NOTICE AS CONDITION PRECEDENT TO CLAIM LIQUIDATED ASCERTAINED DAMAGES (LAD)

Size: px
Start display at page:

Download "NOTICE AS CONDITION PRECEDENT TO CLAIM LIQUIDATED ASCERTAINED DAMAGES (LAD)"

Transcription

1 NOTICE AS CONDITION PRECEDENT TO CLAIM LIQUIDATED ASCERTAINED DAMAGES (LAD) NUR SYAIMASYAZA BT. MANSOR A thesis submitted in fulfilment of the requirements for the award of the degree of Master in Science of Construction Contract Management. Faculty of Built Environment Universiti Teknologi Malaysia July 2011

2 v ABSTRACT Most forms of building contract include a clause entitling the employer to a specified amount of damages, referred to as liquidated and ascertained damages (LAD) if the contractor is late in constructing a project. This clause sets out the procedure and condition that need to be followed by the employer. Some provision for example in clause 40.1 PWD 203A (Rev. 2007) require the employer to issue notice of intention before claiming LAD. The purpose of the issuance of notice is to inform the contractor about the payment or deduction. However, does the issuance of notice is condition precedent to the said claim? Some provision does not specifically expressly state the requirement to issue notice. So, there is an argument that section 56(3) of Contract Act is effective as an implied term to the contract. Based on the respective situations, question arises whether the employer s entitlement to liquidated damages is waived if he fails to issue the said notice. This study is carried out to determine whether notice is condition precedent to claim liquidated damages and the legal impact of notice provision for liquidated damages claim. The study was carried out mainly through documentary analysis of law journals. It was found that when the provision expressly state that notice is condition precedent, the failure to comply with notice provision might jeopardize the employer s claim. However, the employer s claim is not totally rejected because based on prevention principle, the contractor who caused the delay, cannot benefit from its wrong act. When the provision did not expressly state that notice is a condition precedent, it can be condition precedent by implication. The argument that section 56(3) is an implied term to the contract was wrong because section 56(3) is only applicable when the contract becomes voidable.

3 vi ABSTRAK Kebanyakan borang kontrak pembinaan mengandungi klausa bagi membolehkan majikan menuntut ganti rugi jika kontraktor tidak menyiapkan kerja pada tarikh siap yang ditetapkan yang dikenali sebagai Ganti Rugi Tertentu dan Ganti Rugi Ditetapkan. Klausa ini mengandungi prosedur dan syarat yang perlu diikuti oleh pihak yang berkontrak. Terdapat sesetengah klausa yang menyatakan bahawa majikan perlu mengeluarkan notis niat sebelum memohon ganti rugi seperti yang dinyatakan di dalam klause 40.1 JKR 203A (Sem. 2007). Tujuan pengeluaran notis adalah untuk memaklumkan kepada kontraktor mengenai pembayaran atau pemotongan yang akan berlaku. Namun, adakah pengeluaran notis menjadi syarat yang perlu dipenuhi sebelum membuat tuntutan tersebut? Sesetengah klausa tidak menyatakan keperluan untuk mengeluarkan notis niat sebelum menuntut ganti rugi. Oleh itu, terdapat pendapat mengatakan seksyen 56(3) Akta Kontrak 1950 akan bertindak sebagai syarat tersirat kepada kontrak mereka. Berdasarkan situasi yang dinyatakan di atas, persoalan timbul sama ada hak majikan terhadap ganti rugi akan terjejas jika dia gagal mengelurkan notis. Kajian dijalankan untuk mengetahui sama ada notis menjadi syarat sebelum menuntut ganti rugi dan kesan peruntukan notis tersebut dari sudut undang-undang. Kajian telah dijalankan dengan menjalankan analisis dokumentari jurnal undang-undang. Hasil kajian mendapati apabila klausa menyatakan notis menjadi syarat sebelum memohon ganti rugi, kegagalan untuk mematuhi syarat tersebut akan menjejaskan hak majikan terhadap ganti rugi tersebut. Namun, majikan masih layak untuk menerima pampasan kerana berdasarkan prinsip pengelakan, kontraktor tidak boleh mendapat keuntungan daripada kesalahannya sendiri. Pendapat yang menyatakan seksyen 56(3) adalah syarat tersirat kepada kontrak adalah salah kerana seksyen 56(3) hanya boleh terpakai apabila kontrak tersebut menjadi kontrak yang boleh dielakkan.

4 vii TABLE OF CONTENT CHAPTER TITLE PAGE DECLARATION DEDICATION ACKNOWLEDGMENTS ABSTRACT ABSTRAK TABLE OF CONTENT LIST OF CASES LIST OF ABBREVIATIONS LIST OF FIGURE ii iii iv v vi vii xi xiii xiv 1 INTRODUCTION Background of the Study Problem Statement Previous Studies Objective of the Study Scope of the Study Significance of the Study Research Methodology Identifying the Research Issue Literature Review Data Collection Research Analysis Conclusion and Recommendation 13

5 viii 1.8 Organization of the Thesis 15 2 LIQUIDATED AND ASCERTAINED DAMAGES (LAD) Introduction Definition of LAD Issues Concerned on LAD Liquidated damages vs. Penalty clause The Requirement to Prove Loss The Validity of LAD if the Architect/Engineer fails to grant a timely extension of time Can a Party Challenge the Validity of a Liquidated Damages Sum after the Contract has been signed? Provisional Liquidated Ascertained Damages Principle element of enforceable liquidated damages Benefits of imposing liquidated damages Conclusion 32 3 PROVISION OF LIQUIDATED DAMAGES Introduction Contractual Procedure to claim LAD Establish the Default of the Contractor Establish the Existence and Validity of the Liquidated Damages Clause Determine if Employer has Waived his Rights Determine Whether the Relevant Certificates/Notices Have Been Issued Employer Recovers the Liquidated Damages Liquidated Damages Provision in Various Standard Forms JKR 203A (Rev. 2007) PAM 2006 Forms (With and Without Quantities) Editions 40

6 ix IEM.ME 1/94 Form JCT 98 Standard Forms Contracts Principle of Contract Express Terms Implied Terms Terms implied by statute Notices as Condition Precedent Definition of notice The Purpose of Notice Definition of condition precedence Court Interpretation of condition precedence Conclusion 54 4 THE STATUS AND IMPLICATION OF NOTICE PROVISION Introduction Case Analysis Notice as Condition Precedent Notice Not Expressly Stated as Condition Precedent No Notice Provision Validity of notice Conclusion 78 5 CONCLUSION AND RECOMMENDATION Introduction Summary of Research Findings Research s Constraints Suggestions for Further Research Conclusion 82 REFERENCES 83 BIBLIOGRAPHY 88

7 x LIST OF CASES CASES PAGE A.Bell & Son (Paddington) Ltd v CBF Residential Care & Housing Association [1990] 46 BLR ,60 Alfred McAlpine Capital Projects Ltd v. Tilebox Ltd (2005) EWHC 281 (TCC) Bethlehem Steel Corporation v. City of Chicago (1965) 234 F.Supp Brammal and Ogden Ltd v. Sheffield City Council [1983] 29 BLR Brisdale Resources Sdn Bhd v. Law Kim [2004] 6 MLJ Bovis Lend Lease Ltd v. Braehead Glasgow Ltd [2000] All ER (D) ,54,75 Bunge Corporation v. Tradax Export S.A. [1981] 1 W.L.R ,63 CJ Sims Ltd v. Shaftesbury PLC [1991] 60 BLR Clydebank Engineering and Shipbuilding Company Limited v. Don Jose Ramos Ysquierdo-y-Castaneda and Others [1905] AC 6..21,28 Dunlop Tyre v. New Garage [1915] AC ,32 Gaymark Investments Pty Ltd v. Walter Construction Group Ltd [1999] NTSC Hadley v Baxendale (1854) 9 EX Hariram a/l Jayaram & Ors v. Sentul Raya Sdn Bhd [2003] 1 MLJ Holloway Holdings Ltd v Archway Business Centre Ltd 19 August 1991, unreported...4

8 xi Jarvis Brent Ltd v. Rowlinson Construction Ltd [1990] 6 Const LJ ,63,74 J.F. Finnegan Ltd v. Community Housing Association Ltd [1995] 65 BLR ,63,73 Linggi Plantations Ltd v Jagatheesan [1972] 1 MLJ ,32 London Borough of Merton v. Stanley Hugh Leach [1985] 32 BLR Lord Elphinstone v. Monkland Iron and Coal Company [1886] 11 App. Cas Mardale Pipes Plus Ltd v Malaysian International Trading Corp (Japan) Sdn Bhd [2009] 5 MLJ ,71 Multiplex Construction v Honeywell [2007] 1 BLR Osceola County, FI v. Bumble Bee Construction (1985) 479 So.2d Peak Construction (Liverpool) Ltd v. McKinney Foundations Ltd (1970) 1 BLR ,33,57 Philips v. Attorney General of Hong Kong (1993) 61 BLR 41 25,31,33 Pym v, Campbell [1856] 6 E & B Robinson v Harman (1848) 1 EXCH Sakinas Sdn Bhd v. Siew Yik Hau & Anor [2002] 5 MLJ ,23,32,64 Selva Kumar a/l Murugiah v Thiagarajah a/l Retnasamy [1995] 1 MLJ ,32 SS Maniam v. State of Perak [1957] MLJ ,21 Tai Kim Yew & Ors v. Sentul Raya Sdn Bhd [2004] 4 MLJ Temloc v Errill Properties (1987) 39 BLR ,33 Token Construction Co Ltd v. Charlton Estates Ltd (1973) 1 BLR Tool Metal Manufacturing Co. Ltd v. Tungsten Electric Co. Ltd [1955] 2 All ER Tunjang Wawasan Sdn. Bhd. v TNB Generation Bhd [2007] MLJU Wearne Brothers (M) Ltd v Jackson [1966] 2 MLJ Wise v. United States (1919) 249 U.S WW Gear Construction Ltd v. McGee Group Ltd. [2010] EWHC 1460 TCC..50,54

9 xii LIST OF ABBREVIATION All ER - All England Law Report BLR - Building Law Report CIDB - Construction Industry Development Board EWHC - High Court of England and Wales EXCH - Law Reports: Court of Exchequer FIDIC - Federation Internatonale des Ingenieurs-Conseils IEM - The Institute of Engineers, Malaysia LAD - Liquidated and Ascertained Damages MLJ - Malayan Law Journal MLJU - Malayan Law Journal Unreported PAM - Pertubuhan Arkitek Malaysia PWD - Public Work Department JCT - Joint Contracts Tribunal

