The External Resettlement Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project

Similar documents
The External Resettlement Monitoring & Assessment Report

People s Republic of China: Hunan Flood Management Sector Project, Hunan Province, Chenxi County

Resettlement Plan. Urban Flood Control Project Utilizing ADB Loans

Resettlement Plan. Urban Flood Control Project Utilizing ADB Loans

Prepared by Guangxi Baise Development and Investment Group Co., Ltd. with the assistance of Beijing Enrimu Science & Technology Consulting Co., Ltd.

People s Republic of China: Hunan Flood Management Sector Project (Shimen County Subproject)

PRC: Liaoning Small Cities and Towns Development Demonstration Sector Project

External Resettlement Monitoring and Evaluation Report of the World Bank-financed Xining Water Environment Management Project

PRC: Guangxi Southwestern Cities Development Project - Resettlement Due Diligence Report of Shijinglin Road Extension

PRC: Hunan Roads Development II Project External Monitoring Report on Land Acquisition and Resettlement For Yuanling Local Road(II)

Shanxi Small Cities and Towns Development Demonstration Sector Project

External Ethnic Minority Development Monitoring and Evaluation Report. PRC: Hunan Flood Management Sector Project

External Resettlement and Social Development Monitoring and Evaluation Report

Resettlement Plan. PRC: Jiangxi Ji an Sustainable Urban Transport Project. November 2017

Resettlement Policy Framework

CHAPTER 23: DETENTION BASIN STANDARDS Introduction and Goals Administration Standards Standard Attachments 23.

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF)

People s Republic of China: Yunnan Chuxiong Urban Environment Improvement Project

External Resettlement Monitoring and Evaluation Report. People s Republic of China: Guiyang Integrated Water Resources Management (Sector) Project

People s Republic of China: Guizhou Rocky Desertification Area Water Management Project

Resettlement Plan. the Yimu Highway Kedian to Mujiating Section Improvement. Project

PRC: Guiyang Integrated Water Resources Management (Sector) Project

Proposed Loan People s Republic of China: Hebei Elderly Care Development Project

PRC: Guangxi Beibu Gulf Cities Development Project

Article 2These Regulations apply to the residents-resettlement for the Three Gorges Project construction.

PRC: Anhui Chao Lake Environmental Rehabilitation Project

For Harbin Municipal Government Harbin Municipal Water Supply Construction Leading Group Office

PRC: Yunnan Pu er Regional Integrated Road Network Development Project

Annex 2: Does the Xayaburi resettlement comply with Lao law?

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents

Ethnic Minorities Development Framework. PRC: Guiyang Integrated Water Resources Management Sector Project

Guizhou Vocational Education Development Program Land Acquisition and Involuntary Resettlement Due Diligence

PRC: Chongqing Urban Rural Infrastructure Development Demonstration II Project

People s Republic of China: Yunnan Chuxiong Urban Environment Improvement Project

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

RP1633 V3. Resettlement Action Plan. the Anji Subproject. Anji County Government June 2014

Key Issues: Climate Zone: As: Tropical humid. Subjects: - Restoration of livelihood and Rebuilding of Resettled Communities

Indira Sagar Dam. Rs crore but expected to be nearly Rs. 5,000 crore Loss

PRC: Hunan Roads Development III Project Huayuan-Fenghuang Local Road Component

People s Republic of China: Gansu Baiyin Integrated Urban Development Project

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

PRC: Hubei Huangshi Urban Pollution Control and Environmental Management Project

Canterbury Regional Council Flood Protection and Drainage Bylaw 2013

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

RESETTLEMENT ACTION PLAN SHALA NEIGHBOURHOOD HADE PROJECT KOSOVO MONITORING REPORT 1

PRC: Guizhou High Efficiency Water Utilization Demonstration in Rocky Desertification Area Project

CHAPTER 29 DRAINAGE AND DITCHES

PRC: Hefei Urban Environment Improvement Project

Hamilton City Council BYLAWS HAMILTON STORMWATER BYLAW 2015

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

THIS RESTRICTIVE COVENANT MADE THE DAY OF, DEVELOPER/OWNER (the "Grantor") - and - THE CITY OF EDMONTON (the "City")

Public Water Supply and Sewerage Act

RP156 Volume 2. Resettlement Action Plan of Environment Improvement Projects of Dongqianhu Lake in Ningbo City. (The 5th Edition)

EASES Discussion Paper Series SUCCESSFUL RESERVOIR RESETTLEMENT IN CHINA SHUIKOU HYDROELECTRIC PROJECT

Social Management Policy Framework

Wangliao Road (8#) Extension Construction Project in Yongchuan District. Resettlement Action Plan

Key Words: Song Hinh Multipurpose Project, Resettlement, Project Management Board

Subproject: Hai Lang Province: Quang Tri

PRC: Anhui Integrated Transport Sector Improvement Project X056 Shantou, Sixian County- Minxian, Yongqiao District Section

LANDSLIDE PREVENTION LAW

Summer School November Beng Hong Socheat Khemro Ph.D. (UCL, London, England, UK)

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

DISTRICT OF LAKE COUNTRY BYLAW 628, CONSOLIDATED VERSION (Includes amendment as of July 18, 2017)

FILE COPY. Resettlement Action Plan. RP211 Volume 5. World Bank Loan Hunan Urban Development Project. Corridor Component (Zhaoshan Section)

Soil and Watershed Conservation Act, 2039(1982)

FLOOD RISK MANAGEMENT BILL 2011

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

USJI Seminar Washington, DC (19 February 2013) Toward a New Paradigm for Resettlement Policy. Mikiyasu Nakayama

Public Transport Sub-project of Urban Comprehensive Transport Improvement Project in Xi an the south of urban bus hub terminal

MON: Urban Development Sector Project Bulgan Subproject

Resettlement Policy Framework

CHARTER TOWNSHIP OF LANSING INGHAM COUNTY, MICHIGAN ORDINANCE NO. 50.2

PRC: Shaanxi Mountain Road Safety Demonstration Project

DRAINAGE ACT Revised Statutes of Ontario, 1990, Chapter D.17

IC Chapter 3. Mechanic's Liens

RP-0008 VOL. 1. Resettlement Action Plan for Shenyang Urban Transport Project. The World Bank Loan Liaoning Urban Transport Project

RESETTLEMENT ACTION PLAN

CHAPTER 3. Building Code

WAUKESHA COUNTY VILLAGE OF OCONOMOWOC LAKE STATE OF WISCONSIN ORDINANCE NO. 173 (as amended by ordinance 241)

CITY OF KAMLOOPS BY-LAW NO (AS AMENDED)

ITEM 9. Agenda of August 15, 2013

PRC: Xinjiang Tacheng Border Cities and Counties Development Project

AFG: MFF Water Resources Development Investment Program- Tranche 1, Nangarhar Valley Development Authority Grant No: 0167 AFG

DEPARTMENT OF ENVIRONMENTAL QUALITY OFFICE OF OIL, GAS, AND MINERALS FERROUS MINERAL MINING

ORDINANCE NO CHAPTER 71 EROSION AND SEDIMENT CONTROL FOR CONSTRUCTION SITES

j,~~~s I, jri Is I wnflioa LLiNLL ;;dii. is Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

PRC: Shanxi Small Cities and Towns Development Demonstration Sector Project

1.0 Purpose To provide procedural direction for the implementation of Policy PL Work Permits Section 14 Public Lands Act.

