PERFORMANCE BOND: CONDITIONAL OR UNCONDITIONAL 'AZIZAN BIN SUPARDI UNIVERSITI TEKNOLOGI MALAYSIA

Similar documents
UNCONSCIONABLE CALL OF PERFORMANCE BOND WAN NOOR SOLEHHA BINTI WAN NIK FACULTY OF BUILT ENVIRONMENT UNIVERSITI TEKNOLOGI MALAYSIA

Fasda Heights Sdn Bhd - vs - Soon Ee Sing Construction Sdn Bhd

PROFILE OF CONSTRUCTION CONTRACTUAL CLAIMS NUR JAZLIANNA BINTI SAMSUDIN UNIVERSITI TEKNOLOGI MALAYSIA

Performance Bonds. To guarantee /secure the contractor s performance. Recourse to meet losses suffered as a result of the contractor s breach

EQUITABLE REMEDY: SPECIFIC PERFORMANCE THEN LEE LIAN UNIVERSITI TEKNOLOGI MALAYSIA

CONSTRUING CONTRACT CLAUSE: THE LITERAL RULE CHAI SIAW HIONG UNIVERSITI TEKNOLOGI MALAYSIA

SETTING ASIDE AN AWARD: ARBITRATOR S MISCONDUCT LEE SEE KIM MB UNIVERSITI TEKNOLOGI MALAYSIA

TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE

VALID AND INVALID VARIATION OMISSION OF WORKS MOTHILAL A/L MUNIANDY

Held: Per Abdul Hamid Mohamad JCA

IN THE SUPREME COURT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA

PERFORMANCE GUARANTEE OF CONSTRUCTION GUARANTOR. THE CREDIT VALLEY HOSPITAL, a non-share capital corporation incorporated under the laws of Ontario

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.: W-02(IM)(NCC) /2014 BETWEEN

Pilecon Engineering Bhd ABDUL KADIR SULAIMAN, JCA ARIFIN ZAKARIA, JCA NIK HASHIM NIK AB. RAHMAN, JCA 23 FEBRUARY 2007

TERMINATION OF CONTRACTOR DUE TO THE CORRUPTION, UNLAWFUL OR ILLEGAL ACTIVITIES HASNITA HANA BINTI HASSAN UNIVERSITI TEKNOLOGI MALAYSIA

What You Should Know About General Agreements of Indemnity and Why You Should Know It

The Construction Act of Ontario

Debtors 1 LAWS OF MALAYSIA REPRINT. Act 256 DEBTORS ACT Incorporating all amendments up to 1 January 2006

For personal use only

SPECIAL CONDITIONS OF CONTRACT (FOR USE WITH THE ACQS HKIA/HKIS STANDARD FORM OF BUILDING CONTRACT WITH QUANTITIES 2005 EDITION)

CHAPTER 1 INTRODUCTION

DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANG KUASA RAYUAN) [RAYUAN SIVIL NO: W-02(NCVC)(W) /2013] ANTARA DAN

IN THE SUPREME COURT OF BELIZE A.D (CIVIL) CLAIM NO. 36 of 2015 BETWEEN. A&N CONSTURCTION (A firm) AND HERITAGE BANK LIMITED DECISION

Possible Legal Issues of Unilaterally Contract Termination for Convenience

EXTENSION OF TIME IN COMMENCEMENT OF ARBITRATION PROCEEDINGS NOOR HALWANI BT MOKHTAR UNIVERSITI TEKNOLOGI MALAYSIA

HBT 103 BAHASA, UNDANG-UNDANG DAN PENTERJEMAHAN I

Joint Venture (JV) Agreement

1.1 Definitions. In these Conditions, the following definitions apply:

HOPE CONSTRUCTION MATERIALS. General Conditions. of Contract for. the purchase and. supply of. goods, plant, and materials with services (UK only)

Held: Per Abdul Hamid Mohamad JCA

the court has jurisdiction to grant a mandatory injunction on an ex parte application in urgent and exceptional cases;

P Mukundan A/L P K Kunchu Kurup and 2 Others v Daniel A/L Anthony and Another Appeal

DALAM MAHKAMAH TINGGI MALAYA DI KUALA LUMPUR DALAM WILAYAH PERSEKUTUAN, MALAYSIA [GUAMAN SIVIL NO: S ] (NO 2) ANTARA

SOURCE ONE SURETY, LLC.

LAWS OF MALAYSIA HIRE PURCHASE ACT 1967 AND REGULATIONS All amendments up to November, 2003 ACT 212

AGREEMENT FOR THE SUPPLY, DELIVERY, INSTALLATION AND COMMISSIONING OF PASTA COOKER (STEAM OPERATED) AT SATS INFLIGHT CATERING CENTRE 1.

PROSECUTION AND PROGRESS

Wong Kian Wah v Ng Kien Boon

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

MEMORANDUM OF DEPOSIT

INDIAN MARITIME UNIVERSITY (A Central University) Ministry of Shipping, Govt. Of India EAST COAST ROAD, UTHANDI CHENNAI TENDER FOR

DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANGKUSASA RAYUAN) RAYUAN SIVIL NO: W

SCHEDULE 21 PARENT COMPANY GUARANTEE

JUDGMENT. Low Hop Bing JCA:

(RD/T&C/SDB/ENG/JUN2016) Page 1 of 5

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ]

Batu Kemas Industri Sdn Bhd v Kerajaan Malaysia & Anor

Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.

CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE

DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANGKUASA RAYUAN) RAYUAN SIVIL NO: J /2012 ANTARA

ACCOUNT OPENING / CREDIT APPLICATION FORM

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES)

CTR Carbide Dies (Birmingham) Ltd & Rectory Tool Company Ltd

DIRECT LOSS AND EXPENSE RELATING TO REMOTENESS OF DAMAGES LEE XIA SHENG

SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY

KNOW YOUR BOND BEFORE YOU SIGN

Conditions of Contract for Purchase of Goods and Services

CONSULTANCY SERVICES FOR... CONTRACT NO. :... BETWEEN THE GOVERNMENT OF MALAYSIA AND (COMPANY NO. :...)

DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA KES KEBANKRAPAN NO: 29NCC /2015

Agreement to UOB Banker s Guarantee Terms and Conditions

PERINTAH UNIVERSITI DAN KOLEJ UNIVERSITI (PERLEMBAGAAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA) (PINDAAN) 2012

BRITISH COLUMBIA UTILITIES COMMISSION. Rules for Gas Marketers

COGNE UK LTD of Uniformity Steel Works, Don Road, Sheffield, S9 2UD General Conditions of Contract

APPLICATION OF ENGLISH LAW IN MALAYSIA 3.1Introduction The application of English Law in Malaysia is restricted under the Civil law Act 1956.

DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANGKUASA RAYUAN) RAYUAN SIVIL NO. W ANTARA DAN

Attestation of Registrable Instruments (Mining) LAWS OF MALAYSIA REPRINT. Act 387 ATTESTATION OF REGISTRABLE INSTRUMENTS (MINING) ACT 1960

FIRST INDEMNITY OF AMERICA INSURANCE COMPANY INDEMNITY AGREEMENT

First Supplemental Trust Deed

D.R. 48/96 RANG UNDANG-UNDANG. Suatu Akta untuk meminda Kanun Prosedur Jenayah.

