PRC: Guangxi Southwestern Cities Development Project - Resettlement Due Diligence Report of Shijinglin Road Extension

Similar documents
Prepared by Guangxi Baise Development and Investment Group Co., Ltd. with the assistance of Beijing Enrimu Science & Technology Consulting Co., Ltd.

PRC: Liaoning Small Cities and Towns Development Demonstration Sector Project

PRC: Hunan Roads Development II Project External Monitoring Report on Land Acquisition and Resettlement For Yuanling Local Road(II)

PRC: Guangxi Beibu Gulf Cities Development Project

Guizhou Vocational Education Development Program Land Acquisition and Involuntary Resettlement Due Diligence

Resettlement Plan. PRC: Jiangxi Ji an Sustainable Urban Transport Project. November 2017

PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program Tranche 2

PRC: Yunnan Pu er Regional Integrated Road Network Development Project

PRC: Hunan Roads Development III Project Huayuan-Fenghuang Local Road Component

PRC: Chongqing Urban Rural Infrastructure Development Demonstration II Project

People s Republic of China: Gansu Baiyin Integrated Urban Development Project

Proposed Loan People s Republic of China: Hebei Elderly Care Development Project

Resettlement Policy Framework

Resettlement Policy Framework

Shanxi Small Cities and Towns Development Demonstration Sector Project

People s Republic of China: Yunnan Chuxiong Urban Environment Improvement Project

Resettlement Policy Framework and Due Diligence Report

PRC: Anhui Chao Lake Environmental Rehabilitation Project

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents

People s Republic of China: Hunan Flood Management Sector Project, Hunan Province, Chenxi County

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF)

Resettlement Plan. Urban Flood Control Project Utilizing ADB Loans

PRC: Hubei Huangshi Urban Pollution Control and Environmental Management Project

PRC: Guiyang Integrated Water Resources Management (Sector) Project

Resettlement Plan. Urban Flood Control Project Utilizing ADB Loans

People s Republic of China: Yunnan Chuxiong Urban Environment Improvement Project

External Resettlement Monitoring and Evaluation Report of the World Bank-financed Xining Water Environment Management Project

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

PRC: Yunnan Pu er Regional Integrated Road Network Development Project

Public Transport Sub-project of Urban Comprehensive Transport Improvement Project in Xi an the south of urban bus hub terminal

Gender Equality and Development

PRC: Anhui Integrated Transport Sector Improvement Project X056 Shantou, Sixian County- Minxian, Yongqiao District Section

Indonesia: Enhanced Water Security Investment Project

Wangliao Road (8#) Extension Construction Project in Yongchuan District. Resettlement Action Plan

Ethnic Minorities Development Framework. PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Resettlement Plan. the Yimu Highway Kedian to Mujiating Section Improvement. Project

Resettlement Plan: Shuangluan District. Proposed Loan People s Republic of China: Hebei Elderly Care Development Project

Resettlement Action Plan

PRC: Shaanxi Mountain Road Safety Demonstration Project

PRC: Guizhou Vocational Education Development Program

Resettlement and Income Restoration in Thilawa SEZ

The World Bank Financed Zhengzhou Rail Transit Line 3 Phase 1 Project. Supplementary Resettlement Action Plan

The External Resettlement Monitoring & Assessment Report

PRC: Xinjiang Tacheng Border Cities and Counties Development Project

Resettlement in Action

The External Resettlement Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Greater Mekong Subregion: Northern Economic Corridor Project Lao PDR. Summary Social Action Plan

PRC: Shanxi Small Cities and Towns Development Demonstration Sector Project

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

People s Republic of China: Guizhou Rocky Desertification Area Water Management Project

SFG1344 v1. Resettlement Action Plan for Chengde Central Heating Energy Saving Reconstruction Project. Chengde Heating Group

India: Jammu & Kashmir Urban Sector Development Project

PRC: Guiyang Integrated Water Resources Management Sector Project

RESETTLEMENT AND REHABILITATION PLAN

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject

Land Acquisition and Resettlement Due Diligence Report

External Resettlement and Social Development Monitoring and Evaluation Report

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject)

EX-ante Evaluation. 1. Name of the Project. 2. Background and Necessity of the Project. Japanese ODA Loan

