The Commencement Date was 1/1/14 and the Time for Completion was 18 months.

Size: px
Start display at page:

Download "The Commencement Date was 1/1/14 and the Time for Completion was 18 months."

Transcription

1 Scenario for Edinburgh Working Weekend WorldTech is a multinational IT corporation. It entered into a contract with ConstructIT for the construction of a key next-generation datacentre facility in North Cyprus. The contract is the FIDIC Yellow Book with minimal amendment. The law clause said:- Owing to WorldTech s anti-national world view, the applicable law will be the best features of the civil, common law and other legal systems so as to reflect the intentions of the parties and achieve justice between them. The Commencement Date was 1/1/14 and the Time for Completion was 18 months. The following events occurred:- 1 ConstructIT had problems with an insolvent subcontractor (SubmIT) and work on the principal building halted for a period of 5 months from 15 June to 15 November 2014 while a new subcontractor (NepIT) was found and mobilised. Work then resumed. 2 Global Specification update #1 was issued in month 16 and added 5 months work to subsidiary buildings which were originally non-critical and programmed to finish in month Completion of the facilities was achieved on the last day of month Connection of the buildings to WorldTech s Haptic WorldWeb could not take place until month 24 due to delays in its development by WorldTech. 5 ConstructIT claimed four months EOT and prolongation cost in accordance with the Contract. The Engineer s determination refused any EOT or cost. 6 WorldTech claimed five months delay damages, specified at 0.2% per day. They also claimed the removal of the 10% cap because SubmIT s administrator has filed papers showing that they could have returned to work within a month of the insolvency under re-structuring plans but ContractIT elected to negotiate a new subcontract with NepIT, a company belonging to the son of the ContractIT MD. 7 ConstructIT have produced an internal WorldTech document from tender stage which shows that no profits were anticipated until 2017; further that WorldTech had secured deals whereby rent on the facility site only became payable once they were connected. The parties agreed that their disputes should be resolved by arbitration in front of a panel of arbitrators from multiple jurisdictions. At the arbitration hearing, there is no dispute as to facts. The Arbitrators have issued directions for the hearing as follows:- 1 Evidence will be heard from programming experts on the EOT question and practice around the world. 2 Counsel will then address the following questions What EOT is due, if any? Should the 10% cap on delay damages be removed? The argument that there is no loss and no or reduced delay damages payable. 1

2 Month As-Planned Schedule Path A Datacentre 0 months float Contract completion date Activity Critical Activity As-Built Owner Delay Contractor Delay Path B Subsidiary Building +1 month float Schedule Update Month 16 ConstructIT insolvent subcontractor Path A Datacentre -5 months float Path B Subsidiary Building WorldTechadds 5 months of work to Subsidiary Building -4 months float As-Built Schedule 5 months Path A Datacentre Path B Subsidiary Building 2

3 Extracts from FIDIC Yellow Book Extension of Time for Completion 8.4 The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor s Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking Over of the Works and Sections] is or will be delayed by any of the following causes: (a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-Clause 13.3 [Variation Procedure]), (b) a cause of delay giving an entitlement to extension of time under a Sub- Clause of these Conditions, (c) exceptionally adverse climatic conditions, (d) Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions, or (e) any delay, impediment or prevention caused by or attributable to the Employer, the Employer s Personnel, or the Employer s other contractors on the Site. If the Contractor considers himself to be entitled to an extension of the Time for Completion, the Contractor shall give notice to the Engineer in accordance with Sub-Clause 20.1 [Contractor s Claims]. When determining each extension of time under Sub-Clause 20.1, the Engineer shall review previous determinations and may increase, but shall not decrease, the total extension of time. Delay Damages 8.7 If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor shall subject to Sub-Clause 2.5 [Employer s Claims] pay delay damages to the Employer for this default. These delay damages shall be the sum stated in the Appendix to Tender, which shall be paid for every day which shall elapse between the relevant Time for Completion and the date stated in the Taking-Over Certificate. However, the total amount due under this Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the Appendix to Tender. These delay damages shall be the only damages due from the Contractor for such default, other than in the event of termination under Sub-Clause 15.2 [Termination by Employer] prior to completion of the Works. These damages shall not relieve the Contractor from his obligation to complete the Works, or from any other duties, obligations or responsibilities which he may have under the Contract. 3

4 Limitation of Liability 17.6 Neither Party shall be liable to the other Party for loss of use of any Works, loss of profit, loss of any contract or for any indirect or consequential loss or damage which may be suffered by the other Party in connection with the Contract, other than under Sub-Clause 16.4 [Payment on Termination] and Sub-Clause 17.1 [Indemnities]. The total liability of the Contractor to the Employer, under or in connection with the Contract other than under Sub-Clause 4.19 [Electricity, Water and Gas], Sub- Clause 4.20 [Employer s Equipment and Free-Issue Material], Sub-Clause 17.1 [Indemnities] and Sub-Clause 17.5 [Intellectual and Industrial Property Rights], shall not exceed the sum stated in the Particular Conditions or (if a sum is not so stated) the Accepted Contract Amount. This Sub-Clause shall not limit liability in any case of fraud, deliberate default or reckless misconduct by the defaulting Party. 4

5 Brazilian Civil Code, Art. 409 A penalty clause that is stipulated with an obligation, or in a later act, may refer to the complete non-performance of the obligation, to a specific clause or to a mere delay in performance. Brazilian Civil Code, Art. 410 A penalty clause that is established in case of total default on an obligation will give the non-breaching party an option to claim performance of the obligation or payment of the amount stipulated in the penalty clause. Brazilian Civil Code, Art. 411 When the penalty clause is established in case of delay, or in special security of another specific clause, the innocent party has the discretion to demand the fulfillment of the penalty imposed, together with the performance of the primary obligation. Brazilian Civil Code, Art. 412 The amount of the penalty imposed in the penalty clause may not exceed the amount of the primary obligation. Brazilian Civil Code, Art. 413 The penalty shall be equitably reduced by the court if the primary obligation has been partially fulfilled or if the amount of the penalty is manifestly excessive, in view of the nature and purpose of the transaction. Brazilian Civil Code, Art. 416 An innocent party is not required to proof any loss to claim a contractual penalty. Brazilian Civil Code, Art. 416, Sole Paragraph Even if the damage exceeds what was provided for in the penalty clause, the innocent party may not claim additional indemnity if it has not been contracted so. If it has been contracted, the penalty remains as minimum indemnity, and the innocent party is responsible for proving further damage. Brazilian Civil Code, Art. 945 If the innocent party has, by its own fault, concurrent caused the damages incurred by it, its indemnification shall be calculated considering the level/severity of its fault in comparison with the fault of the non-innocent party. 5

