GUIDANCE FOR ADJUDICATORS

Similar documents
USERS GUIDE TO ADJUDICATION

Hong Kong International Arbitration Centre ADJUDICATION RULES

The General Teaching Council for Scotland Fitness to Teach Rules 2017 These Rules are available in alternative formats on request

GUIDE TO ARBITRATION

Challenging the Adjudicator s Decision

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

OPINION OF LORD DRUMMOND YOUNG. in the cause COSTAIN LIMITED. against STRATHCLYDE BUILDERS LIMITED

Statutory Instrument 1998 No The Scheme for Construction Contracts (England and Wales) Regulations 1998

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act

Adjudication. Information note. Adjudication

Code of Practice on the discharge of the obligations of public authorities under the Environmental Information Regulations 2004 (SI 2004 No.

LEGAL ISSUES IN ARBITRATIONS - WHEN AND HOW TO TAKE LEGAL ADVICE

CIArb/IMPRESS ARBITRATION SCHEME RULES ( the Rules ) FOR USE IN ENGLAND & WALES

Joinery Plus Ltd (in administration) v Laing Ltd [2003] Adj.L.R. 01/15

Mission Drift in Statutory Adjudication

RULES FOR EXPERT DETERMINATION

THE LMAA TERMS (2006)

Arbitration Act 1996

Multiplex Constructions (UK) Ltd v Mott Macdonald Ltd [2007] Adj.L.R. 01/10

CONSTRUCTION BRIEFING November 2016

B: Principles of Law. DGT Steel and Cladding Ltd v Cubbitt Building and Interiors Ltd [2007] Adj.L.R. 07/04

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Unit 5 : ADJUDICATION

IMPORTANT NOTICE. Information that must be set out in notice of adjudication served on residential occupier.

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

THE CHARTERED INSURANCE INSTITUTE Disciplinary Procedure Rules

Alternative Dispute Resolution (ADR) In Chapter 36 of his Final Report Jackson LJ wrote:

Before : MR. JUSTICE EDWARDS-STUART Between :

ENGLAND BOXING DISCIPLINARY PROCEDURE

Before: MRS JUSTICE O'FARRELL DBE Between:

Evidence in International Arbitration. Expert Evidence / Expert Determination Clause. 莫世傑 / Danny Mok CILTHK 9 April 2017

IS THE ENFORCEMENT OF AN ADJUDICATOR S DECISION A FOREGONE CONCLUSION? Karen Gidwani. 15 May 2006

The ABTA Arbitration Scheme Rules

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Adjudication Lifecycle

Arbitration Rules of the Court of International Commercial Arbitration of the Chamber of Commerce and Industry of Romania

1996 No (L.5) IMMIGRATION. The Asylum Appeals (Procedure) Rules 1996

Data Protection Bill [HL]

/...1 PRIVATE ARBITRATION KIT

UK ATHLETICS LIMITED ( UKA ) DISCIPLINARY RULES AND DISPUTE RESOLUTION AND DISCIPLINARY PROCEDURES

ALL CHANGE! THE NEW TRIBUNALS

Independent Press Standards Organisation Arbitration Scheme Consultation Paper

Housing Act 1996, Part 7

Investments, Life Insurance & Superannuation Terms of Reference

FINANCIAL GUIDANCE AND CLAIMS BILL [HL] EXPLANATORY NOTES ON COMMONS AMENDMENTS

RULES OF ARBITRATION

Before: MR JUSTICE AKENHEAD Between: BECK INTERIORS LIMITED - and - UK FLOORING CONTRACTORS LIMITED

Dispute Board Rules. in force as from 1 September Standard ICC Dispute Board Clauses. Model Dispute Board Member Agreement

The OIA for Ministers and agencies

Agreement for the Supply of Legal Services by a Barrister at Three New Square

Conditions Precedent to Recovery of Loss and Expense Claims

Rules for the Conduct of an administered Arbitration

RPT-G6. Mobile Homes guidance

Section 112 of the HGCR Act is set out below, with the amendments which will be introduced under the LDEDC Act shown in bold:

THE LAW SOCIETY CONVEYANCING ARBITRATION RULES

EMPLOYMENT AND DISCRIMINATION TRIBUNAL (PROCEDURE) ORDER 2016

Judicial Reviews. Judicial reviews and legal aid

SECTION 1 INTRODUCTORY RULES...

DOCUMENT. A Disciplinary Procedure for dealing internally with complaints against members.

