The Latest from the High Court on Performance Bonds: Simic v New South Wales Land and Housing Corporation [2016] HCA 47 7 December 2016

Similar documents
CASE NOTES PROBUILD CONSTRUCTIONS (AUST) PTY LTD V SHADE SYSTEMS PTY LTD [2018] HCA 4

RECENT DEVELOPMENTS IN EMPLOYMENT DISPUTES: EMPHASISING THE LAW OF CONTRACT. Tom Brennan 1. Barrister, 13 Wentworth Chambers

Contractual Interpretation: A Roundabout Approach

CONSENTS AND APPROVALS BOILERPLATE CLAUSE

SUPREME COURT OF QUEENSLAND

CORRS CONSTRUCTION LAW UPDATE JULY 2016

SUPREME COURT OF QUEENSLAND

For personal use only

Court of Appeal Supreme Court. New South Wales. Abergeldie Contractors Pty Ltd v Fairfield City Council

SUPREME COURT OF QUEENSLAND

Take the example of a witness who gives identification evidence. French CJ, Kiefel, Bell and Keane JJ stated at [50]:

Validity of Migration Act provisions for regional processing on Nauru

IN THE SUPREME COURT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA

UPDATE INSURANCE HUNT & HUNT LAWYERS V MITCHELL MORGAN NOMINEES PTY LTD & ORS APRIL 2013 VELLA OVERTURNED BY HIGH COURT

SUPREME COURT OF QUEENSLAND

For personal use only

The use of extrinsic evidence in aid of construction: a plea for pragmatism 1 Introduction

SUPREME COURT OF QUEENSLAND

Tendency Evidence Post-Hughes

APPEALS FROM VCAT TO THE SUPREME COURT

The clause (ACAS Form COT-3) provided:

THE EASTERN CARIBBEAN SUPREME COURT IN THE COURT OF APPEAL IN THE COURT OF APPEAL BETWEEN [1] GENERAL AVIATION SERVICES LTD. [2] SILVANUS ERNEST.

FEDERAL COURT OF AUSTRALIA

JUDGMENT. This is an exception by the plaintiff to the defendant s plea and counterclaim.

SUPREME COURT OF QUEENSLAND

Topic Pleading and Joinder of claims and parties, Representative and Class Actions 1) Res Judicata (Colbran )

COMPANIES ACT 2016: PRACTICE NOTE NO. 2/2018

Note Deed Poll. Dated 19 December 2014

SUPREME COURT OF QUEENSLAND

Note Deed Poll. Dated 22 August 2013

TAJJOUR V NEW SOUTH WALES, FREEDOM OF ASSOCIATION, AND THE HIGH COURT S UNEVEN EMBRACE OF PROPORTIONALITY REVIEW

SUPREME COURT OF QUEENSLAND

Week 4: Intention and Certainty

The highly anticipated conclusion to a five-year battle over the status of the

BUILDING AND CONSTRUCTION CASES 2018

Counterparts boilerplate clause

Offers of compromise under rule of the UCPR: Learned Friends, Fiji July 2015 ANDREW COMBE BARRISTER AT LAW

SUPREME COURT OF QUEENSLAND

The Impact of Pre-Contractual Conduct on Contractual Interpretation. The Hon Justice Michael Sifris 1

Fasda Heights Sdn Bhd - vs - Soon Ee Sing Construction Sdn Bhd

In Unions New South Wales v New South Wales,1 the High Court of Australia

FEES? NOT SO SIMPLE: ANDREWS AND ORS V AUSTRALIA NEW ZEALAND BANKING GROUP LTD [2012] HCA 30 (6 SEPTEMBER 2012)

A CASE NOTE ON KOOMPAHTOO LOCAL ABORIGINAL LAND COUNCIL v SANPINE PTY LIMITED

FEDERAL COURT OF AUSTRALIA

PASTORAL AND GRAZING LEASES AND NATIVE TITLE

PROBLEMS OF BANK GUARANTEE UNDER THAI LAW

Hema Engineering. State of Karnataka

District Court New South Wales

Immigration Law Conference February 2017 Panel discussion Judicial Review: Emerging Trends & Themes

LIMITS TO STATE PARLIAMENTARY POWER AND THE PROTECTION OF JUDICIAL INTEGRITY: A PRINCIPLED APPROACH?