6 UAE Civil Code Article 290:- It shall be permissible for the judge to reduce the level by which an act has to be made good or to order that it need not be made good if the person suffering harm participated by his own act in bringing about or aggravating the damages. Article 386:- If it is impossible for an obligor to give specific performance of an obligation, he shall be ordered to pay compensation for non-performance of his obligation, unless it is proved that the impossibility of performance arose out of an external cause in which (the obligor) played no part. The same shall apply in the event that the obligor defaults in the performance of his obligation. Article 389:- If the amount of compensation is not fixed by law or by the contract, the judge shall assess it in an amount equivalent to the damage in fact suffered at the time of the occurrence thereof Article 390:- (1) The contracting parties may fix the amount of compensation in advance by making a provision therefor in the contract or in a subsequent agreement, subject to the provisions of the law. (2) The judge may in all cases, upon the application of either of the parties, vary such agreement so as to make the compensation equal to the loss, and any agreement to the contrary shall be void. Under the UAE law, in order for liquidated damages to be awarded, the following requirements must be satisfied (failing which, no liquidated damages would be awarded): A) A breach committed by the party who agreed to pay the liquidated damages; B) Actual damage sustained by the party who invokes the liquidated damages clause ; and C) A causative link between the fault and the damage suffered. (The UAE high courts have confirmed, in several occasions, that this tripartite test must be satisfied. The Dubai Court of Cassation held that the inclusion of a liquidated damages clause into a contract does not supersede this tripartite test for awarding damages. The Federal Supreme Court has also concluded that the liquidated damages are subject to this tripartite test). Article 246: a contract must be performed in accordance with its contents, and in a manner consistent with the requirements of good faith". Decisions of the Dubai Court of Cassation have ruled that a bad faith action of the other contracting party may provide a cause of action in itself for the other. The effect of good faith on the terms of a contract is, therefore, wide reaching and may have a significant impact on the outcome of a dispute. (Article 246 duty of good faith is has been interpreted by courts to have wide reaching implications and not limited to obligations expressly contained in the contract between the parties, but also extends to obligations connected to such contracts by virtue of law, custom and the nature of the transaction. In general terms it means that the parties must not seek unfair advantage or exploit the other, must cooperate, and if possible, avoid conflicts). 1 6

7 Article 472:- The right shall expire if the obligor proves that the performance of it has become impossible for him for an extraneous cause in which he played no part. 2 7

8 PRESS SUMMARY 4 November 2015 Cavendish Square Holding BV (Appellant) v Talal El Makdessi (Respondent); ParkingEye Limited (Respondent) v Beavis (Appellant) [2015] UKSC 67 On appeal from [2012] EWCA Civ 3852 Comm, [2013] EWCA Civ 1539 and [2015] EWCA Civ 402 JUSTICES: Lord Neuberger (President), Lord Mance, Lord Clarke, Lord Sumption, Lord Carnwath, Lord Toulson and Lord Hodge BACKGROUND TO THE APPEALS Cavendish v El Makdessi By an agreement, Mr Makdessi agreed to sell to Cavendish a controlling stake in the holding company of the largest advertising and marketing communications group in the Middle East. The contract provided that if he was in breach of certain restrictive covenants against competing activities, Mr Makdessi would not be entitled to receive the final two instalments of the price paid by Cavendish (clause 5.1) and could be required to sell his remaining shares to Cavendish, at a price excluding the value of the goodwill of the business (clause 5.6). Mr Makdessi subsequently breached these covenants. Mr Makdessi argued that clauses 5.1 and 5.6 were unenforceable penalty clauses. The Court of Appeal, overturning Burton J at first instance, held that the clauses were unenforceable penalties under the penalty rule as traditionally understood. ParkingEye v Beavis ParkingEye Ltd agreed with the owners of the Riverside Retail Park to manage the car park at the site. ParkingEye displayed numerous notices throughout the car park, saying that a failure to comply with a two hour time limit would result in a Parking Charge of 85. On 15 April 2013, Mr Beavis parked in the car park, but overstayed the two hour limit by almost an hour. ParkingEye demanded payment of the 85 charge. Mr Beavis argued that the 85 charge was unenforceable at common law as a penalty, and/or that it was unfair and unenforceable by virtue of the Unfair Terms in Consumer Contracts Regulations The Court of Appeal upheld the first instance decision rejecting those arguments. JUDGMENT The Supreme Court allows the appeal in Cavendish v El Makdessi and dismisses the appeal in ParkingEye v Beavis, thus upholding the validity of the disputed clauses in both cases. Lord Neuberger and Lord Sumption give a joint judgment, with which Lord Clarke and Lord Carnwath agree. Lord Mance and Lord Hodge write concurring judgments. Lord Toulson agrees that the appeal in Cavendish v El Makdessi should be allowed but dissents in ParkingEye v Beavis. REASONS FOR THE JUDGMENT The Legal Principles The penalty rule is an ancient, haphazardly constructed edifice which has not weathered well [3]. However, it is of long standing and a similar rule exists in all other developed systems of law. It also covers types of contract which are not regulated in any other way. It should not therefore be abolished, but neither should it be extended [36-40]. The fundamental principle is that the penalty rule regulates only the contractual remedy available for the breach of primary contractual obligations, and not the fairness of those primary obligations The Supreme Court of the United Kingdom Parliament Square London SW1P 3BD T: /1887 F:

