S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd

Similar documents
SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598

Uni-Navigation Pte Ltd v Wei Loong Shipping Pte Ltd

THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD

PT Tugu Pratama Indonesia v Magma Nusantara Ltd

Luzon Hydro Corp v Transfield Philippines Inc

COURT OF APPEAL FOR BRITISH COLUMBIA

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan

Northern Elevator Manufacturing Sdn Bhd v United Engineers (Singapore) Pte Ltd

Econ Piling Pte Ltd and another (both formerly trading as Econ-NCC Joint Venture) v Shanghai Tunnel Engineering Co Ltd

I. Supreme Court of Singapore - High Court

Zynergy Solar Projects & Services Pvt Ltd v Phoenix Solar Pte Ltd

VIANINI LAVORI S.P.A. v THE HONG KONG HOUSING AUTHORITY - [1992] HKCU 0463

PART 8 ARBITRATION REGULATIONS CONTENTS

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518

Risis Pte Ltd v Polar Gems Pte Ltd and others

JUDGMENT REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV BETWEEN D. C. DEVELOPERS LIMITED. Claimant AND

MEMORANDUM OF DEPOSIT

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC)

Engineering Construction Pte Ltd v Sanchoon Builders Pte Ltd

THE STATUTES OF THE REPUBLIC OF SINGAPORE ARBITRATION ACT (CHAPTER 10)

IN THE SUPREME COURT OF BELIZE A.D.2009 BETWEEN: THE ATTORNEY GENERAL CLAIMANT

Nagasima Electronic Engineering Pte Ltd v APH Trading Pte Ltd

WSG Nimbus Pte Ltd v Board of Control for Cricket in Sri Lanka

EASTERN CARIBBEAN SUPREME COURT IN THE COURT OF APPEAL

SME Care Pte Ltd v Chan Siew Lee Jannie

Four Pillars Enterprises Co Ltd v Beiersdorf Aktiengesellschaft

IN THE HIGH COURT OF JUSTICE BETWEEN QUANTUM CONSTRUCTION LIMITED AND NEWGATE ENTERPRISES CO. LTD.

IN THE SUPREME COURT OF JUDICATURE HIGH COURT CIVIL DIVISION

Transocean Offshore International Ventures Ltd v Burgundy Global Exploration Corp

Mr Suhail Mir Mohamed Ms Amela Mahmic Ms Aurora Pollara Melbourne Senior Member M. Lothian Hearing. 22 July 2014

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

ICC Rules of Conciliation and Arbitration 1975

Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005.

THE ELECTRICITY ARBITRATION ASSOCIATION

Fisher, Stephen J v Sunho Construction Pte Ltd

State Reporting Bureau

NICK S FISHMONGER HOLDINGS (PTY) LTD ALMON MANUEL ALVES DE SOUSA DEFENDANT CLAIM AND COUNTERCLAIM IN CONTRACT CONTRACT PROVIDING

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS

JUDGMENT. SANS SOUCI LIMITED (Appellant) v VRL SERVICES LIMITED (Respondent)

SMALL CLAIMS COURT ACT

CHINA STATE CONSTRUCTION ENGINEERING CORP GUANGDONG BRANCH v MADIFORD LTD - [1992] 1 HKC 320

THE ROLE OF THE COURTS IN THE ARBITRATION PROCESS

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

IN THE SUPREME COURT OF BELIZE A.D.2003 BETWEEN: LYDIA GUERRA PLAINTIFF BELIZE CANE FARMERS

Financiers' Certifier Direct Deed

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28

IN THE HIGH COURT OF JUSTICE. Between MOOTILAL RAMHIT AND SONS CONTRACTING LIMITED. And EDUCATION FACILITIES COMPANY LIMITED [EFCL] And

c t MECHANICS LIEN ACT

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 11, 2002 Session

John Holland Pty Ltd (formerly known as John Holland Construction & Engineering Pty Ltd) v Toyo Engineering Corp (Japan)

SH Design & Build Pte Ltd v BD Cranetech Pte Ltd

Conditions Precedent to Recovery of Loss and Expense Claims

IN THE HIGH COURT OF JUSTICE BETWEEN GORDON WINTER COMPANY LIMITED AND THE NATIONAL GAS COMPANY OF TRINIDAD AND TOBAGO

Pilecon Engineering Bhd ABDUL KADIR SULAIMAN, JCA ARIFIN ZAKARIA, JCA NIK HASHIM NIK AB. RAHMAN, JCA 23 FEBRUARY 2007

