Conditions Precedent to Recovery of Loss and Expense Claims

Similar documents
Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION

NOTICES, TIME BARS AND PROPORTIONALITY

Martin Waldron BL FCIArb MSCSI MRICS

Martin Waldron BL FCIArb MSCSI MRICS

Time and Construction Contracts

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Commencement of Arbitration and Time-Bar Clauses

CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE

Arbitration Rules No.125

Reinforcing Security of Payment in NSW

DATED [ ] 201[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FIRM FREQUENCY RESPONSE AGREEMENT

PART 8 ARBITRATION REGULATIONS CONTENTS


Legal Awareness In The Construction Industry

THE LAW SOCIETY CONVEYANCING ARBITRATION RULES

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

LIMITATION OF ACTIONS ACT

ATM ACCESS AUSTRALIA LIMITED ATM ACCESS CODE

AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN:

THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION CHESTER-LE-STREET GC TRADING LIMITED. (Company)

THE ELECTRICITY ARBITRATION ASSOCIATION

THE COMPANIES ACT 2006 PRIVATE COMPANY LIMITED BY SHARES ARTICLES OF ASSOCIATION NEWCASTLE CRICKET CLUB (COMMUNITY) LIMITED.

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions

AGREEMENT WITH BUILDER. NAME or COMPANY NAME: ADDRESS:

Mutual Indemnity and Hold Harmless Deed

Agreement to UOB Banker s Guarantee Terms and Conditions

NHS conditions of contract for the sale of scrap March 2007

BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011

SRA Compensation Fund Rules 2011

c t MECHANICS LIEN ACT

DATED 20 HSBC BANK PLC. and [FUNDER] and [COMPANY] DEED OF PRIORITY

Employment (Co-Determination in the Workplace) Act (1976:580)

Standard terms and conditions

FIDIC Conditions of Contract for Construction

PAM NORTHERN CHAPTER

Construction Industry Payment and Adjudication 1. construction industry payment and adjudication act 2012

Clause 3 deals with the duties and obligations of the Engineer and his assistants.

Construction Newsletter Issue No. 20

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

CHAPTER 107 CONTRIBUTORY NEGLIGENCE AND JOINT WRONGDOERS

ALIENATION OF LAND ACT NO. 68 OF 1981

1 terms & conditions STAL5/6 AEF.AS

Possible Legal Issues of Unilaterally Contract Termination for Convenience

TERMS AND CONDITIONS OF SALES

Independent Arbitration Scheme for the Chartered Institute of Management Accountants (CIMA)

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

/...1 PRIVATE ARBITRATION KIT

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because:

Terms of Trade. For the provision of Security Systems Installation and Services By MB Security Ltd

STANDARD MASTER SERVICES AGREEMENT

Freight Investor Solutions DMCC Terms of Business

Review of the Western Australian Construction Contracts Act 2004

THE LONDON MARITIME ARBITRATORS ASSOCIATION THE INTERMEDIATE CLAIMS PROCEDURE (2012)

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS

(27 November 1998 to date) ALIENATION OF LAND ACT 68 OF 1981

B I L L. No. 108 An Act respecting the Athletics Commission and Professional Contests or Exhibitions TABLE OF CONTENTS ATHLETICS COMMISSION 1

HINDUSTAN AERONAUTICS LIMITED IMM DEPARTMENT GENERAL TERMS & CONDITIONS OF CONTRACT

General Conditions of CERN Contracts

MCPS MEMBERSHIP AGREEMENT (MA2) AND ANNEXES

TERMS OF REFERENCE. Issued Date: 3 January 2011

CONSULTANCY SERVICES AGREEMENT

THE INTER-STATE MIGRANT WORKMEN (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) ACT, (No. 30 of 1979)

FOUNDATIONS LAW CONTENTS

BASF Tanzania Limited Standard Terms and Conditions of Sale

STANDARD TRADING TERMS for the SUPPLY OF GOODS OR SERVICES to SAFCOR FREIGHT (PTY) LTD trading as BIDVEST PANALPINA LOGISTICS

Access Agreement. Queensland Rail Limited. [Insert name of Operator] [Insert name of Access Holder]

JUDGMENT THE HIGH COURT OF SOUTH AFRICA GAUTENG LOCAL DIVISION, JOHANNESBURG CASE NO: 07897/2016. In the matter between: SAPOR RENTALS (PTY) LIMITED

Working in Partnership

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:-

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 //

including existing and future fixtures, fittings, alterations and additions.

