LIMS IMPLEMENTATION PROJECT HINDSIGHTS How to avoid pitfalls and delays Presented By Kathy Smith Narragansett Bay Commission

Similar documents
Project Management for Lawyers 2015 The Ethics of Legal Project Management

Implementing and Overseeing Electronic Voting and Counting Technologies. Concluding Remarks. Lead Authors. Ben Goldsmith Holly Ruthrauff

Promoting environmental mediation as a tool for public participation and conflict resolution

Key Considerations for Implementing Bodies and Oversight Actors

SASKATCHEWAN ASSOCIATION OF MEDICAL RADIATION TECHNOLOGISTS COUNCIL POLICY MANUAL

Agenda Compliance Committee Open Session

Request for Proposals

case has unique facts, concerns, and legal issues. You must consider many competing

Midwest Reliability Organization

Terms of Reference. Project Title: Women s Political Leadership in Commonwealth Africa: Research and Capacity Building Project

Trading on the Markets Consulting & Corporate Services

Key Considerations for Oversight Actors

NetTest A European Solution from Austria for measuring Broadband Quality SERENTSCHY.COM ADVISORY SERVICES GMBH

UN WOMEN INDONESIA TERMS OF REFERENCE. National Consultant for Women Peace and Security

M o d u l e 1 : A n O v e r v i e w o f U n i t e d N a t i o n s P e a c e k e e p i n g O p e r a t i o n s. L e s s o n 1. 8.

NBIMS-US PROJECT COMMITTEE RULES OF GOVERNANCE

3. The current Unacceptable Behaviour Policy was put in place more than five years ago.

VERMONT S FOUR-STEP PROCESS FOR EFFECTIVE POLICY DEVELOPMENT

TMF Reference Model Steering Committee Charter

GOVERNANCE STRUCTURE. December, Place Photo Here, Otherwise Delete Box

Newark City Schools Strategic Plan

Conflict Management: Conflict Happens. Manage it. Julie Bruno, Sierra College Dolores Davison, Foothill College

A Resource for 4-H Club Officers

III. Good governance and the MDGs

CASE STUDY 2 Portuguese Immigration & Border Service

Getting the foundations right. Mobility Services: Global Immigration

ISSUES AND PROPOSED SOLUTIONS

Clinical Research Services

Project Committee Rules of Governance

ILLINOIS ASSOCIATION OF PUBLIC HEALTH ADMINISTRATORS IAPHA. Request for Proposals (RFP) LEGISLATIVE ADVOCACY LOBBYIST

Border Planning Group

a GAO GAO FOREST SERVICE Better Planning, Guidance, and Data Are Needed to Improve Management of the Competitive Sourcing Program

INTERNAL AUDIT DIVISION REPORT 2017/149

COMPETITIVE SOLICITATION FOR TECHNICAL ASSISTANCE

Welcome to All Things Project and Portfolio Management Part 2

Call for Proposals: Compile an Inventory of Current Resettlement Assistance Program (RAP) Practices and Health Care Services for GARs Across Canada

Insights. Leadership and Planning for State Capitol Renovations. Introduction

STRATEGY FOR COUNTERING MIGRANT SMUGGLING A GLOBAL LAW ENFORCEMENT RESPONSE

THE OPTIONS CLEARING CORPORATION RISK COMMITTEE CHARTER 1

Occasional Paper No 34 - August 1998

Local Governments and the Future of Waste Management and Disposal

Terms of Reference Moving from policy to best practice Focus on the provision of assistance and protection to migrants and raising public awareness

ELECTIONS ALBERTA BUSINESS PLAN 2016/ /20

Robert s Rules of Order. 1.Bylaws: The Organization s Constitution and Bylaws

Ethics Committee Terms of Reference

Terms of Reference. Project Title: Strengthening Electoral Processes and Democratic Institutions

WHEN NATIONAL PRIDE IS BEYOND FACTS. Navigating Conflicting Stakeholder Requirements. Felix Muramutsa

Unit 03. Ngo Quy Nham Foreign Trade University

RISK COMMITTEE OF THE NEX GROUP PLC BOARD

Exemptions within Joint Claims for JSA

Terms of Reference. Title Purpose. Location Contract Duration Contract Supervision

Checklist. Industry Requirements for E-Bonding Solutions. Based on Surety Association of Canada Vendor Guidelines

Terms of Reference (TOR): Stocktaking of the Trade Facilitation Support Program (TFSP)

Getting the public ready to engage in making care safer: Lessons from the anti-smoking movement. April 6, 2017

GOVERNANCE MATTERS. Challenges. GFA approach and services GOVERNANCE

COMPLIANCE PROCEDURES AND MECHANISMS PURSUANT TO ARTICLE 11 OF THE 1996 PROTOCOL TO THE LONDON CONVENTION 1972 (Adopted in 2007: LC 29/17, annex 7)

