Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor

Size: px
Start display at page:

Download "Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor"

Transcription

1 Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor COURT OF APPEAL, PUTRAJAYA CIVIL APPEAL NO: A /2013 MOHD ZAWAWI SALLEH JCA, VERNON ONG LAM KIAT JCA, ABDUL RAHMAN SEBLI JCA 2 JULY 2015 [2016] 1 CIDB-CLR 47 The Plaintiff operated a brick-producing factory. Pursuant to a supply of electricity contract ( the Contract ), the Second Defendant ( Tenaga ) supplied electricity to the Plaintiff. Before execution of the Contract, Tenaga required the Plaintiff to construct a power substation. The substation housed the Plaintiff s switch gear and relay systems, which functioned as a protection system against internal fault. On or about 13 October 1997, the Jabatan Kerja Raya ( JKR ), under the control of the First Defendant, embarked on constructing a rest and recreation area ( the Project ) on the Ipoh Kuala Lumpur highway ( the Project Site ). The First Defendant wrote three (3) letters to Tenaga requesting all electricity cables along the Project site be removed so that construction could be carried out at the Project Site without hindrance or interruption. There was no evidence that Tenaga proceeded to take the necessary steps to comply with the requests made by the First Defendant. In any event, the First Defendant failed to follow-up with Tenaga on the matter. On 5 August 1998, the First Defendant s Contractor, whilst carrying out works on the Project Site, struck an 11kV underground cable belonging to Tenaga. The cable was damaged and interrupted the supply of electricity to the Plaintiff s factory. The operations in the Plaintiff s factory ceased and the Plaintiff s equipment was damaged. The Plaintiff commenced an action against the First Defendant and Tenaga for damages for negligence and breach of contract. The High Court dismissed the Plaintiff s claim for damages and the Plaintiff appealed to the Court of Appeal. Held, allowing the appeal with costs: (1) On the uncontroverted facts, the Contractor was negligent in damaging the Cable. The Contractor ought reasonably to have foreseen that, if it damaged the Cable, the supply of electricity to the factory would likely to be interfered with and the Plaintiff, would likely suffer loss and damages, including injury to its property. (2) The Judicial Commissioner ( JC ) failed to consider whether the Defendants owed the Plaintiff a duty of care in the first place. Apart from the element of the foreseeability of damage, it was also necessary to consider: (i) the question of proximity or neighbourhood between the 47

2 CIDB Construction Law Report 2015 parties, and (ii) the question of whether it was fair, just and reasonable to impose a duty of care in the circumstances. In the circumstances of the instant case, the damage was foreseeable. The First Defendant s witness ("DW1") confirmed the fact that the First Defendant had control over the supervision of the Project works. DW1 said that JKR was the sole party responsible for the supervision of the Project works. Further, JKR had requested Tenaga to relocate the Cable on the Project site so that the cable would not interfere with the Project works. (3) A non-delegable duty of care is an exception to the rule that an employer is not liable for the negligence of an independent contractor. In the instant case, the First Defendant owed a non-delegable duty of care to ensure that the Project works done would not injure third parties. In the discharge of that duty, the First Defendant was obliged to take all necessary precautions; in the context of the present case, to obtain sufficient information on the Project site and the potential hazards such as the existence of underground cables. Further, subsections 7(2) and (3) of the Government Proceedings Act 1956 allowed a claim to be brought against the First defendant for negligence. (4) It must have been within the contemplation of Tenaga that under the Contract, the Plaintiff was reliant on Tenaga for a consistent supply of electricity to its factory for the purposes of manufacturing bricks. Tenaga had been notified by JKR that the Project works would be carried out on the Project site. Three (3) letters had been sent by JKR to Tenaga asking them to remove and/ or to relocate the electrical cables and or poles in the vicinity of the Project site. There was no evidence to indicate whether having been notified of the same, Tenaga took any action to comply with JKR s requests. It was thus reasonably foreseeable that the Project works could cause damage to the Cables belonging to Tenaga and that any corresponding damage flowing therefrom was also reasonably foreseeable. (5) Due to the nature of the Contract and bearing in mind the dangerous nature of electricity, great care must be taken when dealing with electricity and a higher standard of care is expected of those controlling electricity. (6) Apart from the field of law, the Court itself had no other expertise. Thus in cases involving technical, scientific or medical issues which required specialized knowledge, the Court frequently had to rely on the evidence of experts. This was a case in which the Court had no expertise and thus the evidence of an expert was called for to assist the Court in arriving at a correct decision. The key issues in the instant case were highly technical and required experts with proper qualifications, in-depth and specialised knowledge and experience in the field of electrical power installations, power equipment reliability condition assessment, electrical system disturbance/faulty investigation, system protection coordination analysis 48

3 Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor and investigation and analysis of power equipment breakdown and preventive measures. (7) It is the primary duty of an expert to assist the Court in arriving at the right decision; even if he compromises the case of the party who called him and who is paying for his services. This duty overrides any obligation to the party from whom the expert has received instructions or by whom he is paid. The evidence of an expert should not only be independent but should also be seen to be independent. The opinions of experts are relevant facts only insofar as they can assist the Court in forming an opinion upon the issues in the case. As an independent aid to the court, it is essential that an expert witness possesses and retains a standard of absolute personal integrity. (8) Before the court can accept the testimony of an expert, the competency of the expert must be established. When expert opinions are in conflict with one another, the court is obliged to assess the evidence and accept if necessary the most reliable parts in forming its decision. In that process the court may put relevant questions to the expert for the purposes of clarification or eliciting further information. (9) In the instant case, the trial Judge had referred to the evidence of experts PW8 for the Plaintiff and DW5 and DW7 for the Defendants. The evidence of PW4 - an expert for the Plaintiff - was not referred to by the trial Judge. Further, there was nothing in the Grounds of Judgment to indicate that the JC had preferred the evidence of the Defendant s experts and if so, the reasons therefor. The JC had erred in failing to conduct any assessment of the conflicting evidence of the experts. (10) The Court of Appeal would not agree with Tenaga s contention that the Plaintiff s evidence was inconsistent with its (Plaintiff s) pleaded case that the incident caused a power shortage and/or power surge and/or massive voltage surge at the Plaintiff s premises. The Plaintiffs experts view that the severe voltage transient was identified as the cause of the surge actually supported the Plaintiff s case that the incident caused a power surge to occur at the Plaintiff s premises. Had the JC evaluated the competing views, the JC would have found there to be reason to discount the opinion of DW5 for the Defendants. DW5 was not an independent expert as he had received a monetary grant from Tenaga and had been appointed a consultant for the TNB Research Team. Further, DW7 for the Defendants was not an independent or reliable witness and DW7 s opinion was not uninfluenced by the exigencies of litigation. DW7 s evidence ought to have been discounted. On the other hand the Plaintiff s experts evidence did not shift under cross-examination, nor were their views discredited. The views of the Plaintiff s experts ought to have been accepted as they were wholly plausible having regard to all the circumstances. 49

