Permit to Work Systems

Similar documents
PRO Hot Work

Health and Safety Policy

Environmental, Health and Safety. UNC Charlotte Hot Work Program (Welding, Cutting, and Brazing)

Permit to Work System Training for Supervisors Managing Hot Works & Other Permits - Presenter s Guide

Making sense of risk Risk engineering. Marine hot work Permit to Work (PTW) systems

HOT WORK 1. PURPOSE 2. SCOPE 3. KEY TERMS

PRO Hot Work

Hot Work Program. Purpose of Procedure:

HOT WORK MANAGEMENT PROGRAM

HEALTH & SAFETY HOT WORK INSTRUCTIONS

Sample appointment of Site Manager letter COMPANY NAME & LOGO/LETTERHEAD. OCCUPATIONAL HEALTH AND SAFETY ACT, 85 of 1993

Permit to Work Procedure

Safety & Risk Management

HOT WORK PROGRAM OSHA

Roger Williams University Hot Work Plan

Villanova University Department of Environmental Health and Safety Policy and Procedure Manual

Hot Work Procedures. Competent means possessing knowledge, experience and training to perform a specific duty.

HSE - Permit to Work Procedure

HOT WORK PERMIT PROGRAM REVISED AND DISTRIBUTED BY: THE UNIVERSITY OF VERMONT DEPARTMENT OF PHYSICAL PLANT TRAINING & COMPLIANCE OFFICE

Hot Work Procedure. Work Health and Safety Policy Responsible Officer. Executive Director, Infrastructure Services and Development Approved by

Using the WPTW System: Frequently Asked Questions

Permit to Work Major Hazard Standard

Coles Express Work Clearance: Induction for Contractors

Fire caused by Hot Works. A guide to loss prevention

Non Electrical Hot Work Program

SUNY Geneseo ENVIRONMENTAL HEALTH & SAFETY

(WELDING, CUTTING, AND OPEN FLAME WORK)

TAMPA ELECTRIC COMPANY ENERGY SUPPLY HOT WORK PERMITTING PROGRAM

LAWS OF SOLOMON ISLANDS CHAPTER 74 SAFETY AT WORK ARRANGEMENT OF SECTIONS PART I INTRODUCTORY PART II GENERAL DUTIES

Title: Safe Work Procedure. Function: Ecology & Safety No.: CTC-SAF-037 Page: 1 of 6 Reviewed: 3/1/2017 Effective: 4/1/2017 Supersedes: 3/20/16

Safe Code of Practice. No.05 Hot Works Procedure

Hot Work Program. Program Origination: October, 2017

RISKTOPICS. DISCUSSION For the purposes of this document, hot work: Management practices: Hot work Property and Business Interruption January 2013

Desert Research Institute Hot Work Permit Program

Hot Work Program June 2017

Hot Work Permitting Procedure

HOT WORK GUIDELINES 3. MANDATORY AREAS REQUIRING HOT WORK PERMITS Within the Service Station Site

KENNECOTT UTAH COPPER

Hot Work Program. SUNY Canton. Purpose

Hot Work Safety and the Permitting Process. Leaders Guide and Quiz

2007 No. 320 HEALTH AND SAFETY

MCW s Hot Work Permit Program

SAFETY AND HEALTH STANDARD HOT WORK PERMIT Effective Date: 06/10/10 Standard: 16.1 Document Number: KUCSH0040 Rev: 04

"HOT WORK SAFETY AND THE PERMITTING PROCESS"

University of Central Missouri Hot Work Permit Program

Areas that have been designed and constructed for performing open-flame or spark-producing work.

Safe Work Permits Procedure

Hot Work Safety Program

DUQUESNE UNIVERSITY HOT WORK PROGRAM

WORKPLACE SAFETY AND HEALTH ACT (CHAPTER 354A) WORKPLACE SAFETY AND HEALTH (WORK AT HEIGHTS) REGULATIONS 2013

HOT WORK SAFETY GUIDELINE

Hot Work Program. Roles and Responsibilities. Management. PAI Responsibilities

Hot Work Policy & Procedure

PURPOSE:... 3 EMPLOYEE CLASSIFICATIONS:... 3 OUTSIDE PERSONNEL (I.E., CONTRACTORS):... 4 HOT WORK REQUIREMENTS:... 4 EMPLOYEE TRAINING:...