Before: HIS HONOUR JUDGE PETER COULSON QC Between: - and - CUBITT BUILDING AND INTERIORS LIMITED

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 //

2010 No. 791 COPYRIGHT

CIArb/IMPRESS ARBITRATION SCHEME RULES ( the Rules ) FOR USE IN ENGLAND, WALES, SCOTLAND, AND NORTHERN IRELAND

Agreement for the Supply of Legal Services by a Barrister in a Commercial Case

WHAT IS A CONDITION AND PROGNOSIS REPORT AND WHAT PURPOSE DOES IT SERVE IN LEGAL PROCEEDINGS?

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

Resolving tenancy disputes

DISPUTE RESOLUTION RULES

GCC code of practice for criminal investigations and prosecutions under the Chiropractors Act 1994 July 2012

PILOT PART 1 THE OVERRIDING OBJECTIVE

IMPRESS: The Independent Monitor for the Press CIC Regulatory Scheme

Police and crime panels. Guidance on confirmation hearings

Before: THE HONOURABLE MR JUSTICE BARLING (President) LORD CARLILE OF BERRIEW QC SHEILA HEWITT. Sitting as a Tribunal in England and Wales BAA LIMITED

NOTICES, TIME BARS AND PROPORTIONALITY

IMPRESS: The Independent Monitor for the Press CIC Regulatory Scheme

(i) Key characteristics of an effective Adjudicator and. (ii) ANB Evaluation Processes from TeCSA view point

Adjudication Society & Chartered Institute of Arbitrators

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018

- legal sources - - corpus iuris -

Import VAT VAT input tax claim application to Tribunal made out of time - should Tribunal allow to proceed yes

Sample DRT Procedures and Guidelines

English Fee Shifting Techniques Applied in US Arbitrations

THE ELECTRICITY ARBITRATION ASSOCIATION

Terms of Reference ( TOR ).

BERMUDA COPYRIGHT TRIBUNAL RULES 2014 BR 11 / 2014

THE LONDON MARITIME ARBITRATORS ASSOCIATION THE INTERMEDIATE CLAIMS PROCEDURE (2012)

Interpreting and clarifying requests

Summary. Background. A Summary of the Law Commission s Recommendations

New Expert Rules launched by the ICC

CERTIFICATION APPEALS HANDLING PROCESS. For Individual Candidates seeking Certification and Qualified Individuals seeking Re-Certification

EX305. The Fast Track and the Multi-Track in the civil courts. 1. Introduction. 2. Do you need legal help?

Rules. 1. Purpose. 2. Complaints Covered. 3. Complaints Not Covered. 4. Time Limits and Exhaustion of Internal Complaints Procedures

The use of experts in construction disputes in the UAE

Staff information. ICO policy and procedure regarding party political activities

ICE Adjudication Procedure

2009 No (L. 20) TRIBUNALS AND INQUIRIES

THE VALIDITY OF ADJUDICATORS DETERMINATIONS CONTAINING ERRORS OF LAW: THE NSW JUDICIAL APPROACH

Frank Cowl & Ors v Plymouth City Council

Try Construction Ltd v Eton Town House Group Ltd [2003] Adj.L.R. 01/28

Transcription:

CONSTRUCTION UMBRELLA BODIES ADJUDICATION TASK GROUP JULY 2002

GUIDANCE FOR ADJUDICATORS Guidance for adjudicators in adjudications conducted under Part II of the Housing Grants, Construction and Regeneration Act 1996 CONSTRUCTION UMBRELLA BODIES ADJUDICATION TASK GROUP JULY 2002

This Guidance for Adjudicators has been prepared by the British Property Federation www.bpf.propertymall.com the Construction Confederation www.thecc.org.uk the Construction Industry Council www.cic.org.uk and the Constructors Liaison Group now the the National Specialist Contractors Council www.nscc.org.uk and the Specialist Engineering Contractors Group www.secgroup.org.uk through the Construction Umbrella Bodies Adjudication Task Group in conjunction with the Construction Sector Unit of the Department of Trade & Industry (formerly the Construction Industry Directorate of the Department of the Environment, Transport and the Regions) www.dti.gov.uk Published by the Construction Umbrella Bodies Adjudication Task Group c/o Construction Industry Council, 26 Store Street, London WC1E 7BT tel 020 7637 8692 www.cic.org.uk Designed and printed by Astwood Design Consultancy ISBN 1 898671 27 3 Every effort has been made to ensure that this Guidance for Adjudicators is correct at the time of going to print. All parties must rely exclusively upon their own skill and judgment when making use of this document. This Guidance for Adjudicators is intended merely to highlight issues which arise in adjudications under the Construction Act and not to be comprehensive, nor to provide legal advice. Neither the bodies listed above nor any other contributor assumes any liability to anyone for any loss or damage caused by any error or omission whether such error or omission is the result of negligence or any other cause. Any and all such liability is disclaimed. Construction Umbrella Bodies Adjudication Task Group July 2002 Reproduction is authorised, provided it is without amendment and the source is acknowledged.