STREAMLINED JAMS STREAMLINED ARBITRATION RULES & PROCEDURES

7:12 PREVIOUS CHAPTER

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation.

1.2. This book covers the three Agreements published by JBCC (see 2.1 below) and the MBSA 2014 Domestic Subcontract Agreement.

CHAPTER 9 INVESTMENT. Section A

THE REPUBLIC OF UGANDA UGANDA COFFEE TRADE FEDERATION ARBITRATION RULES

SCHEDULE 10 LENDERS REMEDIES AGREEMENT

557. Hearing of proceedings otherwise than in public Power of court to order the return of assets which have been improperly transferred.

Cambridge Assessment Admissions Testing Centre Agreement

WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES

Dated [ ] NORFOLK COUNTY COUNCIL AND [ ] MEMBERS ACCESS AGREEMENT RE LGPS FRAMEWORK ARRANGEMENTS

Rules of the High Court (Family Proceedings) 2009 PART 2 ORDERS WITH RESPECT TO CHILDREN

Labour Court Rules, 2006 ARRANGEMENT OF RULES PART I

Arbitration Act B.E. 2545

TERMS OF TRADING AGREEMENT

General Terms and Conditions of Sale and Delivery of ERC Emissions-Reduzierungs-Concepte GmbH ( ERC )

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

Elements of a Civil Claim

LIENS (770 ILCS 60/) Mechanics Lien Act.

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998

A Summary of Construction Cases in 2012

ARBITRATORS AND MEDIATORS INSTITUTE OF NEW ZEALAND INC ( AMINZ ) AMINZ ARBITRATION APPEAL RULES

General Terms of Contract

Computershare Limited (trading through its division Custodial Services) 2000/006082/06 E. TERMS AND CONDITIONS OF CUSTODY AGREEMENT

Transcription:

Conditions Precedent to Recovery of Loss and Expense Claims Dated 07 January 2011 Author Robert Dalton (Head of Construction and Dispute Resolution NW for Blake Newport) Introduction There is a growing use of condition precedent clauses in contracts, which necessitate the serving of notices to an identified recipient of matters which might delay the works and/or give rise to additional cost. As set out below, where such provisions are properly drafted they are likely to be enforceable. A condition precedent clause requires an event or state of affairs before something else will occur. In a construction context it is generally a provision of the contract which requires the giving of a notice by the contractor, usually within a specified period of time, for any matter that may give rise to a claim for additional time or money. The intention of such provisions is that a failure to comply e.g. issue the required notice will have the effect that the contractor s rights in respect of that matter will be lost. For instance, clause 61.3 of NEC3 relates to the contractor s obligation to notify compensation events and states; if the Contractor does not notify a Compensation Event within 8 weeks of becoming aware of the event he is not entitled to a change in the Price, the Completion Date or a Key Date unless the Project Manager should have notified the event to the contractor but did not. Likewise, clause 28.1 of the 1999 FIDIC form of contract requires the contractor to give notice to the engineer of any event which may give rise to an extension of time or additional payment and states if the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment and the Employer shall be discharged from all liability in connection with the claim. While condition precedent clauses have not generally been a feature of other standard form of building contracts, it is increasingly common to amend these standard forms to introduce such provisions.

Relevant Case Law In Bremer v Vanden 1 the House of Lords stated that a notice provision was unlikely to be a condition precedent unless it prescribed a specific time for delivery of the notice and clearly stated that the rights would be lost in the event that notice was not given. The NEC and FIDIC clauses quoted above clearly accord with this dictum. In City Inn v Shepherd Construction 12 the Inner House of the Court in Session confirmed that a properly drafted condition precedent clause would be enforceable. Shepherd argued that the clause imposed a penalty upon them, because an extension of time to which they were otherwise entitled had not been granted, and delay damages deducted, merely because they had failed to give a notice, rather than as a consequence of any failure on their part to progress the works. The court rejected that argument commenting that the loss suffered by the employer was not converted into a penalty by the fact that the contractor might have avoided the liability by taking certain steps which the contract entitled it to take. Where a contractor s claim is rejected on the grounds that it has failed to serve appropriate notices, the contractor will often argue that the employer s position is contrary to the prevention principle. This principle is based upon the established common law rule that no person can take advantage of the non-fulfilment of a condition, the performance of which he has hindered. In Multiplex Construction v Honeywell Control Systems 3 the court noted that one consequence of the prevention principle is that the employer cannot hold the contractor to a specified completion date if the employer has by act or omission prevented the contractor from completing by that date. Instead time becomes at large and the obligation to complete by this specified date is replaced by an implied obligation to complete within a reasonable time. Whether the prevention principle will defeat a properly drafted condition precedent clause has been examined in a number of cases. The Australian case of Gaymark Investments v Walter Construction 4 is often cited as an example where the court held that the prevention principle presented a formidable barrier to an employer s claim for delay damages, where events which might have given rise to an entitlement to an extension of time were ignored as a consequence of the contractor s failure to issue timely notices. Such an approach has been questioned by the courts in the UK. For example, in the Multiplex case the Judge stated 1 Bremer v Handelgelsellschaft mbh v Vanden Avenne Izegem P.V.B.A [1978] 2 LLR 109 2 City Inn v Shepherd Construction (2003) CILL 2009 3 Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) [2007] EWHC 447 (TCC) 4 Gaymark Investments Pty Ltd v Walter Construction Group [1999]

