CIArb March 2017 Conference Civil-Common Law Divergence and Convergence: The Construction Industry Case Study

Size: px
Start display at page:

Download "CIArb March 2017 Conference Civil-Common Law Divergence and Convergence: The Construction Industry Case Study"

Transcription

1 CIArb March 2017 Conference Civil-Common Law Divergence and Convergence: The Construction Industry Case Study Note Good Faith, Estoppel and Abuse of Rights: The Prevention Principle Contents I. GOOD FAITH IN COMMON LAW JURISDICTIONS... 1 II. ESTOPPEL IN COMMON LAW JURISDICTIONS... 2 III. ABUSE OF RIGHTS IN COMMON LAW JURISDICTIONS... 3 IV. THE PREVENTION PRINCIPLE... 3 A. WHAT IS THE PREVENTION PRINCIPLE?... 3 B. ASSORTED EXAMPLES: WHAT SORT OF ACTS/OMISSIONS ENGAGE THE PREVENTION PRINCIPLE?... 5 C. EFFECT OF THE APPLICATION OF THE PREVENTION PRINCIPLE... 6 D. IS A CONTRACTUAL BREACH REQUIRED FOR THE PREVENTION PRINCIPLE TO OPERATE?... 7 E. CAUSATION ISSUES... 7 F. DEBATE... 9 G. EXCEPTIONS I. GOOD FAITH IN COMMON LAW JURISDICTIONS 1. Generally, a duty of good faith must be imposed by express term. In Mid Essex Hospital Services NHS Trust v Compass Group UK & Ireland Ltd (t/a Medirest) [2013] EWCA Civ 200, Jackson LJ held (at [105]): In addressing this question, I start by reminding myself that there is no general doctrine of good faith in English contract law, although a duty of good faith is implied by law as an incident of certain categories of contract If the parties wish to impose such a duty they must do so expressly. 2. In Chelsfield Advisers LLP v Qatari Diar Real Estate Investment Co [2015] EWHC 1322 (Ch), Richard Spearman QC (sitting as a Deputy High Court Judge) held (at [80]), having endorsed the statement of Jackson LJ above in Medirest [2013] EWCA Civ 200, that: 1

2 I consider that the case is stronger still for saying that if the parties wish to produce the result that each of them has the right to terminate the contract in the event that it loses trust and confidence in the other, even when the other party is not in breach of contract and if that may be unreasonable, then they should do expressly. 3. However, an implied term of good faith (or at least a requirement that the parties exercise a certain degree of communication and co-operation which is equivalent to an obligation of good faith) may operate in so-called relational contracts. The class of relational contracts is not firmly established. However, long-term contracts involving a high degree of interaction between parties are the most likely to be included in that description (e.g. joint venture agreements, franchise agreements and long-term distributorship agreements (see Yam Seng Pte Ltd v International Trade Corporation Ltd [2013] EWHC 111 (QB) at [142]-[143] per Leggatt J)). 4. If an obligation of good faith does exist, then its scope and effect will be a matter of contractual interpretation. In CPC Group Ltd v Qatari Diar Real Estate Investment Co [2010] EWHC 1535 (Ch), Vos J held (at [246]) that an agreement to act in utmost good faith in a sale and purchase transaction forming part of a joint venture agreement for a property development was held to give rise to obligations: to adhere to the spirit of the contract, which was to seek to obtain planning consent for the maximum Developable Area in the shortest possible time, and to observe reasonable commercial standards of fair dealing, and to be faithful to the agreed common purpose, and to act consistently with the justified expectations of the parties. 5. In Medirest [2013] EWCA Civ 200, Jackson LJ held (at [112]), in the context of a longterm agreement for the supply of hospital services, that an agreement to co-operate with each other in good faith gave rise to an obligation to work together honestly endeavouring to achieve the stated purposes. II. ESTOPPEL IN COMMON LAW JURISDICTIONS 6. Estoppel is a doctrine which may prevent a party from denying facts that it has previously asserted, or even from denying the effect of promises previously made by it (which will not be enforced as contracts at common law). There are various different types of estoppel: 6.1. issue estoppel prevents a defendant who is adjudged liable by a competent tribunal from subsequently disputing that it was liable in later proceedings with the same parties; 6.2. estoppel by deed is an evidentiary rule that recitals in a deed may not be denied by the party that made them; 6.3. estoppel by representation prevents a claimant from alleging a fact necessary to its claim if it has previously, by word or conduct, represented the contrary to the 2

3 defendant. It is a defence to a claim (or counterclaim), and is not itself a cause of action; 6.4. estoppel by convention (a variant of estoppel by representation, where two parties to a transaction act upon a basis assumed by both of them, rather than represented by one to the other). III. ABUSE OF RIGHTS IN COMMON LAW JURISDICTIONS 7. In common law jurisdictions, abuse of contractual powers is generally dealt with by implying a duty of reasonableness into many contractual obligations. 8. English law implies terms at common law and under statute in certain situations, for example, as to a price (absent agreement), or as to time (absent agreement). Many of these implied terms, rely on the concept of reasonableness in order to fill gaps in the contract that have been left by the parties. Where the English courts imply a term ad hoc into a particular contract, the courts must have regard to the intention of the parties (i.e. an implied term of reasonableness cannot be implied unless it reflects the parties intentions). 9. In Mona Oil Equipment & Supply Co Ltd v Rhodesia Railways Ltd [1949] 2 All ER 1014, Devlin J held that a term of co-operation (which is very often implied) may only reflect the degree of co-operation necessary to make the contract workable. Thus the implied term may fall far short of a requirement for reasonable co-operation. IV. THE PREVENTION PRINCIPLE A. WHAT IS THE PREVENTION PRINCIPLE? 10. The prevention principle is predicated on the idea that a promisee may not insist upon the performance of a contractual obligation which the promisee has itself by its conduct prevented the promisor from performing. 11. In the Edwardian English case of Wells v Army & Navy Co-operative Society, it was held by Vaughan Williams LJ that: In the contract one finds the time limited within which [a party] is to do his work. This means, not only that he is to do it within that time but it means also that he is to have that time within which to do it. 12. Thus, if the work is expanded so as to require more time, the obligor must be given that time, otherwise the obligee may not be permitted to rely upon its contractual rights against non-compliance because at least one of the causes of delay to the completion date will have arisen as a result of an event for which the obligor takes the risk and the prevention principle then arises. 3

