ENTRY ORDER 2007 VT 5 SUPREME COURT DOCKET NO SEPTEMBER TERM, 2006

Similar documents
ENTRY ORDER 2007 VT 118 SUPREME COURT DOCKET NO SEPTEMBER TERM, 2007

STATE OF VERMONT DECISION ON MOTION. Couture Subdivision Permit

ENTRY ORDER SUPREME COURT DOCKET NO JANUARY TERM, 2007

SUPREME COURT DOCKET NO v. } Franklin Superior Court

Nordlund v. Van Nostrand, Van Nostrand 2007 Trust et al. ( ) 2011 VT 79. [Filed 15-Jul-2011]

Ketchum, Saddlebrook Farm Trust and North Farm Trust v. Town of Dorset ( ) ENTRY ORDER 2011 VT 49 SUPREME COURT DOCKET NO.

2011 VT 61. No In re Estate of Phillip Lovell

Decisions on Cross-Motions for Summary Judgment

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Environmental Division Unit Docket No Vtec

2014 VT 54. No

STATE OF VERMONT. Decision on Motion to Reconsider Denial of Motion for Entry of Judgment Because Necessary Co-Applicant is Lacking

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION. { In re Susan Lee Living Trust Corrective Permit { Docket No.

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION

2018 VT 20. No In re Mahar Conditional Use Permit (Mary Lahiff, Carolyn Hallock, Susan Harritt and

STATE OF VERMONT. Docket No Vtec DECISION ON MOTION. Leverenz Act 250 Jurisdictional Opinion (#6-010)

ENTRY ORDER 2007 VT 131 SUPREME COURT DOCKET NO SEPTEMBER TERM, 2007

2009 VT 16. No (Robert and Lourdes Eustance, Appellants) On Appeal from Environmental Court

ENTRY ORDER 2007 VT 43 SUPREME COURT DOCKET NO MARCH TERM, 2007

STATE OF VERMONT DECISION ON MOTION. Brisson Gravel Extraction Application

STATE OF VERMONT. Decision on Motion to Reconsider

Decision on Motion for Summary Judgment

ENTRY ORDER 2008 VT 57 SUPREME COURT DOCKET NO MARCH TERM, 2008 } } v. } Washington Superior Court

STATE OF VERMONT DECISION ON MOTION. LeGrand & Scata Variance Application

2017 VT 101. No Supreme Court Green Crow Corporation, Inc. On Appeal from v. Superior Court, Addison Unit, Civil Division

2008 VT 88. No (J.P. Carrara and Sons, Inc.) On Appeal from Environmental Court

ENTRY ORDER 2009 VT 104 SUPREME COURT DOCKET NOS & SEPTEMBER TERM, 2009

[r]econstruction of existing seasonal dwelling at 24 Sunset Harbor Road. (Mot. for Summ. J., Ex. A 3, filed Nov. 8, 2011).

2014 VT 3. No On Appeal from v. Superior Court, Orleans Unit, Civil Division. Town of Lowell January Term, 2014

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION

ENTRY ORDER 2010 VT 99 SUPREME COURT DOCKET NO AUGUST TERM, 2010

STATE OF VERMONT. Docket No Vtec. Four Hills Farm Partnership Amendment

STATE OF VERMONT ENVIRONMENTAL COURT

On August 5, 1997, the District Coordinator issued Jurisdictional Opinion #4-127 ("JO").

2010 VT 6. No On Appeal from v. Addison Superior Court. Robert A. Schumacher and Bonnie L. Schumacher September Term, 2009

IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

Decision on Farmer Mold & Machine Works, Inc. s Motion for Summary Judgment

STATE OF VERMONT DECISION ON THE MERITS. Agency of Natural Resources, Petitioner. Hugh McGee, Eileen McGee, Respondents

2016 VT 62. No On Appeal from v. Superior Court, Windham Unit, Civil Division. State of Vermont March Term, 2016

ARTICLE 14 AMENDMENTS

STATE OF VERMONT DECISION ON MOTION. Vt. Turquoise Hospitality, LLC Discharge Permit Application (Permit # ID )

STATE OF VERMONT STIPULATED DECISION ON THE MERITS. This appeal has been the subject of numerous efforts by the parties to negotiate a