4 CIDB Construction Law Report 2015 (11) Apart from the Tenaga s failure to act on the 3 letters from the First Defendant for the removal of the cables in the Project Site, it was evident that Tenaga had also failed to maintain a visible cable marker. The only marker according to DW2 was a slab marker that was underground and it was to protect the cable. If piling work was carried out (and not digging works), the workers would not know that there was a slab marker in that area. As such, Tenaga ought to have informed the JKR of the position of the cable without any specific request. (12) On a balance of probabilities, the incident led to a surge and not an undervoltage as contended by Tenaga. It (Tenaga) had also failed to put in place a protection scheme to protect it s users against a surge. Had there been a surge protection scheme put in place, it was probable that damage would not have been caused to the Plaintiff s equipment. (13) The Plaintiff in the instant case had in place a protective system to protect against under-voltage, which was a mandatory requirement. As such, the question of whether the Plaintiff was contributorily negligent did not arise. COMMENTARY by Rodney Martin Managing Director Charlton Martin Consultants Sdn Bhd Duty of Care Associated with Relocation of Utility Supplies Introduction The Plaintiff, Batu Kemas Industri Sdn Bhd ("Batu Kemas") operated a factory in Tanjong Malim producing bricks. The factory was served by an 11kV electricity supply provided by the Second Defendant, Tenaga Nasional Berhad ("TNB"). All was well until one day a contractor engaged by Jabatan Kerja Raya ("JKR"), under the control of the First Defendant, Kerajaan Malaysia, to construct a rest and recreation area along the Ipoh to Kuala Lumpur highway ("the Project"), struck the 11kV underground cable belonging to TNB causing damage to the cable. As a result of the damage to the cable, the electricity supply to the Batu Kemas factory was interrupted causing operations in the factory to cease and equipment to be damaged as a result of a surge consequent upon the damage caused to the cable. 50

5 Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor Batu Kemas commenced an action in the High Court against Kerajaan Malaysia and TNB for damages for negligence and breach of contract which was dismissed. The High Court dismissed the action on three main grounds: (1) Batu Kemas provided no evidence that it had a protection system in place to protect its machines; (2) There was no duty of care and breach of duty by TNB; (3) Even if such a breach of duty did exist, Batu Kemas s contributory negligence was absolute. Batu Kemas then appealed this decision in the Court of Appeal. There was no question on the facts that the contractor who damaged the cable was negligent in doing so. The contractor ought to have foreseen that if it damaged the cable, the likely interruption of electricity supply to the factory would result in Batu Kemas likely suffering loss and damage. The Court of Appeal examined whether the Defendants owed the Plaintiff a duty of care in the first place. Apart from need for foreseeability, the question of proximity arose as well as whether it was fair and reasonable to impose a duty of care in the circumstances. The Court of Appeal decided the damage was indeed foreseeable. Not only did JKR have sole control over the supervision of the Project works, they had actually requested that TNB relocate the cable on the Project site to avoid interfering with the Project works. Although three letters had been sent by JKR to TNB requesting that they remove or relocate the cable, there was no evidence of any action in this regard having been taken by TNB. It was thus reasonably foreseeable that the Project works could cause damage to the cable belonging to TNB and that any corresponding damage flowing therefrom such as that suffered by TNB s customer, Batu Kemas, was also reasonably foreseeable. Due to the dangerous nature of electricity, great care must be taken when dealing with electricity and a higher standard of care is expected of those controlling it such as TNB. As for the other Defendant, Kerajaan Malaysia, there is a general rule that an employer is not liable for the negligence of an independent contractor. However there are often exceptions to any rule and one such exception applied here. A non-delegable duty of care is an exception to the rule that the employer is not liable for the negligence of an independent contractor. In this case Kerajaan Malaysia had to discharge 51

6 CIDB Construction Law Report 2015 this duty by taking all necessary precautions such as obtaining sufficient information on the Project site and the potential hazards such as the existence of underground cables or other utility services. Apart from TNB s failure to act on the 3 letters from JKR requesting the relocation or removal of the cables from the Project site, it was evident that TNB had also failed to maintain a visible cable marker. TNB had an obligation to inform JKR of the position of the cable without any specific request. Batu Kemas had in place a protection system for its equipment to protect against under voltage, which was a mandatory requirement. As such the question of whether Batu Kemas claim failed due to contributory negligence did not arise. Lessons learnt from the case The execution of construction work brings with it a high degree of risk due to the nature of the enterprise. This risk is more pronounced when work is being executed in the ground where utility services or artificial obstructions may be present. Great care must be taken by those responsible for maintaining utility supplies as well as those with the responsibility for supervising the execution of construction work upon any site, to ensure systems are in place to minimise damage to existing utility services and consequent loss arising therefrom. This judgement demonstrates the special non-delegable duty of care which is owed by those in control of the supply of utility services and those supervising any construction activity which may cause damage to the said utility services if not adequately supervised. Suggested best practices to be adopted Those responsible for arranging any kind of construction work to be undertaken on their behalf relating to development work or any other purpose must be mindful of the fact that existing utility services may well need to be relocated to accommodate such construction work. A duty of care arises to ensure such relocation is undertaken without loss or damage to the utilities or persons or property. There is also an obligation on the part of the utility providers to ensure adequate identification of underground utility services is provided to minimise the possibility of loss or damage arising. From the outset of any construction work, priority must be put on activities associated with undertaking relocation work, with adequate resources being deployed to ensure the duty of care is met. 52

Mehrzad Nabavieh & Anor v Chong Shao Fen & Anor and Another Appeal

Mehrzad Nabavieh & Anor v Chong Shao Fen & Anor and Another Appeal Mehrzad Nabavieh & Anor v Chong Shao Fen & Anor and Another Appeal COURT OF APPEAL, PUTRAJAYA CIVIL APPEALS NOs: W 02 (NCVC) (W) 1698 07/2013 & W 0 2(NCVC) (W) 1699 07/2013 ALIZATUL KHAIR OSMAN JCA, LIM

More information

Allan Kinsey & Anor v Sunway Rahman Putra Sdn Bhd & Anor; Dekon Sdn Bhd (Third Party)

Allan Kinsey & Anor v Sunway Rahman Putra Sdn Bhd & Anor; Dekon Sdn Bhd (Third Party) Allan Kinsey & Anor v Sunway Rahman Putra Sdn Bhd & Anor; Dekon Sdn Bhd (Third Party) HIGH COURT, SHAH ALAM SUIT NO: 22(NCVC) 971 2011 PRASAD SANDOSHAM ABRAHAM J 16 APRIL 2015 [2016] 1 CIDB-CLR 72 The

More information

Electricity Supply (Safety and Network Management) Regulation 2014

Electricity Supply (Safety and Network Management) Regulation 2014 New South Wales Electricity Supply (Safety and Network Management) Regulation 2014 under the Electricity Supply Act 1995 Her Excellency the Governor, with the advice of the Executive Council, has made

More information

MOTORIST DROWNS IN RETENTION POND ADJACENT TO HIGHWAY

MOTORIST DROWNS IN RETENTION POND ADJACENT TO HIGHWAY MOTORIST DROWNS IN RETENTION POND ADJACENT TO HIGHWAY James C. Kozlowski, J.D., Ph.D. 1988 James C. Kozlowski Based upon conversations with many park and recreation administrators, it appears that there

