1 Conditions Precedent to Recovery of Loss and Expense Claims Dated 07 January 2011 Author Robert Dalton (Head of Construction and Dispute Resolution NW for Blake Newport) Introduction There is a growing use of condition precedent clauses in contracts, which necessitate the serving of notices to an identified recipient of matters which might delay the works and/or give rise to additional cost. As set out below, where such provisions are properly drafted they are likely to be enforceable. A condition precedent clause requires an event or state of affairs before something else will occur. In a construction context it is generally a provision of the contract which requires the giving of a notice by the contractor, usually within a specified period of time, for any matter that may give rise to a claim for additional time or money. The intention of such provisions is that a failure to comply e.g. issue the required notice will have the effect that the contractor s rights in respect of that matter will be lost. For instance, clause 61.3 of NEC3 relates to the contractor s obligation to notify compensation events and states; if the Contractor does not notify a Compensation Event within 8 weeks of becoming aware of the event he is not entitled to a change in the Price, the Completion Date or a Key Date unless the Project Manager should have notified the event to the contractor but did not. Likewise, clause 28.1 of the 1999 FIDIC form of contract requires the contractor to give notice to the engineer of any event which may give rise to an extension of time or additional payment and states if the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment and the Employer shall be discharged from all liability in connection with the claim. While condition precedent clauses have not generally been a feature of other standard form of building contracts, it is increasingly common to amend these standard forms to introduce such provisions.

2 Relevant Case Law In Bremer v Vanden 1 the House of Lords stated that a notice provision was unlikely to be a condition precedent unless it prescribed a specific time for delivery of the notice and clearly stated that the rights would be lost in the event that notice was not given. The NEC and FIDIC clauses quoted above clearly accord with this dictum. In City Inn v Shepherd Construction 12 the Inner House of the Court in Session confirmed that a properly drafted condition precedent clause would be enforceable. Shepherd argued that the clause imposed a penalty upon them, because an extension of time to which they were otherwise entitled had not been granted, and delay damages deducted, merely because they had failed to give a notice, rather than as a consequence of any failure on their part to progress the works. The court rejected that argument commenting that the loss suffered by the employer was not converted into a penalty by the fact that the contractor might have avoided the liability by taking certain steps which the contract entitled it to take. Where a contractor s claim is rejected on the grounds that it has failed to serve appropriate notices, the contractor will often argue that the employer s position is contrary to the prevention principle. This principle is based upon the established common law rule that no person can take advantage of the non-fulfilment of a condition, the performance of which he has hindered. In Multiplex Construction v Honeywell Control Systems 3 the court noted that one consequence of the prevention principle is that the employer cannot hold the contractor to a specified completion date if the employer has by act or omission prevented the contractor from completing by that date. Instead time becomes at large and the obligation to complete by this specified date is replaced by an implied obligation to complete within a reasonable time. Whether the prevention principle will defeat a properly drafted condition precedent clause has been examined in a number of cases. The Australian case of Gaymark Investments v Walter Construction 4 is often cited as an example where the court held that the prevention principle presented a formidable barrier to an employer s claim for delay damages, where events which might have given rise to an entitlement to an extension of time were ignored as a consequence of the contractor s failure to issue timely notices. Such an approach has been questioned by the courts in the UK. For example, in the Multiplex case the Judge stated 1 Bremer v Handelgelsellschaft mbh v Vanden Avenne Izegem P.V.B.A [1978] 2 LLR City Inn v Shepherd Construction (2003) CILL Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) [2007] EWHC 447 (TCC) 4 Gaymark Investments Pty Ltd v Walter Construction Group [1999]

3 I have considerable doubt that Gaymark represents the law of England. Contractual terms requiring a contractor to give prompt notice of delay serve a valuable purpose. Such notice enables matters to be investigated while they are still current. Furthermore such notice sometimes gives the employer the opportunity to withdraw the instructions when the financial consequences become apparent. The court rejected the contractor s prevention principle defence on the basis that it was always open to the contractor to protect its interests by giving the relevant notices of delay. Since the Multiplex case, the courts have shown increasing favour towards conditions precedent as an instrument of practical contract administration, including the recent case of WW Gear Construction v McGee Group 5, which is considered in detail below. WW Gear Construction v McGee Group The Facts The contract in this case incorporated the JCT Trade Contract (TC/C) 2002 terms with Amendment No 1:2003, albeit as detailed below this was further amended by the parties. WW Gear Construction ("the Employer") wished to develop a site on the south side of Westminster Bridge, London. The development was to include the construction of the Westminster Park Plaza Hotel. McGee Group ("the Contractor") is a groundworks contractor which was retained by the Employer in August 2007 to carry out excavation and other groundworks for this development. The agreed Contract Sum was 1,812, The Construction Manager named in the Contract was GC Project Management. The Contractor had completed its work in about May Disputes subsequently arose between the parties in relation to payments including the Contractor's claims for loss and expense related to delay and disruption. The Contractor made applications for payment, broadly on a monthly basis. The applications included requests or claims for payment for extended preliminary costs associated, with delay either to individual elements of the works (for instance extended preliminaries for capping beam works) and to the works as a whole from about June For Application 18 which was said to summarise the position up to the end of March 2009, the Contractor referred in its summary to a "Loss & Expense Claim" being "As Attached". That claim, in the sum of 1,555,919.89, included for preliminaries which at least in part had previously formed the subject matter of monthly applications for payment; it included various other delay and disruption claims such as "Site Plant" as well as "Additional Head Office Direct Costs", "Additional Site Management Costs" and "Head Office Overheads & Loss of Profit". 5 WW Gear Construction Ltd v McGee Group Ltd [2010] EWHC 1460

