MYT PETITION FOR THIRD CONTROL PERIOD FY TO FY
|
|
- Caitlin Horn
- 5 years ago
- Views:
Transcription
1 MYT PETITION FOR THIRD CONTROL PERIOD FY TO FY For Business Submitted to HIMACHAL PRADESH ELECTRICITY GULATORY COMMISSION, SHIMLA By HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED, SHIMLA
2 ABBVIATIONS AND ACRONYM LIST Sr. No Abbreviations Descriptions 1. A&G Administrative and General 2. AC Auxiliary Consumption 3. APR Annual Performance Review 4. ARR Aggregate Revenue Requirement 5. AS Accounting Standard 6. CAGR Compound Annual Growth Rate 7. CAPEX Capital Expenditure 8. CERC Central Electricity Regulatory Commission 9. CGS Central Generating Station 10. CoS Cost of Supply/ Service 11. CPPs Captive Power Plants 12. Crs Crores 13. CWIP Capital Work in Progress 14. DF Distribution Franchisee 15. Discom Distribution Companies 16. DPS Delayed Payment Surcharge 17. DS Domestic Service 18. DSM Demand Side Management 19. DTC Distribution Transformer 20. EA/The Act The Electricity Act F&A Finance & Accounts 22. FY Financial Year 23. GFA Gross Fixed Assets 24. G.O. Government Order 25. GoI Government of India 26. GoHP Government of Himachal Pradesh 27. HP Himachal Pradesh 28. HR Human Resource 29. HRA House Rent Allowance 30. HT High Tension 31. HEP Hydro Electric Power 32. IPP Independent Power Producers 33. KV Kilo Volt 34. kva Kilo Volt Ampere 35. kvah Kilo Volt Ampere Hour 36. kw Kilo Watt 37. kwh Kilo Watt Hour 38. LF Load Factor 39. LT Low Tension 40. MD Maximum Demand 41. MOD Merit Order Despatch 42. MoP Ministry of Power 43. MOU Memorandum of Understanding 44. MU Million Units (Million kwh) 45. MVA Mega Volt Ampere 46. MW Mega Watt Feb 2014 Page 1
3 Sr. No Abbreviations Descriptions 47. MYT Multi Year Tariff 48. NEP National Electricity Policy 49. NTP National Tariff Policy 50. NTPC National Thermal Power Corporation 51. O&M Operation & Maintenance 52. PAF Plant Availability Factor 53. PF Provident Fund 54. PFC Power finance Corporation 55. PLF Plant Load Factor 56. PLR Prime Lending Rate 57. PPA Power Purchase Agreement 58. PSD Power Service Division 59. C Rural Electrification Corporation 60. R&M Repair and Maintenance 61. ROE Return on Equity 62. RPO Renewable Purchase Obligation 63. Rs Rupees 64. SBI State Bank of India 65. SLM Straight Line Method 66. SHR Station Heat Rate 67. T&D Transmission and Distribution 68. HPSEBL Himachal Pradesh State Electricity Board Limited 69. HPERC Himachal Pradesh Electricity Regulatory Commission 70. w.e.f With effect from 71. Y-o-Y Year on Year Feb 2014 Page 2
4 TABLE OF CONTENTS MYT Petition for 3 rd (FY to FY ), Business HPSEBL 1. INTRODUCTION ABOUT HPSEBL OBJECTIVE OF THE DOCUMENT OWN GENERATION DETAILS HISTORICAL GENERATION FROM OWN PLANTS GENERATION PROJECTIONS FROM OWN GENERATING STATIONS IN THE 3RD MYT PERIOD DETERMINATION OF ANNUAL FIXED CHARGES ANNUAL FIXED CHARGES FOR BHABA HEP ANNUAL FIXED CHARGES FOR CHABA HEP ANNUAL FIXED CHARGES FOR NOGLI HEP ANNUAL FIXED CHARGES FOR RONGTONG HEP ANNUAL FIXED CHARGES FOR RUKTI HEP ANNUAL FIXED CHARGES FOR ANDHRA HEP ANNUAL FIXED CHARGES FOR GIRI HEP ANNUAL FIXED CHARGES FOR BANER HEP ANNUAL FIXED CHARGES FOR BASSI HEP ANNUAL FIXED CHARGES FOR BINWA HEP ANNUAL FIXED CHARGES FOR BS CHAMBA HEP ANNUAL FIXED CHARGES FOR GAJ HEP ANNUAL FIXED CHARGES FOR LARJI HEP ANNUAL FIXED CHARGES FOR GHANVI II HEP TARIFFS APPROVED BY HPERC FOR 8 SMALL HEPS SPONSE TO COMMISSION S OBSERVATIONS PRAYER List of Tables Table 1: Past Years' till 2nd MYT period... 9 Table 2: restated energy availability of hydro plants...10 Table 3: 3rd MYT Period Projections for...11 Table 4: Calculation of WPI and CPI factors...12 Table 5: GFA details of Bhaba...13 Table 6: AFC for bhaba...14 Table 7: GFA Details of Chaba...15 Table 8: AFC for Chaba...15 Table 9: GFA Details of Nogli...16 Table 10: AFC for Nogli...16 Table 11: GFA Details of RongTong...18 Table 12: AFC for RongTong...18 Table 13: GFA Details for Rukti...19 Table 14: AFC for Rukti HEP...19 Table 15: GFA Details of Andhra...20 Table 16: AFC for Andhra...21 Table 17: GFA Details of Giri...22 Feb 2014 Page 3
5 Table 18: AFC for GIRI...22 Table 19: GFA Details of Baner...23 Table 20: AFC for Baner...23 Table 21: GFA Details of Bassi...25 Table 22: Outstanding loan details of Bassi...25 Table 23: AFC for Bassi...25 Table 24: GFA Details of Binwa...26 Table 25: AFC for Binwa...26 Table 26: GFA details for BS Chamba...27 Table 27: AFC for BS Chamba...28 Table 28: GFA Details of Gaj...29 Table 29: AFC of GAJ...29 Table 30: GFA Details of Larji...30 Table 31: Outstanding Loans of Larji...30 Table 32: AFC for Larji...31 Table 33: GFA Details of Ghanvi II...31 Table 34: Outstanding Loan Deails of Ghanvi II...32 Table 35: AFC for Ghanvi II...32 Table 36: Approved tariff for Small HEPs...32 Feb 2014 Page 4
6 BEFO THE HIMACHAL PRADESH ELECTRICITY GULATORY COMMISSION SHIMLA Filling No.. Case No. IN THE MATTER OF: Filing of the Aggregate Revenue Requirement (ARR) of own generation for the Third (FY to FY ) under Section 62, 64 and 86 of the Electricity Act, 2003 AND IN THE MATTER OF Himachal Pradesh State Electricity Board Limited (hereinafter referred to as "HPSEBL" or "The HPSEBL") Vidyut Bhawan Shimla Applicant AFFIDAVIT I, Son of Shri aged about XX years, Resident of, working as, do hereby solemnly affirm and declare that I have gone through the contents of accompanying application/tariff petition and that the contents of the same are true and correct to the best of my personal knowledge as derived from the official record. I further solemnly affirm and verify that the contents of this affidavit are true and correct to the best of my personal knowledge, no part of it is false and nothing material has been concealed therein. Verified and signed at Shimla on 15 th February, Witness DEPONENT Feb 2014 Page 5
7 BEFO THE HIMACHAL PRADESH ELECTRICITY GULATORY COMMISSION SHIMLA Filing No Case No IN THE MATTER OF: Filing of the Aggregate Revenue Requirement (ARR) of own generation for the Third (FY to FY ) under Section 62, 64 and 86 of the Electricity Act, 2003 AND IN THE MATTER OF Himachal Pradesh State Electricity Board Limited (hereinafter referred to as "HPSEBL" or "The HPSEBL") Vidyut Bhawan Shimla Applicant The Applicant respectfully submits as under: 1. The Himachal Pradesh State Electricity Board was constituted on 1st September, 1971 in accordance with the provisions of Electricity Supply Act (1948). It functioned as Distribution, as well as Transmission licensee for the state of Himachal Pradesh up to 10th June, 2010, when the Government of Himachal Pradesh, in exercise of the power conferred to it, by Section 131 (2), 132, 133 and other applicable provisions of the Electricity Act 2003, vide the Himachal Pradesh Power Sector Reforms transfer Scheme, 2010 transferred the functions of generation, distribution and trading of electricity to Himachal Pradesh State Electricity Board Limited (HPSEBL). The Board at present is engaged in electricity generation, distribution and related activities in the state of Himachal Pradesh. 2. Consequent to the enactment of the Electricity Act, 2003 (hereinafter referred to as the Act ), the process of approval of proposed tariffs is vested with the State Commission. Pursuant to the provisions of Section 61, 62 and 64 of the Act, HPSEBL is filing the current petition, in order to meet its financial requirements for the various hydro generation plants being operated by it. 3. The present petition is filed with the Hon ble HPERC for submission of the ARR of HPSEBL s own generation plants, for the Third Control period (FY to FY ) as per the provisions of HPERC (Terms and Conditions for Determination of Hydro Supply Tariff) Regulations, 2011, read along with First Amendment, 2011 and Second Amendment, HPSEBL along with this petition is submitting the regulatory formats with data & information to an extent applicable and would make available any further information/ additional data required by the Hon ble Commission during the course of MYT & tariff determination process. Feb 2014 Page 6