10 xiii LIST OF FIGURE FIGURE NO. TITLE PAGE 1.1 Research Flow Chart 14

11 CHAPTER 1 INTRODUCTION 1.1 Background of the Study A contract is an agreement between two or more parties which creates obligations to do or not do the specific things that are the subject of that agreement and it is enforceable by law. 1 If one of the parties failed to perform his part of the obligation or he does it not according to the contract, he is considered to be in breach of the contract. 2 It now gives the other party the right to claim for damages for the breach. Damages are normally assessed when breach occurs, and are designed to be compensatory in nature. 3 Two principles important for assessment of damages are the principles of remoteness derived from the famous case of Hadley v Baxendale 4 in which Baron Alderson said: 1 Section 2 of Contracts Act Beatson J. (2002). Anson s Law of Contract. (28th ed.). United States: Oxford University Press. p Molloy J. B., (2001). Liquidated Damages Some General Principles. HKIS Newsletter, 4 May p.1 4 (1854) 9 EX 341

12 2 "Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i.e. according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it". 5 The measures of damages are derived from the equally old case of Robinson v Harman 6 where it was stated: "The rule of common law is that where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed". 7 Damages calculated from these principles are normally assessed after the breach occurs and are known as general or unliquidated damages. However, such approach is difficult to assess and usually the contracting parties like certainty. 8 This lead party to include within their contracts remedies for most common breaches which are known as liquidated damages. Liquidated damages or usually known as liquidated and ascertained damages (LAD) arise where the parties to a contract agree from the start the amount of damages that one party will pay to the other in the event of a specified breach of contract. 9 In England, the imposition of the word ascertained is aim to put a distinction between liquidated damages with penalty where this word will lend 5 Molloy J. B., (2001). Liquidated Damages Some General Principles. HKIS Newsletter, 4 May p.1 6 (1848) 1 EXCH Molloy J. B., (2001). Liquidated Damages Some General Principles. HKIS Newsletter, 4 May p.1 8 Ibid. 9 Murdoch J. (2009). Being Late Can Have Damaging Effects. The Estates Gazette. ProQuest Direct.

13 3 more weight to the argument that the liquidated damages is a genuine and ascertained pre-estimate of the Employer s loss. However in Malaysia, there is no such distinction between liquidated damages and penalty. 10 Most forms of building contract include a clause entitling the client to a specified amount of damages, referred to as Liquidated Damages or Liquidated and Ascertained Damages (LAD) if the Contractor is late in handing over the building. 11 LAD replaces the client s common law right to damages for late completion with a contractual right to a pre-determined sum for the period of delay. 12 These clauses are favoured by employers because they alleviate the need to prove an actual loss. However, this did not apply in Malaysia, because the client still need to prove the actual damages suffered pursuant to section 75 of the Contract Act The imposition of LAD is also purport to provide for a negotiated and fair method of allowing for the possibility of a delay in completion of the project, which provides adequate compensation for the purchaser/owner, while ensuring that the contractor is not too heavily penalized for the delay. 14 One of the issues that can be discussed is regarding the issuance of notice of intention before claiming liquidated damages. If the contract clearly stated that the employer should issue notice of intention to claim liquidated damages, does it invalidate the employer s right to deduct payment if he fail to issue them? Does the issuance of certificate of non-completion is enough to entitle the employer to claim LAD? For example in section 40 P.W.D. Form 203A (Rev. 2007): 10 SS Maniam v. State of Perak [1957] MLJ Clause 40.1 PWD 203A (Rev. 2007), Clause 22.1 PAM 2006, Clause 26.2 CIDB (2000 Edition) 12 Turner B., Liquidated damages clauses in construction contracts. [online] Available at: [Accessed 22 January 2011]. 13 Lim C. F. (1993). Enforcement of Liquidated Damages- To Prove Actual Loss?. The Malayan Law Journal Articles. Vol 1, 1-9. Lexis Nexis Business Solution. 14 PM Professional Resources (2010). Construction Claim and Dispute Resolution. [online] Available at: [Accessed 20 October 2010].

14 4 If the Contractor fails to complete the Works by the Date for Completion or within any extended time granted pursuant to clause 43 (Delay and Extension of Time), the S.O. shall issue a Certificate of Non-completion to the Contractor. Prior to the issuance of the Certificate of Non-completion, the S.O. shall issue a notice to the Contractor informing the Contractor the intention of the Government to impose Liquidated and Ascertained Damages to the Contractor if the Contractor fails to complete the Works by the Date for Completion or within any extended time granted. The clause stated that prior to the issuance of the Certificate of Noncompletion the Superintending Officer shall issue a notice to the contractor informing the intention of the government to impose Liquidated and Ascertained Damages. However, does the issuance of notice is considered condition precedent or just information. If it is considered as condition precedent, does it waive the employer s right to claim liquidated damages if the employer fail issue the notice? In A.Bell & Son (Paddington) Ltd v CBF Residential Care & Housing Association 15 Judge John Newey QC state that the certificate of failure to complete and a written requirement of payment or allowance under the middle part of clause (JCT 98) were conditions precedent to the making of deductions on account of liquidated damages. In Holloway Holdings Ltd v Archway Business Centre Ltd 16 a similar clause in IFC 84 was considered and it was again held that for the employer to be able to deduct liquidated damages there must both be a certificate from the Architect and a written request to the contractor from the employer. 17 On another issue, for example in PWD 203A (Rev. 10/83), it did not mention the requirement to give written notice of intention to claim liquidated damages. Below is the example of the clause: 15 [1990] 46 BLR August 1991, unreported 17 Chappell D. (2007). The JCT Design and Build Contract (3 rd ed.). Oxford:Wiley-Blackwell.

15 5 Clause 40 Damages for Non-completion (PWD 203A (Rev. 10/83)) If the Contractor fails to complete the Works by the Date for Completion stated in the Appendix or within any extended time under Clause 43 hereof and the S.O. certifies in writing that in his opinion the same ought reasonably so to have been completed the Contractor shall pay or allow the Government a sum calculated at the rate stated in the Appendix as Liquidated and Ascertained Damages for the period during which the said Works shall so remain and have remained incomplete and the S.O. may deduct such damages from any monies due to the Contractor. The certificate issued under this Condition shall be referred to as the Certificate of Non-completion. The clause entitled the employer to claim for damages for late completion of the project. From the clause above, there is no requirement for the employer to issue notice of intention to claim liquidated damages. If such situation occurs, can the contractor argue that the employer must issue notice as mention under section 56(3) of the Contract Act? Does section 56(3) of the Contract Act is an implied term to contract between parties? In Section 56 (3) of Contract Act 1950 states: If, in case of a contract voidable on account of the promisor s failure to perform his promise at the time agreed, the promisee accepts performance of the promise at any time other than that agreed, the promisee cannot claim compensation for any loss occasioned by the nonperformance of the promise at the time agreed, unless, at the time of the acceptance, he gives notice to the promisor of his intention to do so.

16 6 From section 56(3) of the Act, it briefly explain that when a party to the contract cannot perform his promise within the stipulated time, the innocent party may either terminate the contract or to treat it as still subsisting. If the innocent party choose to treat the contract as still subsisting, either expressly or by conduct, the contract will continue to exist but the time cease to be of the essence and becomes at large. Consequently, the innocent party will lose their right to claim liquidated damages under the contract. The time can be revived to be of the essence if the innocent party serve a notice to the defaulting party before the time lapse. The notice include the intention of the innocent party to claim compensation due to the breach and setting a new date of completion. The issue here is whether the absence of a clause in the contract such as in PWD 203A (Rev. 10/83) requiring the employer to issued notice, does section 56(3) of the Contract Act 1950 serves as an implied terms and the failure to follow them can waive the employer s right to liquidated damages. In Sakinas Sdn Bhd v. Siew Yik Hau & Anor 18 Abdul Aziz held that section 56(3) did not apply and that it was not necessary to give notice before a right to impose LAD charges arose under a LAD clause. The court in Tunjang Wawasan Sdn. Bhd. v TNB Generation Bhd 19 also held the same decision that where there is a liquidated damages clause section 56(3) does not apply. However in Mardale Pipes Plus Ltd v Malaysian International Trading Corp (Japan) Sdn Bhd (ExxonMobil Exploration and Production Malaysia Inc, third party) 20 the defendant argue that the requirement to give notice of intention to claim liquidated damages as stated in section 56(3) of the Contract Act on the ground of the Act did not apply where there was an LAD clause in the contract. The court held that the failure to issue notice by the defendant had invalidate their right to claim LAD. In fact the LAD clause could only be invoked when a notice under section 56(3) of the Act had been properly given by the defendant. 18 [2002] 5 MLJ [2007] MLJU [2009] 5 MLJ 691

17 7 In Jarvis Brent Ltd v. Rowlinson Construction Ltd 21 a contractor challenge recovery of liquidated damages on grounds that the document actually received from the employer is not the notice of liquidated damages required under the contract. 22 So, what constitutes a notice? Since the clause did not specify what information should be included in the notice, there is argument regarding the issue. 1.2 Problem Statement Although most of the standard form contain provision for liquidated damages, but the procedure and language in the clause is not similar. For example clause 40 (Damages for Non-completion) in PWD 203A (Rev. 10/83), there is no requirement to issue notice by the employer before claiming liquidated damages. While in clause 22.1 PAM 2006 only state that the employer need to inform the contractor in writing of the deduction of LAD. Although there is no requirement to issue notice in the contract, contractor argue that notice should be given before claiming liquidated damages pursuant to section 56(3) of Contract Act 1950 which states that at the time of the acceptance of late delivery, the innocent party need to issue notice to state their intention to claim damages. Question arises whether section 56(3) of Contract Act is an implied term and shall be followed by the contracting parties. In the new version of PWD standard form of contract, government had made an amendment in clause 40 of PWD 203A (Rev. 2007) provides clearly express notice requirement in the clause. It states that the employer prior to the issuance of Certificate of Non-completion must issue notice of intention to claim liquidated damages to inform the contractor about the payment or deduction. However, the clause did not expressly state that notice is condition precedent to the said claim. It is 21 [1990] 6 Const LJ Ndekugri I. and Rycroft M. (2000). The JCT 05 Standard Building Contract Law and Administration. (2 nd ed.) Oxford: Elsevier.

