Client Alert March 2017

Similar documents
Newsletter December 2017

Newsletter February 2018

Global Restructuring & Insolvency Guide

THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. Singapore

Dispute Resolution Around the World. Italy

CLUB MEMBERS PERMITTED TO BRING REPRESENTATIVE ACTION AGAINST CLUB OWNER

Singapore High Court Decides on Set-Offs and Costs Implications

PREPARING FOR NEW PRIVACY REGIMES: PRIVACY PROFESSIONALS VIEWS ON THE GENERAL DATA PROTECTION REGULATION AND PRIVACY SHIELD

ARBITRAL AWARD HELD ENFORCEABLE DESPITE APPLICANT S FAILURE TO FILE EXPERT WITNESS STATEMENT

Dispute Resolution Around the World. Azerbaijan

Draft Circular on the Cross-border Provision of Public Information

Employment and Labor Law Update for 2017

Developments in Construction Law in Singapore (2014)

Singapore Court Rejects Application to Adjourn Enforcement Proceedings Pending Setting Aside Challenge in Arbitral Seat

Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore

Arbitration Act 1996

Navigating the Framework for Claiming against an Insolvent Company

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

The new Arbitration (Guernsey) Law, a guide to the key provisions

PERFORMANCE GUARANTEE

I. Supreme Court of Singapore - High Court

RESERVE POWERS OF MANAGEMENT MAY DEVOLVE TO SHAREHOLDERS WHEN BOARD IS DEADLOCKED

THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD

Enterprise Recon. Software License Agreement

Arbitration Agreement

11th. Edition The Baker McKenzie International Arbitration Yearbook. Philippines

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

the governing law of the Agreement is New York law; and

MEMORANDUM OF UNDERSTANDING BETWEEN (JAINAM HEALTH SERVICES LTD) AND DENTAL SERVICE PROVIDER

CASE UPDATE. The High Court Considers the Status and Scope of an Arbitration Agreement in the Context of a Termination of the Main Contract

Provider Contract for the Provision of Legal Aid Services and Specified Legal Services

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan

Deed of Company Arrangement

Luzon Hydro Corp v Transfield Philippines Inc

Dispute Resolution Around the World. Kazakhstan

TENDER NOTICE. AVAILABILITY OF TENDER DOCUMENTS Tenderers are requested to download the Tender Documents from the SATS Website:

SH Design & Build Pte Ltd v BD Cranetech Pte Ltd

Published on e-first 1 June AGENCY LAW

REQUEST FOR ARBITRATION

BE it enacted by Parliament in the Thirty-second Year of the Republic of India as follows:-- CHAPTER I PRELIMINARY

Dispute Resolution Around the World. Russia

SECURITY SERVICES AND INVESTIGATORS ACT

SME Care Pte Ltd v Chan Siew Lee Jannie

PROCEDURE FOR DETAILED ASSESSMENT OF COSTS AND DEFAULT PROVISIONS

IN THE DISPUTES TRIBUNAL [2011] NZDT 311 APPLICANT RESPONDENT

MEMORANDUM OF UNDERSTANDING BETWEEN (JAINAM HEALTH SERVICES LTD) AND SPECIALIST DOCTOR

Dispute Resolution Around the World. Germany

Introduction 2. What is Self-representation? 2. Who Can Self-represent? 2. Help for Self-represented Litigants 3

MEMORANDUM OF UNDERSTANDING

NOTICE OF ARBITRATION

ADJUDICATION: RAISING OBJECTIONS TO THE ADJUDICATOR S JURISDICTION OR BREACH OF SOP ACT AT THE EARLIEST POSSIBLE OPPORTUNITY

PART I ARBITRATION - CHAPTER I

THE CONSUMER PROTECTION (AMENDMENT) ACT, 2002 THE CONSUMER PROTECTION (AMENDMENT) ACT, 2002 ( 62 OF 2002 ) { Passed by Rajya Sabha on 11.3.

Statutory adjudication and the standard building contract in Singapore Is the Final Payment referable to statutory adjudication?