9 themselves [13]. The relevant contractual remedy typically stipulates payment of money, but it equally applies to obligations to transfer assets, or clauses where one party forfeits a deposit following its own breach of contract [14-18]. What makes a contractual provision penal? Lord Dunedin s tests in Dunlop Pneumatic Tyre Company Ltd. v New Garage and Motor Company Ltd. [1915] AC 79 have too often been treated as a code. The speeches of the rest of the Appellate Committee, particularly Lord Atkinson, are at least as important. The validity of a clause providing for the consequences of a breach of contract depends on whether the innocent party can be said to have a legitimate interest in the enforcement of the clause. There is a legitimate interest in the recovery of a sum constituting a reasonable pre-estimate of damages, but the innocent party may have a legitimate interest in performance which extends beyond the recovery of pecuniary compensation. The law will not generally uphold a contractual remedy where the adverse impact of that remedy significantly exceeds the innocent party s legitimate interest [18-30]. The concepts of deterrence and genuine pre-estimate of loss are unhelpful. The true test is whether the impugned provision is a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation [32]. Lord Mance agrees with that test. The first step is to consider whether any (and if so what) legitimate business interest is served and protected by the clause, and if so and secondly, whether the provision made for that interest is extravagant, exorbitant or unconscionable [152]. The penalty doctrine has been applied to clauses withholding payments, and transfers of moneys worth [ ], and may be considered alongside relief against forfeiture [161]. It should not be abolished or restricted: its existence is justified by its longstanding invocation and endorsement in the United Kingdom, Europe and across common law jurisdictions [ ]. Lord Hodge concurs, reviewing the authorities from England and Scotland and the historical development of the doctrine in Scots law. The doctrine only applies to secondary obligations arising out of a breach of contract, but is not confined to cases requiring the payment of money on breach. It applies to clauses withholding payments on breach, clauses requiring the party in breach to transfer property, and clauses requiring payment of a non-refundable deposit if that deposit is not reasonable as earnest money (particularly where such a clause exceeds the percentage set by long-established practice) [ ]. The test is whether the sum or remedy stipulated as a consequence of a breach of contract is exorbitant or unconscionable when regard is had to the innocent party s interest in the performance of the contract. A clause fixing a level of damages payable on breach will be a penalty if there is an extravagant disproportion between the stipulated sum and the highest level of damages that could possibly arise from the breach [255]. Lord Toulson agrees with Lord Hodge s formulation of the test above, and with Lord Mance and Lord Hodge on the relationship between penalty and forfeiture clauses [294]. Application to Cavendish v El Makdessi The court concludes that neither clause 5.1 nor clause 5.6 are unenforceable penalty clauses, and accordingly allows the appeal. Clause 5.1 is a price adjustment clause. It is not a secondary provision but a primary obligation. The Sellers earn consideration for their shares by (amongst other things) observing the restrictive covenants. Whilst clause 5.1 has no relationship with the measure of loss attributable to the breach, Cavendish also had a legitimate interest in the observance of the restrictive covenants, in order to protect the goodwill of the Group generally. The goodwill of the business was critical to Cavendish and the loyalty of Mr Makdessi was critical to the goodwill. The court cannot assess the precise value of that obligation or determine how much less Cavendish would have paid for the business without the benefit of the restrictive covenants. The parties were the best judges of how it should be reflected in their agreement [73-75]. The Supreme Court of the United Kingdom Parliament Square London SW1P 3BD T: /1887 F:

10 A very similar analysis applies to clause 5.6. It is also a primary obligation, and it could not be treated as invalid without rewriting the contract [83-88]. It was said to be penal because the formula excluded goodwill from the calculation of the payment price. It did not represent the estimated loss attributable to the breach. But it reflected the reduced consideration which Cavendish would have been prepared to pay for the acquisition of the business on the hypothesis that they could not count on the loyalty of Mr Makdessi [79-83]. Lord Mance, Lord Hodge and Lord Toulson concur on both clause 5.1 and clause 5.6 [ ; ; 292]. Application to ParkingEye v Beavis The court dismisses the appeal by a majority of six to one, and declares that the charge does not contravene the penalty rule, or the Unfair Terms in Consumer Contracts Regulations Mr Beavis had a contractual licence to park in the car park on the terms of the notice posted at the entrance, including the two hour limit. The 85 was a charge for contravening the terms of the contractual licence. This is a common scheme, subject to indirect regulation by statute and the British Parking Association s Code of Practice. The charge had two main objects: (i) the management of the efficient use of parking space in the interests of the retail outlets and their users by deterring long-stay or commuter traffic, and (ii) the generation of income in order to run the scheme [94-98]. Unlike in Cavendish v El Makdessi, the penalty rule is engaged. However, the 85 charge is not a penalty. Both ParkingEye and the landowners had a legitimate interest in charging overstaying motorists, which extended beyond the recovery of any loss. The interest of the landowners was the provision and efficient management of customer parking for the retail outlets. The interest of ParkingEye was in income from the charge, which met the running costs of a legitimate scheme plus a profit margin [99]. Further, the charge was neither extravagant nor unconscionable, having regard to practice around the United Kingdom, and taking into account the use of this particular car park and the clear wording of the notices [ ]. The result is the same under the 1999 Regulations. Although the charge may fall under the description of potentially unfair terms at para. 1(e) of Schedule 2, it did not come within the basic test for unfairness in Regulations 5 and 6(1), as that test has been recently interpreted by the Court of Justice in Luxembourg [ ]. Any imbalance in the parties rights did not arise contrary to the requirements of good faith, because ParkingEye and the owners had a legitimate interest in inducing Mr Beavis not to overstay in order to efficiently manage the car park for the benefit of the generality of users of the retail outlets. The charge was no higher than was necessary to achieve that objective. Objectively, the reasonable motorist would have, and often did, agree to the charge [ ]. Lord Mance and Lord Hodge both concur [ ; ]. Lord Toulson (dissenting) would have allowed the appeal, on the grounds that the clause infringes the 1999 Regulations, which reflect the special protection afforded to consumers under the European Directive on unfair terms in consumer contracts. The burden is on the supplier to show that the consumer would have agreed to the terms in individual negotiations on level terms. It is not reasonable to make that assumption in this case, and in any event ParkingEye had not produced sufficient evidence to that effect [ ]. References in square brackets are to paragraphs in the judgment NOTE This summary is provided to assist in understanding the Court s decision. It does not form part of the reasons for the decision. The full judgment of the Court is the only authoritative document. Judgments are public documents and are available at: 10 The Supreme Court of the United Kingdom Parliament Square London SW1P 3BD T: /1887 F:

Penalty Clauses: What is left? Jonathan Owen

Penalty Clauses: What is left? Jonathan Owen Penalty Clauses: What is left? Jonathan Owen The history of the issue 1. Every undergraduate law student has had to grapple with the common law rule against penalty clauses in contracts, in the sense of

More information

Differences between the Civil and Common Law: Part 2: Delay Damages and Taking-Over. Cremona Cotovelea Nina Tsaturova Jeremy Glover

Differences between the Civil and Common Law: Part 2: Delay Damages and Taking-Over. Cremona Cotovelea Nina Tsaturova Jeremy Glover Differences between the Civil and Common Law: Part 2: Delay Damages and Taking-Over Cremona Cotovelea Nina Tsaturova Jeremy Glover Sub-Clause 10.1: Taking Over The Engineer shall, within 28 days after

More information

Enforceability of take-or-pay provisions in English law contracts resolved

Enforceability of take-or-pay provisions in English law contracts resolved Journal of Energy & Natural Resources Law, 2016 http://dx.doi.org/10.1080/02646811.2016.1164554 Enforceability of take-or-pay provisions in English law contracts resolved Ben Holland is a partner in the

More information

Penalty Clauses under Brazilian Law: Is there a common ground with the criteria set forth by Cavendish Square v. Makdessi?