18 8 not clear whether notice is deem as condition precedent before claiming liquidated damages. The foregoing discussion brings us to several pertinent questions: 1) The status of notice if it is stated as condition precedent in the LAD provision? 2) If the provision stated the requirement to issue notice before claiming liquidated damages but without expressly stated as condition precedent, does it considered as condition precedent? 3) If the contract contains no express provision for notice of intention to claim liquidated damages, is it possible to impose general act into the contract in order to make notice as condition precedent? 4) What information should be included in the notice? 1.3 Previous Studies There is several research studies had been carried out concerning liquidated damages. Yong (2006) has done studies on Liquidated and Ascertained Damages (LAD) and Requirement of Mitigation. The objectives were to determine the requirement of mitigation and the extent of the employer s duty to mitigate his losses when enforcing his right under the liquidated damages clause. From the research, it was found that an employer s requirements to mitigate the losses is silent in standard forms of contract, but despite that, the employer is bound to comply with the requirements of mitigation in enforcing LAD by taking all reasonable steps or action in accordance with principles of mitigation.

19 9 Chia (2009) had tried to identify the enforceability of the liquidated damages provision in construction contract. The finding from the research found that the party suffered losses will need to prove when claiming for compensation and required to mitigate the losses before claim for damages. But there is an exceptions to contract of sale and purchase under the Housing Developers Regulation This contract also exempts the party from the need to issue notice of intention when claiming for damages. Mohamad Noor (2008) studied on the legal status of the practice of provisional liquidated damaged (PLD) and identified the reasons and the effect of imposing PLD on contractors. It was found that the contractual provisions must be strictly adhered by the government in order to secure their right to liquidated damages. Furthermore, in Malaysia the provisions are subject to the statutory provisions under the Act. 1.4 Objective of the Study The objective of study is to ascertain whether: 1) The issuance of notice is a condition precedence 2) If so, how it arise Contract Act; or Common Law 3) The implication of notice provision

20 Scope of the Study The approach adopted in this research is case law based. There are no limitations as for the court cases referred to in this study in terms of type of projects as long as the case is related to liquidated ascertained damages and notice to claim LAD. Types of contract involved include construction contracts (between employer and main contractor, and between main contractor and subcontractor) and contracts of sales of goods and land. The standard forms of contract that will be referred to are: a) Public Works Department (P.W.D) Form 203A (Rev. 10/83) & (Rev. 2007) b) Pertubuhan Arkitek Malaysia (PAM) (2nd Edition, 2006) c) Construction Industry Development Board (CIDB) Standard Form of Contract for Building Works (2000 Edition) d) The Institution of Engineers, Malaysia (IEM.ME 1/94 Form) e) Joint Contracts Tribunal (JCT) Standard building contract guide (SBC/G), (1998) & (2005b). 1.6 Significance of the Study Poor understanding of the requirement of notification or the lack of notice has led to disputes and disagreement amongst the various parties in construction contract. The purpose of this study is to give an insight into the issues regarding the notice as condition precedent to claim liquidated damages and the court reaction and its decision concerning the issue. It is hoped that the findings of this study will assist the players in the construction industry to understand the significance of the liquidated damages clause in their contract, plus understand the requirement to issue notice of

21 11 intention to claim liquidated damages and put their best effort to avoid disputes involving those issues. 1.7 Research Methodology Research process and method of approach is vital as guidelines in preparing the research so that the research could be done in an organized way to achieve the research objective. Basically, this research process comprise of five major stages, which involve identifying the research issue, literature review, data collection, research analysis, conclusion and recommendation. Stage 1 Development of Proposal Identifying the Research Issue The initial stage involves the identification area of issues as well as formulating the research objective. First, the overview of the concept of this topic will be done through the initial literature review. The study issue arises from intensive reading of books, journals and articles which can be attained from the UTM library, Building Construction Information Centre (BCIC) and Resource Centre of Alam Bina (RC). Once research objective has been formulated, the scope and limitations for the research will be determined as well as the research title.

22 Literature Review Collection of various documentation and literature regarding the study field is of most important in achieving the research objectives. Data will be collected mainly through documentary analysis. All collected data and information will be recorded systematically. Data will be collected mainly from Malayan Law Journal, Singapore Law Report, Building Law Report, Construction Law Report and other law journals. Data is collected by browsing through the LexisNexis legal database. Important and relevant cases will be collected and used for the analysis at the later stage. In addition, secondary data from books, article reports, seminar papers, newspapers and articles from the internet, is also useful for this research. All the relevant books will be obtained from the Universiti Teknologi Malaysia library and other public libraries. Stage 2 Data & Information Collection Data Collection At this stage, all the collected data, information, ideas, opinions and comments will be arranged and recorded systematically. Important and relevant cases is collected and use for the analysis at the later stage.

23 13 Stage 3 Analysis Research Analysis The fourth stage of research is analysis phase. It involves data analysis, interpretation and data arrangement. Once the previous related court cases are collected, reviewing and clarifying all the facts of the cases will be conducted. The focus will be on the issue of this research. After identifying issues in each case, a thorough discussion and comparison will be done in order to achieve objectives of this study Conclusion and Recommendation In this final stage, discussions will be done based on the findings from the previous stage to fulfil the aims or objective of this research and reach a conclusion. Recommendations for further research will be made as a suggestion for future researcher.

24 14 ISSUE OF THE RESEARCH RESEARCH OBJECTIVES SCOPE AND LIMITATIONS STAGE 1: DEVELOPMENT OF PROPOSAL DETERMINATION OF RESEARCH TITLE RESEARCH METHODOLOGY 1. LITERATURE REVIEW 2. DATA AND INFORMATION COLLECTION 3. RESEARCH ANALYSIS STAGE 2: DATA & INFORMATION COLLECTION DATA AND INFORMATION COLLECTION 1. BREACH OF CONTRACT, DAMAGES 2. LIQUIDATED AND ASCERTAINED DAMAGES (LAD) 3. NOTICE OF INTENTION TO CLAIM LAD 4. LEGAL ISSUES IN RELATION TO NOTICE RESOURCES: 1. Books, Journals, Statutory, and cases. 2. UTM library electronic database: Lexis-Nexis Legal Database eg. Malayan Law Journal, Appeal Cases Report, All England Report, Building Law Report STAGE 3: RESEARCH ANALYSIS OBJECTIVE: TO ASCERTAIN Figure WHETHER 1.1 Research NOTICE Flow Chart IS CONDITION PRECEDENT BEFORE CLAIMING LIQUIDATED DAMAGES CONCLUSION STAGE 4: CONCLUSION

25 Organization of the Thesis Chapter 1: Introduction The first chapter is an introduction to the research topic and covered a few subtopics. The first subtopic is background of the study, followed by problem statement which stated the issues that will be discuss in the study. Then, the next subtopic covered on the previous research on the similar topic; objectives of the research which stated the aims of the study; scope of the research; significance of the study and finally the research methodology that to be used during the process of research Chapter 2: Liquidated and Ascertained Damages (LAD) Briefly, this chapter will covered on definition of liquidated damages, issues concerned on LAD which include liquidated vs. penalty clause; the requirement to prove loss; the validity of LAD if the Architect/Engineer fails to grant a timely extension of time; can a party challenge the validity of a liquidated damages sum after the contract has been signed; and provisional liquidated ascertained damages.

26 Chapter 3: Provision of Liquidated Damages This chapter discuss on contractual procedure to claim liquidated damages. It is divided into five subtopics ie. Establish the default of the contractor; establish the existence and validity of the liquidated damages clause; determine if employer has waived his rights; determine whether the relevant certificates/notices have been issued; and employer recovers the liquidated damages. After that, the topic expend to discuss on liquidated damages provision in various standard forms for example in JKR 203A (Rev. 2007), PAM 2006, CIDB 2000 and etc; definition and purpose of notice; definition and court interpretation of condition precedent Chapter 4: The Status and Implication of Notice Provision This chapter is essential part of the research. Here, case law on condition precedent and notice requirement before claiming liquidated damages shall be analysed and the result discuss in a logical qualitative analysis. The task is to ascertain the status of notice provision in liquidated damages clause; whether it is condition precedent upon claiming liquidated damages Chapter 5: Conclusion and Recommendations This chapter is the final part of the whole report and is a conclusion chapter. Briefly, this chapter will give a detail summary of the research finding to a logical conclusion of the previous chapter, highlight the problem encountered during the course of the research and give recommendation on improving the subject area.

27 83 REFERENCES Adriaanse J. (2005) Construction Contract Law The Essential. Basingstoke: Palgrave Macmillan. Always Associates (2004). Drafting for Liquidated and Ascertained Damages- Avoiding Pitfalls. [online] Available at: [Accessed 24 Mei 2011]. Beatson, J. (2002). Anson s Law of Contract. (28th ed.). United States: Oxford University Press. Barton Legal (2007). Liquidated Damages A Three Stage Process. [online] Available at: [Accessed 28 Jun 2011]. Chappel D., Powell-Smith V. & Sims J. (2004). Building Contract Claims. (4 th ed.). Oxford: Blackwell Publishing Ltd Chappell D. (2007). The JCT Design and Build Contract (3 rd ed.). Oxford:Wiley- Blackwell. Chia M. L. (2009). The Enforceability of Liquidated and Ascertained Damages in Construction Contract. Master. University Teknologi Malaysia.

28 84 Coldwell D., Burchett-Williams A. & Celeste M. (2010). Liquidated Damages. Franchise Law Journal [e-journal] 29 (4) Available through: ProQuest Database [Accessed on 25 Mei 2011] Drewry C. (n.d.). The Availability and Enforceability of Liquidated Damages in Construction Litigation. [online] Available at: df [Accessed 25 May 2011]. Donohoe S. (2011). The WW Gear Case, Conditions Precedent and Construction Contracts. Structural Survey [online] 29 (2) Available through: Emerald Database [Accessed on 17 Jun 2011]. Eggleston B. (1997). Liquidated Damages and Extensions of Time in Construction Contracts. Oxford: Blackwell Science. Elliot C. and Quinn F. (2007) Contract Law. 6 th edition. Edinburgh: Pearson Education Limited. Friedlander M. C. (2001). Contractor Marketing- Penalty Clauses. [online] Available at: [Accessed 23 January 2011]. Glazov J. (2009). Liquidated Damages in Construction Contracts- Enforcing Liquidated Damages. [online] Available at: [Accessed 20 Oktober 2010]. Gillhams Solicitors (2005). Contracts & Disputes: Importance of Implied Terms. [online] Available through: [Accessed on 1 June 2011]

29 85 Government of Malaysia (2006). Public Works Department Form 203A (Revised 2007). Malaysia : Government of Malaysia. Harban, K. S. (2002) Engineering and Construction Contracts Management, Commencement and Administration, Singapore: Lexis Nexis. Harban K.S. (2002) Engineering and Construction Contracts Management Law and Principles. Singapore: Lexis Nexis Hawkswell Kilvington (2003). Liquidated Damages. [online] Available at: [Accessed 24 Mei 2011]. Lal H. (2009). Liquidated Damages. Construction Law Journal, 25(8), pp Lectric Law Library (2011). Notice. [online] Available at: [Accessed on 17 Jun 2011]. Lim C. F. (1993). Enforcement of Liquidated Damages- To Prove Actual Loss?. The Malayan Law Journal Articles. Vol 1, 1-9. Lexis Nexis Business Solution. Lim, G. and Kasim, K. (2002). Sakinas Sdn Bhd V Siew Yik Hau & Anor (2002) 5 MLJ 498: One Step Forward, Two Steps Back? The Malayan Law Journal Articles. Vol 3, Lexis Nexis Business Solutions. Mohamad Noor S. B. (2008). Provisional Liquidated Damages (PLD). Master. University Teknologi Malaysia. Molloy J. B. (2001). Liquidated Damages Some General Principles. HKIS Newsletter. Molloy J. B. (2001). Notice Provisions A Change in Attitude?. HKIS Newsletter.

