THE COMMON LAW OF RESTITUTION

Similar documents
To Discharge By Performance

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied.

Contracts II Professor Keith A. Rowley William S. Boyd School of Law University of Nevada Las Vegas Spring 2003

QUANTUM MERUIT SOME PITFALLS

TYPES OF MONETARY DAMAGES

BETWEEN: CLIFFORD WHITING CLAIMANTS EMILY WHITING

In the contractual context partial failure of consideration is concerned with. Partial Failure of Consideration JOHN TARRANT *

Will Barkerʼs 1015LAW Revision

WEEK 4-6: REMEDIES FOR BREACH

EQUITABLE RELIEF IN THE LAW OF HIRE-PURCHASE

Question 2. Delta has not yet paid for any of the three Model 100 presses despite repeated demands by Press.

Answer A to Question 1

The plaintiff must show that his loss was one which resulted from a breach of contract by the defendant (a direct causal link).

Discharge of Contract Performance, Breach, Frustration Introduction

California Bar Examination

Powell v Braun [1954] 1 All ER 484; Turriff Constructions Ltd v Regalia Knitting Mills Ltd (1971) 9 BLR 24.

!"#$%&'(&)'*+%*+,& /G$+:'($"0B",E$"#'8E,",0"?$+%'9*,$"..."HH" I'('9B0+%*,'09"..."H>" ?E$")*+02"/4'&$9:$"#J2$"..."HK"

California Bar Examination

Contents. Table of Statutes. Table of Secondary Legislation. Table of Cases. The Agreement to Contract

18. PERFORMANCE AND DISCHARGE. Presented by Marisa Schatz, Georgiana Battisonnicol And Nancy Mora 10/28/2015

CONTRACTS AND SALES QUESTION 1

RESTITUTION REMEDIES. Westdeutsche Landesbank Girozentrale v Islington London Borough Council and Other Cases JONATHAN ROSS

California Bar Examination

CONTRACTS. Miscellaneous applications of ACL for Contracts:! 6 PROMISSORY ESTOPPEL! Assumption! Detrimental Reliance!...

Contents. Table of Statutes. Table of Secondary Legislation. Table of Cases. The Agreement to Contract

(LAW COM. NO. 121) PECUNIARY RESTITUTION ON BREACH OF CONTRACT

Opening Assignment. The Bargain. Contracts. Elements of Contract. Ending an Offer. What is an Offer 10/31/2017

IN THE HIGH COURT OF JUSTICE BETWEEN AND TECU CREDIT UNION CO-OPERATIVE SOCIETY LIMITED

LAW OF CONTRACT. LPAB Summer 2017/2018 Week

Table of Contents. Preface... Table of Cases...

by UPPC, Entebbe, by Order of the Government. Hire Purchase Act THE HIRE PURCHASE ACT, ARRANGEMENT OF SECTIONS. PART I PRELIMINARY.

California Bar Examination

REVIEW QUESTIONS TRUE/FALSE QUESTIONS (CIRCLE THE CORRECT ANSWER)

The definitive version of this article is at (2003) 66 Modern Law Review 284, available electronically at

PANCHAKSHARI s PROFESSIONAL ACADEMY Pvt. Ltd. CA CPT Law Unit 12 Test

Special Topics in Small Claims

California Bar Examination

Professional Practice 544

Creation of the K a. Statute of Frauds land part performance one year debt 500 b. Offer master of the offer revoke mailbox rule absence of terms

BUSINESS LAW GUIDEBOOK

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because:

Penalty Clauses: What is left? Jonathan Owen

3. Avoidance of certain provisions in agreements. 9. Restriction on recovery of goods otherwise than by action.

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE June 19, 2008 Session

Introduction to Contracts

OVERVIEW OF CONTRACT LAW

7/23/2010. The. Contract. Sources of contractual obligations

Book Review: The Effect of War on Contracts

Basic Guide to Wisconsin Small Claims Actions

Marks & Spencer plc v BNP Paribas Securities Services [2015] UKSC 72, [2016] AC 742

DOCTRINE OF ULTRA VIRES-EFFECTS AND EXCEPTIONS

Professional Practice 544

STATE OF MICHIGAN COURT OF APPEALS

Present: Hassell, C.J., Lacy, Keenan, Koontz, Kinser, and Lemons, JJ., and Carrico, S.J.

