Crores (ii) 2 nd installment on erection of 220 kv bays - 3.00 Crores (iii) 3 rd installment on installation of 220 kv - 3.00 Crores Transformer on plinth 5. As per the Petitioners, the proposal to convert the existing 132 KV to 220 KV was considered primarily to cater to 40 MVA load of the Respondents. The proposal for conversion is also economically viable, as, it is costing 27 Crores whereas cost to construct 132 KV line comes out to be 38 Crores. 6. The Petitioners have further submitted that, the Respondents have requested that in case any additional consumer asks for power supply from the same substation i.e. converted 220 KV

Substation Maihar subsequently, then the management should recover the cost from them also. Their request was considered in the meeting held on 22.6.2010, and it was agreed that: (c) In case any new EHT consumers(s) comes up within an initial period of 10 years from the date of commissioning of 220 kv Substation Maihar, then he will be insisted upon to contribute towards the cost of conversion. While insisting for contribution, the cost of conversion will be divided into (existing + one) parts and the contribution received from the new party will be distributed to the existing contributors equally. Further, if a fourth EHT consumer also avails power from the converted 220 kv substation, shall pay 5.00 Crores, which shall be distributed to the existing three consumers. This process will go on with any new consumer till expiry of basic 10 years period. It was agreed that a petition on the above lines would be filed with MPERC and that this arrangement is not obligatory for the purpose of above agreement amongst parties. 7. The Petitioners have also submitted that the Respondents have already paid 4.0 Crores each as 1 st installment with a stipulation that the future new EHT consumers if supplied through 220 KV Substation Maihar may also share the cost of conversion which they have borne initially. 8. The Petitioners have also submitted that presently, under the aforesaid Regulation, the prospective EHT consumers coming up in the same area are not required to share the cost of conversion of EHV substation, even if it is a cost effective alternative. 9. The Petitioners further submitted that the Respondents have requested that a period of ten years may be considered for implementation of the proposed cost sharing scheme. So far no other requisition from EHT consumers in the area has been received and in the near future possibility of any new entrants of EHT consumers in the area is remote, therefore, the request of the respondents for period of 10 years from the date of commissioning of 220 KV Substation Maihar may be considered. Period of 10 years also matches with the standard terms of financing of transmission assets and is without any indexation of depreciation factor. 10. During the hearing, the Commission enquired from the Petitioners regarding the cost involved in respect of 220 KV line to be connected to the proposed 132/220 KV Substation which

is proposed to be borne by Petitioner No.1. The representative of Petitioner No.1 submitted that an amount of 1.6 Crores (approx.) shall be incurred by them. The Commission also enquired of the Petitioners as to under what provisions of the Act, the Commission has powers to deal with the subject petition. The representatives of the Petitioners submitted that the petition is filed for approval of cost sharing scheme under provisions of Section 43 and 46 of the Electricity Act, 2003 and under the MPERC (Recovery of Expenses and other charges for providing electric line or plant used for the purpose of giving supply) (Revision-I) Regulations, 2009. The Commission then drew attention to Chapter-III Point No. ix, as per which the entire distribution network including Service Line, notwithstanding the cost has been paid by the consumer, shall be the property of the Distribution Licensee for all purpose and shall be maintained by it. The Distribution Licensee shall have a right to use the network for supplying energy to any other person by tapping the network or otherwise except in cases where such supply is detrimental to the supply to the consumer who had borne the full cost of such network and is connected therewith. As such, there is no provision in the Regulations for cost sharing by consumers. 11. During the hearing, the representatives of the Petitioners could not justify as to why the Petitioner No.1 is incurring expenditure on 220 KV line. They could also not indicate as to how the total cost has been arrived at 27 Crore out of which 20 Crore is being funded by the prospective consumers. The representatives of the Petitioners, however, submitted that the Commission may allow relaxation in MPERC (Recovery of Expenses and other charges for providing electric line or plant used for the purpose of giving supply) (Revision-I) Regulations, 2009 and allow a modified petition. 12. The Commission granted the Petitioners request and directed it to submit modified petition clearly bringing out the relief sought within 15 days i.e. by 16.11.2010. The petition should also bring out the expected total expenditure for affording supply from the upgraded Maihar Sub-station. The next date of hearing was fixed as 23.11.2010. 13. The Petitioners submitted the revised petition on 22.11.2010. 14. During the hearing on 23.11.2010, the representative of the Petitioners submitted the facts of the case and prayed the Commission to : Take the revised petition for approval of including 220/132 KV Substation at

Maihar in Investment Plan with cost sharing of resources. 1.452 Crores under MPPTCL s Consider the scheme of cost sharing by subsequent EHV consumers for making provision in the Appropriate Regulations. 15. During the hearing, the Commission enquired from the Petitioners as to why MPPTCL wants to bear the cost of 1.452 Crores towards cost of removal of 132 KV Tower from the existing 132 KV yard, the cost of erection of additional 132 KV Towers, cost of modification of cable trenches & fencing and other activities as a part of system development. The Commission further enquired under which provision of the Regulations, the Commission could consider the scheme of cost sharing by subsequent EHV consumers, as proposed by the petitioners. The Commission also asked the Petitioners whether they are seeking modification in the existing Regulations. The representatives of the Petitioners submitted that they were seeking relaxation/deviation from the existing regulations. 16. After hearing the representatives of the Petitioners and considering the written submissions, the Commission noted that the prayer submitted in the revised petition cannot be allowed. The Commission however granted liberty to the Petitioner No. 1 to submit a comprehensive petition, making the three Distribution Licensees as Co-Petitioners, in case modifications in the Regulations were required. 17. In view of the above, the Petition No. 68 of 2010 stands disposed of. (C.S.Sharma) (K.K.Garg) (Rakesh Sahni) Member (Eco.) Member (Engg.) Chairman