4 The Employer referred to adjudication issues arising between the parties, including issues relating to the proper interpretation and application of extension of time and delay related loss and expense clauses in the contract. The Adjudicator decided in broad terms against the Employer on these issues. The Employer was not satisfied with this decision albeit it did not seek to challenge the enforceability as such of the decision. Consequently, it sought final declarations in court. The Contract The Contract incorporated the standard Trade Contract (TC/C), albeit amended by the various provisions set out at Part A20 of the Preliminaries and General Conditions. The relevant clauses were as follows (those parts in the body of the clauses which were the subject of the agreed amendments are underlined): Clause If and whenever it becomes reasonably apparent that the commencement, progress or completion of the Works or any part thereof is being or is likely to be delayed, the Trade Contractor shall forthwith give written notice to the Construction Manager and to the Employer of the material circumstances including, insofar as the Trade Contractor is able, the cause or causes of the delay and identify in such notice any event which in his opinion is a Relevant Event as described in clause 2.5. Any written notice given under this clause will be separate from other correspondence and delivered by facsimile and post. It will be headed "this is Delay Notice No " and will be numbered sequentially." It is unnecessary to set out verbatim the provisions of the other extension of time clauses, namely Clauses 2.2, 2.3, 2.4 and 2.5. They make provision for the Contractor to give particulars, if practicable, of the expected effects and extent of delay and for the Construction Manager upon receipt of any notice particulars and estimate of the expected delay to grant extension of time and revise the Completion Period in a fair and reasonable manner. In any event the Construction Manager is required after the expiration of the Completion Period and in any event not later than the expiry of 12 weeks after practical completion to grant fair and reasonable extensions having regard to any of the Relevant Events, irrespective of any notification. Clause 4.21 If the Trade Contractor makes written application to the Construction Manager stating that he has incurred or is likely to incur direct loss and/or expense (of which the Trade Contractor may give his quantification) in the execution of this Trade Contract because the regular

5 progress of the Works or any part thereof has been or is likely to be materially affected by any one or more of the matters referred to in clause 4.22; and if as soon as the Construction Manager is of the opinion that the regular progress of the Works or of any part thereof has been or is likely to be so materially affected as set out in the application of the Trade Contractor then the Construction Manager from time to time thereafter shall ascertain the amount of such loss and/or expense which has been or is being incurred by the Trade Contractor; provided always that:.1 the Trade Contractor's application shall be made as soon as and in any event not later than two months after it has become, or should reasonably have become, apparent to him that the regular progress of the Works or any part thereof has been or was likely to be affected as aforesaid, and such application shall be formally made in writing and fully documented and costed in detail, and it shall be a condition precedent to the Trade Contractor's entitlement under this clause or clause 4.25 that the Trade Contractor has complied fully with all the requirements of this clauses [sic] including, for the accordance [sic] of doubt, the said time period of two months..2 the Trade Contractor shall in support of his application submit to the Construction Manager upon request such information as should reasonably enable the Construction Manager to form an opinion as aforesaid;.3 the Trade Contractor shall submit to the Construction Manager upon request such details of such loss and/or expense as are reasonably necessary for such ascertainment..4 The Trade Contractor shall not be entitled to direct loss and/or expense to the extent that the loss or expense or other matters have been caused or contributed to by their Trade Contractor's negligence or the default." Clause 4.22 listed the matters which could give rise to a loss and expense claim under Clause 4.21; these included the late release of information, failure to give in due time ingress to or egress from the site, Variation instructions and "any impediment, prevention or default, whether by act or omission, by the Client or any person for whom the Client is responsible". Clause 4.25 Save as otherwise provide [sic] in this Clause 4 the provisions of clauses 4.21 and 4.23 are without prejudice to any other remedies or rights of the Trade Contractor under this Trade Contract.

6 The Parties Submissions The Employer sought a final determination from the court as to the true meaning and effect of clause The Employer took issue with the Adjudicator s decision that the condition precedent was devoid of meaning, and argued that clause 4.21 required the Contractor to make a timely and detailed application for loss and expense as a condition precedent to entitlement to such a claim. The Contractor argued that conditions precedents were to be construed strictly and that the words in clause 4.21 should not be construed as barring the Contractor from a legitimate claim for loss and expense if its application were not made within the stipulated two month period. Much of the remaining argument, between the parties, centred on whether the words Trade Contractor s entitlement under this clause were meaningless because there was no entitlement under that sub-sub-clause. The Relevant Principles The court noted the following principles as set out in Chartbrook v Persimmon Homes 6 : a contract should be interpreted by reference to what a reasonable person having all the relevant background knowledge would have understood the words to mean; the court did not readily accept that contractual parties have made a mistake in their written contracts; if something had gone wrong with the language, the court would not attribute to the parties an intention which a reasonable person would not have understood the words to mean; a strong case was needed to persuade a court that something had gone wrong with the language. Once it was clear that something had gone wrong with the language, the court would seek as a matter of construction and interpretation to determine what the parties really meant. In so doing, the court would have regard to the background and context of the contract to see what was intended from the wording of the contract. If it was not possible to determine what was mutually intended from the wording, the background and the context then the court might have to conclude that the parties had produced a meaningless term or contract. 6 Chartbrook Ltd -v- Persimmon Homes Ltd and Another ChD [2007] EWHC 409

7 There was no direct authority on this particular JCT form of contract, but the form of wording was similar and comparable to that used in the earlier editions of the JCT contracts. The court noted the dictum in Merton v Stanley Hugh Leach 7 where clause 24 (1) of the 1963 edition of the JCT contract (the pre-curser to clause 4.21) was held to be an if" clause. By this the judge meant that the provisions of the clause only operated if the contractor invoked them first by making a written application. If the application was made, the architect then had to form an opinion whether loss and/or expense was suffered, if the written application was made within a reasonable time. The Court s Analysis and Decision Applying those principles, the court analysed clause 4.21 to show that it was an if clause similar to that referred by in the Merton case. As a result the court held that: the requirement to make a timely application in writing was a precondition to the recovery of loss and/or expense under clause 4.21; the Contractor had no entitlement to recover such loss and/or expense unless and until it had made such an application because it was the application which activated the assessment process; the parties had agreed through the stipulation in clause , as amended, that the application must be made in a timely manner and in any event no more than two months after it has become or should reasonably have become apparent that the regular progress of the works had been or was likely to be affected; the proper construction of clause 4.21 was that it was a condition precedent to the Contractor's entitlement to recover loss and/or expense. In scrutinising clause 4.21, the court separated the essential elements of the clause as follows: (a) If the Trade Contractor makes written application to the Construction Manager stating that he has incurred or is likely to incur direct loss and/or expense The operation of clause 4.21 was brought about by the Contractor s written application. There was nothing in clause 4.21 which suggested that the Construction Manager or the Employer had any obligation to ascertain loss and expense if there was no application. (b) because the regular progress of the Works has been or is likely to be materially affected 7 London Borough of Merton v Stanley Hugh Leach (1985) 32 BLR 51