COURTS ASIA LIMITED (Incorporated in the Republic of Singapore) (UEN/Company Registration Number: K)

TERMS AND CONDITIONS. BACKGROUND: These Terms and Conditions shall apply to the provision of cleaning services by Cambridge Doms to clients.

What Constitutes a Supplementary Award of CIETAC Arbitration? A Recent Interpretation by a Hong Kong Court

For personal use only

Asian Dispute Review

VINACAPITAL VIETNAM OPPORTUNITY FUND LIMITED. (the "Company") AUDIT COMMITTEE. Terms of Reference. (as adopted on 29 July 2016)

Forfeiture Clause In Incentive Award Plan Did Not Constitute Restraint In Trade

Unauthorised Transactions Not Saved by Conclusive Evidence Clause

High Court Rules That It Has No Original Jurisdiction To Revoke Patents

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. Malaysia

Legal Business. Overview Of Court Procedure. Memoranda on legal and business issues and concerns for multiple industry and business communities

Dispute Resolution Around the World. Austria

(b) The test is that for summary judgment under CPR Part 24.

Local Planning Appeal Tribunal Tribunal d appel de l aménagement local

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE

INTERNATIONAL CENTRE FOR SETTLEMENT OF INVESTMENT DISPUTES

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998

Developments in International Arbitration, Construction & Projects in 2015

ASIA PACIFIC Post-Termination Restriction Overview

IMPRESS: The Independent Monitor for the Press CIC Regulatory Scheme

IN THE COURT OF APPEAL WHITE CONSTRUCTION COMPANY LIMITED. and DCG PROPERTIES LIMITED. 2011: July 25, 26; September 26.

IN THE LAHORE HIGH COURT LAHORE JUDICIAL DEPARTMENT

TENDER NOTICE. SATS Airport Services Pte Ltd (Co Reg. No R) invites tenders for the following:

TERMS OF REFERENCE INSURANCE & FINANCIAL SERVICES OMBUDSMAN SCHEME INCORPORATED

CONSUMER PROTECTION (FAIR TRADING) ACT

Practical Experiences Re Competition Law and Arbitration. 13 November 2009

Audit Committee Terms of Reference

Caribbean Community (CARICOM) Secretariat

AMA/ASMOF ALLIANCE DOCTORS IN TRAINING COMMITTEE TERMS OF REFERENCE. May 2018

Investments, Life Insurance & Superannuation Terms of Reference

COURT JURISDICTION AND PROCEEDINGS TRANSFER ACT

Index (2006) 22 BCL

CONTACT US. Background

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

STATE OF NORTH DAKOTA TRANSPORTATION COMPENDIUM OF LAW

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration

2017 FOOD TRUCK AGREEMENT Between the City of Des Moines and for Food and Beverage Sales in the City of Des Moines Marina

Freedom of Information Act 2000 (FOIA) Decision notice

HOW SECURED IS THE SOP ACT IN ASSISTING CONTRACTORS TO GET PAYMENT?

INVITATION FOR PROPOSAL TO PROVIDE LEGAL CONSULTANCY SERVICES

MAY 2012 BUSINESS AND CORPORATE LAW SOLUTION

Intellectual Property News September 2015

Data Processing Agreement

REPORT OF THE HEARING COMMITTEE

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context

Transcription:

