PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT ON INTERNATIONAL RAILWAYS IN THE ARAB MASHREQ

Similar documents
"ESCWA's Role in Promoting Integrated Transport System in the Arab Region

Transport Corridors Connecting Africa, Asia and Europe through the Arab Region: Priority Corridors and Facilitation Mechanisms

CHAPTER II LABOUR FORCE

CHAPTER II LABOUR FORCE

E Distr. LIMITED E/ESCWA/EDID/2015/IG.3/4(Part III) 10 November 2015 ENGLISH ORIGINAL: ARABIC

Regional prospects: Western Asia Project LINK Meeting Yasuhisa Yamamoto October 20, 2016

CHAPTER X FOREIGN TRADE

Top Cities. of the Middle East & North Africa. July 2012

The financial and economic crisis: impact and response in the Arab States

OUR BEST DAYS ARE AHEAD OF US

INTERNATIONAL MIGRATION AND DEVELOPMENT IN THE ARAB STATES

(Non-legislative acts) DECISIONS

International Law of Freedom of Association in the Arab World

Update on Regional Activities

Regional Consultation on International Migration in the Arab Region

Single Windows and Arab Regional Integration

Investment and Business Environment in the Arab World

A Snapshot of Drinking-water and Sanitation in the Arab States 2010 Update

The volatile security situation in Iraq continued to

West Asia Regional Economic Outlook UN DESA Expert Group Meeting. October 2015 Jose A. Pedrosa-Garcia ESCWA

2 SAGIA seeks to encourage investment, embrace innovation, and enhance the Kingdom s competitiveness Attracting sufficient investment to achieve rapid

REGIONAL PROGRAMME TO COMBAT CRIMINAL & TERRORIST THREATS AND STRENGTHEN CRIMINAL JUSTICE & HEALTH SYSTEMS IN LINE WITH INTERNATIONAL STANDARDS ON

PUBLIC POLICIES FOR GREATER EQUALITY: LESSONS LEARNED IN THE ESCWA REGION

Statistical Appendix

International Civil Aviation Organization. Second Meeting (AIM SG/2) (Kish Island, Iran, 31 August-2 September 2015)

WORLD HEALTH ORGANIZATION ORGANISATION MONDIALE DE LA SANTÉ

GENDER EQUALITY IN THE

9ème Séminaire du Réseau international francophone en promotion de la sécurité et en prévention des traumatismes Beirut, Liban 5-7 mai 2011

GRSP MENA Programmes in the Region

Middle East and North Africa Zone (Gulf Region Report) In brief Programme outcome: Programme(s) summary: Appeal No. MAA80003.

arabyouthsurvey.com #arabyouthsurvey April 21, 2015

CONTENTS. Letter from the CEO Survey methodology Top ten findings Insights 28 About us 29 Country data. Jordan Kuwait Lebanon Libya

Follow-up issues. Summary

The longest-established regional intellectual property firm in the Middle East. Iraq: Request for Comments on the Draft

Migration Governance in the Arab Region and Beyond

CHAPTER 3. Urbanization MANAL EL-BATRAN

Investigating the Geology and Geography of Oil

THE INNOVATION LANDSCAPE IN THE ARAB COUNTRIES

A/58/310. General Assembly. United Nations

THE DEMOGRAPHIC PROFILE OF THE ARAB COUNTRIES

Statistical Appendix

The outlook for the Gulf projects market

NEWSLETTER. ISSUE 1 - January June Message from the Regional Representative Abdel Salam Sidahmed

MAKING ONTARIO HOME2012

Distr. LIMITED. E/ESCWA/SDD/2010/Technical Paper.4 4 October 2010 ARABIC ORIGINAL: ENGLISH

Statistical Appendix

Levels and Trends of International Migration in Asia and the Pacific

Jamal AlFakhouri, Regional CO Coordinator MENA Region

ANNEX 3. MEASUREMENT OF THE ARAB COUNTRIES KNOWLEDGE ECONOMY (BASED ON THE METHODOLOGY OF THE WORLD BANK)*

RESIDENCY PROGRAMME worldwidecitizenship.com GENERAL INFORMATION

Terms of Reference. and. Rules of Procedure. of the. Economic. and. Social Commission. for Western Asia

Policy Brief. Institutional Mechanisms for Gender Accountability in the Arab Region

THE MILLENNIUM DEVELOPMENT GOALS IN THE ARAB REGION 2005

Terms of Reference. and. Rules of Procedure. of the. Economic. and. Social Commission. for Western Asia