8 This made it clear that the application should state in effect that the regular progress was or was likely to be affected by the various matters listed as entitling additional loss and expense. (c) provided always that Use of this wording was often the most obvious indication that the parties intended there to be a condition precedent which was followed by a qualification and explanation of what was required to enable the preceding entitlement to materialise. (d).1 the Trade Contractor's application shall be made as soon as and in any event not later than two months after it has become, or should reasonably have become, apparent to him that the regular progress of the Works has been or was likely to be affected There was nothing particularly onerous on the Contractor to make its application within either the general or specific timetables. The application had to be made within the long stop period of two months after it had become or should reasonably have become apparent that the regular progress of the works was or was likely to be affected. (e) and it shall be a condition precedent to the Trade Contractor's entitlement under this clause that the Trade Contractor has complied fully with all the requirements of this clauses [sic] including, for the accordance [sic] of doubt, the said time period of two months The erroneous references to clause in this part of the sub-clause suggested a lack of attention in the drafting because there was no specific entitlement under clause Essentially, the words in this sub-clause were superfluous because the drafting of the earlier parts of clause 4.21 and was sufficient to establish that the submission of a timely application was a condition precedent to entitlement. Following the dictum in the Chartbrook case, what the parties clearly intended was to refer to that part of the overall clause which actually gave rise to an entitlement which was clause The whole context of clause itself is clause 4.21 and it was obvious that the parties were intending to refer to clause The court was clear in this case how the relevant clauses were intended to operate and was prepared to correct the mistake made in the cross-referencing of clause 4.21 and

9 The judge decided that it was the Contractor s application which triggered the ascertainment process and the fact that there was an obvious mistake in the drafting of one of the subclauses to clause 4.21 did not undermine the clear intent of the clause. It followed that upon a proper construction of clause 4.21, and its sub-clauses, there is a condition precedent to the Contractor s entitlement to recover loss and/or expense. The court did not consider that the requirement for the Contractor to submit a timely application in this regard, no more than two months after either it became or should reasonably have become apparent to him, was unduly onerous in any event. Implications It is even clearer from the Gear case that when contractors are faced with properly drafted clauses of this type, they must be prudent and put in place sufficient commercial and contract management resources to ensure they do not fall foul of these provisions, irrespective of the merits of their case, for want of following the procedure. It is also worthy of note that the parties in this case had through amended clause 4.25 preserved the contractor s right to claim at common law for breach of contract, notwithstanding the validity of the condition precedent provision. The drafters of contracts shall therefore be aware that the right to recover at common law may still be available in the absence of any clear words to the contrary. As a concluding point, it is also worth noting that a failure to follow a condition precedent clause in a contract is not always fatal to the claim. There may be an equitable remedy in estoppel, waiver or variation.

Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Time and Money: Time Bar Clauses Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Introduction This paper focuses on time bar clauses, with a particular reference to clause 20.1

More information

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 TIME AND MONEY: TIME BAR CLAUSES Nicholas Gould 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007 Introduction This paper focuses on time bar clauses, with a particular reference to clause 20.1 of FIDIC.

More information

THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION

THE PREVENTION PRINCIPLE AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION -..". THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS CORDON SMITH Partner, Baker & McKenzie, Wong & Leow, Singapore INTRODUCTION The "prevention principle" operates

More information

NOTICES, TIME BARS AND PROPORTIONALITY

NOTICES, TIME BARS AND PROPORTIONALITY NOTICES, TIME BARS AND PROPORTIONALITY A talk by Sir Rupert Jackson to the Hong Kong Society of Construction Law on 21 st September 2018 CONTENTS 1. Introduction 2. Notice provisions 3. A conundrum 4.

More information

Martin Waldron BL FCIArb MSCSI MRICS

Martin Waldron BL FCIArb MSCSI MRICS Law Library Distillery Building 145-151 Church Street Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie CPD talk on CONDITIONS PRECEDENT In Irish Construction Contracts by Martin

More information

Martin Waldron BL FCIArb MSCSI MRICS

Martin Waldron BL FCIArb MSCSI MRICS MARTIN WALDRON BL FCIArb MSCSI MRICS Law Library Distillery Building 145-151 Church Street Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie Construction Bar Association Construction

More information

Time and Construction Contracts

Time and Construction Contracts Time and Construction Contracts Extensions of Time and the Prevention Principle By Nathan Abbott Introduction The purpose of this paper is to expose and consider the Prevention Principle from a practical

More information

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective for contracts dated from 1 st January 2006 Gafta No.125 Copyright THE GRAIN AND FEED TRADE ASSOCIATION ARBITRATION RULES GAFTA HOUSE 6 CHAPEL PLACE RIVINGTON STREET LONDON EC2A 3SH Tel: +44 20

More information

Commencement of Arbitration and Time-Bar Clauses

Commencement of Arbitration and Time-Bar Clauses Commencement of Arbitration and Time-Bar Clauses by ANDREW TWEEDDALE and KAREN TWEEDDALE 1. INTRODUCTION This article considers how English courts construe time-bar clauses and whether there is an advantage

More information

CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE

CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE 1. GENERAL In these conditions the company means Carbon Link Ltd, trading as CPL Activated Carbons and the customer means the person or company

More information

Arbitration Rules No.125

Arbitration Rules No.125 Effective for Contracts dated from 1 st September 2016 Arbitration Rules No.125 Copyright Printed in England and issued by Gafta THE GRAIN AND FEED TRADE ASSOCIATION 9 LINCOLN S INN FIELDS, LONDON WC2A

More information

Reinforcing Security of Payment in NSW

Reinforcing Security of Payment in NSW Philip Davenport 2011 Despite set backs in the Supreme Court, the NSW Government is firmly behind security of payment and has now strengthened security of payment for subcontractors by giving them the