ANSON S LAW OF CONTRACT. 29th Edition SIR JACK BEATSON

Torts (Interference with Goods) Act 1977 Chapter 32

Company Law: Conwest Exploration Company Limited et al. v. Letain, (1964) S.C.R. 20

IN THE SUPREME COURT OF TEXAS

LEGAL ENGLISH Unit 7 Breach of contract

Breach and Repudiation (Student Copy)

CHAPTER 60:02 TITLE TO LAND (PRESCRIPTION AND LIMITATION) ACT ARRANGEMENT OF SECTIONS

IN THE HIGH COURT OF JUSTICE GARY LEGGE AND MAUREEN LEGGE. Between CHRIS RAMSAWACK AND WESTERN SHIP AND RIG SUPPLIES LIMITED

Carriage of Goods Act 1979

Drafting New York Civil-Litigation Documents: Part IX The Answer

IN THE HIGH COURT OF JUSTICE BETWEEN AND. Before: The Hon. Justice Nolan Bereaux. Mr Gaston Benjamin for Plaintiff Mr Carlton George for Defendants

Note: At the start say Presuming all the elements of a valid contract are satisfied

Topics this week. Part A Classification of Contract Terms. Part B Performance, Breach & Right of Termination

Section 2(a)(iii) of the ISDA Master Agreement: its enforceability and effect

Proposed Amendment in Section 28 of The Contract Act, 1872

All BATCHES DATE: (B-2, P-1) MAXIMUM MARKS: 60 TIMING: 2 Hours

Do you have a contract checklist? 3 How do you get out of the contract? 5. Remedies Checklist 12

APPEAL FROM DECISION OF SOCIAL SECURITY APPEAL TRIBUNAL ON A

Unjust enrichment? Bank secures equitable charge where it failed to get a legal charge: Menelaou v Bank of Cyprus [2015] UKSC 66

THE EQUITABLE DOCTRINE OF RELIEF AGAINST FORFEITURE: A COMMENT ON FOUR RECENT ENGLISH AND AUSTRALIAN DECISIONS

STATE OF MICHIGAN COURT OF APPEALS

Termination of an Offer

STATEMENT OF THE CASE. Lombardo responded with a counterclaim against Madison for unjust enrichment and, on

Legal Purpose and Proper Form

Differences between the Civil and Common Law: Part 2: Delay Damages and Taking-Over. Cremona Cotovelea Nina Tsaturova Jeremy Glover

Vee Networks Ltd. v Econet Wireless International Ltd. [2004] APP.L.R. 12/14

We also consider domicile a part of conflicts, although sometimes not as a separate subject. DOMICILE

LIMITATION OF LIABILITY BY ACCOUNTANTS

Did You Blow the Statute of Limitations?

CONVEYANCING LECTURE ON 31 JULY 2006

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context

SKRINE BREACH OF CONTRACT: TERMINATION AND OTHER OPTIONS. 10 December LEE SHIH ADVOCATES & SOLICITORS

BELIZE LIMITATION ACT CHAPTER 170 REVISED EDITION 2000 SHOWING THE LAW AS AT 31ST DECEMBER, 2000

LAW OFFICE OF MARK ROYSNER Mulholland Highway, Suite 382 Calabasas, CA

ARLINGTON COUNTY CODE. Chapter 51 HOME IMPROVEMENT

Contractual Clauses That Impact Disputes. By David F. Johnson

A LITIGATOR S GUIDE TO DAMAGES January 17, 2017 CONTRACT DAMAGES. *With special thanks to Lesley Campbell, Student-at-Law OVERVIEW

California Bar Examination

Consideration sits alongside, offer and acceptance to form a legally binding contract.

QUANTUM MERUIT QUANTUM MERUIT FOR BUILDING SERVICES PROVIDED UNDER AN UNENFORCEABLE OR TERMINATED CONTRACT INTRODUCTION.