Poverty Registration and Precisely Targeted Multidimensional Poverty Alleviation in China

Involuntary Resettlement Due Diligence Report

MON: Urban Development Sector Project Bulgan Subproject

Resettlement Due Diligence Report

The Study on Migration and Poverty Alleviation Planning of Daning County

Case studies of Cash Transfer Programs (CTP) Sri Lanka, Lebanon and Nepal

Involuntary Resettlement Due Diligence Report

Asian Development Bank s Involuntary Resettlement Safeguards. Project Case Studies in the People s Republic of China

2017 RESETTLEMENT PLAN SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT SFG2836 V7 REV

Resettlement Plan Dili-Tibar-Liquica Road

PRC: Xi an Urban Road Network Improvement Project

Involuntary Resettlement Due Diligence Report

RP1633 V3. Resettlement Action Plan. the Anji Subproject. Anji County Government June 2014

PRC: Xinjiang Regional Road Improvement Project (Korla-Kuqa Section)

Revised Resettlement Plan Tibar-Gleno Road

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

External Resettlement Monitoring and Evaluation Report. People s Republic of China: Guiyang Integrated Water Resources Management (Sector) Project

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Involuntary Resettlement Due Diligence Report

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

Key Issues: Climate Zone: As: Tropical humid. Subjects: - Restoration of livelihood and Rebuilding of Resettled Communities

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE INDEPENDENT STATE OF SAMOA

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

RP-0008 VOL. 1. Resettlement Action Plan for Shenyang Urban Transport Project. The World Bank Loan Liaoning Urban Transport Project

India: Delhi Meerut Regional Rapid Transit System Project

PRC: Hefei Urban Environment Improvement Project

SUMMARY OF THE ABBREVIATED RESETTLEMENT ACTION PLAN (ARAP)

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

PRC: Guizhou High Efficiency Water Utilization Demonstration in Rocky Desertification Area Project

For Harbin Municipal Government Harbin Municipal Water Supply Construction Leading Group Office

Article 2These Regulations apply to the residents-resettlement for the Three Gorges Project construction.

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Ethnic Minorities Development Framework. PRC: Guiyang Integrated Water Resources Management Sector Project

VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project

Involuntary Resettlement Due Diligence Report

VIE: Hanoi Metro Rail System Project Line 3: Nhon-Hanoi Station Section

AFG: MFF Water Resources Development Investment Program- Tranche 1, Nangarhar Valley Development Authority Grant No: 0167 AFG

Arrange of Tourism Infrastructure at Ananuri Castle. Abbreviated Resettlement Action Plan

Social Management Policy Framework

Transcription:

Resettlement Due Diligence Report Project Number: 42010 October 2014 PRC: Guangxi Southwestern Cities Development Project - Resettlement Due Diligence Report of Shijinglin Road Extension Prepared by Chongzuo Investment Corporation for Urban Development For Guangxi Project Management Office This report has been submitted to ADB by the Guangxi Southwestern Cities Development Project Management Office and is made publicly available in accordance with ADB s public communications policy (2011). It does not necessarily reflect the views of ADB.

ADB Loan Project ADB Loan 2657-PRC: Guangxi Southwestern Cities Development Project Chongzuo Shijinglin Road West Extension Resettlement Due Diligence Report Chongzuo Investment Corporation for Urban Development October 2014