CONSULTANCY SERVICES AGREEMENT

THE COMPANIES NAMED IN THIS GUARANTEE

2196 Hire Purchase 1971, No. 147

To all CIMB Bank Gold Investment Account via CIMB Clicks (hereinafter referred to as "GIA via CIMB Clicks") customers,

BASF Tanzania Limited Standard Terms and Conditions of Sale

SKRINE BREACH OF CONTRACT: TERMINATION AND OTHER OPTIONS. 10 December LEE SHIH ADVOCATES & SOLICITORS

Schedule A Page 1 of 6

Under the terms of sale the following meaning shall apply:- You means the person seeking to purchase the goods from us

DETERMINATION OF CONTRACT BY EMPLOYER IN CONSTRUCTION INDUSTRY TAY LEE YONG

John Fish Agencies (PTY) LTD STANDARD TRADING CONDITIONS

Reebok (M) Sdn Bhd v CIMB Bank Berhad

THE LAW RELATING TO GUARANTEES

SECURITY SHARING AGREEMENT. THIS SECURITY SHARING AGREEMENT (this Agreement) is made as of June 25, 2014.

SKRINE ADVOCATES & SOLICITORS. IS CONSTRUCTION INDUSTRY AND PAYMENT ADJUDICATION ACT 2012 RETROSPECTIVE OR PROSPECTIVE? Shannon Rajan Partner SKRINE

The Officious Bystander Test Revisited; Special Reference to Implied Terms in PAM and PWD 203A Standard Form Contracts

COMPANY LAW CIVIL PROCEDURE Held: [1] [2]

IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO: K-01(NCVC)(W)-10-01/2014 BETWEEN

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

ENGINEERS AND ENGINEERING CONTRACTS Liabilities and Powers

COMPOUNDED INTEREST IN FATAL ACCIDENT AND PERSONAL INJURY CLAIMS IN MALAYSIA: THE DEPARTURE FROM THE TRADITIONAL APPROACH

Projects Disputes in Australia: Recent Cases

Suppliers Conditions of Sale, Usage and Warranties. Being the Supplier s Terms and Conditions of Supply

PETROLEUM JOINT VENTURE ASSOCIATION UNIT AGREEMENT [NAME OF UNIT]

MAHKAMAH TINGGI MALAYA DI SHAH ALAM DALAM NEGERI SELANGOR DARUL EHSAN GUAMAN SIVIL NO: 22C-20-09/2014 ANTARA PERBADANAN KEMAJUAN NEGERI SELANGOR DAN

AVK UK LIMITED CONDITIONS OF SALE OF GOODS FROM WEBSITE

DALAM MAHKAMAH RAYUAN MALAYSIA DI PUTRAJAYA (BIDANGKUASA RAYUAN) RAYUAN SIVIL NO: W-02(IM)(NCC) ANTARA

To: CIMB Bank Berhad. ... Branch. CIMB BANK e-gold INVESTMENT ACCOUNT AGREEMENT. This Agreement is effective beginning 1 June 2018.

LAW OF RESTITUTION IN MALAYSIAN CONSTRUCTION CONTRACT WONG FOO YEU UNIVERSITI TEKNOLOGI MALAYSIA

One of the common problems

Business Name: Trading Address: Post Code: Nature of Business: How long established: Company Reg. No: Credit limit requested:

AGREEMENT FOR KIB KENANGA AGENCY NETWORK SERVICE

Transcription:

PERFORMANCE BOND: CONDITIONAL OR UNCONDITIONAL 'AZIZAN BIN SUPARDI UNIVERSITI TEKNOLOGI MALAYSIA

PERFORMANCE BOND: CONDITIONAL OR UNCONDITIONAL 'AZIZAN BIN SUPARDI A master s project report submitted in fulfillment of the requirements for the award of the degree of Master in Science of Construction Contract Management. Faculty of Built Environment Universiti Teknologi Malaysia October 2007

To my family for their love and support iii

ACKNOWLEDGEMENTS With high gratitude to Allah S.W.T. who gave me the ideas and physical strength in preparing this master project. This project would not have been completed without the support and encouragement from the various people involved. Because of that, I wish to express my deepest gratitude to these people who provided valuable cooperation in my carrying out of this final project. First of all, I would give my acknowledgement to my supervisor En Jamaluddin Yaakob for his guidance, support and giving the ideas in preparing of this master project. My appreciation also goes to all the lecturers for the course of Master of Science in Construction Contract Management, for their patient and kind advice during the process of completing the master project. I am also thankful to my parents, Hj Supardi Surtiman and Hjh Zamnah Abdul Hamid, my beloved wife, Noor Baini Abdullah, my three sons, Muhammad Haziq, Muhammad Hakim and Muhammad Hafiy, and a daughter, Nur Batrisyia for their great consideration and encouragement while preparing this master project. Lastly, I would like to thank my classmates for giving me the needed morale support and supplying me with the information on how to write a master project. Thank you to all the parties involved who have provided me with great cooperation that I really need in completing the master project. iv

ABSTRACT In construction contracts, a 'performance bond' is a bond taken out by the contractor, usually with a bank or insurance company (in return for payment of a premium), for the benefit of and at the request of the employer, in a stipulated maximum sum of liability and enforceable by the employer in the event of the contractor's default, repudiation or insolvency, as stated by Nigel M Robinson et. al. in his book, Construction Law in Singapore and Malaysia. He further added that there are two types of performance bonds: Conditional bond or default bond, whereby the surety accepts 'joint and several' responsibility for the performance of the contractor's obligations under the contract; and Unconditional bond or on-demand bond, which is a covenant by the surety (usually a bank) to indemnify the employer following contractor's default, subject to stated terms and up to a sum commonly 5% of the main contract sum. However, in Malaysia, for the past 20 years and since the famous case of Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 3 MLJ 449 to the recent Suharta Development Sdn Bhd v United Overseas Bank (M) Bhd & Anor [2005] 2 MLJ 762, the question of whether the performance bond in a construction contract is a conditional or an unconditional guarantees is still one of the issues relating to performance bond that has been discussed. Thus, in order to determine the types of performance bond applicable in a contract, a thorough understanding of the content of the bond is required. Therefore, the objective of this research is to determine the phrase(s) in the Performance Bond in a construction contract that determine whether the performance bond is a conditional or unconditional on demand guarantee. In order to achieve this objective, the research was conducted by analyzing relevant court cases. From the findings, it can be concluded that unless an undisputed meaning of the words in the performance bond to make the performance bond to be purely conditional or unconditional 'on-demand' bond, most court interpreted performance bond to be an on-demand performance bond which is only conditional upon the beneficiary asserting the basis of the claim upon the issuer of the bond contending that there has been breach of contract. v