Dispute Resolution Singapore Client Alert March 2017 Rong Shun Engineering & Construction Pte Ltd v C.P. Ong Construction Pte Ltd For More Information: Nandakumar Ponniya Principal +65 6434 2663 nandakumar.ponniya Wong Tjen Wee Local Principal +65 6434 2686 tjen.wee.wong Daniel Ho Associate +65 6434 2263 daniel.ho Forging new boundaries: A Court may set aside only part of an adjudication determination The Building and Construction Industry Security of Payment Act (the "SOPA") does not contain provisions that create a power to set aside an adjudication determination, let alone define the grounds on which that power ought to be exercised. In our previous client alert, we discussed the holding by the Singapore High Court that applications to set aside adjudication determinations and/or judgments under section 27 of the SOPA are akin to judicial review proceedings - and that in such applications, the Court is exercising its supervisory jurisdiction. In Rong Shun Engineering & Construction Pte Ltd v C.P. Ong Construction Pte Ltd [2017] SGHC 34, the Singapore High Court considered for the first time whether the Court, in the exercise of its supervisory jurisdiction, has the power to sever and set aside a part of an adjudication determination - as opposed to the entire adjudication determination. 1. Background The Respondent, C.P. Ong Construction Pte Ltd (the "Main Contractor"), invited selected contractors to submit quotations for electrical and fire alarm works in a HDB construction project. The Applicant, Rong Shun Engineering & Construction Pte Ltd (the "Sub- Contractor"), submitted two written quotations in two separate documents, to which the Main Contractor made a counter-offer for each of the two written quotations. The Sub-Contractor accepted the counter-offer. On 20 January 2016, the Sub-Contractor submitted a progress claim for all electrical and fire alarm works done from the commencement of works till 20 January 2016. The Main Contractor did not pay the progress claim; neither did it provide a payment response. Subsequently, the Sub-Contractor took out an adjudication application in relation to the payment claim, and invited the adjudicator to adjudicate upon the Sub- Contractor's claim to recover the retention sum - even though the retention sum claim was not advanced in the progress claim.

The adjudicator awarded the Sub-Contractor: a) The principal sum claimed in the progress claim in its entirety; and b) The retention sum. The Sub-Contractor sought to enforce the determination in the same manner as a judgment and an order that judgment be entered against the Main Contractor in terms of the determination. On the other hand, the Main Contractor argued that the determination should be set aside. The Main Contractor argued that the parties' intention, ascertained objectively from their conduct, was to contract separately for two separate scopes of work: a) The Main Contractor invited separate tenders for each scope of work; b) The Sub-Contractor submitted separate quotations for each scope of work; and c) The Sub-Contractor submitted separate progress claims for each scope of work prior to disputes that arose in the construction project. The Main Contractor also argued that the adjudicator had no power to determine the retention sum claim because it was not part of the Contractor's payment claim. Finally, the Main Contractor argued that the adjudicator had breached his obligation under section 16(3)(c) of the SOPA to comply with the principles of natural justice because he adjudicated upon the retention sum claim while barring the Main Contractor from being heard on that claim. 2. Issues before the High Court The High Court had to consider the three alternative grounds raised by the Main Contractor upon which the determination should be set aside: a) The adjudicator exceeded his jurisdiction by adjudicating upon a claim for payment which did not arise from a single contract ("Issue (a)"); b) The adjudicator exceeded his jurisdiction by adjudicating upon the Sub- Contractor's claim to recover the retention sum when the Sub-Contractor did not advance that claim in the payment claim ("Issue (b)"); and/or c) The adjudicator breached the rules of natural justice by determining this retention sum claim without hearing from the Main Contractor ("Issue (c)"). The Main Contractor argued further that, if any one of these grounds is upheld, the Court has no power to set aside only that part of the determination and that the entire determination must be set aside ("Issue (d)"). 2 Client Alert Mar 2017