2015 VT 40. No On Appeal from v. Superior Court, Chittenden Unit, Civil Division. Deborah Safford March Term, 2014

ENVIRONMENTAL COVENANT

ENTRY ORDER 2010 VT 18 SUPREME COURT DOCKET NO DECEMBER TERM, 2009

ENTRY ORDER 2011 VT 70 SUPREME COURT DOCKET NO JANUARY TERM, 2011

STATE OF VERMONT ENVIRONMENTAL DIVISION Docket No Vtec SUPERIOR COURT. Mahar Conditional Use Appeal DECISION ON MOTION

ENTRY ORDER SUPREME COURT DOCKET NO JANUARY TERM, 2018 } APPEALED FROM: In the above-entitled cause, the Clerk will enter:

PRE-ANNEXATION DEVELOPMENT AGREEMENT

DECISION Defendants Motion for Summary Judgment, and Defendants Motion to Strike

THE SUPREME COURT OF NEW HAMPSHIRE MERRIAM FARM, INC. TOWN OF SURRY. Argued: June 14, 2012 Opinion Issued: July 18, 2012

Present: Hassell, C.J., Keenan, Koontz, Kinser, Lemons, and Agee, JJ., and Russell, S.J.

STATE OF VERMONT. Docket No Vtec DECISION ON MOTIONS. R.L. Vallee, Inc et al TS4

ENTRY ORDER SUPREME COURT DOCKET NO OCTOBER TERM, v. } Windham Superior Court

2017 VT 84. No Timothy B. Tomasi, J. (summary judgment); Howard E. Van Benthuysen, J. (final judgment)

Development Review Templates for Savings Clause Compliance 24 V.S.A Chapter , 4462 and 4464 May, 2005

WAIVER OF PROTEST AGREEMENT

Melanie L. Fein, Trustee,

DECISION AND ORDER. Ford Motor Credit Company ( Ford ) has filed a Complaint for Foreclosure

ENTRY ORDER 2011 VT 115 SUPREME COURT DOCKET NO FEBRUARY TERM, 2011

STATE OF VERMONT. Docket No Vtec SECRETARY, VERMONT AGENCY OF NATURAL RESOURCES, Petitioner, DECISION ON MOTIONS

ENTRY ORDER SUPREME COURT DOCKET NO DECEMBER TERM, 2012

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 6, 2009 Session

Third District Court of Appeal State of Florida

STATE OF VERMONT. Docket No Vtec DECISION ON MOTION. ANR v. Donald Shattuck

STATE OF VERMONT DECISION ON THE MERITS

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION. { Southern Vermont Beagle Club { Docket No Vtec { Decision on the Merits

2010 VT 84. No Harry Clayton and Lucille Clayton. On Appeal from v. Chittenden Superior Court

ENTRY ORDER SUPREME COURT DOCKET NO JULY TERM, 2014

State of Vermont NATURAL RESOURCES BOARD DISTRICT 4 ENVIRONMENTAL COMMISSION 111 West Street Essex Junction Vermont 05452

VERMONT SUPERIOR COURT

NO. COA NORTH CAROLINA COURT OF APPEALS. Filed: 2 April 2013

COVENANT FOR CROSS-USE AGREEMENT FOR SHARED PARKING AND ACCESS

ENTRY ORDER SUPREME COURT DOCKET NO DECEMBER TERM, 2016

VERMONT SUPERIOR COURT

COUNTY VOLUNTARY AGRICULTURAL DISTRICT & ENHANCED VOLUNTARY AGRICULTURAL DISTRICT ORDINANCE ( Draft) ARTICLE I TITLE

Case 4:92-cv SOH Document 72 Filed 01/17/19 Page 1 of 19 PageID #: 730

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION II

ENTRY ORDER 2017 VT 110 SUPREME COURT DOCKET NO NOVEMBER TERM, 2017

VERMONT SUPREME COURT Advisory Committee on Rules of Civil Procedure 2009 Annual Report November 25, 2009

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P : : : : : : : : :

STATE OF MICHIGAN COURT OF APPEALS

CITY OF WARRENVILLE DU PAGE COUNTY, ILLINOIS ORDINANCE NO ORDINANCE APPROVING PRE-ANNEXATION AGREEMENT (JUSTIN MASON 29W602 BUTTERFIELD ROAD)