More information

Civil Liability Amendment (Personal Responsibility) Act 2002 No 92

Civil Liability Amendment (Personal Responsibility) Act 2002 No 92 New South Wales Civil Liability Amendment (Personal Responsibility) Act 2002 No 92 Contents Page 1 Name of Act 2 2 Commencement 2 3 Amendment of Civil Liability Act 2002 No 22 2 4 Consequential repeals

More information

MMC Engineering Group Bhd & Anor v Wayss & Freytag (Malaysia) Sdn Bhd

MMC Engineering Group Bhd & Anor v Wayss & Freytag (Malaysia) Sdn Bhd CIDB Construction Law Report 2015 MMC Engineering Group Bhd & Anor v Wayss & Freytag (Malaysia) Sdn Bhd HIGH COURT, KUALA LUMPUR ORIGINATING SUMMONS NO: 24C(ARB) 2 05/2013 MARY LIM THIAM SUAN J 11 MAY

More information

159 EMPLOYMENT INFORMATION ACT

159 EMPLOYMENT INFORMATION ACT LAWS OF MALAYSIA REPRINT Act 159 EMPLOYMENT INFORMATION ACT 1953 Incorporating all amendments up to 1 January 2006 PUBLISHED BY THE COMMISSIONER OF LAW REVISION, MALAYSIA UNDER THE AUTHORITY OF THE REVISION

More information

PDF Version. ELECTRICAL SAFETY ACT [REPEALED] published by Quickscribe Services Ltd.

PDF Version. ELECTRICAL SAFETY ACT [REPEALED] published by Quickscribe Services Ltd. PDF Version [Printer-friendly - ideal for printing entire document] ELECTRICAL SAFETY ACT [REPEALED] published by DISCLAIMER: These documents are provided for private study or research purposes only. Every

More information

Electricity Supply Act 1995 No 94

Electricity Supply Act 1995 No 94 New South Wales Electricity Supply Act 1995 No 94 Contents Part 1 Preliminary 1 Name of Act 2 Commencement 3 Objects 4 Definitions 5 Act binds Crown Page 2 2 2 2 2 Part 2 Network operations and wholesale

More information

IN THE COURT OF APPEAL, MALAYSIA (APPELLATE JURISDICTION) SITTING AT KUCHING, SARAWAK CIVIL APPEAL NO. Q /2013. Appellant YUNG ING ING

IN THE COURT OF APPEAL, MALAYSIA (APPELLATE JURISDICTION) SITTING AT KUCHING, SARAWAK CIVIL APPEAL NO. Q /2013. Appellant YUNG ING ING IN THE COURT OF APPEAL, MALAYSIA (APPELLATE JURISDICTION) SITTING AT KUCHING, SARAWAK CIVIL APPEAL NO. Q-02-2628-12/2013 Appellant YUNG ING ING v. Respondent HUNFARA CONSTRUCTION SDN. BHD. [In the matter

More information

Electricity Regulations 1947

Electricity Regulations 1947 Western Australia Electricity Act 1945 Electricity Regulations 1947 As at 01 Jan 2011 Version 05-c0-00 Western Australia Electricity Regulations 1947 CONTENTS Part I Preliminary 1. Citation 1 2. Terms

More information

NEGLIGENCE. All four of the following must be demonstrated for a legal claim of negligence to be successful:

NEGLIGENCE. All four of the following must be demonstrated for a legal claim of negligence to be successful: NEGLIGENCE WHAT IS NEGLIGENCE? Negligence is unintentional harm to others as a result of an unsatisfactory degree of care. It occurs when a person NEGLECTS to do something that a reasonably prudent person

More information

Ingles v. The Corporation of the City of Toronto Decision of the Supreme Court of Canada dated March 2, 2000

Ingles v. The Corporation of the City of Toronto Decision of the Supreme Court of Canada dated March 2, 2000 Ingles v. The Corporation of the City of Toronto Decision of the Supreme Court of Canada dated March 2, 2000 (City Council at its regular meeting held on October 3, 4 and 5, 2000, and its Special Meetings

More information

Health and Safety in Employment Act 1992

Health and Safety in Employment Act 1992 Health and Safety in Employment Act 1992 An Act to reform the law relating to the health and safety of employees, and other people at work or affected by the work of other people BE IT ENACTED by the Parliament

More information

294 GOODS VEHICLE LEVY ACT

294 GOODS VEHICLE LEVY ACT Goods Vehicle Levy 1 LAWS OF MALAYSIA REPRINT Act 294 GOODS VEHICLE LEVY ACT 1983 Incorporating all amendments up to 1 January 2006 PUBLISHED BY THE COMMISSIONER OF LAW REVISION, MALAYSIA UNDER THE AUTHORITY

More information

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF TENNESSEE NASHVILLE DIVISION PLAINTIFF, CASE NO.

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF TENNESSEE NASHVILLE DIVISION PLAINTIFF, CASE NO. IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF TENNESSEE NASHVILLE DIVISION BELLSOUTH TELECOMMUNICATIONS, LLC, D/B/A AT&T TENNESSEE, v. PLAINTIFF, CASE NO. METROPOLITAN GOVERNMENT OF NASHVILLE

More information

IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (COMMERCIAL DIVISION) SUIT NO: D BETWEEN

IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (COMMERCIAL DIVISION) SUIT NO: D BETWEEN IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (COMMERCIAL DIVISION) SUIT NO: D5-22-1924-1999 BETWEEN TUCK SIN ENGINEERING & CONSTRUCTION SDN BHD (No. Syarikat:

More information

Facility Crossing Part 2

Facility Crossing Part 2 AGREEMENT Facility Crossing Part 2 November 1993 (reissued December 2001) This Facility Crossing Agreement is currently undergoing a full review by the Canadian Association of Petroleum Landmen. If you

More information

2012 District of Columbia Code Chapter 27 Underground Facilities Protection (Section to Section ) Section Definitions Section

2012 District of Columbia Code Chapter 27 Underground Facilities Protection (Section to Section ) Section Definitions Section Chapter 27 Underground Facilities Protection (Section 34-2701 to Section 34-2709) Section 34-2701 Definitions Section 34-2702 Formation and operation of 1-call center Section 34-2703 Availability of permit

More information

TELECOMMUNICATIONS ORDINANCE (Chapter 106) WIRELESS INTERNET OF THINGS LICENCE. [Company Name]... [Address]

TELECOMMUNICATIONS ORDINANCE (Chapter 106) WIRELESS INTERNET OF THINGS LICENCE. [Company Name]... [Address] Form 034(1) Licence No. TELECOMMUNICATIONS ORDINANCE (Chapter 106) WIRELESS INTERNET OF THINGS LICENCE DATE OF ISSUE: [ ] [Company Name]... of [Address].. (the licensee ) is licensed, subject to the following

More information

View Esteem Sdn Bhd v Bina Puri Holdings Bhd*

View Esteem Sdn Bhd v Bina Puri Holdings Bhd* CIDB Construction Law Report 2016 View Esteem Sdn Bhd v Bina Puri Holdings Bhd* COURT OF APPEAL, PUTRAJAYA CIVIL APPEAL NO: W 02(C)(A) 1507 09/2015 HAMID SULTAN BIN ABU BACKER JCA, PRASAD SANDOSHAM ABRAHAM