4 13. In Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd [2007] EWHC 447 (TCC) (a claim by a main contractor against a sub-contractor blaming them for delays in the design, supply and installation of various electronic communication systems at Wembley Stadium), Jackson J (as he then was) (at [47]-[49]) held as follows: 47 The construction point turns upon the operation of the prevention principle in the context of the present sub-contract. The essence of the prevention principle is that the promisee cannot insist upon the performance of an obligation which he has prevented the promisor from performing. 48 In the field of construction law, one consequence of the prevention principle is that the employer cannot hold the contractor to a specified completion date, if the employer has by act or omission prevented the contractor from completing by that date. Instead, time becomes at large and the obligation to complete by the specified date is replaced by an implied obligation to complete within a reasonable time. The same principle applies as between main contractor and sub-contractor. 49 It is order to avoid the operation of the prevention principle that many construction contracts and sub-contracts include provisions for extension of time. Thus, it can be seen that extension of time clauses exist for the protection of both parties to a construction contract or sub-contract. 14. In Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWHC 2132 (TCC) (another main contractor vs sub-contractor claim), Ramsey J (at [518]) held as follows: The principle is of some antiquity and has a surprising effect on the contractual obligations as to the time for completion. 15. Perhaps the most significant effect of the prevention principle in terms of its practical application is that, as a general rule, the promisee loses its right to claim liquidated damages in respect of a failure by the other party to complete work to time. In McAlpine Humberoak v McDermott International (1992) 8 Const LJ 383, Lloyd LJ noted that Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd 1 BLR 111, The Cape Hatteras [1982] 1 Lloyd s Rep 518 and SMK Cabinets v Hill Modern Electrics Pty Ltd [1984] VR 391 were all cases where an employer was claiming liquidated damages and in all of them it was held that the claim for liquidated damages must fail since the employer could not rely on the original date of completion, nor on a power to extend the date of completion. In the absence of such a power, there could be no fixed date from which the liquidated damages could run. 16. In summary, therefore, where there is a contractually binding date for completion but, for reasons within the obligee s control, the obligor is prevented from completing by the stipulated date, then: the obligee can no longer insist upon completion by the due date; 4

5 16.2. the obligor is then left without a firm date by which to complete; and the obligor must then complete within a reasonable period. 17. According to Pickavance K, Delay and Disruption in Construction Contracts (4th ed) (2010), citing Bramble B and Callahan M, Construction Delay Claims (2009), there does not appear to be any or any significant US case law on the prevention principle. However, the prevention principle is an equitable remedy that is familiar to most common law countries. 18. Furthermore, the prevention principle is encapsulated in Article of the Unidroit Principles of International Commercial Contracts (2010) (interference by the other party) (a party may not rely on the non-performance of the other party to the extent that such non-performance was caused by the first party s act or omission or by another event for which the first party bears the risk). 19. Concepts similar to the common law prevention principle arise in some civil law codes. One example is Article 1147 of the French Civil Code: A debtor shall be ordered to pay damages, if there is occasion, either by reason of the non-performance of the obligation, or by reason of delay in performing, whenever he does not prove that the nonperformance comes from an external cause which may not be ascribed to him, although there is no bad faith on his part. B. ASSORTED EXAMPLES: WHAT SORT OF ACTS/OMISSIONS ENGAGE THE PREVENTION PRINCIPLE? 20. The following examples emerge from the case law where an employer has prevented the completion of the works in some way and has thus been denied relief by virtue of the prevention principle. 21. Failure to give possession of/access to the work site: in Holme v Guppy (1838) 15 ER 1195, the plaintiffs were supposed to complete carpentry work within 4.5 months from the date of the contract, but the defendant failed to give them possession until 4 weeks after the contract entered into force, which in turn caused further delays); in Rapid Building v Ealing Family Housing (1984) 29 BLR 5, the defendant was unable to give possession to the plaintiffs because of squatters which caused 19 days of delay whilst eviction proceedings were prosecuted through the county courts and subsequent eviction measures were taken. 22. Failure to provide plans at the proper time: in Roberts v Bury Commissioners (1870) LR 5 CP 310, failure by the defendants (and third party architects) to supply plans and drawings and failure to set out the land and define roads and failure to give particulars necessary to enable the commencement of the works caused delay. 5

6 23. Improper interference in the carrying out of the works: in Russell v Sa da Bandeira (1862) 13 CB (NS) 149, the plaintiffs had contracted with the defendant to build a warship for the Government of Portugal. A large number of disputes and objections arose during the course of the build as a result of demands made by the defendant (which, in turn, were as a result of demands made (orally) by Portuguese government agents). An arbitrator found that a considerable portion of the delay in completing the vessel was attributable to these disputes and objections. 24. Ordering extras which necessarily delay the works: in Dodd v Churton [1897] 1 QB 562, the additional extras ordered necessitated a delay. The defendant allowed a fortnight s delay but the work took 6 months extra. Even so, liquidated damages were still disallowed on the basis of the prevention principle; in The Cape Hatteras [1982] 1 Lloyd s Rep 518, the plaintiffs provided goods and services to a ship including drydocking, cleaning, painting, modifications and ancillary services for repairs carried out by the ship s crew. The defendant owners and managers attempted to avoid liability for anything more than the agreed price of engine repair and counterclaimed for a 92 day delay. Staughton J rejected the counterclaim on the basis of the defendants delays caused by the additional works requested over and above the agreed engine repair. 25. Failure to deliver components agreed in the contract: in Perini Pacific v Greater Vancouver Sewerage & Drainage District (1966) 57 DLR (2d) 307, the Court of Appeal of British Columbia held that an owner s failure to deliver engines that were agreed to be incorporated into a building (which resulted in the builder failing to complete the work on time) prevented him from relying on a liquidated damages clause. 26. Delay in providing essential instructions: in Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970) 69 LGR 1, an independent engineer nominated by a local authority to do a report on defective foundation piles took 6 months to enter his report and then the local authority took a further 2 months to accept the report. Total delay was 58 weeks. The Court of Appeal held that this prevented reliance on a liquidated damages clause. C. EFFECT OF THE APPLICATION OF THE PREVENTION PRINCIPLE 27. In such circumstances time is at large (i.e. absent an effective extension of time clause and unless the contract clearly provides otherwise, an act of prevention by a party releases the counterparty from its obligation to complete the works within or by any fixed period or date and that original obligation is replaced by an implied obligation to complete within a reasonable time). 6

7 28. Therefore there is no contractual date from which liability to pay liquidated damages may run (Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970) 69 LGR 1). D. IS A CONTRACTUAL BREACH REQUIRED FOR THE PREVENTION PRINCIPLE TO OPERATE? 29. The operation of the prevention principle does not require a breach of contract. It also applies to actions that are lawful and are permissible under the contract terms but which nevertheless have the effect of impeding the progress of the building works. This was established in Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd [2007] EWHC 447 (TCC) at [56] where Jackson J, having reviewed the authorities, derived three propositions, the first of which was: (i) actions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date. E. CAUSATION ISSUES 30. A key aspect of the operation of the prevention principle is that the acts of prevention must have been the cause of the delay. Therefore issues of causation regularly feature in judicial considerations of the prevention principle. 31. According to Keating on Contracts (10th ed) at 8-014, if the prevention occurs after the contractual completion date when the contractor is already in delay, it seems that the employer is able to recover liquidated damages up to the date of prevention and may be able to do so beyond. The cases of McAlpine Humberoak v McDermott International (1992) 58 BLR 1 and SMK Cabinets v Hill Modern Electrics [1984] VR 391 are cited in this respect however the point does not seem to have been decided conclusively yet. 32. The same passage from Keating on Contracts also notes that there may be complications arising if there is a condition precedent to the right to recover liquidated damages in the contract: in Balfour Beatty v Chestermount Properties (1993) 62 BLR 1, where an architect s certificate was such a condition precedent, Colman J concluded that, on a true construction of the contract in that case, the architect was entitled to grant extensions of time as a consequence of relevant events whether such events occurred before or after the completion date as then extended; in Al-Waddan Hotel Ltd v MAN Enterprise SAL (Offshore) [2014] EWHC 4796 (TCC), HHJ Raeside QC held (at [53]) that: It is and must be conceded that if a party desires to rely on the non-performance of a condition precedent he must do nothing to prevent the condition from being performed, and if there is anything that must be done by him to render possible the performance of the condition, a failure by him to do what is required disentitles him from insisting on performance of the condition. 7