8 1. INTRODUCTION 1.1. ABOUT HPSEBL 1. The Himachal Pradesh State Electricity Board was constituted on 1st September, 1971 in accordance with the provisions of Electricity Supply Act (1948). It functioned as Distribution, as well as Transmission licensee for the state of Himachal Pradesh up to 10th June, 2010, when the Government of Himachal Pradesh, in exercise of the power conferred to it, by Section 131 (2), 132, 133 and other applicable provisions of the Electricity Act 2003, vide the Himachal Pradesh Power Sector Reforms transfer Scheme, 2010 transferred the functions of generation, distribution and trading of electricity to Himachal Pradesh State Electricity Board Limited (HPSEBL) 2. Himachal Pradesh State Electricity Board Limited (HPSEBL), having its registered office at Vidyut Bhawan, Shimla, is responsible for generation and supply of uninterrupted & quality power to all categories of consumers in Himachal Pradesh at the most economical rates OBJECTIVE OF THE DOCUMENT 1. The Himachal Pradesh Electricity Regulatory Commission (HPERC), in exercise of the powers conferred on it by section 181 of the Electricity Act 2003 (Act 36 of 2003) and all other powers, has issued HPERC (Terms and Conditions for Determination of Hydro Tariff) Regulations, 2011 along with Amendment 1, 2011 and Amendment 2, 2013, hereinafter referred to as MYT Regulations 2. Based on the MYT Regulations, HPSEBL is filing this MYT petition for the third control period (FY to FY 18-19) for 14 Nos. of hydro generation plants out of the total 22 Nos. of own generation plants. The petition does not include the rest 8 Nos. of small plants (listed below) as their respective tariffs had already been fixed by the Commission as per the HPERC order dated 15 th Jan, 2014 in petition no. 54 of These 8 Nos. of small plants are given below: a. Ghanvi b. Khauli c. Thirot d. Bhaba Augmentation e. Gumma f. Holi g. Sal II h. Killar 3. HPSEBL has prepared the petition as per MYT Regulations, 2011 and its subsequent amendments 1 & 2. HPSEBL submits that there are certain data sets that cannot be Feb 2014 Page 7
9 made available in the prescribed MYT formats due to the inherent complexity and is not attributable to the efficiency of HPSEBL. 4. HPSEBL is filing this petition covering revised estimates (R.E.) for FY and ARR for FY to FY as per HPERC Regulations on Terms and Conditions for Determination of Multi Year Tariff, 2011 and subsequent amendments 1 & 2. Feb 2014 Page 8
10 2. OWN GENERATION DETAILS 2.1. HISTORICAL GENERATION FROM OWN PLANTS The generation (MUs) from FY 2011 to FY 2013 is given as per the actual records of HPSEBL. The revised estimates of FY 2014 generation (MUs) are based on 8 months actual generation (Apr Nov) and the rest 4 months (Dec Mar) projections on the basis of energy availability approved by HPERC or revised design energy proposed by HPSEBL, whichever is applicable. The design and energy of the plants varies a lot during the winters and summers. Hence, monthly projections of the generation (MUs) during the last 4 months are done using the historical trends of these 4 months only instead of simple extrapolation. Out of a total number of 22 plants as mentioned in Table 1, GoHP has a share of 12% in Ghanvi, Baner, Gaj, Larji, Uhl III and Ghanvi II. Hence, HPSEBL receives 88% of the overall generation from all of these plants. The balance is received as free power. Based on the above operational parameters, the actual generation for the past 3 years, the revised estimates for of the net generation are given in the following table: TABLE 1: PAST YEARS' GENERATION TILL 2ND MYT PERIOD Stations Yearly Power Availability (MUs) Power Availability (MUs) from HPSEBL Stations Actual Actual Actual FY FY FY Bhaba Bassi Giri Andhra Ghanvi Baner Gaj Larji Khauli Binwa Thirot Gumma Holi Bhaba Aug Nogli Rongtong Sal-II Chaba FY Feb 2014 Page 9
11 Stations Yearly Power Availability (MUs) Power Availability (MUs) from HPSEBL Stations Actual Actual Actual FY FY FY Rukti Chamba Killar Uhl III - BVPCL Ghanvi II FY Total GENERATION PROJECTIONS FROM OWN GENERATING STATIONS IN THE 3RD MYT PERIOD For the purpose of generation projections in 3 rd control period, the HPERC approved numbers for energy availability and net saleable energy for 17 No. small hydro plants as per the HPERC order dated 15 th Jan, 2014 in petition no. 54 of As per the same order, out of 17 Nos., the tariff for 8 Nos. of these plants was fixed by the Commission for the 3 rd control period and no separate petition is being filed for them. The petition for the rest 9 Nos. small hydro plants along with the 5 No. large plants is prepared in the later sections of the petition. The details of the energy available (small hydro plants) approved by the Commission are given below: TABLE 2: STATED ENERGY AVAILABILITY OF HYDRO PLANTS S N Plant Energy Availability (MU) 1. Andhra Baner Gaj Binwa Nogli Chaba RongTong Rukti Chamba Ghanvi Khauli Thirot Bhaba Augmentation Gumma Holi Sal II Killar 1.16 The 5 No. plants which are not covered under the above mentioned (HPERC order dated 15 th Jan, 2014 in petition no. 54 of 2013) are Larji, Ghanvi II, Bassi, Bhaba and Feb 2014 Page 10
12 Giri. For these 5 No. plants the revised energy estimates as per Memorandum for the Proposal for revision of Design Energy of existing Hydro Electric Plants of HPSEB Ltd submitted by HPSEBL have been considered for projections. TABLE 3: 3RD MYT PERIOD PROJECTIONS FOR GENERATION Yearly Power Availability (MUs) Power Availability (MUs) from HPSEBL Stations Proj. Proj. Proj. Proj. Proj. Stations FY FY FY FY FY Bhaba Bassi Giri Andhra Ghanvi Baner Gaj Larji Khauli Binwa Thirot Gumma Holi Bhaba Aug Nogli Rongtong Sal-II Chaba Rukti Chamba Killar Uhl III - BVPCL Ghanvi II Total In this petition, preliminary estimates of Annual Fixed Charges for three large (above 25 MW) HEPs viz. Bhaba, Giri and Bassi are enclosed. Detailed petition of these plants as required by HPERC s order dated 15 th Jan, 2014 in petition no. 54 of will be subsequently submitted to the Hon ble HPERC. No separate petitions for Larji, Khauli and Bhaba Augmentation would be required as there has been no additional capitalization in Larji while the tariffs for Khauli and Bhaba Augmentation have already been fixed by Hon ble HPERC order dated 15 th Jan, 2014 in petition no. 54 of Feb 2014 Page 11
13 3. DETERMINATION OF ANNUAL FIXED CHARGES 1. Components of Annual Fixed Charge HPSEBL, for the purpose of determination of Annual Fixed Charge and the tariff for sale of electricity from the generating station, has considered the following elements as specified by the HPERC (Terms and Conditions for Determination of Hydro Tariff) Regulations, 2011: i. Operation and Maintenance Expenses (O&M) j. Depreciation k. Interest on Loans l. Interest on Working Capital; and m. Return on Equity (RoE) 2. Other assumptions for the determination of Annual Fixed Charge HPSEBL has estimated the AFC charges for the individual own generating plants based on the norms as per HPERC (Terms and Conditions for Determination of Hydro Tariff), 2011 along with Amendments 1 and 2 and the historical numbers. HPSEBL has considered the following for determination of AFC: a. The completed costs of projects have been taken as considered by the commission as per the MYT order for FY 12 to FY 14 dated 19th July b. The ROE has been 15.50% as per the commission s Hydro Tariff Regulations 2011 and subsequent amendments 1 & 2, except for Larji HEP wherein pre - tax 19.38% has been approved by commission in tariff order c. The O&M expenses have been escalated as per the Amendment 2 of HPERC (Terms and Conditions for Determination of Hydro Tariff), The WPI and CPI considered for this purpose are 8.61% and 9.76% respectively, calculated as below: TABLE 4: CALCULATION OF WPI AND CPI FACTORS FY WPI Index Growth (WPI) CPI Index Growth in CPI Avg 8.61% 9.76% Feb 2014 Page 12