I have considerable doubt that Gaymark represents the law of England. Contractual terms requiring a contractor to give prompt notice of delay serve a valuable purpose. Such notice enables matters to be investigated while they are still current. Furthermore such notice sometimes gives the employer the opportunity to withdraw the instructions when the financial consequences become apparent. The court rejected the contractor s prevention principle defence on the basis that it was always open to the contractor to protect its interests by giving the relevant notices of delay. Since the Multiplex case, the courts have shown increasing favour towards conditions precedent as an instrument of practical contract administration, including the recent case of WW Gear Construction v McGee Group 5, which is considered in detail below. WW Gear Construction v McGee Group The Facts The contract in this case incorporated the JCT Trade Contract (TC/C) 2002 terms with Amendment No 1:2003, albeit as detailed below this was further amended by the parties. WW Gear Construction ("the Employer") wished to develop a site on the south side of Westminster Bridge, London. The development was to include the construction of the Westminster Park Plaza Hotel. McGee Group ("the Contractor") is a groundworks contractor which was retained by the Employer in August 2007 to carry out excavation and other groundworks for this development. The agreed Contract Sum was 1,812,836.75. The Construction Manager named in the Contract was GC Project Management. The Contractor had completed its work in about May 2009. Disputes subsequently arose between the parties in relation to payments including the Contractor's claims for loss and expense related to delay and disruption. The Contractor made applications for payment, broadly on a monthly basis. The applications included requests or claims for payment for extended preliminary costs associated, with delay either to individual elements of the works (for instance extended preliminaries for capping beam works) and to the works as a whole from about June 2008. For Application 18 which was said to summarise the position up to the end of March 2009, the Contractor referred in its summary to a "Loss & Expense Claim" being "As Attached". That claim, in the sum of 1,555,919.89, included for preliminaries which at least in part had previously formed the subject matter of monthly applications for payment; it included various other delay and disruption claims such as "Site Plant" as well as "Additional Head Office Direct Costs", "Additional Site Management Costs" and "Head Office Overheads & Loss of Profit". 5 WW Gear Construction Ltd v McGee Group Ltd [2010] EWHC 1460

The Employer referred to adjudication issues arising between the parties, including issues relating to the proper interpretation and application of extension of time and delay related loss and expense clauses in the contract. The Adjudicator decided in broad terms against the Employer on these issues. The Employer was not satisfied with this decision albeit it did not seek to challenge the enforceability as such of the decision. Consequently, it sought final declarations in court. The Contract The Contract incorporated the standard Trade Contract (TC/C), albeit amended by the various provisions set out at Part A20 of the Preliminaries and General Conditions. The relevant clauses were as follows (those parts in the body of the clauses which were the subject of the agreed amendments are underlined): Clause 2.2.1 If and whenever it becomes reasonably apparent that the commencement, progress or completion of the Works or any part thereof is being or is likely to be delayed, the Trade Contractor shall forthwith give written notice to the Construction Manager and to the Employer of the material circumstances including, insofar as the Trade Contractor is able, the cause or causes of the delay and identify in such notice any event which in his opinion is a Relevant Event as described in clause 2.5. Any written notice given under this clause will be separate from other correspondence and delivered by facsimile and post. It will be headed "this is Delay Notice No " and will be numbered sequentially." It is unnecessary to set out verbatim the provisions of the other extension of time clauses, namely Clauses 2.2, 2.3, 2.4 and 2.5. They make provision for the Contractor to give particulars, if practicable, of the expected effects and extent of delay and for the Construction Manager upon receipt of any notice particulars and estimate of the expected delay to grant extension of time and revise the Completion Period in a fair and reasonable manner. In any event the Construction Manager is required after the expiration of the Completion Period and in any event not later than the expiry of 12 weeks after practical completion to grant fair and reasonable extensions having regard to any of the Relevant Events, irrespective of any notification. Clause 4.21 If the Trade Contractor makes written application to the Construction Manager stating that he has incurred or is likely to incur direct loss and/or expense (of which the Trade Contractor may give his quantification) in the execution of this Trade Contract because the regular

