Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context

Similar documents
OLIVIA WAIYEE LEE Appellant. WHANGAREI DISTRICT COUNCIL Respondent. Winkelmann, Simon France and Woolford JJ

The Contractor s building defects liability in England and Wales

LIMITATION DEFENCES AND LEAKY BUILDINGS

WESTLAND DISTRICT COUNCIL Appellant. PETER CHARLES YORK First Respondent

BELIZE LIMITATION ACT CHAPTER 170 REVISED EDITION 2000 SHOWING THE LAW AS AT 31ST DECEMBER, 2000

SCOPE AND EXTENT OF ENGINEERS LEGAL RESPONSIBILITIES FOR DEFECTS AND CONSTRUCTION ACTIVITIES ON SITE

Elements of a Civil Claim

Did You Blow the Statute of Limitations?

RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW

LITIGATION AND DISPUTE RESOLUTION. Irish Supreme Court Provides Clarity on the Statute of Limitations in a Property Damage Claim.

Limitations Act, 2002: Issues of Concern to Trustees in Bankruptcy

THE BUILDING CONTROL AMENDMENT REGULATIONS. Martin Waldron BL

Table of limitation periods

3. Saver in relation to court s power to dismiss on ground of delay.

Before: MR A WILLIAMSON QC (sitting as a Deputy High Court Judge) Between :

IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY CIV

STATE PROCEEDINGS ACT

Time and Construction Contracts

LIMITATION OF LIABILITY BY ACCOUNTANTS

Galliford Try Construction Ltd v Mott MacDonald Ltd [2008] APP.L.R. 03/14

GAY CONSTRUCTIONS PTY LTD & ANOR v CALEDONIAN TECHMORE (BUILDING) LTD (HANISON CONSTRUCTION CO LTD, THIRD PARTY) - [1994] 2 HKC 562

LIMITATION OF ACTIONS ACT

Contract and Tort Law for Engineers

FINAL DETERMINATION Adjudicator: P A McConnell

Assembly Bill No. 125 Committee on Judiciary

JCLI Scottish Landscape Works Agreement 2013 (JCLI SLWA 2013)

Middle Eastern Oil LLC v National Bank of Abu Dhabi [2008] APP.L.R. 11/27

No. 107,696 IN THE COURT OF APPEALS OF THE STATE OF KANSAS. GREGORY COKER, Appellant, MICHAEL D. SILER, Defendant, and SYLLABUS BY THE COURT

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC JAMES HARDIE NEW ZEALAND Second Plaintiff

TOPIC 2: LEGAL REMEDIES (DAMAGES - IN TORT AND CONTRACT)

NC General Statutes - Chapter 1 Article 5 1

SONSRAM TRUSTEE LIMITED First Appellant. HARRISON GRIERSON CONSULTANTS LIMITED Respondent. Harrison, Venning and Simon France JJ

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998

WENDEN ENGINEERING SERVICE CO LTD v WING HONG CONTRAC- TORS LTD - [1992] 2 HKC 380

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03

PRINCIPLES OF EUROPEAN TORT LAW

CHAPTER 60:02 TITLE TO LAND (PRESCRIPTION AND LIMITATION) ACT ARRANGEMENT OF SECTIONS

TITLE 6 SOVEREIGN IMMUNITY

Editorial. Contents. September edition 4. Keith Lonsdale

MAY 2012 BUSINESS AND CORPORATE LAW SOLUTION

EQUITABLE REMEDIES IN COMMERCIAL LITIGATION: Concurrent session 1A Constructive trust

A BILL FOR A LAW FOR THE ADMINISTRATION OF CIVIL JUSTICE IN EKITI STATE EKITI STATE OF NIGERIA

Civil Liability Amendment (Personal Responsibility) Act 2002 No 92

Limitations Act 2002: A huge reform of existing law

Construction Warranties

Conditions Precedent to Recovery of Loss and Expense Claims

Directors' Duties in Guernsey

Shortfalls on Sale. Toby Watkin

SUPREME COURT OF QUEENSLAND

Consumer Claims Act 1998 No 162

FOUNDATIONS LAW CONTENTS

Case 4:15-cv Document 31 Filed in TXSD on 07/19/16 Page 1 of 10 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION ORDER