1. Summary for Chongzuo Shijinglin Road West Extension 1.1 Extension Content Shijinglin Road West Extension, as part of Chongzuo urban road and traffic safety facilities subproject of Guangxi Southwest Urban Development Project, has a width of 15.5m and a length of 3028.378 m, the road needs widening to a width of 54 m for Guangxi Gardening Expo which will be held in 2015. 1.2 Extension Location Chongzuo Shijinglin Road West Extension is one of main stems, which is connected with the new area in the urban south and Ningming Road to the west and travelling across the Shijinglin conservation area and Shuikouhu conservation area, bridging the southern and the northern part of the city and the old city districts according to Chongzuo master planning in east-west direction. 1.3 Extension Context According to Chongzuo Urban Master Plan (2002-2020), Chongzuo Shijinglin Road West Extension is designed as urban level II road with 6 dual-lanes and width of 60 meters. The construction contains two stages: i) short-term project with width of 15.5 meters, 2 dual-lanes and 50 km/h designed bicycle speed; ii) long-term project with width of 54 meters, 6 dual-lanes and 60 km/h designed bicycle speed. In 2009, Chongzuo Shijinglin Road West Extension is involved in ADB Guangxi Southwest Urban Development Project as one of sub-project of Chongzuo urban road and transport safety project. The 7 th Guangxi Gardening Expo will be held in October 2015 beside northwest Shuikou Lake in Chongzuo. According to Notice on Arrangement of the 6 th and 7 th Guangxi World Garden Expo, infrastructure construction around Expo must be finished by the end of June 2015. Chongzuo Shijinglin Road West Extension, as the main traffic of Chongzuo Expo, cannot meet the traffic requirement due to the Expo event. To solve the issue of actual traffic demand, it is proposed to start long-term Chongzuo Shijinglin Road West Extension project in advance, i.e. extend the road width to 54 meters. 1

1.4 Extension Approval The land use application was approved by Chongzuo Land and Resources Bureau on March 5 2013. (Chongzuo LRB Document No. 66 2013). 2. Extension Land Acquisition and Relocation Impact Chongzuo Shijinglin Road West Extension will increase permanent land acquisition 11.53 ha, affecting 133 persons from 32 households; increase relocation area 1,989.26 m 2, affecting 31 persons from 7 households. Of the relocation affected 7 households, 6 households with 27 persons are also affected by the increased land acquisition. The other household has 4 people doing business in Nanning and live there too. In conclusion, Chongzuo Shijinglin Road West Extension will increase 137 people from 33 households (see Table 1). The extension will require relocation of 2 hafnium electricity poles, 2 hafnium communication poles and 200 meter wires. Among new households involved in extension, there is no disabilities, and other vulnerable people. Also, there is no other ground appendage facilities needs be moved. House demolition Land acquisition Table 1 Shijinglin Road West Extension Resettlement Scope and Impact Male Female Total Area m 3 - - 1989.26 Impact Household - - 7 Impact Person 17 14 31 Area Ha - - 11.53 Impact Household - - 32 Impact Person 68 65 133 Total 1 Impact Household - - 33 Impact Person 70 67 137 Data source: Project Land Acquisition Approval Document, Chongzuo Land Acquisition Office, Chongzuo PMO, survey result. 2.1 Land Acquisition Impact Chongzuo Shijinglin Road West Extension will increase permanent land acquisition 11.53 ha, which is 248% of planned 4.64 ha, including agricultural land 7.83 ha, arable 1 Among 7 relocation households, 6 of them is affected by land acquisition. Therefore the total household and person affected does not equals to the sum of acquisition and relocation. 2

land 2.54 ha, construction land 1.01 ha, and unused land 2.70 ha. (see Table 2) Table 2 Newly-added Land Acquisition (Hectare) Before extension After extension Increase Rate Total Project Land 4.64 16.18 11.53 248.39% Agricultural land 3.72 12.95 7.83 210.71% Arable land 2.29 4.83 2.54 110.90% Construction land 0.38 1.32 1.01 265.99% Unused land 0.55 1.91 2.70 491.48% Data source: Project Land Acquisition Approval Document and Chongzuo PMO Permanent land being acquired formally belongs to Wuwei Concrete Plant, Shuikou Village of Jiangnan township and Xincun Village of Jiangzhou township. The acquisition affects 21 households with 88 persons in Shuikou Village, and 11 households with45 persons in Xincun Village. The rates of land loss of all households involved in the acquisition are all below 5%. Unit Jiangnan Shuikou Village Table 3 Land Acquisition Impact Jiangzhou Xin Village Male Female Total Household 21 11 - - 32 Person 88 45 68 65 133 Data source: Chongzuo Land Acquisition Office and Chongzuo PMO 2.2 Relocation Impact Chongzuo Shijinglin Road West Extension will increase 1,989.26 m 2 of house demolition including 1,552.46 m 2 of brick concrete structure houses and 436.80 m 2 of brick structure houses. Brick concrete structure Table 4 Relocation Area (m 2 ) Brick and wood structure 3 Brick structure Mud house Total old redline 15.5 825.00 0 0 0 825.00 new redline 60 2,377.46 0 436.8 0 2,814.26 increase 1,552.46 0 436.80 0 1,989.26 Data source: Chongzuo PMO House demolition in Chongzuo Shijinglin Road West Extension will make relocation of