ENTRY ORDER SUPREME COURT DOCKET NOS & JUNE TERM, 2015

v. NO. 29,253 and 29,288 Consolidated K.L.A.S. ACT, INC., APPEAL FROM THE DISTRICT COURT OF VALENCIA COUNTY Edmund H. Kase, District Judge

DUMMERSTON DEVELOPMENT REVIEW BOARD. Rules of Procedure and Conflict of Interest Policy Adopted April 10, 2006 and amended April 29, 2008

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE OCTOBER 12, 2000 Session

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

ANNOTATED VERSON. STATE OF VERMONT NATURAL RESOURCES BOARD District Environmental Commissions ACT 250 RULES

DECISION ON MOTIONS FOR SUMMARY JUDGMENT

STATE OF VERMONT PUBLIC SERVICE BOARD CONSERVATION LAW FOUNDATION S BRIEF

State of New York Supreme Court, Appellate Division Third Judicial Department

2017 VT 120. No Provident Funding Associates, L.P. On Appeal from v. Superior Court, Rutland Unit, Civil Division

Enforceability of Subdivision Restrictions Against Subsequent Purchasers: New York Courts Issue Key Rulings

GRANVILLE FARMS, INC., Plaintiff, v. COUNTY OF GRANVILLE, Defendant NO. COA Filed: 03 May 2005

ENTRY ORDER 2008 VT 81 SUPREME COURT DOCKET NO JUNE TERM, 2007

ENTRY ORDER 2011 VT 93 SUPREME COURT DOCKET NO AUGUST TERM, 2010

Draft Model County Voluntary Agricultural District Ordinance. COUNTY VOLUNTARY AGRICULTURAL DISTRICT ORDINANCE ( Draft Only) ARTICLE I TITLE

ARTICLE 4. LEGISLATIVE/QUASI-JUDICIAL PROCEDURES

1. Developer is a(n) individual partnership corporation, doing business in Tarrant County, Texas, whose address is

2018 VT 109. No In re Petition of LK Holdings, LLC

Transcription:

In re Appeal of Hildebrand (2005-537) 2007 VT 5 [Filed 16-Jan-2007] ENTRY ORDER 2007 VT 5 SUPREME COURT DOCKET NO. 2005-537 SEPTEMBER TERM, 2006 In re Appeal of Hildebrand APPEALED FROM: Environmental Court DOCKET NO. 228-12-04 Vtec Durkin Trial Judge: Thomas S. In the above-entitled cause, the Clerk will enter: 1. Joan Hildebrand, and her son James, appeal the Environmental Court's denial of their motion for summary judgment. The court ruled that the Waitsfield Planning Commission had appropriately denied the Hildebrands' application to amend the subdivision permit because they had not demonstrated a change in circumstances. We affirm. 2. A review of the history of the parcel under consideration is necessary to understand the case. In 1992, the Neill family sought approval from the Waitsfield Town Planning Commission to subdivide their 183.5 acre farm, located on both sides of East Warren Road, into four lots. Lots 1, 2, and 4 totaled approximately thirty acres, which the Neills intended to sell. The plan left the Neills with approximately 150 acres, known as lot 3. The Waitsfield Town Plan designates the segment of East Warren Road that runs through the Neill farm as a "scenic corridor... characterized by panoramic views across open fields on both sides of the road." Because of the town plan, the Waitsfield Planning Commission originally raised concerns that the proposed development had the potential to disrupt an important viewshed. Concerns were also raised by an adjacent landowner whose land had conservation restrictions placed on it. In response to these concerns, the Neills proposed limiting the southern two-thirds of lot 4 to agricultural use only, prohibiting further development on this acreage. Lot 4 is approximately sixteen acres. The planning commission adopted the covenants drafted by the Neills, and by a written decision dated March 4, 1992, the planning commission approved the subdivision subject to seven specific conditions. Importantly, the written decision prohibited further subdivision of lots 1, 2, and 4, and required that the agricultural fields in lot 4 be maintained as open fields through grazing, cultivation or mowing on a yearly basis. The decision was not appealed. The Neills sold lot 4 to the Verguras in 1992 with a covenant in the deed intended to preserve the meadowland. Joan Hildebrand and her