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV M VAN DER WAL BUILDERS & CONTRACTORS LTD Plaintiff

CHAPTER 107 CONTRIBUTORY NEGLIGENCE AND JOINT WRONGDOERS

JUDGMENT. BPE Solicitors and another (Respondents) v Gabriel (Appellant)

Privately Funded Civil Litigation CFAs and DBAs Frequently Asked Questions

PRESCRIPTION (SCOTLAND) BILL

JUDGMENT JUDGMENT GIVEN ON. 15 November Lord Neuberger Lord Mance Lord Sumption Lord Reed Lord Hodge. before

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518

Court of Appeals. First District of Texas

Limitation period for breach of fiduciary duty 3 years or 10?

TITLE 6 SOVEREIGN IMMUNITY

STANDARD CFA TERMS AND CONDITIONS FOR PERSONAL INJURY CASES TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL

LIMITATION running the defence

IN THE HIGH COURT OF JUSTICE. Between STEPHEN LORENZO LODAI. And NAGICO INSURANCE COMPANY LIMITED. (formerly known as GTM INSURANCE COMPANY LIMITED)

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

OPINION OF LORD DRUMMOND YOUNG. in the cause COSTAIN LIMITED. against STRATHCLYDE BUILDERS LIMITED

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21

IN THE COURT OF APPEAL BETWEEN THE CHIEF FIRE OFFICER THE PUBLIC SERVICE COMMISSION AND SUMAIR MOHAN

NC General Statutes - Chapter 1 Article 5 1

Damages in Tort 6. Damages in Contract 18. Restitution 27. Rescission 32. Specific Performance 38. Account of Profits 40.

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

*To search for a specific state, click on Edit in the menu bar and then click Find. Type full state name in dialog box and click Next.

Alister Holden & Murray Bridge as Trustees of the Estate of Bruce Morris Claimants. Peter Hanns trading as Hanns Builders & Joiners First Respondent

ADJUDICATIONS UNDER THE CONSTRUCTION CONTRACTS ACT 2002 FAMILY TRUSTS, BODIES CORPORATE AND COMPANIES

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

IN THE REPUBLIC OF TRINIDAD AND TOBAGO IN THE COURT OF APPEAL BETWEEN MAY JOSEPHINE HUMPHREY AND

THE LATEST TORT REFORM: THE CERTIFICATE OF MERIT

Twenty Years Forward, Twenty Years Back A Legal Review. Outline of a Talk to the Professional Indemnity Forum Conference

The Limitation of Actions Act

Bar Council CPD Conference 19 May 2012

IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY CIV [2014] NZHC 520

APPENDIX. Supplement No. published with [Extraordinary Gazette] No. dated, 2015.

IN THE HIGH COURT OF JUSTICE CHARLES SAYERS SHERRY SAYERS. and WILLIAM FRANCOIS CLARA FRANCOIS

TIPS ON RUNNING CIVIL MATTERS IN THE LOCAL COURT. 1. Overview of the Local Court Civil Jurisdiction

Case Note. Carty v London Borough Of Croydon. Andrew Knott. I Context

FINAL DETERMINATION Adjudicator: S Pezaro

REPEALED LIMITATION ACT CHAPTER 266

IN THE SUPREME COURT OF BELIZE A.D (CIVIL) CLAIM NO. 36 of 2015 BETWEEN. A&N CONSTURCTION (A firm) AND HERITAGE BANK LIMITED DECISION

Condemnation Proceedings, a practical synopsis

Assembly Amendment to Assembly Bill No. 125 (BDR 3-588) Title: No Preamble: No Joint Sponsorship: No Digest: Yes

REPUBLIC OF SOUTH AFRICA EXPROPRIATION BILL

CONSTRUCTION DEFECT CLAIM PROCEDURES INTRODUCTION. In 1999, in response to intense lobbying by builders and builders trade organizations

Before : THE HON.MR.JUSTICE RAMSEY Between :

IMPORTANT NOTICE. Information that must be set out in notice of adjudication served on residential occupier.