THE OPTIONS CLEARING CORPORATION GOVERNANCE AND NOMINATING COMMITTEE CHARTER

Reducing the Effects of Licensing Bankruptcy

GOVERNANCE MATTERS. Challenges. GFA approach and services GOVERNANCE

WORKGROUP S CONSENSUS PROCESS AND GUIDING PRINCIPLES CONSENSUS

COMMU ICATIO FROM THE COMMISSIO TO THE EUROPEA PARLIAME T A D THE COU CIL. Measuring Crime in the EU: Statistics Action Plan

Annex I Terms of Reference

Introduction to Project Management

Interagency Council on Printing and Publications Services Washington, DC

COMMENTS ON KAYE COMMISSION REPORT ON INDIGENT DEFENSE. New York City Bar Association

STRATEGIES FOR DEFINING A ROADMAP FOR THE NATIONAL FACILITATION COMMITTEE - THE GHANA EXPERIENCE

PLS 540 Environmental Policy and Management Mark T. Imperial. Topic: The Policy Process

NCAT Procedural Direction 3 EXPERT WITNESSES. This Procedural Direction applies to: Proceedings in all Divisions. (20 December 2013)

Checklist. Industry Requirements for E-Bonding Solutions. Based on Surety Association of Canada Vendor Guidelines. Version date: October 19, 2009

Qualities of Effective Leadership and Its impact on Good Governance

Ethical Culture. Speaking up: Information for CII members about whistleblowing. CII guidance series

INTERSTATE COMPACT FOR JUVENILES

Official Journal of the European Union. (Non-legislative acts) REGULATIONS

ADVERTISEMENT FOR CONSULTANCY

AMERICAN COLLEGE OF HEALTHCARE EXECUTIVES BOARD POLICY #1 CONFLICT OF INTEREST. Policy

Overview of the Consolidation Process Texas Health and Human Services System

Rules of Procedure. Effective: May 4, 2016

RESOLUTION ITU-R 1-7

Quant 101 Learn2Quant HK, 14 September Vinesh Jha CEO, ExtractAlpha

Observations on The Sedona Principles

Procurement Oversight and Procurement Review Committees

ITEMS. Jam~:;;cz.;,;,~:;!:~er STAFF REPORT. Mayor and City Council. Linn Walsh, Assistant to the City Manager

DRAFT WORKING GROUP CHARTER

PERFORMANCE AUDIT REPORT 100-Hour Audit

European Open Science Cloud getting real: policies to launch EOSC and its governance structure. EOSC. Austria takes initiative Vienna

SUPPORT TO MEDIATION PROCESS

Minutes. Call to Order

the implementation and documentation of appropriate arrangements, be publically available; and

TERMS OF REFERENCE. right to know and decide can lead to turning gold, platinum, titanium into schools, hospitals and jobs for locals

Response to the Legal Service Board. Call for evidence on the regulation of immigration advice and services

Labour Hire Accreditation Scheme. Briefing from On-Hire industry leaders in Canterbury

1 UPDATE ON YORK REGION'S APPLICATION FOR THE LOCAL IMMIGRATION PARTNERSHIPS INITIATIVE

Recommendation of the Council for Development Co-operation Actors on Managing the Risk of Corruption

Vacancy: Reinforcing the Institutional Capacities in South and Central Somalia (MIDA), IOM Somalia. Terms of Reference

Making Citizen Engagement Work in Our Communities

The Changing Landscape of Construction Dispute Resolution in Hong Kong: Opportunities for QS?

Resolution adopted by the General Assembly on 2 April [on the report of the Fifth Committee (A/69/422/Add.2)]

Mediation of Catastrophic and Complex Claims

CONFLICT RESOLUTION POLICY

RULE ON LICENSING OF ENERGY ACTIVITIES IN KOSOVO

Transcription:

LIMS IMPLEMENTATION PROJECT HINDSIGHTS How to avoid pitfalls and delays Presented By Kathy Smith Narragansett Bay Commission This presentation s focus is on a project that had many obstacles, delays, overruns and frustrations by all parties. What went wrong What went Right This presentation is intended to help others to achieve a successful LIMS implementation by sharing our experiences and lessons learned.

The LIMS Selection process a crucial part of the LIMS implementation It is very important to select the correct product in the selection process as this has a direct impact on the overall LIMS project. Most systems have about 80% functionality in common; the remaining 20% functionality is of paramount importance in selecting the one with the best benefits for your success and needs. Select one that has the necessary functionality needed, but at the same time there is little worth in selecting a LIMS with superfluous functionality just because. Common mistakes that are made are not having precise detailed requirements that were easily communicated to the vendor. Workflows? What are the goals? It is about the DETAILS Once these requirements are defined the selection process can focus on the vendor.

