JUDGMENT OF THE COURT (Fifth Chamber) 28 March 1996 *

Similar documents
JUDGMENT OF THE COURT (Fifth Chamber) 13 July 2000 *

JUDGMENT OF THE COURT 17 September 1997 * REFERENCE to the Court under Article 177 of the EC Treaty by the Vergabeüberwachungsausschuß.

JUDGMENT OF THE COURT (Fifth Chamber) 10 April 2003 *

JUDGMENT OF THE COURT 29 September 1998 *

JUDGMENT OF THE COURT 22 April 1997 *

JUDGMENT OF THE COURT 11 August 1995 *

JUDGMENT OF THE COURT 5 October 2000 *

JUDGMENT OF THE COURT (Fifth Chamber) 25 April 1996 *

JUDGMENT OF THE COURT 3 May 1994 *

JUDGMENT OF THE COURT 4 April 1995 *

Judgment of the Court of 22 April Nils Draehmpaehl v Urania Immobilienservice OHG

JUDGMENT OF THE COURT 30 April 1996 *

JUDGMENT OF THE COURT (Fifth Chamber) 14 December 2000 (1) (Action for annulment - Regulation (EC) No 2815/98 - Marketing

JUDGMENT OF THE COURT OF FIRST INSTANCE (Third Chamber, Extended Composition) 31 March 1998 *

JUDGMENT OF THE COURT 10 March 1987 *

ORDER OF THE COURT OF FIRST INSTANCE (Third Chamber) 29 April 1999 *

JUDGMENT OF THE COURT (Fifth Chamber) 15 January 2002 *

JUDGMENT OF THE COURT OF FIRST INSTANCE (Fifth Chamber) 28 September 1999 *

JUDGMENT OF THE COURT 9 November 1995 *

JUDGMENT OF THE COURT 26 November 1996 *

JUDGMENT OF THE COURT 10 July 1991 *

JUDGMENT OF THE COURT (First Chamber) 10 April 2003 *

JUDGMENT OF THE COURT 19 September 1995 *

Judgment of the Court (Fifth Chamber) of 18 October Riksskatteverket v Soghra Gharehveran

JUDGMENT OF THE COURT 18 June 2002*

JUDGMENT OF THE COURT. 16 June 1998 (1)

JUDGMENT OF THE COURT (Fifth Chamber) 8 February 2001 *

JUDGMENT OF THE COURT (Fifth Chamber) 23 March 2000 *

JUDGMENT OF THE COURT 14 December 1995 *

JUDGMENT OF THE COURT (Fifth Chamber) 3 June 1999 *

JUDGMENT OF THE COURT (Sixth Chamber) 15 December 1994 *

JUDGMENT OF THE COURT 22 June 1993 *

JUDGMENT OF THE COURT (Fifth Chamber) 17 June 1999 *

JUDGMENT OF THE COURT 30 June 1988*

JUDGMENT OF THE COURT 14 September 1999 *

JUDGMENT OF THE COURT (Second Chamber) 18 July 2007 * ACTION under Article 228 EC for failure to fulfil obligations, brought on 7 December 2004,

JUDGMENT OF THE COURT 2 March 1999"

JUDGMENT OF THE COURT (Fifth Chamber) 31 May 2001 *

Judgment of the Court of 22 April The Queen v Secretary of State for Social Security, ex parte Eunice Sutton