CONTENTS Introduction 1 1. Natural justice (procedural fairness) 2 2. Challenges to jurisdiction 4 3. Intimidatory tactics 5 4. Unmanageable documentation 6 5. Reasons for the decision 7 6. Accidental errors or omissions 8 7. The parties costs 10 INTRODUCTION This Guidance for Adjudicators arises out of the Construction Industry Board s review1 of the first two years operation of the Scheme2 under the Construction Act.3 It covers a number of specific issues raised in that report, and is not comprehensive. Circumstances alter cases, and the guidance should be treated as suggestions to adjudicators rather than rules. It is couched in lay terms and is not intended as a legal interpretation of the provisions of the Act or the Scheme, but as helpful guidance. The guidance is advisory not binding. This Guidance for Adjudicators primarily refers to adjudication conducted under the Scheme in England and Wales but much of it will be applicable elsewhere or when a contractual adjudication procedure is used. 1 Review of the Scheme for Construction Contracts: A CIB Report to the Construction Minister, December 2000: available (together with the DETR Response) on www.cic.org.uk. 2 The Scheme for Construction Contracts (England and Wales) Regulations 1998 (Statutory Instrument 1998 No 649). 3 Part II of the Housing Grants, Construction and Regeneration Act 1996 which came into force on 1 May 1998. 1

1. NATURAL JUSTICE (PROCEDURAL FAIRNESS) The issue The law An adjudicator must conduct the proceedings in accordance with the requirements of natural justice or procedural fairness. In a small number of cases, the courts have not enforced the adjudicator s decision on the grounds that the adjudicator did not act fairly, and it is evident that adjudicators do not always know exactly what it means to act in accordance with natural justice. Natural justice is not a defined term. As one judge put it: Natural justice requires that the procedure before any tribunal which is acting judicially shall be fair in all the circumstances, and I would be very sorry to see this fundamental principle degenerated into hard-and-fast rules.4 There are two main aspects to the need for procedural fairness: no bias and fair hearing. No bias: the adjudicator must be impartial and act independently. For there to be a breach of natural justice it is not necessary for there to be actual bias apparent bias is sufficient. The test is whether there is a real possibility, not probability, that the adjudicator is biased, based on how the reasonable observer would interpret the situation. Bias may occur in a number of ways; for example, if the adjudicator: has, or appears to have, a personal relationship with one of the parties; has, or appears to have, an interest in the outcome of the adjudication (a conflict of interests); conducts the adjudication in a manner which favours, or seems to favour, one party; acts in a manner which is seen, or might be seen, as supporting one party to the detriment of the other. Fair hearing: this means ensuring that each party: has a reasonable opportunity of presenting its case; knows what the case against it is; is in possession of all the evidence and information that is adduced against it or obtained by the adjudicator. The words do not imply that an oral hearing or meeting is necessary. These requirements have to be measured in the context of the time within which the adjudicator has to reach his decision, and the fact that the decision is provisional, pending final resolution of the dispute by arbitration, litigation or agreement. As one judge put it: It is accepted that the adjudicator has to conduct the proceedings in accordance with the rules of natural justice or as fairly as the limitations imposed by Parliament permit.5 4 Wiseman v Borneman [1971] AC 297 HL, per Lord Reid at 308B. 5 Glencot Development & Design Company Ltd v Ben Barrett & Son (Contractors) Ltd [2001] BLR 207, TCC, at p 218, per Judge Humphrey LLoyd; see too Discain Project Services Ltd v Opecprime Development Ltd [2001] BLR 285, TCC, Judge Bowsher. 2