THE LAW RELATING TO GUARANTEES

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802

Republic of South Africa IN THE HIGH COURT OF SOUTH AFRICA (WESTERN CAPE HIGH COURT, CAPE TOWN) JUDGMENT DELIVERED : 3 NOVEMBER 2009

Addisons Contractual Interpretation Series. Best Endeavours

LEGAL CHARACTERISTICS OF THE STANDBY LETTER OF CREDIT

HIGH COURT OF AUSTRALIA

CHOICE OF LAW (GOVERNING LAW) BOILERPLATE CLAUSE

LAW ON THE INTERNATIONAL COMMERCIAL ARBITRATION BULGARIA. Chapter I GENERAL PROVISIONS

A Question of Law: Practice and Procedure in Courts and Tribunals in New South Wales

IN THE COURT OF APPEAL WHITE CONSTRUCTION COMPANY LIMITED. and DCG PROPERTIES LIMITED. 2011: July 25, 26; September 26.

Criminal Organisation Control Legislation and Cases

DEFAMATION. Greens Local Councillor Forum

SUPREME COURT OF QUEENSLAND

CORRS CONSTRUCTION LAW UPDATE MARCH 2016

IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO.3650 OF 2014

This title may be cited as the Uniform Electronic Transactions Act.

Topics this week. Part A Classification of Contract Terms. Part B Performance, Breach & Right of Termination

Reasonableness and withholding consent to an assignment of contractual rights

SOME CURRENT PRACTICAL ISSUES IN CLASS ACTION LITIGATION INTRODUCTION

J U L Y V O L U M E 6 3

Judgment delivered on the 21st day of February locations throughout Australia but, so far as relevant here, at its office at 345 Queen

IN THE COURT OF APPEAL OF BELIZE AD 2014 CIVIL APPEAL NO 4 OF 2011 THE ATTORNEY GENERAL OF BELIZE

Same-sex marriage protected by the US Constitution

Contracts Notes. Contracts Semester (exam)

SUPREME COURT OF QUEENSLAND

JOAN MONICA MALONEY v THE QUEEN [2013] HCA 28

Written Submissions. Liquidation) ACN

Case 2:05-cv TJW Document 211 Filed 12/21/2005 Page 1 of 11

Compulsory Acquisition and Informal Agreements: Spencer v Commonwealth

NEVADA REVISED STATUTES. Title 59 - ELECTRONIC RECORDS AND TRANSACTIONS CHAPTER 719 ELECTRONIC TRANSACTIONS (UNIFORM ACT)

Review of Administrative Decisions on the Merits

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 1999 S 1 SENATE BILL 1266

Construction Law: Recent Developments of Importance

AUSTRALIAN ENVIRONMENTAL LAW NEWS

IN THE CIRCUIT COURT OF COUNTY, ARKANSAS DIVISION PLAINTIFF DEFENDANT S RESPONSES TO PLAINTIFF S REQUEST FOR ADMISSION OF FACTS

UPDATE 24 FEBRUARY 2017 NSW CIVIL PROCEDURE. JP Hamilton, G Lindsay and C Webster

and JUDGMENT [2011: 15, 27 June]

Banking & Financial Services Law Association Conference 29 August Judicial Case Law Update - Australia. Justice Ashley Black

3. Negotiable Instruments Negotiable Instruments

THE CONSUMER PROTECTION LAW

Projects Disputes in Australia: Recent Cases

For personal use only

CISG CASE PRESENTATION

Rules for the Appeals Board of the trading venues of SIX

SUPREME COURT OF QUEENSLAND

U.S. SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 40 - F

DIGITAL ECONOMY STRATEGY

Agreement to UOB Banker s Guarantee Terms and Conditions

Proving lack of consent

SUPREME COURT OF QUEENSLAND

Transcription:

The Latest from the High Court on Performance Bonds: Simic v New South Wales Land and Housing Corporation [2016] HCA 47 7 December 2016 Snapshot Performance bonds are regularly employed by parties in a vast range of commercial enterprises including, most notably, in international commerce and in property transactions. They are to be construed in accordance with the usual principles of contractual interpretation. However, the dual principles of strict performance and autonomy which are generic to performance bonds means that unlike ordinary contracts, no resort can be had to the underlying contract (that is, the agreement pursuant to which a performance bond has been issued) in construing the obligations under the bond. Introduction Performance bonds, sometimes called bank guarantees, are typically issued by a financial institution at the request of a party to a contract. Performance bonds are often issued pursuant to an obligation contained in a construction contract. They take the form of a promise by the issuing institution that it will pay to the beneficiary named in the bond, an amount up to the limit set out in the bond unconditionally or on specified conditions and without reference to the terms of the contract between the parties. The primary question in this case, determined by the High Court of Australia on 7 December 2016, was whether the second respondent (ANZ) as the issuer of a performance bond, had an obligation to pay on demand of the New South Wales Land and Housing Corporation (Corporation), a party claiming to be the beneficiary which, due to an error on the part of the requesting party, was not the beneficiary actually named in the bond. That case turned on the following issues: 1. Whether, as a matter of construction, it is possible to regard the Undertakings as being in favour of the Corporation, instead of a named "Principal" that did not exist; and 2. If not, should the Undertakings be rectified so that each is in favour of the Corporation? The Facts ANZ on the instructions of the third respondent (Nebax), a company of which the first appellant, Mr Simic, was a director, issued two instruments, each in the form of