14 i. For the purpose of projecting R&M cost, the historical R&M cost as a percentage of the historical GFA has been escalated by the WPI factor 8.61% each year. ii. The employee cost has been projected by escalating the historical employee cost by the CPI factor 9.76%. It was further escalated by the year on year growth rate in the employee number. iii. For the purpose of projecting A&G cost, the historical A&G has been escalated by the WPI factor 8.61% each year. d. A depreciation rate of 5.28% has been considered for the first 12 years of capitaliziation. Thereafter, the balance net asset value is equally spread over the useful life of the plant, as per the Tariff conditions issued by Hon HPERC. e. The GoHP has 12% share in the generation of power from plants Gaj, Baner, Ghanvi, Khauli, Ghanvi II and Larji. The same has been reduced from total generation to arrive at the net saleable energy from these plants to recover the AFC ANNUAL FIXED CHARGES FOR BHABA HEP Bhaba HEP is a 120 MW (3 x 40 MW) project commissioned in the year It is a peaking, storage project with underground power station and static excitation. HPSEBL, in its letter dated 17 th April 2008, had submitted a capital cost of INR Cr, against which, the Commission, in both, 1 st MYT tariff order, May 2008 and the 2 nd MYT tariff order, July 2011 had approved a cost of INR Cr. The Hon HPERC had considered 100% debt funding for the plant with no outstanding loans. During the 2 nd, there has been an additional capitalization of INR 2.24 Cr and the same has been added to the gross fixed assets (GFA) from FY onwards. Apart from the opening GFA for FY 2015 of INR Cr (INR Cr + INR 2.24 Cr) a capital expenditure of INR Cr is envisaged to be capitalized in the 3 rd MYT control period out of which INR Cr worth of capital expenditure is intended to be funded through PFC loans, INR 3 Cr through short term borrowings and INR Cr through equity. The complete list of the proposed works under the capital expenditure plan is given in the form F 13 enclosed with the MYT petition. The GFA details along with the depreciation expense for the 3 rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 5: GFA DETAILS OF BHABA GFA Particulars - Bhaba HEP Feb 2014 Page 13
15 Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation A detailed petition would be filed for Bhaba HEP as required by the HPERC order dated 15 th Jan, 2014 in petition no. 54 of As per the enclosed petition, the preliminary estimates of AFC determined for Bhaba HEP are given in the below table. TABLE 6: AFC FOR BHABA S. No. A Particulars - Bhaba HEP Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR CHABA HEP Chaba HEP is a 1.75 MW (2 x 0.5 MW + 3 x 0.25 MW) project commissioned in the year It is a non peaking run of the river project with surface water station and static excitation. The project was initially executed with a capital cost of INR 1.21 Cr and was funded through 100% debt. The same cost was proposed by HPSEBL and approved by the Commission in both 1 st MYT tariff order, May 2008 as well as the 2 nd MYT tariff order, July There was 100% debt funding for the plant with no outstanding loans. During the 2 nd, No additional capitalization had been added to the gross fixed Feb 2014 Page 14
16 assets (GFA). Since it is a 94 year old plant, the initial cost of INR 1.21 Cr was completely depreciated. Apart from the opening GFA for FY 2015 of INR 1.21 Cr, a total capital expenditure of INR 0.96 Cr is envisaged to be capitalized in the 3 rd MYT control period and all of it is intended to be funded through short term borrowings. The details of the proposed works under the capital expenditure plan are given in the form F 13 enclosed with the MYT petition. The GFA details along with the depreciation expense for the 3 rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 7: GFA DETAILS OF CHABA GFA Particulars - Chaba HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation The AFC determined for Chaba HEP is shown as follows: TABLE 8: AFC FOR CHABA S. No. A Particulars - Chaba HEP Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Feb 2014 Page 15
17 13 Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR NOGLI HEP Nogli HEP is a 2.50 MW (2 x x 0.50 MW) project commissioned in the years 1963, 1970 and It is a non peaking, run of the river project with surface power station and static excitation. The project was executed with a capital cost of Rs Cr which was proposed by HPSEBL and the same was approved by HPERC in both the 1 st and 2 nd MYT tariff order. It is a completely depreciated plant with no outstanding loan. The plant was executed with 100% debt (no equity) with no outstanding loan. No additional capitalization (after COD) was proposed by HPSEBL under this plant before the current year. Apart from the opening GFA for FY 2015 of INR Cr, a total capital expenditure of INR 5.20 Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and all of it is intended to be funded through PFC loans. The details of the proposed works under the capital expenditure plan are given in the form F 13 enclosed with the MYT petition. The GFA details along with the depreciation expense for the 3 rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 9: GFA DETAILS OF NOGLI GFA Particulars - Nogli HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation The AFC determined for Nogli HEP is shown as follows: TABLE 10: AFC FOR NOGLI S. No. Particulars - Nogli HEP Feb 2014 Page 16
18 A 1 Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR RONGTONG HEP Rong Tong HEP is a 2 MW (4 x 0.50 MW) project commissioned in the year The project was executed with a capital cost of Rs Cr which was proposed by HPSEBL and the same was approved by HPERC in both the 1 st and 2 nd MYT tariff order. The plant was executed with 100% debt (no equity) with no outstanding loan. There is an additional capitalization of INR 0.04 Cr (after COD) under this plant and added to the gross fixed assets from FY onwards. Apart from the opening GFA for FY 2015 of INR Cr (INR Cr Cr) a total capital expenditure of INR 6.75 Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and all of it is intended to be funded through MN Grants. These grants were allocated as per the 13 th Finance Commission Grant for strengthening of electricity infrastructure in Border Blocks of HP. Since this amount of INR 6.75 Cr is treated as a grant, no depreciation, Interest and finance charges and ROE have been charged on this amount. The details of the proposed works under the capital expenditure plan are given in the form F 13 enclosed with the MYT petition. The generation from FY onwards is the same as approved by the commission as per the HPERC order dated 15 th Jan, 2014 in petition no. 54 of The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. Feb 2014 Page 17
19 TABLE 11: GFA DETAILS OF RONGTONG GFA Particulars - RongTong HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation The AFC determined for Rong Tong HEP is shown as follows: TABLE 12: AFC FOR RONGTONG S. No. A 1 Particulars : RongTong HEP Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR RUKTI HEP Rukti HEP is a 1.50 MW (3 x 0.50 MW) project commissioned in the year 1979 and It is a non peaking plant run of the river and project with surface power station and static excitation. The project was executed with a capital cost of Rs 1.59 Cr which was proposed by HPSEBL and the same was approved by HPERC in both the 1 st and 2 nd MYT tariff order. Feb 2014 Page 18