30 86 Murdoch J. (2009). Being Late Can Have Damaging Effects. The Estates Gazette. ProQuest Direct. Ndekugri I. And Rycroft M. (2000). The JCT 05 Standard Building Contract Law and Administration. (2 nd ed.). Oxford: Elsevier Ltd. Osborne D. (2006). Effect of Conditions Precedent on Building Contracts. Journal of Building Appraisal. Vol 2, , Palgrave Macmillan Ltd. Pertubuhan Arkitek Malaysia (2006). Agreement and Conditions of PAM Contract 2006 (With Quantities). Malaysia : Pertubuhan Arkitek Malaysia. PM Professional Resources (2010). Construction Claim and Dispute Resolution. [online] Available at: [Accessed 20 October 2010]. Powell-Smith V., Chappell D. and Simmonds D. (1989). An Engineering Contract Dictionary. London: Legal Studies and Services (Publishing) Ltd. Sinnadurai, V. (1979). The Law of Contract in Malaysia and Singapore: Cases and Commentary. Kuala Lumpur: Oxford University Press. Turner & Townsend (2009). Liquidated Damages Contract Risk Management. [online] Available at: [Accessed 22 January 2011]. Turner B., Liquidated damages clauses in construction contracts. [online] Available at: [Accessed 22 January 2011].

31 87 Tuuli M.M., Baiden B.K. & Badu E. (2007). Assessment and Enforcement of Liquidated Damages in Construction Contracts in Ghana. Structural Survey [e-journal] 25 (3/4) Available through: Emerald database [Accessed 25 Mei 2011]. Viscarello K. (2006) The Use of Liquidated Damages Clauses in Construction Contracts. [online] Available at: company-newsletter/the-use-of-liquidated-damages-clauses-in-construction- Contracts.aspx [Accessed 20 October 2010]. Yong M. L. (2006). Liquidated and Ascertained Damages (LAD) and Requirement of Mitigation. Master. University Teknologi Malaysia. YourDictionary.com (2011). Notice Law Definition. [online] Available at: [Accessed on 17 Jun 2011]. Wikipedia (2011). Notice. [online] Available at: [Accessed on 17 Jun 2011]. Winser C. (2007). The Prevention Principle After Multiplex v Honeywell. [online] Available through: [Accessed on 1 June 2011].

TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE

TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE 1 TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE 1.1 Background study. It is often said that for a building or construction project, there are three objectives which the owner of the project is aiming 1.

More information

EQUITABLE REMEDY: SPECIFIC PERFORMANCE THEN LEE LIAN UNIVERSITI TEKNOLOGI MALAYSIA

EQUITABLE REMEDY: SPECIFIC PERFORMANCE THEN LEE LIAN UNIVERSITI TEKNOLOGI MALAYSIA EQUITABLE REMEDY: SPECIFIC PERFORMANCE THEN LEE LIAN UNIVERSITI TEKNOLOGI MALAYSIA EQUITABLE REMEDY: SPECIFIC PERFORMANCE THEN LEE LIAN A project report submitted in partial fulfillment of the requirements

More information

UNCONSCIONABLE CALL OF PERFORMANCE BOND WAN NOOR SOLEHHA BINTI WAN NIK FACULTY OF BUILT ENVIRONMENT UNIVERSITI TEKNOLOGI MALAYSIA

UNCONSCIONABLE CALL OF PERFORMANCE BOND WAN NOOR SOLEHHA BINTI WAN NIK FACULTY OF BUILT ENVIRONMENT UNIVERSITI TEKNOLOGI MALAYSIA ii UNCONSCIONABLE CALL OF PERFORMANCE BOND WAN NOOR SOLEHHA BINTI WAN NIK FACULTY OF BUILT ENVIRONMENT UNIVERSITI TEKNOLOGI MALAYSIA iii UNCONSCIONABLE CALL OF PERFORMANCE BOND WAN NOOR SOLEHHA BINTI WAN

More information

PROFILE OF CONSTRUCTION CONTRACTUAL CLAIMS NUR JAZLIANNA BINTI SAMSUDIN UNIVERSITI TEKNOLOGI MALAYSIA

PROFILE OF CONSTRUCTION CONTRACTUAL CLAIMS NUR JAZLIANNA BINTI SAMSUDIN UNIVERSITI TEKNOLOGI MALAYSIA PROFILE OF CONSTRUCTION CONTRACTUAL CLAIMS NUR JAZLIANNA BINTI SAMSUDIN UNIVERSITI TEKNOLOGI MALAYSIA PROFILE OF CONSTRUCTION CONTRACTUAL CLAIMS NUR JAZLIANNA BINTI SAMSUDIN A master s project report submitted

More information

VALID AND INVALID VARIATION OMISSION OF WORKS MOTHILAL A/L MUNIANDY

VALID AND INVALID VARIATION OMISSION OF WORKS MOTHILAL A/L MUNIANDY VALID AND INVALID VARIATION OMISSION OF WORKS MOTHILAL A/L MUNIANDY A dissertation submitted in partial fulfillment of the requirements for the award of the degree of Master of Science (Construction Contract

More information

CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG UNIVERSITI TEKNOLOGI MALAYSIA

CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG UNIVERSITI TEKNOLOGI MALAYSIA CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG UNIVERSITI TEKNOLOGI MALAYSIA CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG A master s project report submitted in fulfillment

More information

SETTING ASIDE AN AWARD: ARBITRATOR S MISCONDUCT LEE SEE KIM MB UNIVERSITI TEKNOLOGI MALAYSIA

SETTING ASIDE AN AWARD: ARBITRATOR S MISCONDUCT LEE SEE KIM MB UNIVERSITI TEKNOLOGI MALAYSIA SETTING ASIDE AN AWARD: ARBITRATOR S MISCONDUCT LEE SEE KIM MB 091119 UNIVERSITI TEKNOLOGI MALAYSIA SETTING ASIDE AN AWARD: ARBITRATOR S MISCONDUCT LEE SEE KIM A project report submitted in partial fulfillment

More information

TERMINATION OF CONTRACTOR DUE TO THE CORRUPTION, UNLAWFUL OR ILLEGAL ACTIVITIES HASNITA HANA BINTI HASSAN UNIVERSITI TEKNOLOGI MALAYSIA

TERMINATION OF CONTRACTOR DUE TO THE CORRUPTION, UNLAWFUL OR ILLEGAL ACTIVITIES HASNITA HANA BINTI HASSAN UNIVERSITI TEKNOLOGI MALAYSIA TERMINATION OF CONTRACTOR DUE TO THE CORRUPTION, UNLAWFUL OR ILLEGAL ACTIVITIES HASNITA HANA BINTI HASSAN UNIVERSITI TEKNOLOGI MALAYSIA TERMINATION OF CONTRACTOR DUE TO THE CORRUPTION, UNLAWFUL OR ILLEGAL

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 Background of Research Contract is defined in various ways. A contract has been defined by Beatson in Anson s Law of Contract as a legally binding agreement made between two

More information

Setem (Pindaan) 1 D.R. 14/2010 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Akta Setem Tajuk ringkas dan permulaan kuat kuasa

Setem (Pindaan) 1 D.R. 14/2010 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Akta Setem Tajuk ringkas dan permulaan kuat kuasa Setem (Pindaan) 1 D.R. 14/2010 RANG UNDANG-UNDANG b e r n a m a Suatu Akta untuk meminda Akta Setem 1949. [ ] DIPERBUAT oleh Parlimen Malaysia seperti yang berikut: Tajuk ringkas dan permulaan kuat kuasa

More information

CONTRACTING OUT OF STATUTORY PROVISION IN MALAYSIAN CONSTRUCTION CONTRACT LEE SZE YIN UNIVERSITI TEKNOLOGI MALAYSIA

CONTRACTING OUT OF STATUTORY PROVISION IN MALAYSIAN CONSTRUCTION CONTRACT LEE SZE YIN UNIVERSITI TEKNOLOGI MALAYSIA CONTRACTING OUT OF STATUTORY PROVISION IN MALAYSIAN CONSTRUCTION CONTRACT LEE SZE YIN UNIVERSITI TEKNOLOGI MALAYSIA i CONTRACTING OUT OF STATUTORY PROVISION IN MALAYSIAN CONSTRUCTION CONTRACT LEE SZE YIN

More information

Conditions Precedent to Recovery of Loss and Expense Claims

Conditions Precedent to Recovery of Loss and Expense Claims Conditions Precedent to Recovery of Loss and Expense Claims Dated 07 January 2011 Author Robert Dalton (Head of Construction and Dispute Resolution NW for Blake Newport) Introduction There is a growing

More information

LAW OF RESTITUTION IN MALAYSIAN CONSTRUCTION CONTRACT WONG FOO YEU UNIVERSITI TEKNOLOGI MALAYSIA

LAW OF RESTITUTION IN MALAYSIAN CONSTRUCTION CONTRACT WONG FOO YEU UNIVERSITI TEKNOLOGI MALAYSIA LAW OF RESTITUTION IN MALAYSIAN CONSTRUCTION CONTRACT WONG FOO YEU UNIVERSITI TEKNOLOGI MALAYSIA LAW OF RESTITUTION IN MALAYSIAN CONSTRUCTION CONTRACT WONG FOO YEU A project report submitted in partial

More information

Possible Legal Issues of Unilaterally Contract Termination for Convenience

Possible Legal Issues of Unilaterally Contract Termination for Convenience Possible Legal Issues of Unilaterally Contract Termination for Convenience Seng Hansen Master Student of Construction Contract Management UTM Email: Hansen_zinck@yahoo.co.id Introduction The Malaysian

More information

NOTICES, TIME BARS AND PROPORTIONALITY

NOTICES, TIME BARS AND PROPORTIONALITY NOTICES, TIME BARS AND PROPORTIONALITY A talk by Sir Rupert Jackson to the Hong Kong Society of Construction Law on 21 st September 2018 CONTENTS 1. Introduction 2. Notice provisions 3. A conundrum 4.