More information

DATED [ ] 201[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FIRM FREQUENCY RESPONSE AGREEMENT

DATED [ ] 201[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FIRM FREQUENCY RESPONSE AGREEMENT DATED [ ] 201[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FIRM FREQUENCY RESPONSE AGREEMENT (NON-BALANCING MECHANISM PARTICIPANT (DYNAMIC)) RELATING TO SITE(S) AT [ ][TENDER RULES AND

More information

PART 8 ARBITRATION REGULATIONS CONTENTS

PART 8 ARBITRATION REGULATIONS CONTENTS PART 8 ARBITRATION REGULATIONS * CONTENTS Section Page 1 Definitions and Interpretations 8-1 2 Commencement 8-2 3 Appointment of Tribunal 8-3 4 Procedure 8-5 5 Notices and Communications 8-5 6 Submission

More information

Page 1 of 6 DISCOVER THOMSON REUTERS CONTACT & SUPPORT PRACTICAL LAW CONSTRUCTION BLOG Since then, the sub-contractor has been refused permission to appeal, and the litigation has now been settled. Despite

More information

Legal Awareness In The Construction Industry

Legal Awareness In The Construction Industry Legal Awareness In The Construction Industry LET S TALK ABOUT PAM 2006 AGAIN 12 March 2014 Sr Peter Moh Mee Ying B.Sc. (Hon) HBP, MBA, FRISM, ICECA, MRICS, Registered QS INTRODUCTION This paper is prepared

More information

THE LAW SOCIETY CONVEYANCING ARBITRATION RULES

THE LAW SOCIETY CONVEYANCING ARBITRATION RULES THE LAW SOCIETY CONVEYANCING ARBITRATION RULES (For disputes arising under the Contract for Sale of Land 2005 Edition) Preamble The Council of the Law Society of New South Wales resolved at a meeting on

More information

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23 JUDGMENT : HHJ Anthony Thornton QC. TCC. 23 rd May 2007 1. Introduction 1. The claimant, Mott MacDonald Ltd ( MM ) is a specialist engineering multi-disciplinary consultancy providing services to the construction

More information

LIMITATION OF ACTIONS ACT

LIMITATION OF ACTIONS ACT LAWS OF KENYA LIMITATION OF ACTIONS ACT CHAPTER 22 Revised Edition 2012 [2010] Published by the National Council for Law Reporting with the Authority of the Attorney-General www.kenyalaw.org [Rev. 2012]

More information

ATM ACCESS AUSTRALIA LIMITED ATM ACCESS CODE

ATM ACCESS AUSTRALIA LIMITED ATM ACCESS CODE Effective 1 January 2011 Version 003 ATM ACCESS AUSTRALIA LIMITED ABN 52 130 571 103 A Company limited by Guarantee ATM ACCESS CODE Commencement Date: 3 March 2009 Copyright 2009 ATM Access Australia Limited

More information

AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN:

AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN: AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN: LUX RESIDENTIAL WARRANTY PROGRAM INC., a federally incorporated corporation doing business in Atlantic Canada AND BUILDER COMPANY NAME: ADDRESS: POSTAL

More information

THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION CHESTER-LE-STREET GC TRADING LIMITED. (Company)

THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION CHESTER-LE-STREET GC TRADING LIMITED. (Company) THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION OF CHESTER-LE-STREET GC TRADING LIMITED (Company) 1. INTERPRETATION 1.1 In these Articles, unless the context otherwise

More information

THE ELECTRICITY ARBITRATION ASSOCIATION

THE ELECTRICITY ARBITRATION ASSOCIATION The Rules of this Association were amended with effect from the 1 st January, 1993 in the manner herein set out. This is to allow for the reference to the Association, in accordance with its Rules, of

More information

THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION NEWCASTLE CRICKET CLUB (COMMUNITY) LIMITED.

THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION NEWCASTLE CRICKET CLUB (COMMUNITY) LIMITED. THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION OF NEWCASTLE CRICKET CLUB (COMMUNITY) LIMITED (Company) 1. INTERPRETATION 1.1 In these Articles, unless the context otherwise

More information

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY 2011 Introductory Provisions Article (1) Definitions 1.1 The following words and phrases shall have the meaning assigned thereto unless

More information

AGREEMENT WITH BUILDER. NAME or COMPANY NAME: ADDRESS:

AGREEMENT WITH BUILDER. NAME or COMPANY NAME: ADDRESS: Rev. 04/15 AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN: ATLANTIC HOME WARRANTY ( AHW ), a body corporate, carrying on business in the Atlantic Provinces and NAME or COMPANY NAME: ADDRESS: POSTAL

More information

Mutual Indemnity and Hold Harmless Deed

Mutual Indemnity and Hold Harmless Deed Mutual Indemnity and Hold Harmless Deed THIS DEED is made the...day of... 20... WHEREAS A. Each of the Signatories may perform Services. B. The Signatories wish to enter into this Deed to create between

More information

Agreement to UOB Banker s Guarantee Terms and Conditions

Agreement to UOB Banker s Guarantee Terms and Conditions Agreement to UOB Banker s Guarantee Terms and Conditions In consideration of United Overseas Bank Limited (the Bank ) agreeing at the Applicant s request to issue the Banker s Guarantee, the Applicant

More information

NHS conditions of contract for the sale of scrap March 2007

NHS conditions of contract for the sale of scrap March 2007 NHS conditions of contract for the sale of scrap March 2007 1 Page Interpretation 3 Variation of conditions 3 Specification 3 Samples 4 Disclaimer 4 Property and risk 5 Payment 5 Removal 5 Recovery of

More information

BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011

BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011 BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011 This is a revised edition of the Substantive Laws, prepared by the Law

More information

SRA Compensation Fund Rules 2011

SRA Compensation Fund Rules 2011 SRA Compensation Fund Rules 2011 Rules dated 17 June 2011 made by the Solicitors Regulation Authority Board, subject to the coming into force of relevant provisions of an Order made under section 69 of

More information

c t MECHANICS LIEN ACT

c t MECHANICS LIEN ACT c t MECHANICS LIEN ACT PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to January 1, 2009. It is intended for information and reference

More information

DATED 20 HSBC BANK PLC. and [FUNDER] and [COMPANY] DEED OF PRIORITY

DATED 20 HSBC BANK PLC. and [FUNDER] and [COMPANY] DEED OF PRIORITY Funder Priority specified assets. DATED 20 HSBC BANK PLC and [FUNDER] and [COMPANY] DEED OF PRIORITY CONTENTS PAGE 1 DEFINITIONS AND INTERPRETATION... 1 2 CONSENTS... 2 3 PRIORITIES... 2 4 CONTINUING SECURITY...

