Washington Construction Law Recent Case Update

Size: px
Start display at page:

Download "Washington Construction Law Recent Case Update"

Transcription

1 Washington Construction Law Recent Case Update No-Damages Damages-for-Delay Written Notice By John P. Ahlers

2 No Damages for Delay Update 2 John P. Ahlers (206)

3 No Damage for Delay Clauses Contract provision stating that time extension is the sole remedy for a delay. RCW Any such clause is against public policy and is void and unenforceable. 3 John P. Ahlers (206)

4 Washington s Statutory Prohibition of No Damage For Delay Clauses RCW (enacted 1979) Any clause in a construction contract... which purports to waive, release,, or extinguish the rights of a contractor, subcontractor, or supplier to damages or an equitable adjustment arising out of unreasonable delay in performance which delay is caused by the acts or omissions of the contractee or persons acting for the contractee is against public policy and is void and unenforceable. 4 John P. Ahlers (206)

5 No Damage for Delay Clauses Open Issues: Only unreasonable delays barred by statute Nominal contract remedy may be enforceable Use of reciprocal liquidated damages in public contracts 5 John P. Ahlers (206)

6 Is It or Isn t It A No Damage for Delay Clause Prohibited By RCW ? Cooperation With Other Contractors, Section (WSDOT 2006) The Contracting Agency may perform other work at or near the site... with other forces than those of the Contractor. This work may be done with or without a contract John P. Ahlers (206)

7 Section (cont.) The coordination of the work shall be taken into account by the Contractor as part of the site investigation... and any resulting costs shall be incidental and included within the unit bid prices in the contract. 7 John P. Ahlers (206)

8 No Damage For Delay Clauses Utilities and Similar Facilities, Section (WSDOT 2006) When others delay the work through late removal or relocation of any utility or similar facility, the Contractor s loss of time will be adjusted by extending contract time in keeping with Section [Extensions of Time]. 8 John P. Ahlers (206)

9 Section (cont.) Any costs resulting from the coordination and prosecution of the work regarding utility adjustment, relocation, replacement, or construction shall be at the Contractor s expense as provided in Section John P. Ahlers (206)

10 No Damage For Delay Clauses Progress Schedule, Section (WSDOT 2006) The Contracting Agency allocates its resources to a contract based on the total time allowed in the contract. The Contracting Agency will accept a progress schedule indicating an early physical completion date but cannot guarantee the Contracting Agency s resources will be available to meet the accelerated schedule. 10 John P. Ahlers (206)

11 No Damage For Delay Clauses Section (cont.) No additional compensation will be allowed if the Contractor is not able to meet their accelerated schedule due to the unavailability of [the] Contracting Agency s resources or for other reasons beyond the Contracting Agency s control. 11 John P. Ahlers (206)

12 Scoccolo Construction v. Renton Contract for street widening. Contract stated relocation of utilities would be by utility companies. Scoccolo required to coordinate relocation with utility companies. 12 John P. Ahlers (206)

13 Scoccolo Construction v. Renton Contract provided: No additional compensation will be made to [Scoccolo] for reason of delay caused by actions of any utility company and [Scoccolo] shall consider such costs to be incidental to the other items of the contract. 13 John P. Ahlers (206)

14 Scoccolo Construction v. Renton Puget Power did not timely complete relocation of the overhead power lines with underground lines. Scoccolo was delayed and damaged. DELAY 14 John P. Ahlers (206)

15 Scoccolo Construction v. Renton Renton's Motion for Summary Judgment based upon the exculpatory contract provision was granted by trial court. Court of Appeals initially reversed but does not directly address the question of whether RCW invalidated the no damage for delay clause of the contract. 15 John P. Ahlers (206)

16 Scoccolo Construction v. Renton On remand, a jury awarded Scoccolo damages ($1 million). Renton appealed for a second time. 16 John P. Ahlers (206)

17 Scoccolo Construction v. Renton The Court of Appeals reversed, thereby invalidating a substantial portion of Scoccolo s jury verdict. The Court held that the utilities were not a person acting for the contractee and therefore the statute did not apply. 17 John P. Ahlers (206)

18 Scoccolo Construction v. Renton Utilities were not a person acting for the contractee despite the fact that the City had written franchise agreements with the utilities which gave it the power to compel the relocation. 18 John P. Ahlers (206)

19 Scoccolo Construction v. Renton Scoccolo had no contractual power to compel the utilities to act. Scoccolo was not in contractual privity with the utilities, therefore Scoccolo cannot pursue the utilities for its delay damages. 19 John P. Ahlers (206)

20 Scoccolo Construction v. Renton Court of Appeals 2005 decision is first reported case to interpret RCW Decision s narrow interpretation of phrase person acting for the contractee likely to result in more owners attempting to reinsert no damage for delay clauses back into their contracts. 20 John P. Ahlers (206)

21 Scoccolo Construction v. Renton Supreme Court Ruling Unanimous verdict in favor of Scoccolo, the utilities were acting for the City. RCW (No Damages for Delay Statute) trumped the exculpatory clause (no compensation for utility company delay). Scoccolo s $1 million is restored. 21 John P. Ahlers (206)

22 Notice Update Post Mike M. Johnson 22 John P. Ahlers (206)

23 3 Elements of Notice 1) Event (Notice of the Event) 2) Claim (Notice of the Claim) 3) Claims Process and Procedure OF EVENT 23 John P. Ahlers (206)

24 Standard Specifications (2004) / WSDOT & Municipal Projects Section (if Contractor is in disagreement with any change order, direction or instruction by Engineer) [Notice of Event] 1. Signed written notice of protest before doing the work. 24 John P. Ahlers (206)

25 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) 2. Supplement written protest within 15 days in writing with the following: (a) Date of protested order; (b) Nature and circumstances which caused the protest; (c) Contract provisions that support protest; 25 John P. Ahlers (206)

26 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) (d) Estimated dollar cost and how estimate was determined; and (e) Analysis of progress schedule showing schedule change or disruption if Contractor claims a schedule change or disruption. 26 John P. Ahlers (206)

27 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) Section (2) 1 Claim [Notice of Claim] 1. Detailed factual statement of claim for additional compensation and time, providing all necessary dates, locations, and items of work affected. 2. Date on which the facts arose which gave rise to the claim. 27 John P. Ahlers (206)

28 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) 3. Name of each Contracting Agency individual, official, or employee involved in or knowledgeable about the claim. 4. Specific provisions of the Contract which support the claim and a statement of the reasons why. 28 John P. Ahlers (206)

29 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) 5. If the claim pertains to discretionary decisions of the Engineer or matters for which the Engineer s decision is final, set out in detail all facts supporting Contractor s position. 6. Identification of any documents and the substance of oral communications supporting the claim. 29 John P. Ahlers (206)

30 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) 7. Copies of any identified documents, other than Contracting Agency documents and documents previously furnished by Contractor, that support the claim. 8. If additional time is sought: (a) Specific days and dates for which time is sought, 30 John P. Ahlers (206)

31 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) (b) Specific reasons why the time extension should be granted, (c) Specific provisions of Section under which time is sought, and (d) Analysis of Contractor s progress schedule to demonstrate reason for time extension. 31 John P. Ahlers (206)

32 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) 9. If additional compensation is sought, the exact amount sought and a breakdown of that amount into the following categories: (a) Labor (b) Materials (c) Direct equipment 32 John P. Ahlers (206)

33 Standard Specifications (2004) / WSDOT & Municipal Projects (cont.) (d) Job overhead (e) Overhead (general and administrative) (f) Subcontractor s claims 10. Notarized statement certifying validity of claim. 33 John P. Ahlers (206)

34 Mike M. Johnson, Inc. v. Spokane County, 150 Wn.2d 375 (2003) Spokane County Owner Mike M. Johnson Contractor Sewer Project 34 John P. Ahlers (206)

