THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS INTRODUCTION

Similar documents
Conditions Precedent to Recovery of Loss and Expense Claims

NOTICES, TIME BARS AND PROPORTIONALITY

Time and Construction Contracts

Time and Money: Time Bar Clauses. Nicholas Gould, Friday 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

TIME AND MONEY: TIME BAR CLAUSES. Nicholas Gould. 5 October 2007 THE FIDIC CONTRACTS CONFERENCE 2007

Martin Waldron BL FCIArb MSCSI MRICS

Adjudicators Discussion 15 June 2016

Commencement of Arbitration and Time-Bar Clauses

Martin Waldron BL FCIArb MSCSI MRICS

Position paper on liability

TIME OF ESSENCE IN CONSTRUCTION. CHAPTER ONE

Exclusive remedies, liquidated damages, the Prevention Principle, consequential loss and implied warranties

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802

SUPREME COURT OF QUEENSLAND

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied.

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

Effect of modifying clauses in standard-form contracts and the impact that this may have on their interpretation.

PROBUILD CONSTRUCTIONS (AUST) PTY LTD v DDI GROUP PTY LTD [2017] NSWCA 151 Court of Appeal: Beazley ACJ, McColl and Macfarlan JJA

INTRODUCTION THE PROBLEM

Identifying and managing risks when performing and terminating contracts

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book

2012 Thomson Reuters. No Claim to Orig. US Gov. Works.

CIArb March 2017 Conference Civil-Common Law Divergence and Convergence: The Construction Industry Case Study

An Engineer s / Dispute Adjudication Board s Decision Is Enforceable By An Arbitral Award

CONSTRUCTION BULLETIN. Welcome to the September edition of our Construction Bulletin. Construction. September

SUPREME COURT OF QUEENSLAND

PAM NORTHERN CHAPTER

COURT OF APPEAL CONFIRMS PAYMENT OF HIRE UNDER TIME CHARTERPARTIES IS NOT A CONDITION

SUPREME COURT OF QUEENSLAND


Mind the Gap: Analysis of Cases and Principles Concerning the Ability of ICC Arbitral Tribunals to Enforce Binding DAB Decisions

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:-

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES)

BUSINESS LAW GUIDEBOOK

Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore

Clause 3 deals with the duties and obligations of the Engineer and his assistants.

SUPREME COURT OF QUEENSLAND

BUILDING CONTRACTS RESPONSIBILITY FOR FAILURE TO CERTIFY PROGRESS PAYMENTS WHERE ARE WE NOW?

Projects Disputes in Australia: Recent Cases

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration

The Contractor s building defects liability in England and Wales

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

Section 112 of the HGCR Act is set out below, with the amendments which will be introduced under the LDEDC Act shown in bold:

SUPREME COURT OF QUEENSLAND

What s news in construction law 16 June 2006

Discrepancies and Divergences of Express & Implied Terms

CONSULTANCY SERVICES AGREEMENT

MCPS MEMBERSHIP AGREEMENT (MA2) AND ANNEXES

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

Agreement to UOB Banker s Guarantee Terms and Conditions

RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW

THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE

Financiers' Certifier Direct Deed

Possible Legal Issues of Unilaterally Contract Termination for Convenience

Construction Newsletter Issue No. 20

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21

PARADISE TIMBERS PTY LTD APPLICATION FOR COMMERCIAL CREDIT

1. This is the Country Addendum for Australia to the UOB Business Internet Banking Service Agreement (the Agreement).

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

MINOR WORKS CONTRACT (SUPERINTENDENT ADMINISTERED) (AMENDED FROM AS ) CENTRAL GIPPSLAND REGION WATER CORPORATION AND ## [INSERT CONTRACTOR]

International Construction Arbitration Alert

Index (2006) 22 BCL

SUPREME COURT OF QUEENSLAND

STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS. 1. Application

Braes of Doune Wind Farm (Scotland) Ltd v Alfred McaLpine Business Services Ltd [2008] APP.L.R. 03/13

Chapter I Introduction

Licence shall mean the terms and conditions for use of the Software as set out in this Agreement.

EXCLUSIONS OF CONSEQUENTIAL LOSS: AN AUSTRALIAN PERSPECTIVE

THE ICC S NEW DISPUTE BOARD RULES. CARROLL S DORGAN Jones Day Paris

GUARANTEE AND INDEMNITY

Speaker: Kim Lovegrove Principal of Lovegrove Solicitors, Commercial and Construction Lawyers.