JUDGMENT OF THE COURT (Fifth Chamber) 2 December 1999 *

JUDGMENT OF THE COURT 2 April 1998 *

JUDGMENT OF THE COURT (Fifth Chamber) 8 June 1999 *

JUDGMENT OF THE COURT 14 December 1995 *

JUDGMENT OF THE COURT 15 March 1988*

JUDGMENT OF THE COURT 23 May 1996 *

JUDGMENT OF THE COURT (Fifth Chamber) 7 March 1996 *

JUDGMENT OF THE COURT (Sixth Chamber) 27 November 2001 *

JUDGMENT OF THE COURT 2 March 1994*

JUDGMENT OF THE COURT (Fifth Chamber) 23 May 1996 *

JUDGMENT OF THE COURT (Fifth Chamber) 14 September 2000 *

JUDGMENT OF THE COURT (Sixth Chamber) 28 October 1999 *

JUDGMENT OF THE COURT (Fifth Chamber) 7 December 1993 *

JUDGMENT OF THE COURT 2 December 1997 *

JUDGMENT OF THE COURT (Fifth Chamber) 22 October 1998 *

JUDGMENT OF THE COURT 20 September 1990 *

JUDGMENT OF THE COURT 22 September 1998 *

JUDGMENT OF THE COURT (First Chamber) 10 June 2004 *

JUDGMENT OF THE COURT (Fifth Chamber) 19 October 2000 *

JUDGMENT OF THE COURT 12 October 1999 *

JUDGMENT OF THE COURT (Third Chamber) 13 July 1995 *

JUDGMENT OF THE COURT (Sixth Chamber) 7 March 1996 *

JUDGMENT OF THE COURT (Fourth Chamber) 26 September 1996 *

JUDGMENT OF THE COURT 5 October 1999 *

JUDGMENT OF THE COURT 30 May 1991 *

JUDGMENT OF THE COURT 5 May 1998 *

JUDGMENT OF THE COURT 28 April 1998 *

JUDGMENT OF THE COURT 20 October 1993 *

JUDGMENT OF THE COURT 4 July 2000 *

JUDGMENT OF THE COURT 9 July 1992 *

JUDGMENT OF THE COURT 1 June 1999 *

JUDGMENT OF THE COURT (Second Chamber) 29 January 2004 *

JUDGMENT OF THE COURT 12 December 2002 *

JUDGMENT OF THE COURT (Fifth Chamber) 11 December 2003 *

JUDGMENT OF THE COURT (Sixth Chamber) 14 December 2000 *

European Court reports 1996 Page I Summary Parties Grounds Decision on costs Operative part. Keywords. Summary. Parties

JUDGMENT OF THE COURT 17 June 1997*

JUDGMENT OF THE COURT 18 January 2001*

JUDGMENT OF THE COURT (Fifth Chamber) 16 September 1999 *

JUDGMENT OF THE COURT 28 April 1988*

Judgment of the Court (Fifth Chamber) of 23 May Reference for a preliminary ruling: Social Security Commissioner - United Kingdom.

JUDGMENT OF THE COURT 8 October 1996 * In Joined Cases C-178/94, C-179/94, C-188/94, C-189/94 and C-190/94,

JUDGMENT OF THE COURT (Sixth Chamber) 16 September 1997*

JUDGMENT OF THE COURT (Fifth Chamber) 11 May 2000 *

JUDGMENT OF THE COURT (Sixth Chamber) 23 April 1991 *

JUDGMENT OF THE COURT 25 July 2002 *

JUDGMENT OF THE COURT OF FIRST INSTANCE (Fourth Chamber) 3 December 2003 *

JUDGMENT OF THE COURT (Grand Chamber) 14 March 2006 * ACTION under Article 228 EC for failure to fulfil obligations, brought on 14 April 2004,

JUDGMENT OF THE COURT (Fifth Chamber) 15 May 2003 *

JUDGMENT OF THE COURT 11 July 2000 *

JUDGMENT OF THE COURT 6 June 1995 *

JUDGMENT OF THE COURT (Third Chamber) 1 July 2004 *

JUDGMENT OF THE COURT 22 June 1999 *

JUDGMENT OF THE COURT. 12 October 1999 (1) (Trade-mark rights - Pharmaceutical products - Parallel imports - Replacement of a trade mark)

JUDGMENT OF THE COURT (Fifth Chamber) 26 June 1990*

JUDGMENT OF THE COURT 11 November 1997'

ORDER OF THE COURT OF FIRST INSTANCE (Second Chamber) 28 November 2005 * European Environmental Bureau (EEB), established in Brussels (Belgium),

JUDGMENT OF THE COURT (Fifth Chamber) 10 May 2001 *

JUDGMENT OF THE COURT 20 September 2001 *

JUDGMENT OF THE COURT 14 December 1995 *

JUDGMENT OF THE COURT (Fifth Chamber) 7 September 1999 *

Transcription:

JUDGMENT OF THE COURT (Fifth Chamber) 28 March 1996 * In Case C-318/94, Commission of the European Communities, represented by Hendrik van Lier, Legal Adviser, and, initially, by Angela Bardenhewer, and, subsequently, by Claudia Schmidt, of its Legal Service, acting as Agents, with an address for service in Luxembourg at the office of Carlos Gómez de la Cruz, also of its Legal Service, Wagner Centre, Kirchberg, applicant, ν Federal Republic of Germany, represented by Ernst Röder, Ministerialrat in the Federal Ministry for Economic Affairs, and Gereon Thiele, Assessor in the same ministry, acting as Agents, D-53107 Bonn, defendant, APPLICATION for a declaration that, the Waterways and Navigation Office, Emden having awarded the public works contract for the dredging of the lower Ems between Papenburg and Oldersum by negotiated procedure without prior publication of a tender notice in the Official Journal of the European Communities, the Federal Republic of Germany has failed to fulfil its obligations under Council Directive 71/305/EEC of 26 July 1971 concerning the coordination of procedures for the award of public works contracts (OJ, English Special Edition 1971 (II), p. 682), as amended by Council Directive 89/440/EEC of 18 July 1989 (OJ 1989 L 210, p. 1), * Language of the case: German. I -1962