progress of the Works or any part thereof has been or is likely to be materially affected by any one or more of the matters referred to in clause 4.22; and if as soon as the Construction Manager is of the opinion that the regular progress of the Works or of any part thereof has been or is likely to be so materially affected as set out in the application of the Trade Contractor then the Construction Manager from time to time thereafter shall ascertain the amount of such loss and/or expense which has been or is being incurred by the Trade Contractor; provided always that:.1 the Trade Contractor's application shall be made as soon as and in any event not later than two months after it has become, or should reasonably have become, apparent to him that the regular progress of the Works or any part thereof has been or was likely to be affected as aforesaid, and such application shall be formally made in writing and fully documented and costed in detail, and it shall be a condition precedent to the Trade Contractor's entitlement under this clause 4.21.1 or clause 4.25 that the Trade Contractor has complied fully with all the requirements of this clauses [sic] including, for the accordance [sic] of doubt, the said time period of two months..2 the Trade Contractor shall in support of his application submit to the Construction Manager upon request such information as should reasonably enable the Construction Manager to form an opinion as aforesaid;.3 the Trade Contractor shall submit to the Construction Manager upon request such details of such loss and/or expense as are reasonably necessary for such ascertainment..4 The Trade Contractor shall not be entitled to direct loss and/or expense to the extent that the loss or expense or other matters have been caused or contributed to by their Trade Contractor's negligence or the default." Clause 4.22 listed the matters which could give rise to a loss and expense claim under Clause 4.21; these included the late release of information, failure to give in due time ingress to or egress from the site, Variation instructions and "any impediment, prevention or default, whether by act or omission, by the Client or any person for whom the Client is responsible". Clause 4.25 Save as otherwise provide [sic] in this Clause 4 the provisions of clauses 4.21 and 4.23 are without prejudice to any other remedies or rights of the Trade Contractor under this Trade Contract.

The Parties Submissions The Employer sought a final determination from the court as to the true meaning and effect of clause 4.21. The Employer took issue with the Adjudicator s decision that the condition precedent was devoid of meaning, and argued that clause 4.21 required the Contractor to make a timely and detailed application for loss and expense as a condition precedent to entitlement to such a claim. The Contractor argued that conditions precedents were to be construed strictly and that the words in clause 4.21 should not be construed as barring the Contractor from a legitimate claim for loss and expense if its application were not made within the stipulated two month period. Much of the remaining argument, between the parties, centred on whether the words Trade Contractor s entitlement under this clause 4.21.1 were meaningless because there was no entitlement under that sub-sub-clause. The Relevant Principles The court noted the following principles as set out in Chartbrook v Persimmon Homes 6 : a contract should be interpreted by reference to what a reasonable person having all the relevant background knowledge would have understood the words to mean; the court did not readily accept that contractual parties have made a mistake in their written contracts; if something had gone wrong with the language, the court would not attribute to the parties an intention which a reasonable person would not have understood the words to mean; a strong case was needed to persuade a court that something had gone wrong with the language. Once it was clear that something had gone wrong with the language, the court would seek as a matter of construction and interpretation to determine what the parties really meant. In so doing, the court would have regard to the background and context of the contract to see what was intended from the wording of the contract. If it was not possible to determine what was mutually intended from the wording, the background and the context then the court might have to conclude that the parties had produced a meaningless term or contract. 6 Chartbrook Ltd -v- Persimmon Homes Ltd and Another ChD [2007] EWHC 409