HSE guidelines. SApril 2017 WORK PERMITS

Guide to Hot Work NFPA 51B Understanding the new requirements after July 1, 2018

MAURITIUS FIRE AND RESCUE SERVICE ACT Act 13 of February 2014

Classification: Public Rev. 00 June 2018 Page 1 of 25

HOT WORK PERMIT PROGRAM AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY

Hot Work Permitting Program

HOT WORK PROGRAM October 2016

Risk Control Guide HOT WORK

OFFICE OF STATE HUMAN RESOURCES

HOT WORK PERMIT PROGRAM AUBURN UNIVERSITY SAFETY AND HEALTH RISK MANAGEMENT AND SAFETY

Annex I To Loughborough University Estates Services Health and Safety Policy

The Ohio State University. Hot Work Permit Program (Welding, Cutting and Brazing)

Hot Work Permit Program

KENNECOTT UTAH COPPER

NORTHERN IRELAND ELECTRICITY SAFETY RULES GUIDANCE DOCUMENT INSTRUCTION FOR OPERATIONS OR WORK ON THE PREMISES

Hot Work and Welding Management Procedures Attached to FIN-INS Introduction. 1.1 Purpose

Hot Works Permit. 1. General Details* (to be completed by Applicant)

General Hot Work Program Guidelines. Lyndsey Beaudin

Hot Work Permit Guidelines

Legal Obligations in Construction Contracts Concluded by Employers Operating in Egypt

CHAPTER 220 THE FACTORIES ACT. Arrangement of Sections.

SAFEWORK PRACTICES SAFE WORK PERMITTING CAT A-1 SOP #6

HOT WORK PROCEDURE. A Page 1 of 20

PROCEDURES FOR HOT WORK PERMITS, HOT WORK DISPENSATIONS & GAS FREE CERTIFICATES

. A. report to the security guard B. inform the foreman C. drink more water D. apply for a Permit-to-work.

Electricity Supply (Safety and Network Management) Regulation 2014

Prevention of Hot Work Fires in Healthcare Facilities. Sherie Van Slyke Engineering Specialist

Coal Mining Safety and Health Act 1999

IWU PHYSICAL PLANT SAFETY PROGRAM

Process: Permit to Work PS-OP-RC-2011

HOT WORK SAFETY GUIDE. Specific responsibilities relating to hot work operations are outlined below.

STANDARD PROCEDURE INSTRUCTION

Loss Prevention Standards

RUTGERS UNIVERSITY HOT WORK PERMIT PROGRAM

4.1 PERMIT TO WORK PROCEDURE

CHAPTER 1 GENERAL. 1

University of Delaware.

RC 7 V2 3/12/07 3:41 am Page 1 RC7 for hot work

University of Nevada, Reno

RUTGERS UNIVERSITY HOT WORK PERMIT PROGRAM

HSE guidelines. SApril 2017 WORK PERMITS

THE CITY OF MANZANITA DOES ORDAIN AS FOLLOWS: SECTION 1: ADMINISTRATION AND ENFORCEMENT. 1.1 Title

EDITION. March 2011 WORK PERMITS. Health. Safety HSEW A WAY OF LIVING. Standards for professionals, be aware!

Work Health and Safety Act 2011 No 10

PURPOSE To specify the minimum requirements for controlling risks associated with Hot Work activities.

Version 3.0 December Self-Lay Agreement. for services connecting to our existing network. Scheme Location Reference Date

Transcription:

Permit to Work Systems Guidance Note 12 Jul 16 1

Permits to work systems Introduction This Guidance Note gives practical information about permit to work systems. A sample template has been included in Appendix 1. If you wish to use this template to construct your own documents, you must ensure that all references to Alcumus SafeContractor Accreditation have been removed and the final documents are clearly incorporated into your existing safety management system. A permit to work (PTW) is a formal written safety control system that is implemented to help prevent accident or injury to personnel, prevent damage to plant/machinery and to prevent damage to a product or to a client site. This is, in particular, required when the work has foreseeable high risk content. The operation of a permit to work system is particularly useful when contractors are on site i.e. for maintenance or installation purposes. The aim of a permit to work system is to remove both unsafe conditions and human error by imposing a formal system which requires formal action. Typical areas / work activities that should be covered by a permit include: Hot works Roof works Confined spaces High Voltage electrical work Asbestos Excavation works Lift works Pressure systems Demolition works Work on scaffold towers, mobile elevated working platforms (MEWPs) Work in isolated locations, or areas with difficult access or those at high levels. Work in the proximity of, or involving, explosives or highly flammable substances. Work involving contractors in any of the above activities on or about your premises Key Points Any person in control of a premises could be required to enforce the use of a Permit to Work. Permits should only be issued by a competent person who understands the risks and the necessary control measures to put in place (Authorising Person). A permit should be task specific and the necessary risk assessments and method statements still need to be done. A permit is not a replacement. 2