Resettlement Action Plan

CROSSRAIL INFORMATION PAPER D2 CONTROL OF ENVIRONMENTAL IMPACTS

2007 No. 320 HEALTH AND SAFETY

Flood Protection Bylaw

HIGHWAYS DEVELOPMENT AND PROTECTION ACT

STATE OF ILLINOIS COUNTY OF BUREAU GENERAL CONSTRUC TION HIGHWAY PERMIT. Whereas, I (we),, hereinafter termed the

Environment and Parks WATER ACT. BEING CHAPTER W-3 RS.A (the "Water Act") ENFORCEMENT ORDER NO. WA-EO-2018/07-LAR

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

F i. Resettlement Action Plan RP21I1. World Bank Loan Hunan Urban Development Project. Corridor Component. Mar (Changsha Section)

The World Bank Financed Zhengzhou Rail Transit Line 3 Phase 1 Project. Supplementary Resettlement Action Plan

Asian Development Bank s Involuntary Resettlement Safeguards. Project Case Studies in the People s Republic of China

Empirical Study on Utilizing Rural Settlement

Transcription:

The Loan No.: 2244-PRC The External Resettlement Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project No.3 Report Changsha Xinghuan Water & Electricity Engineering Technology Development Co., October 2008 1

Project Director : Qin Lin Deputy Project Director : Ren Yu Chen Zizhou Report Preparation: Chen Zizhou Huang Qingyun Ren Yu Li Yuntao Qin Lin Team Member: Chen Zizhou Huang Qingyun Ren Yu Xia Jihong Qin Si Qin Lin Li Yuntao Min Tian 2

Contents 1. M&E Tasks and The Implementation... 4 2. Project Overview... 4 3. Establishment of Resettlement Organization and its Function... 16 4. Engineering Implementation Progress... 23 5. Resettlement Baseline Survey... 28 6. Resettlement Implementation Progress... 36 7. The Affected Persons Appeal and Complaints... 91 8. Support of the Vulnerable Group...100 9. Public Participation, Consultation and Information Disclosure...101 10. The Main Issues and Recommendations...103 11. Conclusion...107 3

1. M&E Tasks and The Implementation ADB-funded Hunan Flood Management Sector Project started to implement in January 2007. ADB and the PPMO of the Project jointly decided that the M&E work of 19 subprojects would be undertaken by Changsha Xinghuan Water & Electricity Engineering Technology Development Co.,( CXWEETD) including 8 core subprojects ( Loudi, Xinhua, Sangzhi, Wugang, Yongzhou, Leiyang, Huaihua and Chenxi) and 11 non-core subprojects ( Cili, Xiangtan, Xupu, Shimen, Jishou, Hengyang City, Hengyang County, Fenghuang, Baojing, Zhongfang and Luxi). The M&E started in early 2007 and the CXWEETD had submitted the No.1 and No.2 M&E reports to ADB and PPMO in November 2007 and in March 2008 respectively. So far, the 6 core subprojects have signed the contract with CXWEETD including Xinhua, Sangzhi, Loudi, Wugang, Huaihua and Yongzhou and the other two subprojects had been in the contract negotiation with CWWEETD; the 4 non-core subprojects have signed the contract with CXWEETD including Cili, Xiangtan, Xupu and Shimen while the other 7 non-core subprojects were still under the contract negotiation with CXWEETD. The No.3 M&E report mainly contains the physical and resettlement implementation progress of the relevant subprojects. The Report cover 9 subprojects including Xinhua, Sangzhi, Loudi, Wugang, Huaihua, Yongzhou, Cili, Xiangtan and Xupu, of which, Cili, Xiangtan and Xupu were included into the Report at first time and therefore the relevant baseline survey was conducted. Generally speaking, resettlement and house demolition were at initial stages and the amount of completed resettlement and house demolition was not large. Hence, the key focus of M&E were on resettlement institutions, the adopted resettlement policies and compensation standards, the progress made in land acquisition and house demolition, resettlement fund raising and disbursement, resettlement information disclosure, the existing problems etc. Based on the ADB requirements, a consolidate M&E report is required coving all the relevant subprojects rather than separate report for each subproject. 2. Project Overview 2.1 Project Scope Hunan Flood Management Sector Project covers 35 counties with severe flood impact. The project area consists of 8 municipalities including Zhuzhou, Hengyang, Youzhou, Loudi, Chengzhou, Shaoyang, Huaihua and one autonomy prefecture, Jishou and 27 counties located in the 12 municipalities. The 8 core subprojects are Loudi, Xinhua, Wugang, Sangzhi, Yongzhou, Leiyang, Huaihua and Chenxi. These subproject areas have comparatively developed economy. They are not only the county seat but also the local financial, communication, commercial and cultural center where a lot of agricultural, industrial and commercial activities concentrated. Although these cities have higher elevation above the sea with 4

undulating topography and little flood impact from Dongting Lake and Four Rivers, they are prone to suffer from flash floods. The flash floods have the characteristics of quite rapid rise and large flow, causing substantive localized damage. Therefore, the Hunan Flood Management Sector Project has the great significance. 2.2 Overview of Core Subprojects 2.2.1 The Engineering Overview According to the engineering scopes and the designed flood protection standards, the structural measures of 8 core subprojects include flood control works, water-logging works, dredging and flood control roads. The total investment of 8 core subprojects is RMB 1.337907 billion Yuan including RMB 198.9377 million Yuan for resettlement cost. After the structural measures completion, the flood protection standards in municipalities will be raised to 1 in 50 year return period and the water logging standard will be raised to 1 in 20 year return period; the flood project standards in counties will be raised to 1 in 20 year return period and the water logging standards will be raised to 1 in 10 year return period. The Project will substantively reduce the flood suffering and damage. The engineering scope of each core subproject refers to table 2.2-1. 2.2.2 The Resettlement Overview The scope of resettlement and land acquisition covers areas with land acquisition and areas where people s production and their lives are unfavorably affected. According to the resettlement plans of 8 core subprojects, the total temporary land acquisition is 2666.75mu; the total permanent land acquisition is 3997.98 mu; the total affected population is 3734 households with 15396 persons; the total relocated population is 976 households with 3691 persons and the demolished house areas are 155519.8m2. The resettlement impact summary of 8 core subprojects refer to Table 2.2-2~2.2-5.. 5