ABSTRAK Di dalam kontrak pembinaan, sesuatu 'bon perlaksanaan' adalah satu bond yang diambil oleh kontraktor, selalunya dengan satu bank atau syarikat insuran (sebagai balasan kepada bayaran premium), untuk faedah dan atas permintaan majikan, mengikut jumlah liability maksimum yang dinyatakan dan dikuatkuasakan oleh majikan di dalam kejadian di mana kemungkiran, keengganan atau kebankrapan kontraktor, seperti dinyatakan oleh Nigel M Robinson et. al. di dalam bukunya, Construction Law in Singapore and Malaysia. Dia menambah bahawa terdapat dua jenis bon perlaksanaan: Conditional bond atau default bond, di mana penjamin menerima tanggungjawab 'bersama dan beberapa' untuk perlaksanaan obligasi kontraktor di bawah kontrak; dan Unconditional bond atau on-demand bond, iaitu permuafakatan oleh penjamin (selalunya bank) untuk menggantirugi majikan atas kemungkiran kontraktor, tertakluk kepada syarat-syarat dan kepada jumlah harga biasanya 5% daripada harga kontrak utama. Akan tetapi, di Malaysia, selama 20 tahun sejak kes Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 3 MLJ 449 kepada Suharta Development Sdn Bhd v United Overseas Bank (M) Bhd & Anor [2005] 2 MLJ 762, persoalan samada bon perlaksanaan di dalam kontrak pembinaan adalah jaminan bersyarat atau tidak, masih salah satu masalah yang diperbincangkan. Oleh itu, untuk menentukan jenis bon perlaksanaan yang digunakan di dalam kontrak, pengetahuan mendalam kandungan bon tersebut adalah diperlukan. Oleh sebab itu, objektif kajian ini adalah untuk menentukan frasa atau frasa-frasa dalam bon perlaksanaan di dalam kontrak pembinaan yang menentukan samada bon perlaksanaan tersebut adalah jaminan bersyarat atau tidak. Untuk mencapai objektif ini, kajian dijalankan dengan menganalisa kes-kes mahkamah yang relevan. Dari keputusannya, kesimpulan boleh dibuat bahawa kecuali makna perkataan-perkataan bon perlaksanaan adalah bersyarat tulen atau tidak bersyarat tulen, kebanyakan mahkamah mentafsir bon perlaksanaan adalah bon perlaksanaan tidak bersyarat di mana syaratnya hanyalah pada waris menuntut hak dengan mengemukakan tuntutan terhadap bon beralasan bahawa terdapat pelanggaran kontrak. vi

TABLE OF CONTENTS PAGE TITLE DECLARATION DEDICATION ACKNOWLEDGEMENT ABSTRACT ABSTRAK TABLE OF CONTENTS LIST OF CASES LIST OF ABBREVIATIONS LIST OF FIGURES / TABLES i ii iii iv v vi vii ix xi xii CHAPTER 1 INTRODUCTION 1.1 Background of Topic 1 1.2 Problem Statement 4 1.3 Objective of Topic 7 1.4 Previous Research 7 1.5 Scope of Topic 8 1.6 Significant of Topic 9 1.7 Methodology and Research Process 9 1.8 The organizational of research proposal 12 vii

PAGE CHAPTER 2 PERFORMANCE BOND 2.1 Introduction 14 2.2 Definition 18 2.3 Nature of Performance Bond 19 2.4 Purpose of Performance Bond 20 2.5 Performance Bond in Construction Contract 21 2.6 Types of Performance Bond 24 2.7 Construction of Performance Bond 26 2.8 Summary 28 CHAPTER 3 COMPARATIVE ANALYSIS: CONDITIONAL VERSUS UNCONDITIONAL PERFORMANCE BOND 3.1 Introduction 31 3.2 Law Cases held and cited to differentiate the Conditionality of the Performance Bond by its wordings 32 3.3 Comparative Analysis of the Law Cases 74 3.4 Summary 79 CHAPTER 4 CONCLUSION AND RECOMMENDATION 4.1 Introduction 82 4.2 Conclusion 84 4.3 Recommendation 89 REFERENCES 91 BIBLIOGRAPHY 93 viii

LIST OF CASES PAGE Australasian Conference Association Ltd v Mainline Constructions Pty Ltd (1978) 141 CLR 335......63 Bocotra Construction Pte Ltd v Attorney General (No 2) [1995] 2 SLR 733......49, 77 China Airlines Ltd v Maltran Air Corp Sdn Bhd [1996] 2 MLJ 517......... 4, 6, 24, 29, 33, 44, 46, 56, 85 Daewoo Engineering & Construction Co Ltd v The Titular Roman Catholic Archibishop of Kuala Lumpur [2004] 7 MLJ 136......33 Damatar Paints (P) Ltd v Indian Oil Corp AIR 1982 Delhi 57....42 Danaharta Managers Sdn Bhd v Huang Ee Hoe & Ors [2002] 2 MLJ 424....34 Easal (Commodities) Ltd v Oriental Credit Ltd [1985] 2 Lloyd's Rep 546....... 35, 36, 39, 45, 49, 50, 52, 54, 55, 58, 71, 72, 74, 77, 78, 79, 87 Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] QB 159......20, 28, 52, 59, 68, 70, 76, 80, 84, 88 Esso Petroleum Malaysia Inc. v. Kago Petroleum Sdn. Bhd. [1995] 1 MLJ 149...6, 26, 29, 32, 37, 46, 55, 58, 61, 70, 73, 74, 75, 78, 80, 81, 86, 87, 89, 90 Fasda Heights Sdn Bhd v Soon Ee Sing Construction Sdn Bhd & Anor [1994] 4 MLJ 199......47, 76, 80, 88 Government of Malaysia v South East Asia Insurance Bhd [2000] 3 MLJ 625......4, 35, 36 IE Contractors Ltd v Lloyd s Bank Plc and Rafidain Bank [1990] 2 Lloyd s Rep 496......26, 27, 29, 37, 50, 61, 62, 70, 71, 75, 80, 81, 86, 87, 89, 90 Jowitt v Callaghan (1938) 38 SR (NSW) 512....64 ix

Kirames Sdn Bhd v Federal Land Development Authority [1991] 2 MLJ 198........25, 64, 70 LEC Contractors (M) Sdn. Bhd. v Castle Inn Sdn Bhd [2000] 3 MLJ 339....... 5, 6, 32, 33, 41 Lotterworld Engineering & Construction Sdn Bhd v Castle Inn Sdn Bhd [1998] 7 MLJ 105........20, 28, 52, 85 Nik Sharifuddin Bin Nik Kadir v Mohaiyani Securities Sdn Bhd [1994] 3 MLJ 551....62 Patel Holdings Sdn Bhd v Estet Pekebun Kecil & Anors [1989] 1 MLJ 190...67 Pesticides India v State Chemicals & Pharmaeuticals Corp of India AIR 1982 Delhi 78....42 Ramal Properties Sdn Bhd v East West-Umi Insurance Sdn Bhd [1998] 5 MLJ 233......54, 78, 81, 88 RD Harbottle (Merchantile) Ltd v National Westminster Bank Ltd [1978] 1 QB 146....60 Re Conley [1938] 2 All ER 127....25 Sime Engineering Sdn Bhd & Anor v Public Bank Berhad [2004] 7 MLJ 475....34 Suharta Development Sdn Bhd v United Overseas Bank (M) Bhd [2005] 2 MLJ 762......5, 31, 32 Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 3 MLJ 449......4, 5, 6, 18, 24, 27, 30, 32, 33, 42, 46, 50, 55, 69, 73, 75, 78, 80, 84, 86, 87 x