8 33. Importantly, in cases where there are concurrent causes of delay (and where each party bears responsibility for one of the causes) the prevention principle will not operate. This is because the delay would have occurred anyway; it cannot be said that the delay would not have occurred but for the delay for which the obligee is responsible. 34. In Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm), the defendant engaged the claimant to build ships for the UK Government under contracts that required the vessels to satisfy the requirements of the UK Maritime Coastguard Agency ( UKMCA ). When the ships were not ready on time, and the issue arose as to whether the defendant was entitled to rescind the contracts, the claimant contended that the delays were caused by the imposition of various new design items imposed by the UKMCA. The defendant, in addition to arguing that the new design items did not constitute contractual variations, countered that the claimant had already fallen behind schedule over a year earlier (and had failed to comply with notice provisions for seeking extensions). In finding that the claimant was not entitled to rely on the prevention principle, Hamblen J held (at [282]): The conduct therefore has to render it impossible or impracticable for the other party to do the work within the stipulated time. The act relied on must actually prevent the contract from carrying out the works within the contract period or, in other words, must cause some actual delay. 35. In Jerram Falkus Construction Ltd v Fenice Investments Ltd [2011] EWHC 1935 (TCC), (a challenge to an adjudication decision where the claimant argued that deletions from the extension of time provisions meant that no extension of time could be granted in relation to acts of prevention and therefore time must be at large), Coulson J held (at [50]) as follows regarding Hamblen J s judgment in Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm): Hamblen J s analysis indicated that, if there were two concurrent causes of delay, one which was the contractor s responsibility, and one which was said to trigger the prevention principle, the principle would not in fact be triggered because the contractor could not show that the employer s conduct made it impossible for him to complete within the stipulated time. The existence of a delay for which the contractor is responsible, covering the same period of delay which was caused by an act of prevention, would mean that the employer had not prevented actual completion. Throughout his analysis, Hamblen J stressed the importance of the contractor proving delay to the actual progress of the work as a result of the alleged act of prevention. 36. In Saga Cruises BDF Ltd v Fincantieri SPA [2016] EWHC 1875 (Comm), Sara Cockerill QC (sitting as a Deputy High Court Judge) held (at [251]), having reviewed the authorities, that: These extracts, in my judgment, point the way clearly. A careful consideration of the authorities indicates that unless there is a concurrency actually affecting the completion date as then scheduled the contractor cannot claim the benefit of it. Causation in fact must be proved based on the situation at the time as regards delay. 8

9 F. DEBATE 37. There has been some judicial criticism of taking a strict approach to the application of the prevention principle to invalidate contractual liquidated damages clauses. 38. In Rapid Building Group Ltd v Ealing Family Housing Association Ltd (1984) 29 BLR 5, Lloyd LJ stated: Like Lord Justice Phillimore in Peak Construction (Liverpool v. McKinney Foundations Ltd, at p.127 of the report, I was somewhat startled to be told in the course of the argument that if any part of the delay was caused by the employer, no matter how slight, then the liquidated damages clause in the contract, clause 22, becomes inoperative. I can well understand how that must necessarily be so in a case in which the delay is indivisible and there is a dispute as to the extent of the employer s responsibility for that delay. But where there are, as it were, two separate and distinct periods of delay with two separate causes, and where the dispute relates only to one of those two causes, then it would seem to me just and convenient that the employer should be able to claim liquidated damages in relation to the other period. 39. The operation of the prevention principle has been limited in situations where an extension of time is not available as regards an employer s default caused by a contractor s failure to comply with contractual notice provisions. In Steria Ltd v Sigma Wireless Communications Ltd [2008] BLR 79, HHJ Davies held (at [95]-[96]) that: It is difficult to see why [the prevention principle should apply to the aforementioned situations], since these circumstances cannot readily be characterised as acts of prevention by the employer. 40. A spanner was thrown in the works by Gaymark Investments Pty Ltd v Walter Construction Group Ltd (formerly Concrete Constructions Group Ltd) 21 Con LJ 71 an Australian case which decided that non-compliance with a notice provision was sufficient to put time at large. However, in Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd [2007] EWHC 447 (TCC), Jackson J held (at [103]), having reviewed academic authority, that: I am bound to say that I see considerable force in Professor Wallace s criticisms of Gaymark. I also see considerable force in the reasoning of the Australian courts in the Turner and Peninsula cases and in the reasoning of the Inner House in City Inn. Whatever may be the law of the Northern Territory in Australia, I have considerable doubt that Gaymark represents the law of England. Contractual terms requiring a contractor to give prompt notice of delay serve a valuable purpose; such notice enables matters to be investigated while they are still current. Furthermore, such notice sometimes gives the employer the opportunity to withdraw instructions when the financial consequences become apparent. If Gaymark is good law, then a 9

10 contractor could disregard with impunity any provision making proper notice a condition precedent. At his option the contractor could set time at large. G. EXCEPTIONS 41. There are two exceptions to the general rule that the obligee will lose (as a result of the application of the prevention principle) the right to rely on a liquidated damages clause: where a contractor agrees to complete works by the due date even though additional work is instructed; and where the contract provides a mechanism for the extension of time for a delay event which otherwise would amount to an act of prevention by the employer. 42. In Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm), Hamblen J held (at [243]), following Multiplex v Honeywell, that: the prevention principle does not apply if the contract provides for an extension of time in respect of relevant events. Where such a mechanism exists, if the relevant act of prevention falls within the scope of the extension of time clause, the contract completion dates are extended as appropriate and the Builder must complete the work by the new date, or pay liquidated damages (or accept any other contractual consequence of late completion). 43. In Walter Lilly & Co Ltd v Mackay [2012] EWHC 1773 (TCC), Akenhead J held (at [370]) that: In any event, I am clearly of the view that, where there is an extension of time clause such as that agreed upon in this case and where delay is caused by two or more effective causes, one of which entitles the contractor to an extension of time as being a relevant event, the contractor is entitled to a full extension of time. Part of the logic of this is that many of the relevant events would otherwise amount to acts of prevention and that it would be wrong in principle to construe Clause 25 on the basis that the contractor should be denied a full extension of time in those circumstances. More importantly however, there is a straight contractual interpretation of Clause 25 which points very strongly in favour of the view that, provided that the relevant events can be shown to have delayed the Works, the contractor is entitled to an extension of time for the whole period of delay caused by the relevant events in question. There is nothing in the wording of Clause 25 which expressly suggests that there is any sort of proviso to the effect that an extension should be reduced if the causation criterion is established. The fact that the architect has to award a fair and reasonable extension does not imply that there should be some apportionment in the case of concurrent delays. The test is primarily a causation one. 44. In Carillion Construction Ltd v Woods Bagot Europe Ltd [2017] EWCA Civ 65, Jackson LJ held (at [55]) that: 10

