Automatic Suspensions

Similar documents
Case No: HT IN THE HIGH COURT OF JUSTICE BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES TECHNOLOGY AND CONSTRUCTION COURT (QBD) Before :

Automatic Suspension

Update. Procurement. Has Pandora s box been opened? Issue 02. Bringing procurement challenges out of time. Autumn 2015

SARAH HANNAFORD QC. Declan Redmond T: +44 (0) E:

Challenges to procurement decisions The issues and the pitfalls

Procurement Challenges. Tactics and Lessons Learnt from Recent Developments 6 December 2016 Jennifer Robinson

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

Before: THE HON MR JUSTICE COULSON Between:

REMEDIES IN PROCUREMENT LAW

STATUTORY INSTRUMENTS. S.I. No. 326 of 2017 EUROPEAN UNION (AWARD OF CONCESSION CONTRACTS) (REVIEW PROCEDURES) REGULATIONS 2017

IN THE HIGH COURT OF JUSTICE. Between NIXON CALLENDER JILLIAN BEDEAU-CALLENDER AND THE PUBLIC SERVICE ASSOCIATION OF TRINIDAD AND TOBAGO AND

Section 112 of the HGCR Act is set out below, with the amendments which will be introduced under the LDEDC Act shown in bold:

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

Private sector-led challenges to anti-competitive behaviour. Growth and fairness: private sector-led challenges to anti-competitive behaviour

Procurement Update. Summer Contents. 1. Welcome. 2. Summary of case law. 3. Procurement News Roundup. 1. Welcome

Table of Contents. Date Issued: June 12, 2009 Date Last Revised: December 15, 2010

Summary table of draft transposition of directive 2007/66/EC into Member States law

TENDER EVALUATION HOW NOT TO DO IT

Before: MRS JUSTICE O'FARRELL DBE Between:

RECOVERING COSTS FALLING DUE UNDER LEASES

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

Patent Enforcement UK perspectives

Presentation by Brenda Barrett. Emeritus Professor of Law Middlesex University

Practice Guideline 9: Guideline for Arbitrators on Making Orders Relating to the Costs of the Arbitration

WHY DO LARGE INFRASTRUCTURE TENDERS FAIL?

Procurement Update. Winter 2013

Recent developments in environmental and agricultural law. UKAEL Conference, September 2011: EU LAW AND THE LAND. Gwion Lewis

The first interim relief application under new CAT Rules: Flynn Pharma Limited v Competition and Markets Authority [2017] CAT 1 (19 January 2017)

HIGH COURT OF JUSTICE [1] IGNATIUS KARL HOOD. and [1] TILLMAN THOMAS [2] NAZIM BURKE [3] FRANKA BERNADINE [4] KEN JOSEPH [5] BERNARD ISSAC

SOLICITORS DISCIPLINARY TRIBUNAL. IN THE MATTER OF THE SOLICITORS ACT 1974 Case No and. Before:

SUPREME COURT OF QUEENSLAND

-and- SKELETON ARGUMENT ON BEHALF OF THE APPELLANT

Before : THE HONOURABLE MR JUSTICE ROTH Between :

Procedure for Considering Appeals to the NHS Gloucestershire Clinical Commissioning Group Individual Funding Request Appeal Panel

JUDGMENT OF THE COURT (Sixth Chamber) 28 October 1999 *

Infinis and damages for regulatory wrongs: Hot topic or damp squib?

MISS MERCEL HISLOP. Claimant/Appellent. and MISS LAURA PERDE JUDGMENT

Galliford Try Construction Ltd v Mott MacDonald Ltd [2008] APP.L.R. 03/14

The Safari Workaround decision

Condemnation Proceedings, a practical synopsis

STANDARD CFA TERMS AND CONDITIONS FOR PERSONAL INJURY CASES TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL

Online Case 8 Parvez. Mooney Everett Solicitors Ltd

UK public procurement: Are you in or out?

FREEDOM OF INFORMATION ACT REQUEST THE ATTORNEY GENERAL S LEGAL ADVICE ON THE IRAQ MILITARY INTERVENTION ADVICE

Conditions Precedent to Recovery of Loss and Expense Claims

GUIDANCE No.25 CORONERS AND THE MEDIA

Dispute Resolution Around the World. Russia

IN THE COURT OF APPEAL BETWEEN THE CHIEF FIRE OFFICER THE PUBLIC SERVICE COMMISSION AND SUMAIR MOHAN

JUDGMENT. Bimini Blue Coalition Limited (Appellant) v The Prime Minister of The Bahamas and others (Respondents)