LIST OF ABBREVIATIONS AC All ER AMR App Cas Build LR CLJ EWCA Civ HL Lloyd s Rep LR MLJ PC QB SCR SLR WLR Law Reports: Appeal Cases All England Law Reports All Malaysia Reports Appeal Cases Building Law Reports Current Law Journal (Malaysia) Court of Appeal, Civil Division (England & Wales) House of Lords Lloyd s List Reports Law Reports Malayan Law Journal Privy Council Queen Bench Session Cases Report Singapore Law Report Weekly Law Report xi

LIST OF FIGURES / TABLES PAGE Figure 1.1: Relationship of Parties to a Bond and the Underlying Contract.....2 Figure 1.2: Time line indicating the validity period of the performance bond..3 Figure 1.3: Flowchart of the research methodology...11 Figure 2.1: The risk spectrum: some principal sources of risk....15 Figure 2.2: The risk spectrum: some principal sources of risk....17 xii

Performance Bond: Conditional or Unconditional INTRODUCTION

CHAPTER 1 INTRODUCTION 1.1 Background of Topic A performance bond is a bond giving security for the carrying out of a contract, where a bond is a deed by which one person (the obligator) commits himself to another (the obligee) to do something or refrain from doing something. 1 In construction contracts, a performance bond is a bond taken out by the contractor, usually with a bank or insurance company (in return for payment of a premium), for the benefit of and at the request of the employer, in a stipulated maximum sum of liability and enforceable by the employer in the event of the contractor s default, repudiation or insolvency. 2 These relationships can be illustrated in Figure 1.1. In Malaysia, most of the need of a performance bond is made through an agreement between the Government, the contractor and a third party (usually a bank or insurance company), whereby the third party agrees to pay a sum of money to the Government, in the event of non-performance of the construction contract by the 1 2 Elizabeth A. Martin (2003), A Dictionary of Law, 5 th Edition reissued with new covers, Oxford University Press, Oxford, p.53 Nigel M. Robinson et. al. (1996), Construction Law in Singapore and Malaysia, 2 nd Edition, Butterworths Asia, Singapore, p.205 1

contractor. 3 It is provided in Clause 37(a) of the P.W.D. Form 203A (Rev. 10/83) Standard Form of Contract to be Used Where Bills of Quantities Form Part of the Contract that the Contractor shall either deposit with the Government a performance bond in cash or alternatively by way of a Treasury's Deposit or Banker's Draft or approved Banker's or Insurance Guarantee equal to 5% of the Contract Sum as a condition precedent to the commencement of work. In other words, the Contractor is not permitted to carry out any work under the Contract unless and until the performance bond is given. The failure of the Contractor to give the performance bond may amount to a fundamental breach of contract entitling the Government to discharge the Contract and sue the Contractor for damages accordingly. 4 Bank Obligator Indemnity Contractor Assured Bond Contract Developer Obligee Figure 1.1: Relationships of Parties to a Bond and the Underlying Contract 5 The validity period of the performance bond is as indicated in Figure 1.2 below. By clause 37(b), the performance bond is required to be maintained for such period as provided in the PWD Bond, i.e. until 6 months after the expiry of the Defects Liability 3 4 5 Khairuddin Abdul Rashid (2004), Guarantee Against Non-Performance of Construction Contract by the Contractor: Performance Guarantee Sum versus Performance Bond, Seminar, 1 st International Conference, Toronto Canada, May 27 2004 May 28 2004, World of Construction Project Management, p. 5 Lim Chong Fong (2004), The Malaysian PWD Form of Construction Contract, Sweet & Maxwell Asia, Petaling Jaya, p. 76 Chow Kok Fong (2004), Law and Practice of Construction Contracts, 3 rd Edition, Sweet & Maxwell Asia, Singapore, p. 525 2

Period stated in the Contract calculated from the date of completion of the Works or any authorized extension thereto or if the contract is determined, until one year after the date of determination. 6 Possession of site Practical completion Completion of making good defects Contractor informed about the bond during tender Construction Defects liability Validity period of the Performance Bond extends to 6 months after the expiry of the defects liability period Figure 1.2: Time line indicating the validity period of the performance bond 7 There are two types of performance bonds, as set out below. 8 Conditional bond or default bond. A default bond is a contract of guarantee whereby the surety accepts joint and several responsibility for the performance of the contractor s obligations under the building contract: the contractor remains primarily liable for his performance and not protected by the bond. Unconditional bond or on-demand bond. An on-demand bond is a covenant by the surety (usually a bank) to indemnify the employer following contractor s default, subject to stated terms and up to a sum commonly between 10 and 20% of the main contract sum. The contractor is not a party to this arrangement. 6 7 8 Lim Chong Fong (2004), p. 77 Khairuddin Abdul Rashid (2004), p. 6 Nigel M. Robinson et. al. (1996), p. 205 but under on-demand bond in Malaysia, subject to stated terms and up to a sum commonly 5% of the main contract sum. 3

Thus, in order to determine the types of performance bond applicable in a contract, a thorough understanding of the content of the bond is required. The Court of Appeal in the famous Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 9 held that: Therefore a performance bond is nothing more than a written guarantee, and in order to interpret the obligations of the bank, one need only to look at the written bond itself to determine what are the terms and conditions agreed upon between the parties. A great deal, therefore, depends on the wording of the bond itself. 1.2 Problem Statement As discussed above, there are two types of performance bond. The distinction between conditional and unconditional 'on demand' guarantee is also been discussed in the case of China Airlines Ltd v Maltran Air Corp Sdn Bhd (formerly known as Maltran Air Services Corp Sdn Bhd) and Another Appeal [1996] 10 and later is agreed upon in the case of Government of Malaysia v South East Asia Insurance Bhd [2000] 11. In the former case, the court cited that: A bank guarantee is a performance bond. There are two types of performance bond. The first type is a conditional bond whereby the guarantor becomes liable upon proof of a breach of the terms of the principal contract by the principal and the beneficiary sustaining loss as a result of such breach. The guarantor's liability will therefore arise as a result of the principal's default. The second type is an unconditional or 'on demand' performance bond which is so drafted that the guarantor will become liable merely when demand is made upon him by the beneficiary 9 10 11 [1995] 3 MLJ 449 [1996] 2 MLJ 517 [2000] 3 MLJ 625 4