COMMISSION ν GERMANY THE COURT (Fifth Chamber), composed of: D. A. O. Edward, President of the Chamber, J. C. Moitinho de Almeida, P. Jann (Rapporteur), L. Sevón and M. Wathelet, Judges, Advocate General: M. B. Elmer, Registrar: R. Grass, having regard to the report of the Judge-Rapporteur, after hearing the Opinion of the Advocate General at the sitting on 8 February 1996, gives the following Judgment 1 By application lodged at the Registry of the Court on 6 December 1994, the Commission of the European Communities brought an action under Article 169 of the EC Treaty for a declaration that, the Waterways and Navigation Office, Emden having awarded the public works contract for the dredging of the lower Ems between Papenburg and Oldersum by negotiated procedure without prior publication of a tender notice in the Official Journal of the European Communities, the Federal Republic of Germany has failed to fulfil its obligations under Council Directive 71/305/EEC of 26 July 1971 concerning the coordination of procedures I -1963

for the award of public works contracts (OJ, English Special Edition 1971 (II), p. 682), as amended by Council Directive 89/440/EEC of 18 July 1989 (OJ 1989 L 210, p. 1, hereinafter 'the Directive'). 2 In September 1989, at the request of the town of Papenburg, a plan was drawn up to alter the bed of the lower Ems with a view to making it navigable for 'Panama' class vessels with a 6.80 metre draught. The deepening of this section of the Ems river was of major economic significance for the region. Moreover, during 1990, the Meyer-Werft shipyard, the largest employer in the region, contracted to deliver a 'Panama' class vessel by 18 February 1992 at the latest. A per diem penalty of USD 80 000 was laid down in the event of failure to comply with that scheduled delivery date. Delivery of the vessel on that date could take place only after completion of this work. 3 Under German legislation, the plans for deepening the lower Ems had to be approved by a procedure requiring, in particular, the agreement of the Weser-Ems Regional Authority. At the end of May 1991, the date envisaged for conclusion of this procedure, the Weser-Ems Regional Authority, which had not previously raised any objection, gave notice that it did not agree to the project on ecological grounds. A decision was then taken to continue the procedure with a view to obtaining approval only of the plans for that part of the project which consisted in temporarily deepening the river bed in order to enable the vessel being built by the Meyer-Werft shipyard to pass through. The plans for this partial project were definitively approved on 15 August 1991. 4 However, on 15 April 1991, the Waterways and Navigation Office, Emden (hereinafter 'the Office'), which intended to award the work in accordance with the I -1964

COMMISSION ν GERMANY open procedure, sent a prior information notice concerning the work envisaged which was published in a supplement to the Official Journal of the European Communities on 20 April 1991. 5 Given the delay in approving the plans, the Office decided to abandon the open procedure and to award the contract by negotiated procedure without prior publication of a tender notice. The contract was awarded on 15 August 1991 pursuant to the latter procedure. 6 By formal notice of 12 November 1991, the Commission instituted Treatyinfringement proceedings against the Federal Republic of Germany under Article 169 of the Treaty on the ground that it had acted in breach of the rules governing the procedure for the award of public works contracts. The Commission pointed out that, in this case, the choice of negotiated procedure could not be justified under Article 5(3)(c) of the Directive. In a letter of 6 March 1992, the German Government disputed that contention. 7 In its reasoned opinion of 27 April 1993, the Commission restated its view and called on the German Government to take the measures necessary to comply with the reasoned opinion and, in particular, to suspend the contract in question, as well as any other contract negotiated on the same terms, within two months of notification of the opinion. 8 In its statement of position of 28 September 1993, the German Government stressed that it was imperative for the work to be completed by 18 February 1992, the date on which the vessel was to be delivered, so that it had to be begun by no I - 1965

later than mid-august 1991. In view of the difficulties arising in the procedure for approval of the plans, it was not possible to follow the open procedure, which would have lasted at least 72 days. 9 The Commission took the view that this reply was unsatisfactory and brought the present action. 10 It is necessary to consider whether the Federal Republic of Germany was entitled, on the basis of Article 5(3)(c) of the Directive, to award the contract in question by negotiated procedure without prior publication of a tender notice. Article 5(3)(c) provides that: 'The contracting authorities may award their public works contracts by negotiated procedure without prior publication of a tender notice, in the following cases: (c) in so far as is strictly necessary when, for reasons of extreme urgency brought about by events unforeseen by the contracting authorities in question, the time-limit laid down for the open, restricted or negotiated procedures referred to in paragraph 2 above cannot be kept. The circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authorities...'. I-1966