35 Mike M. Johnson, Inc. v. Spokane County WSDOT Specifications April 1998 Award County notified Contractor at the preconstruction conference of road widening which caused a revision of the storm sewer. June 4, 1998 Change Order 3 revised the design of the road and sewer ($69,000) changes clause. 35 John P. Ahlers (206)

36 Mike M. Johnson, Inc. v. Spokane County Mike M. Johnson made no objection or protest. (No Notice of event) Later, Mike M. Johnson encounters telephone cables (U.S. West). 36 John P. Ahlers (206)

37 Mike M. Johnson, Inc. v. Spokane County Specification Immediate signed written notice of protest before doing the work. Supplement written notice of protest within 15 days (5 requirements). No protest deemed acceptance. [MJM failed this step] 37 John P. Ahlers (206)

38 Mike M. Johnson, Inc. v. Spokane County Specification Failure to follow protest procedure as a waiver. If protest fails to achieve resolution, must submit claim (10 requirements). Failure to follow claim procedure is waiver of rights. [Consequence of lack of Notice] 38 John P. Ahlers (206)

39 Mike M. Johnson, Inc. v. Spokane County June 26, 1998 MMJ letter: Lists seven concerns, one of which is the phone line causing additional costs and delays. (concerns and claims) July 16, 1998 County letter: Invites a claim. July 24, 1998 MMJ letter: Doing an analysis. 39 John P. Ahlers (206)

40 Mike M. Johnson, Inc. v. Spokane County August 3, 1998 County letter: No claim utility locate statute. August 7, 1998 County letter: MMJ letter too general and nonspecific regarding relief. August 14, 1998 MMJ letter: Expect compensation while waiting for U.S. West relocation. 40 John P. Ahlers (206)

41 Mike M. Johnson, Inc. v. Spokane County August 25, 1998 MMJ s lawyer s letter: $98,000/50 days. No supporting explanations, no reference to contract. January 27, 1998 County letter: Will negotiate, but no waiver. 41 John P. Ahlers (206)

42 Court s Decision Contractor did not comply with the protest procedure Contractor did not follow claim procedure Contractual condition precedent to Contractor s right to seek judicial relief. 42 John P. Ahlers (206)

43 Court s Decision Comments or concerns that do not include the amount of the claim or length of the delay are not in conformity with requirements of protest procedure John P. Ahlers (206)

44 Court s Decision (cont.) Actual notice by the Owner of the condition in i and of itself does not excuse a Contractor from complying with contractual notice provisions. Waiver is established only when the Owner has actual knowledge and directs the Contractor to proceed with the extra work. 44 John P. Ahlers (206)

45 MMJ Dilemma An Owner can: demand additional work outside the scope of the original contract, observe the contractor perform that work, discuss the work with the contractor, and yet deny fair compensation for services rendered if the contractor fails to submit a written request for compensation/time for the demanded work in the required format. 45 John P. Ahlers (206)

46 MMJ Dilemma (cont.) The Owner can direct work be done, and the Owner is not prejudiced by the Contractor s failure to abide by the technical requirements of submitting a claim for payment, but the contractor nevertheless forfeits its claim. 46 John P. Ahlers (206)

47 Weber Construction v. Spokane County, 124 Wn. App. 29, 98 P.3d 60 (2004) Road building project for Spokane County. 47 John P. Ahlers (206)

48 Weber Construction v. Spokane County Project was a cut and fill project whereby material excavated from the site was to be used for fill and embankments. Large boulders were encountered, unsuitable for fill and embankments. 48 John P. Ahlers (206)

49 Weber Construction v. Spokane County It was necessary for Weber to obtain pit run material from another site to make up for the lack of on-site material to build the roadway embankments. A claim was made by Weber for additional compensation as a result of the quantity and quality of the boulders encountered. (Notice of the Event?) 49 John P. Ahlers (206)

50 Weber Construction v. Spokane County On 8/12/99, the County issued Change Order No. 1 which permitted hauling of material from a private quarry and stated that the reason was that excavated material that was planned for use in building the roadbed and embankments contained large boulders that were not suitable for shallow fills and building embankments. (Notice of the Event?) 50 John P. Ahlers (206)

51 Weber Construction v. Spokane County The change order also specified the price for the import material, and an estimated quantity of 14,600 cubic yards. No price was provided for removing and wasting the boulders. (Notice of Claim?) The Standard Specifications applied. Weber protested the change order on 8/19/ John P. Ahlers (206)

52 Weber Construction v. Spokane County Weber supplemented its written protest on 8/31/99, and provided all of the required information except the estimate of the costs of the protested work.. Weber requested that the County identify a dump site for the boulders, and then Weber would provide the County with an estimate and how the estimate was made. [Notice of Claim? Claim = $$] 52 John P. Ahlers (206)

53 Weber Construction v. Spokane County The County steadfastly denied that a change condition existed, and that Weber had any entitlement, much less right to compensation. The County advised Weber of this by 9/8/99 letter. 53 John P. Ahlers (206)

54 Weber Construction v. Spokane County Although the County estimated the quantity of boulders at 14,600 cubic yards in the change order, ultimately over 40,000 cubic yards of boulders were hauled to waste and replaced with import material. The Project was shut down for the winter from 11/99 until 5/ John P. Ahlers (206)

55 Weber Construction v. Spokane County Weber worked full time from 11/99 through 3/00 compiling its costs of the impacts related to its change conditions claim. On 3/10/00 Weber submitted its certified, written claim for over $1,000,000 as required by the Standard Specifications. (Now had price) 55 John P. Ahlers (206)

56 Weber Construction v. Spokane County Weber offered to provide the County with full access to its job cost accounting records so that the County could audit the job costs. The County declined. The case was tried to a jury in Spokane County Superior Court. 56 John P. Ahlers (206)

57 Weber Construction v. Spokane County The trial judge dismissed the case at the conclusion of Weber s case finding that: 1. the existence of the boulders was foreseeable, and 2. Weber did not follow the contract procedures for requesting additional compensation in that it did not provide the estimated cost with its supplemental protest information. 57 John P. Ahlers (206)

58 Weber Construction v. Spokane County On 3/6/03, Division III of the Court of Appeals reversed on both counts, ruling that the issue of whether the County s actual notice of Weber s problems constituted waiver of strict compliance with the contract terms was a question of fact for a jury. 58 John P. Ahlers (206)

59 Weber Construction v. Spokane County Spokane County sought discretionary review from the Washington Supreme Court. Discretionary review was granted. 59 John P. Ahlers (206)

60 Weber Construction v. Spokane County Following the Supreme Court s decision in Mike M. Johnson,, it remanded the Weber case to the Court of Appeals for consideration in light of Mike M. Johnson. On July 27, 2004, the Court of Appeals, for the second time, reversed the trial court. 60 John P. Ahlers (206)

61 Weber Construction v. Spokane County There were two bases to the Court s opinion. First, the Court found that substantial evidence existed that Weber had complied with the requirement to provide required information to supplement its written protest as to the estimated cost of the work. 61 John P. Ahlers (206)

62 Weber Construction v. Spokane County (cont.) The Court found that because the County did not provide the requested information on the disposal of the boulders, Weber could not have stated in good faith how any such estimate was determined. (County precluded Notice Compliance) 62 John P. Ahlers (206)

63 Weber Construction v. Spokane County Substantial evidence supported Weber s compliance with the contract terms. The second basis for the Court s decision, was that the Court found that substantial evidence also existed as to the County s waiver of strict contractual compliance with the protest procedures. 63 John P. Ahlers (206)

64 Weber Construction v. Spokane County Waiver: The Court found that the County knew that Weber was required to provide a dollar cost estimate, and knew that Weber was aware of this requirement and was attempting to meet it. Weber requested information needed to provide the estimate, but the County failed to provide the information. 64 John P. Ahlers (206)

65 American Safety Casualty Insurance v. Olympia, Wn. App. Div. 2 (6/27/06) Contract for sanitary sewer lines between Olympia and Katspan. American Safety Casualty was Katspan's surety. Contract contained Standard Specifications including: 65 John P. Ahlers (206)