Table 2.2-1 8 Core subproject Key Characteristics No. 1 City Name Flood Control works Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi Chengbei, Chengzhong two protection circles; Construction of 4 new embankments with the total length of 36.8 km including 30.90 km long earth embankment and 5.89km long earth and rock embankment; 36.8km long bank protection works and 16.684km long riprap. Construction of a new7.75km long Chengdong flood control embankments; Strengthening 4.5km long Chengxi flood control embankments. Construction of a new 15.485km long flood control embankments including 4.586km long Chengbei embankment, 4.619 km long Chengbei Hongmiao embankment and 6.28km long Chengnan embankment; Rehabilitation of 0.75 km of existing dike; Construction of a new 0.95 km river channel that will divert flood waters from the Chuangcheng River directly to the Nanshui River Construction of 5891m long flood control wall in the main urban area and the Gaoping flood control circle; Construction of 1400m long earth and rock flood control wall in the main urban area; Construction of 1192m long earth dikes;648.5m long masonry bank protection works in main urban area. Construction of 11 sections of new earth dikes with the total length of 25.979km; Construction of 4 sections of new masonry flood control walls with the total length of 8.75 km; Strengthening of the 4 existing dikes with the total length of 10.14km; Construction of 7 sections of concrete slope protection works with the total length of 4.11km; 8 sections of bank collapse rehabilitation with the total length of 10.53km. Construction of a new 12.342km long dike including 6.783 km long dike in the main urban area (5,729km long earth dike and 1.054km long flood control wall) and 5.559km long earth Shuidongjiang dike. Construction of a 13.385km long new earth dike; Construction of 9.64km long flood control wall; Construction of 13.385km long masonry slope protection works; 23.025km long grass slope protection works inside and outside of the flood control dike; Anti-seepage treatment at the foundation of dike with the length of 13.715km. Construction of a new 1220m long earth dike; Construction of gravity-typed water-retaining and earth-retaining wall with the length of 719.1m. 3

2 Water Logging Works Construction of 19 sluice gates; Construction of 2 new water logging pumping stations with capacity of 1385kW; Construction of 4 new sluice gates; 1 new drainage station with installed capacity of 465kw; Construction of 1 new diversion channel; Construction of 3 buried gates. Construction of 4 new pumping stations with capacity of 940kw/ 8 sets; 12 drainage sluice gates, 1 controlling gate, 1 flood control gates; construction of a new 6km long flood diversion channel. Construction of 9 drainage gates in three flood protection circles; Construction of 2 electricity pumping stations with the designed capacity of 220KW in three flood protection circles. Construction of 16 sluice gates including 15 gravity pumping stations and 1 traffic gate; Construction of 6 pumping stations with installed capacity of 1460kw; Construction of 1 flood diversion channel with the length of 1.3km. Upgrading 4 pumping stations, with the designed capacity of 1370kw/14 sets; Construction of 5 new drainage sluice gates. Construction of 10 new sluice gates; Construction of 4 flood diversion channels with the length of 5.44km; Construction of 7 sets of new electricity drainage pumping stations with the designed capacity of 395kw each. Construction of 2 sections of new open channels including 394m long inlet open channel and 813m long. outlet open channel; Construction of 1 new electricity pumping station; Construction of 3 new sluice gates 4

Continued 2.2-1 8 Core subproject Key Characteristics No 3 City Name Other Works Loudi Xinhua Wugang Sangzhi Youzhou Leiyang Huaihua Chenxi 26.2km long river channel dredging and disposal of spoil in Lianshui River and Sunshui River; Construction of flood control command system and other relevant supporting facilities. Construction of flood control roads and river cleaning-up. Yudai Bridge and Tiyun Bridge Enlargement; River dredging in 4 sand beaches and 2 battures. Hardening dike crest surfacing with the length of 23.025km; River dredging in the urban Construction of new masonry gravity-typed water retaining dam with the height of 50m; Construction of one new Tuoping overflow dam; Construction of a new 400m long tunnel. 4 Project Schedule The construction period is planned 34 months with 31 months for major works. The construction period is planned 48 months with 42 months for major works. The construction period is planned 36 months with 24 months for major works. The construction period is planned 37 months with 35 months for major works. The construction period is planned 49 months with 47 months for major works. The construction period is planned 40 months with 38 months for major works. The construction period is planned 48 months with 45 months for major works. The construction period is planned 18 months. 5

5 Project Cost Estimates The total subproject investment is 387.4962 million Yuan including 58.8907 million Yuan for resettlement cost. The total subproject investment is 109.92.03 million Yuan including 16.0251 million Yuan for resettlement cost. The total subproject investment is 113.6 million Yuan with 16.6043 million Yuan for the resettlement cost. The total subproject cost is 95.60 million Yuan including 15.2979 million Yuan for resettlement cost. The total subproject investment is 243.5982 million Yuan including 42.72 million Yuan for the resettlement cost. The total subproject investment is 77.3730 million Yuan including 24.115 million Yuan for resettlement cost. The total subproject investment is 196.7197 million Yuan including 23.3847 million Yuan for resettlement cost. The total subproject investment is 113.6 million Yuan including 1.9 million Yuan for resettlement cost. 6 Project Objectives The flood control standard will be raised to 1 in 50 year return period; The water logging standard will be raised to 1 in 20 year return period. The flood control standard will be raised to 1 in 20 year return period from the current 1 in 5 year return period; The water logging standard will be raised to 1 in 10 year return period. The flood control standard will be raised to 1 in 20 year return period from the current 1 in 5 year return period; The water logging standard will be raised to 1 in 10 year return period from the current 1 in 3 year return period. The flood control standard will be raised to 1 in 20 year return period from the current 1 in 2 year return period; The water logging standard will be 1 in 10 year return period from the current 1 in 2-5 year return period. The flood control standard will be raised to 1 in 20 year return period from the current 1 in 2 year return period; The water logging standard will be raised to 1 in 10 year return period from the current 1 in 2-5 year return period. The flood control standard will be raised to 1 in 20 year return period from the current 1 in 5 year return period; The water logging standard will be raised to 1 in 10 year return period from the current natural drainage conditions. The flood control standard will be raised to 1 in 20 year return period from the current 1 in 5 year return period; The water logging standard will be raised to 1 in 10 year return period from the current natural drainage conditions. The flood control standard will be raised to 1 in 20 year return period from the current 1 in 10 year return period; The water logging standard will be raised to 1 in 10 year return period from the current 1 in 3 return periods. 6