Chapter 1: Success Fee Agreements Terminology

Remedies for Patent Infringement in the Medical Sector

Judicial Code. Contents

Be Careful and Honest in What You Say: Fraud in Arbitration

Before: MR RECORDER BERKLEY MISS EASHA MAGON. and ROYAL & SUN ALLIANCE INSURANCE PLC

[2015] EWHC 854 (QB) 2015 WL

Case Review Winrow v Hemphill [2014] EWHC 3164

COURT OF APPEAL RULES 2009

European Investment Fund. EIF Procurement Guide

The ABTA Arbitration Scheme Rules

LOWIN. and W PORTSMOUTH & CO. JUDGMENT (As Approved)

JUDGMENT. BPE Solicitors and another (Respondents) v Gabriel (Appellant)

FOR USE AFTER 1 NOVEMBER

OMBUDSMAN BILL, 2017

Comments on DG Competition s Guidance on procedures of the Hearing Officers in proceedings relating to Articles 101 and 102 TFEU *

IN THE COUNTY COURT AT NEWCASTLE UPON TYNE Case No: B54YJ494. Before: HIS HONOUR JUDGE FREEDMAN. and JUDGMENT

Re: Dr Fernando Hidalgo Martin v GMC [2014] EWHC 1269 Admin

Remedies: Injunction and Damages. 1. General

CHARTER 1. PREAMBLE. 1.4 This Charter can only be amended by a three quarters majority vote of the Council. 2. PURPOSES AND AIMS OF IACS

Every Loser Wins: Costs Sanctions Following An Unreasonable Failure To Mediate

Legal Briefing. Lungowe & Others v Vedanta Resources Plc & Konkola Copper Mines [2017]

FEDERAL COURT OF AUSTRALIA

BERMUDA BERMUDA INTERNATIONAL CONCILIATION AND ARBITRATION ACT : 29

Revised and updated pre-action protocols came into effect on 6 April 2015 with little advance warning.

IN THE EAST AFRICAN COURT OF JUSTICE AT ARUSHA FIRST INSTANCE DIVISION APPLICATION NO. 5 OF 2013 VENANT MASENGE...APPLICANT VERSUS

IN THE HIGH COURT OF JUSTICE BETWEEN PHILLIP QUASHIE CLAIMANT AND THE CHIEF FIRE OFFICER PROPOSED DEFENDANT

Saudi Center for Commercial Arbitration King Fahad Branch Rd, Al Mutamarat, Riyadh, KSA PO Box 3758, Riyadh Tel:

IN THE SUPREME COURT OF BELIZE A.D. 2011

Considering Contract Termination Under English Common Law

WHAT TO DO IF YOU THINK A BID LOWER THAN YOURS SHOULD BE THROWN OUT AND THE JOB AWARDED TO YOU

CPR Part 36 Offers Problems in Practice. by Dov Ohrenstein

Before : HIS HONOUR JUDGE PLATTS Between : - and -

A guide to civil proceedings in Guernsey

Bid Protests. Presented By: Keith Romanowski, Watkins Meegan LLC Dan Herzfeld, Pillsbury

GOVERNMENT CHALLENGES TO THE RULES ON STANDING IN JUDICIAL REVIEW MEET STRONG AND EFFECTIVE OPPOSITION

Public Procurement 1 Charles Banner, Landmark Chambers Local Government Seminar, 24 Oct 2013

IN THE SUPREME COURT OF BELIZE A.D. 2009

Birse Construction Ltd. v McCormick (U.K.) Ltd [2004] ABC.L.R. 12/09

Interim relief and urgent applications and the post permission stage

January Audit and Risk Committee Terms of Reference

B e f o r e: MR JUSTICE OUSELEY. Between: THE QUEEN ON THE APPLICATION OF ASSOCIATION OF BRITISH COMMUTERS LIMITED Claimant

ANTI-BRIBERY POLICY 1 POLICY STATEMENT

Number: 1124/1/1/09 IN THE COMPETITION APPEAL TRIBUNAL. Victoria House Bloomsbury Place London WC1A 2EB. 3 November 2011

EU-Mexico Free Trade Agreement EU TEXTUAL PROPOSAL. Chapter on Public Procurement

Before: Mrs Justice Whipple Between :

Construction Law: Recent Developments of Importance

TOPIC 13 CIVIL REMEDIES. LTC Harms Japan 2017

INTERNAL REGULATIONS OF THE FEI TRIBUNAL

CHALLENGING DEVELOPMENT PLANS IN THE HIGH COURT MAY 2013 SASHA WHITE Q.C.