More information

Work Health and Safety Act 2011 No 10

Work Health and Safety Act 2011 No 10 New South Wales Work Health and Safety Act 2011 No 10 Contents Part 1 Preliminary Page Division 1 Introduction 1 Name of Act 2 2 Commencement 2 Division 2 Object 3 Object 2 Division 3 Interpretation Subdivision

More information

MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN GUAMAN SIVIL NO: 22C-20-09/2014 ANTARA PERBADANAN KEMAJUAN NEGERI SELANGOR DAN

MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN GUAMAN SIVIL NO: 22C-20-09/2014 ANTARA PERBADANAN KEMAJUAN NEGERI SELANGOR DAN MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN GUAMAN SIVIL NO: 22C--09/14 ANTARA PERBADANAN KEMAJUAN NEGERI SELANGOR PLAINTIF DAN 1. PROJEK LEBUHRAYA USAHASAMA BERHAD (No. Syarikat

More information

Health and Safety at Work, Etc. Act 1974

Health and Safety at Work, Etc. Act 1974 Health and Safety at Work, Etc. Act 1974 Introduction Prior to 1974, health and safety legislation was reactive. It was enacted in response to problems in particular industries, or particular premises

More information

Facility Crossing Agreement

Facility Crossing Agreement THIS AGREEMENT is made and effective as of the day of, 20. BETWEEN ( Grantor ) (hereinafter and in Schedules A, B & C referred to as the Grantor) and ( Grantee ) (hereinafter and in Schedules A, B & C

More information

Facility Crossing Agreement

Facility Crossing Agreement Schedule A Mutually Agreed to Terms and Conditions Schedule A forms part of the Facility Crossing Agreement. 1. Interpretation 1.01 In this Agreement, including the recitals, the words and terms used shall

More information

GEOTHERMAL RESOURCES ACT

GEOTHERMAL RESOURCES ACT LAWS OF KENYA GEOTHERMAL RESOURCES ACT CHAPTER 314A Revised Edition 2012 [1982] Published by the National Council for Law Reporting with the Authority of the Attorney-General www.kenyalaw.org [Rev. 2012]

More information

Wong Kian Wah v Ng Kien Boon

Wong Kian Wah v Ng Kien Boon IN THE COURT OF APPEAL OF MALAYSIA Coram: Hamid Sultan Abu Backer, JCA; Abdul Rahman Sebli, JCA; Mary Lim, JCA Wong Kian Wah v Ng Kien Boon Citation: [2018] MYCA 230 Suit Number: Civil Appeal No. W 02(NCVC)(W)

More information

THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE AND ST. LUCIA ELECTRICITY SERVICES LTD AND

THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE AND ST. LUCIA ELECTRICITY SERVICES LTD AND SAINT LUCIA Claim No. SLUHCV2002/1144 BETWEEN: THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE PEOPLE S DISCOUNT DRUGS LTD Claimant Consolidated with SLUHCV2003/0345 AND ST. LUCIA ELECTRICITY

More information

BETWEEN. LAI CHENG OOI (f) (the executrix of the estate of Lee Tain Lee Thien Chiung, deceased) AND

BETWEEN. LAI CHENG OOI (f) (the executrix of the estate of Lee Tain Lee Thien Chiung, deceased) AND IN THE COURT OF APPEAL, MALAYSIA AT PUTRAJAYA (APPELLATE JURISDICTION) CIVIL APPEAL NO. S-01(IM)(NCVC)-145-04/2016 [Kota Kinabalu High Court OS No. BKI-24NCVC-44/5-2015] BETWEEN LAI CHENG OOI (f) (the

More information

ABDUL AZIZ ISMAIL & ORS v. ROYAL SELANGOR CLUB

ABDUL AZIZ ISMAIL & ORS v. ROYAL SELANGOR CLUB Abdul Aziz Ismail & Ors [2015] 2 MELR v. Royal Selangor Club 325 ABDUL AZIZ ISMAIL & ORS v. ROYAL SELANGOR CLUB Industrial Court, Kuala Lumpur Eddie Yeo Soon Chye Award No: 327 of 2015 [Case No: 13(25)(22)(25)/4-1255/2011]

More information

TORTS SPECIFIC TORTS NEGLIGENCE

TORTS SPECIFIC TORTS NEGLIGENCE TORTS A tort is a private civil wrong. It is prosecuted by the individual or entity that was wronged against the wrongdoer. One aim of tort law is to provide compensation for injuries. The goal of the

More information

Whistleblower Protection 1 LAWS OF MALAYSIA. Act 711 WHISTLEBLOWER PROTECTION ACT 2010

Whistleblower Protection 1 LAWS OF MALAYSIA. Act 711 WHISTLEBLOWER PROTECTION ACT 2010 Whistleblower Protection 1 LAWS OF MALAYSIA Act 711 WHISTLEBLOWER PROTECTION ACT 2010 2 Laws of Malaysia ACT 711 Date of Royal Assent...... 2 June 2010 Date of publication in the Gazette......... 10 June

More information

APRIL 1998, NRPA LAW REVIEW DUTY TO INSTRUCT, WARN, & DEMONSTRATE UNFAMILIAR JUMPING EXERCISE

APRIL 1998, NRPA LAW REVIEW DUTY TO INSTRUCT, WARN, & DEMONSTRATE UNFAMILIAR JUMPING EXERCISE DUTY TO INSTRUCT, WARN, & DEMONSTRATE UNFAMILIAR JUMPING EXERCISE As illustrated by Dibortolo decision described herein, activity instructors may have a legal duty to provide instructions (including warnings

More information

ELECTRICITY SUPPLY ACT 1990

ELECTRICITY SUPPLY ACT 1990 ELECTRICITY SUPPLY ACT 1990 ELECTRICITY REGULATIONS (AMENDMENT) 20xx In exercise of the powers conferred by section 53 of the Electricity Supply Act 1990 [Act 447], the Minister makes the following regulations:

More information

Coal Mining Safety and Health Act 1999

Coal Mining Safety and Health Act 1999 Queensland Coal Mining Safety and Health Act 1999 Reprinted as in force on 14 December 2007 Reprint No. 2B This reprint is prepared by the Office of the Queensland Parliamentary Counsel Warning This reprint

More information

Electricity Act, 1998 Loi de 1998 sur l électricité

Electricity Act, 1998 Loi de 1998 sur l électricité Electricity Act, 1998 Loi de 1998 sur l électricité ONTARIO REGULATION 22/04 ELECTRICAL DISTRIBUTION SAFETY Consolidation Period: From October 1, 2017 to the e-laws currency date. Last amendment: O. Reg.