Hitec Power Protection BV v MCI Worldcom Ltd [2002] Adj.L.R. 08/15

Online Case 8 Parvez. Mooney Everett Solicitors Ltd

M. Stephen Turner, P.A., and J. Nels Bjorkquist, of Broad and Cassel, Tallahassee, for Appellant.

IN THE SMALL CLAIMS COURT OF NOVA SCOTIA Cite as: Custom Clean Atlantic Ltd. v. GSF Canada Inc., 2016 NSSM 17 PRELIMINARY RULING ON JURISDICTION

CONSTRUCTION ADJUDICATION. The Basis for Setting Aside Adjudication Determinations

SUPREME COURT OF QUEENSLAND

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT

IN THE HIGH COURT OF JUSTICE. Between ROBERTO CHARLES AND SHASTRI PRABHUDIAL

Sobati General Trading LLC v PT Multistrada Arahsarana

A Case Study in Litigation in Support of Arbitration: China, England, and The Turks and Caicos Islands

IN THE HIGH COURT OF JUSTICE GARY LEGGE AND MAUREEN LEGGE. Between CHRIS RAMSAWACK AND WESTERN SHIP AND RIG SUPPLIES LIMITED

ARBITRATION RULES OF THE COMMON COURT OF JUSTICE AND ARBITRATION

PRIVATE INTERNATIONAL LAW : CONFLICT OF LAWS

IN THE SUPREME COURT OF BELIZE A.D (CIVIL) CLAIM NO. 261 of 2017 BETWEEN

Petroleum Products and Energy Act 13 of 1990 section 4A(2)(b)

RULES FOR ARBITRATION BETWEEN THE BANK FOR INTERNATIONAL SETTLEMENTS AND PRIVATE PARTIES

PLEASE NOTE. For more information concerning the history of this Act, please see the Table of Public Acts.

IN THE CARIBBEAN COURT OF JUSTICE Appellate Jurisdiction ON APPEAL FROM THE COURT OF APPEAL OF GUYANA

Irish Environmental Law Association

IN THE COURT OF APPEAL MOVING TARGET LIMITED. and. Before: The Honourable Mr. Satrohan Singh. [February 22, March 22, 1999] JUDGMENT

Part 36 Extraordinary Remedies

GOVERNMENT OF THE SOVEREIGN DEMOCRATIC REPUBLIC OF FIJI DECREE NO. 7 SMALL CLAIMS TRIBUNAL DECREE, 1991 ARRANGEMENT OF SECTIONS

THE LONDON BAR ARBITRATION SCHEME. Administered by The London Common Law and Commercial Bar Association

TERMS AND CONDITIONS I. GENERAL CONDITION OF TENDER GENERAL CONDITIONS OF THE CONTRACT

Patrick Anthony Gleeson Christina Adrienne Gleeson Geoffrey David Harrison Melbourne Senior Member R Walker Hearing ORDER

IN THE HIGH COURT OF JUSTICE BETWEEN AND. Before: The Hon. Justice Nolan Bereaux. Mr Gaston Benjamin for Plaintiff Mr Carlton George for Defendants

GUTSCHE FAMILY INVESTMENTS (PTY) LIMITED

Citation: Jurisdiction: Singapore

Uniform Class Proceedings Act

IN THE REPUBLIC OF TRINIDAD AND TOBAGO IN THE COURT OF APPEAL BETWEEN FIRST NATIONAL CREDIT UNION CO-OPERATIVE SOCIETY LIMITED AND

PART 6: RESOLVING ISSUES AND PRESERVING RIGHTS

IBHUBHEZI POWERLINES CC

THE LAW SOCIETY CONVEYANCING ARBITRATION RULES

Independent Arbitration Scheme for the Chartered Institute of Management Accountants (CIMA)

IN THE HIGH COURT OF JUSTICE BETWEEN AND

Law of Arbitration DR. ZULKIFLI HASAN

SAINT LUCIA. IN THE HICH COURT OF JUSTICE (CIVIl) A.D Between: JUDCEMENT. Mr Kenneth Monplaisir, OC for the Plaintiff

AON SOUTH AFRICA (PTY) LTD & ASSOCIATED & SUBSIDIARY COMPANIES INTERNAL COMPLAINTS RESOLUTION POLICY AND PROCEDURE DOCUMENT

CASE UPDATE. The High Court Considers the Status and Scope of an Arbitration Agreement in the Context of a Termination of the Main Contract

Through Mr. Atul Nigam, Mr. Amit Tiwari, Advs. versus

L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal

ICC/CMI Rules International Maritime Arbitration Organization in force as from 1 January 1978

JOHN HOLLAND PTY LTD v CHIDAMBARA DENIAL OF NATURAL JUSTICE AND JURISDICTIONAL ERROR IN ADJUDICATION PROCEEDINGS A CASE NOTE I.