OPPORTUNITIES IN ASIA

UNWTO Commission for the Middle East Thirty-sixth meeting Madrid, Spain, November 2012

2010 Annual Arab Public Opinion Survey

Middle East & North Africa Facebook Demographics

Nomadic Diplomacy: The Case of Yemen

The Introduction of International Road Transport Agreements of China. Ministry of Transoprt of China Mar

Ease of doing business in the Gulf countries

EXPORT CONTROL OFFICER. EXPORT CONTROL OFFICER (ECO) Panel Discussion. Todd Willis Assistant Director Office of Enforcement Analysis CHINA

ISC Learning Contract Academic Standards Talk Introduction to Academic Personal Tutor Book Police Registration. Fire Safety Talk Lunch

Demographic Profile of the Arab Region Realizing the Demographic Dividend

Building Knowledge Economy (KE) Model for Arab Countries

REPORT OF THE CULTURE COMMISSION (CLT)

Sixteenth meeting of the Regional Programme Review Group on lymphatic filariasis elimination and other preventive chemotherapy programmes

March 7, Second Annual ASDA A Burson-Marsteller Arab Youth Survey

The Arab Division for Experts on Geographical Names

UNHCR s programmes in the Middle East have

The role of ASEAN labour attachés in the protection of migrant workers

The EU, the Mediterranean and the Middle East - A longstanding partnership

DUE DILIGENCE PRICES & PRODUCTS

Al JAZEERA CENTrE FOr STUDIES

Non-UEMS Applicants EBOPRAS experience

Policy Frameworks to Accelerate Poverty Reduction Efforts

Israeli Nuclear Capabilities and Threat

Keller Group plc. Keller in the Middle East. Wolfgang Sondermann

Welcome Week Timetable

Departamento de Medio Oriente

Economic Growth and Unemployment in SMEs: The Need for New Policy Framework

The Future of Migration: Building Capacities for Change

Original language: English SC66 Doc CONVENTION ON INTERNATIONAL TRADE IN ENDANGERED SPECIES OF WILD FAUNA AND FLORA

Session 2: The importance of institutions and standards for soft connectivity

Gulf Cooperation Council Interconnection Authority (GCCIA) Request for Bidding Proposal for KSA Oman Border IRU Dark Fiber

Kuwaiti MPs Want Amendments to Residency Law for Expats. 58% of Installed Software in Jordan Pirated

Foundation for the Future. Towards promoting democracy and human rights through strengthening CSOs in the Broader Middle East and North Africa.

August 2013 Security Threat to Americans Abroad

Survey of Economic and Social Developments in the Arab Region

Country programme documents ending in 2017 and 2018

Declaration of Action on

The Perception of Japanese Abroad Towards the Middle East. Past and Present

The Bayt.com Middle East and North Africa Salary Survey May 2013

Press Release Political unrest in the Arab world shakes up regional economy UN report

arabyouthsurvey.com #arabyouthsurvey

Toward Global and Regional Partnerships to Support Transformative Agenda in Official Statistics in the Arab region

O V E R V I E W. Qatar Saudi Arabia Syrian Arab Republic United Arab Emirates 250, , , ,000 50,000 UNHCR GLOBAL REPORT 1999

PART II SELECTED SOCIAL INDICATORS

Dr Neil Partrick East Sussex United Kingdom

T H E R O Y A L E M B A S S Y O F S A U D I A R A B I A I N R O M E FOCUS ON R O M E, N O V E M B E R

Transcription:

ECONOMIC AND SOCIAL COMMISSION FOR WESTERN ASIA (ESCWA) PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT ON INTERNATIONAL RAILWAYS IN THE ARAB MASHREQ United Nations

Distr. LIMITED E/ESCWA/GRID/2006/Technical Paper.1 25 November 2006 ENGLISH ORIGINAL: ARABIC ECONOMIC AND SOCIAL COMMISSION FOR WESTERN ASIA (ESCWA) PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT ON INTERNATIONAL RAILWAYS IN THE ARAB MASHREQ United Nations New York, 2006 06-0411