Penalty Clauses under Brazilian Law: Is there a common ground with the criteria set forth by Cavendish Square v. Makdessi? Penalty Clauses under Brazilian Law: Is there a common ground with the criteria set forth by Cavendish Square v. Makdessi? Thiago Moreira Caio Lucas Gabra 1. Introduction Although extensively debated by

More information

Before : - and

Before : - and Neutral Citation Number: [2015] EWCA Civ 402 Case No: B2/2014/2010 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE COUNTY COURT AT CHELMSFORD His Honour Judge Moloney Q.C. Claim No. 3JD05152

More information

Delays. Dr. Mohammad S. El-Mashaleh. Delays

Delays. Dr. Mohammad S. El-Mashaleh. Delays Delays 1 Delays A delay is the time during which some part of the construction project has been extended or not performed due to an unanticipated (or anticipated) circumstance May be caused by any of the

More information

UK: Engineering, Procurement & Construction Briefing

UK: Engineering, Procurement & Construction Briefing UK: Engineering, Procurement & Construction Briefing May 2013 Contents Introduction 01 Liquidated damages vs penalty 01 causes a clear cut dichotomy? Varying the construction methods 03 to catch up how

More information

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE CIV [2018] NZHC HOBSON STREET LIMITED First Defendant

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE CIV [2018] NZHC HOBSON STREET LIMITED First Defendant IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE BETWEEN CIV 2016-404-2940 [2018] NZHC 32 HONEY BEES PRESCHOOL LIMITED First Plaintiff JASON JAMES Second

More information

GENERAL CONDITIONS OF THE CONTRACT (Applicable to purchase orders)

GENERAL CONDITIONS OF THE CONTRACT (Applicable to purchase orders) GENERAL CONDITIONS OF THE CONTRACT (Applicable to purchase orders) ARTICLE 1 PERFORMANCE OF THE CONTRACT 1.1. The Contractor shall perform the Contract to the highest professional standards. The Contractor

More information

Oil & Gas JOA Defaults: Enforcing Forfeiture Clauses after the Cavendish Square Decision

Oil & Gas JOA Defaults: Enforcing Forfeiture Clauses after the Cavendish Square Decision Oil & Gas JOA Defaults: Enforcing Forfeiture Clauses after the Cavendish Square Decision February 2016 The continuing decline in oil & gas prices has led to increasing numbers of defaults under oil & gas

More information

General Conditions of CERN Contracts

General Conditions of CERN Contracts ORGANISATION CERN/FC/5312-II/Rev. EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH General Conditions of CERN Contracts CERN/FC/6211/II- Original: English/French 14

More information

Software Licence Agreement

Software Licence Agreement @tesseract.co.uk HP12 3RE United Kingdom Software Licence Agreement Cranbox Limited T/A Tesseract 1. Licence 1.1 We hereby grant you a non-exclusive, non-transferable and limited license for the term of

More information

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules

More information

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - Background I practice in the building and construction industry as a mediator and conciliator, assisting contracted parties in

More information

LFMI MEDIA SERVICES LIMITED T/A RUE POINT MEDIA

LFMI MEDIA SERVICES LIMITED T/A RUE POINT MEDIA Dated: September 2017 LFMI MEDIA SERVICES LIMITED T/A RUE POINT MEDIA TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES 1. INTERPRETATION 1.1 THE FOLLOWING DEFINITIONS AND RULES OF INTERPRETATION APPLY IN

More information

TERMS AND CONDITIONS. V6 (15 December 2017) 2017 Intercontinental Exchange, Inc. 1 of 6

TERMS AND CONDITIONS. V6 (15 December 2017) 2017 Intercontinental Exchange, Inc. 1 of 6 TERMS AND CONDITIONS 1. AGREEMENT AND DEFINED TERMS (a) The terms of this agreement (this Agreement ) consist of: (1) these Terms and Conditions; (2) an order form making reference to these Terms and Conditions

More information

SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY

SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY THIS SUPPLY AGREEMENT (the Agreement ) is made on the applicable dates

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS This Contract comprises the Sales Confirmation overleaf and these terms and conditions to the exclusion of all other terms and conditions (including any terms or conditions which Buyer purports to apply

More information

MINOR SERVICES AGREEMENT FORM

MINOR SERVICES AGREEMENT FORM Agreement Title: Agreement for Agreement Date: Contractor: Address: This Agreement is comprised of: (i) (ii) (iii) (iv) the Minor Services Schedule 1 Special Conditions; Schedule 2 Terms and Conditions;

More information

Lunch & Learn Liquidated Damages Best Practice Alistair Maughan 10 February 2014 Morrison & Foerster (UK) LLP

Lunch & Learn Liquidated Damages Best Practice Alistair Maughan 10 February 2014 Morrison & Foerster (UK) LLP Lunch & Learn Liquidated Damages Best Practice Alistair Maughan 10 February 2014 Morrison & Foerster (UK) LLP 2013 Morrison & Foerster (UK) LLP All Rights Reserved mofo.com Lunch & Learn 2 nd Monday of

More information

Decennial Liability in Construction: Law and practice in the United Arab Emirates

Decennial Liability in Construction: Law and practice in the United Arab Emirates Decennial Liability in Construction: Law and practice in the United Arab Emirates Professor Aymen Masadeh The British University in Dubai aymen.masadeh@buid.ac.ae Abstract Decennial liability arises in

More information

Reigning Supreme: Events at the UK Supreme Court in 2015

Reigning Supreme: Events at the UK Supreme Court in 2015 Reigning Supreme: Events at the UK Supreme Court in 2015 Dickson, B. (2016). Reigning Supreme: Events at the UK Supreme Court in 2015. New Law Journal, 166, 19-20. Published in: New Law Journal Document

More information

Oasys Software Licence and Support Agreement

Oasys Software Licence and Support Agreement Last updated 21 st December 2015 Oasys Software Licence and Support Agreement This Software Licence and Support Agreement ( Agreement ) is a legal agreement between you, either an individual or an entity,

More information

Time and Construction Contracts

Time and Construction Contracts Time and Construction Contracts Extensions of Time and the Prevention Principle By Nathan Abbott Introduction The purpose of this paper is to expose and consider the Prevention Principle from a practical

More information

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied.