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

Saunders v Caerphilly County Borough Council

Transcription:

Automatic Suspensions Heather Sargent 22 May 2018

Regulation 95 of the Public Contracts Regulations 2015: 95. Contract-making suspended by challenge to award decision (1) Where (a) a claim form has been issued in respect of a contracting authority's decision to award the contract, (b) the contracting authority has become aware that the claim form has been issued and that it relates to that decision, and (c) the contract has not been entered into, the contracting authority is required to refrain from entering into the contract. (2) The requirement continues until any of the following occurs (a) the Court brings the requirement to an end by interim order under regulation 96(1)(a)

In deciding whether to lift the automatic suspension: American Cyanamid principles (i) Does C's case raise a serious issue to be tried? (ii) If so, would damages be an adequate remedy (for either party)? (iii) If not, where does the balance of convenience lie?

The initial approach of English courts: lift the automatic suspension Indigo Services [2010] EWHC 3237 (QB): AS lifted Exel Europe Ltd [2010] EWHC 3332 (TCC): AS lifted A change in approach in late 2014? NATS (Services) Ltd v Gatwick Airport Ltd [2015] PTSR 566: AS maintained R (Edenred (UK Group) Limited) v HM Treasury[2014] EWHC 3555 (QB): AS maintained

Mixed fortunes during 2015: Solent NHS Trust v Hampshire County Council [2015] EWHC 457 (TCC): AS lifted Bristol Missing Link Ltd v Bristol CC [2015] EWHC 876 (TCC): AS maintained OpenView Security Solutions Ltd v Merton LBC [2015] EWHC 2694 (TCC): AS lifted Counted4 Community Interest Co v Sunderland CC [2015] EWHC 3898 (TCC): AS maintained

Developments since mid-2016: (i) High Court judgments in the Kent and Perinatal Institute cases (ii) Judgment of Supreme Court in Energy Solutions EU Ltd v Nuclear Decommissioning Authority (iii) High Court decision in Lancashire

Kent Community Health NHS Foundation Trust v NHS Swale Clinical Commissioning Group [2016] EWHC 1393 (TCC) 27 May 2016 AS lifted: Is common ground that proceedings raise serious issue to be tried C contends that damages would not be an adequate remedy for it as a not-for-profit organisation

Stewart-Smith J: [15] and [16]: there may be cases where the infringement of the interest that a party is trying to protect by way of an injunction may not be adequately compensated by an award of damages. A person's privacy or reputation is the paradigm example. There may be other considerations which lead to the conclusion that the Claimant in a particular case may not be adequately compensated by an award of damages because an award of damages does not reflect the substantial justice of the case. The Court must focus on the interests of the Claimant.

Questions Coulson J s judgment in Bristol Missing Link at [55]: I can see no reason why damages should be regarded as an inadequate remedy simply because the Claimant, whether as a not-for-profit organisation or for other reasons, has not suffered and will not suffer substantial financial loss But: the additional factors in BML were capable of rendering damages inadequate: The substantial justice of that case had to reflect the fact that, although their immediate and recoverable financial losses would be modest, the knock on effects (which, at least arguably, would not be compensated in damages) would be catastrophic

In Kent: In purely financial terms, the losses that would be incurred if the Trust fails to win the contract can be assessed without obvious difficulty and can be made the subject of an appropriate award of damages Counsel for C submits that it is not doing substantial justice to a claimant who is not engaging in the procurement process to generate money if the Court says that all the Claimant can recover is money. If, as he submits is the case here, the Claimant engages in the procurement because, in its judgment and belief as a public benefit corporation, a single provider of services across Kent is for the public benefit then simply to award damages for financial losses fails to meet that C's real concerns, because the Court is giving it a remedy that is essentially irrelevant to its wider purpose.

To my mind there is ultimately a short answer to this submission, which is that the Court is never going to rule on the question whether the public benefit is better served by having one provider of integrated services or more than one.

Balance of convenience: C suggests having claim heard outside of London so that it can be heard sooner. Judge notes that this would result in increased costs. A real risk that the delay if AS maintained would make the difference between getting the new arrangements in place in time for the winter and being unable to do so Judge concludes that factors are fairly evenly balanced and it is therefore a counsel of prudence to maintain the status quo:

What is the status quo? C contends that the status quo is that it is in place providing services CCGs observe that C s contract has expired and the status quo would allow it to enter into a new contract with Virgin Care unless injuncted CCGs argument is accepted

Perinatal Institute v Healthcare Quality Improvement Partnership [2016] EWHC 2626 (TCC) 26 October 2016 AS lifted On serious issue to be tried: HQID argues that there is not one because PI is out of time to make its complaint. Jefford J: there is at least a serious issue to be tried as to whether the complaints are time-barred

On adequacy of damages: I do not read what Coulson J. said at paragraph 55 of the judgment, quoted above, as setting out an absolute rule or principle that a non-profit organisation can never be adequately compensated in damages. Rather, in my view, he identifies that this is an argument open to a non-profit organisation against which background he then considered the consequences for BMLL of the lifting of the suspension in order to answer the question of whether it would be just to confine BMLL to recovering its minimal financial loss. The fact that an organisation is non-profit may make it more likely that it cannot be adequately compensated in damages and the BMLL case itself provides an example where that was the case because the project in question was at the heart of its activities, there would be a significant knock on effect to its other activities, and it would suffer significant reputational damage