COMMISSION ν GERMANY 11 Before Directive 71/305 was amended by Directive 89/440, Article 9 of the earlier directive provided that: 'Authorities awarding contracts may award their works contracts without applying the provisions of this Directive, except those of Article 10, in the following cases: (d) in so far as is strictly necessary when, for reasons of extreme urgency brought [about] by events unforeseen by the authorities awarding contracts, the timelimit laid down in other procedures cannot be kept...'. 12 In so far as Article 5(3)(c) of the Directive reproduces the wording of the former Article 9(d), those provisions must be given the same interpretation. 13 The Court has held in this regard that the provisions of Article 9 of Directive 71/305, which authorize derogations from the rules intended to ensure the effectiveness of the rights conferred by the Treaty in relation to public works contracts, must be interpreted strictly and that the burden of proving the existence of exceptional circumstances justifying a derogation lies on the person seeking to rely on those circumstances (Case C-57/94 Commission ν Italy [1995] ECR 1-1249, paragraph 23). 1 4 The Court has also held that, according to Article 9(d) of Directive 71/305, the derogation for which it provides, namely exemption from the obligation to publish a notice of a call for tenders, is available only if three conditions are fulfilled concurrently. That derogation requires the existence of an unforeseeable event, I -1967

extreme urgency, rendering the observance of time-limits laid down by other procedures impossible, and, finally, a causal link between the unforeseeable event and the extreme urgency resulting therefrom (Case C-107/92 Commission ν Italy [1993] ECR I-4655, paragraph 12). If one of those conditions is not satisfied, use of the negotiated procedure will not be justified. 15 According to the German Government, the event which the contracting authorities could not have foreseen was the totally unexpected refusal by the Weser-Ems Regional Authority to grant its approval following its deliberation. 16 That argument cannot be accepted. 17 It must be stressed that, in order to take account of the public and private interests concerned in procedures for approving public works projects, Member States may confer on natural or legal persons potentially concerned by a project certain rights which the competent authorities must respect. 18 The possibility that a body which must approve a project might, before expiry of the period laid down for this purpose, raise objections for reasons which it is entitled to put forward is, consequently, something which is foreseeable in plan approval procedure. 19 The refusal of the Weser-Ems Regional Authority to approve the project for dredging the lower Ems, thereby obliging the competent authorities to amend that I-1968

COMMISSION ν GERMANY project, cannot therefore be regarded as an event unforeseen by the contracting authorities within the meaning of Article 5(3)(c) of the Directive. 20 It follows from the foregoing, without its being necessary to determine whether the other derogation conditions were satisfied in this case, that, the Waterways and Navigation Office, Emden having awarded the public works contract for the dredging of the lower Ems between Papenburg and Oldersum by negotiated procedure without prior publication of a tender notice in the Official Journal of the European Communities, the Federal Republic of Germany has failed to fulfil its obligations under Council Directive 71/305/EEC of 26 July 1971 concerning the coordination of procedures for the award of public works contracts, as amended by Council Directive 89/440/EEC of 18 July 1989. Costs 21 Under Article 69(2) of the Rules of Procedure, the unsuccessful party is to be ordered to pay the costs. Since the Federal Republic of Germany has been unsuccessful, it must be ordered to pay the costs. On those grounds, THE COURT (Fifth Chamber) hereby: 1. Declares that, the Waterways and Navigation Office, Emden having awarded the public works contract for the dredging of the lower Ems between Papenburg and Oldersum by negotiated procedure without prior I - 1969

publication of a tender notice in the Official Journal of the European Communities, the Federal Republic of Germany has failed to fulfil its obligations under Council Directive 71/305/EEC of 26 July 1971 concerning the coordination of procedures for the award of public works contracts, as amended by Council Directive 89/440/EEC of 18 July 1989; 2. Orders the Federal Republic of Germany to pay the costs. Edward Moitinho de Almeida Jann Sevón Wathelet Delivered in open court in Luxembourg on 28 March 1996. R. Grass Registrar D. A. O. Edward President of the Fifth Chamber I-1970