More information

Work Health and Safety Act 2011 No 10

Work Health and Safety Act 2011 No 10 New South Wales Work Health and Safety Act 2011 No 10 Status information Currency of version Current version for 1 January 2014 to date (generated 17 October 2014 at 13:12). Legislation on the NSW legislation

More information

ORDINANCE NO BE IT ORDAINED BY THE GOVERNING BODY OF THE CITY OF LAWRENCE, KANSAS:

ORDINANCE NO BE IT ORDAINED BY THE GOVERNING BODY OF THE CITY OF LAWRENCE, KANSAS: APPENDIX B FRANCHISE AGREEMENTS NOTE: The franchise agreements included herein are for information only. Each contains the substance as adopted by the Governing Body but publication clauses, repealers

More information

NORTHERN IRELAND ELECTRICITY SAFETY RULES GUIDANCE DOCUMENT INSTRUCTION FOR OPERATIONS OR WORK ON THE PREMISES

NORTHERN IRELAND ELECTRICITY SAFETY RULES GUIDANCE DOCUMENT INSTRUCTION FOR OPERATIONS OR WORK ON THE PREMISES ONCE PRINTED THIS IS AN UNCONTROLLED DOCUMENT NORTHERN IRELAND ELECTRICITY SAFETY RULES GUIDANCE DOCUMENT INSTRUCTION FOR OPERATIONS OR WORK ON THE PREMISES OF CUSTOMERS RECEIVING HIGH VOLTAGE SUPPLY SRG

More information

OCCUPIERS LIABILITY ACT

OCCUPIERS LIABILITY ACT c t OCCUPIERS LIABILITY ACT PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to November 1, 2003. It is intended for information and

More information

Telecommunications Carriers Forum. Co-siting Code

Telecommunications Carriers Forum. Co-siting Code Telecommunications Carriers Forum Co-siting Code December 2007 2007 The Telecommunications Carriers' Forum Inc. All rights reserved. Copyright in the material contained in this document belongs to the

More information

RENEWABLE ENERGY INTERCONNECTION AGREEMENT

RENEWABLE ENERGY INTERCONNECTION AGREEMENT RENEWABLE ENERGY INTERCONNECTION AGREEMENT This Renewable Energy Interconnection Agreement is made this day of, 20 BETWEEN THE BARBADOS LIGHT & POWER COMPANY LIMITED, a company incorporated under the Companies

More information

DEPARTMENT OF LABOUR. Government Notice. R: October Electrical Installation Regulations, 1992

DEPARTMENT OF LABOUR. Government Notice. R: October Electrical Installation Regulations, 1992 DEPARTMENT OF LABOUR Government Notice. R: 2920 23 October 1992 Electrical Installation Regulations, 1992 The Minister of Manpower has, under section 35 of the Machinery and Occupational Safety Act, 1983

More information

RIGHT-OF-WAY APPLICATION EXCAVATION PERMIT

RIGHT-OF-WAY APPLICATION EXCAVATION PERMIT City of St. Cloud Engineering Department 400 2nd Street South St. Cloud, MN 56301 320-255-7249 RIGHT-OF-WAY APPLICATION EXCAVATION PERMIT Name of Utility Company: Address: City/State/Zip: Telephone: Email:

More information

MALAYSIA IN THE HIGH COURT IN SABAH AND SARAWAK AT FEDERAL TERRITORY, LABUAN. CIVIL CASE NO: LBN-24NCvC-6/ BETWEEN SEJATI SDN. BHD..

MALAYSIA IN THE HIGH COURT IN SABAH AND SARAWAK AT FEDERAL TERRITORY, LABUAN. CIVIL CASE NO: LBN-24NCvC-6/ BETWEEN SEJATI SDN. BHD.. MALAYSIA IN THE HIGH COURT IN SABAH AND SARAWAK AT FEDERAL TERRITORY, LABUAN CIVIL CASE NO: LBN-24NCvC-6/8-2016 BETWEEN SEJATI SDN. BHD.. PLAINTIFF AND DIRECTOR OF LANDS AND SURVEYS.. 1 ST DEFENDANT SABAH

More information

STATE OF MASSACHUSETTS CHAPTER 82

STATE OF MASSACHUSETTS CHAPTER 82 STATE OF MASSACHUSETTS CHAPTER 82 SECTION 40. The following words, as used in this section and sections 40A to 40E, inclusive, shall have the following meanings: "Company", natural gas pipeline company,

More information

Pricing Supplement. Pricing Supplement dated 12 October 2016 TNB GLOBAL VENTURES CAPITAL BERHAD

Pricing Supplement. Pricing Supplement dated 12 October 2016 TNB GLOBAL VENTURES CAPITAL BERHAD Pricing Supplement Pricing Supplement dated 12 October 2016 TNB GLOBAL VENTURES CAPITAL BERHAD Company Number: 1189462-U Issue of U.S.$750,000,000 Sukuk due 2026 under the U.S.$2,500,000,000 Multicurrency

More information

ARLINGTON COUNTY CODE. Chapter 55 UNDERGROUND UTILITY PROTECTION

ARLINGTON COUNTY CODE. Chapter 55 UNDERGROUND UTILITY PROTECTION Chapter 55 55-1. Short Title. 55-2. Authorization and Declaration of Policy. 55-3. Definitions. 55-4. Administration and Enforcement. 55-5. Responsibilities of the Contractor. 55-6. Responsibilities of

More information

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.: W-02(IM)(NCC) /2014 BETWEEN

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.: W-02(IM)(NCC) /2014 BETWEEN IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.: W-02(IM)(NCC)-676-04/2014 BETWEEN ZAMIL STEEL VIETNAM BUILDINGS CO. LTD. - APPELLANT AND G.T.K. BERHAD (Company No.: 198500-P)

More information

SCHEDULE 2B NATIONAL TERMS OF CONNECTION

SCHEDULE 2B NATIONAL TERMS OF CONNECTION SCHEDULE 2B NATIONAL TERMS OF CONNECTION Version 8.0 effective from 01 October 2016 SECTION 1 (A) Introduction: The electricity that is supplied to, or exported from, the premises is conveyed using the

More information

SP MANWEB PLC - GENERAL BILATERAL TERMS AND CONDITIONS FOR ADOPTION OF CONTESTABLE WORKS PART 1 - GENERAL TERMS AND CONDITIONS

SP MANWEB PLC - GENERAL BILATERAL TERMS AND CONDITIONS FOR ADOPTION OF CONTESTABLE WORKS PART 1 - GENERAL TERMS AND CONDITIONS 1. DEFINITIONS PART 1 - GENERAL TERMS AND CONDITIONS 1.1 The following words and expressions shall (except to the extent that the context otherwise requires) have the meanings hereby assigned to them:-

More information

FILED: NIAGARA COUNTY CLERK 02/15/ :54 PM INDEX NO. E157285/2015 NYSCEF DOC. NO. 7 RECEIVED NYSCEF: 02/15/2017

FILED: NIAGARA COUNTY CLERK 02/15/ :54 PM INDEX NO. E157285/2015 NYSCEF DOC. NO. 7 RECEIVED NYSCEF: 02/15/2017 STATE OF NEW YORK SUPREME COURT: COUNTY OF NIAGARA MARTINE JURON vs. Plaintiff, GENERAL MOTORS COMPANY, GENERAL MOTORS HOLDING CORPORATION, COMPLAINT GENERAL MOTORS LLC, SATURN OF CLARENCE, INC., now known

More information

Electricity (Hazards from Trees) Regulations 2003

Electricity (Hazards from Trees) Regulations 2003 Reprint as at (SR 2003/375) Dame Sian Elias, Administrator of the Government Order in Council At Wellington this 15th day of December 2003 Present: Her Excellency the Administrator of the Government in

More information

THE BUILDING CONTROL AMENDMENT REGULATIONS. Martin Waldron BL

THE BUILDING CONTROL AMENDMENT REGULATIONS. Martin Waldron BL MARTIN WALDRON BL FCIArb MSCSI MRICS Accredited Adjudicator & Mediator Law Library The Four Courts Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie THE BUILDING CONTROL AMENDMENT