husband bought lot 4 in 1995. Their deed also contained a covenant preserving the meadowland. 3. On April 30, 2004, Joan Hildebrand, through her son, submitted a subdivision application to the planning commission to further divide lot 4 into two parcels of approximately ten and approximately six acres. James Hildebrand wishes to construct a single family home and install a driveway on the six acre parcel, which is currently undeveloped meadowland. The Waitsfield Subdivision Regulations allow for amendment of previously issued subdivision permits, but they do not set out standards an applicant must meet to gain approval for an amendment. 4. The planning commission expressed its opposition to modifying or eliminating the existing permit conditions absent a showing of significant changed or mitigating circumstances. In response, the Hildebrands submitted letters from members of the Neill family, original grantors and now neighboring property owners of the Hildebrands' parcel. The letters indicate that the Neills do not oppose subdivision of lot 4 to allow another single family home. The Hildebrands presented no other evidence of changed circumstances beyond the assertion that "times have changed." The Commission denied the application for subdivision approval, and the Hildbrands appealed to the Environmental Court. The Town of Waitsfield entered an appearance in the appeal. 5. The Hildebrands moved for summary judgment and submitted affidavits from the Neill family members stating, again, that they had no objection to amending the permit. Both the Hildebrands and the Town agreed that there is no clear rule regarding the standard applicable to requests to amend previously granted municipal land use permits. Both parties urged the Environmental Court to use Act 250 as a guide and to apply the standards articulated by the Environmental Board and upheld by this Court in In re Stowe Club Highlands, 166 Vt. 33, 687 A.2d 102 (1996), and In re Nehemiah Assocs., 166 Vt. 593, 689 A.2d 424 (1996) (mem.), reconsidered after remand, 168 Vt. 288, 719 A.2d 34 (1998) (hereinafter Nehemiah II). 6. In Stowe Club Highlands, the original developer, Stowe Club Associates, sought and received an Act 250 permit to develop a 250 acre tract of land with a conference center, hotel, townhouses, and a 23-lot subdivision. 166 Vt. at 34, 687 A.2d at 103. As in this case, one condition in the permit required a meadow on the project tract to "be retained for agricultural uses." Id. In addition, the district commission had made findings, based on statements in the permit application, that the "Meadow Lot" would remain open and would be reserved for agriculture. Id. These findings were incorporated into the permit as a condition of approval. Id. The property was conveyed to a new owner, Stowe Club Highlands, and it sought to amend the original permit to allow the construction of a single-family home on the meadow lot. Id. Both the district commission and the Environmental Board concluded that the proposed development violated the original permit governing the project, and denied the permit modification. Id. 7. On appeal, this Court stated, "the central question... is not whether to give effect to the original permit conditions, but under what circumstances those permit conditions may be modified." Id. at 37, 687 A.2d at 105. We approved the board's decision to examine: "(a) changes in factual or regulatory circumstances beyond the control of a permittee; (b) changes in the construction or operation of the permittee's project,