Jefford J: there is a financial loss that can be compensated in damages: (i) PI s tender costs and (ii) the contribution to its overheads that PI would have recovered through the contract had it been successful Just, in all the circumstances, to confine PI to damages: PI s position is in no way similar to that of [C in BML]. There is no existing service provision which PI will be deprived of if the suspension is lifted and there is no suggestion or evidence that failure to obtain this contract will have any negative, let alone, catastrophic impact on PI s activities. PI may feel strongly that their bid was a better bid; they may have grave concerns about the NPEU bid; and these may be of far greater importance to them than any potential claim for damages, but that does not mean that it would be unjust to confine PI to its remedy in damages

Balance of convenience: Best case scenario still results in months of delay in the implementation of the project Public interest weighs heavily in favour of avoiding that further delay: is a data collection and review project aimed at the reduction of perinatal mortality rates: there is a clear public interest in this project proceeding as soon as possible

Energy Solutions EU Ltd v Nuclear Decommissioning Authority [2017] 1 WLR 1373 Supreme Court judgment 11 April 2017 Issue (iii) ([40] ff.): Can an award of damages be refused because C did not issue its claim form during the standstill period (i.e. before the contracting authority entered into the contract? Standstill period: 10 days from receipt by C of notification that it has not been awarded the contract. Contracting authority may not enter into the contract during this period. Challenge period: 30 days beginning with date when C first knew or ought to have known that grounds for starting legal proceedings had arisen

NDA argues that ATK (the unsuccessful tenderer) failed to mitigate its loss, by deliberately deciding not to issue a claim form until after the NDA had entered into the contract Had ATK issued its claim form before NDA entered into the contract, automatic suspension would have taken effect If ATK thereafter succeeded, it would in due course be awarded the contract and avoid the ( 100m) loss claimed Supreme Court notes: If the Court opted to maintain the automatic suspension, NDA would have had the benefit of a cross-undertaking and/or security from ATK

[46]: the actual entry into any contract appears in effect to be treated not as the relevant breach, but as the consequence of the prior breach consisting in the prior wrongful decision to award the contract : failure to mitigate is in principle available as an argument; however: [47]: We are concerned with a very unusual form of mitigation, whereby, it is suggested, ATK should have taken steps to prevent the NDA giving effect to the NDA s infringement. [52]: ATK may in its own interests have preferred to rest on a claim for damages if its challenge to the contract award decision succeeded, rather than give a cross-undertaking and expose itself to an indeterminate liability thereunder if its challenge failed.

[55]: Supreme Court notes that contracting authority could have waited until the end of the 30 day challenge period before entering into the contract Conclusion: ATK has not failed unreasonably to mitigate its loss: [56]:

In summary, an economic operator is entitled, in the face of what it views as (and later proves to have been) a breach of duty by the contracting authority, to leave it to the authority to take the risk of implementing its wrongful award decision. The economic operator cannot be said to be acting unreasonably if it fails to stop the authority from perpetrating a breach of duty which the authority could itself stop perpetrating. It cannot be said to be acting unreasonably if it refuses to give an undertaking or put up security in order to maintain a stop which it has in the first instance obtained by issuing a claim form before the authority has entered into the contract to give effect to its wrongful contract award decision.

N.b. NDA: an award of damages can only be made under the PCR where the breach of the Directive is sufficiently serious Therefore: claimants who decide not to trigger an automatic suspension, but opt instead to wait until the contract has been entered into before claiming damages, will now (i.e. post-nda) be gambling on the Court concluding that the breach was sufficiently serious

Lancashire Care NHS Foundation Trust v Lancashire County Council [2018] EWHC 200 (TCC) Fraser J: a claimant no longer has an automatic right to damages since the decision in NDA. To what extent, if at all, can and should this be addressed when considering the adequacy of damages?

[23] Both parties were agreed that at an interlocutory stage of a case and in particular, at the interlocutory stage in this particular case on these particular facts the court could not come to a decision on the question of whether the alleged breaches were or could be classified as "sufficiently serious". Both parties were agreed that the point should be taken into account when considering the question of adequacy of damages as presenting an additional requirement which any claimant had to satisfy to recover damages at all. That is therefore the approach, by agreement in this case, which I adopt. It does however form part of the consideration necessary to arrive at a preliminary conclusion of the effectiveness of the remedy, and it may arise for further and more detailed consideration in the future.

Discussion

hsargent@landmarkchambers.co.uk