CONTENTS Introduction... 1 Chapter I. SUMMARY OF THE PROPOSED PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT... 1 Page II. DETAILS OF THE PROPOSED PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT... 1 A. Media aspects... 1 B. The completion of economic feasibility studies on missing links... 2 C. Technical specifications of routes... 2 III. TIMETABLE OF PROPOSED PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT... 3 LIST OF TABLES 1. Links missing from the international rail network... 5 2. Technical specifications for each route section (as in annex II of the Agreement)... 7 3. Schedule of technical specifications of the rail network... 8 4. Proposed timetable for implementation of the Agreement... 9 LIST OF FIGURES I. Summary of the plan of action for implementation of the Agreement... 3 II. Load dimensions in accordance with International Union of Railways specifications... 4 iii

Introduction As part of the process of developing the Integrated Transport System in the Arab Mashreq (ITSAM), the Economic and Social Commission for Western Asia (ESCWA) has concluded agreements on networks of international roads and railways in the region, with the aim of strengthening thereby the links between the countries of the region and achieving regional integration. With the entry into force of those agreements, it became necessary to formulate plans of action for their implementation. This document contains a draft plan of action for the implementation of the Agreement on International Railways in the Arab Mashreq. That Agreement * was adopted on 14 April 2003 and entered into force on 23 May 2005 after it had been ratified by four countries, namely, Egypt, Jordan, Lebanon and the Syrian Arab Republic. Implementation of the Agreement requires that member countries, in coordination with ESCWA, formulate the necessary plans for that purpose. ESCWA prepared a proposed plan of action that comprises general steps that will assist countries in carrying out their undertakings in respect of the Agreement: it was left up to each country to formulate detailed executive plans appropriate to their circumstances, as set forth below. I. SUMMARY OF THE PROPOSED PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT Figure I shows the steps that are required for proper implementation of the Agreement. Those steps fall into the following three main categories: (a) Media aspects; (b) The completion of economic feasibility studies on missing links; (c) Technical specifications of routes. II. DETAILS OF THE PROPOSED PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT A. MEDIA ASPECTS 1. Preparation of pamphlet about and map of the Agreement ESCWA undertook to prepare a pamphlet and coloured map that includes a description of the Agreement and the routes comprising the international rail network, together with an outline of Agreement goals and benefits. The pamphlet has been produced and distributed to member countries at all the relevant meetings organized or participated in by ESCWA. If member countries provide the modest sums necessary, further copies may be printed at a cost of $1,000 per 5,000 copies. 2. The launching of a publicity campaign on the Agreement As real implementation of the Agreement begins, rail users must be made acquainted with its goals and benefits. Each country must therefore carry out an awareness campaign in local newspapers, on television stations and other media, which should be launched at least one month before the date on which implementation of the Agreement is begun. It is suggested that such campaigns should be initiated in April 2006. * United Nations, the Economic and Social Commission for Western Asia, The Agreement on International Railways in the Arab Mashreq, Beirut, 5 March 2003 (E/ESCWA/TRANS/2002/1/Rev.2). 7

B. THE COMPLETION OF ECONOMIC FEASIBILITY STUDIES ON MISSING LINKS 1. Inventory of missing links In all, some 60 per cent of the total length is missing from the international rail network adopted in the Agreement. An inventory of missing links is therefore an essential step towards Agreement implementation. Table 1 sets out such an inventory, by network route. 2. Setting priorities for feasibility studies At this stage, priorities are set for feasibility studies of the missing links set forth in table 1. The priorities will be identified by the ESCWA Committee on Transport in accordance with a set of standards and bases, taking into account political, technical, economic and environmental considerations. 3. The preparation of feasibility studies Feasibility studies of the missing links will be prepared in accordance with the priorities set in the preceding step and subject to the availability of the funds necessary to carry out such studies. 4. The determination of priorities for the building of missing links Priorities for building the missing links will be determined on the basis of the outcomes of the economic feasibility studies prepared in the preceding step and subject to the availability from a variety of sources of the funds necessary to build those links. C. TECHNICAL SPECIFICATIONS FOR THE ROUTES 1. The preparation of a schedule of technical specifications for each section of existing links At this stage, the existing links and the technical specifications for each section thereof will be enumerated along the lines of the model in table 2, which was prepared in accordance with the specifications set forth in annex II of the Agreement. 2. The identification of specifications on each section that do not accord with the Agreement Each country shall make an inventory of all the routes on its territory and identify those sections where specifications do not accord with those set forth in annex II of the Agreement. The requisite studies should then be carried out. 3. The completion of the work necessary to improve existing links Each country shall undertake to carry out the work necessary to ensure that the network routes in its territory reach the requisite standard. ESCWA should be notified of the timetable to which each country intends to work in carrying out the improvements necessary to upgrade all parts of the network. 4. The building of the missing links in accordance with the priorities determined in step four and Agreement technical specifications This is the final step in Agreement implementation and includes the building of the missing links in accordance with the priorities determined as a result of the economic feasibility studies and the technical specifications set forth in annex II of the Agreement (see table 3 of this document), in addition to the availability of the sums necessary for that purpose. 2