Civil Procedure Act 2010

Before: HIS HONOUR JUDGE WULWIK Between: - and -

Continuing to act after negligence rights, problems and consequences

Distillers Co (Biochemicals) Ltd v. Thompson. [1971] AC 458 (Privy Council on appeal from the New South Wales Court of Appeal)

Transcription:

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Received (in revised form): 11th September, 2005 Sarah Wilson is an associate solicitor within Watson Burton LLP s Construction Law Unit, one of the largest specialist construction legal departments outside of London. Sarah s clients vary from developers and main contractors through to design professionals and subcontractors. She specialises in large-scale, high-value engineering and construction disputes and has widereaching experience of various dispute resolution forums such as the Technology and Construction Court, arbitration, adjudication and mediation. She is an associate of the Chartered Institute of Arbitrators and is a committee member of the Northumbria branch. Abstract This paper carries out an examination of the current law relating to limitation and causes of action (tortious and contractual) within a construction context and explains the main provisions from the Limitation Act 1980. It further analyses application of the 1980 Act in light of the recent decision, Abbott v Will Gannon & Smith Ltd. This new judgment involved analysis and reconciliation of the decisions in the key cases: Murphy v Brentwood DC and Pirelli General Cable Works Limited v Oscar Faber & Partners. Although the case law in this area sets out the principles for limitation and causes of action in general law the decisions come from construction-based disputes and are relevant to the author s legal specialism. Keywords: limitation, cause of action, tortious/contractual, Limitation Act 1980 Watson Burton LLP 1 St James Gate Newcastle upon Tyne NE99 1YQ, UK Tel: þ44 (0)191 244 4444 E-mail: sarah.wilson@watsonburton. com INTRODUCTION A builder who causes damage in the course of construction is liable for losses that result. Construction consultants, on the other hand, provide advice (sometimes in the form of design) which raises problems when it turns out to be negligent. In particular, with regard to the time limits to bring proceedings, does time start to run when the advice is given, when the building is complete or when the damage occurs? These are the issues considered in the cases reviewed in this paper. The issue to be considered by the Court of Appeal judges in the case of Abbott v Will Gannon & Smith Ltd [2005] EWCA CIV 198 (hereinafter referred to as Will Gannon ) was whether Murphy v Brentwood DC [1991] AC398 ( Murphy ) was inconsistent with Pirelli General Cable 344 q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353

Examining the current law relating to limitation and causes of action Works Limited v Oscar Faber & Partners [1983] 2 AC1 ( Pirelli ) and, if so, whether Pirelli was still good law. In Pirelli, the House of Lords found that, for limitation purposes, the cause of action against the consulting engineer for negligent design accrued when physical damage to the building first occurred. This decision had been followed by the Deputy District Judge who gave the first instance decision on Will Gannon. The argument put forward on behalf of the engineers was that in Murphy the Court of Appeal had found that a cause of action accrues when the building owner suffers economic loss and that this was when the negligently designed work had been completed because it was at this stage that the building required remedial work. ABBOTT V WILL GANNON Abbott v Will Gannon The facts of the case The facts of Will Gannon are indistinguishable from those in Pirelli. A summary of Pirelli is detailed further on in this paper but, in the meantime, the facts of Will Gannon are summarised below. May 1995 The defendant consulting structural and civil engineers were engaged by the claimant, who owned a hotel in Torquay, to design the work to remedy structural defects to a bay window in the hotel. March 1997 The work, in accordance with the engineer s design, was completed by a third party. Late 1999 The claimant hotel owner first noticed that the lintel over the bay window had moved and caused cracking. The claimant had to spend circa 20,000 to remedy this problem. 15th September, 2003 Proceedings in contract and tort were issued against the engineer upon the following basis: there was a breach of contract/duty of care; such breaches had caused the defects which appeared in 1999; and claiming the cost of repair and consequential losses. Procedural points Before reviewing the arguments put forward by the parties it would be helpful to note these procedural points to get a fuller view of the extent of this case. The contract was not in writing but it was agreed that it q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353 345

