* IN THE HIGH COURT OF DELHI AT NEW DELHI. % Judgment pronounced on: 27 th January, ARB. P. No.373/2015. versus

Similar documents
HINDUSTAN CONSTRUCTION COMPANY LTD... Petitioner Through Mr.Dherainder Negi, Adv. with Ms.Smita Bhargava, Adv.

IN THE HIGH COURT OF DELHI AT NEW DELHI. AA No.396/2007. Date of decision: December 3, Vs.

IN THE SUPREME COURT OF INDIA ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 20 OF Vs. DEVAS MULTIMEDIA P. LTD...

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL No.11249/2018 [Arising out of SLP (CIVIL) No.

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS OF 2017 M/S LION ENGINEERING CONSULTANTS VERSUS O R D E R

Review Petition No.116/2015 In Arb. Pet. No.17/2013 (D/O). 1. The Gauhati Municipal Corporation. Panbazar, Guwahati.

M/S. SAIPEM TRIUNE ENGINEERING PVT. LTD. Plaintiff. - versus - INDIAN OIL PETRONAS PVT. LTD.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, Date of Judgment :

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 ARB.P. 63/2012 Date of Decision : December 06, 2012

Through Mr.Prabhjit Jauhar Adv. with Ms.Anupama Kaul, Adv.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE Date of Judgment: FAO (OS) 298/2010

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on: 29 th November, 2017 Pronounced on: 08 th December versus

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SERVICE MATTER ARB P. 180/2003. Judgment delivered on: versus

THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 Judgment delivered on:

Bar and Bench (

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION & CONCILIATION ACT, 1996 Judgement delivered on: O.M.P.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR DECLARATION. Date of Reserve: January 14, Date of Order: January 21, 2009

2 entered into an agreement, which is called a Conducting Agreement, with the respondent on In terms of the agreement, the appellant was r

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CONSUMER PROTECTION ACT, Date of Decision: W.P.(C) 8285/2010 & C.M. No.

* IN THE HIGH COURT OF DELHI AT NEW DELHI. + ARB.A. 5/2015 & IA 2340/2015 (for stay) versus

THE ADMINISTRATIVE TRIBUNALS ACT, 1985 ACT NO. 13 OF 1985 [27th February, 1985.]

* IN THE HIGH COURT OF DELHI AT NEW DELHI. % Judgment reserved on: 19 th July, 2016 Judgment delivered on: 29 th July, 2016

* IN THE HIGH COURT OF DELHI AT NEW DELHI. % Date of Decision: 23 rd December, ARB.P. 351/2015 and I.A. No.21099/2015.

IN THE HIGH COURT OF DELHI : NEW DELHI. SUBJECT : Bihar Shops and Establishment Act, W.P.(C) No. 5114/2005. Judgment decided on:

* IN THE HIGH COURT OF DELHI AT NEW DELHI. Reserved on: % Date of Decision: WP(C) No.7084 of 2010

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY MATTER. Date of Decision : January 16, 2007 W.P.(C) 344/2007

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NOS OF 2018 (Arising out of SLP(C) Nos.

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO Of 2011 SRI MAHABIR PROSAD CHOUDHARY...APPELLANT(S) VERSUS

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB. P. 537/2016. versus J U D G M E NT

M/S. Iritech Inc vs The Controller Of Patents on 20 April, % Judgment pronounced on: 20th April, 2017

IN THE HIGH COURT OF DELHI AT NEW DELHI. SUBJECT : Arbitration and Conciliation Act, OMP No.356/2004. Date of decision : 30th November, 2007

* IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 6105/2011. % SADHNA BHARDWAJ.. Petitioner Through: Mr. Dipak Bhattarcharya, Adv.

ONGC PETRO ADDITIONS LTD. Vs. DAELIM INDUSTRIAL COMPANY LTD. KOREA

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on: 22 nd November, 2017 Pronounced on: 11 th December, 2017 POWER GRID CORPORATION

* IN THE HIGH COURT OF DELHI AT NEW DELHI. % Judgment pronounced on: 20 th April, versus. Advocates who appeared in this case:

Through: Versus. Through: 2. To be referred to the reporter or not? Yes. 3. Whether the judgment should be reported in the Digest?