III. TIMETABLE FOR THE PLAN OF ACTION FOR IMPLEMENTATION OF THE AGREEMENT Table 4 shows the timetable for the proposed plan of action for implementation of the Agreement, of which the most important dates are set forth below: - Preparation of a pamphlet about the Agreement (ESCWA has prepared that pamphlet) 30 January 2004 - Launch of the publicity campaign 1 April 2006 - Completion of economic feasibility studies on missing links 31 December 2008 - Completion of the work necessary to improve existing links 31 December 2012 - Building the missing links 31 December 2020 As soon as this plan of action is adopted, each country that is party to the Agreement must implement tables 2 and 4 and notify ESCWA by 30 December 2006 at the latest in preparation for follow-up of plan of action implementation by the ESCWA Committee on Transport. Figure I. Summary of the plan of action for implementation of the Agreement A. Media aspects Preparation of pamphlet about and map of Agreement (1) B. Completion of the economic feasibility studies Inventory of missing links (1) C. Technical specifications for routes Preparation of schedule of technical specifications for each section of the existing network (1) Launching of media campaign about the Agreement (2) Setting of priorities for feasibility studies (2) Identification of specifications on each section that do not accord with those of the Agreement (2) Preparation of feasibility studies (3) Completion of work required to improve existing links (3) Determination of priorities for building the missing links (4) Building of missing track in accordance with the priorities determined in step 4 and Agreement specifications (4) 3

Figure II. Load dimensions in accordance with International Union of Railways specifications 4

TABLE 1. LINKS MISSING FROM THE INTERNATIONAL RAIL NETWORK Umm Qasr (Kuwait) Kuwait Kuwait R05 138 Kuwait Nuwayseeb border point (Kuwait/Saudi Arabia) Kuwait R05 105 Nuwayseeb border point (Kuwait/Saudi Arabia) Khafji border point (Saudi Arabia/Kuwait) Kuwait R05 20 Khafji border point (Saudi Arabia/Kuwait) Abu Hadriyah Saudi Arabia R05 145 Abu Hadriyah Dammam Saudi Arabia R05 155 Dammam Salwa Saudi Arabia R05 375 Salwa Batha a border point (Saudi Arabia/United Arab Emirates) Saudi Arabia R05 120 Batha a border point (Saudi Arabia/United Arab Emirates) Al Ghweifat border point (United Arab Emirates/Saudi Arabia) Saudi Arabia R05 32 Al Ghweifat border point (United Arab Emirates/Saudi Arabia) Abu Dhabi United Arab Emirates R05 315 Abu Dhabi Dubai United Arab Emirates R05 93 Dubai Sharja United Arab Emirates R05 80 Sharja Fujairah United Arab Emirates R05 100 Fujairah Kalba border point (United Arab Emirates/Oman) United Arab Emirates R05 10 Kalba border point (United Arab Emirates/Oman) Khatmat Malahaw border point (Oman /United Arab Emirates) United Arab Emirates R05 10 Khatmat Malahaw border point (Oman /United Arab Emirates) Sohar Oman R05 65 Sohar Muscat Oman R05 236 Muscat Thumrayt Oman R05 930 Thumrayt Salalah Oman R05 72 Total 3 001 Al Azraq Omari border point (Jordan/Saudi Arabia) Jordan R15 42 Omari border point (Jordan/Saudi Arabia) Hadithah border point (Saudi Arabia/ Jordan) Jordan R15 18 Hadithah border point (Saudi Arabia/ Jordan) Quoryat Saudi Arabia R15 100 Quoryat Dawmat al-jandal Saudi Arabia R15 300 Dawmat al-jandal Ha il Saudi Arabia R15 315 Ha il Buraydah Saudi Arabia R15 330 Buraydah Riyadh Saudi Arabia R15 413 Total 1 518 5