Table2.2-2 Temporary Land Acquisition Item City Administrative villages Temporary Land Occupation Area Loudi Xinhua Wugang Sangzhi Youzhou Leiyang Huaihua Chenxi 5 administrative villages in 4 townships( resident ial committees) 1243.66mu of various types of land 2 administrative villages in 1 development zone 174.5mu of various types of land 4 administrative villages in 3 townships( residenti al committees) 164.55mu of various types of land 5 administrative villages in a township 127.38mu of various types of land 10 administrative villages in 7 townships(residen tial committees) 346.4mu of various types of land 1 administrative villages in 1 township(residential committees) 118.44mu of various types of land 2 administrative villages in 2 township(residentia l committees 359.82mu of various types of land 3 administrative villages in 1 township 132mu of various types of land Types of Temporary Land Occupation Dry land 139.59mu; Shrubbery 434.94mu; Grassland 669.13mu. Dry land 33.4mu; Timber forest 18.4mu; Shrubbery 36.7mu and Grassland 86mu Dry land10.23mu; Timber forest 54.88mu; Shrubbery 99.44mu Dry land 12.74mu; Shrubbery 25.48mu; Wasteland 89.16 mu Dry land 13.6mu;Shrubber y 332.8mu Dry land 35mu;Shrubbery 33.73mu;Wasteland 49.71mu Shrubbery Dry land 40mu; Shrubbery 66mu; Wasteland 26mu. Average Land Acquisition Year 2 years 2 years 2 years 2 years 2 years 2 years 2 years 2 years 7

Table 2.2-3 Permanent Land Acquisition City Item Administrative villages Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi 16 Administrative villages in 5 townships (residential committees) 1 development zone and 6 Administrative villages 23 Administrative villages in 4 townships ( residential committees) 11 Administrative villages in 1 townships 31 Administrative villages (residential committees) in 2 districts and 11 townships. 6 Administrative villages in 2 subdistricts. 11 Administrative villages in 3 subdistricts. 3 Administrative villages in one township. Permanent Land Acquisition 1589.55mu of various of land 473.4mu of various of land 218.27mu of various of land 67.57mu of various of land 914.24mu of various of land 265.32mu of various of land 422.26mu of various of land 47.37mu of various of land Including collective land Paddy field 359.36mu; Dry land 222.96mu; Vegetable land 179.05mu; Orchard land 7.62mu; Fish pond 39.75mu; Shrubbery 11.02mu; Timber forest 81.68mu; Rural residential plot 4.59mu; Idle land 622.69mu Paddy field 366.8mu; Dry land 95.94mu;Vegetable land 2mu;Rural residential plot 8.65mu and Enterprise land 20.64mu Paddy field 100.26mu;Dry land 13.70mu; Orchard land 6.04mu; Rural residential plot 8.10mu and Idle land 61.64mu Dry land 0.57mu; Vegetable land 52.31mu; wet land 1.65mu Paddy field 126.16mu; Dry land 245.49mu; Vegetable land 99.75mu; Orchard land 22.3mu; Pond 11.1mu; Timber forest 87.49mu; Rural residential plot, 23.7mu and Idle land 129.7mu Paddy field 126.16mu; Dry land 245.49mu; Vegetable land 99.75mu; Orchard land 22.3mu; Pond 11.1mu; Timber forest 87.49mu; Rural residential plot 23.7mu; Idle land 129.7mu Paddy field 134.9mu; Dry land 8.1mu; Vegetable land 53.2mu; Pond 28.5mu; Economic forest 4.5mu; Timber forest 9.3mu; Rural residential plot 4.05mu and Idle land 124.71mu Paddy field 40.94mu; Dry land 3.5mu; Pond 0.28mu; Rural residential plot 0.81mu and Idle land 1.84mu 8

Including national land Industrial land 30.11mu; Urban residential land 16.62 mu; Urban Idle land and other land 14.1mu Industrial land 8.32mu; Urban residential land 13.20mu;Urban idle land and other land 37.01mu Urban residential land 11.32mu; Urban idle land and other land 1.72mu Industrial land 14.63mu; Urban residential land 68.73mu; Urban idle land and other land 85.19mu Industrial land 21.4mu; Urban idle land and other land 3.4mu Housing plot 12.7mu Table 2.2-4 Project Affected Persons Items City Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi Subtotal HH Pers ons HH Total Population 782 4214 628 Land Acquisition without resettlement Resettlement without land Acquisition Land Acquisition and Resettlement 631 1748 596 Per son s 201 8 176 4 HH Pers ons HH Pers ons HH Pers ons HH 414 1978 60 472 759 2612 352 1521 684 2398 55 183 3734 218 555 17 78 446 1491 257 1112 545 1916 49 152 2759 8816 113 352 6 39 193 782 41 193 301 1062 71 307 126 417 3 15 854 3167 38 136 26 133 3 10 3 8 12 59 24 102 13 65 3 11 122 524 Pers ons HH Pers ons HH Pers ons HH Pers ons 1539 6 Affected Enterprises 18 1808 4 82 11 595 8 291 33 7881 8 5284 8 210 90 1615 1 Resettled Enterprises 4 82 2 56 1 16 7 154 9

Individual shops 94 170 22 36 8 40 11 17 3 7 1 3 2 5 141 278 Economic Rehabilitation Resettlement with housing construction Vulnerable Groups Affected Ethnic Minority 1021 637 276 56 543 419 588 121 0 3661 151 488 32 172 196 792 37 176 313 1121 95 409 139 483 4 16 967 3657 39 85 22 76 9 95 15 37 14 316 139 139 Table 2.2-5 Area of Demolished Houses City Unit Loudi Xinhua Wugang Sangzhi Yongzhou Leiyang Huaihua Chenxi Subtotal Item House Demolition HH 151 32 196 44 313 95 139 6 974 Perso ns 488 172 792 201 1121 409 482 26 3685 incl Urban HH 134 155 44 290 124 746 Perso ns 421 621 201 1014 407 2664 Rural HH 17 32 41 23 95 15 6 228 10

Perso ns 67 172 171 107 409 76 26 1021 The Total Areas of House Demolition m2 30723.26 5272 14486.48 16860.04 41619.35 21506.96 24232.24 819.44 155519.8 Urban m2 26260.92 10980.41 16860.04 33025.88 18574 105701.3 Incl Rural m2 4462.34 5272 3506.07 8593.47 21506.96 5658.24 819.44 49818.52 11