MAY 2012 BUSINESS AND CORPORATE LAW SOLUTION

Liquidated Damages in Delaware

The Specific Relief Act, 1963

Before the court is defendants Margaret S. Marean and Erion H. Marean' s motion for

Emily M. Weitzenboeck, 2011 Norwegian Research Center for Computers & Law

IC Chapter 3. Mechanic's Liens

Transcription:

THE COMMON LAW OF RESTITUTION SIXTH STUDY PACK CONTRACTUAL BENEFITS Where the plaintiff has him/herself conferred the benefit on the defendant. Where the plaintiff conferred a benefit under an ineffective transaction. Westdeutsche Landesbank Girozentrale v. Islington LBC [1996] A.C. 669 Benefit conferred in accordance with contract. Recovery usually inherent in action to escape from the contract e.g. misrep. Some situations- breach-may be separate stage. CONTRACT DISCHARGED BY BREACH Restitution only once contract has been terminated. Money recovered only if there s been a total failure of consideration. Services- action for quantum meruit and no problem with unwanted benefit defencebenefit obviously requested under contract. (i) The innocent party money - Action for money had and received. Can recover if total failure of consideration. Giles v. Edwards Defendant had contracted to sell to plaintiff all the corded wood growing on a particular estate- defendant had all wood and corded some and plaintiff paid 20 guin. Defendant didn t cord all and plaintiff recovered none of the wood. Court held that plaintiff would recover because total failure of consideration. Consideration must wholly fail. Margaret Halliwell 2006-03-06 1

If work abandoned half-way-through- can t terminate contract and seek contract price paid- just to pursue remedy in breach. No objection to restitutionary claim on grounds that it enables plaintiff to escape a bad bargain. Wilkinson v. Lloyd Plaintiff agreed to buy shares in a mining co from defendant. Plaintiff paid shares but before transfer, directors passed resolution preventing any transfer of shares in defendant s name. Breach on defendant s part because should have sought consent of directors first. Market value of shares fell so rather than damages or specific performance - plaintiff tried to recover money paid. Allowed and therefore escaped the consequences of bad bargains. Total failure of consideration. Compare with confinement of reliance based damages in contract. chattels- Difficult problem- where delivery of chattel- does intermediate enjoyment of chattel prevent plaintiff from claiming total failure of consideration. e.g. Hunt v. Silk. A had agreed for 10 to let a house to B. A was to execute repairs and draw up lease within 10 days. In meantime B paid 10 and went into occupation. A didn t do repairs, nor execute the lease. A tried to recover 10. court said couldn t recover and had to sue for breach. Intermediate enjoyment meant party couldn t be restored to status quo. In relation to chattels where defeat as to title then will be a total failure of consideration. Rowland v. Divell Plaintiff bought car from defendant- used for several months- discovered defendant hadn t got good title- gave it up to actual owner & claimed purchase price. C/A allowed rejected Hunt v Silk. L.J. Atkin- plaintiff hadn t got what bargained for lawful possession of car- had only got de facto possession. Contrast with Yeoman Credits v. Apps Def bought car on HP from dealer, term excluded all liability for worthiness. Defendant- kept car- refused to pay further instalment. Car taken off him by HP company and he was sued. Defendant counter-claimed in restitution. C/A- was fundamental breach but not failure of consideration. Here no defect as to title but only as to quality. Law Commission No. 65- recommended change in law. Where defective title to chattels- whilst P could recover price paid, ought to account for amount of enjoyment or use made. Margaret Halliwell 2006-03-06 2

Rec only in working paper. Why a requirement of total failure of consideration? Explanation- court reluctant to apportion money paid against benefit conferredprobably because of complexity. Led into problem of valuing benefit. Reasons not very convincing- court provision to apportion and value benefit under frustration. Law Commission- Part 3- failed to substantially perform but has conferred benefit- Innocent party should recover money paid- subject to reasonable value for benefits conferred being given. Following Law Commission Report No 121- changed mind and rejected proposal. Leave law unchanged, but didn t explain why. services rendered - Damages always available for breach and if contract severable into parts- can recover the agreed sum for severed part in normal contractual claim. Problem where contract is entire. Agreed sum only available after complete performance. Quantum meriut for value of services rendered but unclear authority. Planche v. Colburn Defendant had engaged plaintiff to write a book. Plaintiff ready and willing to complete - when had done part defendant said terminated series of which book was to be part and refused to pay. Court said plaintiff could recover quantum merit even though hadn t handed out book that he d written. Could be an example of status quo, reliance based damages. Very difficult to say basis of claim is unjust enrichment because no enrichment no part of book ever received. Chandler v. Boswell Contract to build excavation tunnel. After much of work done-contractors not allowed to complete. Held- could recover either damages for breach of contract or quantum merit for the value of work done. De Barnardy v Harding Defendant right to advertise and sell tickets for seats to view funeral of Duke of Wellington. Plaintiff incurred expenses in preparing advertisement when, in breach, defendant told him not to proceed. Albeit described as quantum meruit- but equally could be reliance based damages. Margaret Halliwell 2006-03-06 3