Guidance for adjudicators 1. If you are aware of any connection, however remote, that you have or have had with either party, or of any matter which either party might see as being a conflict of interests, notify the parties and consider refusing the appointment. If anything comes to light after you have been appointed, ask the parties if they wish you to continue; if necessary, resign.6 2. Ensure that all your actions are, and are seen to be, fair. Before taking any action, (for example, declining to accept late information7) ask yourself: Am I acting fairly? Does it appear that I am acting unfairly? 3. Although the Scheme does not make express provision for the submission of a response to the referral notice, give the responding party a reasonable opportunity to respond, and consider any response that is served.8 You may also instruct that a response is served, and specify the timetable for this to be done.9 4. Use great care if you communicate with one party (or its representatives, experts or witnesses) in the absence of the other, either in a meeting or over the telephone. If contact with one party alone is necessary or unavoidable, keep a detailed record of what is said and send it to both parties as soon as practicable. If you receive unsolicited telephone calls, consider requiring that the information is conveyed in a form which can be sent to the other party and yourself, for example by fax or email. Ensure that both parties know what is happening at all times. 5. In the case of necessary telephone calls, consider using telephone conferencing. 6. Consider obtaining the views of the parties before making directions other than those you consider routine. 7. Notify as early as possible final deadlines for the supply of information and dates for meetings. 8. Although your role is investigatory and inquisitorial, when undertaking investigations ask yourself whether you are attempting to make or supplement one party s case; do not argue the case for one of the parties, either before or when giving your decision, or in setting out your reasons. 9. Consider carefully before indicating disapproval of the way in which one party conducts his case. 10. Guard against seeming to have made up your mind as to the merits of the case before having heard or seen all the evidence. 11. Ensure that any information on which you intend to rely in reaching your decision is known to both parties, so that they both have an opportunity of responding. 6 The Scheme, paragraph 9(1). 7 The Scheme, paragraph 15. 8 The Scheme, paragraph 17. 9 The Scheme, paragraph 13(a). 3

2. CHALLENGES TO JURISDICTION The issue Almost the only way that a party can stop an adjudication proceeding is by alleging that the adjudicator lacks the jurisdiction that is, the authority to deal with the issues raised. If an adjudicator proceeds without the necessary jurisdiction his decision will not be enforceable. On the other hand if he fails to proceed when he does have jurisdiction, that is unjust to the referring party. Examples of grounds on which jurisdictional challenges may be made are: the contract is not a construction contract within the Act;10 the relevant activities are not construction operations within the Act;11 the adjudicator was not properly appointed, for example because he is not the adjudicator named in the contract, the wrong Adjudicator Nominating Body made the appointment, the appointment was too late, or the adjudicator has a conflict of interests; it is asserted that there is no dispute. The law Unless the parties otherwise agree, an adjudicator does not have the power to make a final decision as to whether he has jurisdiction to act as an adjudicator under the Scheme; only the courts can do that. However, as one judge put it: It is clearly prudent, indeed desirable, for an adjudicator faced with a jurisdictional challenge which is not a frivolous one to investigate his own jurisdiction and to reach his own non-binding conclusion as to that challenge. An adjudicator would find it hard to comply with the statutory duty of impartiality if he or she ignored such a challenge. 12 Guidance for adjudicators 1. If you are faced with a jurisdictional challenge, you should investigate, seek the views of the parties and reach your own conclusion on the merits of the challenge. If you fail to do so, it may seem that you are not impartial. 2. If you conclude that you do have jurisdiction, you should tell the parties immediately and continue with the adjudication. 3. If you conclude that you do not have jurisdiction, you should tell the parties immediately and give notice in writing of your intention to resign. 13 4. If you are unsure whether you have jurisdiction, nevertheless make a judgment as to whether to proceed or resign. If you proceed, consider obtaining confirmation from the referring party that it wishes you to continue. 5. If you proceed, consider obtaining confirmation from the referring party that it wishes you to continue. 10 The Act, sections 104 to 107. 11 The Act, section 105. 12 Christiani & Nielsen Ltd v The Lowry Centre Development Company Ltd unreported, 29 June 2000, TCC, per Judge Thornton. 13 The Scheme, paragraph 9(1). 4