66 American Safety Casualty Ins. v. Olympia , 1 notice and protest, immediate notice with supplemental information within 15 days (Notice of Event) (1) 1 and (2), claim requirements (Notice of Claim) (3), 1 suit must be brought within 180 days of final acceptance (Claim Procedure) 66 John P. Ahlers (206)

67 Issue: Did Olympia Waive the Contract's Lawsuit And Protest Time Limits? Trial court said no on motion for summary judgment and awarded fees to Olympia. Court of Appeals reversed. 67 John P. Ahlers (206)

68 American Safety Casualty Ins. v. Olympia 1/5/01 City sent Katspan a letter granting 20-day time extension. Katspan disagreed by letter and referred to earlier letter. Neither letter complied with protest requirements. 68 John P. Ahlers (206)

69 American Safety Casualty Ins. v. Olympia 2/26/01 Katspan sent another letter to City seeking to preserve its right to request time and money and stating that it would prepare additional documentation. Katspan did not provide the documentation. 69 John P. Ahlers (206)

70 American Safety Casualty Ins. v. Olympia When project almost complete, City's representative sent Katspan two letters asking for the information Katspan had promised in its 2/26/01 letter. Katspan responded that the information would be coming shortly. It was never sent. 70 John P. Ahlers (206)

71 American Safety Casualty Ins. v. Olympia City's representative sent Katspan a letter requesting that it execute a change order for all additional work. Katspan refused. Katspan became insolvent and assigned its rights to American Safety. 9/10/01 City accepted project as complete. 71 John P. Ahlers (206)

72 American Safety Casualty Ins. v. Olympia 11/01 American Safety sought an equitable adjustment of $767,995. Request did not comply with claim requirements. 3/02 American Safety's attorney contacted City's attorney. 72 John P. Ahlers (206)

73 American Safety Casualty Ins. v. Olympia Thereafter, City advised it needed additional information and documentation to make the requested equitable adjustment. America Safety advised it was having difficulty obtaining the documents and asked if the City would negotiate without information. 73 John P. Ahlers (206)

74 American Safety Casualty Ins. v. Olympia City responded that it would proceed, but would not negotiate. It claimed it had inadequate backup information. 5/02 American Safety sent City two 3-ring 3 binders containing information. 8/02 City responded it needed additional information. 74 John P. Ahlers (206)

75 American Safety Casualty Ins. v. Olympia 11/02 City again requested additional information. 1/03 American Safety notified City that it had received 4 or 5 boxes from Katspan, and they were available for review. City reviewed the documents. 75 John P. Ahlers (206)

76 American Safety Casualty Ins. v. Olympia 4/23/03 City notified American Safety that the documents did not contain all of the requested/required information. City stated American Safety had until 5/16/03 to produce the information, and that if it failed, the City would deny the claim. Deadline was not met. 76 John P. Ahlers (206)

77 American Safety Casualty Ins. v. Olympia 7/31/03 American Safety through its consultant contacted the City to discuss information City was demanding. 8/4/03 City's accountant responded that he had been given the green light to discuss. 8/03 Consultants exchanged s E about information and how American Safety should format it. 77 John P. Ahlers (206)

78 American Safety Casualty Ins. v. Olympia 5/21/04 American Safety contacted the City to notify it that information was available. City responded and denied American Safety's claim and stated that it could no longer file suit because suit was untimely under the contract. 8/04 American Safety sued City. 78 John P. Ahlers (206)

79 American Safety Casualty Ins. v. Olympia Court of Appeals Decision: Court distinguished Mike M. Johnson.. City did not continuously express its intent to abide by contractual provisions. [Now standard] If City had no intention of allowing litigation, it should have informed American Safety. 79 John P. Ahlers (206)

80 American Safety Casualty Ins. v. Olympia City could also have halted all communication. City's continued requests for information, reference to future litigation,, and deadlines for production well beyond the contract limitations created inferences that the City waived the contract terms. 80 John P. Ahlers (206)

81 American Safety Casualty Ins. v. Olympia Court further found that issues of fact remained as to whether the totality of the circumstances resulted in an implicit waiver of the contract provisions for timeliness of claim and suit. 81 John P. Ahlers (206)

82 Strand Hunt Construction v. Lake Washington School Dist., Wn. App. Div. I (9/5/06) $37 million high school project Delay Impact caused by design conflict 82 John P. Ahlers (206)

83 Key Contract Document Provisions: Changes could be up to 10% of the contract amount. Compensation for changes based on direct cost plus a fee calculated as percentage of direct costs. 83 John P. Ahlers (206)

84 Key Provisions (cont.) Fee on changes is an allowance for all combined overhead, profit, and other costs, including all office, home office, and site overhead, and includes delay and impact costs of any kind. Claims to be submitted within 14 days of the event giving rise to them. [Claim Notice] 84 John P. Ahlers (206)

85 Key Provisions (cont.) Claims to include a clear description of the claim, the proposed change in the Contract Sum and/or time of the Claim and provide data supporting the Claim. [Definition of Claims] Claims not so made are waived. 85 John P. Ahlers (206)

86 Strand Hunt 6/29/03 Letter from Strand Hunt to District requesting compensation for inordinate number of RFIs caused by defective drawings. Over 1,500 RFIs. 400 were directly related to change orders. Strand Hunt preliminary figures of $752,053 in direct cost impacts and $426,045 for indirect costs for labor inefficiencies. 86 John P. Ahlers (206)

87 Strand Hunt District stated 6/29 letter did not constitute a claim and did not comply with contract requirements. 7/23/03 Strand Hunt sent District a letter entitled "Claim for Multiplicity Impacts." Requested $2,434,813 for an inordinate number of RFIs and other defects in contract documents. (Claim increased about 4 times.) 87 John P. Ahlers (206)

88 Strand Hunt District denied claim. 7/31/03 Strand Hunt filed suit. 11/04 Strand Hunt submitted "Consolidated Request for Equitable Adjustment" for $4,538,366. (Claim increased about 2 times.) 88 John P. Ahlers (206)

89 Strand Hunt District moved for partial summary judgment seeking dismissal of Strand Hunt's claims for cumulative impact damages, field overhead delay damages, and home office overhead damages because Strand Hunt failed to comply with contract requirements for claims. 89 John P. Ahlers (206)

90 Strand Hunt District further contended that claims for overhead were barred because they were indirect delay damages which could only be asserted in connection with direct damage claims. 3/7/05 trial court granted District's motion. 90 John P. Ahlers (206)

91 Strand Hunt 8/18/05 trial court entered order clarifying that its earlier order dismissed Strand Hunt's quantum meruit claims. Court of Appeals affirmed. 91 John P. Ahlers (206)

92 Strand Hunt Strand Hunt failed to comply with the requirements for submitting a claim. Court rejected Strand Hunt's contention that it would have been impossible for it to submit claims in the manner and time frame specified in the contract. 92 John P. Ahlers (206)

93 Strand Hunt Court did not understand how Strand Hunt could fail to notice $4,538,366 in expenses. Court rejected Strand Hunt's contention that the event giving rise to cumulative impact claim was a dispute with the District. Such an interpretation would render the contractual claim requirements meaningless. 93 John P. Ahlers (206)

94 Strand Hunt Court rejected quantum meruit claim as contract anticipated changes and contained provisions regarding degree and nature of changes. Court rejected Strand Hunt's contention that RCW (No-Damages Damages-For-Delay) overturned the contract provision regarding delay damages. Strand Hunt agreed to such terms and should have complied with them. 94 John P. Ahlers (206)

95 Strand Hunt Court rejected Strand Hunt's recovery of home office overhead per Eichleay formula as Strand Hunt worked continuously, and was never suspended, even though worked allegedly inefficiently. 95 John P. Ahlers (206)

96 Legislative Solution failure to submit claim notice or claim-related documentation

97 Legislative Solution party failing to provide such notice has the initial burden to make a prima facie showing that the party failing to receive such notice was not prejudiced thereby