11 In the present case the sub-contract contains a perfectly workable extension of time clause. If event B causes, say, two months delay, then the sub-contractor obtains a two month extension of time. The fact that the extension commences on date A, not date C, does not bring the prevention principle into operation. The sub-contractor is not prevented from carrying out the sub-contract works within the extended period which the sub-contract allows. If the sub-contractor fails to complete within that period (either through its own fault or because of the fault of others for whom the subcontractor is responsible, or because of events for which the sub-contractor bears the risk) then the sub-contractor is liable to the main contractor under clause 12 of the conditions. The question whether the extension of time is contiguous or noncontiguous may affect the quantification of that liability. But it does not bring into play the prevention principle. 23 February 2017 Nothing in this text is intended to constitute or should be read as constituting legal advice. Should you require advice on any of the issues discussed in this text, please contact us directly. 11

NOTICES, TIME BARS AND PROPORTIONALITY

NOTICES, TIME BARS AND PROPORTIONALITY NOTICES, TIME BARS AND PROPORTIONALITY A talk by Sir Rupert Jackson to the Hong Kong Society of Construction Law on 21 st September 2018 CONTENTS 1. Introduction 2. Notice provisions 3. A conundrum 4.

More information

International Construction Arbitration Alert

International Construction Arbitration Alert International Construction Arbitration Alert Concurrent Delay Is the English Court of Appeal s Clarification Conclusive? September 13, 2018 Key Points The Court of Appeal has held that a clause denying

More information

Commencement of Arbitration and Time-Bar Clauses

Commencement of Arbitration and Time-Bar Clauses Commencement of Arbitration and Time-Bar Clauses by ANDREW TWEEDDALE and KAREN TWEEDDALE 1. INTRODUCTION This article considers how English courts construe time-bar clauses and whether there is an advantage

More information

Time and Construction Contracts

Time and Construction Contracts Time and Construction Contracts Extensions of Time and the Prevention Principle By Nathan Abbott Introduction The purpose of this paper is to expose and consider the Prevention Principle from a practical

More information

THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION

THE PREVENTION PRINCIPLE AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION -..". THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS CORDON SMITH Partner, Baker & McKenzie, Wong & Leow, Singapore INTRODUCTION The "prevention principle" operates

More information

Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Time and Money: Time Bar Clauses Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Introduction This paper focuses on time bar clauses, with a particular reference to clause 20.1

More information

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 TIME AND MONEY: TIME BAR CLAUSES Nicholas Gould 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Introduction This paper focuses on time bar clauses, with a particular reference to clause 20.1 of FIDIC.

More information

Conditions Precedent to Recovery of Loss and Expense Claims

Conditions Precedent to Recovery of Loss and Expense Claims Conditions Precedent to Recovery of Loss and Expense Claims Dated 07 January 2011 Author Robert Dalton (Head of Construction and Dispute Resolution NW for Blake Newport) Introduction There is a growing

More information

Construction Newsletter Issue No. 20

Construction Newsletter Issue No. 20 Construction Newsletter Issue No. 20 www.4pumpcourt.com Construction Causation Global Claims Extensions of Time Loss and Expense Walter Lilly v Giles Patrick Mackay [2012] EWHC 1773 (TCC) Mr Justice Akenhead

More information

INTRODUCTION THE PROBLEM

INTRODUCTION THE PROBLEM Concurrent Delay: A Contractor Get Out of Jail Card or Employer Windfall? Michael Stokes, Managing Director, Navigant Samuel Widdowson, Associate Director, Navigant INTRODUCTION Delay of some sort is almost

More information

2012 Thomson Reuters. No Claim to Orig. US Gov. Works.

2012 Thomson Reuters. No Claim to Orig. US Gov. Works. 2011 JCCCL 71 Page 1 Journal of the Canadian College of Construction Lawyers 2011 *71 Time at Large in Canada Christopher J. O'Connor, Q.C., Dirk Laudan Copyright 2011 by Thomson Reuters Canada Limited;

More information

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 1 BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 HIGH COURT KAPLAN J ACTION NO 11313 OF 1993 28 July 1994 Civil Procedure -- Summary judgment -- Lack

More information

SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598

SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598 SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598 HIGH COURT KAPLAN J ACTION NO 7005 OF 1991 2 July 1992 Civil Procedure -- Stay of proceedings -- Summary judgment -- Payment

More information

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied.

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied. CITY UNIVERSITY OF HONG KONG Breach and Remedy Refer to Richards, P. Law of Contract Chapters 16-18 Uff, J. Construction Law 9 th Edition Chapter 9 BREACH OF CONTRACT A breach of contract occurs where

More information

The Contractor s building defects liability in England and Wales

The Contractor s building defects liability in England and Wales The Contractor s building defects liability in England and Wales We discuss in this paper in what circumstances can a contractor be found liable for defects discovered by the building occupier several

More information

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22 JUDGMENT : Mr Justice Ramsey : TCC. 22 nd May 2007 Introduction 1. This is an application for leave to appeal under s.69(3) of the Arbitration Act 1996. The arbitration concerns the appointment of the

More information

In Site. Delivery of an adjudicator s decision what happens if it is not delivered in time?

In Site. Delivery of an adjudicator s decision what happens if it is not delivered in time? Autumn 2010 Authors: Kevin Greene kevin.greene@klgates.com +44.(0)20.7360.8188 Inga K. Hall inga.hall@klgates.com +44.(0)20.7360.8137 Suzannah E. Boyd suzannah.boyd@klgates.com +44.(0)20.7360.8186 Lee

More information

B: Principles of Law. DGT Steel and Cladding Ltd v Cubbitt Building and Interiors Ltd [2007] Adj.L.R. 07/04

B: Principles of Law. DGT Steel and Cladding Ltd v Cubbitt Building and Interiors Ltd [2007] Adj.L.R. 07/04 JUDGMENT : HIS HONOUR JUDGE PETER COULSON QC: TCC. 4 th July 2007 A: Introduction 1. This application raises a short but important point of principle in connection with the law relating to adjudication.