not reasonably foreseeable at the time the permit was issued; or (c) changes in technology." Id. at 38, 687 A.2d at 105. Our decision in Nehemiah II refined the permit-amendment standards articulated in Stowe Club Highlands and Nehemiah I, noting that they are intended to "assist in assessing the competing policies of flexibility and finality in the permitting process." Nehemiah II, 168 Vt. at 294, 719 A.2d at 37. We further explained that "[e]ven where the Board finds such a change, there are certain situations where an amendment may not be justified, for instance where the change was reasonably foreseeable at the time of permit application. Otherwise, the initial permitting process would be merely a prologue to continued applications for permit amendments." Id. at 294, 719 A.2d at 38 (internal quotation marks omitted). 8. The Environmental Court applied these standards, denied the Hildebrands' motion for summary judgment and granted summary judgment in favor of the Town, thereby affirming the planning commission's denial of the subdivision amendment application. This appeal followed. 9. This Court reviews summary judgment rulings de novo, applying the same standard as the trial court. Washington v. Pierce, 2005 VT 125, 17, 179 Vt. 318, 895 A.2d 173. Summary judgment is appropriate when the "pleadings, [and] depositions,... together with the affidavits, if any,... show that there is no genuine issue as to any material fact and that any party is entitled to judgment as a matter of law." V.R.C.P. 56(c). "Summary judgment when appropriate may be rendered against the moving party." Id. 10. The Hildebrands raise four issues on appeal. First, they argue that the permit conditions may be challenged directly in a petition to amend them, despite the language of 24 V.S.A. 4472(d). Second, they suggest that if the original conditions cannot be attacked directly, they may still be amended. Third, they challenge the Environmental Court's use of Stowe Club Highlands as a means for evaluating permit amendments. Finally, they advocate more flexibility in the permit process when adjoining landowners do not object to the proposed amendments. 11. The Environmental Court began its analysis by noting the clear policy reasons favoring the finality of decisions of appropriate municipal panels and officers and acknowledging that this Court has discerned an unmistakable intent by the Legislature "to limit zoning disputes to a well-defined procedure and to provide finality at the end of the proceedings." In re Dep't of Bldgs. and General Servs., 2003 VT 92, 21, 176 Vt. 41, 838 A.2d 78 (quoting City of S. Burlington v. Dep't of Corr., 171 Vt. 587, 590, 762 A.2d 1229, 1231 (2000) (mem.) (citing 24 V.S.A. 4472)). Section 4472 requires interested persons to appeal a permit condition to the Environmental Court. Failure to do so binds successors in interest. The Environmental Court held that, while neither the bylaws, subdivision regulations, nor the Vermont Planning and Development Act expressly prohibit applications to amend final subdivision permits, the enacted, unappealed subdivision permit conditions that are the subject of a subsequent amendment application are considered final and cannot be collaterally challenged under the explicit and interpreted directive of 24 V.S.A. 4472. We agree. 12. As the Environmental Court discussed, this rule of finality is tempered by flexibility built into the system. Nehemiah II, 168 Vt. at 294, 719 A.2d at 37. The court held that, although the original conditions

may no longer be challenged, they may be amended in appropriate circumstances. Again, we agree. The Environmental Court applied the three part test set out in In re Stowe Club Highlands, and In re Nehemiah Associates, Inc., and it determined that the permit could not be amended. The Hildebrands focus their appeal on whether the Environmental Court erred in applying the standards developed under Act 250. We find that the court reasonably applied these standards, and we affirm. 13. Because the competing interests in this case are so similar to those in Stowe Club Highlands, the Environmental Court reasonably used the Act 250 standards in deciding this case. The court appropriately determined that there had been no change in critical regulatory and factual circumstances surrounding the parcel at issue and the 1992 subdivision permit. The Hildebrands do not dispute this finding. 14. With regard to the second criterion, whether any change has occurred in the construction or operation of the permittee's project that was not reasonably foreseeable at the time the permit was issued, the Hildebrands offer only the support of the neighboring landowners for the amendment. We agree with the Environmental Court that the surrounding landowners' lack of objection to the permit condition does not qualify as a change in circumstances. Further, the court noted that it was entirely foreseeable that a future landowner might attempt to further subdivide Lot 4, and that this perceived pressure to further subdivide valued open land was one initial reason for the condition limiting further subdivision of Lot 4. 15. The Hildebrands did not suggest that a change in technology had occurred that would justify amending the subdivision permit and the Environmental Court found none in the evidence presented. This finding, too, is unchallenged on appeal. 16. Finally, the Hildebrands argue that when the surrounding landowners do not object to a permit amendment, the planning commission should simply allow the amendment. We disagree. Subdivision permits and amendments are the Town's primary tool for effectuating the town plan. This is certainly not the first time that a town's long-term goals for preservation of common resources have hindered the short-term gain of a small group of neighbors, nor will it be the last. The Stowe Club Highlands test allows sufficient flexibility to relieve landowners from permit conditions that have become unworkable while preventing the permit amendment process from becoming a piecemeal referendum on the town plan. 17. For the foregoing reasons, we hold that the Environmental Court's application of the standards developed under Act 250 to this local subdivision permit was appropriate and its conclusion denying the permit amendment is sound. Affirmed. BY THE COURT: Paul L. Reiber, Chief Justice

Denise R. Johnson, Associate Justice Marilyn S. Skoglund, Associate Justice Brian L. Burgess, Associate Justice Geoffrey W. Crawford, Superior Judge, Specially Assigned