98 Legislative Solution "prejudiced" means being deprived of the opportunity to mitigate cost, time, or both cost and time impacts

TYPES OF MONETARY DAMAGES

TYPES OF MONETARY DAMAGES TYPES OF MONETARY DAMAGES A breach of contract entitles the non-breaching party to sue for money damages, including: Compensatory Damages: Damages that compensate the non-breaching party for the injuries

More information

Managing Contracts In Crisis (A Legal Perspective) American Public Works Association April 19, 2018

Managing Contracts In Crisis (A Legal Perspective) American Public Works Association April 19, 2018 Managing Contracts In Crisis (A Legal Perspective) American Public Works Association April 19, 2018 By: William A. Linton Inslee Best Doezie & Ryder, P.S. Bellevue, Washington 2 1 Course Outline General

More information

PACIFICA LAW GROUP Annual Summary Construction Procurement

PACIFICA LAW GROUP Annual Summary Construction Procurement PACIFICA LAW GROUP 2018 Annual Summary Construction Procurement We are pleased to offer this comprehensive summary of the major construction and procurement developments in 2018 that have an impact on

More information

NO. COA NORTH CAROLINA COURT OF APPEALS. Filed: 4 December Appeal by defendants from Amended Judgment entered 8 March

NO. COA NORTH CAROLINA COURT OF APPEALS. Filed: 4 December Appeal by defendants from Amended Judgment entered 8 March NO. COA12-636 NORTH CAROLINA COURT OF APPEALS Filed: 4 December 2012 SOUTHERN SEEDING SERVICE, INC., Plaintiff, v. Guilford County No. 09 CVS 12411 W.C. ENGLISH, INC.; LIBERTY MUTUAL INSURANCE COMPANY;

More information

PROSECUTION AND PROGRESS

PROSECUTION AND PROGRESS PROSECUTION AND PROGRESS 1.01 SUBLETTING OR ASSIGNMENT OF CONTRACT A. Work by Contractor: 1. The Contractor shall perform, with its own organization and forces, work amounting to no less than 30% of the

More information

Illinois Legal Update. Patrick M. Miller, Partner

Illinois Legal Update. Patrick M. Miller, Partner Illinois Legal Update Patrick M. Miller, Partner ILLINOIS Legal Update Case Law Update: Limitations periods applicable to construction related and indemnification claims Strict application of affidavit

More information

GOODS & SERVICES AGREEMENT FOR ORDINARY MAINTENANCE. between the City of and

GOODS & SERVICES AGREEMENT FOR ORDINARY MAINTENANCE. between the City of and GOODS & SERVICES AGREEMENT FOR ORDINARY MAINTENANCE between the City of and [Insert Vendor's Co. Name] THIS AGREEMENT is made by and between the City of, a Washington municipal corporation (hereinafter

More information

MAINE MECHANIC S LIEN LAW

MAINE MECHANIC S LIEN LAW MAINE MECHANIC S LIEN LAW 2018-2019 Go to: Maine Mechanic s Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified

More information

Home Foundation Subcontractor Services Agreement

Home Foundation Subcontractor Services Agreement Home Foundation Subcontractor Services Agreement This Packet Includes: 1. General Information 2. Instructions and Checklist 3. Step-by-Step Instructions 4. Home Foundation Subcontractor Services Agreement

More information

Chapter II BAY MILLS COURT OF APPEALS

Chapter II BAY MILLS COURT OF APPEALS Chapter II BAY MILLS COURT OF APPEALS 201. CREATION OF THE BAY MILLS COURT OF APPEALS. There shall be a Bay Mills Court of Appeals consisting of the three appeals judges. Any number of judges may be appointed

More information

Delays. Dr. Mohammad S. El-Mashaleh. Delays

Delays. Dr. Mohammad S. El-Mashaleh. Delays Delays 1 Delays A delay is the time during which some part of the construction project has been extended or not performed due to an unanticipated (or anticipated) circumstance May be caused by any of the

More information

Assembly Bill No. 125 Committee on Judiciary

Assembly Bill No. 125 Committee on Judiciary - Assembly Bill No. 125 Committee on Judiciary CHAPTER... AN ACT relating to constructional defects; enacting provisions governing the indemnification of a controlling party by a subcontractor for certain

More information

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION II

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION II IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION II Filed Washington State Court of Appeals Division Two November 22, 2016 MICHAEL NOEL, and DIANA NOEL, individually and as the marital community

More information

No. 103,973 IN THE COURT OF APPEALS OF THE STATE OF KANSAS. MIDWEST ASPHALT COATING, INC., Appellant, CHELSEA PLAZA HOMES, INC., et al., Appellees.

No. 103,973 IN THE COURT OF APPEALS OF THE STATE OF KANSAS. MIDWEST ASPHALT COATING, INC., Appellant, CHELSEA PLAZA HOMES, INC., et al., Appellees. No. 103,973 IN THE COURT OF APPEALS OF THE STATE OF KANSAS MIDWEST ASPHALT COATING, INC., Appellant, v. CHELSEA PLAZA HOMES, INC., et al., Appellees. SYLLABUS BY THE COURT 1. A court may not award attorney

More information

TELECOMMUNICATIONS RIGHT-OF-WAY USE FRANCHISE AGREEMENT

TELECOMMUNICATIONS RIGHT-OF-WAY USE FRANCHISE AGREEMENT Exhibit A TELECOMMUNICATIONS RIGHT-OF-WAY USE FRANCHISE AGREEMENT Whereas, Zayo Group, LLC, a Delaware limited liability company ("COMPANY"), and the City of University Place ("City") have engaged in negotiations

More information

BRIDGE AUTHORITY, COURT OF APPEALS OF MICHIGAN

BRIDGE AUTHORITY, COURT OF APPEALS OF MICHIGAN LEXSEE ABHE & SVBODA INC, Plaintiff-Appellant, v STATE OF MICHIGAN, DEPARTMENT OF TRANSPORTATION, and MACKINAC BRIDGE AUTHORITY, Defendants-Appellees. No. 332489 COURT OF APPEALS OF MICHIGAN 2017 Mich.

More information

08 LC A BILL TO BE ENTITLED AN ACT

08 LC A BILL TO BE ENTITLED AN ACT Senate Bill 374 By: Senators Weber of the 40th and Seabaugh of the 28th A BILL TO BE ENTITLED AN ACT 1 To amend Part 3 of Article 8 of Chapter 14 of Title 44 of the Official Code of Georgia 2 Annotated,

More information

RULES OF THE RHODE ISLAND HEALTH AND EDUCATIONAL BUILDING CORPORATION FOR THE PROCUREMENT OF SUPPLIES. SERVICES, BOND COUNSEL AND LEGAL COUNSEL

RULES OF THE RHODE ISLAND HEALTH AND EDUCATIONAL BUILDING CORPORATION FOR THE PROCUREMENT OF SUPPLIES. SERVICES, BOND COUNSEL AND LEGAL COUNSEL RULES OF THE RHODE ISLAND HEALTH AND EDUCATIONAL BUILDING CORPORATION FOR THE PROCUREMENT OF SUPPLIES. SERVICES, BOND COUNSEL AND LEGAL COUNSEL RULES OF THE RHODE ISLAND HEALTH AND EDUCATIONAL BUILDING

More information

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS 1. Applicability. 2. Delivery. GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS a. These terms and conditions of sale (these "Terms") are the only terms which govern the sale of the goods ("Goods") by

More information

SCOPE OF WORK 1.03 COORDINATION OF SPECIFICATIONS, PLANS, AND SPECIAL PROVISIONS

SCOPE OF WORK 1.03 COORDINATION OF SPECIFICATIONS, PLANS, AND SPECIAL PROVISIONS SCOPE OF WORK 1.01 INTENT OF THE CONTRACT DOCUMENTS A. These SUDAS Standard Specifications have been prepared to provide construction utilizing the best general practices and construction methods, utilizing

More information

ORDINANCE NO THE CITY COUNCIL OF THE CITY OF ISSAQUAH, WASHINGTON, DO ORDAIN AS FOLLOWS: Section 1. Definitions.