More information

DIRECT LOSS AND EXPENSE RELATING TO REMOTENESS OF DAMAGES LEE XIA SHENG

DIRECT LOSS AND EXPENSE RELATING TO REMOTENESS OF DAMAGES LEE XIA SHENG DIRECT LOSS AND EXPENSE RELATING TO REMOTENESS OF DAMAGES LEE XIA SHENG A project report submitted in partial fulfilment of the requirement for the award of the degree of Master of Science (Construction

More information

PERINTAH UNIVERSITI DAN KOLEJ UNIVERSITI (PERLEMBAGAAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA) (PINDAAN) 2012

PERINTAH UNIVERSITI DAN KOLEJ UNIVERSITI (PERLEMBAGAAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA) (PINDAAN) 2012 WARTA KERAJAAN PERSEKUTUAN 22 November 2012 22 November 2012 P.U. (A) 401 FEDERAL GOVERNMENT GAZETTE PERINTAH UNIVERSITI DAN KOLEJ UNIVERSITI (PERLEMBAGAAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA) (PINDAAN)

More information

HBT 103 BAHASA, UNDANG-UNDANG DAN PENTERJEMAHAN I

HBT 103 BAHASA, UNDANG-UNDANG DAN PENTERJEMAHAN I UNIVERSITI SAINS MALAYSIA Peperiksaan Semester Pertama Sidang Akademik 2006/2007 Oktober/November 2006 HBT 103 BAHASA, UNDANG-UNDANG DAN PENTERJEMAHAN I Masa : 3 jam Sila pastikan bahawa kertas peperiksaan

More information

EMPLOYER S RIGHTS AND CONTRACTOR S LIABILITIES IN RELATION TO CONSTRUCTION DEFECTS AFTER FINAL CERTIFICATE TAN PEI LING UNIVERSITI TEKNOLOGI MALAYSIA

EMPLOYER S RIGHTS AND CONTRACTOR S LIABILITIES IN RELATION TO CONSTRUCTION DEFECTS AFTER FINAL CERTIFICATE TAN PEI LING UNIVERSITI TEKNOLOGI MALAYSIA EMPLOYER S RIGHTS AND CONTRACTOR S LIABILITIES IN RELATION TO CONSTRUCTION DEFECTS AFTER FINAL CERTIFICATE TAN PEI LING UNIVERSITI TEKNOLOGI MALAYSIA DEDICATION To my beloved father, mother, sister and

More information

DALAM MAHKAMAH TINGGI MALAYA DI KOTA BHARU DALAM NEGERI KELANTAN, MALAYSIA GUAMAN SIVIL NO: DA-22-NCVC-6-02/2017 ANTARA MESRA BUDI SDN.

DALAM MAHKAMAH TINGGI MALAYA DI KOTA BHARU DALAM NEGERI KELANTAN, MALAYSIA GUAMAN SIVIL NO: DA-22-NCVC-6-02/2017 ANTARA MESRA BUDI SDN. DALAM MAHKAMAH TINGGI MALAYA DI KOTA BHARU DALAM NEGERI KELANTAN, MALAYSIA GUAMAN SIVIL NO: DA-22-NCVC-6-02/2017 ANTARA MESRA BUDI SDN. BHD PLAINTIF DAN LEMBAGA KEMAJUAN TANAH PERSEKUTUAN (FELDA) DEFENDAN

More information

Held: Per Abdul Hamid Mohamad JCA

Held: Per Abdul Hamid Mohamad JCA 1 PP v. HO HUAH TEONG COURT OF APPEAL, KUALA LUMPUR LAMIN MOHD YUNUS, PCA; ABDUL HAMID MOHAMAD, JCA; ABDUL KADIR SULAIMAN, JCA CRIMINAL APPEAL NO: P09-3-97 3 AUGUST 2001 [2001] 3 CLJ 722 CRIMINAL PROCEDURE:

More information

Time and Construction Contracts

Time and Construction Contracts Time and Construction Contracts Extensions of Time and the Prevention Principle By Nathan Abbott Introduction The purpose of this paper is to expose and consider the Prevention Principle from a practical

More information

TERMINATION FOR CONVENIENCE BY EMPLOYER IN CONSTRUCTION CONTRACT LAU SIEW SOON FACULTY OF BUILT ENVIRONMENT UNIVERSITI TEKNOLOGI MALAYSIA

TERMINATION FOR CONVENIENCE BY EMPLOYER IN CONSTRUCTION CONTRACT LAU SIEW SOON FACULTY OF BUILT ENVIRONMENT UNIVERSITI TEKNOLOGI MALAYSIA TERMINATION FOR CONVENIENCE BY EMPLOYER IN CONSTRUCTION CONTRACT LAU SIEW SOON FACULTY OF BUILT ENVIRONMENT UNIVERSITI TEKNOLOGI MALAYSIA i TERMINATION FOR CONVENIENCE BY EMPLOYER IN CONSTRUCTION CONTRACT

More information

A PROPOSED METHODOLOGY TO DEVELOP DISASTER RECOVERY PLAN FOR CICT UTM HUSSEIN YUSUF SHEIKH ALI UNIVERSITI TEKNOLOGI MALAYSIA

A PROPOSED METHODOLOGY TO DEVELOP DISASTER RECOVERY PLAN FOR CICT UTM HUSSEIN YUSUF SHEIKH ALI UNIVERSITI TEKNOLOGI MALAYSIA 1 A PROPOSED METHODOLOGY TO DEVELOP DISASTER RECOVERY PLAN FOR CICT UTM HUSSEIN YUSUF SHEIKH ALI UNIVERSITI TEKNOLOGI MALAYSIA UNIVERSITI TEKNOLOGI MALAYSIA DECLARATION OF THESIS / POSTGRADUATE PROJECT

More information

Kanun Tatacara Jenayah (Pindaan) (No. 2) 1 D.R. 17/2012 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Kanun Tatacara Jenayah.

Kanun Tatacara Jenayah (Pindaan) (No. 2) 1 D.R. 17/2012 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Kanun Tatacara Jenayah. Kanun Tatacara Jenayah (Pindaan) (No. 2) 1 D.R. 17/2012 RANG UNDANG-UNDANG b e r n a m a Suatu Akta untuk meminda Kanun Tatacara Jenayah. [ ] DIPERBUAT oleh Parlimen Malaysia seperti yang berikut: Tajuk

More information

Majlis Perbandaran Seremban v Era Baru Sdn Bhd and Another Appeal

Majlis Perbandaran Seremban v Era Baru Sdn Bhd and Another Appeal IN THE COURT OF APPEAL OF MALAYSIA Coram: Tengku Maimun Tuan Mat, JCA; Abdul Rahman Sebli, JCA; Suraya Othman, JCA Majlis Perbandaran Seremban v Era Baru Sdn Bhd and Another Appeal Citation: [2018] MYCA

More information

P Mukundan A/L P K Kunchu Kurup and 2 Others v Daniel A/L Anthony and Another Appeal

P Mukundan A/L P K Kunchu Kurup and 2 Others v Daniel A/L Anthony and Another Appeal IN THE COURT OF APPEAL OF MALAYSIA Coram: Tengku Maimun Tuan Mat, JCA; Nallini Pathmanathan, JCA; Suraya Othman, JCA P Mukundan A/L P K Kunchu Kurup and 2 Others v Daniel A/L Anthony and Another Appeal

More information

THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION

THE PREVENTION PRINCIPLE AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION -..". THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS CORDON SMITH Partner, Baker & McKenzie, Wong & Leow, Singapore INTRODUCTION The "prevention principle" operates

More information

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied.

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied. CITY UNIVERSITY OF HONG KONG Breach and Remedy Refer to Richards, P. Law of Contract Chapters 16-18 Uff, J. Construction Law 9 th Edition Chapter 9 BREACH OF CONTRACT A breach of contract occurs where

More information

D.R. 48/96 RANG UNDANG-UNDANG. Suatu Akta untuk meminda Kanun Prosedur Jenayah.

D.R. 48/96 RANG UNDANG-UNDANG. Suatu Akta untuk meminda Kanun Prosedur Jenayah. D.R. 48/96 Naskhah Sahih Bahasa Inggeris RANG UNDANG-UNDANG b e r n a m a Suatu Akta untuk meminda Kanun Prosedur Jenayah. [ ] MAKA INILAH DIPERBUAT UNDANG-UNDANG oleh Seri Paduka Baginda Yang di-pertuan

More information

Martin Waldron BL FCIArb MSCSI MRICS

Martin Waldron BL FCIArb MSCSI MRICS MARTIN WALDRON BL FCIArb MSCSI MRICS Law Library Distillery Building 145-151 Church Street Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie Construction Bar Association Construction

More information

PERFORMANCE BOND: CONDITIONAL OR UNCONDITIONAL 'AZIZAN BIN SUPARDI UNIVERSITI TEKNOLOGI MALAYSIA

PERFORMANCE BOND: CONDITIONAL OR UNCONDITIONAL 'AZIZAN BIN SUPARDI UNIVERSITI TEKNOLOGI MALAYSIA PERFORMANCE BOND: CONDITIONAL OR UNCONDITIONAL 'AZIZAN BIN SUPARDI UNIVERSITI TEKNOLOGI MALAYSIA PERFORMANCE BOND: CONDITIONAL OR UNCONDITIONAL 'AZIZAN BIN SUPARDI A master s project report submitted in

More information

Held: Per Abdul Hamid Mohamad JCA

Held: Per Abdul Hamid Mohamad JCA 1 M/S LAKSAMANA REALTY SDN BHD v. GOH ENG HWA COURT OF APPEAL, KUALA LUMPUR ABDUL HAMID MOHAMAD, JCA; MOHD NOOR AHMAD, JCA; ABDUL AZIZ MOHAMAD, JCA CIVIL APPEAL NOS: M-02-347-2001, M-02-388-2001 & M-02-530-2001

More information

PERMOHONAN PEMBAHARUAN PERMIT APPLICATION FOR A RENEWAL OF PERMIT

PERMOHONAN PEMBAHARUAN PERMIT APPLICATION FOR A RENEWAL OF PERMIT Borang SPAN/P/2 JADUAL KEEMPAT [subkaedah 8(2)/subrule 8(2)] AKTA INDUSTRI PERKHIDMATAN AIR 2006 WATER SERVICES INDUSTRY ACT 2006 KAEDAH-KAEDAH INDUSTRI PERKHIDMATAN AIR (PERMIT) 2007 WATER SERVICES INDUSTRY