Middle Eastern Oil LLC v National Bank of Abu Dhabi [2008] APP.L.R. 11/27

A CASE NOTE ON KOOMPAHTOO LOCAL ABORIGINAL LAND COUNCIL v SANPINE PTY LIMITED

Terms of Trade. For the provision of Security Systems Installation and Services By MB Security Ltd

CONVEYANCING LECTURE ON 31 JULY 2006

Client Alert March 2017

--- WHELAN J --- ACD Tridon Inc v Tridon Australia Pty Ltd [2002] NSWSC 896, distinguished. --- Mr A P Trichardt

CONSENTS AND APPROVALS BOILERPLATE CLAUSE

SUPREME COURT OF QUEENSLAND

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518

Australian Standard. General conditions of contract AS This is a free 7 page sample. Access the full version online.

Corbett Court P/L v Quasar Constructions (NSW) P/L [2008] Adj.L.R. 11/19

V Page 1 of 5

CHINA STATE CONSTRUCTION ENGINEERING CORP GUANGDONG BRANCH v MADIFORD LTD - [1992] 1 HKC 320

RETAIL CLIENT AGREEMENT. AxiForex Pty. Ltd. Level 10, 90 Arthur St, North Sydney, NSW 2060 AUSTRALIA

SUPREME COURT OF QUEENSLAND

Statutory adjudication and the standard building contract in Singapore Is the Final Payment referable to statutory adjudication?

IN THE HIGH COURT OF SOUTH AFRICA (NORTHERN CAPE HIGH COURT, KIMBELEY) JUDGMENT

Insolvent Companies s 553C

Deed of Company Arrangement

Econ Piling Pte Ltd and another (both formerly trading as Econ-NCC Joint Venture) v Shanghai Tunnel Engineering Co Ltd

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan

CHOICE OF LAW (GOVERNING LAW) BOILERPLATE CLAUSE

TRADING TERMS OF KLINGER LTD

SUPREME COURT OF QUEENSLAND

INDIVIDUAL DEED OF SURETYSHIP

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS

SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598

EMPLOYER AGREEMENT PARTIES BACKGROUND AGREED TERMS. (1) The SFA; and. (2) The Employer.

Cheshire Academies Trust Standard Terms & Conditions

Transcription:

-..". THE "PREVENTION PRINCIPLE" AND CONDITIONS PRECEDENT: RECENT AUSTRALIAN DEVELOPMENTS CORDON SMITH Partner, Baker & McKenzie, Wong & Leow, Singapore INTRODUCTION The "prevention principle" operates to invalidate a liquidated damages clause where the owner causes completion of the works to be delayed, leaving the owner to prove its damages at large, and the contractor obliged only to complete the works within a reasonable time. The exception to the operation of the prevention principle is where the contract contains a clear and specific mechanism for extending time for owner-caused delays, and the owner or contract administrator has validly extended time. I The prevention principle is founded upon the broader notion that a party cannot impose a contractual obligation if that party has prevented the other party from complying with the obligation. Lord Dennin~, in Amalgamated Building Contractors Ltd v. Waltham Holy Cross UDC, said: "... the building owner cannot insist on a condition if it is his own fault that the condition has not been fulfilled." Brooking J in SMK Cabinets v. Hili Modern Electrics Pty Ltd 3 described the prevention principle as being "grounded upon considerations of fairness and reasonableness". Many standard forms of construction contract require a contractor to give notice of an event which may entitle him to an extension of time, with the rationale being that early notice enables the owner or contract administrator to verify the claim and to monitor the event and its impact upon progress of the work." These types of clauses are to be construed contra proferentem and are generally not regarded as conditions precedent to a contractor's entitlement to an extension of time unless express and clear language is used," and there is usually a defined duty on the contract administrator to consider the contractor's entitlement to an extension whether or not the contractor has made an application to extend." More recently, some standard forms and owner's drafted contracts stipulate contractor's notices as "conditions precedent" to an extension of J Peak Construction Ltdv. McKinnry Foundations Ltd (1970) 1 BLR Ill. " [1952] 2 All ER 452 at 455, applying Roberts v. Bury Improvements Comrs (1870) LR 5 CP 310., [1984] VR 39l. 1 See, for example, Aoki Corp v. Lippoland (Singapore) Pie Ltd [1995] 2 SLR 609, per Khoo J at 615..; Bremer Handelsgesellschaft mbh v. Vanden Avenne-lzegem PVBA [1978] 2 Lloyd's Rep 109. 6 As held in London Borough. of Merton v. Leach (1985) 32 BLR 51 in relation to clause 23 of the JCT Standard Form of Building Contract 1963.