ORDINANCE NO THE CITY COUNCIL OF THE CITY OF ISSAQUAH, WASHINGTON, DO ORDAIN AS FOLLOWS: Section 1. Definitions. ORDINANCE NO. 2591 AN ORDINANCE GRANTING PUGET SOUND ENERGY, INC., A WASHINGTON CORPORATION, ITS SUCCESSORS AND ASSIGNS, THE RIGHT, PRIVILEGE, AUTHORITY AND FRANCHISE TO SET, ERECT, LAY, CONSTRUCT, EXTEND,

More information

IN THE COURT OF APPEALS OF THE STATE OF OREGON

IN THE COURT OF APPEALS OF THE STATE OF OREGON No. 126 March 21, 2018 811 IN THE COURT OF APPEALS OF THE STATE OF OREGON Rich JONES, Plaintiff-Appellant, v. FOUR CORNERS ROD AND GUN CLUB, an Oregon non-profit corporation, Defendant-Respondent. Kip

More information

Assembly Amendment to Assembly Bill No. 125 (BDR 3-588) Title: No Preamble: No Joint Sponsorship: No Digest: Yes

Assembly Amendment to Assembly Bill No. 125 (BDR 3-588) Title: No Preamble: No Joint Sponsorship: No Digest: Yes 0 Session (th) A AB Amendment No. Assembly Amendment to Assembly Bill No. (BDR -) Proposed by: Assembly Committee on Judiciary Amends: Summary: No Title: No Preamble: No Joint Sponsorship: No Digest: Yes

More information

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS 1. Applicability. (a) These terms and conditions of sale (these "Terms") are the only terms which govern the sale of the goods ("Goods") by Tecogen Inc.

More information

Louisiana Construction Law Update

Louisiana Construction Law Update FEBRUARY 2013 Louisiana Construction Law Update The Construction Law Update is published by Baldwin Haspel Burke & Mayer, LLC for the benefit of its clients and others having interest in the construction

More information

BOROUGH OF FOX CHAPEL BIDS FOR RUBBISH CONTAINER BINS. CONTRACT NUMBERS and 08-06

BOROUGH OF FOX CHAPEL BIDS FOR RUBBISH CONTAINER BINS. CONTRACT NUMBERS and 08-06 BIDS FOR RUBBISH CONTAINER BINS CONTRACT NUMBERS 08-05 and 08-06 December 2008 FOX CHAPEL BOROUGH County of Allegheny, Commonwealth of Pennsylvania BIDS FOR RUBBISH CONTAINER BINS CONTRACT NUMBERS 08-05

More information

The Consultant selected by the IDA will perform the following services:

The Consultant selected by the IDA will perform the following services: Request for Proposals for Consulting Forestry Services Carroll County Industrial Development Authority October 20, 2014 I. Consulting Forester Services a. Background: The Carroll County Industrial Development

More information

IN THE SUPREME COURT OF THE STATE OF WASHINGTON

IN THE SUPREME COURT OF THE STATE OF WASHINGTON IN THE SUPREME COURT OF THE STATE OF WASHINGTON PATTY J. GANDEE, individually and on ) behalf of a Class of similarly situated ) No. 87674-6 Washington residents, ) ) Respondent, ) ) v. ) En Banc ) LDL

More information

Sunnyside Valley Irrigation District

Sunnyside Valley Irrigation District 2019 Perforated HDPE Pipe Bid Package Sealed bids will be received until 11:00 am. January 4th, 2019 at Field Office 1105 Yakima Valley Hwy. P.O. Box 239 Sunnyside, WA 98944 509-837-6980 Project Contact:

More information

Municipal Code Online Inc. Software as a Service Agreement

Municipal Code Online Inc. Software as a Service Agreement Exhibit A Municipal Code Online Inc. Software as a Service Agreement This Municipal Code Online, Inc. Software as a Service Agreement ( SaaS Agreement ) is made and entered into on this date, by and between

More information

Saudi Center for Commercial Arbitration King Fahad Branch Rd, Al Mutamarat, Riyadh, KSA PO Box 3758, Riyadh Tel:

Saudi Center for Commercial Arbitration King Fahad Branch Rd, Al Mutamarat, Riyadh, KSA PO Box 3758, Riyadh Tel: SCCA Arbitration Rules Shaaban 1437 - May 2016 Saudi Center for Commercial Arbitration King Fahad Branch Rd, Al Mutamarat, Riyadh, KSA PO Box 3758, Riyadh 11481 Tel: 920003625 info@sadr.org www.sadr.org

More information

Purchase Agreement (Services)

Purchase Agreement (Services) Purchase Agreement (Services) SLS SAMPLE DOCUMENT 06/30/17 This is a Purchase Agreement ( Agreement ), dated as of [month day, year] ( Effective Date ), between [ ] ( Client ) and ( Vendor ). BACKGROUND

More information

2010 CUMULATIVE SUPPLEMENT Chapter 11: Georgia Construction and Design Law

2010 CUMULATIVE SUPPLEMENT Chapter 11: Georgia Construction and Design Law 2010 CUMULATIVE SUPPLEMENT Chapter 11: Georgia Construction and Design Law IX Construction Liens Replace the first paragraph with the following: Mechanics and materialmen s liens are established by Code

More information

RHODE ISLAND MECHANIC S LIEN LAW

RHODE ISLAND MECHANIC S LIEN LAW RHODE ISLAND MECHANIC S LIEN LAW 2018-2019 Go to: Rhode Island Mechanics Lien Forms: More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When

More information

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON COLUMBIA STATE BANK, a Washington State banking corporation, No. 65959-6-I Appellant, DIVISION ONE v. UNPUBLISHED OPINION NORMANDY PARK INVESTORS, LLC,

More information

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF ASH EQUIPMENT CO., INC. D/B/A AMERICAN HYDRO; AND ASH EQUIPMENT CO., INC., A

More information

Time and Construction Contracts

Time and Construction Contracts Time and Construction Contracts Extensions of Time and the Prevention Principle By Nathan Abbott Introduction The purpose of this paper is to expose and consider the Prevention Principle from a practical

More information

RIGHT-OF-WAY APPLICATION EXCAVATION PERMIT

RIGHT-OF-WAY APPLICATION EXCAVATION PERMIT City of St. Cloud Engineering Department 400 2nd Street South St. Cloud, MN 56301 320-255-7249 RIGHT-OF-WAY APPLICATION EXCAVATION PERMIT Name of Utility Company: Address: City/State/Zip: Telephone: Email:

More information

NC General Statutes - Chapter 44A Article 2 1

NC General Statutes - Chapter 44A Article 2 1 Article 2. Statutory Liens on Real Property. Part 1. Liens of Mechanics, Laborers, and Materialmen Dealing with Owner. 44A-7. Definitions. Unless the context otherwise requires, the following definitions

More information

CONSULTANCY SERVICES AGREEMENT

CONSULTANCY SERVICES AGREEMENT DATED 2010 [INSERT NAME OF CUSTOMER] (Customer) CAVALLINO HOLDINGS PTY LIMITED ACN 136 816 656 ATF THE DAYTONA DISCRETIONARY TRUST T/A INSIGHT ACUMEN (Consultant) CONSULTANCY SERVICES AGREEMENT Suite 5,

More information

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION II

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION II IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION II WAQAS SALEEMI, a single man, and FAROOQ SHARYAR, a single man, Respondents, v. DOCTOR S ASSOCIATES, INC., a Florida corporation, PUBLISHED

More information

H SUBSTITUTE HOUSE BILL State of Washington 58th Legislature 2004 Regular Session

