Routing the Alaska Pipeline Project through the Tetlin National Wildlife Refuge What responsibilities do agencies have under ANILCA?

Similar documents
MEMORANDUM OF UNDERSTANDING. Among

ANGTA Certificate and Right-of-Way Options Options

33 CFR Part 320 General Regulatory Policies

THE AMERICAN LAW INSTITUTE Continuing Legal Education Environmental Law 2017

Applying for Presidential Permits for Border Crossing Facilities (Mexico)

3.2 Assignments and Assumptions of Responsibilities to Comply with Federal Environmental laws Other Than NEPA

Sandra Y. Snyder Regulatory Attorney for Environment & Personnel Safety

Congressional Roll Call Votes on the Keystone XL Pipeline

MEMORANDUM OF UNDERSTANDING Between THE UNITED STATES OF AMERICA And THE STATE OF LOUISIANA

Appendix L Authorization

Case 0:16-cv WPD Document 34 Entered on FLSD Docket 01/22/2017 Page 1 of 10 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA. RIVER WATCH, non-profit

National Oceanic and Atmospheric Administration. Resource Agency Procedures for Conditions and Prescriptions in Hydropower

U.S. ARMY CORPS OF ENGINEERS REGULATORY DIVISION WILMINGTON DISTRICT

National Ass n of Home Builders v. Defenders of Wildlife, 551 U.S. 644 (2007)

EPA S UNPRECEDENTED EXERCISE OF AUTHORITY UNDER CLEAN WATER ACT SECTION 404(C)

Citizen s Guide to the Permitting and Approval Process for Land Development in Pennsylvania

CUSHMAN PROJECT FERC Project No Settlement Agreement for the Cushman Project

ENRD Deputy Assistant Attorneys General and Section Chiefs. Jeffrey H. Wood, Acting Assistant Attorney General

NOTICE ANNOUNCING RE-ISSUANCE OF A REGIONAL GENERAL PERMIT

CITY OF FORTUNA, Defendant. /

UNITED STATES OF AMERICA 118 FERC 62,144 FEDERAL ENERGY REGULATORY COMMISSION

Appendices. Appendix I: National Marine Sanctuaries Act. Appendices. 16 U.S.C et seq., as amended by Public Law

NATIONAL ASSOCIATION OF HOME BUILDERS, ET AL. v. DEFENDERS OF WILDLIFE ET AL. SUPREME COURT OF THE UNITED STATES 551 U.S. 644

NOTE CWA AND ESA: NINE IS A PARTY, TEN IS A CROWD NATIONAL ASSOCIATION OF HOME BUILDERS V. DEFENDERS OF WILDLIFE, 127 S. CT (2007).

Changes to Federal Permit Regulations for Incidental Take of Eagles and Take of Eagle Nests

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION OFFICE OF NATIONAL MARINE SANCTUARIES SEPTEMBER 2009

UNITED STATES OF AMERICA 118 FERC 62,141 FEDERAL ENERGY REGULATORY COMMISSION

Administrative & Judicial Challenges to Environmental Permits. Greg L. Johnson

Navajo Nation Surface Water Quality Standards Certification Regulations

Water Resources Reform and Development Act of 2014: Comparison of Select Provisions

1824 Gibbons vs. Ogden. The Supreme Court clearly arms the principle that commerce" for purposes of the Commerce Clause includes navigation.

Clean Water Act Section 401: Background and Issues

WikiLeaks Document Release

Joshua M. Kindred, Environmental Counsel, Alaska Oil & Gas Association

Coeur Alaska, Inc. v. Southeast Alaska Conservation Council, 129 S. Ct (U.S. 2009).

Case 4:08-cv CW Document 230 Filed 11/18/08 Page 1 of 9 IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF CALIFORNIA

Clean Water Act Jurisdiction: Submitting Requests for Jurisdictional Determinations and Wetland Delineation Approvals/Verification

By the authority vested in me as President by the Constitution and the laws of the United States of America, I hereby direct the following:

Coastal Zone Management Act of 1972

Scott Bulgrin, Pueblo of Sandia

Journal of Environmental and Sustainability Law

INTERAGENCY COOPERATION

DOCKET NO. D CP-1 DELAWARE RIVER BASIN COMMISSION

Deepwater Port License Application: Liberty Natural Gas LLC, Port Ambrose Deepwater Port;

OVERVIEW OF AUTHORITIES AND JURISDICTION

OFFICE OF THE FEDERAL COORDINATOR FOR ALASKA NATURAL GAS TRANSPORTATION PROJECTS

Jenna R. DiFrancesco Burns White LLC Pittsburgh, Pennsylvania 1. Due to recent technological developments, the production of natural gas in the United