2 an unconditional promise to pay (Undertakings), in favour of a named "Principal" that did not exist: "New South Wales Land & Housing Department trading as Housing NSW. Mr Simic gave Ms Hanna, an officer of the ANZ, the details to enable her to generate the Undertakings using a computer template. Mr Simic did not give Ms Hanna a copy of the Construction Contract or a copy of the draft Unconditional Bankers Certificate. The Corporation made a demand for payment under each Undertaking. ANZ did not pay on the demands because the Corporation was not the named Principal. The Court of Appeal In approaching the constructional question, Emmett AJA (with whom Bathurst CJ and Ward JA agreed), who wrote the leading judgment in the Court of Appeal, held that ordinary principles of construction were applicable. His Honour approached the question of construction on the basis that it was anterior to the principle of strict compliance, which he held pertained to performance. The principle of autonomy went to construction because it was directed to the question as to which documents could be employed for the purpose of determining what the performance bonds meant. It was therefore permissible to have regard to the construction contract to that extent in order to determine the correct construction of the Undertakings. The Court of Appeal thus concluded that upon the proper construction of the Undertakings, the defined "Principal" meant the Corporation and, it followed, "once the Corporation had furnished to ANZ indisputable evidence that it was the entity that was a party, as 'Principal', to the contract or agreement with Nebax described in the Undertakings, there was no basis upon which ANZ would be entitled to refrain from meeting the demand" 1. Emmett AJA did not deal with the question of rectification. The High Court Consistent with established banking practice, no party contended that the Undertakings were to be construed otherwise than in accordance with ordinary principles of contract construction. There was also no dispute about those principles of construction. Proper construction of the Undertakings The Court said that a proper construction of each Undertaking is to be determined objectively by reference to its text, context and purpose: Electricity Generation Corporation v Woodside Energy Ltd: "[T]he objective approach [is] to be adopted in determining the rights and liabilities of parties to a contract. The meaning of the terms of a commercial contract is to be determined by what a reasonable businessperson would have understood those terms to mean. [I]t will require consideration of the language used by the parties, the surrounding circumstances 1 Simic v New South Wales Land and Housing Corporation [2015] NSWCA 413 at [114]

3 known to them and the commercial purpose or objects to be secured by the contract. Appreciation of the commercial purpose or objects is facilitated by an understanding 'of the genesis of the transaction, the background, the context [and] the market in which the parties are operating'. 2 The starting point for the proper construction of the Undertakings is the language used in each Undertaking. ANZ was obliged to pay a stipulated amount without regard to the performance or non-performance of any party to that contract or agreement 3. The Court held, for the reasons including those following, that it was not open to construe "New South Wales Land & Housing Department" where it appeared as the "Principal" in each Undertaking as referring to the Corporation. 4 First, the Corporation and a "department" of the New South Wales Government are legally distinct. The Corporation is a statutory corporation that can sue and be sued in its own name. By contrast, a department of the New South Wales Government is an emanation of the Crown in the right of the State of New South Wales. Second, although the "contract or agreement" referred to in each Undertaking provides a link to the Corporation which is significant for the purposes of rectification, it is either irrelevant or of no assistance for the purposes of construction. That is because, subject to fraud perpetrated by a beneficiary, an instrument of this nature (unconditional promise to pay on demand) is independent of any underlying transaction and any other contract. That principle the principle of autonomy reflects that those instruments, by their nature, stand alone. Not only are they equivalent to cash but, by their terms, they also require that the obligations of the issuer are not determined by reference to the underlying contract. The principle of autonomy dictates that the surrounding circumstances and commercial purpose of the Construction Contract are different from those of the Undertakings. 5 Third, the inability to construe the "Principal" named in each Undertaking as the Corporation is impelled by the commercial purpose or objects of such an instrument. The Court noted that letters of credit or documentary credits, and performance bonds or guarantees both involve an undertaking, usually by a bank, to make payment on satisfaction of certain conditions. In each case, the issuer is not required or intended to be concerned with the terms of the underlying contract or, subsequently, with whether the favouree or beneficiary of the security has sufficiently performed its obligations under that contract. Fourth, the inability to construe the named "Principal" as referring to the Corporation was necessitated by commercial reality. In issuing a banking instrument of this nature, the issuer relies upon, and acts in accordance with, the instructions of the applicant, and is contractually bound to do so. The fact that the applications were completed based on incorrect instructions did not alter ANZ's contractual relationship with Nebax. 2 251 CLR 640 at 656-657 [35]; [2014] HCA 7; 3 Gageler, Nettle, Gordon JJ at [82] 4 French CJ at [10]; Kiefel J at [31]; Gageler, Nettle, Gordon JJ at [84]-[101]; 5 Gageler, Nettle, Gordon JJ at [85]