7:12 PREVIOUS CHAPTER

Transcription:

[1993] 1 SLR(R) SINGAPORE LAW REPORTS (REISSUE) 793 S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd [1993] SGHC 104 High Court Suit No 1986 of 1991 Amarjeet Singh JC 10 May 1993 Arbitration Stay of court proceedings Court s discretion under Arbitration Act (Cap 10, 1985 Rev Ed) Whether request for extension of time to file defence and counterclaim and for further and better particulars constituted a step in the proceedings Section 7 Arbitration Act (Cap 10, 1985 Rev Ed) Building and Construction Law Building and construction contracts Traditional type of contracts Nominated subcontractor Subsequent oral agreement Whether dispute under subsequent oral agreement a dispute in connection with subcontract Civil Procedure Pleadings Further and better particulars Request for particulars Whether request for particulars made by letter can be equated to an application to court for further particulars Order 18 r 12(6) Rules of the Supreme Court (Cap 322, R 5, 1990 Ed) Facts The defendant Lee Kim Tah (Pte) Ltd, a construction company, entered into a contract dated 6 February 1986 to erect a building for the Singapore Institute of Standards and Industrial Research (the SISR building ). At a later date the defendant engaged the plaintiff S P Chua Pte Ltd as a nominated subcontractor to carry out waterproofing works on the SISR building under a subcontract dated 4 September 1986. There was an arbitration clause in the subcontract. In the middle of carrying out the work, as the plaintiff had financial difficulties, it entered into an oral agreement with the defendant that the defendant would purchase labour and materials for the plaintiff. The plaintiff agreed to confirm in writing on each occasion the costs of such purchases so that they could be deducted from its progress payments. The plaintiff brought an action to recover the balance of $102,368.65 for works done and materials supplied by it under the subcontract. The defendant refused to pay the balance. It claimed that it had a good defence because the plaintiff had performed defective waterproofing works so it was entitled to make deductions and set-offs for the cost of rectification work. The defendant also claimed it was entitled to make deductions and set-offs in respect of the cost of supply of materials on the plaintiff s behalf, which exceeded the plaintiff s claim. The defendant entered an appearance in the proceedings, requested an extension of time to file a defence and counterclaim, then requested further and better particulars by letter served on the plaintiff and filed in court. The defendant then applied for an order that all further proceedings be stayed pursuant to s 7 of the

794 SINGAPORE LAW REPORTS (REISSUE) [1993] 1 SLR(R) Arbitration Act (Cap 10, 1985 Rev Ed) claiming that the arbitration clause covered the plaintiff s claim. The assistant registrar dismissed the defendant s application and the defendant appealed. There were two issues before the court: (a) whether the dispute fell within the arbitration clause (which the plaintiff disputed inter alia on the ground that the oral agreement had been made after the subcontract and so did not come within it) and if so; (b) whether the defendant had taken a step in the proceedings pursuant to s 7 of the Arbitration Act by requesting extra time to file its defence and for better and further particulars. Held, allowing the defendant s appeal: (1) The words arising out of and in connection with this sub-contract or under of or in connection with the sub-contract works or as to any certificated decision direction or instruction of the architect in the arbitration clause were wide enough to cover any dispute except a dispute on whether there was ever a contract at all. The arbitration clause was wide enough to cover the issue of construction and to cover the dispute in relation to the question of the oral agreement between the parties. In any case, the dispute concerning the set-off over these payments was in connection with the subcontract works as the materials supplied was for the subcontract: at [11]. (2) The particulars in support of the plaintiff s claim in respect of the balance were sketchy and there was inadequate detail of the amount due before deductions. The defendant was correct therefore to request more particulars. This request could not be equated with an application to court for further particulars. It was a piece of correspondence between solicitors of the parties and could not constitute a step in the action: at [18] and [19]. (3) As the dispute fell within the arbitration clause, the defendant had not taken any step in the proceedings and was ready and willing to do all things necessary for the proper conduct of the arbitration, the assistant registrar s decision would be set aside and the present proceedings would be stayed: at [20]. Case(s) referred to Brighton Marine Palace and Pier Ltd v Woodhouse [1893] 2 Ch 486 (refd) Eagle Star Insurance Co Ltd v Yuval Insurance Co Ltd [1978] 1 Lloyd s Rep 357 (folld) Ford s Hotel Company, Limited v Bartlett [1896] AC 1 (refd) HE Daniels Ltd v Carmel Exporters and Importers Ltd [1953] 2 QB 242 (folld) Ives and Barker v Willans [1894] 2 Ch 478 (refd) Parker, Gaines & Co, Limited v Turpin [1918] 1 KB 358 (refd) Thorburn v Barnes [1867] 2 LRCP 384 (folld) Legislation referred to Arbitration Act (Cap 10, 1985 Rev Ed) s 7 (consd) Rules of the Supreme Court (Cap 322, R 5, 1990 Ed) O 18 r 12(6) (consd); O 18 r 7