Wilson contained the usual implied term that the engineers would carry out the work with reasonable care and skill. The parties had reached agreement that the contract claim was out of time and that this left only the tortious claim. The limitation point was tried as a preliminary issue on facts agreed between the parties. Legal issue For the tortious claim to proceed the proceedings must be commenced within six years (under Section 2 of the Limitation Act 1980) of the accrual of the claim. The claim accrues when the damage occurs. Therefore, under Section 2, the question was when the cause of action accrued: was it when the work was completed (March 1997) as contended by the engineers in which case the claim was time barred or was it when the damage occurred to the building (and the claimant contended that this was shortly before he first noticed the cracking in late 1999) in which case it was not time barred. The judge at first instance had not made a specific finding on these points but found in favour of the claimant, stating: if cracks first appeared within six years of the issue of proceedings [the claim] is not statute barred. As the cracks appeared in 1999 and proceedings were commenced in 2003 they were not statute barred. Limitation Act 1980 BACK TO BASICS THE LIMITATION ACT 1980 It may be helpful to review the relevant statute in relation to time limits for commencing proceedings prior to a review of the cases referred to by the Court of Appeal in Will Gannon. The Limitation Act 1980 has been referred to previously and the relevant extracts are quoted in the Appendix to this paper. The Limitation Act 1980 is the statutory instrument which defines the time limits within which court proceedings must be commenced. Failure to comply with those time limits means proceedings cannot be commenced/proceed and it is up to the claimant to show that the proceedings have been brought within the relevant time limits. It is therefore crucial that the time limits are observed. There are important differences between claims in contract and claims in tort. Contract While this paper deals with tortious claims rather than contractual claims, it may be helpful to note the contrast made. The ordinary time limit for a claim in a simple contract is six years from the date on which the cause of action accrues (Section 5), whereas for a contract by deed the time limit is 12 years (Section 8). In both cases, time starts to run from the date of breach of contract and not from the date of its discovery. Having said that, where a contractor is responsible under an entire contract to complete works, the limitation period for defects generally runs from the date of completion rather than from any earlier date when that part of the works, relevant to the subject matter of the defects, was carried out. 346 q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353

Examining the current law relating to limitation and causes of action Tort The time limit for a claim in tort (for example, negligence) is generally six years from the date on which the cause of action accrues (Section 2). For negligence claims, where damage is an essential ingredient, the cause of action accrues when the damage occurs. It is therefore quite common for the limitation period on a simple contract claim to expire prior to the tortious claim. It should be noted that Section 14A, an amendment to the Limitation Act by way of the Latent Damage Act 1986, provides a special time limit for negligence claims where facts relevant to the cause of action are not known at the date of accrual. Essentially, it extends the primary limitation period (six years) by three years from the claimant s date of knowledge in respect of the damage. This was of no assistance in Will Gannon, however, as the date of knowledge was late 1999 and the three-year period expired in late 2002. PIRELLI The facts of the case In this case the engineer negligently designed a chimney for a factory belonging to the plaintiff. The chronology was as follows. July 1969 Construction of the chimney was completed. Pirelli By April 1970 Cracks had developed in the chimney which remained undiscovered (ie more than eight years before the proceedings were issued). November 1977 The cracks were discovered and required remedial works. October 1978 Proceedings were issued by the claimant following the remedial works. Legal arguments The defendant suggested three possible dates for the start of the Limitation Period: the date when the plaintiff relied upon the negligent advice (ie prior to July 1969); the date when the construction was completed (July 1969); the date when the cracks first occurred (prior to April 1970). The plaintiff argued that the start of the Limitation Period was the date when the damage was discovered or, with reasonable diligence, ought to q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353 347

