EIA CASE LAW UPDATE. Andrew Byass

Similar documents
EIA: nuts and bolts. James Maurici Q.C. Landmark Chambers

Recent developments in environmental and agricultural law. UKAEL Conference, September 2011: EU LAW AND THE LAND. Gwion Lewis

The Thirty-Nine Essex Street Annual Review of Planning Case Law

Before : LORD JUSTICE PATTEN LORD JUSTICE BEATSON and SIR STANLEY BURNTON Between :

Assessment - Don t let the tail wag the dog. Richard Kimblin No. 5 Chambers 1

EIA screening: themes from the recent case law. Zoë Leventhal Landmark Chambers 13 March 2015 At Oxford City Council

-and- SKELETON ARGUMENT ON BEHALF OF THE APPELLANT

ENVIRONMENTAL LAW UPDATE. TIM BULEY Landmark Chambers

-and- APPROVED JUDGMENT

Environmental Law and Planning Update

Planning and Environment Case Law Update. Richard Harwood QC, Martin Edwards and Caroline Allen

Judgment Approved by the court for handing down

Habitats Issues in Plan-Making. Alex Goodman Landmark Chambers

5.1 The new Planning Bill will incorporate a number of general provisions underlying its operation. These are likely to include:

ENVIRONMENTAL IMPACT ASSESSMENT, STRATEGIC ENVIRONMENTAL ASSESSMENT and THE HABITATS DIRECTIVE: RECENT DEVELOPMENTS

07/03/2018. Cases. Case law update Kate Ashworth. Forest of Dean District Council and Resilient Energy Serverndale Limited v R(Peter Wright)

Recent Developments in Case Law. Presented by Hashi Mohamed RTPI South East May 2018

Time limits and service in judicial review and statutory challenges

AVOCETTA MADRID MEETING 2012 UNITED KINGDOM 1 RICHARD MACRORY

Judicial Review. Where do we stand? Will proposals for further judicial review reform make any difference? Procedure & Practice

Before : SIR GEORGE NEWMAN (sitting as a Deputy High Court Judge) Between :

Environmental judicial review. Paul Stookes

THE GENERAL POWER OF COMPETENCE UNDER THE LOCALISM ACT 2011

OVERCOMING IMPEDIMENTS - SIMON PICKLES

Before : THE HONOURABLE MR JUSTICE SINGH Between :

The Pinsent Masons Planning Toolkit Series

Before: LORD JUSTICE SULLIVAN LADY JUSTICE GLOSTER and LORD JUSTICE VOS Between:

Interim relief and urgent applications and the post permission stage

Before: MR JUSTICE WYN WILLIAMS Between:

ASYLUM AND IMMIGRATION TRIBUNAL

Ensuring access to environmental justice in England and Wales

Planning, Local Government & Administrative Law Case Update. April by Mark C. Mohammed, Advocate

Before : MR JUSTICE KENNETH PARKER Between :

A LEADING LAW FIRM WITH A APPROACH

Castle Debate Climate Change Litigation Richard Wald Barrister 39 Essex Chambers

Planning obligations and CIL. Nathalie Lieven QC

PLANNING APPEALS: HIGH COURT CHALLENGES. Stephen Morgan Landmark Chambers

ENVIRONMENTAL LAW UPDATE FEBRUARY 2015 RICHARD WALD CATHERINE DOBSON

Since joining Chambers in 2014, Alexander is developing a busy specialist practice at the planning and local government bar.

PERMITTED DEVELOPMENT ISSUES

Prior Approval of Permitted Development Ongoing Problems and Issues

Planning Case Law Update 1. John Pugh-Smith, Ned Helme, Zack Simons RSS... 4 SEA&EIA... 9

R (Champion) v North Norfolk District Council

SWALA - 1 st March Planning law topic. Housing land supply: how far can you go in the Administrative Court?