More information

Debtors 1 LAWS OF MALAYSIA REPRINT. Act 256 DEBTORS ACT Incorporating all amendments up to 1 January 2006

Debtors 1 LAWS OF MALAYSIA REPRINT. Act 256 DEBTORS ACT Incorporating all amendments up to 1 January 2006 Debtors 1 LAWS OF MALAYSIA REPRINT Act 256 DEBTORS ACT 1957 Incorporating all amendments up to 1 January 2006 PUBLISHED BY THE COMMISSIONER OF LAW REVISION, MALAYSIA UNDER THE AUTHORITY OF THE REVISION

More information

OCTOBER 2012 LAW REVIEW OBVIOUS TREE HAZARD ON PARK SLEDDING HILL

OCTOBER 2012 LAW REVIEW OBVIOUS TREE HAZARD ON PARK SLEDDING HILL OBVIOUS TREE HAZARD ON PARK SLEDDING HILL James C. Kozlowski, J.D., Ph.D. 2012 James C. Kozlowski Under traditional principles of landowner liability for negligence, the landowner generally owes a legal

More information

OCCUPATIONAL HEALTH AND SAFETY ACT NO 85 OF 1993

OCCUPATIONAL HEALTH AND SAFETY ACT NO 85 OF 1993 REVISION No.: 0 Page 1 of 23 OCCUPATIONAL HEALTH AND SAFETY ACT NO 85 OF 1993 CONTENTS CLICK ON PAGE NUMBER TO GO TO SECTION OR REGULATION AND USE WEB TOOLBAR TO NAVIGATE Pre-amble 3 Section 7 3 Section

More information

NC General Statutes - Chapter 42 Article 7 1

NC General Statutes - Chapter 42 Article 7 1 Article 7. Expedited Eviction of Drug Traffickers and Other Criminals. 42-59. Definitions. As used in this Article: (1) "Complete eviction" means the eviction and removal of a tenant and all members of

More information

STATE OF MICHIGAN COURT OF APPEALS

STATE OF MICHIGAN COURT OF APPEALS STATE OF MICHIGAN COURT OF APPEALS ALAN BUGAI and JUDITH BUGAI, Plaintiffs-Appellees, UNPUBLISHED April 11, 2017 v No. 331551 Otsego Circuit Court WARD LAKE ENERGY, LC No. 15-015723-NI Defendant-Appellant.

More information

IN THE HIGH COURT OF JUSTICE BETWEEN DUKHARAN DHABAN. And THE PORT AUTHORITY OF TRINIDAD AND TOBAGO (PATT)

IN THE HIGH COURT OF JUSTICE BETWEEN DUKHARAN DHABAN. And THE PORT AUTHORITY OF TRINIDAD AND TOBAGO (PATT) REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV 2008-01684 BETWEEN DUKHARAN DHABAN CLAIMANT And THE PORT AUTHORITY OF TRINIDAD AND TOBAGO (PATT) THE SEAMEN AND WATERFRONT WORKER S TRADE

More information

Robin Rigg Offshore Wind Farm (Navigation and Fishing) (Scotland) Bill

Robin Rigg Offshore Wind Farm (Navigation and Fishing) (Scotland) Bill Robin Rigg Offshore Wind Farm (Navigation and Fishing) (Scotland) Bill [AS INTRODUCED] CONTENTS Section 1 Authority for works obstructing navigation and fishing 2 Power to deviate from specified locations

More information

CODE OF ORDINANCES, DENVER, IOWA

CODE OF ORDINANCES, DENVER, IOWA Title 14 PUBLIC UTILITIES* Chapters: 14.04 Electrical Utility 14.08 Wires and Poles Chapter 14.04 ELECTRICAL UTILITY Sections: 14.04.010 State Regulations Adopted 14.04.020 Adoption of Rules and Charges

More information

SECTION 2 REGULATIONS

SECTION 2 REGULATIONS Original page 7 SECTION 2 REGULATIONS 2.1 Undertaking of the Company 2.1.1 Scope The Company undertakes to furnish communications service via the Company's own facilities, resale of another company's services,

More information

Illinois Official Reports

Illinois Official Reports Illinois Official Reports Appellate Court Bulduk v. Walgreen Co., 2015 IL App (1st) 150166 Appellate Court Caption SAIME SEBNEM BULDUK and ABDULLAH BULDUK, Plaintiffs-Appellants, v. WALGREEN COMPANY, an

More information

Permit to Work Procedure

Permit to Work Procedure 1. Purpose The permit to work procedure provides a system for managing certain high risk activities at NT Airports sites. The purpose of this procedure is to: 2. Scope Provide a level of control to ensure

More information

REMOTENESS OF DAMAGES

REMOTENESS OF DAMAGES REMOTENESS OF DAMAGES certainly now the rule about liability for the tort of negligence and it is a matter of convenience whether we say that where the damage is not of this kind there may be a breach

More information

SCOPE AND EXTENT OF ENGINEERS LEGAL RESPONSIBILITIES FOR DEFECTS AND CONSTRUCTION ACTIVITIES ON SITE

SCOPE AND EXTENT OF ENGINEERS LEGAL RESPONSIBILITIES FOR DEFECTS AND CONSTRUCTION ACTIVITIES ON SITE IES-MOM Seminar on "Moving Beyond Nicoll Highway Incident" SCOPE AND EXTENT OF ENGINEERS LEGAL RESPONSIBILITIES FOR DEFECTS AND CONSTRUCTION ACTIVITIES ON SITE presented by MONICA NEO Advocate & Solicitor

More information

DECEMBER 1985 LAW REVIEW WRITTEN SUPERVISION STANDARD NOT FOLLOWED IN GOLF MISHAP. James C. Kozlowski, J.D James C.

DECEMBER 1985 LAW REVIEW WRITTEN SUPERVISION STANDARD NOT FOLLOWED IN GOLF MISHAP. James C. Kozlowski, J.D James C. WRITTEN SUPERVISION STANDARD NOT FOLLOWED IN GOLF MISHAP James C. Kozlowski, J.D. 1985 James C. Kozlowski The Brahatcek case described herein provides a good illustration of negligence liability based

More information

ASTRONOMY GEOGRAPHIC ADVANTAGE BILL

ASTRONOMY GEOGRAPHIC ADVANTAGE BILL REPUBLIC OF SOUTH AFRICA ASTRONOMY GEOGRAPHIC ADVANTAGE BILL (As introduced in the National Assembly (proposed section 7); Bill published in Government Gazette No. 29897 of 2 May 07) (The English text

More information

CHAPTER 74:01 BOTSWANA POWER CORPORATION ARRANGEMENT OF SECTIONS PART I Preliminary

CHAPTER 74:01 BOTSWANA POWER CORPORATION ARRANGEMENT OF SECTIONS PART I Preliminary SECTION CHAPTER 74:01 BOTSWANA POWER CORPORATION ARRANGEMENT OF SECTIONS PART I Preliminary 1. Short title 2. Interpretation PART II Establishment, Constitution and Membership of the Corporation 3. Establishment

More information

DATED THIS DAY OF 2017 BETWEEN. TENAGA NASIONAL BERHAD (Company Registration No.: W) ( TNB ) AND