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied. CITY UNIVERSITY OF HONG KONG Breach and Remedy Refer to Richards, P. Law of Contract Chapters 16-18 Uff, J. Construction Law 9 th Edition Chapter 9 BREACH OF CONTRACT A breach of contract occurs where

More information

36 month Software User Licence Agreement

36 month Software User Licence Agreement 36 month Software User Licence Agreement Boris Software Ltd, This licence agreement (Licence) is a legal agreement between you (Licensee or you) and Boris Software Limited whose registered office is situated

More information

Freeview AERIAL INSTALLER TRADE MARK LICENCE CAI Registered Installers. THIS LICENCE dated is made BETWEEN:

Freeview AERIAL INSTALLER TRADE MARK LICENCE CAI Registered Installers. THIS LICENCE dated is made BETWEEN: Freeview AERIAL INSTALLER TRADE MARK LICENCE CAI Registered Installers THIS LICENCE dated is made BETWEEN: a company incorporated under the laws of with company registration no. whose principal office

More information

Exact Online Additional App Center Partner Terms

Exact Online Additional App Center Partner Terms Exact Online Additional App Center Partner Terms Revised version November 2018 Despite the continued efforts of Exact to ensure that the information in this document is as complete and up-to-date as possible,

More information

Terms of Business

Terms of Business Terms of Business Terms of Business PLEASE NOTE: These terms of business govern the relationship between You as a Buyer or Supplier respectively and Us as a provider of Services to You in your capacity

More information

Terms of Use for Forestry Commission Spatial Data

Terms of Use for Forestry Commission Spatial Data Terms of Use for Forestry Commission Spatial Data The Forestry Commission creates (or derives) and then publishes a range of information and data. These Terms of Use (ToU) set out how this information

More information

Agreement to UOB Banker s Guarantee Terms and Conditions

Agreement to UOB Banker s Guarantee Terms and Conditions Agreement to UOB Banker s Guarantee Terms and Conditions In consideration of United Overseas Bank Limited (the Bank ) agreeing at the Applicant s request to issue the Banker s Guarantee, the Applicant

More information

Effective Date means the date on which the Licensee first downloads and/or uses all or any part of the Software;

Effective Date means the date on which the Licensee first downloads and/or uses all or any part of the Software; NC SQUARED LIMITED END USER LICENCE AGREEMENT Please read this End User Licence Agreement ( Licence Agreement ) carefully. By downloading and/or using all or any part of the Software, you ( Licensee )

More information

STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS. 1. Application

STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS. 1. Application STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS 1. Application The Buyer orders and the Supplier, by accepting the Order, agrees that it will supply the Goods specified and subject to these Conditions

More information

3. Avoidance of certain provisions in agreements. 9. Restriction on recovery of goods otherwise than by action.

3. Avoidance of certain provisions in agreements. 9. Restriction on recovery of goods otherwise than by action. ARRANGEMENT OF SECTIONS Preliminary SECTION HIRE PURCHASE ACT 1. Transactions regulated by this Act. Operation and termination of agreements, etc. 2. Requirements relating to hire purchase and credit sale

More information

FINAL SUPPLY CHAIN SOLUTION LTD TERMS AND CONDITIONS FOR THE SUPPLY OF LOGISTICS SERVICES

FINAL SUPPLY CHAIN SOLUTION LTD TERMS AND CONDITIONS FOR THE SUPPLY OF LOGISTICS SERVICES SUPPLY CHAIN SOLUTION LTD TERMS AND CONDITIONS FOR THE SUPPLY OF LOGISTICS SERVICES Supply Chain Solution Ltd is not a common carrier and only accepts goods for carriage and/or storage on that condition

More information

EIS. Terms and Conditions. Tel: Fax: EIS

EIS. Terms and Conditions.  Tel: Fax: EIS EIS Terms and Conditions www.eisit.uk info@eisit.uk Tel: 0300 065 8800 Fax: 01622 663591 EIS The Shepway Centre, Oxford Road, Maidstone, Kent, ME15 8AW 1. Definitions and Interpretation 1.1. In this Contract

More information

Conditions of Contract for Purchase of Goods and Services

Conditions of Contract for Purchase of Goods and Services Conditions of Contract for Purchase of Goods and Services DOCUMENT GOVERNANCE Policy Owner Head of Procurement Effective date 1 March 2017 This policy will be reviewed every six months. CONTENTS 1. DEFINITIONS

More information

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:-

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:- Clause 10 Summary Clause 10 deals with the Taking-Over of the Works, Sections, or parts of the Works. Sub-Clause 10.1 deals with the Taking-Over of the Works and Sections. Taking-Over by the Employer happens

More information

PROFESSIONAL SERVICES AGREEMENT

PROFESSIONAL SERVICES AGREEMENT DATED 2006 (1) PROFIT THROUGH CHANGE LIMITED (2) - and - PROFESSIONAL SERVICES AGREEMENT CONTENTS 1. DEFINITIONS AND INTERPRETATION...1 2. COMMENCEMENT AND DURATION...2 3. PROVISION OF SERVICES...2 4.

More information

IES Commercial EULA. This licence should be used for any new commercial users of the VE Pro (including Gaia software) i.e. after 11 April 2011.

IES Commercial EULA. This licence should be used for any new commercial users of the VE Pro (including Gaia software) i.e. after 11 April 2011. IES Commercial EULA This licence should be used for any new commercial users of the VE Pro (including Gaia software) i.e. after 11 April 2011. INTEGRATED ENVIRONMENTAL SOLUTIONS LIMITED STANDARD LICENCE

More information

Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.

Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Geldbach UK Ltd The customer's attention is drawn in particular to the provisions of clause 9. 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: Business Day: a day

More information

1. General. 2. Right of Use

1. General. 2. Right of Use 1. General 1.1. These General Terms and Conditions of Service ( T&C ) together with the Service Order and any Additional Terms (as defined in the Service Order), if any, constitute the entire Agreement

More information

Banking & Financial Services Law Association Conference 29 August Judicial Case Law Update - Australia. Justice Ashley Black

Banking & Financial Services Law Association Conference 29 August Judicial Case Law Update - Australia. Justice Ashley Black Banking & Financial Services Law Association Conference 29 August 2016 Judicial Case Law Update - Australia Justice Ashley Black Supreme Court of New South Wales I will spend about half of the paper on

More information

Website Development Agreement

Website Development Agreement Website Development Agreement This WEB SITE DEVELOPMENT AGREEMENT ("Agreement") is an agreement between Lotta Digital (Lotta Digital is a registered name of Qikmo Technology Inc.) ("Company") and the party

More information

The person, group or company identified in the accompanying and recorded in the online shop (the "User").

The person, group or company identified in the accompanying  and recorded in the online shop (the User). TRIAL SUBSCRIPTION LICENCE between HISTORIC ENVIRONMENT SCOTLAND, a statutory incorporation established by the Historic Environment Scotland Act 2014, and a registered charity (Scottish Charity number

More information

Licence shall mean the terms and conditions for use of the Software as set out in this Agreement.