More information

PERATURAN-PERATURAN PERLINDUNGAN DATA PERIBADI (PENGKOMPAUNAN KESALAHAN) 2016 PERSONAL DATA PROTECTION (COMPOUNDING OF OFFENCES) REGULATIONS 2016

PERATURAN-PERATURAN PERLINDUNGAN DATA PERIBADI (PENGKOMPAUNAN KESALAHAN) 2016 PERSONAL DATA PROTECTION (COMPOUNDING OF OFFENCES) REGULATIONS 2016 WARTA KERAJAAN PERSEKUTUAN 14 Mac 2016 14 March 2016 P.U. (A) 60 FEDERAL GOVERNMENT GAZETTE PERATURAN-PERATURAN PERLINDUNGAN DATA PERIBADI (PENGKOMPAUNAN KESALAHAN) 2016 PERSONAL DATA PROTECTION (COMPOUNDING

More information

ARBITRATION AGREEMENT IN SUBCONTRACT: INCORPORATION BY REFERENCE MOHAMAD SYAHMI BIN SELIMAN

ARBITRATION AGREEMENT IN SUBCONTRACT: INCORPORATION BY REFERENCE MOHAMAD SYAHMI BIN SELIMAN ARBITRATION AGREEMENT IN SUBCONTRACT: INCORPORATION BY REFERENCE MOHAMAD SYAHMI BIN SELIMAN Dissertation Submitted in Fulfillment of the Requirement for the Award of Master of Construction Contract Management

More information

As the contractor fulfills his various obligations under

As the contractor fulfills his various obligations under Final Certificates: A Review Of Pertinent Substantive And Procedural Issues By Ir. Harbans Singh K.S. 1 engineering & law As the contractor fulfills his various obligations under the contract, the satisfactory

More information

DETERMINATION OF CONTRACT BY EMPLOYER IN CONSTRUCTION INDUSTRY TAY LEE YONG

DETERMINATION OF CONTRACT BY EMPLOYER IN CONSTRUCTION INDUSTRY TAY LEE YONG i DETERMINATION OF CONTRACT BY EMPLOYER IN CONSTRUCTION INDUSTRY TAY LEE YONG A project report submitted in partial fulfilment of the requirement for the award of the degree of Master of Science (Construction

More information

March IR Law Free Newsletter. IR Law provides the following advisory/consultation services to Members and Non-Members*: Disciplinary proceedings

March IR Law Free Newsletter. IR Law provides the following advisory/consultation services to Members and Non-Members*: Disciplinary proceedings IRLaw CORPORATE INDUSTRIAL RELATIONS CONSULTANCY Dear Readers, This is our Free Newsletter, examining some updates on the new Public Holiday for Sarawak, Personal Data Protection Act (PDPA) and our usual

More information

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation.

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation. Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation. English law does not require a particular form to contracts, therefore the terms and ultimately

More information

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN PERMOHONAN SEMAKAN KEHAKIMAN NO /2017 ANTARA LAWAN

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN PERMOHONAN SEMAKAN KEHAKIMAN NO /2017 ANTARA LAWAN DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN PERMOHONAN SEMAKAN KEHAKIMAN NO. 44-16-01/2017 ANTARA AZLI BIN TUAN KOB (NO. K/P : 670326-71-5309) PEMOHON LAWAN 1. LEMBAGA PENCEGAHAN

More information

EXTENSION OF TIME IN COMMENCEMENT OF ARBITRATION PROCEEDINGS NOOR HALWANI BT MOKHTAR UNIVERSITI TEKNOLOGI MALAYSIA

EXTENSION OF TIME IN COMMENCEMENT OF ARBITRATION PROCEEDINGS NOOR HALWANI BT MOKHTAR UNIVERSITI TEKNOLOGI MALAYSIA EXTENSION OF TIME IN COMMENCEMENT OF ARBITRATION PROCEEDINGS NOOR HALWANI BT MOKHTAR UNIVERSITI TEKNOLOGI MALAYSIA EXTENSION OF TIME IN COMMENCEMENT OF ARBITRATION PROCEEDINGS NOOR HALWANI BT MOKHTAR A

More information

D.R. 40/2006 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Akta Kastam DIPERBUAT oleh Parlimen Malaysia seperti yang berikut:

D.R. 40/2006 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Akta Kastam DIPERBUAT oleh Parlimen Malaysia seperti yang berikut: D.R. 40/2006 RANG UNDANG-UNDANG b e r n a m a Suatu Akta untuk meminda Akta Kastam 1967. [ ] DIPERBUAT oleh Parlimen Malaysia seperti yang berikut: Tajuk ringkas dan permulaan kuat kuasa 1. (1) Akta ini

More information

PAM NORTHERN CHAPTER

PAM NORTHERN CHAPTER PAM NORTHERN CHAPTER SATURDAY, 27 FEBRUARY 2016 DELAY AND DISRUPTION IN CONSTRUCTION CONTRACTS BY LIM HOCK SIANG MESSRS PRESGRAVE & MATTHEWS STANDARD CHARTERED BANK CHAMBERS, 2 LEBUH PANTAI, 10300 PENANG,

More information

Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Time and Money: Time Bar Clauses Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Introduction This paper focuses on time bar clauses, with a particular reference to clause 20.1

More information

IN THE HIGH COURT OF JUSTICE BETWEEN AND TECU CREDIT UNION CO-OPERATIVE SOCIETY LIMITED

IN THE HIGH COURT OF JUSTICE BETWEEN AND TECU CREDIT UNION CO-OPERATIVE SOCIETY LIMITED REPUBLIC OF TRINIDAD AND TOBAGO CV 2010-01135 IN THE HIGH COURT OF JUSTICE BETWEEN ERNEST TROTMAN CAMILLE RICHARDS TROTMAN Claimants AND TECU CREDIT UNION CO-OPERATIVE SOCIETY LIMITED ************************************************

More information

VALID AND INVALID VARIATION OMISSION OF WORKS MOTHILAL A/L MUNIANDY

VALID AND INVALID VARIATION OMISSION OF WORKS MOTHILAL A/L MUNIANDY VALID AND INVALID VARIATION OMISSION OF WORKS MOTHILAL A/L MUNIANDY A dissertation submitted in partial fulfillment of the requirements for the award of the degree of Master of Science (Construction Contract

More information

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 TIME AND MONEY: TIME BAR CLAUSES Nicholas Gould 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Introduction This paper focuses on time bar clauses, with a particular reference to clause 20.1 of FIDIC.

More information

LIMITATION PERIOD IN LATENT DEFECTS

LIMITATION PERIOD IN LATENT DEFECTS LIMITATION PERIOD IN LATENT DEFECTS MAZUAN BIN LIN A dissertation submitted in partial fulfillment of the requirements for the award of the degree of Master of Construction Contract Management Faculty

More information

CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG UNIVERSITI TEKNOLOGI MALAYSIA

CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG UNIVERSITI TEKNOLOGI MALAYSIA CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG UNIVERSITI TEKNOLOGI MALAYSIA CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG A master s project report submitted in fulfillment

More information

Statutory Declarations 1 LAWS OF MALAYSIA. Act 783 STATUTORY DECLARATIONS ACT (Revised 2016)

Statutory Declarations 1 LAWS OF MALAYSIA. Act 783 STATUTORY DECLARATIONS ACT (Revised 2016) Statutory Declarations 1 STATUTORY DECLARATIONS ACT 1960 (Revised 2016) REVISED BY THE COMMISSIONER OF LAW REVISION, MALAYSIA UNDER THE AUTHORITY OF THE REVISION OF LAWS ACT 1968 2016 2 Laws of Malaysia

More information

The Contractor s building defects liability in England and Wales

The Contractor s building defects liability in England and Wales The Contractor s building defects liability in England and Wales We discuss in this paper in what circumstances can a contractor be found liable for defects discovered by the building occupier several

More information

Commencement of Arbitration and Time-Bar Clauses

Commencement of Arbitration and Time-Bar Clauses Commencement of Arbitration and Time-Bar Clauses by ANDREW TWEEDDALE and KAREN TWEEDDALE 1. INTRODUCTION This article considers how English courts construe time-bar clauses and whether there is an advantage

More information

EMPLOYMENT APPLICATION FORM ABX CORPORATION SDN BHD ( V) & UTS GROUP OF COMPANIES

EMPLOYMENT APPLICATION FORM ABX CORPORATION SDN BHD ( V) & UTS GROUP OF COMPANIES INSTRUCTIONS: 1. Please read the application form carefully and complete it in BLOCK LETTERS. 2. Please return the completed application form together with one (1) recent passport size photograph and photocopy

More information

D.R. 41/94. b er nama. Suatu Akta untuk meminda Kanun Prosedur Jenayah [ ]

D.R. 41/94. b er nama. Suatu Akta untuk meminda Kanun Prosedur Jenayah [ ] D.R. 41/94 Naskhah Sahih Bahasa Inggeris RANG UNDANG-UNDANG b er nama Suatu Akta untuk meminda Kanun Prosedur Jenayah [ ] MAKA INILAH DIPERBUAT UNDANG-UNDAN oleh Seri Paduka Baginda Yang di-pertuan Agong

More information

2. The following group of persons shall not be eligible to participate in this Contest:

2. The following group of persons shall not be eligible to participate in this Contest: MAYBELLINE MALAYSIA #MAYBELLINETOPSPENDER CONTEST Eligibility 1. This MAYBELLINE MALAYSIA #MAYBELLINETOPSPENDER CONTEST [ Contest ] is organised by L Oreal Malaysia Sdn. Bhd. [328418-A] [ the Organiser

More information

DIDALAM MAHKAMAH TINGGI JENAYAH 4 KUALA LUMPUR DIDALAM WILAYAH PERSEKUTUAN KUALA LUMPUR PERMOHONAN JENAYAH NO: /2016

DIDALAM MAHKAMAH TINGGI JENAYAH 4 KUALA LUMPUR DIDALAM WILAYAH PERSEKUTUAN KUALA LUMPUR PERMOHONAN JENAYAH NO: /2016 1 DIDALAM MAHKAMAH TINGGI JENAYAH 4 KUALA LUMPUR DIDALAM WILAYAH PERSEKUTUAN KUALA LUMPUR PERMOHONAN JENAYAH NO: 44-103-08/2016 MOHD FAHMI REDZA BIN MOHD ZARIN LAWAN PENDAKWA RAYA PERMOHONAN JENAYAH NO:

More information

FEDERAL GOVERNMENT GAZETTE

FEDERAL GOVERNMENT GAZETTE WARTAKERAJAAN PERSEKUTUAN 12 Oktober 2017 12 October 2017 P.U. (A) 314 FEDERAL GOVERNMENT GAZETTE PERINTAH KAWALAN HARGA DAN ANTIPENCATUTAN (PENANDAAN HARGA BARANGAN HARGA TERKAWAL) (NO. 6) 2017 PRICE

More information

UNDANG-UNDANG MALAYSIA

UNDANG-UNDANG MALAYSIA Maktab Kerjasama (Perbadanan) (Pindaan) 1 UNDANG-UNDANG MALAYSIA Akta A1398 akta MAKTAB KERJASAMA (PERBADANAN) (PINDAAN) 2011 2 Undang-Undang Malaysia Akta A1398 Tarikh Perkenan Diraja...... 5 Ogos 2011

More information

View Esteem Sdn Bhd v Bina Puri Holdings Bhd*

View Esteem Sdn Bhd v Bina Puri Holdings Bhd* CIDB Construction Law Report 2016 View Esteem Sdn Bhd v Bina Puri Holdings Bhd* COURT OF APPEAL, PUTRAJAYA CIVIL APPEAL NO: W 02(C)(A) 1507 09/2015 HAMID SULTAN BIN ABU BACKER JCA, PRASAD SANDOSHAM ABRAHAM

More information

Martin Waldron BL FCIArb MSCSI MRICS

Martin Waldron BL FCIArb MSCSI MRICS Law Library Distillery Building 145-151 Church Street Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie CPD talk on CONDITIONS PRECEDENT In Irish Construction Contracts by Martin

More information

D.R. 5/94 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Ordinan Perkapalan Saudagar 1952.

D.R. 5/94 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Ordinan Perkapalan Saudagar 1952. D.R. 5/94 Naskhah Sahih Bahasa Inggeris RANG UNDANG-UNDANG b e r n a m a Suatu Akta untuk meminda Ordinan Perkapalan Saudagar 1952. MAKA INILAH DIPERBUAT UNDANG-UNDANG oleh Seri Paduka Baginda Yang di-pertuan

More information

KONTRAK Diputuskan: [1] [2] [3] [4]

KONTRAK Diputuskan: [1] [2] [3] [4] 1 MOH & ASSOCIATES (M) SDN. BHD LWN. FOCUS PROPERTIES SDN. BHD. & SATU LAGI MAHKAMAH TINGGI MALAYA, PULAU PINANG ABDUL HAMID MOHAMAD GUAMAN SIVIL NO. 23-71-88 29 OGOS 1990 [1990] 1 CLJ Rep 417; [1990]

More information

LIABILITIES OF THE CONTRACT ADMINISTRATOR IN CERTIFICATION AZLINA BINTI ZAINAL ABIDIN

LIABILITIES OF THE CONTRACT ADMINISTRATOR IN CERTIFICATION AZLINA BINTI ZAINAL ABIDIN LIABILITIES OF THE CONTRACT ADMINISTRATOR IN CERTIFICATION AZLINA BINTI ZAINAL ABIDIN A project report submitted in partial fulfillment of the requirements for the award of the degree of Master of Science

More information

SKRINE ADVOCATES & SOLICITORS. IS CONSTRUCTION INDUSTRY AND PAYMENT ADJUDICATION ACT 2012 RETROSPECTIVE OR PROSPECTIVE? Shannon Rajan Partner SKRINE

SKRINE ADVOCATES & SOLICITORS. IS CONSTRUCTION INDUSTRY AND PAYMENT ADJUDICATION ACT 2012 RETROSPECTIVE OR PROSPECTIVE? Shannon Rajan Partner SKRINE SKRINE ADVOCATES & SOLICITORS IS CONSTRUCTION INDUSTRY AND PAYMENT ADJUDICATION ACT 2012 RETROSPECTIVE OR PROSPECTIVE? Shannon Rajan Partner SKRINE Global Arbitration Review (GAR) Ranked in Top 100 International

More information

The plaintiff must show that his loss was one which resulted from a breach of contract by the defendant (a direct causal link).

The plaintiff must show that his loss was one which resulted from a breach of contract by the defendant (a direct causal link). 1. CAUSATION The plaintiff must show that his loss was one which resulted from a breach of contract by the defendant (a direct causal link). An act of the defendant in a sequence of events leading to a

More information

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO: K-01(NCVC)(W)-10-01/2014 BETWEEN

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO: K-01(NCVC)(W)-10-01/2014 BETWEEN IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO: K-01(NCVC)(W)-10-01/2014 BETWEEN PERBADANAN KEMAJUAN NEGERI KEDAH APPELLANT AND CBH RUBBER SDN. BHD. (COMPANY NO: 945835-A)

More information

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA KES KEBANKRAPAN NO: /2013

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA KES KEBANKRAPAN NO: /2013 DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA KES KEBANKRAPAN NO: 29-3300-03/2013 PER : YASMIN PEREMA BINTI ABDULLAH (NO. K/P: 730427-05-5030). PERAYU/ PENGHUTANG

More information

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - Background I practice in the building and construction industry as a mediator and conciliator, assisting contracted parties in

More information

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.: W-02(IM)(NCC) /2014 BETWEEN

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.: W-02(IM)(NCC) /2014 BETWEEN IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.: W-02(IM)(NCC)-676-04/2014 BETWEEN ZAMIL STEEL VIETNAM BUILDINGS CO. LTD. - APPELLANT AND G.T.K. BERHAD (Company No.: 198500-P)

More information

KEAHLIAN HOMECLUB TERMA DAN SYARAT:

KEAHLIAN HOMECLUB TERMA DAN SYARAT: KEAHLIAN HOMECLUB TERMA DAN SYARAT: Program HomeClub ( HomeClub ), dikendalikan oleh COURTS (Malaysia) Sdn Bhd ( COURTS ). Di bawah program HomeClub, pelanggan yang diiktiraf layak untuk menerima keistimewaan

More information

Datuk Wira SM Faisal bin SM Nasimuddin Kamal lwn Datin Wira Emilia binti Hanafi & 4 lagi

Datuk Wira SM Faisal bin SM Nasimuddin Kamal lwn Datin Wira Emilia binti Hanafi & 4 lagi Page 1 Malayan Law Journal Unreported/2017/Volume/Datuk Wira SM Faisal bin SM Nasimuddin Kamal lwn Datin Wira Emilia binti Hanafi & 4 lagi - [2017] MLJU 1449-28 August 2017 [2017] MLJU 1449 Datuk Wira

More information

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA KES KEBANKRAPAN NO: 29NCC /2015

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA KES KEBANKRAPAN NO: 29NCC /2015 DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA KES KEBANKRAPAN NO: 29NCC-10794-12/2015 BERKENAAN : KAMALASAN A/L TANGARAJOO (NO. K/P: 850522-08-6763). PENGHUTANG

More information

TABLE OF CONTENTS TITLE DECLARATION DEDICATION ACKNOWLEDGEMENT ABSTRACT ABSTRAK LIST OF CASES LIST OF FIGURES LIST OF ABBREVIATIONS LIST OF APPENDICES

TABLE OF CONTENTS TITLE DECLARATION DEDICATION ACKNOWLEDGEMENT ABSTRACT ABSTRAK LIST OF CASES LIST OF FIGURES LIST OF ABBREVIATIONS LIST OF APPENDICES vii TABLE OF CONTENTS CHAPTER TITLE PAGE TITLE DECLARATION DEDICATION ACKNOWLEDGEMENT ABSTRACT ABSTRAK TABLE OF CONTENTS LIST OF CASES LIST OF FIGURES LIST OF ABBREVIATIONS LIST OF APPENDICES i ii iii

More information

MAYBANK GOLD INVESTMENT ACCOUNT AGREEMENT

MAYBANK GOLD INVESTMENT ACCOUNT AGREEMENT To: Malayan Banking Berhad (the Bank ) Branch / Cawangan MAYBANK GOLD INVESTMENT ACCOUNT AGREEMENT Dear Sirs: I/We the undersigned hereby request and authorise the Bank from time to time at my/our direction

More information

Attestation of Registrable Instruments (Mining) LAWS OF MALAYSIA REPRINT. Act 387 ATTESTATION OF REGISTRABLE INSTRUMENTS (MINING) ACT 1960

Attestation of Registrable Instruments (Mining) LAWS OF MALAYSIA REPRINT. Act 387 ATTESTATION OF REGISTRABLE INSTRUMENTS (MINING) ACT 1960 Attestation of Registrable Instruments (Mining) 1 LAWS OF MALAYSIA REPRINT Act 387 ATTESTATION OF REGISTRABLE INSTRUMENTS (MINING) ACT 1960 Incorporating all amendments up to 1 January 2006 PUBLISHED BY

More information

D.R. 18/2012 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Kanun Keseksaan. DIPERBUAT oleh Parlimen Malaysia seperti yang berikut:

D.R. 18/2012 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Kanun Keseksaan. DIPERBUAT oleh Parlimen Malaysia seperti yang berikut: Kanun Keseksaan (Pindaan) 1 D.R. 18/2012 RANG UNDANG-UNDANG b e r n a m a Suatu Akta untuk meminda Kanun Keseksaan. [ ] DIPERBUAT oleh Parlimen Malaysia seperti yang berikut: Tajuk ringkas dan permulaan

More information

1. Overseas Union Bank Ltd. v. Chuah Ah Sai [1989] 1 LNS 2; [1989] 3 MLJ En. Paul Chin (Tetuan Gan Teik Chee & Ho) bagi pihak Plaintif.