More information

Employment (Co-Determination in the Workplace) Act (1976:580)

Employment (Co-Determination in the Workplace) Act (1976:580) Employment (Co-Determination in the Workplace) Act (1976:580) Amendments: up to and including SFS 2013:615 Introductory Provisions Section 1 This Act shall apply to the relationship between employer and

More information

Standard terms and conditions

Standard terms and conditions müller quadax gmbh Teslastraße 6 74670 Forchtenberg Germany Tel. +49 7947 828-20 Fax +49 7947 828-14 Email info@quadax.de Website www.quadax.de Section 1 General / scope of application (1) These standard

More information

FIDIC Conditions of Contract for Construction

FIDIC Conditions of Contract for Construction FIDIC Conditions of Contract for Construction 1 1 General Provisions 2 1 1.1 Definitions 1.1.1 The Contract Contract means the Contract Agreement, the Letter of Acceptance, the Letter of Tender, these

More information

PAM NORTHERN CHAPTER

PAM NORTHERN CHAPTER PAM NORTHERN CHAPTER SATURDAY, 27 FEBRUARY 2016 DELAY AND DISRUPTION IN CONSTRUCTION CONTRACTS BY LIM HOCK SIANG MESSRS PRESGRAVE & MATTHEWS STANDARD CHARTERED BANK CHAMBERS, 2 LEBUH PANTAI, 10300 PENANG,

More information

Construction Industry Payment and Adjudication 1. construction industry payment and adjudication act 2012

Construction Industry Payment and Adjudication 1. construction industry payment and adjudication act 2012 Construction Industry Payment and Adjudication 1 laws OF MALAYSIA construction industry payment and adjudication act 2012 2 Laws of Malaysia Date of Royal Assent...... 18 June 2012 Date of publication

More information

Clause 3 deals with the duties and obligations of the Engineer and his assistants.

Clause 3 deals with the duties and obligations of the Engineer and his assistants. Clause 3 Summary Clause 3 deals with the duties and obligations of the Engineer and his assistants. Sub-Clause 3.1 deals with the role and duties of the Engineer. The Engineer is deemed to act for the

More information

Construction Newsletter Issue No. 20

Construction Newsletter Issue No. 20 Construction Newsletter Issue No. 20 www.4pumpcourt.com Construction Causation Global Claims Extensions of Time Loss and Expense Walter Lilly v Giles Patrick Mackay [2012] EWHC 1773 (TCC) Mr Justice Akenhead

More information

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000. Preamble This Arbitration Procedure has been prepared by Engineers Ireland principally for use with the Engineers Ireland Conditions of Contract for arbitrations conducted under the Arbitration Acts 1954

More information

CHAPTER 107 CONTRIBUTORY NEGLIGENCE AND JOINT WRONGDOERS

CHAPTER 107 CONTRIBUTORY NEGLIGENCE AND JOINT WRONGDOERS Cap.107] CONTRIBUTORY NEGLIGENCE AND JOINT WRONGDOERS CHAPTER 107 CONTRIBUTORY NEGLIGENCE AND JOINT WRONGDOERS Act No. 12 of 1968. AN ACT TO AMEND THE LAW RELATING TO CONTRIBUTORY NEGLIGENCE AND JOINT

More information

ALIENATION OF LAND ACT NO. 68 OF 1981

ALIENATION OF LAND ACT NO. 68 OF 1981 ALIENATION OF LAND ACT NO. 68 OF 1981 [View Regulation] [ASSENTED TO 28 AUGUST, 1981] DATE OF COMMENCEMENT: 19 OCTOBER, 1982] (except s. 26 on 6 December, 1983) (English text signed by the State President)

More information

1 terms & conditions STAL5/6 AEF.AS

1 terms & conditions STAL5/6 AEF.AS 'Literature' means catalogues, pamphlets, price lists and advertising literature provided by us and includes materials on our website. CRYOGENETICS LTD TERMS AND CONDITIONS FOR EQUINE SEMEN STORAGE AND

More information

Possible Legal Issues of Unilaterally Contract Termination for Convenience

Possible Legal Issues of Unilaterally Contract Termination for Convenience Possible Legal Issues of Unilaterally Contract Termination for Convenience Seng Hansen Master Student of Construction Contract Management UTM Email: Hansen_zinck@yahoo.co.id Introduction The Malaysian

More information

TERMS AND CONDITIONS OF SALES

TERMS AND CONDITIONS OF SALES 1. Acceptance No Contract, Order or information (literature, drawings etc.) provided to or by the Purchaser shall be binding on Infra Green Ltd unless confirmed in the Infra Green Ltd Order Confirmation.

More information

Independent Arbitration Scheme for the Chartered Institute of Management Accountants (CIMA)

Independent Arbitration Scheme for the Chartered Institute of Management Accountants (CIMA) Independent Arbitration Scheme for the Chartered Institute of Management Accountants (CIMA) 2007 Edition 1 Introduction 1.1 The Independent Arbitration Scheme for the Chartered Institute of Management

More information

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS These Trading Terms and Conditions are to be read and understood prior to the execution of the Application for Commercial Credit Account.