Licence shall mean the terms and conditions for use of the Software as set out in this Agreement. Octopus Deploy End User Licence Agreement Important notice please read carefully before installing the software: this licence agreement ("Agreement") is a legal agreement between you ("Licensee", "You"

More information

CAROUSEL TERMS AND CONDITIONS

CAROUSEL TERMS AND CONDITIONS CAROUSEL TERMS AND CONDITIONS 1 Our Contract with you 1.1 We are Carousel Logistics Limited, incorporated and registered in England and Wales with company number 01908712, our registered office is c/o

More information

LORDS AMENDMENTS TO THE ENTERPRISE AND REGULATORY REFORM BILL

LORDS AMENDMENTS TO THE ENTERPRISE AND REGULATORY REFORM BILL LORDS AMENDMENTS TO THE ENTERPRISE AND REGULATORY REFORM BILL [The page and line references are to HL Bill 45, the bill as first printed for the Lords.] Clause 1 1 Page 1, line 10, leave out subsection

More information

Before : His Honour Judge Bird Sitting as a Judge of this Court. Between: -and- Hearing dates: 11 December Approved Judgment

Before : His Honour Judge Bird Sitting as a Judge of this Court. Between: -and- Hearing dates: 11 December Approved Judgment IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION MANCHESTER DISTRICT REGISTRY MERCANTILE COURT Case No: BA40MA109 Date: 19 January 2016 Before : His Honour Judge Bird Sitting as a Judge of this Court

More information

incorporate, or which are implied by trade, custom, practice or course of dealing.

incorporate, or which are implied by trade, custom, practice or course of dealing. CUSTOMER TERMS AND CONDITIONS 1. INTERPRETATION 1.1 Definitions. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Conditions: the terms

More information

Lumiere London Limited Terms & Conditions

Lumiere London Limited Terms & Conditions Lumiere London Limited Terms & Conditions Date: 07/09/2016 Lumiere London Limited - Terms & Conditions 1. INTERPRETATION 1.1 Definitions. In these Terms & Conditions, the following definitions apply: Business

More information

Client Service Agreement

Client Service Agreement Payleadr Pty. Ltd. ACN 615 881 162 Client Service Agreement Date: 01/05/2018 This Agreement is an agreement between Payleadr Pty Ltd ACN 615 881 162 (we, us) and you (being the entity requesting our Services

More information

GLOBAL-ROAM SOFTWARE LICENCE AGREEMENT 1) LICENCE

GLOBAL-ROAM SOFTWARE LICENCE AGREEMENT 1) LICENCE GLOBAL-ROAM SOFTWARE LICENCE AGREEMENT This is a legal Agreement between GLOBAL-ROAM Pty Ltd (ACN 091 533 587) and the Licensee for the use of the Software. By ordering, downloading, installing, or using

More information

Client Order Routing Agreement Standard Terms and Conditions

Client Order Routing Agreement Standard Terms and Conditions Client Order Routing Agreement Standard Terms and Conditions These terms and conditions apply to the COR Form and form part of the Client Order Routing agreement (the Agreement ) between: Cboe Chi-X Europe

More information

Trócaire General Terms and Conditions for Procurement

Trócaire General Terms and Conditions for Procurement Trócaire General Terms and Conditions for Procurement Version 1 February 2014 1. Contractors Obligations 1.1 The Contractor undertakes to perform its obligations arising from this Agreement with due care,

More information

PARKING EYE LIMITED. BARRY BEAVIS Defendant (Claim - 152) MARTIN WARDLEY Defendant (Claim -169)

PARKING EYE LIMITED. BARRY BEAVIS Defendant (Claim - 152) MARTIN WARDLEY Defendant (Claim -169) IN THE COUNTY COURT AT CAMBRIDGE Claims Nos 3JD05152 / 3DJ05169 HHJ MOLONEY QC PARKING EYE LIMITED Claimant And BARRY BEAVIS Defendant (Claim - 152) MARTIN WARDLEY Defendant (Claim -169) Jonathan Kirk

More information

Affiliate Partnership Terms & Conditions

Affiliate Partnership Terms & Conditions Affiliate Partnership Terms & Conditions FXCC PROVIDES THE FOLLOWING: 1. WHEREAS the Affiliate is entitled to refer new clients to the Company subject to the terms and conditions of the present agreement;

More information

a) " Agreement " means the agreement between B.C. Ltd dba Edge Telecom Consultants and Customer which is composed of:

a)  Agreement  means the agreement between B.C. Ltd dba Edge Telecom Consultants and Customer which is composed of: 1. Definitions In this agreement, the following capitalized words have the following meanings: a) " Agreement " means the agreement between 0997473 B.C. Ltd dba Edge Telecom Consultants and Customer which

More information

Penalty Clauses What Has Changed?

Penalty Clauses What Has Changed? Pace International Law Review Volume 30 Issue 1 Winter 2017 Article 4 December 2017 Penalty Clauses What Has Changed? Bruno Zeller University of Western Australia, Law School Follow this and additional

More information

March 2016 INVESTOR TERMS OF SERVICE

March 2016 INVESTOR TERMS OF SERVICE March 2016 INVESTOR TERMS OF SERVICE This Agreement is between you and Financial Pulse Limited and sets out the terms on which Financial Pulse offers you access to and use of certain services via the online

More information

Deed of Guarantee and Indemnity

Deed of Guarantee and Indemnity Deed of Guarantee and Indemnity To: Shenwan Hongyuan Securities (H.K. Limited Shenwan Hongyuan Futures (H.K. Limited 1. In consideration of your granting and/or continuing to make available advances, credit

More information

GAC GLOBAL HUB SERVICES HUB AGENCY STANDARD TERMS AND CONDITIONS. 1.1 In this Agreement, the following words shall have the following meanings:

GAC GLOBAL HUB SERVICES HUB AGENCY STANDARD TERMS AND CONDITIONS. 1.1 In this Agreement, the following words shall have the following meanings: GAC GLOBAL HUB SERVICES HUB AGENCY STANDARD TERMS AND CONDITIONS 1. DEFINITIONS 1.1 In this Agreement, the following words shall have the following meanings: "Affiliate" means a legal entity that at any

More information

MWC19 Barcelona Speaker Video Footage - Terms of Use

MWC19 Barcelona Speaker Video Footage - Terms of Use MWC19 Barcelona Speaker Video Footage - Terms of Use These Terms were last updated on 11 February 2019 and supersede any previous terms and conditions Acceptance of the Terms of Use These terms of use

More information

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS ICON DRILLING ABN 75 067 226 484 PURCHASE ORDER TERMS & CONDITIONS Acceptance of this offer is subject to the terms and conditions of this Agreement. Acceptance of materials, work or services, payment

More information

STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES. React Computer Partnership Ltd

STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES. React Computer Partnership Ltd STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES OF React Computer Partnership Ltd 1 DEFINITIONS In this document the following words shall have the following meanings: 1.1 "Agreement" means

More information

CMS Commercial Law Group Guide. Distribution and Agency Agreements

CMS Commercial Law Group Guide. Distribution and Agency Agreements CMS Commercial Law Group Guide Distribution and Agency Agreements February 2014 Whilst many aspects of the distribution relationship will be similar when distributing within the EU there are important