with no necessity for the beneficiary to prove any default by the principal in performance of the principal contract. However, in Malaysia, for the past 20 years and since the famous Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 12 to the recent Suharta Development Sdn Bhd v United Overseas Bank (M) Bhd & Anor [2005] 13, the question of whether the performance bond in a construction contract is a conditional or an unconditional guarantees is still one of the issues relating to performance bond that been discussed. In Suharta Development Sdn Bhd v United Overseas Bank (M) Bhd & Anor [2005] 14, Abdul Wahab Said Ahmad JC stated that: A performance bond or guarantee is in fact a written contract to guarantee due performance in the event of breach or non performance of the contract. In determining whether it is conditional or otherwise, the court is concerned with the contractual construction or interpretation of the bond or guarantee itself. A great deal depends on the wording of the guarantee itself to discover the intention of the parties. The defendant contended that the terms of the guarantee is conditional and cited Teknik Cekap Sdn Bhd v Public Bank Bhd [1995] 3 MLJ 449 whilst the plaintiff relied on LEC Contractors (M) Sdn Bhd (formerly known as Lotterworld Engineering & Construction Sdn Bhd) v Castle Inn Sdn Bhd & Anor [2000] 3 MLJ 339. In both the cases the terms of the bond are similar to that in the case before me. The Court of Appeal in Teknik Cekap Sdn Bhd held the bond to be conditional but in LEC Contractors (M) Sdn Bhd held it is an on demand bond. 12 13 14 [1995] 3 MLJ 449 [2005] 2 MLJ 762 ibid 5

In LEC Contractors (M) Sdn Bhd Mokhtar Sidin JCA distinguished the case of Teknik Cekap and at p 358 said: That is the position of an on demand performance bond. It is clear to us that the bank guarantee in the present appeal is a performance bond. From the wordings of the guarantee it is clear to us that it is 'on demand' performance bond as stated in Esso Petroleum Malaysia Inc v Kago Petroleum Sdn Bhd: 'All that was required to trigger them was a demand in writing'; or in the words of Mohamed Dzaidin FCJ in the case of China Airlines Ltd v Maltran AirCorp Sdn Bhd: 'the guarantor will become liable merely when demand is made upon the beneficiary with no necessity for the beneficiary to prove any default by the principal in performance of the principal contract'. The appellant claimed that the bank guarantee is a conditional bond. To support this contention learned counsel for the appellant referred to the case of Teknik Cekap, a decision of this court where the court held that a performance bond was a conditional bond. It was held by the court that because the bond began the words: 'If the subcontractor shall in any respect fail to execute the contract or commit any breach of his obligations thereunder then the guarantor shall pay'. Apparently this is the case in Malaysia where similar wordings has been used where the court has held that it was a conditional bond. From the above case, therefore, it is important to determine the content of the performance bond: whether the client can call upon the bond in the case of nonperformance of the contractor or can the bank restraint the client from calling the bond among other. So, the phrase(s) in the bond shall be the issue of discussion. 6

This phrase(s) should also be in written form. A clear written phrase(s) that make up the content of the performance bond can clear the distinction between conditional and unconditional on demand guarantee. Hence it is important and necessary to understand the circumstances in performance bond, which will be available to the parties to a building contract. And from that, the parties involved will clearly defined their rights and liability against bonds and guarantee to assist the respective party in construction contract. 15 1.3 Objective of Topic As such, this Masters Project has the objective to determine the phrase(s) in the Performance Bond in a construction contract that determine whether the performance bond is a conditional or an unconditional on demand guarantee. By clearing this issue, it is hoped that no more dispute will arise under the interpretation of the content of the Performance Bond especially in a construction contract. 1.4 Previous Research There is quite a number of similar research have been done previously. The first was by Dr Khairuddin Abdul Rashid called Guarantee against Non-performance of Construction Contract by the Contractor: Performance Guarantee Sum versus Performance Bond. This research was presented at the 1 st International Conference at Toronto, Canada on May 27 2004 to May 28 2004 organized by the World of 15 Nur'Ain Ismail (2007), Performance Bond and An Injunction, Master's Project Report (Dissertation), Universiti Teknologi Malaysia, p. 6. 7

Construction Project Management. This study aims to fulfill two key objectives: to review literature and Government documents relating to the rules on the requirement for performance bond or performance guarantee sum for public infrastructure contracts in Malaysia; and to assess the consequences to the Government of the contractors' opting for either the performance bond or the performance guarantee sum. The second was by En. Jamaluddin Yaakob called Performance Bond in Construction Contract: Problems with Drafting & Calling the Bonds. This research was presented at the seminar on Issues on Non-Performance of Construction Contract at Rumah Alumni, Universiti Teknologi Malaysia, Skudai, Johor on February 26 2005 organized by the Department of Quantity Surveying, Faculty of Built Environment, Universiti Teknologi Malaysia. The main objective of this paper is examine the correlation between the wordings of performance bonds and the problems that arise when making a call on the bond. The third was by Nur'Ain Ismail called Performance Bond and An Injunction. This research was a master s project report (dissertation) submitted on July 2007 in fulfillment of the requirements for the award of the degree of Master in Science of Construction Contract Management, Universiti Teknologi Malaysia. The objective of the study is to identify legal principles used by the courts in granting or rejecting an application for injunction against bondsmen from making payment or against employer from receiving the bonds. 1.5 Scope of Topic As far as the scope of study is concerned, this Masters Project paper gather some medium of literatures such as the standard forms of contract (for example, PWD203A), 8

other related documents (for example, Bank Guarantee for Performance Bond or PWD Q7/81), and relevant law cases (for example, from Malayan law Journal) as well as Reference Books and other mediums (for example, journals, articles, magazines, newspapers, internets, etc.) for analyzing the legal interpretation between conditional and unconditional on demand performance bond in construction contract. 1.6 Significance of Topic As has been mentioned in the objective, this research is important to the construction industry because it determines the phrase(s) in the Performance Bond in a construction contract whether the phrase(s) is/are conditional or unconditional on demand guarantees. By clearing this issue, it is hoped that no more dispute will arise due to the interpretation of the content of the Performance Bond especially in a construction contract. Hopefully, this study will add as a reference to the Malaysian construction contract practice to be more effective. 1.7 Methodology and Research Process Basically, this Masters Project paper adopts five steps as its methodology and research process in order to achieve its objective. The steps are discussed further as follows: Step 1: Identification of Research Topic This is to give a thorough understanding what is this research is all about with some initial definition of the topic under study. 9

Step 2 Research Objective This is the determining of what the research is hoping to achieve in studying the determination on the phrase(s) in the Performance Bond in a construction contract whether they is/are conditional or unconditional on demand guarantees. Step 3: Data Collection This is of course the gathering and consuming the medium of literatures as stated in the Scope of Study above. The medium of literatures is divided into two categories, namely the primary data and secondary data as shown in Figure 1.3 below. Step 4: Analysis This is the main text of this Masters Project dissertation which is analyzing and commenting the content of the Performance Bond in relation to whether it is a conditional or an unconditional on demand guarantee through the legal point of view from the examples of judgment held in law cases and later written systematically into chapters in this Masters Project paper. By using the words Performance Bond, 67 cases for the past 20 years were downloaded from the Malayan Law Journal to be analyzed further. From the first reading and screening of the above cases, the judge of 25 cases did interpret the distinction between conditional and unconditional Performance Bond. Further screening was done from the 25 cases whereby only cases which the judge discussed on the wordings or phrase(s) of the Performance Bond will be further analyzed. From this, 15 cases were identified to be further consumed. 10