Permits should only be in place for a limited duration and be clearly dated and with specific conditions attached. Permits should not be transferred to other people or companies. Any safety precautions required should be done prior to work commencing. The permit should state these requirements, for example, electrical isolation or discharge of pressuring systems. The authorising person should only sign and date the permit when they are satisfied that all precautionary measures have been taken. If risks are too high, for example because of bad weather conditions or dangerous structure, then a permit should not be issued. When operating several permits at once, a Permit Register should be used to prevent conflicts in work activities. Each permit should have a unique reference number. All permits should be retained by the authorising person. An example of a General Application permit is provided at the end of this guidance note. You can find examples of specific permits Guidance Notes 5 & 19 Confined Spaces and Hot Works. Permitted conditions Listed below are some examples of control measures that should be considered when issuing a permit (not exhaustive): Roof works Testing roof fragility Edge protection Prevention of falls of materials or objects Personal Protective Equipment. Atmospheric monitoring Isolation Emergency procedures Adequate means of access. Hot works Good housekeeping Use of protective curtains All 'hot works' equipment should be regularly maintained and inspected Ensure a competent person visits the area after the hot works has finished to ensure that no smouldering embers or hot surfaces remain Provision of suitable fire extinguishers Ensure that sprinklers (if installed) are isolated and reactivated after the works. 3

Isolation Once the permit comes into operation, where necessary, warning signs and often a lookout need to be posted around the area where work is being undertaken. When working on machinery and / or electrical systems, they should be physically isolated i.e. locked off (possibly with the contractor's own padlock) etc. When plant is isolated, it should be stated as being such on the permit. Cancellation of a permit When the operations laid out in the permit have been completed, it should be cancelled immediately and returned to the originator. They should ensure that the work detailed on the permit has been done satisfactorily. They should then sign off the permit to ensure that it is fully cancelled. NOTE: This may only be done when all personnel and equipment involved in the work detailed on the permit has been removed from the permit working area. Returning to service The plant or work area etc. may now be returned to service. The person responsible for the plant or work area must be satisfied that it is safe to do this - this person might require a final inspection before countersigning the final close of the permit. Training All staff should be made aware of the importance of the use and procedure of permit to work systems when they are in place or introduced into the workplace. Overview Permit to work forms should incorporate the following features: The permit must specify who is to do the work, the time for which it is valid, the work to be done and the necessary precautions During the permit, no person shall work on any plant not covered by the permit No person shall carry out work which is not authorised by the permit. If there is to be a change in the work, the permit must be amended / cancelled. This can only be done by the authorised originator of the permit There must be liaison with other work areas whose activities could be affected by the permit system 4

Where the permit to work is to be carried out on part of a site or on specific plant, the limits of the work must be clearly marked Permits must take into account all contractors on site, who should be briefed prior to the commencement of work. Further Guidance Guidance on permit-to-work systems: A guide for the petroleum, chemical and allied industries HSG250 ISBN: 9780717629435 Available at: http://www.hse.gov.uk/pubns/books/hsg250.htm http://www.hse.gov.uk/safemaintenance/permits.htm http://www.hse.gov.uk/humanfactors/topics/ptw.htm 5

Appendix 1 Permit to work Permit Number: Contracting Company: Location of work: Scope of works: Permit valid from: Time: Date: Permit valid to: Time: Date: Electricity Gas Water Air Fire Alarm System Fire Sprinkler System Other: The following services have been isolated / locked off Yes / No Point of Isolation Name (print) Name (signature) Date Other Precautions (e.g. public safety, traffic movement, lone working etc.) Tools & Equipment to be used (e.g. Scaffold, PPE, Welding sets, 110V Tools etc.) Before work starts All the above boxes must be completed and permit signed by both Client Authorising Person and Contractor Site Supervisor before work commences. Time: Contractor Site Supervisor Client Authorising Person On Completion of work Work has been completed, all isolations reinstated, and all persons under my control have been withdrawn. Time: Contractor Site Supervisor Client Authorising Person 6