More information

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22 JUDGMENT : Mr Justice Ramsey : TCC. 22 nd May 2007 Introduction 1. This is an application for leave to appeal under s.69(3) of the Arbitration Act 1996. The arbitration concerns the appointment of the

More information

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY Report of the DTI s post-consultation event held in London on 14th February 2006 On Valentine s Day 2006, the Right Honourable Alun Michael MP compared

More information

/...1 PRIVATE ARBITRATION KIT

/...1 PRIVATE ARBITRATION KIT 1007453/...1 PRIVATE ARBITRATION KIT Introduction This document contains Guidelines, Rules and a Model Agreement in respect of private arbitrations. It is designed to assist practitioners when referring

More information

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because:

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because: United Kingdom Letters of intent and contract formation RTS Flexible Systems Limited (Respondents) v Molkerei Alois Muller Gmbh & Company KG (UK Production) (Appellants) [2010] UKSC 14C Chris Hill and

More information

Terms of Trade. For the provision of Security Systems Installation and Services By MB Security Ltd

Terms of Trade. For the provision of Security Systems Installation and Services By MB Security Ltd Terms of Trade For the provision of Security Systems Installation and Services By MB Security Ltd Cavell Leitch Page 1 of 4 1. INTRODUCTION All goods and services supplied by the Contractor to the Customer

More information

STANDARD MASTER SERVICES AGREEMENT

STANDARD MASTER SERVICES AGREEMENT STANDARD MASTER SERVICES AGREEMENT HUGE CONNECT (PTY) LIMITED and herein referred to as Huge Connect 1 INTERPRETATION 1.1 In this Agreement the following expressions shall have the following meanings respectively:

More information

Freight Investor Solutions DMCC Terms of Business

Freight Investor Solutions DMCC Terms of Business Freight Investor Solutions DMCC Terms of Business 1. COMMENCEMENT 1.1 The term Agreement hereunder shall mean collectively these Terms of Business ( Terms ), and Freight Investor Solutions DMCC Order Execution

More information

Review of the Western Australian Construction Contracts Act 2004

Review of the Western Australian Construction Contracts Act 2004 Review of the Western Australian Construction Contracts Act 2004 Submission to the Building Commission Civil Contractors Federation (WA Branch) Submission to the Australian Government by the Civil Contractors

More information

THE LONDON MARITIME ARBITRATORS ASSOCIATION THE INTERMEDIATE CLAIMS PROCEDURE (2012)

THE LONDON MARITIME ARBITRATORS ASSOCIATION THE INTERMEDIATE CLAIMS PROCEDURE (2012) THE LONDON MARITIME ARBITRATORS ASSOCIATION THE INTERMEDIATE CLAIMS PROCEDURE (2012) Effective for appointments on or after 1 January 2012 1 THE LMAA INTERMEDIATE CLAIMS PROCEDURE 2012 (as developed in

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) 1. Scope of Application and Interpretation 1.1 Where parties have agreed to refer their disputes

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS CONTENTS Rule 1 Scope of Application and Interpretation 1 Rule 2 Notice, Calculation of Periods of Time 3 Rule 3 Notice of Arbitration 4 Rule 4 Response to Notice of Arbitration 6 Rule 5 Expedited Procedure

More information

(27 November 1998 to date) ALIENATION OF LAND ACT 68 OF 1981

(27 November 1998 to date) ALIENATION OF LAND ACT 68 OF 1981 (27 November 1998 to date) [This is the current version and applies as from 27 November 1998, i.e. the date of commencement of the Alienation of Land Amendment Act 103 of 1998 to date] ALIENATION OF LAND

More information

B I L L. No. 108 An Act respecting the Athletics Commission and Professional Contests or Exhibitions TABLE OF CONTENTS ATHLETICS COMMISSION 1

B I L L. No. 108 An Act respecting the Athletics Commission and Professional Contests or Exhibitions TABLE OF CONTENTS ATHLETICS COMMISSION 1 1 B I L L No. 108 An Act respecting the Athletics Commission and Professional Contests or Exhibitions TABLE OF CONTENTS PART I Preliminary Matters 1 Short title 2 Interpretation PART II Commission 3 Commission

More information

HINDUSTAN AERONAUTICS LIMITED IMM DEPARTMENT GENERAL TERMS & CONDITIONS OF CONTRACT

HINDUSTAN AERONAUTICS LIMITED IMM DEPARTMENT GENERAL TERMS & CONDITIONS OF CONTRACT QUALITY & WKMANSHIP HINDUSTAN AERONAUTICS LIMITED IMM DEPARTMENT GENERAL TERMS & CONDITIONS OF CONTRACT 1. Generally the stores shall be of the best quality and workmanship. Contractor shall comply with

More information

General Conditions of CERN Contracts

General Conditions of CERN Contracts ORGANISATION CERN/FC/5312-II/Rev. EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH General Conditions of CERN Contracts CERN/FC/6211/II- Original: English/French 14

More information

MCPS MEMBERSHIP AGREEMENT (MA2) AND ANNEXES

MCPS MEMBERSHIP AGREEMENT (MA2) AND ANNEXES MCPS MEMBERSHIP AGREEMENT (MA2) AND ANNEXES 1. APPOINTMENT OF MCPS 1.1 The Member hereby appoints MCPS to act as the Member s sole and exclusive agent in the Territory to manage and administer the Rights

More information

TERMS OF REFERENCE. Issued Date: 3 January 2011

TERMS OF REFERENCE. Issued Date: 3 January 2011 TERMS OF REFERENCE Issued Date: 3 January 2011 Last Revised Date: 21 March 2017 List of Revisions Revision No. Revision Date Effective Date Revision 1 23 November 2015 1 December 2015 Revision 2 21 March

More information

CONSULTANCY SERVICES AGREEMENT

CONSULTANCY SERVICES AGREEMENT DATED 2010 [INSERT NAME OF CUSTOMER] (Customer) CAVALLINO HOLDINGS PTY LIMITED ACN 136 816 656 ATF THE DAYTONA DISCRETIONARY TRUST T/A INSIGHT ACUMEN (Consultant) CONSULTANCY SERVICES AGREEMENT Suite 5,

More information

THE INTER-STATE MIGRANT WORKMEN (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) ACT, (No. 30 of 1979)

THE INTER-STATE MIGRANT WORKMEN (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) ACT, (No. 30 of 1979) THE INTER-STATE MIGRANT WORKMEN (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) ACT, 1979 (No. 30 of 1979) [11 th June, 1979] An Act to regulate the employment of inter-state migrant workmen and to

More information

FOUNDATIONS LAW CONTENTS

FOUNDATIONS LAW CONTENTS DIFC LAW NO. 3 OF 2018 CONTENTS PART 1: GENERAL... 1 1. Title... 1 2. Legislative authority... 1 3. Application of the Law... 1 4. Scope of the Law... 1 5. Date of enactment... 1 6. Commencement... 1 7.