Definition of Research Topic Data Collection Primary Data Secondary Data The standard forms of contract (for example, PWD203A) Other related documents (for example, Bank Guarantee for Performance Bond or PWD Q7/81) Relevant law cases (for example, from Malayan law Journal) Reference Books and other mediums (for example, journals, articles, magazines, newspapers, internets, etc.) Analysis of Data Conclusion & Recommendation Figure 1.3: Flowchart of the research methodology 11

Step 5: Conclusion and Recommendation This step concludes and summarizes the whole of the Masters Project paper, the outcome of objective achievable as well as making some recommendations to the outcomes. This Masters Project paper also hope to produce a new revised Bank Guarantee for Performance Bond that cleared the issue of interpreting the content whether it is conditional or not. 1.8 The organizational of the research proposal This Masters Project paper seeks to achieve its aim in five chapters with the main reference will be the identification of phrase(s) in the Performance Bond in a construction contract that differentiate between conditional and unconditional on demand guarantee: Chapter 1: Introduction The introduction is the first chapter consists of the overview of this Masters Project paper as well as stating the aim and objectives, issue or problem statement, scope and methodology of study, previously similar research, and brief description of chapter organization. Chapter 2: Performance Bond The second chapter is basically the brief information on the bond application, management and its effectiveness in the Malaysian construction contract practice. 12

Chapter 3: Comparative Analysis: Conditional versus Unconditional Performance Bond The third chapter is basically the detail legal issues regarding the identification of phrase(s) in the Performance Bond that differentiate between conditional and unconditional on demand guarantee. Chapter 4: Conclusion and Recommendation Lastly, chapter five conclude and summarize the whole of the paper, the outcome of objective achievable as well as making some recommendation to the outcomes as well as developing a new Bank Guarantee for Performance Bond. This will add to the existing references for students and practitioners in the Malaysian Construction Industry especially in the context of Construction Contract Management. 13

Performance Bond: Conditional or Unconditional PERFORMANCE BOND

CHAPTER 2 PERFORMANCE BOND 2.1 Introduction The success of a construction project is measured by its timely completion to specification within the budget allocated. However, in the execution of any engineering project there is invariably an element of risk involved 16 : that is to say, construction is a highly risky business, where the level of risk is considered much higher than in other types of economic activities. 17 Figure 2.1 illustrates the risk spectrum which identifies some principal sources of risk. Furthermore, projects involve commercial risks and they involve people. 18 All parties take some form of risk when they enter into construction contract. The acceptance of an obligation brings with it the acceptance of a commensurate risk, i.e. the risk of being unable to fulfill the obligation because one's own inadequacy, incapacity, inadvertence or error, or because of interference from outside sources or supervening events. 19 16 17 18 19 S Radhakrihnan (1999), Legal Aspects of Insurance for Engineering Projects, Article, [1999] 1 MLJ cxxx; [1999] 1 MLJA 130 Khairuddin Abdul Rashid (2004), p. 1 John Murdoch and Will Hughes (2000), Construction Contracts Law and Management, 3 rd Edition, Spon Press, London, p. 7 Nigel M. Robinson et. al. (1996), p. 185 14

BUSINESS RISK (Will the development fulfill its intended purpose?) FINANCIAL RISK (Will the development be available?) DEVELOPMENT RISK MONEY RATE RISK (Will the cost of money change?) PRICE/COST LEVEL RISK (Will the price/cost level change?) DESIGN RISK (Will the design be cost-efficient?) (Will it have good buildability?) MANAGEMENT RISK (Will the construction management be efficient and effective?) CONSTRUCTION RISK DAMAGE OR INJURY RISK (Will there be third party claims?) (Will there be damage to the works?) POLITICAL/SOCIAL RISKS (Will the operating environment change?) INTER-PERSONAL RISKS (Will there be personality clashes?) (Will there be industrial unrest?) ESTIMATING/PRICING RISKS (Will there be measurement/pricing error?) Figure 2.1: The risk spectrum: some principal sources of risk 20 20 ibid 15

The following examples summarize many of the risks. 21 Some of them are contractor's risks (for example: payments; price fluctuation; etc.) and some are employer's risks (for example: workmanship; materials and goods; insolvency; etc.): Physical works ground conditions; artificial obstructions; defective materials or workmanship; tests and samples; weather; site preparation; inadequacy of staff, labour, plant, materials, time or finance. Delay and disputes possession of site; late supply of information; inefficient execution of work; delay outside both parties' control; layout disputes. Direction and supervision greed; incompetence; inefficiency; unreasonableness; partiality; poor communication; mistakes in documents; defective designs; compliance with requirements; unclear requirements; inappropriate consultants or contractors; changes in requirements. Damage and injury to persons and property negligence or breach of warranty; uninsurable matters; accidents; uninsurable risks; consequential losses; exclusions, gaps and time limits in insurance cover. External factors government policy on taxes, labour, safety or other laws; planning approvals; financial constraints; energy or pay restraints; cost of war or civil commotion; malicious damage; intimidation; industrial disputes. Payment delay in settling claims and certifying; delay in payment; legal limits on recovery of interest; insolvency; funding constraints; shortcomings in the measure and value process; exchange rates; inflation. Law and arbitration delay in resolving disputes; injustice; uncertainty due to lack of records or ambiguity of contract; cost of obtaining decision; enforcing decisions; changes in statutes; new interpretations of common law. Risks are inevitable and cannot be eliminated. They can, however, be transferred. 22 One of the main roles of a contract is to distribute risks between the parties. 21 22 John Murdoch and Will Hughes (2000), p. 83 ibid, p. 85 16

Standard forms of contracts contained express risks distributing provisions. Risk transferring contracts commonly exist between the various parties concerned in construction 23, as shown in Figure 2.2. The contracting parties: Nature of the contract: Client Contractor Designer Nominated subcontractor Nominated supplier Contract for services and indemnities Contract for services Performance warranty Material quality and/or fitness warranty Contractor Sub-contractor Supplier Contract for services and indemnities Contract for sale and warranty Insurer Client Contractor Subcontractor Supplier Designer Fire Insurance (existing buildings) (1) Contractor's 'All Risks' Employers' liability Public liability Contract works, material and plant (2) Employer's risks (as specified) Loss or damage to materials in transit Professional indemnity Surety Or Guarantor or Bondsman Client Contractor Contractor's performance bond Subcontractor's performance bond Contract of indemnity against calls on main bond Figure 2.2: The risk spectrum: some principal sources of risk 24 23 24 Nigel M. Robinson et. al. (1996), p. 188 Ibid, p. 189 17