More information

THE INTERPRETATION OF EXCLUSION CLAUSES

THE INTERPRETATION OF EXCLUSION CLAUSES BRIEFING THE INTERPRETATION OF EXCLUSION CLAUSES MAY 2016 LITERAL AND NATURAL MEANING IS OF PRIMARY IMPORTANCE COMMERCIALITY MAY BE CONSIDERED THE COURT MAY ALSO CONSIDER APPLICATION OF THE CONTRA PROFERENTEM

More information

CARGO CHARTER GENERAL TERMS AND CONDITIONS

CARGO CHARTER GENERAL TERMS AND CONDITIONS CARGO CHARTER GENERAL TERMS AND CONDITIONS 1. DEFINITIONS 1.1. In these Cargo Charter Terms and Conditions capitalised words and expressions have the meanings set out for them below: Cargo Charter Summary

More information

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE THE FOLLOWING TERMS AND CONDITIONS, AND THOSE SPECIFIED ON THE FACE OF THIS PURCHASE ORDER, SHALL EXCLUSIVELY GOVERN THE PURCHASE OF ALL MATERIALS

More information

Website Disclaimer. by SEQ Legal

Website Disclaimer. by SEQ Legal Website Disclaimer by SEQ Legal Website disclaimer 1 (1) Introduction This disclaimer governs your use of our website; by using our website, you accept this disclaimer in full. 2 If you disagree with any

More information

Index. Volume 21 (2005) 21 BCL

Index. Volume 21 (2005) 21 BCL Index Abandoned claims judgment on, principally concerned with costs, 12-13, 33-44 whether cost reduction appropriate because of, 125 Access to the premises AS 4917-2003, 9-10 Acts Interpretation Act 1954

More information

QUICKPOLE.CA TERMS OF SERVICE. Last Modified On: July 12 th, 2018

QUICKPOLE.CA TERMS OF SERVICE. Last Modified On: July 12 th, 2018 1. PRELIMINARY PROVISIONS: QUICKPOLE.CA TERMS OF SERVICE Last Modified On: July 12 th, 2018 1.1 Introduction. Welcome to our website's Terms and Conditions ("Agreement"). The provisions of this Agreement

More information

JUDGMENT. R (on the application of Gibson) (Appellant) v Secretary of State for Justice (Respondent)

JUDGMENT. R (on the application of Gibson) (Appellant) v Secretary of State for Justice (Respondent) Hilary Term [2018] UKSC 2 On appeal from: [2015] EWCA Civ 1148 JUDGMENT R (on the application of Gibson) (Appellant) v Secretary of State for Justice (Respondent) before Lord Mance, Deputy President Lord

More information

Reinforcing Security of Payment in NSW

Reinforcing Security of Payment in NSW Philip Davenport 2011 Despite set backs in the Supreme Court, the NSW Government is firmly behind security of payment and has now strengthened security of payment for subcontractors by giving them the

More information

GENERAL TERMS & CONDITIONS FOR SUPPLYING MATERIALS AND SERVICES TO COCA-COLA SABCO MOZAMBIQUE (GTCCCSM)

GENERAL TERMS & CONDITIONS FOR SUPPLYING MATERIALS AND SERVICES TO COCA-COLA SABCO MOZAMBIQUE (GTCCCSM) Signed for (all pages) on behalf of SUPPLIER and hereby warrants that (s)he is duly authorised to sign and accept this complete GTCCCSM, consisting of 9 (nine) pages and all it Appendices, on behalf of

More information

Code of Practice means the Valpak Green Dot Code of Practice as set out on the Website, which may be updated from time to time.

Code of Practice means the Valpak Green Dot Code of Practice as set out on the Website, which may be updated from time to time. TERMS AND CONDITIONS FOR THE USE OF GREEN DOT 1. Definitions and Interpretation: Agreement means this written agreement. Authorised Packaging means the packaging in respect of which the User/prospective

More information

PLEASE READ CAREFULLY BEFORE AGREEING TO THE TERMS AND CONDITIONS

PLEASE READ CAREFULLY BEFORE AGREEING TO THE TERMS AND CONDITIONS PLEASE READ CAREFULLY BEFORE AGREEING TO THE TERMS AND CONDITIONS This is a legal Agreement, as amended from time to time, between you ( the Client ) and CHAS 2013 Limited, whose company number is 08466203

More information

EQUITABLE RELIEF IN THE LAW OF HIRE-PURCHASE

EQUITABLE RELIEF IN THE LAW OF HIRE-PURCHASE EQUITABLE RELIEF IN THE LAW OF HIRE-PURCHASE THE article by Mr. Aubrey L. Diamond in the Modern Law Review of September, 1956 (at p. 498), advanced the view that the court has power to grant equitable

More information

STANDARD TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES

STANDARD TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES . DEFINITIONS: In this document the following words shall have the following meanings: 1.1 "Agreement" means these Terms and Conditions; 1.2 "Customer" means the organisation or person who purchases goods

More information

Terms & Conditions for Heathrow ID Pass Scheme (the Terms )

Terms & Conditions for Heathrow ID Pass Scheme (the Terms ) Terms & Conditions for Heathrow ID Pass Scheme (the Terms ) 1. DEFINITIONS AND INTERPRETATION 1.1 In these Terms where the context admits: Airport means Heathrow Airport; Airport Operator means Heathrow

More information

THIS INDEPENDENT ENGINEER'S AGREEMENT (this Independent Engineer's Agreement) is made on [ ]

THIS INDEPENDENT ENGINEER'S AGREEMENT (this Independent Engineer's Agreement) is made on [ ] THIS INDEPENDENT ENGINEER'S AGREEMENT (this Independent Engineer's Agreement) is made on [ ] AMONG (1) REGIONAL TRANSPORTATION DISTRICT (RTD); (2) DENVER TRANSIT PARTNERS, LLC, a limited liability company

More information

AWORKER WORK TOKEN PURCHASE AGREEMENT

AWORKER WORK TOKEN PURCHASE AGREEMENT AWORKER WORK TOKEN PURCHASE AGREEMENT PLEASE READ THIS TOKEN PURCHASE AGREEMENT CAREFULLY. NOTE THAT SECTIONS 14 AND 15 CONTAIN A BINDING ARBITRATION CLAUSE AND REPRESENTATIVE ACTION WAIVER, WHICH AFFECT

More information

Company Policies CHEMIDOSE LIMITED. Chemical dosing specialists

Company Policies CHEMIDOSE LIMITED. Chemical dosing specialists Company Policies CHEMIDOSE LIMITED Chemical dosing specialists Unit 1 Centre 2000 St.Michael s Road Sittingbourne Kent ME10 3DZ Tel:01795 425169 www.chemidose.co.uk Chemidose Policies, Terms and Conditions