SCOPE COMMUNICATIONS Problem Number 1: SCOPE ü Deliverables ü Boundaries ü Requirements q Clear, Concise and Detailed q Putting a Box around it

SCOPE STATEMENT NEEDS TO INCLUDE: Ø JUSTIFICATION Describes the business need the project addresses. Ø PRODUCT SCOPE Identifies products, services and/or results your project will produce Ø ACCEPTANCE CRITERIA The conditions that must be met before project deliverables are accepted Ø DELIVERABLES This identifies the products, services and /or results (the objectives) Ø ASSUMPTIONS - Statements on how vendor will address uncertain information

Ø CONSTRAINTS Identify restrictions that limit what can be achieved Ø PROJECT EXCLUSIONS Statement about what the project will not accomplish or produce. Summary: All stakeholders agreed on a set of requirements that in hindsight did not provide sufficient detail. Detailed understanding of the scope is essential for all stakeholders. Depending on the level of detail in the scope will certainly facilitate the decision making for the go/no go decision by the client and vendor. The project managers needs to be mindful of scope growth.

What Happened??? Success was hard to achieve, even though in the end we were successful. Agreement by all parties on deliverables, timelines, differed: Scope verses discovery Ø The Scope of the project was defined in Statement of Work Ø Discovery happened after all the contracts were signed; creating many issues instantly Ø Account Manager should have an active role in the account; Ø The Account Manager should play a key role, it should be established as to the role of the Account Manager

Problem Number 2: SCHEDULE Ø The project MUST HAVE a defined schedule with realistic measureable milestones. Ø All projects are dynamic and need a meaning schedule to accommodate this dynamic. Ø Both client and vendor MUST be a part of the process. Ø The schedule is crucial in measuring how well the project is going; and if expectations are being met Ø Have a defined plan for what happens when the schedule slips or changes --- IT WILL Ø Without a schedule the project is destine to possible overruns and failure

Problem Number 3: RESOURCES Ø Ensure resources are identified for project ü what resources are needed ü When is the resource needed Ø Identify internal and external teams ü areas of expertise ü how teams will work together cohesively Ø Identify standard implementation processes ü Increases team efficiency ü This will eliminate re-work Ø Conflict resolution Ø Have a documented plan Ø Imperative all parties agree with plan

WITHOUT COMMUNICATIONS THE PROJECT IS BUSTED! The key to success is communicate communicate communicate Ø No hidden agendas open communications Ø Detailed, written communication plan Ø Professional show mutual respect for everyone s contributions Ø Problems Identify, document communicate Ø Accomplishments communicate to all stakeholders Ø Conflict Escalation Plan Ø Identify decision makers ie. Supporters, observers, doers

TESTING q Define test procedures q A description of the strategies/approach that will be used q Define acceptance TRAINING q What will be covered in training q Length of training q Who will do training q What type of training q User guides

q Never assume ask Ask Questions detailed questions q What is the state of the financial health of the vendor? q What are the future plans for the company? q Does the vendor have a large development group q Escalation processes for the project and after implementation? q Ask for references q Ask about functionality, growth potential, how they see the vision of the vendor for the future q How the implementation went and details of how problem resolution was handled q How qualified was the team that did their implementation; would they recommend them

q Ask about support? q Are there different levels; which level do they have? q How often they need to reach out to support q What is the turn around time for problems q Critical problems how are they handled/ escalated q How would they rate support overall from 1-10 q Ask what assurances you have for completion dates and what happens when the project slips penalties? q Ask about the relationship of the Account Manager to the project q Will he/she play a role in oversight? q Ask about frequency of upgrades q Inquire about applying upgrades/cost q Ask how many people would be assigned to the project

q How are they selected; Do they work on site/off site; What are the resources when problems arise? q How are bugs identified and handled? The escalation process. q Will there be someone on site for the duration; will they spilt their time with other projects pulled away q If an escalation process is defined and it doesn t work; what is the recourse q Find out about training, who, length, curriculum q What process is used for testing q If there is a discovery process what documents will come out of this process q Will there be a workflow defined for client acceptance

What were the top 6 pitfalls? q Workflow requirements not shared with customer q Communication flow between project managers q Defining communication flow between the teams and how it should be streamlined for effectiveness q Lack of being forthright with schedule and delays; q Did not understand how sales and service organizations worked; were they cohesive? q There were gaps of time when the implementation team was pulled away for other projects

What were the positives? q In spite of many pitfalls and setbacks the implementation was a success and has been well received within our user community. q The vendor remained committed to the completion of the project and worked with us through all obstacles. q The system integrated new technology, making our user community more productive, data integrity, data defensibility and functionality that promotes future growth. q The vendor reached out to us and really stepped up to make things right; a commitment to not cut corners but deliver a solid LIMS. q Based on our goals and needs the LIMS is effective and reliable and has met and exceeded the expectations.

SUMMATION The project completed It did not complete on time It was an extensive, aggressive schedule and a very large project q Do Not Assume Anything. Come to the table prepared, be willing to challenge decisions made by implementation team. Be a team player. q Look to implementation team for options and insist on having them presented so that the best one is selected. q Be open to new ideas. Set expectations early on; be firm q Ask questions about the implementation process and the success rate of the vendor s q Understand how the sales and service organizations worked; were they cohesive?

So why did the project ultimately succeed in spite of all the problems encountered? PERSEVERANCE The commitment of the vendor was always there; along with the commitment from the user community. All parties remained committed and focused to see the project to completion.