4 Lastly, the principle of strict compliance dictates that an issuer of a performance bond should only accept documents that comply strictly with the requirements stipulated in an instrument of this nature. The principle is fundamental to the efficacy and dependability of banking instruments such as the Undertakings. This point was eloquently made in the judgment of Kiefel J in which her Honour said, ANZ was obliged only to pay the amount specified to the entity named in the Undertakings, upon production of the original Undertakings and a demand for payment. No process of construction could effect the inclusion of the Corporation's name in lieu of the name appearing in the Undertakings. ANZ was not obliged to enquire into the background giving rise to the error of identification, which was not evident from the Undertakings themselves. 6 Rectification For relief by rectification, it must be demonstrated that, at the time of the execution of the written instrument sought to be rectified, there was an "agreement" between the parties in the sense that the parties had a "common intention", and that the written instrument was to conform to that agreement. Critically, it must also be demonstrated that the written instrument does not reflect the "agreement" because of a common mistake. There is no requirement for communication of that common intention by express statement but it must at least be the parties' actual intentions, viewed objectively from their words or actions, and must be correspondingly held by each party. The Court held that the evidence before the primary judge disclosed that all parties to the transaction intended that the Undertakings should enure to the benefit of the party with which Nebax entered into the Construction Contract. It was Mr Simic's intention, and, therefore, Nebax's intention, that the Undertakings should operate in favour of Nebax's counterparty to the Construction Contract. Similarly, it was Ms Hanna's understanding, and, therefore, ANZ's understanding, that the Undertakings were to be entered into in relation to the Construction Contract. 7 As the primary judge found, Mr Simic, and, therefore, Nebax, made a further mistake in informing Ms Hanna of the name of Nebax's counterparty to the Construction Contract. Mr Simic erroneously stated that the name of the counterparty was "New South Wales Land & Housing Department Trading As Housing NSW ABN 45754121940". That error was repeated in the applications prepared by Ms Hanna and signed by Mr Simic. Ms Hanna, and therefore ANZ, then unwittingly perpetuated the mistake by including the name "New South Wales Land & Housing Department Trading As Housing NSW ABN 45754121940" as the name of the counterparty in the Undertakings produced pursuant to the applications. Conclusion 6 Kiefel J at [31] 7 French CJ at [15]-[17]; Kiefel J at [50]; Gageler, Nettle & Gordon JJ at [107]-[109]

5 The orders made by the Court of Appeal were set aside and the Undertakings issued by ANZ were ordered to be rectified by substituting the words "New South Wales Land and Housing Corporation ABN 24 960 729 253" for the words "New South Wales Land & Housing Department Trading As Housing NSW ABN 45754121940". The principle of strict compliance means that it is not possible as a matter of construction to refer to the underlying contract to determine the identity of a party, the manner in which the bond was intended to operate or the validity or enforceability of the bond itself at least as between the issuer of a bond and the beneficiary or favouree. The issuer's sole concern is to provide security in accordance with its contract with its customer and, when the security is issued, to see whether there has occurred the event stipulated in the instrument on which the issuer's obligation to pay arises. Further, the principle of autonomy reflects that performance bonds, of their nature stand alone. That principle dictates that the surrounding circumstances and commercial purpose of the contract underlying the performance bond are different from those of the Undertakings and, accordingly, irrelevant to and not admissible on the question of construction of the performance bond itself. Dated: 7 March 2017 Anthony Lo Surdo SC 12 Wentworth Selborne Chambers T: 9223 3181 E: losurdo@12thfloor.com.au W: www.12thfloor.com.au W: www.silkmediator.com.au