398 The International Construction Law Review,[2002 time. For example, subclause 20.1 offidic's new "Conditions of Contract for Plant and Design-Build" (1st Edition, 1999) (the New Yellow Book) requires the contractor to give notice to the Engineer "describing the event or circumstance giving rise to the claim... as soon as practicable, and not later than 28 days after the Contractor became aware or should have become aware, of the event or circumstance" ifhe considers himself to be entitled to any extension of the time for completion, and further states": "If the Contractor fails to give notice of a claim within such period of28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim." Notices of extension of time claims expressed as conditions precedent give rise to a tension between the owner's freedom to insist on conditions precedent and the prevention principle where the owner delays completion of the works and the contractor fails to comply with the notice requirements. Commentators have referred to this tension, albeit without the benefit of authority on the point, and have suggested that an owner in these circumstances may not be able to recover liquidated damages. For example, the authors of Keating on Building Contracts states: "There are, however, conceptual difficulties, it is submitted, where the event causing delay has been caused by the employer's default... There is no authority on whether the employer can in those circumstances recover liquidated damages. It is arguable that although the contractor may not be entitled to an extension of time, the employer would not be able to recover liquidated damages on the basis that he cannot take advantage of his own breach of contract." Similarly, the author of Liquidated Damages and Extension of Time in Construction Contracts states": "If an application by the contractor was a condition precedent to an extension, it would be at the option of the contractor whether or not the provisions were effective, and by choosing not to apply for an extension to cover acts of prevention the contractor could render the liquidated damages provisions inoperative." In Australia, it was thought that the courts may have been prepared to resolve the tension in favour of the owner to avoid the consequence of the owner's prohibition on recovery of liquidated damages as a result of the contractor's failure to exercise a "contractual right", as a result of the dicta of Cole J in Turner Corporation v. Austotel Pty ue: "If the Builder, having a right to claim an extension of time fails to do so, it cannot claim that the act of prevention which would have entitled it to an extension of the time for 7 FIDIC's new forms entitled, Conditions of Contract for Construction (1st Edition, 1999) (the New Red Book), and Conditions of Contract for EPC Turnkey Projects (1st Edition, 1999) (the Silver Book) are drafted in similar terms (at subclause 20.1). 8 S Furst and V Ramsey, Keating on Building Contracts (Sweet and Maxwell, 7th Edition, 2001), at p. 292. 9 B Eggleston, Liquidated Damages and Extension of Time in Construction Contracts (Blackwell Science Ltd, 2nd Edition, 1997), at pp. 163-164. 10 (1994) 13 BCL 378 at pp. 384-385.

Pt 3]_ ''Prevention Principle" and Conditions Precedent 399 Practical Completion resulted in its inability to complete by that time. A party to a contract cannot rely upon preventing conduct of the other party where it failed to exercise a contractual right which would have negated the affect [sic] of that preventing conduct." However, two recent Australian state courts have considered the very issue referred to by the commentators and distinguished Cole]'s dicta in Turner Corporation v. Austotel Pty Ltd on the facts, the combined effect of which may limit the extent to which owners can rely on the protection of conditions precedent to the contractor's entitlement to an extension of time. GAYMARKINVESTMENTSPTYLTDv.WALTER CONSTRUCTION GROUP LTD The first of these cases is the decision of Mr Justice Bailey in the Supreme Court of the Northern Territory in Gaymark Investments Pty Ltd v. Walter Construction Group Ltd." The case arose out of the construction by Waiter Construction Group Ltd (formerly Concrete Constructions Group Ltd) ("Concrete Constructions") of a hotel in Darwin during 1996 and 1997 for Gaymark Investments Pty Ltd ("Gaymark"). At arbitration of the dispute, the arbitrator found, that: (a) Concrete Constructions was delayed in completing the work, including a delay of 77 days by causes for which Gaymark was responsible, but its application for extension of time was barred because of Concrete Constructions' failure to comply with the notification requirements of the contract's extension of time clause; and (b) the 77 days' delay constituted "acts of prevention" by Gaymark, with the result that there was no date for practical completion and Concrete Constructions was then obliged to complete the work within a reasonable time (which the arbitrator found that it in fact did), with the consequence being that Gaymark was prevented from recovering liquidated damages for delay (totalling some $565,500). Gaymark appealed against the arbitrator's award under section 38 of the Commercial Arbitration Act 1984 12 on the basis, amongst other things, that the arbitrator erred in law in relation to the application of the prevention principle and that, as a consequence, Gaymark was entitled to the liquidated damages for delay. Bailey J upheld the arbitrator's award that, in the absence of strict compliance with the conditions precedent to an extension of time, and where Concrete Constructions had been actually delayed by an act, omission or breach for which Gaymark was responsible, there was no provision for an II [1999] NTSC 143. 12 S.38 of the Commercial Arbitration Act 1985 provides for a restrictive right to an appeal to the court on any question of law arising out of an arbitrator's award.