3. INTIMIDATORY TACTICS The issue There is growing evidence that some adjudicators are experiencing intimidatory or bullying tactics from the parties or their representatives during the course of an adjudication. For example, undue pressure may be put on the adjudicator to adopt a course of action desired by one of the parties. This may be by means of aggressive threats or other actions designed to reduce the control that the adjudicator has over the process. It may involve: making spurious challenges to the adjudicator s jurisdiction; causing delay with the intention of obtaining an extension of time; deliberately confusing the adjudicator through the use of technical or esoteric legal arguments; threatening to take no further part in the adjudication or to take legal action against the adjudicator, or to report him to his professional institution. The law Paragraph 13 of the Scheme lists some of the steps that an adjudicator can take in order to determine the dispute, and paragraph 14 requires the parties to comply with any request or direction of the adjudicator. Guidance for adjudicators 1. Recognise such tactics early and counter them firmly but fairly. Remember that you are in control of the procedure. 2. Where necessary, require that all arguments are put in writing with a copy sent to the other party. 3. Follow the advice regarding telephone calls in section 1 (page 3, paragraph 4), that a detailed record be kept. Consider refusing to discuss any matter over the telephone. 4. Respond politely but firmly if a party is behaving in an intimidatory manner; it may be appropriate, where arguments are being put forward aggressively or at undue length, to limit the length of submissions that may be made. 5. Always remember that while issues raised by the parties should be taken into account, they or their representatives should not deflect you from the duties placed upon you. 6. If one party goes to court, for example to challenge jurisdiction, continue the adjudication unless both parties agree otherwise or the court so directs. 7. Remember that adjudication is a rapid procedure leading to a provisional decision and that, if need be, the complexities of the underlying dispute can be resolved in arbitration or litigation. 8. Do not lose your temper! 5

4. UNMANAGEABLE DOCUMENTATION The issue Sometimes one party submits unmanageable and disproportionate quantities of documentation to the adjudicator, making it difficult for the other party to respond and for the adjudicator to reach his decision within the time limit. Some adjudicators express concern that if they seek to limit the amount of paperwork that they receive or consider, they will be vulnerable to challenge either on the grounds of natural justice or because it would be a breach of paragraph 17 of the Scheme (which requires the adjudicator to consider any relevant information). They (wrongly) believe that they must take into account all information submitted to them in the course of the adjudication. The law As explained, natural justice requires (amongst other things) that the adjudicator must give each party a reasonable opportunity to present its case and act fairly between the parties. However, fairness must be set within the context of adjudication as a fast and interim procedure. Paragraph 17 of the Scheme requires the adjudicator to consider any relevant information submitted to him. Paragraph 13(g) gives the adjudicator power to limit the length of written documents submitted to him. Guidance for adjudicators 1. The responsibility for judging what is or is not relevant information lies with you but in principle it is information that is evidential of the issues or events that a party has to prove in order to further its case. 2. The duty in paragraph 17 also needs to be considered in the light of the extensive powers given to you by paragraph 13. In particular consider giving directions as to the timetable, any deadlines, or limits as to the length or quantity of written documents. 3. Consider seeking consent to an extension of time in order to give you a proper opportunity to consider the papers and the other party s response.14 4. Remember that you are in control of the procedure. Consider limiting at the outset the amount of material to be submitted, taking into account the nature and value of the dispute. To prevent documents being drip-fed, you can stipulate that all submissions and all documents must be received by a certain date.15 5. Consider requiring a party to provide a concise statement of its case, cross referenced to a bundle of back-up documentation, and a chronology (although an extension of time may also be needed). 6 14 The Scheme, paragraph 19(1). 15 The Scheme, paragraph 13(g).

Guidance for adjudicators 6. Consider whether the documentation properly relates to the dispute being adjudicated or to another issue (which may or may not be a dispute between the parties). The introduction of matters that have not been canvassed by the referring party at or before the referral may point to there not yet being a dispute within your jurisdiction.16 7. Consider your powers under paragraph 15 of the Scheme where a party declines to comply with a request without showing sufficient cause. 16 Edmund Nuttall Ltd v RG Carter Ltd [2002] EWHC 400, TCC, Judge Seymour (available on www2.bailii.org), and Fastrack Contractors Ltd v Morrison Construction Ltd [2000] BLR 168, TCC, Judge Thornton. 5. REASONS FOR THE DECISION The issue The law The adjudicator is obliged to give reasons for his decision if requested by one of the parties. The possibility of receiving a request at a late stage during the adjudication, or even after the decision has been given, has caused concern amongst adjudicators. Paragraph 22 of the Scheme provides: If requested by one of the parties to the dispute, the adjudicator shall provide reasons for his decision. The adjudicator also has a wide discretion, under paragraph 13(g) and (h) to give directions as to the timetable for the adjudication, any deadlines and issue other directions relating to the conduct of the adjudication. Guidance for adjudicators 1. Consider setting a date at the outset by which any request to give reasons must be made. 7