H SUBSTITUTE HOUSE BILL State of Washington 58th Legislature 2004 Regular Session H-4810.1 SUBSTITUTE HOUSE BILL 3187 State of Washington 58th Legislature 2004 Regular Session By House Committee on Commerce & Labor (originally sponsored by Representatives Romero, Hudgins, Conway, Hunt,

More information

IN THE COURT OF APPEALS STATE OF ARIZONA DIVISION ONE ) ) ) ) ) ) ) ) ) ) ) Appeal from the Superior Court in Maricopa County

IN THE COURT OF APPEALS STATE OF ARIZONA DIVISION ONE ) ) ) ) ) ) ) ) ) ) ) Appeal from the Superior Court in Maricopa County NOTICE: THIS DECISION DOES NOT CREATE LEGAL PRECEDENT AND MAY NOT BE CITED EXCEPT AS AUTHORIZED BY APPLICABLE RULES. See Ariz.R.Sup.Ct. 111(c; ARCAP 28(c; Ariz.R.Crim.P. 31.24 IN THE COURT OF APPEALS STATE

More information

SureQuick Express Bond Application

SureQuick Express Bond Application SureQuick Express Bond Application General Information Contractor Company Name Business Phone No. ( ) Mobile ( ) Home ( ) E-mail address Type of work done? Operates as Proprietorship Partnership Corporation

More information

1. Purpose. 2. Scope of Procurement Authority.

1. Purpose. 2. Scope of Procurement Authority. Rules Governing Procurement of Goods, Services, Insurance, and Construction by a Public Institution of Higher Education of the Commonwealth of Virginia Governed by Subchapter 3 of the Restructured Higher

More information

Guidelines for Submittals for Land Disturbance Permits

Guidelines for Submittals for Land Disturbance Permits Guidelines for Submittals for Land Disturbance Permits A Land Disturbance Permit (LDP) is a local permit required by the City of Shawnee for any land disturbance occurring in a given area. "Land Disturbance"

More information

The Corporation of The Township of Lanark Highlands. TENDER #PW Resurfacing Lavant Mill Road

The Corporation of The Township of Lanark Highlands. TENDER #PW Resurfacing Lavant Mill Road The Corporation of The TENDER #PW 2016-02 Resurfacing Name of Firm or Individual Address Telephone and Fax Number Email Address Name of Person Signing for Firm Position of Person Signing for Firm TENDERS

More information

STATE OF MICHIGAN COURT OF APPEALS

STATE OF MICHIGAN COURT OF APPEALS STATE OF MICHIGAN COURT OF APPEALS KNAPP S VILLAGE, L.L.C, Plaintiff/Counter Defendant- Appellant, UNPUBLISHED June 26, 2014 V No. 314464 Kent Circuit Court KNAPP CROSSING, L.L.C, LC No. 11-004386-CZ and

More information

ECONOMIC DEVELOPMENT PARTNERSHIP AGREEMENT BETWEEN THE PORT OF SEATTLE AND THE CITY OF

ECONOMIC DEVELOPMENT PARTNERSHIP AGREEMENT BETWEEN THE PORT OF SEATTLE AND THE CITY OF ECONOMIC DEVELOPMENT PARTNERSHIP AGREEMENT BETWEEN THE PORT OF SEATTLE AND THE CITY OF This Economic Development Partnership Agreement (the Agreement ) is made and entered into as of, 20, by and between

More information

Request For Proposals Hwy 124 E ADA Door Opener Hallsville City Hall

Request For Proposals Hwy 124 E ADA Door Opener Hallsville City Hall Request For Proposals 2018-1 202 Hwy 124 E ADA Door Opener Hallsville City Hall The City of Hallsville, Missouri (the City ) seeks bids from qualified contractors for all materials and labor to install

More information

BASF Tanzania Limited Standard Terms and Conditions of Sale

BASF Tanzania Limited Standard Terms and Conditions of Sale 1. SCOPE OF APPLICATION All current and future supplies of products and services (including any literature or other information) offered by BASF to the Customer (collectively referred to as the Goods )

More information

IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO Opinion Number: 2013-NMCA-019 Filing Date: November 14, 2012 Docket No. 30,773 JOURNEYMAN CONSTRUCTION, LP, v. Plaintiff-Appellant, PREMIER HOSPITALITY

More information

BOND AGREEMENT CERTIFICATE OF OCCUPANCY - CASH ONLY COMPLETION OF PUBLIC OR PRIVATE IMPROVEMENTS

BOND AGREEMENT CERTIFICATE OF OCCUPANCY - CASH ONLY COMPLETION OF PUBLIC OR PRIVATE IMPROVEMENTS BOND AGREEMENT CERTIFICATE OF OCCUPANCY - CASH ONLY COMPLETION OF PUBLIC OR PRIVATE IMPROVEMENTS All property owners on record with Tooele County MUST be listed as Applicants. They must each sign and have

More information

RULES OF PROCEDURE BEFORE THE COWLITZ COUNTY HEARINGS EXAMINER

RULES OF PROCEDURE BEFORE THE COWLITZ COUNTY HEARINGS EXAMINER RULES OF PROCEDURE BEFORE THE COWLITZ COUNTY HEARINGS EXAMINER INTRODUCTION The following Rules of Procedure have been adopted by the Cowlitz County Hearing Examiner. The examiner and deputy examiners

More information

UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF FLORIDA PATENT CASE SCHEDULE. Answer or Other Response to Complaint 5 weeks

UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF FLORIDA PATENT CASE SCHEDULE. Answer or Other Response to Complaint 5 weeks UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF FLORIDA PATENT CASE SCHEDULE Event Service of Complaint Scheduled Time Total Time After Complaint Answer or Other Response to Complaint 5 weeks Initial

More information

You may owe fees for use of the App or the Services. Check with your Financial Institution for applicable rates.

You may owe fees for use of the App or the Services. Check with your Financial Institution for applicable rates. CardValet Terms of Use THIS IS A LEGAL AGREEMENT BETWEEN YOU AND THE FINANCIAL INSTITUTION THAT ISSUED YOU THE PAYMENT CARD THAT YOU REGISTER WITHIN THIS APPLICATION ( Financial Institution ), stating

More information

IN THE SUPERIOR COURT OF THE STATE OF WASHINGTON IN AND FOR THE COUNTY OF KING ) ))

IN THE SUPERIOR COURT OF THE STATE OF WASHINGTON IN AND FOR THE COUNTY OF KING ) )) 1 Honorable Laura Gene Middaugh 2 3 6 7 8 9 10 11 1 1 16 17 l8~ IN THE SUPERIOR COURT OF THE STATE OF WASHINGTON IN AND FOR THE COUNTY OF KING CITY OF SEATTLE, a Washington municipal Corporation, No. 11-2-11719-7

More information

CITY OF ENID RIGHT-OF-WAY AGREEMENT

CITY OF ENID RIGHT-OF-WAY AGREEMENT CITY OF ENID RIGHT-OF-WAY AGREEMENT This Right-of-Way Agreement ( Agreement ) is entered into by and between the City of Enid, an Oklahoma Municipal Corporation, hereinafter referred to as City, and hereinafter

More information

AAA Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex, Commercial Disputes)

AAA Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex, Commercial Disputes) APPENDIX 4 AAA Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex, Commercial Disputes) Commercial Mediation Procedures M-1. Agreement of Parties Whenever, by

More information

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE THE FOLLOWING TERMS AND CONDITIONS, AND THOSE SPECIFIED ON THE FACE OF THIS PURCHASE ORDER, SHALL EXCLUSIVELY GOVERN THE PURCHASE OF ALL MATERIALS

More information

Table of Contents. Date Issued: June 12, 2009 Date Last Revised: December 15, 2010

Table of Contents. Date Issued: June 12, 2009 Date Last Revised: December 15, 2010 Date Issued: June 12, 2009 Date Last Revised: December 15, 2010 CHAPTER 28. Protests Table of Contents CHAPTER 28. Protests... 28 1 28.1 General... 28 2 28.1.1 Policy... 28 2 28.1.2 Notice to Offerors...