[1993] 1 SLR(R) S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd 795 Andre Yeap (Allen & Gledhill) for the appellant/defendant; Ravintheran Krishnasamy (Ching & Co) for the respondent/plaintiff. 10 May 1993 Judgment reserved. Amarjeet Singh JC: 1 The defendants, a construction company, entered into a contract dated 6 February 1986 with the Singapore Institute of Standards and Industrial Research ( SISIR ) to put up a building known as SISIR Building. The defendants later engaged the plaintiffs as a nominated subcontractor to carry out waterproofing works in respect of the roofing of the said building under a subcontract ( the subcontract ) dated on or about 4 September 1986. 2 In the midst of executing their works, the plaintiffs ran into financial difficulty. They then entered into an oral arrangement with the defendants which was confirmed in writing by the plaintiffs whereby the defendants would undertake the purchase of material or payment of labour on the defendants account. Each time the plaintiffs requested the defendants to purchase building materials for them, they wrote to the defendants confirming at the same time that the costs of such purchases could be deducted from progress payments due to them. 3 When the plaintiffs brought an action to recover the balance of a sum of $102,368.65 for work done and materials supplied by the plaintiffs under the subcontract in respect of the waterproofing works between the end of 1986 and beginning of 1988, the defendants refused to pay the balance due contending that they had a good defence to the action in that: (a) the plaintiffs performed defective waterproofing works and the defendants were entitled to make such claims by way of deductions or set-offs as are necessary to defray the defendants costs incurred in carrying out rectification works; (b) the defendants were further entitled to make deductions and claim a set-off in respect of the cost of supply of certain material on the plaintiffs behalf and such claims in set-offs exceeded the plaintiffs claim. 4 After entering an appearance in the proceedings against them, the defendants requested from the plaintiffs an extension of time to file a defence and counterclaim and when time was granted, followed up instead with a request for further and better particulars by way of a letter which was served on the plaintiffs and filed in court. The plaintiffs responded by filing and serving the further and better particulars. Thereafter the defendants took out an application for an order that all further proceedings in this action be stayed pursuant to s 7 of the Arbitration Act (Cap 10, 1985 Rev Ed), the plaintiffs and the defendants having under the subcontract agreed

796 SINGAPORE LAW REPORTS (REISSUE) [1993] 1 SLR(R) to refer to arbitration the matters in respect of which the action was brought by the plaintiffs. 5 The learned assistant registrar dismissed the defendants application with costs with the result that the defendants filed an appeal against that decision. I allowed the appeal and stayed the proceedings in the suit and fixed the defendants costs, the parties not objecting to the same. 6 Two issues were canvassed before me: (a) whether the dispute falls within the arbitration clause; (b) if so, whether the defendants had taken a step in the proceedings pursuant to s 7 of the Arbitration Act by requesting an extension of time to file their defence and counterclaim and/or by the request for further and better particulars and had thereby elected to abandon their right to stay the proceedings in favour of allowing the action to proceed. 7 Clause 14(1) of the subcontract and s 7 of the Arbitration Act provide as follows: Clause 14(1): Any dispute between the parties hereto as to any matter arising under or out of or in connection with this sub-contract or under or out of or in connection with the sub-contract works or as to any certificate decision direction or instruction of the architect, shall be referred to the arbitration and final decision of a person to be agreed by the parties or failing such agreement within 28 days of either party giving written notice requiring arbitration to the other, to a person to be appointed on the written request of either party by or on behalf of the president or vice-president for the time being of the Singapore Institute of Architects, or failing such appointment within 28 days of receipt of such written request, such person as may be appointed by the courts. Section 7: (1) If any party to an arbitration agreement, or any person claiming through or under him, commences any legal proceedings against any other party to the arbitration agreement, or any person claiming through or under him, in respect of any matter agreed to be referred, any party to the legal proceedings may at any time after appearance, and before delivering any pleadings or taking any other steps in the proceedings, apply to the court to stay the proceedings. (2) The court or a judge thereof, if satisfied that there is no sufficient reason why the matter should not be referred in accordance with the arbitration agreement, and that the applicant was, at the time when the proceedings were commenced, and still remains, ready and willing to do all things necessary to the proper conduct of the arbitration, may make an order staying the proceedings.