DATED THIS DAY OF 2017 BETWEEN. TENAGA NASIONAL BERHAD (Company Registration No.: W) ( TNB ) AND DATED THIS DAY OF 2017 BETWEEN TENAGA NASIONAL BERHAD (Company Registration No.: 200866-W ( TNB AND EACH ORIGINAL PARTY AND EACH ACCEDING PARTY AS DEFINED HEREIN NEDA FRAMEWORK AGREEMENT THIS NEDA FRAMEWORK

More information

LAW REVIEW SEPTEMBER 1992 PLAYGROUND LIABILITY FOR EXPOSED CONCRETE FOOTING UNDER MONKEY BARS IN STATE PARK

LAW REVIEW SEPTEMBER 1992 PLAYGROUND LIABILITY FOR EXPOSED CONCRETE FOOTING UNDER MONKEY BARS IN STATE PARK PLAYGROUND LIABILITY FOR EXPOSED CONCRETE FOOTING UNDER MONKEY BARS IN STATE PARK James C. Kozlowski, J.D., Ph.D. 1992 James C. Kozlowski Documents like the Consumer Product Safety Commission's Handbook

More information

California Bar Examination

California Bar Examination California Bar Examination Essay Question: Torts And Selected Answers The Orahte Group is NOT affiliated with The State Bar of California PRACTICE PACKET p.1 Question Autos, Inc. manufactures a two-seater

More information

LAW REVIEW JUNE 1992 RAINWATER ACCUMULATED IN CLOSED CITY POOL RAISES ATTRACTIVE NUISANCE RISK

LAW REVIEW JUNE 1992 RAINWATER ACCUMULATED IN CLOSED CITY POOL RAISES ATTRACTIVE NUISANCE RISK RAINWATER ACCUMULATED IN CLOSED CITY POOL RAISES ATTRACTIVE NUISANCE RISK James C. Kozlowski, J.D., Ph.D. 1992 James C. Kozlowski The March 1992 law column entitled "Swimming Pool Not 'Attractive Nuisance'

More information

Dangerous Goods Safety Management Act 2001

Dangerous Goods Safety Management Act 2001 Queensland Dangerous Goods Safety Management Act 2001 Reprinted as in force on 18 December 2009 Reprint No. 3 This reprint is prepared by the Office of the Queensland Parliamentary Counsel Warning This

More information

Function of the Jury Burden of Proof and Greater Weight of the Evidence Credibility of Witness Weight of the Evidence

Function of the Jury Burden of Proof and Greater Weight of the Evidence Credibility of Witness Weight of the Evidence 101.05 Function of the Jury Members of the jury, all the evidence has been presented. It is now your duty to decide the facts from the evidence. You must then apply to those facts the law which I am about

More information

the court has jurisdiction to grant a mandatory injunction on an ex parte application in urgent and exceptional cases;

the court has jurisdiction to grant a mandatory injunction on an ex parte application in urgent and exceptional cases; [1986] 1 MLJ 256 BANK ISLAM MALAYSIA BHD v TINTA PRESS SDN BHD & ORS OCJ KUALA LUMPUR ZAKARIA YATIM J CIVIL SUIT NO C2518 OF 1984 20 August 1985 Practice and Procedure Interlocutory mandatory injunction

More information

v No Wayne Circuit Court REDFORD UNION HIGH SCHOOL, REDFORD

v No Wayne Circuit Court REDFORD UNION HIGH SCHOOL, REDFORD S T A T E O F M I C H I G A N C O U R T O F A P P E A L S DEONTA JACKSON-JAMES, Plaintiff-Appellant, UNPUBLISHED October 11, 2018 v No. 337569 Wayne Circuit Court REDFORD UNION HIGH SCHOOL, REDFORD LC

More information

354 DRAINAGE WORKS ACT

354 DRAINAGE WORKS ACT LAWS OF MALAYSIA REPRINT Act 354 DRAINAGE WORKS ACT 1954 Incorporating all amendments up to 1 January 2006 PUBLISHED BY THE COMMISSIONER OF LAW REVISION, MALAYSIA UNDER THE AUTHORITY OF THE REVISION OF

More information

Expropriation Act (SFS 1972:719) (with amendments up to and including SFS 2005:941)

Expropriation Act (SFS 1972:719) (with amendments up to and including SFS 2005:941) 276 Expropriation Act Expropriation Act (SFS 1972:719) (with amendments up to and including SFS 2005:941) Chap. 1. Introductory provisions Section 1. A real property unit belonging to a party other than

More information

201X No. TRANSPORT AND WORKS, ENGLAND. The Network Rail (Suffolk Level Crossing Reduction) Order CONTENTS TRANSPORT ENGLAND PART 1 PRELIMINARY

201X No. TRANSPORT AND WORKS, ENGLAND. The Network Rail (Suffolk Level Crossing Reduction) Order CONTENTS TRANSPORT ENGLAND PART 1 PRELIMINARY 24.05.18 S T A T U T O R Y I N S T R U M E N T S 201X No. TRANSPORT AND WORKS, ENGLAND TRANSPORT ENGLAND The Network Rail (Suffolk Level Crossing Reduction) Order Made - - - - *** Coming into force - -

More information

ELECTRICITY ACT Cap 95 8 July 1939 ELECTRICITY ACT. Revised Laws of Mauritius

ELECTRICITY ACT Cap 95 8 July 1939 ELECTRICITY ACT. Revised Laws of Mauritius Revised Laws of Mauritius ELECTRICITY ACT Cap 95 8 July 1939 ARRANGEMENT OF SECTIONS SECTION 1. Short title 2. Interpretation 3. Application of Act 4. Permit for supply of electricity 5. Objections to

More information

ELECTRICITY ACT 1939

ELECTRICITY ACT 1939 ELECTRICITY ACT 1939 Act 21/1939 Lane Cap 95 ARRANGEMENT OF SECTIONS 1. Short title 2. Interpretation 3. Application of Act 4. Permits for the supply of electricity 5. Objections to the granting of a permit

More information

275 GOVERNMENT FUNDING ACT

275 GOVERNMENT FUNDING ACT Government Funding 1 LAWS OF MALAYSIA REPRINT Act 275 GOVERNMENT FUNDING ACT 1983 Incorporating all amendments up to 1 January 2006 PUBLISHED BY THE COMMISSIONER OF LAW REVISION, MALAYSIA UNDER THE AUTHORITY

More information

FILED: NEW YORK COUNTY CLERK 06/07/ :33 PM INDEX NO /2016 NYSCEF DOC. NO. 49 RECEIVED NYSCEF: 06/07/2016

FILED: NEW YORK COUNTY CLERK 06/07/ :33 PM INDEX NO /2016 NYSCEF DOC. NO. 49 RECEIVED NYSCEF: 06/07/2016 FILED NEW YORK COUNTY CLERK 06/07/2016 0433 PM INDEX NO. 190115/2016 NYSCEF DOC. NO. 49 RECEIVED NYSCEF 06/07/2016 LYNCH DASKAL EMERY LLP 137 West 25th Street, 5th Floor New York, NY 10001 (212) 302-2400