In the context of public infrastructure work in Malaysia, one major risk to the Government is non-performance of construction contracts by the contractors. 25 As illustrated in Figure 2.2, performance bond is a legal and management instrument used by employers to manage risk with respect to contractor's nonperformance. 2.2 Definition As mentioned in Chapter 1, a performance bond is a bond giving security for the carrying out of a contract, where a bond is a deed by which one person (the obligator) commits himself to another (the obligee) to do something or refrain from doing something. 26 In construction contracts, a performance bond is a bond taken out by the contractor, usually with a bank or insurance company (in return for payment of a premium), for the benefit of and at the request of the employer, in a stipulated maximum sum of liability and enforceable by the employer in the event of the contractor s default, repudiation or insolvency. 27 In Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 28, Shaik Daud JCA further defines performance bond by stating: Having considered the submissions it is relevant to find out what therefore is a performance bond. As I see it there is nothing special or unique in a performance bond. It is in fact a written contract of guarantee by a bank, other financial institutions or in some cases as insurance company, whereby they guarantee the due performance of a contract and in the 25 26 27 28 Khairuddin Abdul Rashid (2004), p. 1 Elizabeth A. Martin (2003), p.53 Nigel M. Robinson et. al. (1996), p.205 [1995] 3 MLJ 449 18

event of a breach or non-performance of the contract, they guarantee to pay, on a written demand being made, the sum stipulated in the guarantee. Therefore, a performance bond is nothing more than a written guarantee, and in order to interpret the obligations of the bank, one need to look at the written bond itself to determine what are the terms and conditions agreed upon between the parties. A great deal, therefore, depends on the wording of the bond itself. 2.3 Nature of Performance Bond A bond or guarantee is an arrangement under which the performance of a contractual duty owed by one person (A) to another (B) is backed up by a third party (C). What happens is that C promises to pay B a sum of money if A fails to fulfill the relevant duty. In this context A is commonly known as the principal debtor or simply principal; B is called the beneficiary; and C is called the bondsman, surety or guarantor. 29 In a construction contract, performance bond is also a three-party instrument between bondsman, the employer and the contractor. The agreement, however, binds the contractor to comply with the terms of a contract. If the contractor fails to perform the contract, the bondsman assumes the responsibility to indemnify the employer up to the maximum amount of the bond. The Bondsman's obligation to pay is now arises when called upon to do so by the employer. The obligation to pay is, however, independent of the underlying contract. This is due to the fact that the performance bond is like a letter of credit and designed to release 'no quibble' cash to the beneficiary in the event the call on the bond. This is agreed by 29 John Murdoch and Will Hughes (2000), p. 230 19

what Lord Denning MR said in Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] 30 that: A performance bond is a new creature so far as we are concerned. It has many similarities to a letter of credit, with which of course we are very familiar. It has been long established that when a letter of credit is issued and confirmed by a bank, the bank must pay it if the documents are in order and the terms of the credit are satisfied. Any dispute between buyer and seller must be settled between themselves. The bank must honour the credit. 2.4 Purpose of Performance Bond Rekhraj J in the case of Lotterworld Engineering & Construction Sdn Bhd v Castle Inn Sdn Bhd & Anor [1998] 31 stated that the purpose of performance bond is as follows: It is to be understood that the purpose of the performance bond in the construction industry is to perform the role of an effective safeguards against non-performance, inadequate performance or delayed performance and its production provides a security as readily available to be realized, when the prescribed event occurs, viz a viz simply failing to complete the work which had been contracted to carry out. 30 31 [1978] QB 159, [1978] 1 All ER 976, [1977] 3 WLR 764, [1978] 1 Lloyd's Rep 166, 6 Build LR 1, 10 Legal Decisions Affecting Bankers 50 [1998] 7 MLJ 105 20

The purpose of a bond is therefore to provide the employer with some financial security in the form of a cash payable by the bank for the contractor's failure to perform his obligation under the construction contract. 2.5 Performance Bond in Construction Contract Whether or not a contractor is required to provide performance bond depends on the terms of the contract. In Malaysia, as in Chapter 1, Clause 37(a) of the P.W.D. Form 203A (Rev. 10/83) Standard Form of Contract to be Used Where Bills of Quantities Form Part of the Contract states that the Contractor shall either deposit with the Government a performance bond in cash or alternatively by way of a Treasury's Deposit or Banker's Draft or approved Banker's or Insurance Guarantee equal to 5% of the Contract Sum as a condition precedent to the commencement of work. In other words, the Contractor is not permitted to carry out any work under the Contract unless and until the performance bond is given. The failure of the Contractor to give the performance bond may amount to a fundamental breach of contract entitling the Government to discharge the Contract and sue the Contractor for damages accordingly. 32 However, it is not the only places where performance bond is mentioned. Under Clause 10 of the Conditions of Tendering in the Form of Tender (PWD 203B Rev. 1/82) states the following: The successful tenderer shall so soon as it practicable but before the commencement of the Works deposit with the Superintending Officer Performance Bond amounting to 5% of the Contract Sum; 32 Lim Chong Fong (2004), p. 76 21

Another place where the requirement of performance bond is mandatory before commencement of contractor's works is under Clause 4 of the Letter of Acceptance (PWD 203D Rev. 1/82), which states: I wish to draw your attention to the Conditions of Tendering whereby as conditions precedent to the commencement of the Works, you are required to deposit with the Government or the Superintending Officer Performance Bond amounting (being 5% of the Contract Sum) in cash or in the form of Treasury's Deposit, Banker's Draft or an approved banker's or Insurance Guarantee. It is also unusual for private projects to require the contract to provide performance bond. Performance Bond, however, is the precondition for: Taking possession of site By Clause 38(a) of the P.W.D. Form 203A (Rev. 10/83) Standard Form of Contract to be Used Where Bills of Quantities Form Part of the Contract it is made clear that even if possession of the Site has been given, the Contractor cannot commence work unless and until the performance bond and the insurance policies required under the Contract have been deposited with the Government or the Superintending Officer. Thus if the Contractor delays in depositing the performance bond or insurance, he does so at his own peril as the time available for the execution of the Works under the Contract would be ticking away. 33 Advance payment The advance payment is paid to the Contractor upon application from him together with a bank or insurance guarantee for the amount of advance to be paid, 33 Lim Chong Fong (2004), p. 80 22

and provided that he has returned the Letter of Acceptance duly signed and witnessed, and submitted the Performance Bond and the requisite insurance policies required by the Contract. 34 First interim payment It is further provided that, other than for the first Interim Certificate, the Superintending Officer need not issue further Interim Certificates unless and until the Contractor has returned to the Government the Letter of Acceptance of Tender duly signed by the Contractor, and has deposited with him or the Government the insurance policies and performance bond required under clauses 33, 34, 36 and 37 of these Conditions in the P.W.D. Form 203A (Rev. 10/83) Standard Form of Contract to be Used Where Bills of Quantities Form Part of the Contract respectively. 35 As mentioned in Chapter 1, the validity period of the performance bond is as indicated in Figure 1.2 hereinbefore. By clause 37(b) of the P.W.D. Form 203A (Rev. 10/83) Standard Form of Contract to be Used Where Bills of Quantities Form Part of the Contract, the performance bond is required to be maintained for such period as provided in the PWD Bond, i.e. until 6 months after the expiry of the Defects Liability Period stated in the Contract calculated from the date of completion of the Works or any authorized extension thereto or if the contract is determined, until one year after the date of determination. 36 34 35 36 Jabatan Kerja Raya (1988), A Guide on the Administration of Public Works Contracts, Ibu Pejabat JKR Malaysia, p. 301. Lim Chong Fong (2004), p. 110 Lim Chong Fong (2004), p. 77 23