There was no direct authority on this particular JCT form of contract, but the form of wording was similar and comparable to that used in the earlier editions of the JCT contracts. The court noted the dictum in Merton v Stanley Hugh Leach 7 where clause 24 (1) of the 1963 edition of the JCT contract (the pre-curser to clause 4.21) was held to be an if" clause. By this the judge meant that the provisions of the clause only operated if the contractor invoked them first by making a written application. If the application was made, the architect then had to form an opinion whether loss and/or expense was suffered, if the written application was made within a reasonable time. The Court s Analysis and Decision Applying those principles, the court analysed clause 4.21 to show that it was an if clause similar to that referred by in the Merton case. As a result the court held that: the requirement to make a timely application in writing was a precondition to the recovery of loss and/or expense under clause 4.21; the Contractor had no entitlement to recover such loss and/or expense unless and until it had made such an application because it was the application which activated the assessment process; the parties had agreed through the stipulation in clause 4.21.1, as amended, that the application must be made in a timely manner and in any event no more than two months after it has become or should reasonably have become apparent that the regular progress of the works had been or was likely to be affected; the proper construction of clause 4.21 was that it was a condition precedent to the Contractor's entitlement to recover loss and/or expense. In scrutinising clause 4.21, the court separated the essential elements of the clause as follows: (a) If the Trade Contractor makes written application to the Construction Manager stating that he has incurred or is likely to incur direct loss and/or expense The operation of clause 4.21 was brought about by the Contractor s written application. There was nothing in clause 4.21 which suggested that the Construction Manager or the Employer had any obligation to ascertain loss and expense if there was no application. (b) because the regular progress of the Works has been or is likely to be materially affected 7 London Borough of Merton v Stanley Hugh Leach (1985) 32 BLR 51

This made it clear that the application should state in effect that the regular progress was or was likely to be affected by the various matters listed as entitling additional loss and expense. (c) provided always that Use of this wording was often the most obvious indication that the parties intended there to be a condition precedent which was followed by a qualification and explanation of what was required to enable the preceding entitlement to materialise. (d).1 the Trade Contractor's application shall be made as soon as and in any event not later than two months after it has become, or should reasonably have become, apparent to him that the regular progress of the Works has been or was likely to be affected There was nothing particularly onerous on the Contractor to make its application within either the general or specific timetables. The application had to be made within the long stop period of two months after it had become or should reasonably have become apparent that the regular progress of the works was or was likely to be affected. (e) and it shall be a condition precedent to the Trade Contractor's entitlement under this clause 4.21.1 that the Trade Contractor has complied fully with all the requirements of this clauses [sic] 4.21.1 including, for the accordance [sic] of doubt, the said time period of two months The erroneous references to clause 4.21.1 in this part of the sub-clause suggested a lack of attention in the drafting because there was no specific entitlement under clause 4.21.1. Essentially, the words in this sub-clause were superfluous because the drafting of the earlier parts of clause 4.21 and 4.21.1 was sufficient to establish that the submission of a timely application was a condition precedent to entitlement. Following the dictum in the Chartbrook case, what the parties clearly intended was to refer to that part of the overall clause which actually gave rise to an entitlement which was clause 4.21. The whole context of clause 4.21.1 itself is clause 4.21 and it was obvious that the parties were intending to refer to clause 4.21. The court was clear in this case how the relevant clauses were intended to operate and was prepared to correct the mistake made in the cross-referencing of clause 4.21 and 4.21.1.

The judge decided that it was the Contractor s application which triggered the ascertainment process and the fact that there was an obvious mistake in the drafting of one of the subclauses to clause 4.21 did not undermine the clear intent of the clause. It followed that upon a proper construction of clause 4.21, and its sub-clauses, there is a condition precedent to the Contractor s entitlement to recover loss and/or expense. The court did not consider that the requirement for the Contractor to submit a timely application in this regard, no more than two months after either it became or should reasonably have become apparent to him, was unduly onerous in any event. Implications It is even clearer from the Gear case that when contractors are faced with properly drafted clauses of this type, they must be prudent and put in place sufficient commercial and contract management resources to ensure they do not fall foul of these provisions, irrespective of the merits of their case, for want of following the procedure. It is also worthy of note that the parties in this case had through amended clause 4.25 preserved the contractor s right to claim at common law for breach of contract, notwithstanding the validity of the condition precedent provision. The drafters of contracts shall therefore be aware that the right to recover at common law may still be available in the absence of any clear words to the contrary. As a concluding point, it is also worth noting that a failure to follow a condition precedent clause in a contract is not always fatal to the claim. There may be an equitable remedy in estoppel, waiver or variation.