More information

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules

More information

CHAPTER 02 ELECTION PROTESTS SECTION.0100 ELECTION PROTESTS

CHAPTER 02 ELECTION PROTESTS SECTION.0100 ELECTION PROTESTS CHAPTER 02 ELECTION PROTESTS SECTION.0100 ELECTION PROTESTS 08 NCAC 02.0101 COMPLAINTS CONCERNING CONDUCT OF ELECTIONS 08 NCAC 02.0102 PRELIMINARY CONSIDERATION OF COMPLAINT BY COUNTY BOARD 08 NCAC 02.0103

More information

LOUISIANA MECHANIC S LIEN LAW

LOUISIANA MECHANIC S LIEN LAW LOUISIANA MECHANIC S LIEN LAW 2018-2019 Go to: Louisiana Mechanic s Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to

More information

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON LEE HAYNES, an adult individual, ) NO. 66542-1-I ) Appellant, ) DIVISION ONE ) v. ) UNPUBLISHED OPINION ) SNOHOMISH COUNTY, and ) SNOHOMISH COUNTY PUBLIC

More information

CONTRACTOR INFORMATION - Attach most recent company year-end financial statement or tax return.

CONTRACTOR INFORMATION - Attach most recent company year-end financial statement or tax return. This program is not intended for use on the following types of contracts; Subdivision Completion Multi-year Terms Indefinite Quantity Service Contracts Design Build Efficiency Guarantees Software Programs

More information

ORDINANCE NO. 906 AN ORDINANCE AMENDING THE ATHENS MUNICIPAL CODE BY REVISING CHAPTER 2 OF TITLE 16 IN ITS ENTIRETY.

ORDINANCE NO. 906 AN ORDINANCE AMENDING THE ATHENS MUNICIPAL CODE BY REVISING CHAPTER 2 OF TITLE 16 IN ITS ENTIRETY. ORDINANCE NO. 906 AN ORDINANCE AMENDING THE ATHENS MUNICIPAL CODE BY REVISING CHAPTER 2 OF TITLE 16 IN ITS ENTIRETY. BE IT ORDAINED BY THE CITY OF ATHENS, TENNESSEE, AS FOLLOWS: Section 1. Chapter 2 of

More information

SECTION ADDENDA EL DORADO IRRIGATION DISTRICT GILMORE, POLARIS, AND RIDGEWAY WATERLINE REPLACEMENT PROJECT ADDENDUM NO. 1 JANUARY 25, 2017

SECTION ADDENDA EL DORADO IRRIGATION DISTRICT GILMORE, POLARIS, AND RIDGEWAY WATERLINE REPLACEMENT PROJECT ADDENDUM NO. 1 JANUARY 25, 2017 SECTION 00910 ADDENDA EL DORADO IRRIGATION DISTRICT GILMORE, POLARIS, AND RIDGEWAY WATERLINE REPLACEMENT PROJECT ADDENDUM NO. 1 JANUARY 25, 2017 This Addendum No. 1 ( Addendum ) as dated above modifies

More information

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS ICON DRILLING ABN 75 067 226 484 PURCHASE ORDER TERMS & CONDITIONS Acceptance of this offer is subject to the terms and conditions of this Agreement. Acceptance of materials, work or services, payment

More information

FOOD TRUCK APPLICATION: FOOD TRUCK FESTIVAL AT THE MOUNT JUNE 24 th & 25th FOOD TRUCK NAME: CONTACT NAME: CONTACT PHONE NUMBER: - - CONTACT STREET:

FOOD TRUCK APPLICATION: FOOD TRUCK FESTIVAL AT THE MOUNT JUNE 24 th & 25th FOOD TRUCK NAME: CONTACT NAME: CONTACT PHONE NUMBER: - - CONTACT STREET: FOOD TRUCK APPLICATION: FOOD TRUCK FESTIVAL AT THE MOUNT JUNE 24 th & 25th FOOD TRUCK NAME: CONTACT NAME: CONTACT PHONE NUMBER: - - CONTACT STREET: CITY: STATE: ZIP: CONTACT EMAIL: NATURE OF FOOD ITEMS

More information

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ]

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ] EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT IRREVOCABLE STANDBY DESIGN-BUILD LETTER OF CREDIT ISSUER PLACE FOR PRESENTATION OF DRAFT APPLICANT BENEFICIARY [ ] [Name and address of banking institution

More information

PHYSICAL THERAPY LICENSURE COMPACT

PHYSICAL THERAPY LICENSURE COMPACT 1 PHYSICAL THERAPY LICENSURE COMPACT 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 SECTION 1. PURPOSE The purpose of this Compact is to facilitate interstate practice of physical therapy with the goal of

More information

I, Accept this proposal and make a payment of $ to confirm my commitment.

I, Accept this proposal and make a payment of $ to confirm my commitment. This Solar Home Improvement Agreement (this Agreement ) is between Golden Gate Green Finance dba Golden Gate Power, California General and Electrical Contractor license number 1002922 ( Golden Gate Power,

More information

CONTRACT FOR SALE AND PURCHASE

CONTRACT FOR SALE AND PURCHASE CONTRACT FOR SALE AND PURCHASE THIS CONTRACT FOR SALE AND PURCHASE ("Agreement") is entered into on this day of, 20, by and between BROWARD COUNTY, a political subdivision of the State of Florida ("COUNTY''

More information

QUOTE DOCUMENTS FOR KING PARKING EXPANSION Forest Avenue. Des Moines, Iowa QUOTE # Q6747. Owner

QUOTE DOCUMENTS FOR KING PARKING EXPANSION Forest Avenue. Des Moines, Iowa QUOTE # Q6747. Owner QUOTE DOCUMENTS FOR KING PARKING EXPANSION 1849 Forest Avenue Des Moines, Iowa QUOTE # Q6747 Owner Des Moines Independent Community School District 1917 Dean Avenue Des Moines, Iowa 50316 DES MOINES PUBLIC

More information

Spearman, J. Paul Brecht, who publicly endorsed a King County Council

Spearman, J. Paul Brecht, who publicly endorsed a King County Council IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON PAUL BRECHT, v. Appellant, NORTH CREEK LAW FIRM, MARK LAMB and JANE DOE LAMB, Respondents. No. 65058-1-I DIVISION ONE UNPUBLISHED FILED: August 1, 2011

More information

FORM 4. RULE 26(f) REPORT (PATENT CASES) UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA

FORM 4. RULE 26(f) REPORT (PATENT CASES) UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA FORM 4. RULE 26(f REPORT (PATENT CASES UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA Name of Plaintiff CIVIL FILE NO. Plaintiff, v. RULE 26(f REPORT (PATENT CASES Name of Defendant Defendant. The

More information

CHAPTER 2 PROCUREMENT ORGANIZATION

CHAPTER 2 PROCUREMENT ORGANIZATION CHAPTER 2 PROCUREMENT ORGANIZATION 2101. Creation and Membership of the Procurement Policy Office. 2102. Duties and Responsibilities. 2103. Creation of the General Services Agency. 2104. Authority of the

More information

Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE

Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE Prufrex USA, Inc. TERMS AND CONDITIONS OF PURCHASE 1 Contract Formation: These Terms and Conditions of Purchase (the "Terms and Conditions") apply to any purchases by Prufrex USA, Inc., its subsidiaries,

More information

Linda James, v. McDonald's Corporation Readers were referred to this case on page 630

Linda James, v. McDonald's Corporation Readers were referred to this case on page 630 Linda James, v. McDonald's Corporation Readers were referred to this case on page 630 Linda James, v. McDonald's Corporation. 417 F.3d 672 U.S. Court of Appeals for the Seventh Circuit August 2, 2005 RIPPLE,

More information

TITLE VI - WATER AND SEWAGE DIVISION 3 WELLS

TITLE VI - WATER AND SEWAGE DIVISION 3 WELLS TITLE VI - WATER AND SEWAGE DIVISION 3 WELLS Chapter 1 - Wells 631-1. Purpose. 631-2. Definitions and Interpretation. 631-3. Permit Applications. 631-4. Application Procedure. 631-5. Filing Fees. 631-6.