Before: THE HONOURABLE MR JUSTICE BARLING (President) LORD CARLILE OF BERRIEW QC SHEILA HEWITT. Sitting as a Tribunal in England and Wales BAA LIMITED

Before : LORD JUSTICE PILL LADY JUSTICE ARDEN and LORD JUSTICE SULLIVAN Between :

Before : HIS HONOUR JUDGE ROBINSON Between :

Before: The Chancellor of the High Court Lord Justice Lindblom and Lord Justice Hickinbottom Between:

Before : THE HONOURABLE MRS JUSTICE LANG DBE Between :

39 Essex Street ENVIRONMENTAL & PLANNING LAW UPDATE 1 Top 10 Planning and Environmental Cases of February 2015

Before: LORD JUSTICE SULLIVAN LORD JUSTICE TOMLINSON and LORD JUSTICE LEWISON Between:

A joint CPRE/ELF guide Plan B: How to challenge bad developments in court

A LEADING LAW FIRM WITH A APPROACH

IN THE COURT OF SESSION WRITTEN SUBMISSIONS FOR THE UNITED NATIONS HIGH COMMISSIONER FOR REFUGEES IN THE APPLICATION FOR LEAVE TO APPEAL BY I.A.

CITY OF LONDON LAW SOCIETY PLANNING AND ENVIRONMENTAL LAW COMMITTEE

ENVIRONMENTAL IMPACT ASSESSMENT: AVOIDING THE ELEPHANT-TRAPS

Before: THE HON. MRS JUSTICE NICOLA DAVIES DBE Between :

SECTION 106 AND CIL Andrew Parkinson

COSTS IN JUDICIAL REVIEW. Richard Turney

ENFORCEMENT ACTION AGAINST UNLAWFUL DEVELOPMENT BY GYPSIES

Judgment As Approved by the Court

CHALLENGING DEVELOPMENT PLANS IN THE HIGH COURT MAY 2013 SASHA WHITE Q.C.

K v London Borough of Hillingdon (SEN) [2011] UKUT 71 (AAC) ADMINISTRATIVE APPEALS CHAMBER

IN THE COURT OF APPEAL. Between THE ATTORNEY GENERAL OF TRINIDAD AND TOBAGO. And

Plan B: How to challenge bad developments in court. A short guide to how and when you can challenge planning decisions in the courts

JUDGMENT. R (on the application of AA) (FC) (Appellant) v Secretary of State for the Home Department (Respondent)

Housing Law Update. April Daniel Skinner Batchelors

Before : MR JUSTICE DOVE Between :

PROCEDURAL UPDATE. Richard Moules. Landmark Chambers

PLANNING CASE LAW UPDATE

Before : PRESIDENT OF THE QUEEN'S BENCH DIVISION LADY JUSTICE SMITH and LORD JUSTICE AIKENS Between :

B e f o r e: DAVID ELVIN QC. (Sitting as a Deputy High Court Judge) Between: THE QUEEN ON THE APPLICATION OF WYNN-WILLIAMS

IN THE UPPER TRIBUNAL

It s a fair cop: Supreme Court reviews duty of care

Before : THE HONOURABLE MR JUSTICE SUPPERSTONE Between :

Ministry of Justice: Judicial Review proposals for reform Response by Thompsons Solicitors January 2013

THE ILLEGALITY DEFENCE FOLLOWING. Patel v Mirza [2016] UKSC 42

(2) Portland and Brunswick Squares Association

Before : HIS HONOUR JUDGE PLATTS Between : - and -

Petitioner: Carmichael, QC, Bryce; Drummond Miller LLP. Respondent: McIlvride; Office of the Advocate General

Proportionality and Legitimate Expectation Jonathan Moffett. Introduction

nplaw Planning and Environmental Law Newsletter October 2017 Norfolk Public Law

The Home at the Bottom of the Garden - Immunity from Enforcement Issues in Planning.