20 The plant was executed with 100% debt (no equity) with no outstanding loan. No additional capitalization (after COD) was proposed by HPSEBL under this plant. Apart from the opening GFA for FY 2015 of INR 1.59 Cr, a total capital expenditure of INR 6.57 Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and all of it is intended to be funded through MN Grants. These grants were allocated as per the 13 th Finance Commission Grant for strengthening of electricity infrastructure in Border Blocks of HP. Since this amount of INR 6.57 Cr is treated as a grant, no depreciation, Interest and finance charges and ROE have been charged on this amount. The details of the proposed works under the capital expenditure plan are given in the form F 13 enclosed with the MYT petition. The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 13: GFA DETAILS FOR RUKTI GFA Particulars - Rukti HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation The AFC determined for Rukti HEP is shown as follows: TABLE 14: AFC FOR RUKTI HEP S. No. A Particulars - Rukti HEP Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Feb 2014 Page 19
21 S. No. A Particulars - Rukti HEP Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR ANDHRA HEP Andhra HEP is a MW (3 x 5.65 MW) project commissioned by the HPSEBL in the year It is a peaking, storage project with surface power station and static excitation. The project was executed with a capital cost of Rs Cr which was proposed by HPSEBL and the same was approved by HPERC in both the 1 st and 2 nd MYT tariff order. The plant was executed with 100% debt (no equity) with no outstanding loan. No additional capitalization (after COD) had happened in the 1 st and 2 nd MYT period under this plant. Apart from the opening GFA for FY 2015 of INR Cr, a total capital expenditure of INR Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and out of it, INR Cr is intended to be funded through PFC loans, INR 4.86 Cr through equity and INR 1.78 Cr through short term borrowings. The complete details of the proposed works under the capital expenditure plan of Andhra plant are given in the form F 13 enclosed with the MYT petition. The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 15: GFA DETAILS OF ANDHRA GFA Particulars - Andhra HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Feb 2014 Page 20
22 GFA Particulars - Andhra HEP Annual Depreciation The AFC determined for Andhra HEP is shown as follows: TABLE 16: AFC FOR ANDHRA S. No. A Particulars Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR GIRI HEP Giri HEP is a 60 MW (2 x 30 MW) project commissioned in the year It is a non peaking run of the river project with semi underground power station and rotating excitation. HPSEBL, in its letter dated 17 th April 2008, had submitted a capital cost of INR 40.02Cr, against which, the Commission, in its 1 st MYT tariff order, May 2008 and 2 nd MYT tariff order, July 2011 had approved a cost of INR Cr. The Hon HPERC had considered 100% debt funding for the plant with no outstanding loans. During the 2 nd Control Period, there has been an additional capitalization of INR 5.28 Cr and the same has been added to the gross fixed assets (GFA) from FY onwards. Apart from the opening GFA for FY 2015 of INR Cr (INR Cr Cr) a total capital expenditure of INR Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and out of it, INR Cr is intended to be funded through PFC loans, INR Cr through equity and INR 2.05 Cr through short Feb 2014 Page 21
23 term borrowings. The complete details of the proposed works under the capital expenditure plan of Giri plant are given in the form F 13 enclosed with the MYT petition. The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 17: GFA DETAILS OF GIRI GFA Particulars - Giri HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation A detailed petition would be filed for Giri HEP as required by the HPERC order dated 15 th Jan, 2014 in petition no. 54 of As per the enclosed petition, the preliminary estimates of AFC determined for Giri HEP are given in the below table. TABLE 18: AFC FOR GIRI S. No. A Particulars - Giri HEP Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) Feb 2014 Page 22
24 3.8. ANNUAL FIXED CHARGES FOR BANER HEP Baner HEP is a 12 MW (3 x 4 MW) project commissioned by the HPSEBL in the year HPSEBL had submitted a capital cost of INR 68.79Cr, against which, the Commission, in its 1 st MYT tariff order, May 2008 and 2 nd MYT tariff order, July 2011 had approved a cost of INR Cr. The financing of the capital cost of INR Cr is through PFC, LIC and GoHP loan of INR Cr along with a of the GOHP equity of INR 15 Cr on which an has been calculated as per the HPERC Regulations, During the 2 nd, there has been an additional capitalization of INR 0.20 Cr and the same has been added to the gross fixed assets (GFA) from FY onwards. Apart from the opening GFA for FY 2015 of INR Cr (INR Cr Cr) a total capital expenditure of INR 2.90 Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and out of it, INR.1.45 Cr is intended to be funded through PFC loans, INR 0.30 Cr through equity and INR 1.15 Cr through short term borrowings. The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 19: GFA DETAILS OF BANER GFA Particulars - Baner HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation The AFC for Baner in the 3 rd control period is given below: TABLE 20: AFC FOR BANER S. No. Particulars - Baner HEP A 1 Gross (Design Energy) (MU) Feb 2014 Page 23
25 S. No. Particulars - Baner HEP A 2 Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to 12% (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR BASSI HEP Bassi HEP is a 60 MW (4 x 15 MW) project commissioned in the year 1970, 1971 and It is a peaking, storage project with surface power station and rotating exciters. The Commission in the 1 st MYT tariff order had approved a capital cost of INR Cr as the original cost of the project, funded through 100% debt with no outstanding loan. In the 2 nd MYT tariff order, the Commission had also considered an additional capitalization of INR Cr, scaling up the GFA for FY 2012 to INR Cr, for which PFC loan of INR 80 Cr had been considered with the rest of the amount of INR being assumed to be met by state plan. A cumulative additional capitalization till FY 2014 for INR Cr pertaining to a RMU scheme (including INR Cr above) has been added to the original GFA of INR Cr, scaling up the opening GFA of FY 2015 to Cr. Apart from the opening GFA, a total capital expenditure of INR Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and out of it, INR Cr is intended to be funded through PFC loans, INR 2.20 Cr through equity and INR 2.79 Cr through short term borrowings. The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. Feb 2014 Page 24
26 TABLE 21: GFA DETAILS OF BASSI GFA Particulars - Bassi HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation There are loans outstanding for Bassi and the table below shows the yearwise principal repayment and interest in the 3 rd MY control period: TABLE 22: OUTSTANDING LOAN DETAILS OF BASSI Loan Schedule - Bassi Principal Repayments INR Crores Interest Charges INR Crores A detailed petition would be filed for Bassi HEP as required by the HPERC order dated 15 th Jan, 2014 in petition no. 54 of As per the enclosed petition, the preliminary estimates of AFC determined for Bassi HEP are given in the below table. TABLE 23: AFC FOR BASSI S. Particulars - Bassi HEP No A 1 Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) Feb 2014 Page 25
27 3.10. ANNUAL FIXED CHARGES FOR BINWA HEP Binwa HEP is a 6 MW (2 x 3 MW) project commissioned in the year The project was executed with a capital cost of Rs Cr which was proposed by HPSEBL and the same was approved by HPERC in both the 1 st and 2 nd MYT tariff order. The plant was executed with 100% debt (no equity) with no outstanding loan. An additional capitalization (after COD) of INR 0.08 Cr was proposed by HPSEBL under this plant in the 2 nd MYT period. Apart from the opening GFA for FY 2015 of INR Cr (INR Cr Cr) a total capital expenditure of INR Cr is envisaged to be capitalized and added to the gross fixed assets in the 3 rd MYT control period and out of it, INR Cr is intended to be funded through PFC loans, INR 2.90 Cr through equity and INR 1 Cr through short term borrowings. The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 24: GFA DETAILS OF BINWA GFA Particulars - Binwa HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation The AFC determined for Binwa HEP is shown as follows: TABLE 25: AFC FOR BINWA S. Particulars - Binwa HEP No A 1 Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Feb 2014 Page 26