More information

AGREEMENT FOR PHYSICIAN SERVICES RECITALS. B. The District owns and operates Hospital in, Washington (the "Hospital");

AGREEMENT FOR PHYSICIAN SERVICES RECITALS. B. The District owns and operates Hospital in, Washington (the Hospital); AGREEMENT FOR PHYSICIAN SERVICES This Agreement for Physician Services (the "Agreement") is made and entered into as of, by and between Public Hospital District No. of County, Washington (the "District"),

More information

Agreement to UOB Banker s Guarantee Terms and Conditions

Agreement to UOB Banker s Guarantee Terms and Conditions Agreement to UOB Banker s Guarantee Terms and Conditions In consideration of United Overseas Bank Limited (the Bank ) agreeing at the Applicant s request to issue the Banker s Guarantee, the Applicant

More information

GOVERNMENT CODE CHAPTER PUBLIC WORK PERFORMANCE AND PAYMENT BONDS SUBCHAPTER A. GENERAL PROVISIONS Sec DEFINITIONS.

GOVERNMENT CODE CHAPTER PUBLIC WORK PERFORMANCE AND PAYMENT BONDS SUBCHAPTER A. GENERAL PROVISIONS Sec DEFINITIONS. GOVERNMENT CODE CHAPTER 2253. PUBLIC WORK PERFORMANCE AND PAYMENT BONDS SUBCHAPTER A. GENERAL PROVISIONS Sec. 2253.001. DEFINITIONS. In this chapter: (1) "Governmental entity" means a governmental or quasi-governmental

More information

CASH MANAGEMENT SERVICES MASTER AGREEMENT

CASH MANAGEMENT SERVICES MASTER AGREEMENT This Cash Management Services Master Agreement (the Master Agreement ) and any applicable Schedules (the Master Agreement and any applicable Schedules are together referred to as the Agreement ) sets out

More information

Remote Deposit Capture Application End User License Agreement

Remote Deposit Capture Application End User License Agreement Notre Dame Federal Credit Union Remote Deposit Capture Application End User License Agreement This Remote Deposit Capture Application End User License Agreement ( Agreement ) constitutes a legal agreement

More information

ASTM Supplier s Declaration of Conformity Program Participant Agreement

ASTM Supplier s Declaration of Conformity Program Participant Agreement ASTM Supplier s Declaration of Conformity Program Participant Agreement This Agreement effective (the Effective Date), between ASTM International ( ASTM ), a Pennsylvania nonprofit corporation, having

More information

TRIBAL CODE CHAPTER 82: APPEALS

TRIBAL CODE CHAPTER 82: APPEALS TRIBAL CODE CHAPTER 82: APPEALS CONTENTS: 82.101 Purpose... 82-3 82.102 Definitions... 82-3 82.103 Judge of Court of Appeals... 82-4 82.104 Term... 82-4 82.105 Chief Judge... 82-4 82.106 Clerk... 82-4

More information

PROCUREMENT POLICIES AND PROCEDURES. BOARD OF DIRECTORS POLICY AND PROCEDURE No. BOD 014

PROCUREMENT POLICIES AND PROCEDURES. BOARD OF DIRECTORS POLICY AND PROCEDURE No. BOD 014 PROCUREMENT POLICIES AND PROCEDURES BOARD OF DIRECTORS POLICY AND PROCEDURE No. BOD 014 APPROVED BY CRRA BOARD OF DIRECTORS EFFECTIVE SEPTEMBER 24, 2009 CONTENTS 1. PREAMBLE...1 1.1 General Policy... 1

More information

INDEPENDENT CONTRACTOR TERMS OF AGREEMENT Return to the Division of Human Resources when complete. Name: Individual: Business: (mark one)

INDEPENDENT CONTRACTOR TERMS OF AGREEMENT Return to the Division of Human Resources when complete. Name: Individual: Business: (mark one) INDEPENDENT CONTRACTOR TERMS OF AGREEMENT Return to the Division of Human Resources when complete. Part One: University Information ( University or KSU) Contracting University Department/Office: Contracting

More information

MASSACHUSETTS SCHOOL BUILDING AUTHORITY FEASIBILITY STUDY AGREEMENT

MASSACHUSETTS SCHOOL BUILDING AUTHORITY FEASIBILITY STUDY AGREEMENT MASSACHUSETTS SCHOOL BUILDING AUTHORITY FEASIBILITY STUDY AGREEMENT This Feasibility Study Agreement, dated the XXXX day of XXXXXXXXXX, 20XX (the Agreement ) is between the Massachusetts School Building

More information

(129th General Assembly) (Amended Substitute House Bill Number 383) AN ACT

(129th General Assembly) (Amended Substitute House Bill Number 383) AN ACT (129th General Assembly) (Amended Substitute House Bill Number 383) AN ACT To amend section 1345.01 and to enact sections 4722.01 to 4722.04 and 4722.06 to 4722.08 of the Revised Code to make changes relative

More information

CHAPTER 18 SEWERS AND SEWAGE DISPOSAL. Part 1 Sewer Connections

CHAPTER 18 SEWERS AND SEWAGE DISPOSAL. Part 1 Sewer Connections CHAPTER 18 SEWERS AND SEWAGE DISPOSAL Part 1 Sewer Connections 101. Definitions 102. Use of Public Sewers Required 103. Building Sewers and Connections 104. Rules and Regulations Governing Building Sewers

More information

STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES

STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES JAMS STREAMLINED ARBITRATION RULES & PROCEDURES Effective JULY 15, 2009 STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES JAMS provides arbitration and mediation services from Resolution Centers

More information

We look forward to working together with you on this project and please feel free to call me at (907) if you have any questions.

We look forward to working together with you on this project and please feel free to call me at (907) if you have any questions. MATANUSKA-SUSITNA BOROUGH Department of Finance 350 East Dahlia Avenue Palmer, AK 99645 Phone (907) 745-4801 Fax (907) 745-0886 www.matsugov.us October 1, 2018 Big Lake Community Council PO Box 520931

More information

Enforcement BYLAW, ARTICLE 19

Enforcement BYLAW, ARTICLE 19 BYLAW, ARTICLE Enforcement.01 General Principles..01.1 Mission of the Enforcement Program. It is the mission of the NCAA enforcement program to uphold integrity and fair play among the NCAA membership,

More information

1.000 Development Permit Procedures and Administration

1.000 Development Permit Procedures and Administration CHAPTER 1 1.000 Development Permit Procedures and Administration 1.010 Purpose and Applicability A. The purpose of this chapter of the City of Lacey Development Guidelines and Public Works Standards is

More information

PN /19/2012 DISPUTE RESOLUTION BOARD PROCESS

PN /19/2012 DISPUTE RESOLUTION BOARD PROCESS PN 108 10/19/2012 DISPUTE RESOLUTION BOARD PROCESS The Department s Dispute Resolution Board Process is based upon the partnering approach to construction administration and must be followed by the Contractor

More information

BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF COMMERCE, TEXAS:

BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF COMMERCE, TEXAS: ORDINANCE NO. AN ORDINANCE GRANTING TO FARMERS ELECTRIC COOPERATIVE,INC., ITS SUCCESSORS AND ASSIGNS, AN ELECTRIC POWER FRANCHISE TO USE THE PRESENT AND FUTURE STREETS, ALLEYS, HIGHWAYS, PUBLIC UTILITY

More information

LISTING AGREEMENT STANDARD TERMS AND CONDITIONS Date: March 1, 2016

LISTING AGREEMENT STANDARD TERMS AND CONDITIONS Date: March 1, 2016 LISTING AGREEMENT STANDARD TERMS AND CONDITIONS Date: March 1, 2016 ARTICLE 1 Definition 1.1 Definitions. In this Agreement, the following words shall have the following meanings: Agreement means this

More information