More information

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and Neutral Citation Number: [2016] EWHC 1893 (Comm) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION COMMERCIAL COURT Case No: CL-2015-000762 Royal Courts of Justice Strand, London, WC2A 2LL Date: 29/07/2016

More information

Declan Redmond T: +44 (0) E:

Declan Redmond T: +44 (0) E: Keating Chambers 15 Essex Street London WC2R 3AA T +44 (0)20 7544 2600 F +44 (0)20 7544 2700 keatingchambers.com DX: LDE 1045 Call: 2008 pbury@keatingchambers.com Areas of practice Clerks' Details Construction

More information

Section 112 of the HGCR Act is set out below, with the amendments which will be introduced under the LDEDC Act shown in bold:

Section 112 of the HGCR Act is set out below, with the amendments which will be introduced under the LDEDC Act shown in bold: SUSPENSION OF WORK By Peter Sheridan Introduction The remedy of suspension of work for non-payment or late payment is likely to be of increased interest as the credit crunch and the recession continue

More information

1. What are the current challenges to enforcement of multi-tiered dispute resolution clauses?

1. What are the current challenges to enforcement of multi-tiered dispute resolution clauses? England Simon Hart RPC London Simon.Hart@rpc.co.uk Law firm bio 1. What are the current challenges to enforcement of multi-tiered dispute resolution clauses? There are two key challenges a party may face

More information

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 //

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 // CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE PROFESSIONAL NEGLIGENCE ENERGY INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS Edmund Neuberger Call Date 2008 // eneuberger@atkinchambers.com PRACTICE Edmund

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION Reportable IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL No. 19 of 2018 (Arising out of SLP (Civil) No.31049 of 2016) M/S. INOX WIND LTD.... Appellant Versus M/S THERMOCABLES

More information

Challenging the Adjudicator s Decision

Challenging the Adjudicator s Decision Jeremy Glover 1. Mr Justice Coulson, no doubt quite deliberately, noted in 2007 that: With challenges based on jurisdiction and natural justice diffi cult (although not of course impossible) to establish

More information

Time when at large in construction contracts

Time when at large in construction contracts 1 Time when at large in construction contracts By P.C. Markanda Naresh Markanda Rajesh Markanda While inviting tenders, the employer stipulates the time within which it is required of the successful bidder

More information

Hitec Power Protection BV v MCI Worldcom Ltd [2002] Adj.L.R. 08/15

Hitec Power Protection BV v MCI Worldcom Ltd [2002] Adj.L.R. 08/15 JUDGMENT : His Honour Judge Richard Seymour QC : 15 th August 2002. TCC. 1. The application before the court is that of the claimant, a company called Hitec Power Protection BV, for summary judgment for

More information

The material in this paper is based upon the law of England and Wales.

The material in this paper is based upon the law of England and Wales. DESIGN LIABILITY: REASONABLE SKILL AND CARE OR FITNESS FOR PURPOSE May 2016 ADAM ROBB The material in this paper is based upon the law of England and Wales. This material is only intended to provoke and

More information

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Received (in revised form): 11th September, 2005 Sarah Wilson is an associate

More information

Before : MR. JUSTICE EDWARDS-STUART Between :

Before : MR. JUSTICE EDWARDS-STUART Between : Neutral Citation Number: [2014] EWHC 4006 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-2014-000022 (Formerly HT-14-372) Royal Courts of Justice

More information

CIB (2016) : ISBN

CIB (2016) : ISBN Hughes, John and Agapiou, Andrew and Blackie, John (2016) Legal developments in relation to concurrent delay : the position of the English and Scottish courts. In: Proceedings of the CIB 2016 World Building

More information

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS ICON DRILLING ABN 75 067 226 484 PURCHASE ORDER TERMS & CONDITIONS Acceptance of this offer is subject to the terms and conditions of this Agreement. Acceptance of materials, work or services, payment

More information

PAM NORTHERN CHAPTER

PAM NORTHERN CHAPTER PAM NORTHERN CHAPTER SATURDAY, 27 FEBRUARY 2016 DELAY AND DISRUPTION IN CONSTRUCTION CONTRACTS BY LIM HOCK SIANG MESSRS PRESGRAVE & MATTHEWS STANDARD CHARTERED BANK CHAMBERS, 2 LEBUH PANTAI, 10300 PENANG,

More information

Commercial Briefing. Consideration, Anti- Oral Variation Clauses and Collateral Unilateral Contracts. Andrew Bowen QC (Scotland) FCIARB

Commercial Briefing. Consideration, Anti- Oral Variation Clauses and Collateral Unilateral Contracts. Andrew Bowen QC (Scotland) FCIARB Spring 2018 Number 5 Commercial Briefing Andrew Bowen QC (Scotland) FCIARB Consideration, Anti- Oral Variation Clauses and Collateral Unilateral Contracts MWB Business Exchange Centres Ltd v Rock Advertising

More information

TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE

TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE 1 TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE 1.1 Background study. It is often said that for a building or construction project, there are three objectives which the owner of the project is aiming 1.

More information

PAY NOW, ARBITRATE LATER?

PAY NOW, ARBITRATE LATER? BRIEFING PAY NOW, ARBITRATE LATER? OCTOBER 2018 ENGLISH HIGH COURT HOLDS THAT ONLY MATTERS THAT GO DIRECTLY TO ENFORCEABILITY OF ADJUDICATOR S DECISION WILL FALL WITHIN ARBITRATION AGREEMENT EXCEPTION

More information

Adjudicators Discussion 15 June 2016

Adjudicators Discussion 15 June 2016 Probuild Constructions v DDI Group Alucity v ASC/ Alucity v Hick Adjudicators Discussion 15 June 2016 David Campbell-Williams Two recent cases Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd

More information

IN THE SUPREME COURT OF SOUTH AFRICA APPELLATE DIVISION

IN THE SUPREME COURT OF SOUTH AFRICA APPELLATE DIVISION CASE NO 449/91 IN THE SUPREME COURT OF SOUTH AFRICA APPELLATE DIVISION In the matter between: GROUP FIVE BUILDING LIMITED Appellant and MINISTER OF COMMUNITY DEVELOPMENT Defendant CORAM: JOUBERT, E M GROSSKOPF,

More information

Galliford Try Construction Ltd v Mott MacDonald Ltd [2008] APP.L.R. 03/14

Galliford Try Construction Ltd v Mott MacDonald Ltd [2008] APP.L.R. 03/14 JUDGMENT : Mr Justice Coulson : TCC. 14 th March 2008 Introduction 1. This is an application by the Defendant for an order that paragraphs 39 to 48 inclusive of the witness statement of Mr Joseph Martin,

More information

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28 CA on Appeal from High Court of Justice TCC (HHJ Bowsher QC) before Waller LJ; Chadwick LJ. 28 th January 2000. JUDGMENT : Lord Justice Waller: 1. This is an appeal from the decision of His Honour Judge

More information

THE WRITTEN CONTRACT AND DISPUTES IN ADJUDICATION. 1. Section 107 of The Housing Grants, Construction and Regeneration Act 1996

THE WRITTEN CONTRACT AND DISPUTES IN ADJUDICATION. 1. Section 107 of The Housing Grants, Construction and Regeneration Act 1996 THE WRITTEN CONTRACT AND DISPUTES IN ADJUDICATION 1. Section 107 of The Housing Grants, Construction and Regeneration Act 1996 deals with the need for the construction contract to be in writing: (1) The

More information

LONDON BIRMINGHAM BRISTOL EDINBURGH GLASGOW LEEDS MANCHESTER BRUSSELS DUBAI HONG KONG SHANGHAI BEIJING.