2.3 Non-core Subprojects 2.3.1 The Engineering Overview The 4 non-core subprojects comprised of the flood control works, the water logging works, the river course dredging and the flood control roads etc including Cili, Xiangtan, Xupu and Shimen Counties. The total investment of these 4 subprojects was 403.27 million CNY including 71.23 million CNY resettlement cost. After the subprojects completion, the flood control and waterlogging standards will be increased to 1/50 years and 1/20 years for cities while those will be improved to 1/20 years and 1/10 years at the county level. These will dramatically reduce the risks of flooding and water logging. The engineering characteristics of each subproject were shown in the following table2.3-1. Shimen subproject didn t start the resettlement yet. The other non-core subprojects like, Jishou and others didn t signed the service contract with the CXWEETD and therefore the external M&E didn t commence yet. 2.3.2 The Resettlement Overview According to Resettlement Plans (July 2008 version) for 3 subprojects, Cili, Xiangtan and Xupu, the temporary land acquisition will be 862.03mu and the permanent land acquisition will be 757.74mu in total for these three subprojects. There will be 557 households with 2302 persons affected; the house demolition will affect 243 households with 932 persons. There will be 40061.16m2 to be dismantled. The relevant tables were shown as Table 2.3-2~2.3-5. Table 2.3-1: The Engineering Characteristics of Non-core Subprojects No. Name of Works Cili County Xiangtan City Xupu County 1 Flood control works 14.279km long new embankment; 572 m long express way; 4 km long strengthened earth embankment 2 Water Logging 5 new sluice gates; 3 pumping stations with the capacity of 1224kw; Repair of 2 drainage ditches with 1.15km length; Repair of 4 drainage ditches with 4.75km length. Shaoyanggang River Section Training works; Heightening and strengthening 11.8km long Chengnan enclosed Embankment with the flood control standard of 1/50 years The electric pumping station upgrading; 4 new pumps with the capacity of 315kw each; diversion channel dredged and cemented with 5.573 length; the foundation anti-seepage treatment in Shiwanlong embankment and 2567m long new masonry flood control wall; 770m long new earth embankment and 310m long new sub-embankment. 4 new sluice gates; 1 access gate; 800m long river block removing; 1 new electric pumping station( 3* 220kw). 12

Gongnong Gate at Shiyanggang 3 Other Works Flood control command system andalso equipped with relevant management facilities Flood control command system andalso equipped with relevant management facilities 4 Schedule The planned implementation period was 34 months and the time for main works was 24 months. 5 Budget Estimates The total investment was 93.21million CNY including 9.76 million CNY for resettlement cost The planned implementation period was 21 months and the time for main works was 18 months. The total investment was 130.45million CNY including 28.78 million CNY for resettlement cost The planned implementation period was 33 months and the time for main works was 32 months. The total investment was 63.79million CNY including 10.54 million CNY for resettlement cost 6 The Project Objectives The flood protection standards will be improved to 1/20 years from the current ½ year and the water logging standards will be improved to 1/10 years The flood protection standard will be improved to 1/100 year in the urban area. The flood protection standards will be improved to 1/20 years from the current ½ year and the water logging standards will be improved to 1/10 years Table 2.3-2: Temporary Land Occupation of Non-core Subprojects Items Cili Xiangtan Xupu Affected villages 7 villages in one town 3 subdistricts 3 villages Areas of Temporary land occupation 283.13mu for various kinds of land 390.9mu for various kinds of land 188mu for various kinds of land Types of Land occupied 54.1mu paddy field; 36.6mu dry land; 83.15mu shrubs; 24.3 mu river banks; 84.98mu wasteland 42.7mu paddy field; 41.1mu dry land; 134.4 mu timber forestry; 146.8 mu shrubs; 25.9 mu wasteland 47.7mu dry land; 60.3mu shrubs; 80mu wasteland. The average period of land occupation 2 years 2 years 2 years 13

Table 2.3-3: Permanent Land Acquisition of Non-core Subprojects Items Cili Xiangtan Xupu Affected villages 6 villages in one town 6 villages in 2 sub-districts in 2 districts 2 villages and 5 residential committees Permanent acquisition land 149.36 mu for various land 499,8mu for various land 108.58 mu for various land Including collective land 35.32 mu dry land; 14.5mu commercial vegetable land; 44.53 mu river banks; 39.97mu orchard; 1.5mu wasteland; and 11.82mu housing plot 39.6 mu dry land; 34.7 farmland; 60mu pond; 16.2mu housing plot; 41.4mu river banks. 36mu farmland; 20.88mu orchard and 2.38mu housing plot. Including land state-owned 1.72mu Urban construction land ( enterprise land) 27.2 mu industrial land; 12mu housing land and 286.6mu other lands 49.32mu urban construction land Table 2.3-4: The Affected persons of Non-core Subprojects Item No.of HH Cili Xiangtan Xupu Subtotal No.of Persons No.of HH No.of Persons No.of HH No.of Persons No.of HH No.of Persons Total Population Land acquisition House Demolition Land acquisition and House demolition Affected enterprises Individual Shops Pop. With production Rehabilitation Pop. with house rebuilding 228 595 221 1200 108 507 557 2302 188 440 54 228 65 276 307 944 32 103 167 594 35 187 234 884 8 32 8 44 16 76 1 9 7 378 11 117 19 504 5 11 3 10 8 21 74 136 116 326 33 107 167 594 43 231 243 932 14

The affected vulnerable group The affected Ethnic minorities 14 11 10 35 79 79 Table 2.3-5: House Demolition of Non-core Subprojects Item Unit Cili Xiangtan Xupu Subtotal The total Population HH 40 167 43 250 affected by house demolition Person 135 594 231 960 Including Urban Pop. Rural Pop. HH 113 35 148 Person 389 187 576 HH 33 54 8 95 Person 107 205 44 356 House Demolition Total Areas M 2 8623.16 17476 13962 40061.16 Including Urban House Area Rural House Area M 2 8777 1784 10561 M 2 8623.16 8699 12178 29500.16 15

3. Establishment of Resettlement Organization and its Function 3.1 Resettlement Organization Operation In Core Subprojects The resettlement institutions and staffing have been reported in No.1 Report and No.2 Report for Loudi, Xinhua, Wugang,Sangzhi, Huaihua and Yongzhou. The focuses of No.3 report are on the commissioning of resettlement implementation agencies, the implementation procedures, the adopted measures, the internal monitoring, information management and resettlement work performance etc. (1) Loudi Commissioning of Resettlement Implementation Agency: on May 25 2006, Loudi Flood Control Work Construction Management Division signed the Agreement on Land Acquisition and House Demolition Contracting with Loudi Land Acquisition and House Demolition Office. Implementation Procedures: After signing agreements regarding land acquisition and house demolition, the relevant compensation will be delivered to the affected villages, village groups, and communities and then to the affected people. The Adopted Measures: the RIB was distributed; the survey results regarding land acquisition and the compensation standards were disclosed in the affected villages; the resettlement staffs in the PMO held workshops and groups meetings with affected communities many times to promote the resettlement policies and listen to their opinions. The Internal Monitoring: the internal monitoring mechanism was not well established and the internal monitoring report couldn t be submitted regularly. This area should be strengthened. Information Management: a dedicated staff is responsible for information management. All the hard copies are filed. However, the computerization of the filing management is not very good. An e-database isn t established. The Resettlement Work Performance: staffs are quite familiar with the work process and the relevant laws and regulations. They listened to the APs carefully and responded to them timely. In case APs are dissatisfied with compensation standards, they explained to them very patiently. APs felt satisfied with these. (2) Xinhua Commissioning of Resettlement Implementation Agency: Xinhua PMO signed the Agreement on Land Acquisition and House with Xinhua Land Acquisition and House Demolition Office. Implementation Procedures: After signing agreements regarding land acquisition and house demolition, the relevant compensation will be delivered to the affected villages, 16