M/S UTC FIRE & SECURITY INDIA LTD Through: Ms Jasleen K. Oberoi and Ms Surbhi Mehta, Advs.

IN THE HIGH COURT OF KARNATAKA AT BANGALORE DATED THIS THE 1 ST DAY OF MARCH 2014 BEFORE: THE HON BLE MR. JUSTICE ANAND BYRAREDDY

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL. Original Application No. 129/2013 (CZ)

IN THE HIGH COURT OF KARNATAKA, BANGALORE BEFORE THE HON'BLE MR.JUSTICE RAM MOHAN REDDY C.M.P. NO.178/2013

IN THE HIGH COURT OF DELHI : NEW DELHI SUBJECT : SERVICE MATTER W.P.(C) No.9681/2009 Judgment decided on:

* IN THE HIGH COURT OF DELHI AT NEW DELHI. + CS(OS) No.2524A/1995 & IA No.515/1996

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS OF 2019

- 1 - IN THE HIGH COURT OF KARNATAKA AT BANGALORE DATED THIS THE 2 nd DAY OF JULY, 2012 BEFORE THE HON BLE MR.JUSTICE ARAVIND KUMAR

Through :Mr. Rajiv Nayar, Sr. Advocate with Mr. Darpan Wadhwa, Ms. Abhiruchi Arora, Mr. Akhil Sachar and Ms. Jaishree Shukla, Advs.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, Date of Reserve: Date of Order:

+OMP 191/2009 % M/s Delhi Apartments Pvt. Ltd. Through: Mr. Sandeep Sethi, Sr. Advocate with Mr. D. Moitra, Advocates

Case No.3 of Shri P.Subrahmanyam, Chairman Shri Venkat Chary, Member, Shri Jayant Deo, Member.

Bar & Bench (

*IN THE HIGH COURT OF DELHI AT NEW DELHI. % Judgment Reserved on: 18 th November, 2015 Judgment Delivered on: 02 nd February, 2016

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE FAO.No.301/2010 Reserved on: Decided on:

IN THE HIGH COURT OF MADRAS. C.R.P. (NPD) No. 574 of Decided On:

India. Neerav Merchant. Majmudar & Partners Mumbai. Law firm bio

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL Nos OF Surat Singh (Dead).Appellant(s) VERSUS

3. The Senior Divisional Personnel Officer South Western Railway Hubli Division, Hubli PETITIONERS

HONOURABLE MR.JUSTICE D.A.MEHTA HONOURABLE MS.JUSTICE H.N.DEVANI. KANUBHAI M PATEL HUF - Petitioner(s) Versus

State Of A.P vs V. Sarma Rao & Ors. Etc. Etc on 10 November, 2006

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL Nos OF 2017 (ARISING OUT OF SLP (CIVIL) Nos.

IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION WRIT PETITION (C) NO. 14 OF General Insurance Council & Ors.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CONDONATION OF DELAY. W.P (C ) No /2006. Judgment reserved on: October 19, 2006

IN THE HIGH COURT OF DELHI AT NEW DELHI. 1. Writ Petition (Civil) No of Judgment reserved on: August 30, 2007

IN THE HIGH COURT OF KARNATAKA AT BENGALURU PRESENT THE HON BLE MR.JUSTICE VINEET SARAN AND THE HON BLE MRS.JUSTICE S SUJATHA

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO OF 2018 (Arising from SLP(C) Nos.28137/2018)

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO OF 2018 [ARISING OUT OF SLP(CIVIL) NO OF 2018] VERSUS

W.P.(C) 6328/2013 & CM No.13822/2013

W.P. (C) No. 8579/2007 Page 1 of 5

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR PERMANENT INJUNCTION. CS (OS) No.284/2012. Date of order:

* IN THE HIGH COURT OF DELHI AT NEW DELHI. + W.P.(C) 5537/2018 & CM Nos /2018 & 33487/2018. versus

IN THE HIGH COURT OF JHARKHAND AT RANCHI L. P. A. No. 511 of 2009

IN THE HIGH COURT OF DELHI AT NEW DELHI. SUBJECT : Delhi Sales Tax Act, Judgment reserved on : Judgment delivered on :

$~19 * IN THE HIGH COURT OF DELHI AT NEW DELHI + FAO 156/2014. versus

* IN THE HIGH COURT OF DELHI AT NEW DELHI. Through CORAM: HON'BLE MR. JUSTICE SANJIV KHANNA O R D E R

* IN THE HIGH COURT OF DELHI AT NEW DELHI Judgment Reserved on: February 05, 2016 % Judgment Delivered on : February 08, FAO(OS) 476/2015

THE HIGH COURT OF DELHI AT NEW DELHI

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO.3349 OF M/s. J.G.Engineers Pvt. Ltd.