2.6 Types of Performance Bond As also mentioned in Chapter 1, there are two types of performance bond: conditional and unconditional or on demand. Mohamed Dzaiddin FCJ in delivering the grounds of judgment of the court in China Airlines Ltd v Maltran Air Corp Sdn Bhd (formerly known as Maltran Air Services Corp Sdn Bhd) and Another Appeal [1996] 37 reveal this by saying: A bank guarantee is a performance bond. There are two types of performance bond. The first type is a conditional bond whereby the guarantor becomes liable upon proof of a breach of the terms of the principal contract by the principal and the beneficiary sustaining loss as a result of such breach. The guarantor's liability will therefore arise as a result of the principal's default. The second type is an unconditional or 'on demand' performance bond which is so drafted that the guarantor will become liable merely when demand is made upon him by the beneficiary with no necessity for the beneficiary to prove any default by the principal in performance of the principal contract. A sample of a conditional performance bond can be found in the case of Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 38 as follows: If the sub-contractor (unless relieved from the performance of any clause of the contract or by statute or by the decision of a tribunal of competent jurisdiction) shall in any respect fail to execute the contract or commit any breach of his obligations thereunder then the guarantor shall pay to the contractor up to and not exceeding the sum of RM422,000 (Malaysian 37 38 [1996] 2 MLJ 517 [1995] 3 MLJ 449 24

Ringgit four hundred twenty two thousand) only representing 10% of the contract value or such part thereof on the contractor's demand notwithstanding any contestation or protest by the sub-contractor or by the guarantor or by any other third party, provided always that the total of all partial demands so made shall not exceed the sum of RM422,000 (Malaysian Ringgit four hundred twenty two thousand) only and that the guarantor's liability to pay the contractor as aforesaid shall correspondingly be reduced proportionate to any partial demand having been made as aforesaid. On the other hand, a sample of an unconditional on demand performance bond can be found in the case of Kirames Sdn Bhd v Federal Land Development Authority [1991] 39 as follows: We, Jerneh Insurance Corporation Sdn Bhd Limited, having the registered office at 7th Floor, Wisma MISC, No 2, Jalan Conlay, Kuala Lumpur do hereby irrevocable and absolutely guarantee that the sum of Ringgit 117,535 by way of security deposit under the said contract shall be paid to you by us as per the following terms: (a) (b) the said sum of Ringgit 117,535 shall be paid by us forthwith on demand by you in writing without your having to assign any reason whatsoever for such demand; the said sum of Ringgit 117,535 shall be paid by us forthwith to you irrespective of whether or not there is any dispute between the said contract and yourselves (the Authority) in respect of or relating to the said contract or in respect of any other matter and irrespective of whether 39 [1991] 2 MLJ 198 25

or not such said dispute, if any, has been settled, resolved, litigated or adjudicated upon otherwise howsoever. Thus it is seen in the above samples that the main distinction between the two types of bond is with respect to the requirements for making call on the bond. In conditional performance bond, the beneficiary must comply with conditions precedent for calling the bond. In on demand performance bond, on the other hands, the only condition precedent for calling the bond is a written notice to the guarantor. 2.7 Construction of Performance Bond In order to determine the construction of a performance bond, Sir Denys Buckley stipulated in the case of IE Contractors Ltd v Lloyds Bank PLC, and Rafidain Bank [1990] 40 that: I am in entire agreement with the proposition that to discover what the parties intended should trigger the indemnity under the bond involves a straightforward exercise of construction, or interpretation, of the bond to discover the intention of the parties in that respect. The Malaysian Superior courts have referred to and approved this approach in a number of cases. One of the case that the Superior Court approval of the above IE Contractors Ltd v Lloyds Bank PLC, and Rafidain Bank [1990] 41 judgment is Esso 40 41 [1990] 2 Lloyd's Rep 496, SI Build LR 1 [1990] 2 Lloyd's Rep 496, SI Build LR 1 26

Petroleum Malaysia Inc v Kago Petroleum Sdn Bhd [1995] 42. Peh Swee Chin FCJ in delivering the grounds of judgment of the court said that: That the real issue of a performance bond is one of contractual interpretation was the unanimous view of three judges in the Court of Appeal in IE Contractors Ltd v Lloyds Bank plc and Rafidain Bank [1990] 2 Lloyd's Rep 496; (1991) 51 BLR 1. It is not our intention to write an essay on performance bonds, in the instant appeal, except to repeat that it 'involves a straightforward exercise of construction, or interpretation, of the bond to discover the intention of the parties' -- per Sir Denys Buckley in IE Contractors [1990] 2 Lloyd's Rep 496 at p 503; (1991) 51 BLR 1 at p 15. Another judgment is by Shaik Daud JCA in Teknik Cekap Sdn Bhd v Public Bank Berhad [1995] 43. In this Court of Appeal, he had also approved IE Contractors Ltd v Lloyds Bank PLC, and Rafidain Bank [1990] 44, as per Chapter 1, by saying: Therefore a performance bond is nothing more than a written guarantee, and in order to interpret the obligations of the bank, one need only to look at the written bond itself to determine what are the terms and conditions agreed upon between the parties. A great deal, therefore, depends on the wording of the bond itself. 42 43 44 [1995] 1 MLJ 149 [1995] 3 MLJ 449 [1990] 2 Lloyd's Rep 496, SI Build LR 1 27

2.8 Summary Historically, Lord Denning MR said in Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] 45 in interpreting performance bond: A performance bond is a new creature so far as we are concerned. It has many similarities to a letter of credit, with which of course we are very familiar. It has been long established that when a letter of credit is issued and confirmed by a bank, the bank must pay it if the documents are in order and the terms of the credit are satisfied. Any dispute between buyer and seller must be settled between themselves. The bank must honour the credit. However, Rekhraj J in the case of Lotterworld Engineering & Construction Sdn Bhd v Castle Inn Sdn Bhd & Anor [1998] 46 stated that the purpose of performance bond is as follows: It is to be understood that the purpose of the performance bond in the construction industry is to perform the role of an effective safeguards against non-performance, inadequate performance or delayed performance and its production provides a security as readily available to be realized, when the prescribed event occurs, viz a viz simply failing to complete the work which had been contracted to carry out. 45 46 [1978] QB 159, [1978] 1 All ER 976, [1977] 3 WLR 764, [1978] 1 Lloyd's Rep 166, 6 Build LR 1, 10 Legal Decisions Affecting Bankers 50 [1998] 7 MLJ 105 28