4 households in Shuikou Village and 3 households in Xincun Village, affecting 31 persons in total. Table 5 Relocation Impact Jiangnan Shuikou Village Jiangzhou Xin Village Male Female Total Household 4 3 - - 4 Person 18 13 17 14 31 Data source: Chongzuo Relocation Office, PMO and survey result 3. Public Consulting and Information Disclosure During the extension designing, Chongzuo Land Acquisition and Relocation Office, local government and urban investment company jointly conducted public consultation and information disclosure to affected people, in the 2 villages once a week on average. The consultation and disclosure covers the reasons for widening the road, the impacts, the compensation, site of relocation, etc. which much facilitated the affected people s understanding the situation and cooperation. 4. Land Acquisition and Relocation Compensation According to Chongzuo Document No.148 (2012), from January 2013 on, the compensation standard increased (see Table 6). In fact, besides the policy compensation, Chongzuo Municipal Government will offer additional CNY 75,000 to each affected household. Table 6 Land Acquisition and Relocation Compensation Standard Item Unit Before 2013 After Jan 2013 Arable land CNY/mu Paddy/dry land 13,700 Paddy/dry land 23,290 Arable land CNY/mu Vegetable land 25,384 Vegetable land 41,249 Young crop CNY/mu Paddy land 1,300 dry land 2,313.60 Sugar cane 2,313 Vegetable land 2,100 Vegetable land 2,100 Brick and concrete house CNY/m 3 600~900 600~900 Compensation CNY/household 0 75,000 Data source: Government Document No. 148 (2012) and updated Resettlement Plan 4

5. Resettlement Plan The three affected households from Xin Village will be resettled to centralized settlement site which is near Chongzuo bus station, and will be offered additional compensation and 30 m 2 homestead with Santongyiping 2 for the households to build their new houses. The four affected households in Shuikou Village will be resettled in their Village through assistance from the Chongzuo resettlement Office, and local government, and will be offered compensation and homestead with Santongyiping. During the period of relocation, the government will offer temporary transition fee, including house build fee and per diem, in specific: i) a temporary living place and CNY 30,000 house build fee 3 ; ii) a per diem of CNY 150 per month until moving in to new houses. 6. Recovery Measures for affected households The affected 33 households will follow similar recovery plan to that in the project updated resettlement plan, including: 0.3 mu land for each person affected; Priority job opportunity, including created by the engineering company, etc; Various training for affected people, such as driving, chief, gardening, etc. Social Insurance for the affected people, including pension and medical insurance as indicated in Guangxi Relocation Farmers Insurance Document; Subsistence allowances for vulnerable people; 7. Complaint Mechanism The original project complaint mechanism is followed. The affected household, group or individual can submit complaint concerning any resettlement and compensation issue. Besides government complaint procedure, the project has established public complaint procedure through village committee. The affected group or person, if not satisfied to local complaint result, can seek for legal solution. The project will conduct public meeting, resettlement booklet and media to help affected person understand the procedure. The resettlement authorities shall deal with complaint in time. 2 That is, flat ground with access to road, access to electricity and access to water. 3 In fact CNY 10,000 per household will be adequate for building a new temporary house. 5

8. Cost Estimate The cost of extension compensation is CNY 8,300,000, including CNY 4,100,000 of land acquisition fee, CNY 3,200,000 of resettlement fee and CNY 1,000,000 for others. 9. Resettlement Implementation Progress By the end of August 2014, land acquisition was completed. Relocation of 7 households will be completed by end of February 2015, and will be moved to new houses in April 2015. The ground appendages will be finished by the end of February 2015. 10. Internal and External Monitoring From 3 rd quarter 2014 on, the project internal and external monitoring will include land acquisition, relocation and resettlement impact and livelihoods recovery for Chongzuo Shijinglin Road west extension construction. 6