TABLE 1 (continued) Al Mudawara border point (Jordan/Saudi Arabia) Halat Ammar border point (Saudi Arabia /Jordan) Jordan R25 15 Halat Ammar border point (Saudi Arabia /Jordan) Tabukk Saudi Arabia R25 100 Tabuk Medina Saudi Arabia R25 710 Rabigh Jeddah Saudi Arabia R25 460 Jeddah Darb Saudi Arabia R25 500 Darb Al Tuwal border point (Saudi Arabia/Yemen) Saudi Arabia R25 220 Al Tuwal border point (Saudi Arabia/Yemen) Harad border point (Yemen/ Saudi Arabia) Saudi Arabia R25 17 Harad border point (Yemen/ Saudi Arabia) Hodeidah Yemen R25 265 Hodeidah Al Mukha Yemen R25 225 Total 2 512 Syrian Arab Deir-Ez-Zor Tadmur Republic R20 126 Total 126 Haklania Tarabil border point (Iraq/Jordan) Iraq R40 325 Tarabil border point (Iraq/Jordan) Karamah border point (Jordan/Iraq) Jordan R40 5 Karamah border point (Jordan/Iraq) Safawy Jordan R40 239 Safawy Zarqa Jordan R40 90 Zarqa Amman Jordan R40 40 Total 699 Gaza Rafah border point (Palestinian Occupied Territories/Egypt) Palestine R50 8 Total 8 Ma an Aqaba Jordan R60 16 Aqaba Nuweiba Jordan R60 73 Nuweiba Nakhl Egypt R60 150 Nakhl Verdun Bridge Egypt R60 250 Total 489 Mecca Jeddah Saudi Arabia R80 918 Total 918 6

TABLE 1 (continued) Doha Salwah Qatar R82 110 Total 110 Mazyounah border point Thumrayt (Oman/Yemen) Oman R90 160 Mazyounah border point (Oman/Yemen) Shahan border point (Yemen/ Oman) Oman R90 20 Shahan border point (Yemen/ Oman) Gheizah Yemen R90 125 Gheizah Mukalla Yemen R90 451 Mukalla Aden Yemen R90 617 Aden Bab al-mandab Yemen R90 862 Total 2 235 Total length of rail approved for Arab Mashreq 19 528 Total length of track missing from the international rail network approved for Arab Mashreq 11 616 Percentage of missing track 59.50 TABLE 2. TECHNICAL SPECIFICATIONS FOR EACH ROUTE SECTION (AS IN ANNEX II OF THE AGREEMENT) Name of section Track width Vehicle loading gauge Minimum distance between track centres Nominal minimum speed Authorized mass per axle (220 k per hour) Authorized mass per axle (locomotive) (120 k per hour) Authorized mass per axle (locomotive) (140 k per hour) Authorized mass per linear metre Test train (bridge design) Minimum platform length in principal stations Minimum useful siding length Electrical voltage 7

TABLE 3. SCHEDULE OF TECHNICAL SPECIFICATIONS FOR RAIL NETWORK New lines For passenger traffic For passenger and goods only traffic Standard Standard (1 435 mm) (1 435 mm) Serial No. Technical specifications Existing lines 1 Track width Standard (1 435 mm) 2 Vehicle loading gauge UIC/B* UIC/B* UIC/B* 3 Minimum distance between track centres 4 m 4 m 4 m 4 Nominal minimum speed 120 km/h 120 km/h 120 km/h 5 Authorized mass per axle For locomotives (# 200 km/hr) For wagons (# 120 km/hr) (# 140 km/hr) 22.5 tons 20 tons 18 tons - - - - 22.5 tons 20 tons 18 tons 6 Authorized mass per linear metre 8 tons - 8 tons 7 Test train (bridge design) UIC 71 - UIC 71 8 Minimum platform length in principal stations 250 m 250 m 250 m 9 Minimum useful siding length 500 m - 500 m 10 Electrical voltage - In accordance with UIC and Trans-European Railway Network specifications * See figure II. 8

TABLE 4. PROPOSED TIMETABLE FOR IMPLEMENTATION OF THE AGREEMENT 1 Preparation of pamphlet about and map of the Agreement 2 Launching of publicity campaign about the Agreement 3 Inventory of missing links 4 Setting priorities for feasibility studies 5 Preparation of feasibility studies 6 Determination of priorities for the building of missing links 7 Preparation of schedule of technical specifications for each section of existing links 8 Identification of specifications that do not conform to those of the Agreement 9 Completion of work necessary for improvement of existing links 10 Building missing links in accordance with the priorities determined in step 4 and Agreement technical specifications 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Note: (-) indicates ideal date of completion. 9