More information

THE REGIONAL MUNICIPALITY OF PEEL BY-LAW NUMBER

THE REGIONAL MUNICIPALITY OF PEEL BY-LAW NUMBER THE REGIONAL MUNICIPALITY OF PEEL BY-LAW NUMBER 10-2017 A by-law respecting the prevention of Backflow into the Municipal Drinking Water System of The Regional Municipality of Peel. WHEREAS, the Region

More information

THE TAMIL NADU LIFTS RULES, (G.o.Ms.No.173, Energy (B1), 3rd November 1997)

THE TAMIL NADU LIFTS RULES, (G.o.Ms.No.173, Energy (B1), 3rd November 1997) No.SRO.A/117(c)/97.- THE TAMIL NADU LIFTS RULES, 1997 (G.o.Ms.No.173, Energy (B1), 3rd November 1997) In exercise of the powers conferred by sub-section (1) of Section 22 of the Tamil Nadu Lifts Act, 1997

More information

83 CONTINENTAL SHELF ACT

83 CONTINENTAL SHELF ACT LAWS OF MALAYSIA REPRINT Act 83 CONTINENTAL SHELF ACT 1966 Incorporating all amendments up to 1 January 2006 PUBLISHED BY THE COMMISSIONER OF LAW REVISION, MALAYSIA UNDER THE AUTHORITY OF THE REVISION

More information

CLOSING INSTRUCTIONS. this case. As I mentioned at the beginning of the trial, you must keep an open

CLOSING INSTRUCTIONS. this case. As I mentioned at the beginning of the trial, you must keep an open CLOSING INSTRUCTIONS I. GENERAL CLOSING INSTRUCTIONS Members of the jury, it is now time for me to tell you the law that applies to this case. As I mentioned at the beginning of the trial, you must keep

More information

SECTION #6 - REFERENCE #2. Standard Toronto Hydro Connection Agreements Terms of Conditions

SECTION #6 - REFERENCE #2. Standard Toronto Hydro Connection Agreements Terms of Conditions SECTION #6 - REFERENCE #2 Standard Toronto Hydro Connection Agreements Terms of Conditions : o Toronto Hydro-Electric System Limited Connection Agreement Schedule B1: o Micro-Embedded Generation Facility

More information

FRAMEWORK AGREEMENT RELATING TO NETWORK ACCESS AND ADOPTION OF ELECTRICITY CONNECTIONS AND DISTRIBUTION EQUIPMENT BETWEEN

FRAMEWORK AGREEMENT RELATING TO NETWORK ACCESS AND ADOPTION OF ELECTRICITY CONNECTIONS AND DISTRIBUTION EQUIPMENT BETWEEN FRAMEWORK AGREEMENT RELATING TO NETWORK ACCESS AND ADOPTION OF ELECTRICITY CONNECTIONS AND DISTRIBUTION EQUIPMENT BETWEEN WESTERN POWER DISTRIBUTION (SOUTH WEST) PLC, WESTERN POWER DISTRIBUTION (SOUTH

More information

Wyandotte Municipal Services

Wyandotte Municipal Services Electric, Steam, Water Cable Television and High Speed Internet Service since 1889 An Equal Opportunity Employer Wyandotte Municipal Services Expedited Generator Interconnection Requirements INTRODUCTION

More information

NORTHERN IRELAND ELECTRICITY plc. and THE CONNECTED PARTY NAMED IN PART C OF THIS AGREEMENT HIGH VOLTAGE CONNECTION AGREEMENT

NORTHERN IRELAND ELECTRICITY plc. and THE CONNECTED PARTY NAMED IN PART C OF THIS AGREEMENT HIGH VOLTAGE CONNECTION AGREEMENT NORTHERN IRELAND ELECTRICITY plc and THE CONNECTED PARTY NAMED IN PART C OF THIS AGREEMENT HIGH VOLTAGE CONNECTION AGREEMENT CMS Cameron McKenna Mitre House 160 Aldersgate Street London EC1A 4DD T +44(0)20

More information

MSC TRUSTGATE.COM RELYING PARTY AGREEMENT

MSC TRUSTGATE.COM RELYING PARTY AGREEMENT MSC TRUSTGATE.COM RELYING PARTY AGREEMENT PLEASE READ THIS RELYING PARTY AGREEMENT ( AGREEMENT ) BEFORE VALIDATING A SYMANTECSYMANTEC TRUST NETWORKSM ( STN ) DIGITAL CERTIFICATE ("CERTIFICATE"), USING

More information

Consumer Protection Act

Consumer Protection Act NB: Unofficial translation Ministry of Justice, Finland Consumer Protection Act (38/1978; amendments up to 29/2005 included) Chapter 1 General provisions Section 1 (1) This Act applies to the offering,

More information

INDUSTRIAL COURT OF MALAYSIA CASE NO: 15/4-388/14 BETWEEN YASMIN BINTI HARON AND EXTOL CORPORATION (M) SDN. BHD. AWARD NO: 342 OF 2017

INDUSTRIAL COURT OF MALAYSIA CASE NO: 15/4-388/14 BETWEEN YASMIN BINTI HARON AND EXTOL CORPORATION (M) SDN. BHD. AWARD NO: 342 OF 2017 INDUSTRIAL COURT OF MALAYSIA CASE NO: 15/4-388/14 BETWEEN YASMIN BINTI HARON AND EXTOL CORPORATION (M) SDN. BHD. AWARD NO: 342 OF 2017 Before : Y.A. PUAN REIHANA BTE ABD.RAZAK CHAIRMAN (SITTING ALONE)

More information

2007 Disaster and Emergency Management No.13 SAMOA

2007 Disaster and Emergency Management No.13 SAMOA 2007 Disaster and Emergency Management No.13 SAMOA Arrangement of Provisions Part 1 - Preliminary 1. Short title and commencement 2. Interpretation 3. Act to bind the Government 4. Objects Part 2 Disaster

More information

NOTICES ACCOMPANYING THE ELECTRONIC PROSPECTUS/INFORMATION MEMORANDUM/KNOWLEDGE PACK AND E-IPO APPLICATION FORMS FROM THE WEBSITE

NOTICES ACCOMPANYING THE ELECTRONIC PROSPECTUS/INFORMATION MEMORANDUM/KNOWLEDGE PACK AND E-IPO APPLICATION FORMS FROM THE WEBSITE NOTICES ACCOMPANYING THE ELECTRONIC PROSPECTUS/INFORMATION MEMORANDUM/KNOWLEDGE PACK AND E-IPO APPLICATION FORMS FROM THE WEBSITE The person responsible for the issuance, circulation or dissemination of

More information

[DRAFT AMENDMENTS AS AT 24/10/17 ILLUSTRATIVE REGULATIONS FOR THE PURPOSES OF CONSULTATION ONLY] 2004 No HEALTH AND SAFETY

[DRAFT AMENDMENTS AS AT 24/10/17 ILLUSTRATIVE REGULATIONS FOR THE PURPOSES OF CONSULTATION ONLY] 2004 No HEALTH AND SAFETY [DRAFT AMENDMENTS AS AT 24/10/17 ILLUSTRATIVE REGULATIONS FOR THE PURPOSES OF CONSULTATION ONLY] 2004 No. 1769 HEALTH AND SAFETY The Justification of Practices Involving Ionising Radiation Regulations

More information