Chapter 11: Appeals and other supplementary provisions

JUDGMENT. O Connor (Appellant) v Bar Standards Board (Respondent)

"A very talented junior who can more than hold his own in the company of QCs." Chambers and Partners 2017

HIGH COURT PLANNING CHALLENGES COSTS: AARHUS, THE SULLIVAN REPORT, BUGLIFE AND HINTON ORGANICS. Nathalie Lieven QC

Before : DAVID CASEMENT QC (Sitting as a Deputy High Court Judge) Between :

Protective Costs Orders in UK Environmental and Public Law Cases. John Litton QC

Under construction: drafting and interpretation of land options

Upper Tribunal Immigration and Asylum Chamber. Judicial Review Decision Notice

What is required to satisfy the investigative obligation under Article 2 and/or 3 ECHR? JENNI RICHARDS

RURAL PLANNING UPDATE. By Jonathan Easton

Before : MR JUSTICE GREEN Between :

TIME TO REVISIT FORUM NON CONVENIENS IN THE UK? GROUP JOSI REINSURANCE CO V UGIC

Challenges to Development Plans new plans, new problems; The Planning and Compensation Bill

LAW SHEET No.5 THE DISCRETION OF THE CORONER

Neighbourhood Planning

Bristol Planning Law and Policy Conference Legal Update

A2 self-employed workers and social welfare rights - Solovastru v Minister for Social and Family Affairs

Transcription:

EIA CASE LAW UPDATE Andrew Byass

Themes The standard of review Screening decisions: split development Screening decisions: cumulative effects Planning enforcement / retrospective permission HS2 (briefly)

The standard of review: screening (1) R. (on the application of Evans) v SSCLG [2013] EWCA Civ 114; [2013] J.P.L. 1027 Mr Evans relied on the Aarhus Convention and on the Aarhus Convention Compliance Committee's December 2010 report expressing concern about the Wednesbury approach to say that the Wednesbury test was inadequate to review screening decisions The Court upheld the Wednesbury approach applied in R. (on the application of Loader) v SSCLG [2012] EWCA Civ 869, which had in turn relied upon the ECJ s judgment in Commission v United Kingdom (C-508/03)

The standard of review: screening (2) Per Pill LJ (Toulson and Sullivan LLJ agreeing) in Loader: 43. What emerges is that the test to be applied is: Is this project likely to have significant effects on the environment? That is clear from European and national authority, including the Commission Guidance at B3.4.1. The criteria to be applied are set out in the Regulations and judgment is to be exercised by planning authorities focusing on the circumstances of the particular case. The Commission Guidance recognises the value of national guidance, and planning authorities have a degree of freedom in appraising whether or not a particular project must be made subject to an assessment. Only if there is a manifest error of assessment will the [Court] intervene...

The standard of review: further information (1) R. (on the application of Evans) v Basingstoke and Deane BC [2013] EWHC 899 (Admin) A different Mr Evans sought to argue that the adequacy of further information provided under regulation 19 of the EEA Regulations should not be reviewable on Wednesbury grounds. Instead, it should be for the Court to decide The argument: whereas an environmental statement by virtue of the EEA Regulations must contain information as is reasonably required, no qualification of reasonableness exists in regulation 19 (see at [172]).

The standard of review: further information (2) The submission was rejected. The considerations that lead to Wednesbury review of environmental statements (following the decision of Sullivan J in R (on the application of Blewett) v Derbyshire County Council [2003] EWHC 2775 (Admin)) apply mutatis mutandis to further information : It is not necessary or desirable for statements or further information to address every conceivable environmental impact The statutory scheme provides opportunities for consultation, including in respect of further information, which are specifically in place to redress deficiencies

Screening decisions: split development (1) R. (on the application of Save Britain's Heritage) v SSCLG [2013] EWHC 2268 (Admin) The issue was when does demolition fall to be assessed as part of wider redevelopment proposals If it can be shown that the demolition will proceed irrespective of future development (here the Chapel to be demolished was derelict and a hazard) then likely no splitting or salami slicing (see at [258]) The test is objective albeit in assessing the circumstances evidence as to the intentions of the developer was both relevant and admissible (see at [291])

Screening decisions: cumulative effect (1) R. (on the application of Burridge) v Breckland DC [2013] EWCA Civ 228 Two applications for planning permission: (1372) for a biomass renewable energy plant and (0445) for a combined heat and power plant. (0455) was to be powered by the biogas produced by (1372), carried by a connecting pipeline It was argued that the applications should not be treated together as an application under regulation 7 of the EEA Regulations, following R (on the application of Candlish) v Hastings BC [2006] Env LR 13