[1993] 1 SLR(R) S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd 797 Whether dispute falls within arbitration clause? 8 The plaintiffs contention that the dispute did not fall within the arbitration clause was two-fold. Firstly, it was that the architect who had supervision of the project had certified the sums for payment as they became due to the plaintiffs in respect of the works done and material supplied by them and the defendants were thus bound to honour the payments under the subcontract as a certification would not have been done if the works were defective. The defendants could not, in the circumstances, raise a claim in respect of alleged defective works and any rectifications they may have done. Secondly, the defendants could not set off any sums against those due to them in respect of material and labour supplied by the defendants after they ran into financial difficulties as that arrangement was made subsequent to the subcontract and the dispute was therefore not within the scope of the said subcontract. 9 In respect of the first argument, the defendants countered that notwithstanding the certification of the architect, the architect had conveyed his dissatisfaction with the completed works which was reflected in the architect s letter dated 10 May 1991 requesting for a remedial work to be done upon the defects being discovered. The plaintiffs had refused or neglected to respond and as such the defendants had to carry out the rectification works to comply with the architect s specifications. The defendants had a contractual right to deductions and set-off as this was provided for in the main contract with SISIR. Under the subcontract the plaintiffs were deemed to have knowledge of the provisions of the main contract, the provisions of which were applicable to resolve any ambiguity in the terms of the subcontract between the parties. 10 In respect of the second issue, the defendants submitted that even if the oral arrangement made by the defendants to supply material and labour to the plaintiffs after they became financially troubled was made after the subcontract, the arbitration clause was wide enough to cover the dispute in question since the subsequent oral arrangement was in connection with the subcontract. 11 I upheld the submission of the defendants counsel. In my opinion, the words of the arbitration clause arising out of and in connection with this sub-contract or under or out of or in connection with the sub-contract works or as to any certificated decision direction or instruction of the architect is wide enough to cover the dispute in question relating to the first objection raised by the plaintiffs. The term as to any matter arising under or out of or in connection with this sub-contract or under or out of or in connection with this sub-contract works was decided in the case of HE Daniels Ltd v Carmel Exporters and Importers Ltd [1953] 2 QB 242 to cover every dispute except a dispute whether there was ever a contract at all. The clause is wide enough to cover the issue of construction as well: Thorburn v Barnes [1867] 2 LRCP 284. The clause is similarly wide enough

798 SINGAPORE LAW REPORTS (REISSUE) [1993] 1 SLR(R) to cover the dispute in relation to the question of the oral arrangement made by the plaintiffs with the defendants to supply them with material and labour when during the course of the subcontract they became financially strapped. The oral arrangements to supply material was confirmed by the plaintiffs in writing. They had also agreed to the cost of the material supplied by the defendants be deducted from the progress payments due to them. The dispute in respect of the set-off over these payments was, in any case, in my opinion in connection with the subcontract works as the material supplied was for the subcontract and not otherwise. Whether step in the proceedings taken 12 The defendants had in the instant case admittedly: (a) requested for an extension of time to file their defence and counterclaim and had been given such an extension by the plaintiffs; (b) requested for further and better particulars and also sent a reminder to the plaintiffs in respect thereof and the plaintiffs had subsequently filed and served the same on the defendants. 13 The question was whether any or both these acts constituted a step in the proceedings so as to deprive the defendants of their recourse to arbitration. 14 Quite apart from the request by the defendants for extension of time to file their defence and counterclaim, the plaintiffs counsel contended that the filing of the further and better particulars constituted a pleading and a letter requesting for such particulars forms part of the pleadings as under O 18 r 12(6) the rule requires a defendant applying to court for particulars to first make a request by letter for the particulars and goes on to state that the court may refuse to make the order for particulars subsequently unless there are sufficient reasons for an application by letter not having been made in the first place. Further, counsel argued that under r 7, were [sic] particulars are given pursuant to a request, the request has to be incorporated with the particulars, each item of the particulars following immediately after the corresponding item of the request in much the same way as in an order of the court; further, the defendants had sought and the plaintiffs had given ample particulars. As a result, counsel stated the defendants had clearly by their acts intended to defend the proceedings. 15 What constitutes a step in the proceedings was discussed in Eagle Star Insurance Co Ltd v Yuval Insurance Co Ltd [1978] 1 Lloyd s Rep 357. Drawing on previous authority, Lord Denning MR stated: In order to ask for the court proceedings to be stayed, the defendant must apply to the court: at any time after appearance and before delivering or taking any other steps in the proceedings. Those are the words of s 4 of the 1950 Act and s 1 of the 1975 Act. It has been discussed in several cases. On principle it is a step by which the