28 S. Particulars - Binwa HEP No A 4 Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR BS CHAMBA HEP Chamba HEP is a 0.45 MW (3 X 0.15 MW) project commissioned in the years 1938, 1957 and It is a non peaking run of the river project with surface power station and rotating exciters. The project was executed with a capital cost of Rs 0.50 Cr which was proposed by HPSEBL and the same was approved by HPERC in both the 1 st and 2 nd MYT tariff order. The plant was executed with 100% debt (no equity) with no outstanding loan. No additional capitalization (after COD) was proposed by HPSEBL under this plant. As far as the future expenditure of BS Chamba is concerned, INR 2 Cr are planned to be spent on maintenance of the plant. A contracting agency named M/S ASG Transectors have been appointed for the purpose and as per their contract, all future expenditure would be done by the agency. The GFA details along with the depreciation expense for the 3rd are presented in the following table. The depreciation expenses for the existing GFA and the proposed additions to the GFA have been separately calculated. TABLE 26: GFA DETAILS FOR BS CHAMBA GFA Particulars - BS HEP Original GFA as approved by HPERC Depreciation New GFA (planned in 3rd MYT period) Accumulated New GFA Depreciation on New GFA Feb 2014 Page 27
29 GFA Particulars - BS HEP Total GFA (actual till 2nd MYT period + Planned in 3rd MYT period) Annual Depreciation The AFC determined for Chamba HEP is shown as follows: TABLE 27: AFC FOR BS CHAMBA S. Particulars: Chamba HEP No A 1 Gross (Design Energy) (MU) Total Auxiliary (MU) Net at Bus (MU) Less: Free Power to GOHP (MU) Energy Available for Sale (MU) O&M expenses (INR Cr) % (INR Cr) Interest & Finance Charges (INR Cr) Return on Equity (INR Cr) Interest on Working Capital (INR Cr) Annual Fixed Charges (INR Cr) Capacity Charges (INR Cr) Fixed Charges (INR Cr) ANNUAL FIXED CHARGES FOR GAJ HEP Gaj HEP is a MW (3 x 3.50 MW) project commissioned by the HPSEBL in the year HPSEBL had submitted a capital cost for Gaj HEP of INR Cr, against which, the Commission, in its 1 st MYT tariff order, May 2008 and 2 nd MYT tariff order, July 2011 had approved a cost of INR Cr. The sources of funding for the capital cost of INR Cr were considered to be PFC, LIC and GoHP loan of INR Cr along with GoHP equity of INR 15 Cr on which an has been calculated as per the HPERC Regulations, During the 2 nd, there has been an additional capitalization of INR 1.06 Cr and the same has been added to the gross fixed assets (GFA) from FY onwards. Apart from the opening GFA for FY 2015 of INR Cr (INR Cr Cr) a total capital expenditure of INR 3.96 Cr is envisaged to be capitalized and added to the gross Feb 2014 Page 28
Before the Madhya Pradesh Electricity Regulatory Commission, Bhopal
Table of Contents 1 Comparison of Claimed and Allowed Annual Revenue Requirement for FY 2010-11 5 2. Power Purchase Cost and Intra State Transmission Charges... 5 3. Operation & Maintenance (O&M) Cost...
More informationOrder on. Petition No. 58/2013
MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 4 th and 5 th Floor, Metro Plaza, Bittan Market, Bhopal - 462 016 IN THE MATTER OF: Order on ARR & Retail Supply Tariff for Special Economic Zone (SEZ)
More informationOrder on. Petition No. 38/2013
MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 4 th and 5 th Floor, Metro Plaza, Bittan Market, Bhopal - 462 016 IN THE MATTER OF: Order on ARR & Retail Supply Tariff for Special Economic Zone (SEZ)
More informationMADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL
MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL Subject: Dated: 7 th February, 2013 M/s Essar Power M. P. Limited DAILY ORDER (Date of Motion Hearing : 5 th February, 2013) Petition No.03/2013
More informationJHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI
JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI IN THE MATTER OF Case No. 04 of 2010 MUKHTIAR SINGH, Chairperson An application for review of Tariff Order for FY 2009-10 of Tata Steel Limited
More informationMYT Order For the period FY , FY and FY
MYT Order For the period FY 2013-14, FY 2014-15 and FY 2015-16 SAIL Bokaro Ranchi September 2014 TABLE OF CONTENTS A1: INTRODUCTION... 5 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION... 5 STEEL AUTHORITY
More informationMADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL. ORDER (Date of Order : 7 th September, 2012)
MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL Sub : In the matter of approval of Power Purchase Agreement. ORDER (Date of Order : 7 th September, 2012) Petition No.11 of 2012 1. MP Power Management
More informationBEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA.
In the matter of:- BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. M/s Tangnu Romai Power Generation (P) Ltd. House No. 835, Excel Society, Sector-48 Chandigarh-160047 through Sh.
More informationBEFORE THE H.P. ELECTRICITY REGULATORY COMMISSION AT SHIMLA
BEFORE THE H.P. ELECTRICITY REGULATORY COMMISSION AT SHIMLA Petition No. 151/2004 In the matter of:- Filing of petition by Uttaranchal Jal Vidyut Nigam Ltd. for determining the generation tariff for inter-state
More informationBEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW. Petition No.: 960/2014
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW Petition No.: 960/2014 IN THE MATTER OF: Petition under Section 63 of the Electricity Act, 2003 read with Clause 10.4 of the Guidelines
More informationCase No.139 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationBEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member In the matter of: Fixation of transmission tariff for 7.2 KM 400 KV dedicated
More informationDraft Supplementary Power Purchase Agreement
Draft Supplementary Power Purchase Agreement Between Paschimanchal Vidyut Vitran Nigam Ltd. ( Procurer 1 ) and Poorvanchal Vidyut Vitran Nigam Ltd. ( Procurer 2 ) and Madhyanchal Vidyut Vitran Nigam Ltd.
More informationBEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. Investigate and to take appropriate action against M/s Torrent and further to cancel the
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum ShriDesh Deepak Verma, Chairman Smt. Meenakshi Singh, Member Shri I. B. Pandey, Member In the matter of Investigate and to take appropriate
More informationPetition No 973 of 2014 and 1036,1037,1038,1039 &1040 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW
Petition No 973 of 2014 and 1036,1037,1038,1039 &1040 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order: 07.01.16 Present: Hon ble Shri Desh Deepak Verma, Chairman
More informationCase No. 22 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.com
More informationM/s. BLA Power Pvt. Ltd. - Petitioner. 4. M. P. Madhya Kshetra Vidyut Vitaran Co. Ltd., Bhopal -Respondents
MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL Sub: In the matter of review petition filed by M/s BLA Power Pvt. Ltd. under section Petition No. 16 of 2015. Petition No. 35 of 2015 ORDER (Date
More informationPetition No.881 of 2013, 952 of 2014, 1043 of 2015, 1092& 1093 of 2016 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW
Petition No.881 of 2013, 92 of 2014, 1043 of 201, 1092& 1093 of 2016 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW PRESENT: 1. Hon ble Sri. Desh Deepak Verma, Chairman 2. Hon ble Sri.