Screening decisions: cumulative effect (2) This argument was rejected. A purposive approach that accorded with reality was needed. The reality included that: The applications were linked on their face The officer reports expressly linked one to the other The applications came before the Planning Committee for consideration on the same date The decisions in respect of the applications were issued on the same date This avoided the problem of neither project exceeding the relevant threshold in Schedule 2 and so EIA being entirely avoided (see at [80])

Planning enforcement (1) R. (on the application of Evans) v Basingstoke and Deane BC [2013] EWCA Civ 1635 The same Mr Evans who sought to argue that the adequacy of further information should not be reviewed on Wednesbury grounds At first instance and on appeal, he had also argued that the provisions in the TCPA 1990, s. 171B, conferring immunity against enforcement were contrary to Community law It was an attempt to re-open the thrust of the matters sought to be raised in Commission v UK (Case C-98/04), but which had been ruled inadmissible and never enlivened again

Planning enforcement (2) Stadlen J at first instance rejected the argument, inter alia, on the basis of the Community law principle of legal certainty. An analogy could be drawn with the time limits imposed in respect of bringing legal proceedings to challenge administrative decisions The CoA, in an ex tempore judgment, upheld Stadlen J s judgment for essentially the same reasons. Since it is Community law that cloaks the enforcement provisions with legality, there can be no conflict with the EIA Directive

Planning enforcement (3) S. 102 TCPA 1990 (relating to discontinuance of use or removal of buildings) was raised as a potential means of remedy. Such reliance was rejected: it is a draconian power, likely requires payment of compensation, and requires consideration of the development plan and to any other material considerations Failure to exercise the power under s. 102 upon request by a Claimant is an area of potential future challenge

Planning enforcement (4) R. (on the application of Baker) v Bath and North East Somerset Council [2013] EWHC 946 Ms Baker lived near a waste composting facility which had operated in breach of planning conditions and then without planning permission Her challenge was to the failure to take enforcement action following a positive screening direction made by the Secretary of State, in reliance upon the first instance judgment in Ardagh Glass Ltd v Chester City Council [2009] EWHC 745 (Admin) Delays ensued after the screening direction, relating to the provision of an environmental statement

Planning enforcement (5) Mr Justice Kenneth Parker held that there was no duty to take immediate enforcement action in respect of unlawful EIA development There had however been a delay of some 14 months in producing a environmental statement, up to February 2013, and a request at this time for a further three months to produce such a statement It was held to be reasonable to allow this extra time. A then recently instructed environmental consultant had attended a meeting at the Council in February 2013 and had provided assurances about the provision of the environmental statement, which the Council was entitled to accept

Retrospective permission (1) R (on the application of David Padden) v Maidstone Borough Council [2014] EWHC 51 (Admin) Challenge to retrospective permission for recreational fishing lakes, involving importation of 650,000m 3 of construction waste material Evidence of consequential ground water flooding at nearby property Council granted permission having considered the content of an ES which was alleged to be deficient and without considering, inter alia, whether (1) there were exceptional circumstances and (2) an unfair or improper advantage had been gained

Retrospective permission (2) Need to consider exceptionality / unfair or improper advantage arose from C-215/06 Commission v Ireland and Ardagh Glass [2011] P.T.S.R. 1498 Per Commission v Ireland, it should remain the exception Per Ardagh Glass, the decision-maker should consider: whether granting permission would give the developer an advantage he ought to be denied, whether the public can be given an equal opportunity to form and advance their views and whether the circumstances can be said to be exceptional The failure to consider these matters resulted in the quashing of the decision

Conclusion HS2 Action Alliance Limited, Buckinghamshire County Council & Others, Heathrow Hub Limited & Another v Secretary of State for Transport [2014] UKSC 3 As to the relationship between SEA and EIA, at [34], quoting Commission guidance: The two directives are to a large extent complementary: the SEA is up-stream and identifies the best options at an early planning stage, and the EIA is down-stream and refers to the projects that are coming through at a later stage. In theory, an overlap of the two processes is unlikely to occur.