More information

WRITTEN STATEMENT UNDER THE MOBILE HOMES ACT 1983

WRITTEN STATEMENT UNDER THE MOBILE HOMES ACT 1983 WRITTEN STATEMENT UNDER THE MOBILE HOMES ACT 1983 IMPORTANT: PLEASE READ THIS STATEMENT CAREFULLY AND KEEP IT IN A SAFE PLACE. IT SETS OUT THE TERMS ON WHICH YOU WILL BE ENTITLED TO KEEP YOUR MOBILE HOME

More information

ASX BENCHMARK DATA SUBSCRIBER TERMS AND CONDITIONS

ASX BENCHMARK DATA SUBSCRIBER TERMS AND CONDITIONS ASX BENCHMARK DATA SUBSCRIBER TERMS AND CONDITIONS These terms and conditions govern any end user subscription access or use of ASX Benchmark Data. 1. Subscription Service We will use reasonable endeavours

More information

NATIONAL GRID GAS PLC NTS CHARGING MODEL SOFTWARE LICENCE AGREEMENT

NATIONAL GRID GAS PLC NTS CHARGING MODEL SOFTWARE LICENCE AGREEMENT NATIONAL GRID GAS PLC NTS CHARGING MODEL SOFTWARE LICENCE AGREEMENT CONTENTS Clause Heading Page 1 Definitions... 1 2 Nature of Licence... 1 3 Duration of the Licence and Updates... 2 4 Restrictions on

More information

STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT )

STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT ) STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT ) 1. BASIS OF SALE 1.1 EXION Asia Pte Ltd ( EXION ) shall sell and the Purchaser shall purchase the Goods and/or Services in accordance with

More information

Design and Artists Copyright Society Copyright Licensing Membership Agreement Terms and Conditions. December 2015

Design and Artists Copyright Society Copyright Licensing Membership Agreement Terms and Conditions. December 2015 DACS 33 Old Bethnal Green Road London E2 6AA T +44 (0) 20 7336 8811 F +44 (0) 20 7336 8822 E info@dacs.org.uk Design and Artists Copyright Society Copyright Licensing Membership Agreement December 2015

More information

Status: This is the original version (as it was originally enacted). ELIZABETH II c. 19. Employment Act CHAPTER 19 PART I TRADE UNIONS

Status: This is the original version (as it was originally enacted). ELIZABETH II c. 19. Employment Act CHAPTER 19 PART I TRADE UNIONS ELIZABETH II c. 19 Employment Act 1988 1988 CHAPTER 19 An Act to make provision with respect to trade unions, their members and their property, to things done for the purpose of enforcing membership of

More information

Contract Law Highlights of 2015

Contract Law Highlights of 2015 Lunch & Learn Christmas Special 264856 Contract Law Highlights of 2015 14 December 2015 Alistair Maughan, Sue McLean, Sarah Wells, Mercedes Samavi 2014 Morrison & Foerster (UK) LLP All Rights Reserved

More information

AVK UK LIMITED CONDITIONS OF SALE OF GOODS FROM WEBSITE

AVK UK LIMITED CONDITIONS OF SALE OF GOODS FROM WEBSITE General AVK UK LIMITED CONDITIONS OF SALE OF GOODS FROM WEBSITE PLEASE READ THESE TERMS CAREFULLY AND MAKE SURE THAT YOU UNDERSTAND THEM, BEFORE ORDERING ANY GOODS FROM OUR SITE. BECAUSE OF THE NATURE

More information

ITC MODEL CONTRACT FOR AN INTERNATIONAL COMMERCIAL AGENCY

ITC MODEL CONTRACT FOR AN INTERNATIONAL COMMERCIAL AGENCY ITC MODEL CONTRACT FOR AN INTERNATIONAL COMMERCIAL AGENCY EXTRACT FROM "MODEL CONTRACTS FOR SMALL FIRMS" GENEVA 2010 Contents Foreword Acknowledgements Introduction iii v ix Chapter 1 International Contractual

More information

LANEAXIS AXIS TOKEN SALE TERMS

LANEAXIS AXIS TOKEN SALE TERMS LANEAXIS AXIS TOKEN SALE TERMS Last updated: June 1, 2018 PLEASE READ THESE TOKEN SALE TERMS CAREFULLY. NOTE THAT SECTIONS 15 AND 16 CONTAIN A BINDING ARBITRATION CLAUSE AND REPRESENTATIVE ACTION WAIVER,

More information

Working in Partnership

Working in Partnership Terms and Conditions 1. Definitions 1.1 In these conditions (Unless the context otherwise requires): The Act means the Telecommunications Act 2003 and any amendments, modifications, re-enactments of the

More information

III.2 Model Written Statement November 2006

III.2 Model Written Statement November 2006 III.2 Model Written Statement November 2006 The Model Written Statement has been prepared in conjunction with the National Park Homes Council, BH&HPA s National Legal Adviser, Tony Beard of Tozers Solicitors

More information

Commercial Agents (Council Directive) Regulations 1993/3053

Commercial Agents (Council Directive) Regulations 1993/3053 This version in force from: December 7, 1993 to present Made: 7 December 1993 Laid before Parliament: 8 December 1993 Coming into Force: 1 January 1994 The Secretary of State, being a Minister designated

More information

I, Accept this proposal and make a payment of $ to confirm my commitment.

I, Accept this proposal and make a payment of $ to confirm my commitment. This Solar Home Improvement Agreement (this Agreement ) is between Golden Gate Green Finance dba Golden Gate Power, California General and Electrical Contractor license number 1002922 ( Golden Gate Power,

More information

CONDITIONS OF SALE DEFINITIONS

CONDITIONS OF SALE DEFINITIONS CONDITIONS OF SALE 1. DEFINITIONS In these Terms and Conditions (the Conditions ), the following words shall have the following meanings:- "Company" shall mean Marshalls Mono Limited or any member of the

More information

DISPUTE RESOLUTION BULLETIN

DISPUTE RESOLUTION BULLETIN Dispute Resolution December 2015 DISPUTE RESOLUTION BULLETIN Welcome to the December edition of our Dispute Resolution Bulletin. In our first article this month, Partner, Steven Paull, and Trainee Solicitor,

More information

A LITIGATOR S GUIDE TO DAMAGES January 17, 2017 CONTRACT DAMAGES. *With special thanks to Lesley Campbell, Student-at-Law OVERVIEW

A LITIGATOR S GUIDE TO DAMAGES January 17, 2017 CONTRACT DAMAGES. *With special thanks to Lesley Campbell, Student-at-Law OVERVIEW A LITIGATOR S GUIDE TO DAMAGES January 17, 2017 CONTRACT DAMAGES Harvin D. Pitch / Jennifer J. Lake *With special thanks to Lesley Campbell, Student-at-Law OVERVIEW 1. Specific Performance & Mitigation

More information