More informationNo. HPSEBL/CE(SO&P)/IS-60A(Vol-IV)/ Dated:
Tender Document No.: 4 HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED (A State Government Undertaking) Office of the Chief Engineer (SO&P), Vidyut Bhawan, Shimla-171004 (HP) Tel./Fax No. 0177-2653119,
More informationBEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA
BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA Petition No. 82 of 2012 M/S Himachal Chamber of Commerce and Industry C/O Goel Diesel Service, Bhupper, Poanta Sahib, Distt. Sirmour
More informationBEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member In the matter of: Petitioner Respondents UPNEDA, Vibhuti Khand, Gomti Nagar,
More informationORDER (Date of Hearing : 23 rd November, 2010) (Date of Order : 24 th November, 2010)
MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION, BHOPAL Sub : In the matter of petition for approval of cost sharing scheme by prospective EHT ORDER (Date of Hearing : 23 rd November, 2010) (Date of Order
More informationNo. HPSEBL/CE(SO&P)/IS-60A(Vol-II)/ As per list attached.
HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED (A State Government Undertaking) Office of the Chief Engineer (SO&P), Vidyut Bhawan, Shimla-171004. (HP) Tel./Fax No. 0177-2657901, Email: ceso@hpseb.in,
More informationSuo-Motu Petition No. 2/2018
Page 1 of 6 BEFORE THE ARUNACHAL PRADESH STATE ELECTRICITY REGULATORY COMMISSION ITANAGAR Suo-Motu Petition No. 2/2018 In the Matter of Compliance of Renewable Purchase Obligation targets as specified
More informationBEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member In the matter of: Petitioner Respondents UPNEDA, Vibhuti Khand, Gomti Nagar,
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2015 INDEX
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2015 INDEX Part A: PRELIMINARY 4 1. Short Title, extent and commencement 4 2. Definitions 4 3. Eligibility to seek
More informationRespondents. Present in the Hearing: Respondents
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Smt. Meenakshi Singh, Member Shri I. B. Pandey, Member In the matter of: Petition u/s 86 (1) (c) & (f),
More informationCase No. 94 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationORDER (Hearing on & )
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Smt. Meenakshi Singh, Member Shri I. B. Pandey, Member In the matter of: Petition u/s 86 (1) (c) & (f),
More informationCase No. 68 of Coram. Shri. I. M. Bohari, Member Shri. Mukesh Khullar, Member. M/s RattanIndia Nasik Power Ltd.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationHIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA NOTIFICATION Shimla, the 21 st September, 2015
HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA NOTIFICATION Shimla, the 21 st September, 2015 No. HPERC/419.- In exercise of the powers conferred by section 46, read with section 181, of the
More informationSEVENTEENTH AMENDMENT TO MADHYA PRADESH ELECTRICITY SUPPLY CODE, 2004.
Notified on 25/06/2010 Bhopal, 14 th June, 2010 No. 1548 /MPERC/2010. In exercise of powers conferred by Section 181(1) and 181 (2) (x) read with Section 50 of the Electricity Act, 2003 and for removal
More informationMADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL ORDER
MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL ORDER (Date of Order : 7 th September, 2012) Petition Nos.7, 8, 9, 10 & 12 of 2012 1. MP Power Management Co. Ltd., Jabalpur 2. MP Paschim Kshetra
More informationIN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO OF 2018 VERSUS WITH CIVIL APPEAL NO OF 2018 JUDGMENT
REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 5865 OF 2018 UTTAR HARYANA BIJLI VITRAN NIGAM LTD. [UHBVNL] & ANR. APPELLANTS VERSUS ADANI POWER LTD. & ORS. RESPONDENTS
More information3. M. P. Poorv Kshetra Vidyut Vitaran Co. Ltd. - Respondents Shakti Bhawan, Rampur, Jabalpur
Order (Date of Motion Hearing: 30 th May 2017) (Date of Order: 02 nd June 2017) BLA Power Pvt. Ltd. 84, Marker Chambers Nariman Point, Mumbai-400 021 - Petitioner Vs. 1. Energy Department, Government of
More informationTHE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW
Petition No 851 & 861 of 2012 Before THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW Date of Order: 20.03.2013 IN THE MATTER OF: Deemed Energy claim of RPSCL Petition No 851 of 2012 BETWEEN
More informationREGISTERED CONSUMERS GRIEVANCES REDRESSAL FORUM AT KASUMPTI SHIMLA-9 No. CGRF/Comp. No. 1453/1/17/005
REGISTERED CONSUMERS GRIEVANCES REDRESSAL FORUM AT KASUMPTI SHIMLA-9 No. CGRF/Comp. No. 1453/1/17/005 Dated:- KBM Food Product, V/s. HPSEBL & Others. Complaint No 1453/1/17/005 1. KBM Food Product, 2.
More informationUTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Notice dated U/s130 of Electricity Act2003.
UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW In the matter of : Notice dated 12.5.2007 U/s130 of Electricity Act2003. AND In the matter of : 1. Managing Director, U.P.Power Corporation Limited,
More informationAND FOR PROCUREMENT OF POWER ON VARIABLE CHARGE BASIS
POWER PURCHASE AGREEMENT BETWEEN M/S (Insert Name of the Company) AND GOVERNMENT OF MADHYA PRADESH FOR PROCUREMENT OF POWER ON VARIABLE CHARGE BASIS 2012 Designation of Signatory of IPP TABLE OF CONTENTS
More informationBEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai
BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai-400 005 Case Nos. 16 and 17 of 2000 IN THE MATTER OF (I) PETITION OF PRAYAS,
More informationAddendum-3, dated 01 March 2018 for the recalled tender. This addendum shall be the part of the RFP, Draft PPA, ISA and LSA.
Addendum-3, dated 01 March 2018 for the recalled tender. This addendum shall be the part of the RFP, Draft PPA, ISA and LSA. Sl. No. Existing Clause no. Existing clause Amended clause (Read as) 1. Page
More informationDRAFT STANDARD POWER PURCHASE AGREEMENT FOR PROCUREMENT OF.. MW SOLAR POWER ON LONG TERM BASIS. Between... [ Insert Name of Solar Power Developer]
DRAFT STANDARD POWER PURCHASE AGREEMENT FOR PROCUREMENT OF.. MW SOLAR POWER ON LONG TERM BASIS Between.. [ Insert Name of Solar Power Developer] And NTPC Vidyut Vyapar Nigam Ltd. (NVVN). [Insert month
More informationFile No.23014/1/2017-CLD Government of India Ministry of Coal <0> OFFICE MEMORANDUM
File No.23014/1/2017-CLD Government of India Ministry of Coal IMMEDIATE BY FAX New Delhi, the 2gMarch, 2017 OFFICE MEMORANDUM Subject: Meeting of the Standing Linkage Committee (Long-Term) for Power/Sponge/Cement
More informationKERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION
KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION No. 1824/CT/KSERC/2012 Dated, Thiruvananthapuram 10 th September, 2013 Kerala State Electricity Regulatory Commission (Connectivity and Intrastate
More informationORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012)
ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012) M/s Birla Corporation Ltd. - Petitioner Unit Satna Cement Works, PO Birla Vikas, Satna 485005 (MP). V/s MP Poorv Kshetra
More informationAPPLICATION FOR LICENCE PROPOSED MODIFICATION- Lic.No SCC/47/2009-MEKOTEX (PVT) ITD
AV\ Mekotex (Private) Limited (Textile Spinning, Weaving, Denim, Processing & Printing Mills) Ref: Mekotex/556/03/14-2 Registrar NEPRA Islamabad Mar 2015 APPLICATION FOR LICENCE PROPOSED MODIFICATION-
More informationBefore The J&K State Electricity Regulatory Commission Jammu
Before The J&K State Electricity Regulatory Commission Jammu Petition No. JKSERC/37/SM of 2013 In the matter of: Implementation of the provisions of Section 49 of the Jammu & Kashmir Electricity Act, 2010
More informationCase No. 61 of In the matter of. Petition of Wardha Power Company Ltd. for Review of Order dated 17 January, 2014 in Case No.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More information765 kv S/C Mainpuri-Hapur & Mainpuri-Greater Noida Line with 765 kv/400 kv AIS at Hapur & Greater Noida and Associated Schemes/Work
TRANSMISSION SERVICE AGREEMENT FOR PROCUREMENT OF TRANSMISSION SERVICES FOR TRANSMISSION OF ELECTRICITY THROUGH TARIFF BASED COMPETITIVE BIDDING FOR 765 kv S/C Mainpuri-Hapur & Mainpuri-Greater Noida Line
More informationSri. Alex Soharab. V.F, M/s. Southern Engineering Corporation, V/830-A, Development Area, Edayar, Muppathadom , Aluva.