Reserved on: 7 th August, Pronounced on: 13 th August, # SAIL EX-EMPLOYEES ASSOCIATION...Petitioner

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NOS OF 2019 (Arising out of SLP(C) Nos of 2012)

* IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 7262/2014

IN THE SUPREME COURT OF INDIA CRIMINAL APPELLATE JURISDICTION. CRIMINAL APPEAL NO. 483 OF 2019 (Arising out of SLP(Crl.) No.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION ACT. Arb. Appl. No. 261/2008. Date of decision :

IN THE HIGH COURT OF JHARKHAND AT RANCHI. W.P. (L) No of 2008

ARBITRATION AGREEMENT

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SERVICE MATTER. Through : Mr.Harvinder Singh with Ms. Sonia Khurana, Advs.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION & CONCILIATION ACT. Date of decision: 8th March, 2013 EFA(OS) 34/2012

.. IN HIGH COURT OF DELHI:AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE. I.A. No /2006 in C.S.(OS) No.795/2004

JOINT VENTURE/SHARE HOLDERS AGREEMENT. THIS AGREEMENT is executed at [Name of city ] on the day of [Date, month and year ]

THE ARBITRATION AND CONCILIATION (AMENDMENT) BILL, 2015

THE INTER-STATE RIVER WATER DISPUTES ACT, 1956 ACT NO. 33 OF [28th August, 1956.]

* IN THE HIGH COURT OF DELHI AT NEW DELHI % Judgment delivered on: WP(C) 687/2015 and CM No.1222/2015 VERSUS

Karnataka Power... vs Ashok Iron Works Pvt. Ltd on 9 February, Karnataka Power... vs Ashok Iron Works Pvt. Ltd on 9 February, 2009

ICC Rules of Conciliation and Arbitration 1975

versus Through Mr. Saleem Ahmed, ASC for the State with SI Ravi Kumar. Mr. Surender Singh, Adv. for R-2.

State Bank of India. Deputy Commercial Tax Officer, Suryapet, Nalgonda District, and others (and vice versa)

IN THE HIGH COURT OF KARNATAKA DHARWAD BENCH BEFORE THE HON'BLE MR. JUSTICE B.MANOHAR. W.P. No & W.P.Nos /2012(T-RES)

* IN THE HIGH COURT OF DELHI AT NEW DELHI. + W.P.(C) 4784/2014 and CM No.9529/2014 (Stay)

2015-TIOL-820-HC-MAD-CX IN THE HIGH COURT OF MADRAS. Writ Appeal No. 821 of 2012 MP No. 1 of 2012

IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION

IN THE HIGH COURT OF DELHI AT NEW DELHI

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO(s) OF 2013 NEW INDIA ASSURANCE CO. LTD

Sub: In the matter of representation in compliance to the directions of Hon ble High Court, Jabalpur in Writ Petition no.

Transcription:

* IN THE HIGH COURT OF DELHI AT NEW DELHI % Judgment pronounced on: 27 th January, 2016 + ARB. P. No.373/2015 CONCEPT INFRACON PVT. LTD... Petitioner Through: Mr.Balaji Subramanium, Adv. with Mr.Samar Bansal and Mr.Vinayak Mehrotra, Advs. versus HIMALAYA CREST POWER LTD.... Respondent Through: Mr.Arun Arora, Adv. with Ms.Preeti,Adv. CORAM: HON'BLE MR.JUSTICE MANMOHAN SINGH MANMOHAN SINGH, J. 1. The present arbitration petition has been filed under Section11 of the Arbitration and Conciliation Act seeking appointment of a sole Arbitrator to resolve the disputes that have arisen between the petitioner and the respondent in relation to the Agreement signed between the parties in the year 2011 (hereinafter referred to as the "2011 agreement"). 2. The 2011 Agreement was executed between the parties on 28 th April, 2011 with the petitioner as the contractor and the respondent as the employer. The scope of the agreement was for the contractor to complete the balance civil work in the hydroelectric power project known as Timbi Hydroelectric Project in Himachal Pradesh. Arb.P. No. 373/2015 Page 1 of 10