3. The High Court's Decision As a preliminary point, the High Court held that a failure to raise a jurisdictional ground in a payment response or otherwise in the course of an adjudication does not estop a respondent from taking that point before a court when applying to set aside a determination or when resisting an application to enforce a determination. Issue (a) The High Court held that it is possible under the SOPA for a payment claim to comprise more than one progress payment (i.e., a claim for payment arising over more than one reference period). However, the High Court examined various provisions in the SOPA and held that the SOPA mandates that a "payment claim" within the meaning of section 10 of the SOPA must arise from one contract: "the Act mandates that one adjudication application be founded on one payment claim which arises from one contract" However, on the evidence, the High Court held that the Sub-Contractor's progress claim arose from one contract comprising two scopes of work. The High Court was also satisfied based on evidence that the quotations for each scope of work were separated for administrative convenience rather than contractual effect. Accordingly, the High Court held that the progress claim arose from a single contract, and was therefore a "payment claim" within the meaning of section 10 of the SOPA. Issue (b) The High Court held that the adjudicator exceeded his jurisdiction by adjudicating upon the retention sum claim. The High Court held that the payment claim fixes the parameters of the substantive content of an adjudication application, subject only to any additional issues introduced by a duly-served payment response. Accordingly, no payment claim dispute within the meaning of section 13(1) of the SOPA arose in connection with the retention sum claim, or could arise once the respondent failed to serve a payment response. The adjudicator was never clothed with the statutory power to deal with the retention sum claim. Issue (c) As a result of its holding in Issue (b), the High Court found no sense to decide whether the adjudicator breached the rules of natural justice in determining a claim which he had no statutory authority to determine. In any event, the High Court stated that even if it were wrong in its holding in Issue (b), section 15(3) of the SOPA operates to bar the adjudicator's jurisdiction from considering any reasons that a respondent failed to include in its payment response. 3 Client Alert Mar 2017

Issue (d) Most significantly, the High Court's holdings in Issues (a), (b) and (c) results in the outcome that the adjudicator had the statutory authority to adjudicate upon the Contractor's payment claim, but had no statutory authority to adjudicate upon the Contractor's retention sum claim. The question then is whether it is only the adjudicator's determination of the retention sum claim which was a nullity; or whether his entire determination was a nullity. The High Court answered in the former. The High Court stated that the power to set aside an adjudication determination is a common law power which exists outside the SOPA. The High Court restated that this was an aspect of the High Court's supervisory jurisdiction (i.e., the inherent power at common law of a superior court to review the proceedings and decisions of inferior courts and tribunals or other public bodies discharging public functions). In that context, the High Court held that the doctrine of severance, when applied to an adjudication determination, permits the Court to give the maximum effect permitted by law to an adjudication determination - and thereby to advance the purpose of the SOPA. The High Court therefore exercised the power to sever in order to set aside that part - and only that part - of the determination comprising the retention sum claim. However, the power to sever can be exercised only if "it is both textually severable and substantially severable from the remainder of the determination". 4. Conclusion The High Court provided some practical observations on when different scopes of work under different tenders may still result in a single contract - which can be useful in the construction industry where it is common for many sub-tenders to be carried out. Most significantly, the High Court had set out the ground-breaking principles upon which an adjudication determination under the SOPA is severable for jurisdictional error: a) The severance should not undermine the interim finality and enforceability of the remainder of the determination under the SOPA; b) The valid part of the adjudicator's reasons should still be grammatical and coherent (i.e., severed part is "textually severable" from the remainder of the determination); c) The valid part of the determination should be identifiable in terms of liability and quantum, without adjustment or contribution by the Court (i.e., severed part is "substantially severable" from the remainder of the determination); and 4 Client Alert Mar 2017

www.bakermckenzie.com Baker & McKenzie. Wong & Leow 8 Marina Boulevard #05-01 Marina Bay Financial Centre Tower 1 Singapore 018981 Tel: +65 6338 1888 Fax: +65 6337 5100 d) The Court may modify the text of the adjudicator's determination in order to achieve severance if the Court is satisfied that it is effecting no change in the substantial effect of the adjudication determination after accounting for the jurisdictional error and its necessary editorial consequences. The Main Contractor has since appealed against this decision and it remains to be seen whether the Court of Appeal will endorse this decision. For now, adjudication determinations can be set aside in part - but only where the severed part is still textually severable and substantially severable from the remainder of the determination. 2017 Baker & McKenzie. All rights reserved. Baker & McKenzie.Wong & Leow is a member of Baker & McKenzie International, a Swiss Verein with member law firms around the world. In accordance with the common terminology used in professional service organizations, reference to a "partner" means a person who is a partner, or equivalent, in such a law firm. Similarly, reference to an "office" means an office of any such law firm. This may qualify as "Attorney Advertising" requiring notice in some jurisdictions. Prior results do not guarantee a similar outcome. This alert is provided as general information and does not constitute legal advice. 5 Client Alert Mar 2017