Environmental Policy and Political Geography. Strip Mining Diagram. Mountaintop Removal, WV 5/18/2011. Domestic Environmental Issues

Informational Report 1 March 2015

PUBLIC NOTICE (01-17)

Public Notice. P.O. Box 1125 Prospect, Kentucky 40059

8-7. Communications and Legislation Committee. Board of Directors. 4/9/2019 Board Meeting. Subject. Executive Summary. Details

William Kovacs, Senior Vice President, Environment, Technology & Regulatory Affairs, U.S. Chamber of Commerce, Washington, DC

Subject: Opinion on Whether Trinity River Record of Decision is a Rule

ISSUE BRIEF NUMBER IB82046 AUTHOR: William C. Jolly. Environment and Natural Resources Policy Division THE LIBRARY OF CONGRESS

UNITED STATES OF AMERICA 118 FERC 62,159 FEDERAL ENERGY REGULATORY COMMISSION

US Code (Unofficial compilation from the Legal Information Institute) TITLE 43 - PUBLIC LANDS CHAPTER 34 TRANS-ALASKA PIPELINE

REPORT TO CONGRESS. Background

a. Suitable material dredged between June 1 and November 30 may be disposed at SF -10.

COLUMBIA RIVER TREATY & WOTUS RULES UPDATES. Henry s Fork Watershed Council Jerry R. Rigby Rigby, Andrus & Rigby Law, PLLC

CC266 The Platte Rive, Issue of Navigability

Secretary of the Senate Office of Public Records 232 Hart Building Washington, DC


IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF ALASKA

SETTLEMENT AGREEMENT. 1. This Settlement Agreement is entered into this 23d day. of December, 1998 (hereinafter the Effective Date ) among

Arkansas Waterways Commission

Public Notice ISSUED:

Coastal Wetlands Planning, Protection & Restoration Act Public Law , Title III (abbreviated summary of the Act, not part of the Act)

SENATE STAFF ANALYSIS AND ECONOMIC IMPACT STATEMENT

February 20, Dear Acting Administrator Wheeler and Assistant Secretary James:

Congressional Roll Call Votes on the Keystone XL Pipeline

ENR Case Notes, Vol. 34 Recent Environmental Cases and Rules

Case 1:13-cv KBJ Document 49 Filed 11/13/13 Page 1 of 60 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

THIS MEMORANDUM OF UNDERSTANDING (hereinafter "MOU") is entered into by and

SETTLEMENT AGREEMENT CONCERNING THE RELICENSING OF THE PELTON ROUND BUTTE HYDROELECTRIC PROJECT FERC PROJECT NO AMONG

Case 2:07-cv RSL Document 51 Filed 11/09/17 Page 1 of 12

Exports of Liquefied Natural Gas (LNG)

MARINE SPATIAL PLANNING IN U.S. WATERS

One Hundred Fourteenth Congress of the United States of America

Ocean Dumping: An Old Problem Continues

National Marine Sanctuaries

Consolidation of State and Federal Wetland Permitting Programs Implementation of House Bill 759 (Chapter , Laws of Florida) Florida

16 USC NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

SUBJECT: Supreme Court Ruling Concerning CWA Jurisdiction over Isolated Waters

L. Regulation of surface water transfers. (a) Certificate Required. No person, without first obtaining a certificate from the Commission,

on taking action to further proposed projects prior to completion of the environmental review

MONTHLY LEGISLATIVE UPDATE

UNITED STATES OF AMERICA 134 FERC 62,197 FEDERAL ENERGY REGULATORY COMMISSION. Clean River Power 15, LLC Project No

Conservation Congress v. U.S. Forest Service

OFFICE OF THE FEDERAL COORDINATOR FOR ALASKA NATURAL GAS. Natural Gas Transportation Projects is adopting a final policy

Case 5:18-cv Document 85 Filed 03/21/18 Page 1 of 13 PageID #: 7313

CRS Report for Congress

Public Notice CESWF-95-LOP-2. Number: Excavation Activities. Activity: Date Issued: July 7, 1995

CRS Report for Congress

Admiralty Inlet Pilot Tidal Project FERC No Appendix H. Adaptive Management Framework

UNITED STATES DISTRICT COURT DISTRICT OF ARIZONA Prescott Division

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING. (Issued July 19, 2018)

16 USC NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

The Waters of the United States Rule: Legislative Options and 114 th Congress Responses

Transcription:

Routing the Alaska Pipeline Project through the Tetlin National Wildlife Refuge What responsibilities do agencies have under ANILCA? The Alaska Pipeline Project (APP) is proposing a pipeline route that will cross the U.S.-Canada border from lands within the Tetlin National Wildlife Refuge. Congress created the Tetlin National Wildlife Refuge as a conservation system unit through the Alaska National Interest Lands Conservation Act (ANILCA). ANILCA establishes general processes that must be followed and findings that must be made in determining whether federal agencies will approve the construction of transportation or utility systems when they cross lands set aside under that act. In addition, Congress subsequently enacted the Alaska Natural Gas Pipeline Act (ANGPA), which establishes specific procedures for processing permit applications for pipelines that would deliver natural gas from the North Slope of Alaska to the Canadian border. Requirements of ANILCA In 1980, Congress enacted ANILCA and established the Tetlin National Wildlife Refuge as well as other protected lands in Alaska of particular national interest. The statute also established a procedure, Title XI of the act, 16 U.S.C. 3161-3172, for reviewing proposed transportation or utility systems through these newly protected areas using a consolidated process for approval or disapproval. Hereafter, references made to ANILCA are specific to the requirements of Title XI of the act and the implementing regulations, 43 CFR Part 36. ANILCA defines a term, applicable law, which is the law under which an agency would authorize a transportation or utility system if not for ANILCA. The statute then adds additional procedures and findings that apply when considering transportation and utility systems in conservation system units in addition to considerations under each agency s applicable law. ANILCA requires all federal agencies that must authorize all of or part of a transportation or utility system to participate in a unified process. It defines the term ''Federal agency'' to mean any Federal department or agency that has any function or duty under applicable law. This imposes the procedural requirements of ANILCA on all federal agencies that must approve a transportation or utility system. ANILCA's procedural steps must be followed with respect to authorization of the entire system when all or a part of the system would pass through a conservation system unit identified in ANILCA. Accordingly, ANILCA requires each agency that must issue any permit or license for the project to determine whether to approve the system, and leaves intact any other requirements of each agency to issue the permits, licenses or other approvals that would otherwise be required. ANILCA requires that a lead agency prepare a single environmental impact statement (EIS) for the entire system in compliance with the National Environmental Policy Act. ANILCA provides specific timeframes for preparation of the EIS. The draft EIS must be prepared within nine months of the date the application is filed and the final EIS is to be completed three months later. ANILCA allows the lead agency to determine additional time is necessary for good cause. That single EIS is to be relied on by all of the agencies in making their decisions with respect to the system. While each agency must make the required findings, the data, information and analysis supporting the findings would normally be included in the EIS. So unless the applicable law provides different standards for decisions, the findings for each agency should be substantially the same. 1

Each agency must make its ANILCA determination and decision whether to approve the project within four months of the completion of the final EIS. If each agency approves the proposal in accordance with ANILCA considerations and its applicable laws, the system is deemed approved and each agency shall promptly issue its respective authorization. If any agency decides to disapprove, the project is deemed disapproved. The applicant has the right to appeal to the President. The President may override an agency s disapproval on the basis of two findings: 1. The project would be in the public interest, and 2. The project would be compatible with the purposes for which the conservation unit was established. In making the decision, the President shall consider the EIS, public and agency comments, and the findings and recommendations of the federal agencies that rendered a decision with respect to the ANILCA application. Agencies in the ANILCA process Determining which agencies would be required to participate in an ANILCA process is not straightforward. The drafters of ANILCA intended for all agencies with jurisdiction for issuing any permit, right-of-way, license, certificate or other authorization required for a system that passes through a conservation system unit to participate. For some approvals, it is clear that an agency will be required to participate in the ANILCA process. For example: The Secretary of the Interior grants the right-of-way to cross all federal lands, after consulting with other agencies with interests in the land. The Federal Energy Regulatory Commission (FERC) issues a certificate of public convenience and necessity under Section 7 of the Natural Gas Act, authorization for the export of natural gas under Section 3 of the Natural Gas Act, and a Presidential Permit under Executive Order 10485 for border facilities at the international boundary between the United States and Canada. The U.S. Army Corps of Engineers (USACE) issues permits to place fill into wetlands under 404 of the Clean Water Act and for work in navigable waters under 10 of the Rivers and Harbors Act. USACE is also responsible for ocean disposal sites of dredged material as appropriate and the transport of dredged material to the site under 103 of the Marine Protection, Research and Sanctuaries Act, if the application includes such a proposal. The U.S. Coast Guard issues permits under the Rivers and Harbors Act and the General Bridge Act, if the pipeline crosses any navigable waterway. For other agencies, it is less obvious whether the law under which they may authorize the project meets the definition of applicable law under ANILCA. For instance, incidental take statements are normally issued under the Endangered Species Act by the Fish and Wildlife Service and the National Marine Fisheries Service for major projects involving a biological opinion and letters of authorization or incidental harassment authorizations for incidental take of marine mammals under the Marine Mammal Protection Act. The Fish and Wildlife Service is also responsible for permits for take of bald and golden eagles and their nests under the Bald and Golden Eagle Protection Act. These statements or authorizations address the taking or harassing of these species, which presumptively could be mitigated through reasonable and prudent measures and avoidance. Thus, it is unclear whether the 2