More information

BASF Tanzania Limited Standard Terms and Conditions of Sale

BASF Tanzania Limited Standard Terms and Conditions of Sale 1. SCOPE OF APPLICATION All current and future supplies of products and services (including any literature or other information) offered by BASF to the Customer (collectively referred to as the Goods )

More information

STANDARD TRADING TERMS for the SUPPLY OF GOODS OR SERVICES to SAFCOR FREIGHT (PTY) LTD trading as BIDVEST PANALPINA LOGISTICS

STANDARD TRADING TERMS for the SUPPLY OF GOODS OR SERVICES to SAFCOR FREIGHT (PTY) LTD trading as BIDVEST PANALPINA LOGISTICS STANDARD TRADING TERMS for the SUPPLY OF GOODS OR SERVICES to SAFCOR FREIGHT (PTY) LTD trading as BIDVEST PANALPINA LOGISTICS 1. Definitions In these Conditions the words set out hereunder shall have the

More information

Access Agreement. Queensland Rail Limited. [Insert name of Operator] [Insert name of Access Holder]

Access Agreement. Queensland Rail Limited. [Insert name of Operator] [Insert name of Access Holder] Queensland Rail Limited [Insert name of Operator] [Insert name of Access Holder] Access Agreement [Note: This agreement is a standard access agreement and is based on the following assumptions, that: the

More information

JUDGMENT THE HIGH COURT OF SOUTH AFRICA GAUTENG LOCAL DIVISION, JOHANNESBURG CASE NO: 07897/2016. In the matter between: SAPOR RENTALS (PTY) LIMITED

JUDGMENT THE HIGH COURT OF SOUTH AFRICA GAUTENG LOCAL DIVISION, JOHANNESBURG CASE NO: 07897/2016. In the matter between: SAPOR RENTALS (PTY) LIMITED THE HIGH COURT OF SOUTH AFRICA GAUTENG LOCAL DIVISION, JOHANNESBURG CASE NO: 07897/2016 (1) REPORTABLE: NO (2) OF INTEREST TO OTHER JUDGES: NO (3) REVISED. 23 February 2017.. DATE... SIGNATURE In the matter

More information

Working in Partnership

Working in Partnership Terms and Conditions 1. Definitions 1.1 In these conditions (Unless the context otherwise requires): The Act means the Telecommunications Act 2003 and any amendments, modifications, re-enactments of the

More information

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:-

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:- Clause 10 Summary Clause 10 deals with the Taking-Over of the Works, Sections, or parts of the Works. Sub-Clause 10.1 deals with the Taking-Over of the Works and Sections. Taking-Over by the Employer happens

More information

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 //

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 // CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE PROFESSIONAL NEGLIGENCE ENERGY INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS Edmund Neuberger Call Date 2008 // eneuberger@atkinchambers.com PRACTICE Edmund

More information

including existing and future fixtures, fittings, alterations and additions.

including existing and future fixtures, fittings, alterations and additions. Version 2.3 Account No: Date: In this document: we, us and our means Fleet Mortgages Limited of 2 nd Floor, Flagship House, Reading Road North, Fleet, Hampshire, GU51 4WP (registered in England and Wales

More information

STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES

STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES JAMS STREAMLINED ARBITRATION RULES & PROCEDURES Effective JULY 15, 2009 STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES JAMS provides arbitration and mediation services from Resolution Centers

More information

7:12 PREVIOUS CHAPTER

7:12 PREVIOUS CHAPTER TITLE 7 Chapter 7:12 TITLE 7 PREVIOUS CHAPTER SMALL CLAIMS COURTS ACT Acts 20/1992, 8/1996, 22/2001, 14/2002; S.I. s 134/1996, 136/1996, 158/2000 ARRANGEMENT OF SECTIONS PART I PRELIMINARY Section 1. Short

More information

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation.

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation. Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation. English law does not require a particular form to contracts, therefore the terms and ultimately

More information

1.2. This book covers the three Agreements published by JBCC (see 2.1 below) and the MBSA 2014 Domestic Subcontract Agreement.

1.2. This book covers the three Agreements published by JBCC (see 2.1 below) and the MBSA 2014 Domestic Subcontract Agreement. JBCC March 2014 AGREEMENTS 1 2 3 4 5 6 7 Text books available concerning JBCC 2014 General - Contract Documents issued by JBCC Synopsis of important changes JBCC PBA 2007 2014 Contract Data Tender process

More information

CHAPTER 9 INVESTMENT. Section A

CHAPTER 9 INVESTMENT. Section A CHAPTER 9 INVESTMENT Section A Article 9.1: Definitions For the purposes of this Chapter: Centre means the International Centre for Settlement of Investment Disputes (ICSID) established by the ICSID Convention;

More information

THE REPUBLIC OF UGANDA UGANDA COFFEE TRADE FEDERATION ARBITRATION RULES

THE REPUBLIC OF UGANDA UGANDA COFFEE TRADE FEDERATION ARBITRATION RULES THE REPUBLIC OF UGANDA UGANDA COFFEE TRADE FEDERATION ARBITRATION RULES Adopted by Resolution of the Members of the Uganda Coffee Trade Federation (UCTF) Limited at the 2 nd Annual General Meeting Held

More information

SCHEDULE 10 LENDERS REMEDIES AGREEMENT

SCHEDULE 10 LENDERS REMEDIES AGREEMENT SCHEDULE 10 LENDERS REMEDIES AGREEMENT for the Saskatchewan Joint-Use Schools Project # 2 HER MAJESTY THE QUEEN IN RIGHT OF THE PROVINCE OF SASKATCHEWAN COMPUTERSHARE TRUST COMPANY OF CANADA, AS INDENTURE

More information

557. Hearing of proceedings otherwise than in public Power of court to order the return of assets which have been improperly transferred.