1 CONSUMER GRIEVANCE REDRESSAL FORUM CENTRAL REGION (Formed under Section 42(5) of the Electricity Act 2003) 220 kv Substation Compound, HMTColony P.O. Kalamasery, Pin 683 503 Phone No. 0484-2556500 Website
More informationCASE No. 337 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More information2. Chief Engineer (PPA) UP Power Corporation Limited 14 th Floor, Shakti Bhawan Ext. 14 Ashok Marg, Lucknow.Respondent
PRESENT: Petition No. 967 & 968 of 2014 and 1016 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order : 14.07.2015 1. Hon ble Sri Desh Deepak Verma, Chairman 2. Hon
More informationV/s. Uttranchal Jal Vidyut Nigam Ltd; (UJJWAL) Maharani Bagh, GMS Road, Dehradun. V/s
Petition No. 79/2007 2008-09 for DHAKRANI generating station of Uttranchal Jal 3. U.P. Jal Vidyut Nigam Ltd, Petition No. 80/2007 2008-09 for CHIBRO generating station of Uttranchal Jal 1 3. U.P. Jal Vidyut
More informationREQUEST FOR SELECTION (RfS) DOCUMENT FOR PROCUREMENT OF 50 MW POWER GENERATED FROM BIOMASS PROJECTS IN MAHARASHTRA ISSUED BY
Maharashtra State Electricity Distribution Co. Ltd REQUEST FOR SELECTION (RfS) DOCUMENT FOR PROCUREMENT OF 50 MW POWER GENERATED FROM BIOMASS PROJECTS IN MAHARASHTRA RfS No. MSEDCL/RE/BIOMASS/2018/38 Dated
More informationHPSEBL Form CS-1 (b) HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED (A STATE GOVERNMENT UNDERTAKING)
Wattage Wattage HPSEBL Form CS-1 (b) HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED (A STATE GOVERNMENT UNDERTAKING) Application and Agreement Form for other than Domestic Electricity Connection. Application
More informationCase No. 17 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Reliance Infrastructure Ltd., Santacruz (E).
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationCONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015
CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015 Shri Nilesh M. Kolhe At.Aajanti Po.Tq.Hinganghat District - Wardha.,,VS.. Complainant 1. Executive Engineer,
More informationBEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Smt. Meenakshi Singh, Member Shri I. B. Pandey, Member In the matter of: Sub: Petition No. 777 of 2011
More informationTHE JHARKHAND GAZETTE EXTRAORIDINARY PUBLISHED BY AUTHORITY 19 ASHUIN, 1928 (S) Ranchi, Wednesday the 11 th October, 2006
THE JHARKHAND GAZETTE EXTRAORIDINARY PUBLISHED BY AUTHORITY No. 559 19 ASHUIN, 1928 (S) Ranchi, Wednesday the 11 th October, 2006 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI NOTIFICATION The
More informationBEFORE THE FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES IN SOUTHERN POWER DISTRIBUTION COMPANY OF A.P LIMITED TIRUPATI
BEFORE THE FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES IN SOUTHERN POWER DISTRIBUTION COMPANY OF A.P LIMITED TIRUPATI On this the ----------- day of July 2014 In C.G.No: 201/2013-14/ Kadapa Circle Present
More informationSEVENTH AMENDMENT TO MADHYA PRADESH ELECTRICITY SUPPLY CODE, 2004
Bhopal, dated: 12 th July, 2006 No.1740&MPERC&2006. In exercise of powers conferred by Section 181 (1) of the Electricity Act, 2003 (No. 36 of 2003) and also in compliance of the notification dated 08
More informationTable 1. Nepal: Monthly Data for Key Macroeconomic Indicators.
Table 1. : Monthly Data for Key Macroeconomic Indicators. 1 1 Year-on-year change, in percent Oct Nov Dec FY to date Oct Nov Dec FY to date Oct Nov Dec FY to date ( months) ( months) ( months) Inflation
More informationCase No. 295 of Coram. Anand B. Kulkarni, Chairperson Mukesh Khullar, Member. Adani Power Maharashtra Limited (APML)
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationBEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. The H.P. State Electricity Board, Vidyut Bhawan, Shimla-4
BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA In the matter of:- The H.P. State Electricity Board, Vidyut Bhawan, Shimla-4 V/s M/S Padmavati Steels Ltd; Vill Johron, Trilokpur Road,
More informationThe Himachal Pradesh Electricity Supply Code, 2009 CHAPTER - 1 GENERAL
HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION NOTIFICATION No. HPERC/390-09 Shimla 2, 26 th May, 2009 In exercise of powers conferred by Section 50 and clause (x) of sub-section (2) of Section 181of
More informationAGREEMENT FOR SUPPLY OF HT ENERGY
AGREEMENT FOR SUPPLY OF HT ENERGY This agreement made on the.. day of.., 200 between the Development Commissioner, Cochin Special Economic Zone, Kakkanad for and on behalf of Cochin Special Economic Zone
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION NOTIFICATION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2014
104 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION NOTIFICATION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2014 ELECTRICITY ACT, 2003. No./MERC/Tech/Open Access Transmission/Regulations/2014/561. In exercise
More information(A Govt. of Maharashtra Undertaking) - CIN: U40109MH2005SGC153645
(A Govt. of Maharashtra Undertaking) - CIN: U40109MH2005SGC153645 PROCEDURE FOR DISTRIBUTION OPEN ACCESS INDEX Sr. No. Chapters Page No. 01 Preamble 02 02 Types of Open Access 02 03 Eligibility to Seek
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2016 INDEX
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2016 INDEX Part A: PRELIMINARY 3 1. Short Title, Applicability and Commencement 3 2. Definitions 3 3. Eligibility to
More informationASSAM ELECTRICITY REGULATORY COMMISSION (DEVIATION SETTLEMENT MECHANISM AND RELATED MATTERS) REGULATIONS, 2018 NOTIFICATION
ASSAM ELECTRICITY REGULATORY COMMISSION (DEVIATION SETTLEMENT MECHANISM AND RELATED MATTERS) REGULATIONS, 2018 November 2018 NOTIFICATION No. AERC 694/2018 - In exercise of the powers conferred under sub-section
More informationBIHAR ELECTRICITY REGULATORY COMMISSION
BIHAR ELECTRICITY REGULATORY COMMISSION Vidyut Bhawan-II, J.L. Nehru Marg, Patna 800 021. Case No. 39/2016 IN THE MATTER OF:- PETITION UNDER SECTION 142 OF THE ELECTRICITY ACT, 2003 FOR NON COMPLIANCE
More informationNEW DELHI. Shri M. Deena. to the National Load Despatch e Energy Certificates to
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 22/MP/2013 Coram: Shri V.S.Verma, Member Shri M. Deena Dayalan, Member Date Hearing: 2.7.2013 Date Order : 15.7.2013 In the matter Petition
More informationExecutive Summary Case No 140 of 2017
Executive Summary Case No 140 of 2017 BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION CASE NO. 140 OF 2017 1. Reliance Infrastructure Limited 2. Reliance Electric Generation and Supply Limited..
More informationBEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2017
BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION In the matter of: AT GANDHINAGAR PETITION NO. 1643 OF 2017 Petition for deciding the maintainability and admissibility under GERC (Conduct of Business)
More informationDraft JSERC (Terms and Conditions for Intra State Open Access) Regulations, 2016
Draft JSERC (Terms and Conditions for Intra State Open Access) Regulations, 2016 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION In exercise of powers conferred by Section 181 read with relevant provisions
More informationThe Chairman, Himachal Pradesh Micro & Small Enterprises Facilitation Council-cum-Director of Industries, H.P.
Format for filing reference under Section 18 of Micro, Small & Medium Enterprises Development Act-2006 & Rule 4 (6) of Himachal Pradesh Micro & Small Enterprises Facilitation Council Rules-2007. To The
More informationKERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram. November 27, Tamil Nadu Electricity Board
KERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram Present : Shri.M.K.G.Pillai, Chairman Shri.C.Balakrishnan, Member November 27, 2004 Tamil Nadu Electricity Board Petitioner Petition No.DP18
More informationCase No. 7 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationIn the matter of: M/s Rauzagaon Chini Mills (A unit of Balrampur Chini Mills Ltd.) Rauzagaon , District Barabanki (U.P.
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Petition No. 1007 /2015 Quorum Shri Desh Deepak Verma, Chairman Smt. Meenakshi Singh, Member Shri I. B. Pandey, Member In the matter of: Petition
More informationEffectiveness of the Measures. Against Theft of Electricity in EA 2003
Effectiveness of the Measures Against Theft of Electricity in EA 2003 Submitted by: Hasnain Rangwala Date: 14/01/2011 1 P a g e INDEX Sr. No. Topic Pg. No. 1 Introduction 3 2 Different provisions for theft
More informationBEFRE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA.
BEFRE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. In the matter of- M/s Ambuja Cements Limited, Darlaghat, Tehsil Arki, District Solan (H.P) through Sh.Chanchal Kumar its President-cum-Authorised
More informationGovernment of Himachal Pradesh Department of Cooperation NOTIFICATION
(Authoritative English Text of this Department Notification No Coop. A(2)-2/99(S)-II dated 11-1-2007 as required under clause (3) of Article 348 of the Constitution of India). Government of Himachal Pradesh
More informationThe Orissa Electricity (Duty) Act, 1961.
The Orissa Electricity (Duty) Act, 1961. An Act to levy a duty on the consumption of electrical energy on the State of Orissa. Be it enacted by the legislature of the State of Orissa in the Twelfth year
More informationCase No. 64 of Shri. V. P. Raja, Chairman Shri. Vijay L. Sonavane, Member ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail: mercindia@mercindia.org.in
More information42, Free Press House, 1, Kalpana Square, 215, Nariman Point, Bhubaneswar Mumbai AUDITORS REPORT
To AUDITORS REPORT The Board of Directors, Western Electricity Supply Company of Limited Plot No.N/122, IRC Village, Nayapalli, Bhubaneswar 751 012. We have audited the attached Balance Sheet of Western
More informationTHE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO)
THE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO) (NO. 4/99) (Issued under OERC Order Dt. 31.03.99 in Case No. 25/98) Western Electricity Supply Company of Orissa Limited Registered office:
More informationFigure 1. Nepal: Recent Fiscal Developments
Figure 1. : Recent Fiscal Developments Strong revenue growth combined with subdued capital spending kept the budget in surplus the past years. Fiscal Performance Revenue Capital expenditure 1 Current expenditure
More informationCENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION No.L-7/105(121)/2007-CERC Dated the 25 th January, 2008 In exercise of powers conferred by Section 178 of the Electricity Act, 2003 and
More informationBhopal dated 6th August, 2004
Bhopal dated 6th August, 2004 No.2118/MPERC/2004. In exercise of the powers conferred by section 181 (2) (ze, zg) read with section 62(2) and 64 (1) of the Electricity Act, 2003 enacted by the parliament,
More informationPUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH. Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh, Member
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No.70 of 2014 Date of Order: 22.04.2015 Present: Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh,
More informationCase No. 135 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member. (1) M/s B.S.Channabasappa & Sons...Petitioner 1
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel No 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercgovin Website:
More informationRequest for Proposal Document. For Selection of Developer for Setting up of
Request for Proposal Document For Selection of Developer for Setting up of 8 MW Solar PV Power Plant on the land of Procurer at Village Jaun Samana, Greater Noida For Procurement on Long Term Basis by
More informationPUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No. 58 of 2017 Date of order: 11.06.2018 Present: Ms. Kusumjit Sidhu, Chairperon Sh. S.S. Sarna, Member
More informationCase No. 02 of Shri V. P. Raja, Chairman Shri S. B. Kulkarni, Member Shri V. L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No. 1, 13th Floor, Cuffe Parade, Mumbai - 400005 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in Case
More informationTAMIL NADU GOVERNMENT GAZETTE. Part VI --- Section 2 (Supplement)
TAMIL NADU GOVERNMENT GAZETTE PUBLISHED BY AUTHORITY No. 30A CHENNAI, WEDNESDAY, AUGUST 3, 2005 Aadi 18, Parthiba, Thiruvalluvar Aandu - 2036 Part VI --- Section 2 (Supplement) NOTIFICATIONS BY HEADS OF
More informationCENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 211/MP/2012
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 211/MP/2012 Coram: Dr. Pramod Deo, Chairperson Shri S. Jayaraman, Member Shri V.S. Verma, Member Shri M. Deena Dayalan, Member Date of Hearing:
More informationThe Structure of Electricity Costs and Pricing Policies in Albania
The Structure of Electricity Costs and Pricing Policies in Albania Indrit Baholli Tariff and Prices Department, ERE Tirana, September 19, 2007 1 Role of ERE in Electricity Structure ERE plays a key role
More information'8. Sue ~ /44 tie. HIMACHAL PRADESH SUTE ELECTRICITY BOARD LIMITED -, (A State Govt. Undertaking)
L -. ~~~~-----~,~----"'- --.----,---~--,~--- '" SeLl &~,...,I."~--..."'. '"'_ "",,~~w,~~miii..w""""".~"-"-,*-#"rr,. 1' '8. Sue ~ /44 tie HIMACHAL PRADESH SUTE ELECTRICITY BOARD LIMITED -, (A State Govt.
More informationBEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION. PETITION No. CP 02/17
BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION PETITION No. CP 02/17 In the matter of : Non implementation of the order dated 29.05.2017 in P/005/2016 of Kerala State Electricity Ombudsman.
More informationUTTARAKHAND POWER CORPORATION LTD. BID DOCUMENT FOR PURCHASE OF POWER COMMERCIAL AND GENERAL CONDITIONS
UTTARAKHAND POWER CORPORATION LTD. COMMERCIAL AND GENERAL CONDITIONS SPECIFICATION NO. UPCL/CGM-04/10-11 (POWER PURCHASE) Dated 26.07.10 Bid Document Available on the UPCL s web-site (www.upcl.org) Chief
More information