transportation or utility system could be constructed without such statements or authorizations, since the taking or harassing of threatened or endangered species is otherwise outlawed. EPA may have to participate in the process under its authority to issue a National Pollution Discharge Elimination System (NPDES) permit under 402 of the Clean Water Act to allow discharges into waters of the United States. The authority to issue NPDES permits for oil and gas activities has not yet been delegated to the state of Alaska as part of the state program under the Clean Water Act. The state is working to obtain this authority to issue such permits in the near future. If it does so before APP files its applications, then the EPA may not need to participate in the ANILCA process. Requirements of ANGPA While ANILCA provides a general approach to processing permit applications for transportation or utility systems through conservation system units, ANGPA provides a specific process for approving and constructing one specific system a natural gas pipeline from the North Slope of Alaska to the Canadian border. ANGPA establishes a specific expedited procedure for the preparation of an EIS for an Alaska natural gas transportation project. Congress designated the FERC as the lead agency to prepare a single EIS that consolidates the environmental reviews of all federal agencies considering any aspect of the Alaska natural gas transportation project. ANGPA also requires that: 1. The EIS "shall be adopted by each Federal agency"... in satisfaction of the responsibilities of the Federal agency under section 102(2)(C) of the National Environmental Policy Act. 2. All agencies considering an aspect of the construction and operation of a project shall cooperate with FERC and comply with the commission s deadlines in preparation of the environmental impact statement. ANGPA established clear deadlines for the completion of the EIS. A draft EIS must be completed within 12 months of the filing of a complete application with the FERC. The final EIS must be completed six months later. FERC is then required to determine whether to issue a certificate of public convenience and necessity within 60 days after completion of the final EIS. ANGPA is silent with respect to the timing of other agencies' decisions. Requirements of the Energy Policy Act of 2005 Section 313 of the Energy Policy Act (EPAct) of 2005 applies permitting provisions comparable to those in ANGPA to other projects under the Natural Gas Act. EPAct designates FERC as the lead agency for preparation of environmental impact statements for natural gas projects. In addition, it authorizes FERC to establish schedules for all federal authorizations that all other agencies must meet. The statute authorizes the applicant to seek judicial enforcement of the schedules. Pursuant to this authority, FERC has issued regulations that require other agencies to make a decision on their authorizations for natural gas projects subject to Section 3 or 7 of the Natural Gas Act no later than 90 days after FERC issues its final environmental document, unless another schedule is established by federal law. 3

Comparison of ANILCA, ANGPA, and EPAct Aside from the obvious difference that ANILCA is a general statute that applies to any transportation or utility system that crosses any conservation system unit in Alaska, and that ANGPA addresses a particular gas line from one specific place to another, there are many similarities and a few differences between ANILCA and ANGPA. Both statutes require most or all of the federal agencies that make decisions with regard to the project to participate in the preparation of a single EIS prepared by a chosen lead agency. ANGPA's language is a bit broader in this regard, extending the obligation to rely on the EIS to all federal agencies with decisions to make about the pipeline that may not meet ANILCA's test of issuing an authorization essential for the construction of the pipeline. The time frames for NEPA compliance are different with ANILCA requiring an EIS to be complete within 12 months as opposed to the 18-month timeframe under ANGPA. This difference reflects a congressional recognition that the Alaska gas line is more complex to construct than a road or telephone line and that more agencies are likely to be included in the decision process. The time difference can be resolved if the lead agency follows the procedure outlined in ANILCA for extending the time for preparation of an EIS publish a notice in the Federal Register, signed by the head of the lead agency, indicating that it has determined that good cause exists to extend the ANILCA deadlines for NEPA to correspond with ANGPA's deadlines. ANILCA, ANGPA, and EPAct all require schedules for a NEPA environmental review and timely issuance of authorizations. The key difference is the timing of the authorizations: 1. Agencies that must approve a transportation or utility system under ANILCA have four months after the final EIS to complete their decisions, followed by the issuance of the authorization, if appropriate. 2. Agencies that do not have to approve a transportation or utility system under ANILCA have 90 days after the final EIS (under EPAct) to make their decisions. The figure below highlights the different timelines under ANILCA, ANGPA, and EPAct. 4

Looking Forward If the pipeline routing as proposed by APP continues through Tetlin Wildlife Refuge, ANILCA will define the approval or disapproval process for certain federal agencies. It will be necessary for each agency to makes it own determination if it is considered an applicable agency with an applicable law. Additionally, it will be necessary for APP to have obtained sufficient data at the time of their application to FERC to meet not only the data needs for the EIS but also for each authorization. 5