1. Overseas Union Bank Ltd. v. Chuah Ah Sai [1989] 1 LNS 2; [1989] 3 MLJ En. Paul Chin (Tetuan Gan Teik Chee & Ho) bagi pihak Plaintif. 1 LOO CHEONG FOO BERNIAGA SEBAGAI SHARIKAT LOO BROTHERS v. MOHAMED ABDUL KADER A/L SHAUKAT ALI HIGH COURT, PULAU PINANG ABDUL HAMID MOHAMAD J SAMAN PEMULA NO. 24-1077-95 24 SEPTEMBER 1996 [1996] 1 LNS

More information

DALAM MAHKAMAH TINGGI MALAYA DI KOTA BHARU DALAM NEGERI KELANTAN GUAMAN SIVIL NO: MT(2)22-NCVC-44-03/2013 ANTARA MUSTOFA BIN HUSSIN PLAINTIF DAN

DALAM MAHKAMAH TINGGI MALAYA DI KOTA BHARU DALAM NEGERI KELANTAN GUAMAN SIVIL NO: MT(2)22-NCVC-44-03/2013 ANTARA MUSTOFA BIN HUSSIN PLAINTIF DAN DALAM MAHKAMAH TINGGI MALAYA DI KOTA BHARU DALAM NEGERI KELANTAN GUAMAN SIVIL NO: MT(2)22-NCVC-44-03/2013 ANTARA MUSTOFA BIN HUSSIN PLAINTIF DAN RAHIMAH BINTI MOHAMAD DEFENDAN ALASAN PENGHAKIMAN (Interlokutari

More information

(RD/T&C/SDB/ENG/JUN2016) Page 1 of 5

(RD/T&C/SDB/ENG/JUN2016) Page 1 of 5 Setem Hasil Revenue CIMB BANK BERHAD (13491-P) Stamp PERJANJIAN SEWA PETI SIMPANAN KESELAMATAN / AGREEMENT FOR HIRE OF SAFE DEPOSIT BOX No.: CIMB Bank Berhad (13491-P) (selepas ini dirujuk sebagai Bank

More information

D.R. 13/2007 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Akta Kanun Keseksaan (Pindaan) 2006.

D.R. 13/2007 RANG UNDANG-UNDANG. b e r n a m a. Suatu Akta untuk meminda Akta Kanun Keseksaan (Pindaan) 2006. D.R. 13/2007 RANG UNDANG-UNDANG b e r n a m a Suatu Akta untuk meminda Akta Kanun Keseksaan (Pindaan) 2006. DIPERBUAT oleh Parlimen Malaysia seperti yang berikut: Tajuk ringkas dan permulaan kuat kuasa

More information

ARTICLES CONSTRUCTION CONTRACT & MANAGEMENT ISSUES

ARTICLES CONSTRUCTION CONTRACT & MANAGEMENT ISSUES CONSTRUCTION CONTRACT & MANAGEMENT ISSUES In this second quarter issue of Master Builders Journal for 2014, BK Burns & Ong Sdn Bhd, a subsidiary of BK Asia Pacific, an international construction consultancy

More information

PERATURAN-PERATURAN PERTUBUHAN

PERATURAN-PERATURAN PERTUBUHAN PERSATUAN HOTEL BUDGET MALAYSIA (Malaysia Budget Hotel Association) PERATURAN-PERATURAN PERTUBUHAN Rules &Regulation ''\ PPM/WP 434/01(2) PPP/WP (128/01 (PERTUBUHAN 3) MALAYSIA AKTA PERTUBUHAN 1966 PERATURAN-PERATURAN

More information

ADJUDICATOR DETERMINES OWN JURISDICTION: A PREDICTION FOR THE PROPOSED CONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT

ADJUDICATOR DETERMINES OWN JURISDICTION: A PREDICTION FOR THE PROPOSED CONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT ADJUDICATOR DETERMINES OWN JURISDICTION: A PREDICTION FOR THE PROPOSED CONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT IMRAN BIN MOHD YUSOP UNIVERSITI TEKNOLOGI MALAYSIA ADJUDICATOR DETERMINES OWN JURISDICTION:

More information

Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor

Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor COURT OF APPEAL, PUTRAJAYA CIVIL APPEAL NO: A 01 16 01/2013 MOHD ZAWAWI SALLEH JCA, VERNON

More information

Management Bhd dan lain-lain

Management Bhd dan lain-lain Teang Soo Thong dan satu lagi lwn Malaysia Venture apital [2016] 9 MLJ Management hd dan lain-lain (as Zanah Mehat ) 777 Teang Soo Thong dan satu lagi lwn Malaysia Venture apital Management hd dan lain-lain

More information

Held (dismissing the appeal with costs) Per Abdul Hamid Mohamad FCJ (dissenting):

Held (dismissing the appeal with costs) Per Abdul Hamid Mohamad FCJ (dissenting): 1 PERWIRA HABIB BANK MALAYSIA BHD v. LUM CHOON REALTY SDN BHD FEDERAL COURT, PUTRAJAYA STEVE SHIM, CJ (SABAH & SARAWAK); ABDUL HAMID MOHAMAD, FCJ; PAJAN SINGH GILL, FCJ CIVIL APPLICATION NO: 02-13-2003

More information

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA RAYUAN SIVIL NO: BA-12NCVC-7-01/2016 ANTARA

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA RAYUAN SIVIL NO: BA-12NCVC-7-01/2016 ANTARA DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA RAYUAN SIVIL NO: BA-12NCVC-7-01/2016 ANTARA OBNET SDN BHD (DAHULU DIKENALI SEBAGAI INTELLIGENT EDGE SOLUTIONS SDN BHD)

More information

MOK YONG KONG & ANOR v MOK YONG CHUAN

MOK YONG KONG & ANOR v MOK YONG CHUAN Page 1 Malayan Law Journal Reports/2002/Volume 2/MOK YONG KONG & ANOR v MOK YONG CHUAN - [2002] 2 MLJ 718-20 February 2002 [2002] 2 MLJ 718 MOK YONG KONG & ANOR v MOK YONG CHUAN COURT OF APPEAL (KUALA

More information

Time when at large in construction contracts

Time when at large in construction contracts 1 Time when at large in construction contracts By P.C. Markanda Naresh Markanda Rajesh Markanda While inviting tenders, the employer stipulates the time within which it is required of the successful bidder

More information

CRITERIA IN ASCERTAINING PROFESSIONAL NEGLIGENCE ABU BAKAR BIN HASSAN UNIVERSITI TEKNOLOGI MALAYSIA

CRITERIA IN ASCERTAINING PROFESSIONAL NEGLIGENCE ABU BAKAR BIN HASSAN UNIVERSITI TEKNOLOGI MALAYSIA CRITERIA IN ASCERTAINING PROFESSIONAL NEGLIGENCE ABU BAKAR BIN HASSAN UNIVERSITI TEKNOLOGI MALAYSIA CRITERIA IN ASCERTAINING PROFESSIONAL NEGLIGENCE ABU BAKAR BIN HASSAN A master s project report submitted

More information

COMPANY LAW CIVIL PROCEDURE Held: [1] [2]

COMPANY LAW CIVIL PROCEDURE Held: [1] [2] 1 TAN SRI ABDUL AZIZ ZAIN & ORS v. UNITED OVERSEAS LAND LTD & ORS HIGH COURT MALAYA, PULAU PINANG ABDUL HAMID MOHAMAD J CIVIL SUIT NO: 22-265-95 12 OCTOBER 1998 [1998] 4 CLJ 321 COMPANY LAW: Suit by Company

More information

Legal Awareness In The Construction Industry

Legal Awareness In The Construction Industry Legal Awareness In The Construction Industry LET S TALK ABOUT PAM 2006 AGAIN 12 March 2014 Sr Peter Moh Mee Ying B.Sc. (Hon) HBP, MBA, FRISM, ICECA, MRICS, Registered QS INTRODUCTION This paper is prepared

More information

Held (dismissing the appeal): Per Abdul Hamid Mohamad FCJ:

Held (dismissing the appeal): Per Abdul Hamid Mohamad FCJ: 1 SEJAHRATUL DURSINA v. KERAJAAN MALAYSIA & ORS FEDERAL COURT, PUTRAJAYA ABDUL HAMID MOHAMAD, FCJ; PAJAN SINGH GILL, FCJ; ALAUDDIN MOHD SHERIFF, FCJ; RICHARD MALANJUM, FCJ; AUGUSTINE PAUL, FCJ CRIMINAL

More information

DAMAGES FOR BREACH OF CONTRACTS: EMERGING JUDICIAL TRENDS

DAMAGES FOR BREACH OF CONTRACTS: EMERGING JUDICIAL TRENDS DAMAGES FOR BREACH OF CONTRACTS: EMERGING JUDICIAL TRENDS SUMMARY Contracts are an integral part of everyday s life, all over the world. Thus every complex imposes obligations on the parties. If the contract

More information

UNIVERSITI PUTRA MALAYSIA BALANCE OF PAYMENT OF ASEAN FIVE PLUS THREE YONG CHEN CHEN FEP

UNIVERSITI PUTRA MALAYSIA BALANCE OF PAYMENT OF ASEAN FIVE PLUS THREE YONG CHEN CHEN FEP UNIVERSITI PUTRA MALAYSIA EFFECTS OF TRADE LIBERALIZATION ON ECONOMIC GROWTH AND BALANCE OF PAYMENT OF ASEAN FIVE PLUS THREE YONG CHEN CHEN FEP 2007 15 EFFECTS OF TRADE LIBERALIZATION ON ECONOMIC GROWTH

More information

IN THE HIGH COURT OF JUSTICE GARY LEGGE AND MAUREEN LEGGE. Between CHRIS RAMSAWACK AND WESTERN SHIP AND RIG SUPPLIES LIMITED

IN THE HIGH COURT OF JUSTICE GARY LEGGE AND MAUREEN LEGGE. Between CHRIS RAMSAWACK AND WESTERN SHIP AND RIG SUPPLIES LIMITED THE REPUBLIC OF TRINIDAD AND TOBAGO CV No. 2013-00249 IN THE HIGH COURT OF JUSTICE GARY LEGGE 1 st Claimant AND MAUREEN LEGGE 2 nd Claimant Between CHRIS RAMSAWACK 1 st Defendant AND WESTERN SHIP AND RIG

More information

INTRODUCTION THE PROBLEM

INTRODUCTION THE PROBLEM Concurrent Delay: A Contractor Get Out of Jail Card or Employer Windfall? Michael Stokes, Managing Director, Navigant Samuel Widdowson, Associate Director, Navigant INTRODUCTION Delay of some sort is almost

More information

Penalty Clauses: What is left? Jonathan Owen

Penalty Clauses: What is left? Jonathan Owen Penalty Clauses: What is left? Jonathan Owen The history of the issue 1. Every undergraduate law student has had to grapple with the common law rule against penalty clauses in contracts, in the sense of

More information

DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANG KUASA RAYUAN) [RAYUAN SIVIL NO: W-02(NCVC)(W) /2013] ANTARA DAN

DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANG KUASA RAYUAN) [RAYUAN SIVIL NO: W-02(NCVC)(W) /2013] ANTARA DAN DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANG KUASA RAYUAN) [RAYUAN SIVIL NO: W-02(NCVC)(W)-143-01/2013] ANTARA 1. MUAFAKAT KEKAL SDN BHD 2. PERBADANAN PENGURUSAN PALM SPRING @ DAMANSARA... PERAYU DAN 1. PESURUHJAYA

More information