LONDON BIRMINGHAM BRISTOL EDINBURGH GLASGOW LEEDS MANCHESTER BRUSSELS DUBAI HONG KONG SHANGHAI BEIJING. Bulletin The Bulletin has been compiled by the Hong Kong Office of Pinsent Masons and summarises recent legal developments in the fields of construction & infrastructure in the Asia Pacific region. For

More information

Before: MRS JUSTICE O'FARRELL DBE Between:

Before: MRS JUSTICE O'FARRELL DBE Between: Neutral Citation Number: [2017] EWHC 2395 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-2017-000173 Royal Courts of Justice Strand, London, WC2A

More information

Canterbury Law Review [Vol

Canterbury Law Review [Vol Canterbury Law Review [Vol. 1. 19811 REFORM OF PRIVITY introduction The doctrine of privity as laid down by the courts in the 19th century has long been the target of law reformers. As long ago as 1937

More information

Before: HIS HONOUR JUDGE PETER COULSON QC Between: - and - CUBITT BUILDING AND INTERIORS LIMITED

Before: HIS HONOUR JUDGE PETER COULSON QC Between: - and - CUBITT BUILDING AND INTERIORS LIMITED Neutral Citation Number: [2007] EWHC 1584 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-07-130 St. Dunstan s House 133-137 Fetter Lane London EC4A

More information

Before : MR JUSTICE PETER SMITH Between :

Before : MR JUSTICE PETER SMITH Between : Neutral Citation Number: [2010] EWHC 1023 (Ch) IN THE HIGH COURT OF JUSTICE CHANCERY DIVISION Case No: HC09CO1648 Royal Courts of Justice Strand, London, WC2A 2LL Date: 11/05/2010 Before : MR JUSTICE PETER

More information

Recent Developments in Adjudication

Recent Developments in Adjudication Richard Bailey Recent Developments in Adjudication Introduction On 1 May 2008 it will be ten years since statutory adjudication was introduced into construction contracts by the Housing Grants, Construction

More information

What s news in construction law 16 June 2006

What s news in construction law 16 June 2006 2 What s news in construction law 16 June 2006 Warranties & indemnities the lessons from Ellington & Tempo services For as long as contracts have existed, issues have arisen in relation to provisions involving

More information

Martin Waldron BL FCIArb MSCSI MRICS

Martin Waldron BL FCIArb MSCSI MRICS MARTIN WALDRON BL FCIArb MSCSI MRICS Law Library Distillery Building 145-151 Church Street Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie Construction Bar Association Construction

More information

Axa Re v Ace Global Markets Ltd. [2006] APP.L.R. 01/20

Axa Re v Ace Global Markets Ltd. [2006] APP.L.R. 01/20 JUDGMENT : MRS JUSTICE GLOSTER: Commercial Court. 20 th January 2006 1. This is an application by the claimant reinsurer, Axa Re ("Axa"), for a declaration under section 72(1)(a) of the Arbitration Act

More information

Projects Disputes in Australia: Recent Cases

Projects Disputes in Australia: Recent Cases WHITE PAPER June 2017 Projects Disputes in Australia: Recent Cases The High Court of Australia and courts in other Australian States have recently ruled on matters of significant importance to the country

More information

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because:

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because: United Kingdom Letters of intent and contract formation RTS Flexible Systems Limited (Respondents) v Molkerei Alois Muller Gmbh & Company KG (UK Production) (Appellants) [2010] UKSC 14C Chris Hill and

More information

Arbitration Act 1996

Arbitration Act 1996 Arbitration Act 1996 An Act to restate and improve the law relating to arbitration pursuant to an arbitration agreement; to make other provision relating to arbitration and arbitration awards; and for

More information

Before: MR JUSTICE AKENHEAD Between: BECK INTERIORS LIMITED - and - UK FLOORING CONTRACTORS LIMITED

Before: MR JUSTICE AKENHEAD Between: BECK INTERIORS LIMITED - and - UK FLOORING CONTRACTORS LIMITED Neutral Citation Number: [2012] EWHC 1808 (TCC) Case No: HT-12-176 IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Before: MR JUSTICE AKENHEAD - - - - - - - - - -

More information

Considering Contract Termination Under English Common Law

Considering Contract Termination Under English Common Law Portfolio Media. Inc. 111 West 19 th Street, 5th Floor New York, NY 10011 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Considering Contract Termination Under English

More information

Index. Volume 21 (2005) 21 BCL

Index. Volume 21 (2005) 21 BCL Index Abandoned claims judgment on, principally concerned with costs, 12-13, 33-44 whether cost reduction appropriate because of, 125 Access to the premises AS 4917-2003, 9-10 Acts Interpretation Act 1954

More information

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23 JUDGMENT : HHJ Anthony Thornton QC. TCC. 23 rd May 2007 1. Introduction 1. The claimant, Mott MacDonald Ltd ( MM ) is a specialist engineering multi-disciplinary consultancy providing services to the construction

More information

Elements of a Civil Claim

Elements of a Civil Claim Elements of a Civil Claim This presentation provides an overview of the elements of a civil claim, with particular reference to construction claims, and looks at each dispute resolution option in the context

More information

BRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018

BRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018 BRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018 THE UK SUPREME COURT HAS OVERTURNED THE DECISION OF THE COURT OF APPEAL, AND DETERMINED THAT NO ORAL MODIFICATION CLAUSES ARE EFFECTIVE

More information

Shipping and International Trade News Bulletin

Shipping and International Trade News Bulletin Shipping and International Trade News Bulletin The Supreme Court Decision in THE GLOBAL SANTOSH: defining responsibility for vicarious contractual performance The Supreme Court handed down its decision

More information

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation.