557. Hearing of proceedings otherwise than in public Power of court to order the return of assets which have been improperly transferred. 557. Hearing of proceedings otherwise than in public. 558. Power of court to order the return of assets which have been improperly transferred. 559. Reporting to Director of Corporate Enforcement of misconduct

More information

Cambridge Assessment Admissions Testing Centre Agreement

Cambridge Assessment Admissions Testing Centre Agreement Cambridge Assessment Admissions Testing Centre Agreement This Cambridge Assessment Admissions Testing ( Admissions Testing ) Centre Agreement ( the Agreement ) is made between: (1) The Chancellor, Masters

More information

WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES

WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES APPENDIX 3.17 WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES (as from 1 October 2002) I. GENERAL PROVISIONS Abbreviated Expressions Article 1 In these Rules: Arbitration Agreement means

More information

Dated [ ] NORFOLK COUNTY COUNCIL AND [ ] MEMBERS ACCESS AGREEMENT RE LGPS FRAMEWORK ARRANGEMENTS

Dated [ ] NORFOLK COUNTY COUNCIL AND [ ] MEMBERS ACCESS AGREEMENT RE LGPS FRAMEWORK ARRANGEMENTS Dated [ ] NORFOLK COUNTY COUNCIL AND [ ] MEMBERS ACCESS AGREEMENT RE LGPS FRAMEWORK ARRANGEMENTS nplaw/[ ] 1 THIS AGREEMENT is made the day of [ ] BETWEEN NORFOLK COUNTY COUNCIL of County Hall, Martineau

More information

Rules of the High Court (Family Proceedings) 2009 PART 2 ORDERS WITH RESPECT TO CHILDREN

Rules of the High Court (Family Proceedings) 2009 PART 2 ORDERS WITH RESPECT TO CHILDREN 6. Application of Part 2 PART 2 ORDERS WITH RESPECT TO CHILDREN This Part applies to family proceedings in the Court so far as they relate to any matter under Part 1 or 2 of the 2001 Act with respect to

More information

Labour Court Rules, 2006 ARRANGEMENT OF RULES PART I

Labour Court Rules, 2006 ARRANGEMENT OF RULES PART I DISTRIBUTED BY VERITAS TRUST Tel: [263] [4] 794478 Fax & Messages [263] [4] 793592 E-mail: veritas@mango.zw VERITAS MAKES EVERY EFFORT TO ENSURE THE PROVISION OF RELIABLE INFORMATION, BUT CANNOT TAKE LEGAL

More information

Arbitration Act B.E. 2545

Arbitration Act B.E. 2545 1 (Translation) Arbitration Act B.E. 2545 BHUMIBOL ADULYADEJ, REX., Given on the 23 rd day of April B.E. 2545 (2002) Being the 57 th Year of the Present Reign. His Majesty King Bhumibol Adulyadej is graciously

More information

TERMS OF TRADING AGREEMENT

TERMS OF TRADING AGREEMENT Incorporating KAILIS BROS Pty Ltd (ACN 008 723 000), NATIONAL FISHERIES Pty Ltd (ACN 009 412 382), TRILOR Pty Ltd (ACN 008 877 290) and CENVILL PTY LTD (ACN 009 013 843). Operating Address: 23 CATALANO

More information

General Terms and Conditions of Sale and Delivery of ERC Emissions-Reduzierungs-Concepte GmbH ( ERC )

General Terms and Conditions of Sale and Delivery of ERC Emissions-Reduzierungs-Concepte GmbH ( ERC ) 1. General General Terms and Conditions of Sale and Delivery of 1.1 The following Terms and Conditions shall exclusively apply to all business transactions with the Purchaser. They apply to business transactions

More information

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - Background I practice in the building and construction industry as a mediator and conciliator, assisting contracted parties in

More information

Elements of a Civil Claim

Elements of a Civil Claim Elements of a Civil Claim This presentation provides an overview of the elements of a civil claim, with particular reference to construction claims, and looks at each dispute resolution option in the context

More information

LIENS (770 ILCS 60/) Mechanics Lien Act.

LIENS (770 ILCS 60/) Mechanics Lien Act. LIENS (770 ILCS 60/) Mechanics Lien Act. (770 ILCS 60/0.01) (from Ch. 82, par. 0.01) Sec. 0.01. Short title. This Act may be cited as the Mechanics Lien Act. (Source: P.A. 86-1324.) (770 ILCS 60/1) (from

More information

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998 FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998 IN exercise of the powers conferred upon me by Section 25 of the High Court Act, I hereby make the following Rules: Citation 1.

More information

A Summary of Construction Cases in 2012

A Summary of Construction Cases in 2012 A Summary of Construction Cases in 2012 Formation of Contract Specialist Insulation Limited v Pro-Duct (Fife) Limited Each party proceeds on the basis that their standard form of contract regulates the

More information

ARBITRATORS AND MEDIATORS INSTITUTE OF NEW ZEALAND INC ( AMINZ ) AMINZ ARBITRATION APPEAL RULES

ARBITRATORS AND MEDIATORS INSTITUTE OF NEW ZEALAND INC ( AMINZ ) AMINZ ARBITRATION APPEAL RULES ARBITRATORS AND MEDIATORS INSTITUTE OF NEW ZEALAND INC ( AMINZ ) AMINZ ARBITRATION APPEAL TRIBUNAL AMINZ ARBITRATION APPEAL RULES Adopted 27 May 2009 AMINZ Council AMINZ ARBITRATION APPEAL RULES 1. Purpose

More information

General Terms of Contract

General Terms of Contract APPENDIX III General Terms of Contract GENERAL CONDITIONS OF CONTRACT 1. GENERAL PROVISIONS 1. 1 Definitions Unless the context otherwise requires, the following terms whenever used in this Contract have

More information

Computershare Limited (trading through its division Custodial Services) 2000/006082/06 E. TERMS AND CONDITIONS OF CUSTODY AGREEMENT

Computershare Limited (trading through its division Custodial Services) 2000/006082/06 E. TERMS AND CONDITIONS OF CUSTODY AGREEMENT Computershare Limited (trading through its division Custodial Services) 2000/006082/06 E. TERMS AND CONDITIONS OF CUSTODY AGREEMENT 1. INTERPRETATION 1.1 Unless otherwise expressly stated, or the context

More information