3. The petitioner's case is that it has not been paid for work done by it. The petitioner's obligation under the 2011 Agreement was to carry out 'balance civil work' at the project. This is because the initial part of the work had been executed by a different contractor under an agreement signed in 2005 (hereinafter referred to as the "2005 Agreement"). In the Letter of Acceptance dated 18 th April, 2011 issued by the respondent to the petitioner, it was expressly provided that the "scope of work and terms and conditions shall be in accordance with our earlier Tender Call No.1396/Timbi/Civil/2005". Thus, all the terms and conditions of the 2005 Agreement were incorporated into the 2011 Agreement. 4. The relevant dispute resolution clauses in the 2011 Agreement (incorporated through the 2005 Agreement) are as follows : Clause 1.1 para 1: The Adjudicator is the person appointed jointly by the Employer and the Contractor to resolve disputes in the first instance, as provided for in clauses 24 and 25. The name of the Adjudicator is defined in the Contract Data. Clause 24: If the Contractor believes that a decision taken by the Engineer was either outside the authority given to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be referred to the Adjudicator within 14 days of the notification of the Engineer's decision. Clause 25.1: The Adjudicator shall give a decision in writing within 28 days of receipt of a notification of a dispute. Clause 25.2: The Adjudicator shall be paid daily at the rate specified in the Contract Data together with reimbursable expenses of the types specified in the Contract Data and the cost shall be divided equally between the Employer and Arb.P. No. 373/2015 Page 2 of 10

the Contractor, whatever decision is reached by the Adjudicator. Either party may refer a decision of the Adjudicator to an Arbitrator within 28 days of the Adjudicator's written decision. If neither party refers the dispute to arbitration within the above 28 days, the Adjudicator's decision will be final and binding. Clause 25.3: The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special Conditions of Contract. Clause 25.3(f) (Special Conditions of Contract): Where the value of the contract is Rs. 50 millions and below, the disputes or differences arising shall be referred to the Sole Arbitrator. The Sole Arbitrator should be appointed by agreement between the parties; failing such agreement, by the appointing authority, namely the Indian Council for Arbitration/ President of the Institution of Engineers (India)/The International Center for Alternative Dispute Resolution (India). 5. The procedure envisaged under the 2011 Agreement is that disputes are to be first referred to an Adjudicator and thereafter to be referred to arbitration. The value of the dispute in the present case is admittedly less than Rs. 5 crore and therefore, the matter is to be decided by a sole Arbitrator as provided in clause 25.3 (f). However, portion of the clause pertaining to the appointing authority is unenforceable since it mentions three separate institutions, namely the Indian Council of Arbitration, the President of the Institution of Engineers (India), and the International Centre for Alternative Dispute Resolution (India). These are three separate, independent and totally unconnected institutions and it is impossible to determine which one shall be the appointing authority. Hence, this application has been filed in this Court either for referring the matter to the Delhi Arb.P. No. 373/2015 Page 3 of 10

International Arbitration Centre established by this Court or to appoint sole Arbitrator by this Court. 6. Thereafter, as per the respondent the disputes arose between the parties as the petitioner abandoned the contract after completion of only 5% of the total work. 7. The petitioner by notice dated 19 th May, 2007 claimed a sum of Rs.18,49,533/-. The respondent gave a notice of fundamental breaches of contract and levy of liquidated damages in the sum of Rs.29,28,990/- by notice dated 13 th March, 2015. 8. On 11 th March, 2015, the petitioner referred its disputes to Mr. G.S. Chandpuri for adjudication. As per Clauses 24 and 25 of the contract, the Adjudicator was required to submit a decision within 28 days. However, on 8 th April, 2015, after a period of 28 days, Mr. Chandpuri replied while declining to adjudicate the matter. Therefore, it is submitted that the petitioner has complied with the pre-arbitral procedure laid down in the contract to the extent possible. 9. Thereafter, on 6 th May, 2015 the petitioner issued the notice for Arbitration to the respondent. It also suggested the names of two persons vide notice dated 6 th May, 2015 for the appointment of Arbitrator. However, the respondent did not reply to the said notice. Thereafter, the petitioner was constrained to approach this Court for appointment of a sole Arbitrator. 10. The respondent has opposed the petition by primarily contending that the reference would be premature since the matter has not been first dealt with by an adjudicator. Arb.P. No. 373/2015 Page 4 of 10