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation. Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation. English law does not require a particular form to contracts, therefore the terms and ultimately

More information

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21 JUDGMENT : Mr Justice Blackburne. Ch. Div. 21 st February 2003. 1. This is an appeal against orders made by Chief Registrar James on 28 November 2002, dismissing two applications by Peter Shalson to set

More information

Freight Investor Solutions DMCC Terms of Business

Freight Investor Solutions DMCC Terms of Business Freight Investor Solutions DMCC Terms of Business 1. COMMENCEMENT 1.1 The term Agreement hereunder shall mean collectively these Terms of Business ( Terms ), and Freight Investor Solutions DMCC Order Execution

More information

Saunders v Caerphilly County Borough Council

Saunders v Caerphilly County Borough Council Saunders v Caerphilly County Borough Council Philip Robson, Pupil, St John s Chambers Philip Robson provides a case analysis of John Richard Saunders v Caerphilly County Borough Council. Published on 26th

More information

Braes of Doune Wind Farm (Scotland) Ltd v Alfred McaLpine Business Services Ltd [2008] APP.L.R. 03/13

Braes of Doune Wind Farm (Scotland) Ltd v Alfred McaLpine Business Services Ltd [2008] APP.L.R. 03/13 JUDGMENT : Mr. Justice Akenhead: TCC. 13 th March 2008 Introduction 1. There are two applications before the Court relating to the First Award of an arbitrator, Mr John Uff CBE QC. This award relates to

More information

WENDEN ENGINEERING SERVICE CO LTD v WING HONG CONTRAC- TORS LTD - [1992] 2 HKC 380

WENDEN ENGINEERING SERVICE CO LTD v WING HONG CONTRAC- TORS LTD - [1992] 2 HKC 380 WENDEN ENGINEERING SERVICE CO LTD v WING HONG CONTRAC- TORS LTD - [1992] 2 HKC 380 HIGH COURT KAPLAN J MISCELLANEOUS PROCEEDINGS NO 1644 OF 1992 30 July 1992 Arbitration -- Time limit -- Clause in arbitration

More information

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802 NEW SOUTH WALES SUPREME COURT CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802 JURISDICTION: Equity FILE NUMBER(S): 55037/2009 HEARING DATE(S): 24 July 2009 JUDGMENT

More information

Clause 3 deals with the duties and obligations of the Engineer and his assistants.

Clause 3 deals with the duties and obligations of the Engineer and his assistants. Clause 3 Summary Clause 3 deals with the duties and obligations of the Engineer and his assistants. Sub-Clause 3.1 deals with the role and duties of the Engineer. The Engineer is deemed to act for the

More information

Riaz Hussain QC PRACTICE BUILDING DISPUTES. Call Date: 2001, Silk: 2016 //

Riaz Hussain QC PRACTICE BUILDING DISPUTES. Call Date: 2001, Silk: 2016 // GENERAL COMMERCIAL AND INVESTMENT DISPUTES ENERGY, NATURAL RESOURCES AND UTILITIES BUILDING DISPUTES ADJUDICATION PROFESSIONAL NEGLIGENCE Riaz Hussain QC Call Date: 2001, Silk: 2016 // rhussain@atkinchambers.com

More information

A GUIDE TO TERMINATION OF LONG TERM CONTRACTS IN THE ENERGY SECTOR KEY POINTS AND RECENT DEVELOPMENTS

A GUIDE TO TERMINATION OF LONG TERM CONTRACTS IN THE ENERGY SECTOR KEY POINTS AND RECENT DEVELOPMENTS A GUIDE TO TERMINATION OF LONG TERM CONTRACTS IN THE ENERGY SECTOR KEY POINTS AND RECENT DEVELOPMENTS By Dan Jewell (Senior Associate), Elinor Thomas (Legal Director), Simon Collier (Senior Associate)

More information

Consideration sits alongside, offer and acceptance to form a legally binding contract.

Consideration sits alongside, offer and acceptance to form a legally binding contract. CITY UNIVERSITY OF HONG KONG Consideration and Estoppel Refer to Richards Law of Contract Chapter 3 A Introduction Background and function Consideration sits alongside, offer and acceptance to form a legally

More information

LEGAL ISSUES IN ARBITRATIONS - WHEN AND HOW TO TAKE LEGAL ADVICE

LEGAL ISSUES IN ARBITRATIONS - WHEN AND HOW TO TAKE LEGAL ADVICE LEGAL ISSUES IN ARBITRATIONS - WHEN AND HOW TO TAKE LEGAL ADVICE A paper for the Rural Arbix conference on 15 October 2015 1. The options 1. If a legal issue comes up in an arbitration, there are five

More information

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES)

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES) RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES) 1. DEFINITIONS In these Conditions: Business Day means a day other than a Saturday, Sunday or public holiday in England when banks in London

More information

Middle Eastern Oil LLC v National Bank of Abu Dhabi [2008] APP.L.R. 11/27

Middle Eastern Oil LLC v National Bank of Abu Dhabi [2008] APP.L.R. 11/27 JUDGMENT : Mr. Justice Teare : Commercial Court. 27 th November 2008. Introduction 1. This is an application by the Defendant for an order staying the proceedings which have been commenced in this Court

More information

IN THE HIGH COURT OF JUSTICE BETWEEN INDRA ANNIE RAMJATTAN AND MEDISERV INTERNATIONAL LIMITED *********************

IN THE HIGH COURT OF JUSTICE BETWEEN INDRA ANNIE RAMJATTAN AND MEDISERV INTERNATIONAL LIMITED ********************* REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV2010-05295 BETWEEN INDRA ANNIE RAMJATTAN Claimant AND MEDISERV INTERNATIONAL LIMITED Defendant ********************* Before the Honourable

More information

Before: MR ALEXANDER NISSEN QC Between:

Before: MR ALEXANDER NISSEN QC Between: Neutral Citation Number: [2018] EWHC 1472 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-2018-000066 The Rolls Building, Fetter Lane London, EC4

More information

Division 1 Preliminary

Division 1 Preliminary Division 1 Preliminary s. 151 Preliminary Division 1 s. 151 Division 1 Preliminary Subdivision 1 Interpretation 151. Terms used in this Part and Part 10 (1) In this Part and Part 10 acquiring authority,

More information

FLOODING CLAIMS. By Andrew Williams. Last winter was the wettest since records began in It s a fair bet, then, that

FLOODING CLAIMS. By Andrew Williams. Last winter was the wettest since records began in It s a fair bet, then, that By Andrew Williams Last winter was the wettest since records began in 1766. It s a fair bet, then, that there may be several flooding claims arising out of the events of that winter that have yet to be

More information

Before: TRANSGRAIN SHIPPING (SINGAPORE) PTE LTD. - and - YANGTZE NAVIGATION (HONG KONG) CO LTD MV YANGTZE XING HUA

Before: TRANSGRAIN SHIPPING (SINGAPORE) PTE LTD. - and - YANGTZE NAVIGATION (HONG KONG) CO LTD MV YANGTZE XING HUA Neutral Citation Number: [2017] EWCA Civ 2107 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT QUEEN S BENCH DIVISION COMMERCIAL COURT THE HONOURABLE MR JUSTICE TEARE [2016] EWHC 3132

More information

ELA ARBITRATION AND ADR GROUP. Issues arising from Brussels I Recast and Rome I

ELA ARBITRATION AND ADR GROUP. Issues arising from Brussels I Recast and Rome I ELA ARBITRATION AND ADR GROUP Issues arising from Brussels I Recast and Rome I Question 1 Arbitration and Brussels I Recast: Do we agree that that arbitration is outside Brussels I and that the Regulations

More information

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory Arbitration Act 1996 1996 CHAPTER 23 1 Part I Arbitration pursuant to an arbitration agreement Introductory 1. General principles. 2. Scope of application of provisions. 3. The seat of the arbitration.