6. ACCIDENTAL ERRORS OR OMISSIONS The issue The law Uncertainty has arisen regarding the extent to which an adjudicator may correct accidental errors or omissions (errors) in his decision once it has been delivered to the parties. Once the adjudicator has delivered his decision, his jurisdiction over the dispute is ended. However, where there is an error on the face of the decision, it seems that the adjudicator retains a power to make corrections. As one judge put it: in the absence of a specific agreement by the parties to the contrary, there is to be implied into the agreement for adjudication the power of the adjudicator to correct an error arising from an accidental error or omission or to clarify or remove any ambiguity in the decision which he has reached, provided this is done within a reasonable time and without prejudicing the other party. 17 The power is contractual, so the parties are at liberty either to exclude the power or to limit it as they see fit (for example, in a contractual adjudication procedure). Alternatively, the adjudicator or Adjudicator Nominating Body may set out the terms of the power in the appointment agreement. It is for the adjudicator to decide whether there is an error or not. The following types of error are covered, according to Bloor: accidental error; omission; clarification; removal of ambiguity. This generally reflects section 57 of the Arbitration Act 1996. By analogy with arbitration, an adjudicator may correct his award to give true effect to his first thoughts and intentions, but would not be able to change the substantive decision because he has second thoughts or intentions. Correction of the error must take place within a reasonable time bearing in mind the speed of the adjudication procedure. In the case of Bloor, this was within two and a half hours of publication of the decision; however in another case, Mr Justice Dyson, as he then was, found it at least arguable that the adjudicator had the right to correct a mistake after more than a week.18 17 Bloor Construction (UK) Ltd v Bowmer & Kirkland (London) Ltd [2000] BLR 314, TCC, at p 320, per Judge Toulmin. 18 Edmund Nuttall Ltd v Sevenoaks District Council unreported, 14 April 2000, TCC. 8 G U I D A N C E F O R A D J U D I C A T O R S

Guidance for adjudicators 1. Always check whether the parties have made an agreement excluding or limiting your right to make corrections. If they have, comply strictly with such agreement. 2. You may become aware that you have made an error, or one of the parties may raise the matter with you. In either case, consider inviting the parties (or other party) to make submissions to you. 3. If you are satisfied that you have made an error, correct it as soon as possible and notify the parties. 4. Bear in mind how much time has elapsed since you delivered the decision, and any action that the parties may have taken. 5. Remember that you have the right to decide that you have not made an error. 6. It may be appropriate (for example, in the case of decisions involving complex arithmetical calculations) to consider issuing a draft decision (in whole or part) a short time before delivering your final decision, inviting the parties to scrutinise it for possible accidental errors. 7. Never forget your primary duty to act fairly as between the parties. 9 G U I D A N C E F O R A D J U D I C A T O R S

7. THE PARTIES COSTS The issue The law There has been some uncertainty as to whether or not the adjudicator has power to decide that one party pay another party s costs. The Scheme is silent on the question of the parties (as opposed to the adjudicator s) costs. It was generally understood by the industry that, in the absence of any express provision in the Act or the Scheme, the adjudicator did not have the power to order one party to pay another s costs. Some doubt was thrown on this when in one case it was decided that the Scheme gave the adjudicator the power to award costs as part of his case management powers.19 In a subsequent case, the judge expressly disagreed with this view and this has been reinforced by a further case. In both instances, the judges clearly say that neither the Act nor the Scheme gives the adjudicator power to award costs.20 Indeed, the second case goes further and says that a party s costs of an adjudication cannot be recovered as damages in a subsequent court action. In all the cases the judges acknowledge that the parties are free to give the power to an adjudicator by contract. Guidance for adjudicators 1. It now appears clear that, in adjudications under the Scheme, each party is responsible for its own costs and you do not have the power to order one party to pay another s costs. It may be possible for you to be given that power by the parties, either by the terms of the adjudication procedure, or by the parties so agreeing after the dispute has arisen. 19 John Cothliff Ltd v Allen Build (North West) Ltd unreported 29th July 1999, Liverpool CC, Judge Marshall Evans, [1999] CILL 1530; the Scheme, paragraph 13(h). 20 Northern Developments (Cumbria) Ltd v J & J Nichol [2000] BLR 158, TCC, Judge Bowsher and Total M and E Services Ltd v ABB Building Technologies Ltd [2002] EWHC 248, TCC, Judge Wilcox (available on www.bailii.org/ew/cases). 10 G U I D A N C E F O R A D J U D I C A T O R S

Published by the Construction Umbrella Bodies Adjudication Task Group c/o Construction Industry Council, 26 Store Street, London WC1E 7BT tel 020 7637 8692 www.cic.org.uk Designed and printed by Astwood Design Consultancy