village groups, and communities and then to the affected people. The Adopted Measures: the RIB was distributed; the survey results regarding land acquisition and the compensation standards were disclosed in the affected villages; the resettlement staffs in the PMO held workshops and groups meetings with affected communities many times to promote the resettlement policies and listen to their opinions. The Internal Monitoring: the internal monitoring mechanism was not well established and the internal monitoring report couldn t be submitted regularly. Information Management: All the hard copies are filed. A preliminary resettlement information database was established. However, the information management needs to be strengthened. The Resettlement Work Performance: staffs are familiar with the work process and the relevant laws and regulations but some are not familiar with these. They strictly enforced the relevant laws and regulations. However, they should have more patience to the affected persons. (3) Wugang Commissioning of Resettlement Implementation Agency: Wugang PMO signed the Agreement on Land Acquisition and House with Wugang Land Acquisition and House Demolition Office. Implementation Procedures: After signing agreements regarding land acquisition and house demolition, the relevant compensation will be delivered to the affected villages, village groups, and communities and then to the affected people. The Adopted Measures: the RIB was distributed; the survey results regarding land acquisition and the compensation standards were disclosed in the affected villages via mass media; the resettlement staffs in the PMO held workshops and groups meetings with affected communities many times to promote the resettlement policies and listen to their opinions. The Internal Monitoring: the internal monitoring mechanism was not well established and the internal monitoring report couldn t be submitted regularly. Information Management: a dedicated staff is responsible for information management. All the hard copies are filed. A preliminary resettlement information database was established. However, the information management needs to be strengthened. The Resettlement Work Performance: staffs are quite familiar with the work process and the relevant laws and regulations. They listened to the APs carefully and responded to them timely. In case APs are dissatisfied with compensation standards, they explained to them very patiently. APs felt satisfied with these. (4) Sangzhi 17

Commissioning of Resettlement Implementation Agency: Sangzhi PMO signed the Agreement on Real Estate Appraisal with Zhangjiajie Hengtai Real Estate Appraisal Company Ltd and Agreement on Real Estate Measuring with Sangzhi County Housing Measuring Team. Implementation Procedures: After signing agreements regarding land acquisition and house demolition, the relevant compensation will be delivered to the affected villages, village groups, and communities and then to the affected people. The Adopted Measures: the RIB was distributed; the survey results regarding land acquisition and the compensation standards were disclosed in the affected villages; the resettlement staffs in the PMO held workshops and groups meetings with affected communities many times to promote the resettlement policies and listen to their opinions. The Internal Monitoring: the internal monitoring mechanism was not well established and the internal monitoring report couldn t be submitted regularly. Information Management: All the hard copies are not properly filed. There was no resettlement information database. However, the information management needs to be strengthened. The Resettlement Work Performance: staffs are quite familiar with the work process and the relevant laws and regulations. They listened to the APs carefully and responded to them timely. In case APs are dissatisfied with compensation standards, they explained to them very patiently. APs felt satisfied with these. (5) Huaihua Commissioning of Resettlement Implementation Agency: Sangzhi PMO signed the Agreements on Real Estate Appraisal with Huaihua City Wealth Appraisal Company and Huaihua City Guangnian Appraisal Company. Implementation Procedures: After signing agreements regarding land acquisition and house demolition, the relevant compensation will be delivered to the affected villages, village groups, and communities and then to the affected people. The Adopted Measures: the RIB was distributed; the survey results regarding land acquisition and the compensation standards were disclosed in the affected villages; the resettlement staffs in the PMO held workshops and groups meetings with affected communities many times to promote the resettlement policies and listen to their opinions. The Internal Monitoring: the internal monitoring mechanism was not well established and the internal monitoring report couldn t be submitted regularly. Information Management: a dedicated staff is responsible for information management. All the hard copies are filed. However, the computerization of the filing management is not very good. An e-database isn t established. The Resettlement Work Performance: staffs are quite familiar with the work process 18

and the relevant laws and regulations. They listened to the APs carefully and responded to them timely. However, the teamwork is not very good. Sometimes, the working efficiency was low. (6) Yongzhou Commissioning of Resettlement Implementation Agency: For Lengshuitan District: Yongzhou PMO signed the Agreement with Yongzhou City House Demoltion Office who are responsible for physical indices verification, house demoltion, land acquisition etc. For Lingling District: Yongzhou PMO signed the Agreement with Lingling District House Demolition Office who is responsible for physical indices verification, house demolition, land acquisition etc. Implementation Procedures: After signing agreements regarding land acquisition and house demolition, the relevant compensation will be delivered to the affected villages, village groups, and communities and then to the affected people. The Adopted Measures: the RIB was distributed; the survey results regarding land acquisition and the compensation standards were disclosed in the affected villages; the resettlement staffs in the PMO held workshops and groups meetings with affected communities many times to promote the resettlement policies and listen to their opinions. The Internal Monitoring: the internal monitoring mechanism was not well established and the internal monitoring report couldn t be submitted regularly. Information Management: No a dedicated staff is responsible for information management. All the hard copies are not properly filed. An e-database isn t established. The Resettlement Work Performance: staffs are familiar with the work process and the relevant laws and regulations. They listened to the APs carefully and responded to them timely. (7) Leiyang and Chenxi Subprojects No agreements were signed between CXWEETD and these two subprojects. No M&E were undertaken so far. 3.2 Resettlement Organizations and Operation in Non-core Subprojects 3.2.1 Project Management Organizations Local Government put high priority on the subprojects and established the project management organizations for the project equipped with qualified staffs. (1) Cili According to No.16[2002] Document, Cili County Urban Flood Control Works 19