Plaintiff can use restitution action to get more than he would get in damages, Lodder v. Slower. Good example in the American case: Boomer v. Muir Boomer a sub-contractor of Muir, engaged in building a large dam. Terms of contract- Boomer to receive monthly progress payment on an agreed schedule- but after 18 months- argument & Boomer left site. Court- fundamental breach by Muir in failing to provide materials & Boomer entitled to walk off site and treat contract as terminated. 258,000 dollars on a quantum merit- even though only extra 20,000 if he d stayed on and completed. Innocent party can recover more on quantum meruit than under contract law. Fairer to give proportion of contract price. (ii) The Party in breach money - If innocent party has terminated for breach can party in breach recover payment already paid under terms of contract. General rule not entitled to bring an action on grounds of total failure of consideration. Remedy depends on distinction between part payment and earnest payment. Was money as deposit or in guarantee and security for performance of contract? Earnest payment is guarantee, part-payment is any other money. Howe v. Smith General rule earnest payment not recoverable, whereas partpayments are. Dies v. British & International Mining & Finance - Part-payment of purchase price-deposit is recoverable subject to the innocent party s right to set-off a claim in damages. Mr J Stable: Matter of construction which category payment is in and is dependent on intention of parties. More likely to be construed as earnest payment where expressed as forfeiture clause. Cases where an earnest payment will also be recoverable if it s shown to be so penal that it s unconscionable for the other person to return the benefit. Margaret Halliwell 2006-03-06 4

Stockloser v. Johnson Plaintiff agreed to buy plant & machinery from defendant. Purchase by instalments and if defaulted for more than 28 days clause said seller could terminate, keep instalments and retake possession of plant and machinery. Defendant did this. Plaintiff brought action for return of instalments because was forfeiture clause was penal. Equity should grant relief as with penalty clause. C/A refused on the facts but majority reasoning of Denning L.J. and Somerville L.J.J.: -in principle such relief would be available. - An equity of restitution Denning L.J. two conditions must be satisfied 1) Clause must be penal in nature what is forfeited must be out of all proportion must be out of all proportion to loss suffered. 2) Must be unconscionable to retain the money. Both acknowledged that unjust enrichment of innocent party at expense of party in breach. Minority reasoning LJ. Rimer more than just inequitable before earnest payment can be recovered- should be fraud or sharp practice. Authority doubted in Galbraith v. Mitchenall but Dubious authority, relied on CA authority on agreed damages, which was subsequently overruled by the HoL anyway. Some support in Shilo Spinners v. Harding Obiter dicta of Lord Simon: unfettered and unlimited jurisdiction to relieve against contractual forfeitures and penalties Lord Diplock in Scandinavian Trading v. Tankeer Co v. Flota Petrolera Ecuatioriana, The Scaptrade [1983] 2 A.C. 694 Lord Diplock rejected this view as a : a beguiling heresy services rendered - Can party in breach recover for the value of his services prior to breach. Have to distinguish between severable and entire contract. Normal contractual action for agreed sum if severable. Entire contract- won t be able to bring action for agreed sum. Margaret Halliwell 2006-03-06 5