11. In the present contract between the parties, the name of Adjudicator was yet to be agreed to by and between the parties as the same was left in blank in contract data at page 7 of respondent s documents and the said name was to be filled in after the Adjudicator was appointed by mutual consent of the parties. 12. The Adjudicator jointly appointed by the parties is required to give decision in writing within 28 days of receipt of a notification of a dispute as per clause 25.1. The Adjudicator s decision would be final and binding on the parties unless either of the parties refer the decision of the Adjudicator to an Arbitrator within 28 days of the Adjudicator s written decision. 13. The dispute resolution machinery provides for Replacement of Adjudicator as under:- Should the Adjudicator resign or die or should the Employer of the Contractor agree that the Adjudicator is not fulfilling his function in accordance with the provisions of the Contract, a new Adjudicator will be jointly appointed by the Employer and the Contractor. In case of disagreement between the employer and the Contractor, within 30 days, the Adjudicator shall be designated by the Appointing Authority designated in the Contract Date at the request of either party, within 14 days of such request. In view of the clause 25.2 of the contract, a written decision of the Adjudicator is a mandatory condition precedent to reference of dispute to sole Arbitrator designated by the Appointing Authorities mentioned in clause 4 of Conditions of Contract i.e. Indian Council of Arbitration or President of Institution of Engineers (India) or the International Centre for Alternative Disputes Resolution. Arb.P. No. 373/2015 Page 5 of 10

14. In the present case, the petitioner and the respondent did not jointly designated any person to act as Adjudicator for resolution of disputes between the parties as the petitioner never approached the respondent for appointment of an Adjudicator with mutual consent. The petitioner, no doubt, unilaterally approached Mr.G.S. Chandpuri, with reference to Agreement No.1397/Timbi/balance main works/2011 dated 28 th April, 2011 clearly mentioning that the agreement was between the petitioner and respondent. 15. There is a force in the submission of the counsel for the respondent that Mr.Chandpuri is a stranger to the contract between the petitioner and the respondent. Mr.Chandpuri was nominated as Adjudicator by the respondent and one erstwhile contractor namely, M/s Srinivasa Constructions Limited Hyderabad in the year 2005. Mr.Chandpuri could not have been aware of the petitioner in any manner as Mr.Chandpuri s name was not mentioned in the contract executed between the petitioner and the respondent in the year 2011 and the petitioner wrongfully approached Mr.Chandpuri vide its letter dated 11 th March, 2015 for getting his consent to act as an Adjudicator for resolution of dispute between the parties. It is the admitted position that in response to the petitioner, Mr.Chandpuri rightly informed the petitioner by his handwritten letter dated 8 th April, 2015 that Mr.Chandpuri was not aware about the contract and did not know anything about the matter. 16. Thus, Mr.Chandpuri was not jointly appointed by the petitioner and the respondent. The parties need to jointly apppoint an Adjudicator in terms of clause 1.1 of the Conditions of Contract Arb.P. No. 373/2015 Page 6 of 10

between the parties as stated herein above. The petitioner did not contact the respondent for jointly nominating a person as Adjudicator for resolution of dispute. 17. Clause 26 of the Conditions of Contract provides that in case of disagreement between the parties the nominated institutions can be approached for designating a person as Adjudicator who would give his written decision in 28 days. The decision by an Adjudicator cannot be considered as merely directory because the parties have consciously adopted this particular mode of resolution of disputes bteween the parties by a written contract and the procedure of resolution of the dispute between the parties through Adjudicator has not yet been exhausted in terms of the contract. 18. In the case of Municipal Corporation Jabalpur v. Rajesh Construction, 2007 (2) Arb.LR 65 (SC), the Supreme Court after considering the disputes resolution machinery provided for by agreement between the parties and Section 11(6) (c) that where a person, including an institution, fails to perform any function entrusted to him or it under that procedure, a party may request the Chief Justice or any person or institution designated by him to take the necessary measures, unless the agreement on the appointment procedure provides other means for securing the appointment and held as under :- 24.That apart, it has to be kept in mind that it is always the duty of the court to construe the arbitration agreement in a manner so as to uphold the same. Therefore we must hold that the High Court ought not to have appointed an arbitrator in a manner, which was inconsistent with the arbitration agreement. Arb.P. No. 373/2015 Page 7 of 10