Wilson have been discovered (and presumably it was argued that this date was November 1977). The decision in Pirelli The decision was that the cause of action accrued when the physical damage first occurred to the building. In this case, it was spring 1970, being the date when the cracks to the chimney must have come into existence. This meant that the claimant had failed to commence proceedings within six years of the accrual of the cause of action and the claim therefore failed. It should be noted that this case pre-dates the amendment of the Limitation Act 1980 by the Latent Damage Act 1986 and therefore Section 14A (as referred to above) whereby the Limitation Period can be extended for a further three years from the claimant s date of knowledge (in this case November 1977) was of no assistance to the claimant. Indeed, it was as a result of the perceived injustice in Pirelli that Section 14A was introduced into the 1980 Act. Doomed from the start argument The judgment in Pirelli suggested that, while generally speaking a cause of action accrues only when physical damage has occurred to a building, there could be an exception to this where the advice of an architect or consulting engineer leads to the erection of a building which is so defective as to be doomed from the start. This point was considered in the further House of Lords case, Ketteman v Hansel Properties [1987] AC189 ( Ketteman ), which in turn was considered in Will Gannon. KETTEMAN V HANSEL Ketteman v Hansel The facts Very briefly, the facts of this case were that houses had been built on defective foundations and the architects, defending allegations of defective design, argued that the cause of action accrued when the foundations for the houses were laid by the builders. This argument was based on the idea that the houses were doomed from the start and so this was the point at which the plaintiff suffered economic loss, ie when the houses became less valuable than they would have been had the foundations been adequate. Counsel for the defendant put forward an argument that the buyer suffered two kinds of damage as follows. The first was physical damage, in which case the cause of action for negligence accrued when the physical damage occurred. The second was economic loss, ie diminution in value, which occurred at the time of construction. Decision This argument was rejected. The court found that the defects in the houses were latent, no one knew of their existence until the damage occurred and 348 q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353

Examining the current law relating to limitation and causes of action it was only when the damage had occurred that a cause of action arose. The judgment cited and approved Pirelli in respect of the proposition that a latent defect in a building does not give rise to a cause of action until damage occurs. The court referred to the doomed from the start point made in Pirelli. Lord Keith was of the view that the judges in Pirelli had not intended this argument to apply to latent defects which would eventually result in damage because Pirelli concerned such a defect and the court had found that the cause of action accrued when damage occurred. Lord Brandon, in Ketteman, suggested that it was an attempt to leave an opening for special cases. But his opinion was that there had been no attempt in Pirelli to differentiate between causes of action where the claimant was seeking to: make good defects, ie physical damage; and recover the diminution in market value, ie economic loss. MURPHY V BRENTWOOD DC The facts This is another case regarding a house built on defective foundations, although there were no limitation issues. In this case, the claimant brought proceedings against Brentwood District Council to recover the diminution in the market value of the house. Essentially, this case deals with tortious liability with regard to latent defects and distinguishes between: defects which cause injury to an individual or damage to property; and those that do not. Murphy v Brentwood DC In the latter case, the loss sustained by the building owner was economic either the defective property could be repaired and the cost of repair was the loss sustained or, if the defect could not be repaired, the loss was the reduced value of the property. As economic losses they are only recoverable if they flow from breach of a relevant contractual duty but are not recoverable in tort unless there is some special relationship of proximity. In his judgment on Murphy, Lord Keith commented upon Pirelli stating: If the plaintiffs had happened to discover the defect before any damage had occurred there would seem to be no good reason for holding that they would not have had a cause of action at that stage, without having to wait until some damage had occurred. They would have suffered economic loss through having a defective chimney upon which they required to expend money for the purpose of removing the defect... where the tortious liability arose out of a contractual relationship with professional people, the duty extended to take reasonable care not to cause economic loss to the client by the advice given. This was all examined in Will Gannon, however, and the view was that it does not obviously overrule Pirelli but merely deals with the situation q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353 349