More information

Proper law of the arbitration agreement how does it fit. with the rest of the contract? Professor Phillip Capper

Proper law of the arbitration agreement how does it fit. with the rest of the contract? Professor Phillip Capper Proper law of the arbitration agreement how does it fit with the rest of the contract? BIICL Fifteenth Annual Review of the Arbitration Act 1996 19 April 2012 Professor Phillip Capper What is the Issue?

More information

Construction Industry Long Service Leave Act 1997

Construction Industry Long Service Leave Act 1997 Version No. 010 Construction Industry Long Service Leave Act 1997 Version incorporating amendments as at 1 March 2005 TABLE OF PROVISIONS Section Page PART 1 PRELIMINARY 1 1. Purpose 1 2. Commencement

More information

Vee Networks Ltd. v Econet Wireless International Ltd. [2004] APP.L.R. 12/14

Vee Networks Ltd. v Econet Wireless International Ltd. [2004] APP.L.R. 12/14 JUDGMENT : Mr Justice Colman : Commercial Court. 14 th December 2004 Introduction 1. The primary application before the court is under section 67 of the Arbitration Act 1996 to challenge an arbitration

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV M VAN DER WAL BUILDERS & CONTRACTORS LTD Plaintiff

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV M VAN DER WAL BUILDERS & CONTRACTORS LTD Plaintiff IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2011-004-000083 BETWEEN AND M VAN DER WAL BUILDERS & CONTRACTORS LTD Plaintiff PETER WALKER AND PHILIPPA DUNPHY Defendants Hearing: 24 August 2011

More information

Adjudication. Information note. Adjudication

Adjudication. Information note. Adjudication Information note In July 1994 Sir Michael Latham published his report Constructing the Team. In the report were recommendations concerning adjudication. Following these recommendations, provisions for

More information

CONSULTANCY SERVICES AGREEMENT

CONSULTANCY SERVICES AGREEMENT DATED 2010 [INSERT NAME OF CUSTOMER] (Customer) CAVALLINO HOLDINGS PTY LIMITED ACN 136 816 656 ATF THE DAYTONA DISCRETIONARY TRUST T/A INSIGHT ACUMEN (Consultant) CONSULTANCY SERVICES AGREEMENT Suite 5,

More information

Enforceability of take-or-pay provisions in English law contracts resolved

Enforceability of take-or-pay provisions in English law contracts resolved Journal of Energy & Natural Resources Law, 2016 http://dx.doi.org/10.1080/02646811.2016.1164554 Enforceability of take-or-pay provisions in English law contracts resolved Ben Holland is a partner in the

More information

TREATY SERIES 1999 Nº 1. International Convention on Salvage

TREATY SERIES 1999 Nº 1. International Convention on Salvage TREATY SERIES 1999 Nº 1 International Convention on Salvage Done at London on 28 April 1989 Signed on behalf of Ireland on 26 June 1990 Ireland s Instrument of Ratification deposited with the Secretary-General

More information

SAMPLE NOTES FROM OUR LLB CORE GUIDE:

SAMPLE NOTES FROM OUR LLB CORE GUIDE: SAMPLE NOTES FROM OUR LLB CORE GUIDE: CONTRACT LAW PRIVITY CHAPTER LLB Answered is a comprehensive, first-class set of exam-focused study notes for the Undergraduate Law Degree. Please visit LLBanswered.com

More information

IN THE SUPREME COURT OF THE UNITED KINGDOM

IN THE SUPREME COURT OF THE UNITED KINGDOM IN THE SUPREME COURT OF THE UNITED KINGDOM 21 December 2010 Before Registered at the Court of Justice under No. ~ 6b 5.21:. Lord Phillips Lord Rodger Lord Collins (1)JPMorgan Chase Bank, N.A. (2) J.P.Morgan

More information

HOW FAR CAN YOU ACT IN YOUR OWN SELF-INTEREST?

HOW FAR CAN YOU ACT IN YOUR OWN SELF-INTEREST? DISPUTE RESOLUTION This is the fourth in our series of contract disputes practical guides, designed to provide clients with practical guidance on some key issues that feature in disputes relating to commercial

More information

Martin Bowdery QC PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date: 1980, Silk: 2000 //

Martin Bowdery QC PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date: 1980, Silk: 2000 // CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE ENERGY, NATURAL RESOURCES AND UTILITIES INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS PROFESSIONAL NEGLIGENCE TRANSPORT GENERAL COMMERCIAL Martin Bowdery QC

More information

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000. Preamble This Arbitration Procedure has been prepared by Engineers Ireland principally for use with the Engineers Ireland Conditions of Contract for arbitrations conducted under the Arbitration Acts 1954

More information

LAWRENCE v NCL (BAHAMAS) LIMITED [2017] EWCA Civ 2222

LAWRENCE v NCL (BAHAMAS) LIMITED [2017] EWCA Civ 2222 LAWRENCE v NCL (BAHAMAS) LIMITED [2017] EWCA Civ 2222 Lord Justice Hamblen: Introduction 1. This is a renewed application for permission to appeal against a decision of the Admiralty Registrar, Jervis

More information

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan 184 SINGAPORE LAW REPORTS (REISSUE) [2004] 3 SLR(R) Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan [2004] SGHC 109 High Court Originating Motion No 31 of 2003 Judith Prakash

More information

Before : THE HON.MR.JUSTICE RAMSEY Between :

Before : THE HON.MR.JUSTICE RAMSEY Between : Neutral Citation Number: [2009] EWHC 2634 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-09-238 Royal Courts of Justice Strand, London, WC2A 2LL

More information

Topics this week. Part A Classification of Contract Terms. Part B Performance, Breach & Right of Termination

Topics this week. Part A Classification of Contract Terms. Part B Performance, Breach & Right of Termination Topics this week So far we have looked at contract formation and how terms are incorporated into the contract. We have also looked at how to interpret the meaning of contract terms and whether extrinsic

More information

UNIDROIT PRINCIPLES OF INTERNATIONAL COMMERCIAL CONTRACTS 2004 (I)

UNIDROIT PRINCIPLES OF INTERNATIONAL COMMERCIAL CONTRACTS 2004 (I) UNIDROIT PRINCIPLES OF INTERNATIONAL COMMERCIAL CONTRACTS 2004 (I) PREAMBLE (Purpose of the Principles) These Principles set forth general rules for international commercial contracts. They shall be applied

More information

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03 JUDGMENT : Master Haworth : Costs Court. 3 rd September 2008 1. This is an appeal pursuant to CPR Rule 47.20 from a decision of Costs Officer Martin in relation to a detailed assessment which took place

More information