Classic case is Sumpter v. Hedges Plaintiff builder contracted to erect buildings for lump sum of 565. Entire contract. After work done to the value of 330 became insolvent and told defendant couldn t complete. Defendant accepted as repudiatory breach - got somebody else to finish work using materials which plaintiff had left. Plaintiff claimed quantum meruit. Plaintiff couldn t recover in respect of work done- defendant had no choice but to accept. Therefore, no incontrovertible benefit. Fact that work had been done couldn t be used as evidence of a new contract to pay for work actually done. Plaintiff could recover payment for building materials left behind- quantum valebat. Practically- defendant could retain building for little money. Injustice of rule perhaps illustrated in Bolton v. Mahadeva? Plaintiff agreed for 560- to install central heating. Central heating system did not work properly so defendant terminated. Could plaintiff agree on quantum meruit for value of work done? CA - entire contract and therefore no recovery for quantum meruit. Rejected view that contract had been substantially performed. Defendants would have to pay 174 to put the central heating system right. - so defendants got cheap central heating system for 174. Hoenig v. Isaacs Exception - rule of contract- where performance substantial - can claim agreed sum subject to set-off. (e.g. install effective radiators but fail to paint them) Is this present position satisfactory? 3 policies underlying 1) would encourage party in breach to break entire contract. 2) If entire- then to allow remedy before completion - would go entirely to party s intentions or agreed allocation of risk. 3) Negatives any question of unjust enrichment by very fact of breach. Counter arguments Margaret Halliwell 2006-03-06 6

1) damages a sufficient deterrent to breach as normal. 2) Parties haven t consciously dealt with the issue of part performance. Law commission Report 121- present law unsatisfactory - Party should be entitled to quantum merit whilst leaving intact innocent party s right to claim damages. Would depend on whether party in breach had conferred a benefit. Note four points: 1) Wider scope of remedy- doesn t just apply to party in breach of entire contract also apply to each stage of a severable contract. Would extend to part-performer who isn t in breach but has no remedy under existing law. 2) Remedy won1t apply where contract is still on foot - it must be terminated by innocent party. 3) Remedy won t apply subject to one exception where already has remedy under existing law. Exception is Sumpter v Hedges, quantum valebat. 4) Won t apply- where parties have contracted out of it- i.e. they ve made clear where risk of part performance lies. 5) Won t apply to contracts for sale of goods and carriage of goods by sea. 6) What s meant by benefit and how valued - unlike Law Reform (Frustrated Contracts) Act, s.163 proposal is that benefit should not be considered valuable benefit. Valuable considered to be too vague. Nor should there be restriction to substantial benefit. Valuation largely left to court.: party who has conferred a benefit shall be entitled to a sum representing the value of what he s done to the person who has the benefit of it - shouldn t be linked to pro-rata contract principle - but if excludes pro-ratawould allow contract breaker to be better off by partial rather than complete performance. Commission, therefore, recommended that should be on upper limit of a prorata proportion of contract price. 7) Question of set off or counter-claim for damages - Commission clear that innocent party would be able to claim. Report gives some hypothetical examples: a) Party in breach, Y, makes bad bargain. Y agrees to do work for X for 4,500. Does 2/3 of work then, in breach, refuses to continue. Market value of work already done is 5,000. Margaret Halliwell 2006-03-06 7

Had Y completed the work done would have been worth 7,500. Although the value of the work done is 5,000, the pro-rata contract price provides the upper limit. 2/3rds of 4,500, upper limit- 2/3 rd of that 3,000. Most he can recover is 3,000- but set off damages. The contract damages available to X is measured as 2,500-1,500 = 1,000. 2,500 represents the price X needs to complete ( 7,500-5,000) 1,500, the costs saved, represents the difference between the contract price and the value adjudged under this provision.- which are costs of completion 2,500 minus costs saved 1,500 (represents difference between contract price and value under this provision i.e. 4,500 & 3,000) Upper limit 3.000-1,000 = 2,000. b) Party in breach (Y) makes good bargain. Agrees to do work for X for 19,000. Does 2/3rds work and refuses to continue. Value of work done is 15,000 but if he d completed value of work done f work would only have been 7,500 Can recover 5,000- because upper limit i.e. 2/3rds of contract price is actually set at 6,000. No offset contractual damages for X - because would only have to pay 2,500 to complete. Report not yet implemented- but restitutionary analysis has been used. Ch does seem to be unsatisfactory remedy. Remember- not taking account of any consequential loss- all based on fact that innocent party can mitigate. Margaret Halliwell 2006-03-06 8