Wilson where the claimant discovers the defect before the damage occurs and concludes that the claimant has a claim for economic loss if there is a special relationship. Invercargill City Council v Hamlin INVERCARGILL CITY COUNCIL V HAMLIN Invercargill City Council v Hamlin [1996] AC624 ( Invercargill ) was a New Zealand Privy Counsel case which examined both Pirelli and Murphy and was itself examined in Will Gannon. The New Zealand courts took a completely different approach to Pirelli which is illustrated by this case. It was stated in Invercargill that: the cause of action accrues when the cracks become so bad and all the defects so obvious, that any reasonable home-owner would call in an expert. The New Zealand courts therefore look for the date when the physical damage is reasonably discovered by the property owner. It was further stated in this case that: the Plaintiff s loss occurs when the market value of the house is depreciated by reason of the defective foundations and not before. Lord Lloyd giving judgment recognised that: in the common case the occurrence of the loss and the discovery of the loss will coincide, and that the date of the cause of action marks the moment when the market value of the building is depreciated and therefore the moment when economic loss occurs. Judge Lloyd considered the benefits of the approach of the New Zealand court (over Pirelli) to be as follows: it avoids the practical and theoretical difficulties relating to Pirelli; it means that a cause of action accrues when all the elements necessary to support the plaintiff s claim are in existence, including the loss or damage to the value of a property necessary to a claim for economic loss in the case of a defect; and it means that an undiscoverable crack is irrelevant because it cannot affect the value of the building. SUMMARY OF WILL GANNON The court summarised the position with regard to Murphy as being that the claimant may only sue in tort in respect of a latent defect in the building in the following circumstances: for personal injury; for damage to property caused by a latent defect in a building; and for economic loss where there is a special relationship between the parties. The court conceded, however, that the decision in Murphy leaves it unclear as to whether this extends to damage to the building itself before the defect is discovered. In addition, the definition of a special relationship is unclear as discussed in Will Gannon. It is clear that the duty in such case extends to taking care not to cause economic loss, but 350 q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353

Examining the current law relating to limitation and causes of action when does such loss occur in a case such as the present and does the duty not to cause physical damage to property constitute a separate cause of action for limitation purposes? The engineer s argument was that: the claimant had only suffered economic loss; loss occurred when the defectively designed work to the bay window was completed, ie March 1997 (the economic loss had been suffered at this point as the claimant s building was defective at this point); and the cause of action for negligent design accrued when the economic loss was first suffered. The court decided, however, that it was bound by the decisions in Pirelli and Ketteman to uphold the first instance decision of the District Judge, namely that the cause of action accrued when physical damage to the building first occurred. The reasoning behind this seems to have been as follows: Summary the facts in Pirelli are indistinguishable from the facts in Will Gannon; Pirelli was approved in Ketteman; Pirelli was cited without disapproval in Murphy (and two members, ie Lords Bridge and Brandon, were party to the decisions in both Pirelli and Murphy); Pirelli had not been expressly overruled, and the court considered that Pirelli had not been impliedly overruled. In particular, reference was made to the comments made in Invercargill that, while Pirelli was not good law in New Zealand, it was not for the New Zealand court to say whether or not it was good law in England; and only the House of Lords can decide whether Pirelli has been overruled. The court went on to deal with the position in the event that it was not bound by Pirelli and the claimant s cause of action accrued at the time when economic loss was suffered. The court decided that the cause of action accrued in 1999 and the claim was not therefore time barred. The basis of this decision was as follows: that the economic loss did not occur in March 1997 (as argued by the defendant s engineers) because the defective design had not caused any loss at that time; the loss would occur with the cost of repairs or depreciation in the market value; and the court accepted the analysis in Invercargill which avoids practical and theoretical difficulties with the timing of the loss and discovery of the defects coinciding. CONCLUSION This is an important case, particularly for construction professionals. It is noteworthy that the Court of Appeal s view was that the House of Lords was the appropriate court (if necessary) to overrule Pirelli. It is significant q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353 351