Construction Management Station was established, which is responsible for the subproject management and implementation. (2) Xiangtan According to No.158 [2007] Document, Xiangtan City Urban Flood Control Works Project Leading Group was established, which is responsible for the subproject supervision and coordination. Under this leading group, the Project Management Office was established, responsible for the subproject daily management and implementation. (3) Xupu According to No.47 [2007] Document, Xupu County Urban Flood Control Works Project Leading Group was established on 12June 2007, which is responsible for the subproject supervision and coordination. (4) Shimen and other subprojects No resettlement started in Shimen County. Jishou and other subprojects didn t sign the M&E contract with the External Monitor. 3.2.2 Resettlement Management Organizations Under each subproject management office, there was a resettlement division established who was responsible for organization and coordination of the resettlement activities. The division includes the members from the local government, planning, land resources, water resources and agriculture etc. these people were quite experienced and they were mainly involved into the coordination of the resettlement activities and also resettlement implementation activities. As for Cili subproject, there was a resettlement and house demolition division under the PMO. There were 5 staffs. The PMO has commissioned the qualified resettlement and land acquisition office who will undertake the appraisal and review of the lands and houses and also be involved into the concrete resettlement implementation activities. As for Xiangtan subproject, there was a resettlement and house demolition division under the Xiangtan Water Resources Bureau (WRB). There 13 staffs. The WRB has commissioned the qualified resettlement and land acquisition office who will undertake the appraisal and review of the lands and houses and also be involved into the concrete resettlement implementation activities. As for Xupu subproject, there was a resettlement and house demolition division under the Xupu Water Resources Bureau (WRB). There were 6 staffs. The WRB has commissioned the qualified resettlement and land acquisition office who will undertake the appraisal and review of the lands and houses and also be involved into the concrete resettlement implementation activities. No resettlement started in Shimen County. Jishou and other subprojects didn t sign the M&E contract with the External Monitor. 20

3.2.3 Resettlement Organization s Operation (1) Cili Subprojects Physical Indices survey and confirmation: the resettlement staff, the technical engineers, the village committee and the affected households had joint physical indices surveys and confirmation. The commissioned land acquisition and resettlement office was responsible for appraisal of these affected properties. Signing the land acquisition and house demolition agreement: after the confirmation of the physical indices, the PMO had negotiations with the village committee and affected households regarding land acquisition and house demolition compensation. Then, the PMO signed the agreement with the affected village committee regarding land acquisition and house demolition contracting and land acquisition compensation scheme and also directly signed the compensation agreements with the affected households. these signed agreement were sent to Cili County Land Resources Bureau and PMO for information. House Demolition implementation: the PMO and the commissioned House Demolition Office together with the village committee were jointly involved into the implementation of house demolition. Fund Delivery: the compensation fund for land acquisition will be settled between PMO and the village committees publicly. Then the village committees held the village meetings to discuss about the compensation allocation scheme. After signing the compensation agreements with PMO regarding the house demolition, PMO paid the compensation to the affected households directly. Account Audit: when one phase of land acquisition and resettlement is completed, the relevant account will be submitted to the County Audit Bureau for auditing. (2) Xiangtan Subprojects Physical Indices survey and confirmation: the resettlement staff, the technical engineers, the Urban Land Acquisition and House Demolition Office, the village committee and the affected households had joint physical indices surveys and confirmation. The commissioned land acquisition and resettlement office was responsible for appraisal of these affected properties. Signing the land acquisition and house demolition agreement: the PMO was responsible for signing the agreements and sent them to, the Urban Land Acquisition and House Demolition Office for information. 21

House Demolition implementation the commissioned House Demolition Office was responsible for the implementation of house demolition. Fund Delivery: the compensation fund for land acquisition will be settled between PMO and the village committees publicly. Then the village committees held the village meetings to discuss about the compensation allocation scheme. After signing the compensation agreements with PMO regarding the house demolition, PMO paid the compensation to the affected households directly. Account Audit: when one phase of land acquisition and resettlement is completed, the relevant account will be submitted to the City Audit Bureau for auditing. (3) Xupu Subprojects Physical Indices survey and confirmation: the resettlement staff, the technical engineers, the Land Acquisition and House Demolition Office, the village committee and the affected households had joint physical indices surveys and confirmation. The commissioned land acquisition and resettlement office was responsible for appraisal of these affected properties. Signing the land acquisition and house demolition agreement: after the confirmation of the physical indices, the PMO had negotiations with the village committee and affected households regarding land acquisition and house demolition compensation. Then, the PMO signed the agreement with the affected village committee regarding land acquisition and house demolition contracting and land acquisition compensation scheme and also directly signed the compensation agreements with the affected households. these signed agreement were sent to Xupu County Land Resources Bureau and Xupu County House Demolition Management Office for information. House Demolition implementation: the commissioned House Demolition Office was responsible for implementation of house demolition. Fund Delivery: the compensation fund for land acquisition will be settled between PMO and the village committees publicly. Then the village committees held the village meetings to discuss about the compensation allocation scheme. After signing the compensation agreements with PMO regarding the house demolition, PMO paid the compensation to the affected households directly. Account Audit: when one phase of land acquisition and resettlement is completed, the relevant account will be submitted to the County Audit Bureau for auditing. (4) Shimen and other Subprojects 22

No resettlement started in Shimen County. Jishou and other subprojects didn t sign the M&E contract with the External Monitor. 4. Engineering Implementation Progress 4.1 Engineering Implementation Progress in Core Subprojects Currently, the 6 core subprojects have divided the embankment sections and the relevant construction bidding works have been completed. The relevant construction contractors and the supervision companies were fielded. However, the actual progress was behind the schedule due to various constraints. The details of the core subprojects implementation were described as the following. 23

Yong zhou Subproject The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project Table 4.1-1: Project Implementation Progress of Core Subprojects No. Name of Contract Packages Contract Value (10 4 CNY) Contract Period (Day) Commence to Work Physical Progress Investment (10 4 CNY Investment () 1 Civil works in the Old City Area of Chengbei Protection 4357.23 2007.1.18 1995 46 Loudi Circle Civil works 2 of Lishui Section of Chengzhong Protection Circle 5932.79 2007.1.18 4000 67 Xinhua 1 Chengxi Package 1699.52 2007.9.29 1604 94 2 Chengdong Package 3215.73 2007.10.16 1823 57 1 Chenbei Protection 2457.92 2007.1.11 850 49 Wugang Circle Chengnan 2 Protection 2653.42 2007.1.11 810 100 Circle 1 Main Urban Protection 3035 2007.10.8 1500 49 Sangzhi Circle Gao Jiaping 2 Protection 1069 2007.4.1 1069 100 Circle Huaihua 1 Phase 1 2300 2007.3 78 1799.5 78 1 C9 contract package in the east of the river 1023.22 2007.7 1500 147 Lengshui tan Lingning 2 1 2 C10 contract package in the west of the river C8 contract package in the west of the river C7 contract package in the east of the river 2713.10 2008.3 200 7 2107.10 2007.8 1455 69 3030.17 2008.3 0 24