[1993] 1 SLR(R) S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd 799 defendant evinces an election to abide by the court proceedings and waives his right to ask for arbitration: Like any election, it must be an equivocal act done with knowledge of the material circumstances 16 Lord Denning went on to state at 361: [I]n order to deprive a defendant of his recourse to arbitration a step in the proceedings must be one which impliedly affirms the correctness of the proceedings and the willingness of the defendant to go along with a determination by the courts of law instead of arbitration. 17 The case discussed in Eagle Star draws a distinction between what may be described as an extra judicial act done by the defendant and one by which he invokes the jurisdiction of the court. Thus in Ives and Barker v Willans [1894] 2 Ch 478, a defendant by a formal document, applied for a delivery of a statement of claim from the plaintiff. The application was held not to be a step in the proceedings as the defendant was entitled to ask for materials affecting his right and remedies to form an opinion as to course of conduct he should take and choose between alternatives. In Brighton Marine Palace and Pier Ltd v Woodhouse [1893] 2 Ch 486 it was held that the defendants solicitors writing for further time to deliver a defence did not constitute a step in the proceedings. In Ford s Hotel Company, Limited v Bartlett [1896] AC 1 on the other hand, where the defendants fourth request for an extension of time being refused (the earlier requests being allowed) the defendants subsequent act of applying by a summons for such an extension proved fatal and was equated with a statement to the effect that the defendants were to defend the action. In Parker, Gaines & Co, Limited v Turpin [1918] 1 KB 358, the respondents applied for discovery of documents. Having obtained the order, they were given discovery in the action. Subsequently they applied to the court to have the proceedings stayed on the ground that they had forgotten or overlooked the arbitration clause in the contract. It was held that the respondents had already taken an unequivocal step which clearly evinced an election to abide by the court proceedings. Mr Justice AT Lawrence said obiter in the course of his judgment: I should have been disposed to look leniently upon the respondent s application for particulars, if that had been the only step alleged, because the particulars were not very ample. But an application for discovery is a very different matter. 18 Having considered the arguments and the law, I was of the view that the particulars given in support of the plaintiffs claim in respect of the balance of $102,368.65 said to be due to them were sketchy. There was an inadequate description of the plaintiffs claim in respect of the amount due before deductions. The deductions were themselves in turn lumped together without particulars. The agreed bills of the defendants were themselves not particularised with their amounts in the statement of claim.

800 SINGAPORE LAW REPORTS (REISSUE) [1993] 1 SLR(R) 19 The defendants were therefore correct in requesting for more particulars so that they could be fully apprised of the details of the plaintiffs works and materials supplied and relate their claims to the amounts due to them for materials supplied and cost incurred in respect of the rectification works. The particulars were also not as ample as they were made out to be. The request for particulars could not, in my opinion, be equated with an application to court for further particulars. At most, it was a piece of correspondence between the solicitors of the parties and did not, in my opinion, constitute a step in the action. Indeed, Mr Justice AT Lawrence in the Parker, Gaines s case had gone much further when he said, though obiter, that he would have been disposed to looking leniently where the respondent had made an application for particulars, if that was the only step he had taken. 20 In the circumstances, as the dispute falls within the arbitration clause and the defendants had not taken any step in the proceedings and as they were ready and willing to do all things necessary to the proper conduct of the arbitration, I set aside the decision of the assistant registrar and allowed the defendants appeal with costs and stayed the proceedings in the action. Headnoted by Rebecca Fay Jordan.