Wilson to note that a claim for 20,000 got as far as the Court of Appeal and it is highly unlikely that it will proceed further in costly appeals. It will be interesting to see if the House of Lords does take the opportunity, in the near future, to clarify the position, which can only help claimants and professionals alike. The judge in Will Gannon stated: So what is the present state of the law of England? With three House of Lords cases to guide us it ought to be possible to give a clear answer to this question, but I regret that I feel unable to do so with any confidence. Unfortunately, this not only shows how the law can change but also that it is definitely not an exact science. The effect of Will Gannon is obviously reduced where a contract is executed under deed (as this increases the time in which a claimant may bring proceedings under contract from six to 12 years). But professionals rarely enter into contracts under deed. It now seems that discoverability is the key concept and the court is moving nearer to the New Zealand concept where the loss and discovery of defects usually will need to coincide before time starts to run. APPENDIX: EXTRACTS FROM THE LIMITATION ACT 1980 2. Time limit for actions founded on tort An action founded on tort shall not be brought after the expiration of six years from the date on which the cause of action accrued. 5. Time limit for actions founded on simple contract An action founded on simple contract shall not be brought after the expiration of six years from the date on which the cause of action accrued. 8. Time limit for actions on a specialty (1) An action upon a specialty shall not be brought after the expiration of twelve years from the date on which the cause of action accrued. (2) Subsection (1) above shall not affect any action for which a shorter period of limitation is prescribed by any other provision of this Act. 14A. Special time limit for negligence actions where facts relevant to cause of action are not known at date of accrual (1) This section applies to any action for damages for negligence, other than one to which Section 11 of this Act applies, where the starting date for reckoning the period of limitation under subsection (4)(b) below falls after the date on which the cause of action accrued. (2) Section 2 of this Act shall not apply to an action to which this section applies. (3) An action to which this section applies shall not be brought after the expiration of the period applicable in accordance with subsection (4) below. (4) That period is either: (a) six years from the date on which the cause of action accrued; or (b) three years from the starting date as defined by subsection (5) below, if that period expires later than the period mentioned in paragraph (a) above. 352 q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353

Examining the current law relating to limitation and causes of action (5) For the purposes of this section, the starting date for reckoning the period of limitation under subsection (4)(b) above is the earliest date on which the plaintiff or any person in whom the cause of action was vested before him first had both the knowledge required for bringing an action for damages in respect of the relevant damage and a right to bring such an action. (6) In subsection (5) above the knowledge required for bringing an action for damages in respect of the relevant damage means knowledge both: (a) of the material facts about the damage in respect of which damages are claimed; and (b) of the other facts relevant to the current action mentioned in subsection (8) below. (7) For the purposes of subsection (6)(a) above, the material facts about the damage are such facts about the damage as would lead a reasonable person who had suffered such damage to consider it sufficiently serious to justify his instituting proceedings for damages against a defendant who did not dispute liability and was able to satisfy a judgment. (8) The other facts referred to in subsection (6)(b) above are: (a) that the damage was attributable in whole or in part to the act or omission which is alleged to constitute negligence; and (b) the identity of the defendant; and (c) if it is alleged that the act or omission was that of a person other than the defendant, the identity of that person and the additional facts supporting the bringing of an action against the defendant. (9) Knowledge that any acts or omissions did or did not, as a matter of law, involve negligence is irrelevant for the purposes of subsection (5) above. (10) For the purposes of this section a person s knowledge includes knowledge which he might reasonably have been expected to acquire: (a) from facts observable or ascertainable by him; or (b) from facts ascertainable by him with the help of appropriate expert advice which it is reasonable for him to seek; but a person shall not be taken by virtue of this subsection to have knowledge of a fact ascertainable only with the help of expert advice so long as he has taken all reasonable steps to obtain (and, where appropriate, to act on) that advice. q PALGRAVE MACMILLAN LTD 1744 9545 Journal of Building Appraisal VOL.1 NO.4 PP 344 353 353