(1) Loudi Subproject There were two embankment sections including Chengbei Circle( old city area) and Chengzhong Circle( Lishui section): A. Civil Works of the Chengbei Circle: the contract price was 43.57 million CNY; the construction company was Hunan Water Resources and Hydropower General Company; the supervision company was Hunan Water Resources and Electricity Engineering Supervision Consulting Company; the construction started on 18 January 2007 and so far, the completed embankment was 2.6km long from Lianyuan Bridge to Jixing Section with the total investment of 19.95 million CNY, accounting for 45.79 of the total embankment section. B. Civil Works of the Chengzhong Circle: the contract price was 59.32 million CNY; the construction company was Hunan Water Resources and Hydropower No.1 Company; the supervision company was Hunan Water Resources and Electricity Engineering Supervision Consulting Company; the construction started on 18 January 2007 and so far, the completed embankment flood control embankment foundation treatment with 4.4km long and 1.2 km long from Lianyuan Bridge to Jixing Road Section with the total investment of 40 million CNY, accounting for 67.42 of the total embankment section. (2) Xinhua Subproject There were two embankment sections including Chengxi and Chengdong. A. Chenxi: the contract price was 16.99 million CNY; the construction company was Hunan Water Resources and Hydropower No.1 Company; the supervision company was Loudi Water Resources and Hydropower Construction Supervision Company; the construction started on 29 September 2007; Chainage k0+000~ k3+000 completed slope protection and the crest hardening; Chainage k3+000~ k4+190 completed the foundation excavation; built a new pumping station and repaired a sluice gate; 300m long foundation grouting treatment. All these spent 16.04 million CNY and 94 of the works completed. B. Chendong: the contract price was 32.15 million CNY; the construction company was Hunan Xinkang Construction Company; the supervision company was Loudi Water Resources and Hydropower Construction Supervision Company; the construction started on 16 October 2007; Chainage k0+000~k3+000 completed earthwork excavation, the embankment body filling and road surface; Chainage k3+000~k4+600 completed deep grouting; completed sluice gate at chainage K1+140. All these spent 18.23 million CNY and 57 of the works completed. (3) Wugang Subproject There were two embankment sections including Chengbei and Chengnan. 25

A. Chenbei: the contract price was 24.57 million CNY; the construction company was Hunan Construction Group Company; the supervision company was Shaoyang Kaituo Water Resources and Hydropower Construction Supervision Company; the construction started on 11 January 2007; the completed embankment include 700m long from Yudai Bridge to Dongta and the1500m long embankment from Tiyun Bridge northward was under the construction. All these spent 8 million CNY and 35 of the works completed. B. Chennan: the contract price was 26.53 million CNY; the construction company was Hunan Donggang Construction Development Company; the supervision company was Shaoyang Kaituo Water Resources and Hydropower Construction Supervision Company; the construction started on 11 January 2007; the completed embankment include 700m long from Xiaojiaba toyudai Bridge and the1500m long embankment from Tiyun Bridge southward was under the construction. All these spent 8.1 million CNY and 31 of the works completed. (4) Sangzhi Subproject There were two embankment sections including Main Urban Protection Circle and Gaojiaping Protection Circle: A. Main Urban Protection Circle: the contract price was 30.35 million CNY; the construction company was Yiyang Water Resources and Hydropower General Company; the supervision company was Hunan Yuhui Water Resources and Electricity Engineering Supervision Consulting Company; the construction started on 8 October 2007 and so far, completed chainage A0+000 ~ A1+390 embankment foundation excavation and C15 concrete backfill; chainage C0+000~C1+075 embankment foundation excavation and C15 concrete backfill with the total investment of 15 million CNY, accounting for 49 of the total embankment section. B. Gaojiaping Protection Circle: the contract price was 10.69 million CNY; the construction company was Hunan Water Resources and Hydropower Construction Company; the supervision company was Hunan Jianghe Water Resources and Hydropower Construction Consulting Company; the construction started on 8 October 2007 and so far, completed chainage 0-120~0+911.38 earthwork; chainage A0+000~A1+470 embankment foundation excavation and backfill with the total investment of 10.69 million CNY, accounting for 100 of the total embankment section (5) Huaihua Subproject Only Phase one works started with the contract price of 23 million CNY. The construction company was Hunan Water Resources and Hydropower Construction Company; the supervision company was Hunan Y Water Resources and Electricity Engineering Supervision Consulting Company; the construction started in March 2007. 78 of the civil works completed including slope repairing. All these spent 17.99 million CNY and 78 of the works competed. 26

(6) Yongzhou Subproject The External Monitoring and Evaluation Report of ADB-funded Hunan Flood Management Sector Project There were two districts in Yongzhou City including Lengshuitan and Lingling. There were two embankment sections in Lengshuitan District including Hedong and Hexi. Hedong C9 Section: the contract price was 10.23 million CNY; the construction company was Hunan Xiangyu Hydropower Construction Company; the supervision company was Hunan Water Resources and Hydropower Construction Consulting Company; the construction started in July 2007; completed chainage 0+000~2+800 earth embankment with total investment of 15 million CNY; the completed works accounted for 100 of the total. Hexi C10 Section: the contract price was 27.13 million CNY; the construction company was Hunan Water Resources Hydropower Mechanism Construction Company; the supervision company was Hunan Water Resources and Hydropower Construction Consulting Company; the construction started in March 2008; completed chainage 1+921 ~ 3+481.74 earth embankment and 11+448.42 ~ 13+370.91 masonry embankment with total investment of 2 million CNY; the completed works accounted for 7 of the total. There were two embankment sections in Lingling District including Hedong and Hexi embankment. Hexi C8 Section: the contract price was 21.07 million CNY; the construction company was Hunan Water Resources and Hydropower Engineering General Company; the supervision company was Hunan Water Resources and Hydropower Construction Consulting Company; the construction started in August 2007; completed 3.25km long concrete flood control wall with total investment of 14.55 million CNY; the completed works accounted for 60 of the total. Hedong C7 Section: the contract price was 30.30 million CNY; the construction company was Hunan Water Resources and Hydropower Engineering No.1 Company; the supervision company was Hunan Water Resources and Hydropower Construction Consulting Company; the commence to work was in March 2008 but the construction didn t start yet. (7) Leiyang and Chenxi Subprojects Leiyang and Chenxi subprojects didn t sign the M&E contract with the External Monitor. 4.2 Engineering Implementation Progress in the Non-core Subprojects Three subprojects started the civil works construction and land acquisition and house demolition including Cili, Xiangtan and Xupu. Cili Subproject: there were 3 civil works packages. Currently only Yong an package was under the implementation with the spending of 26 of the total; the bidding of 27