19. In the case of Indian Iron and Steel Co. Ltd. v. Tiwari Road Lines 2007 (2) Arb.LR 270 (SC) it was held as under:- 8. In the present case the agreement executed between the parties contains an arbitration clause and clause 13.1 clearly provides that all disputes and differences whatsoever arising between the parties out of or relating to the construction, meaning and operation or effect of the contract or the breach thereof shall be settled by arbitration in accordance with the Rules of Arbitration of the Indian Council of Arbitration and the award made in pursuance thereof shall be binding on the parties. This clause is in accordance with sub-section (2) of Section 11 of the Act. There being an agreed procedure for resolution of disputes by arbitration in accordance with the Rules of Arbitration of the Indian Council of Arbitration subsections (3), (4) and (5) of Section 11 can have no application. The stage for invoking sub-section (6) of Section 11 had also not arrived. In these circumstances, the application moved by the respondent before the City Civil Court, Hyderabad, which was a designated authority in accordance with the scheme framed by the Chief Justice of the Andhra Pradesh High Court, was not maintainable at all and the City Civil Court had no jurisdiction or authority to appoint an arbitrator. Thus the order dated 31-3-2004 passed by the Chief Judge, City Civil Courts, Hyderabad, appointing a retired judicial officer as arbitrator is clearly without jurisdiction and has to be set aside. 9. The legislative scheme of Section 11 is very clear. If the parties have agreed on a procedure for appointing the arbitrator or arbitrators as contemplated by sub-section (2) thereof, then the dispute between the parties has to be decided in accordance with the said procedure and recourse to the Chief Justice or his designate cannot be taken straightaway. A party can approach the Chief Justice or his designate only if the parties have not agreed on a procedure for appointing the arbitrator as contemplated by sub-section (2) of Section 11 of the Act or the various contingencies provided for in sub-section Arb.P. No. 373/2015 Page 8 of 10

(6) have arisen. Since the parties here had agreed on a procedure for appointing an arbitrator for settling the dispute by arbitration as contemplated by sub-section (2) and there is no allegation that any one of the contingencies enumerated in clause (a) or (b) or (c) of sub-section (6) had arisen, the application moved by the respondent herein to the City Civil Court, Hyderabad, was clearly not maintainable and the said court had no jurisdiction to entertain such an application and pass any order. 20. Even as per amended Sub-Section 6(A) of Section 11, the Court while considering any application, shall confine to examination of the existence of an arbitration agreement. The present petition filed by the petitioner for appointment of a sole Arbitrator is not maintainble in view of the mandatory clauses of the Dispute Resolution Machinery agreed to by and between the parties whereunder a written decision by an Adjudicator jointly nominated by the parties or designated by the appointing authority such as President of Institution of Engineers (India) is a condition precedent to arbitration proceedings and it is a written decision of the Adjudicator which is binding and final between the parties unless one of the parties dissatisfied with the written decision refers the said written decision of the Adjudicator for arbitration in term of clause 25.2 of the Conditions of Contract. 21. In view of the above settled law and facts in the present case, the respondent has valid force in its submissions. The notice issued by the petitioner to invoke arbitration is not issued as per the terms of the contract. However, counsel for the respondent has fairly agreed that as in another matter, this Court in Arb.P. No.324/2010 had requested the Director of IIT, Delhi to nominate a suitable adjudicator Arb.P. No. 373/2015 Page 9 of 10

in terms of agreement, the respondent has no objection if similar order is passed. 22. The petition is accordingly disposed of with the request to the Director of IIT, Delhi to nominate a suitable adjudicator. 23. No costs. JANUARY 27, 2016 (MANMOHAN SINGH) JUDGE Arb.P. No. 373/2015 Page 10 of 10