~ ---... -----~ 400 The International Construction Law Review [,2002 extension of time, and therefore Gaymark was not entitled to recover liquidated damages for delay. The contract between the parties was the Australian National Public Works Conference (NWPC) standard form of building contract, the NPWC Edition 3 (1981), amended by Gaymark in a number of substantial respects by a schedule of special conditions. The contract provided for payment by Concrete Constructions to Gaymark of liquidated damages for delay in completion of $6,500 per day, up to a maximum of $2,300,000. Significantly, Gaymark had deleted subclause GC35.4 of NWPC Edition 3 which gave the superintendent the right to extend time for practical completion at any time and for any reason, notwithstanding that the contractor had not given notice of a claim for an extension of time. Instead, Gaymark drafted a set of special conditions dealing with Concrete Constructions' entitlement to an extension of time, which included at subclause SC19.2 that: "The Contractor shall only be entitled to an extension of time for Practical Completion where:... the Contractor has complied strictly with the provisions of subcl. SC19.1 and in particular has given the notices required by subcl. SC19.1 strictly in the manner and within the times stipulated by that sub-clause." Relevantly, subclause SC19.1 provided that Concrete Constructions was obliged to give a notice of the delay to the Superintendent: "as soon as practicable and in any event not later than 14 days after the cause of delay first arose", and thereafter: "As soon as practicable and in any event not later than twenty-one (21) days after giving the notice under the preceding paragraph, the Contractor shall where it wishes to claim an extension of time, give a further notice in writing to the Superintendent stating a fair and reasonable time by which in its opinion the Date of Practical Completion of the Works should be extended... " In the Supreme Court, Gaymark argued that the arbitrator erred in law in concluding that: (1) Gaymark could have no entitlement to liquidated damages under the contract in consequence of the application of the "prevention principle"; and (2) Concrete Constructions' obligations to complete the work under the contract by the date specified in the contract had been replaced with an obligation to complete within a reasonable time (i.e. "time at large"). Gaymark relied on the dicta of ColeJ in Turner Corp Ltd v. A ustotel Pty Ltd,13 referred to above, that Concrete Constructions cannot rely upon Gaymark's preventing conduct where it failed to meet the notification requirements for an extension of time. l~ (1994) 13 BeL 378 at pp. 384-385.

)?t3f ''Prevention Principle" and Conditions Precedent 401 Concrete Constructions relied upon the prevention principle, as articulated by Salmon L] in the landmark English Court of Appeal case of Peak Construction Ltd v. McKinney Foundations Ltd 14 : "If the employer wishes to recover liquidated damages for failure by the contractors to complete on time in spite of the fact that some of the delay is due to the employer's own fault or breach of contract, then the extension of time clause should provide, expressly or by necessary inference, for an extension on account of such a fault or breach on the part of the employer." Bailey] referred to the arbitrator's interpretation of subclause SC19, and in particular, that it contained no reference to the superintendent having a power to "grant" or "allow" an extension of time. He then referred to the arbitrator's reasoning on the three possible constructions of sub clause SC19 and sub clause GC35.2, which stipulated Concrete Constructions' completion obligation as being subject to an entitlement to an extension of time. First, to imply a term similar to subclause GC35.4, giving the superintendent power to allow an extension in this situation. He thought this not possible, given the apparent care by which Gaymark had drafted SC19. Secondly, to say that "it is too bad for the contractor", that, by his own carelessness in not observing clause SC19 he has simply cost himself the right to recover delay costs, and had exposed himself to the risk of liquidated damages. The arbitrator said that the first consequence, loss of delay costs, was not an absurd result but the second consequence he considered an absurd result because it would mean that the owner would be paid for his own errors. The arbitrator said this left open only the third alternative, that Gaymark, in redrafting the extension of time provisions, was deemed to have elected to take the risk that it would not cause an actual delay to the contractor such as actually to delay the latter in achieving completion of the works, or that, if it did, that the contractor would apply for an extension within the stipulated times. Bailey] impliedly adopted the arbitrator's reasoning and distinguished the decision in Turner Corp Lid on the bases that in that case the owner had not caused the delay to the contractor achieving practical completion and that the standard form contract in that case ("Building Works Contract-]CCA 1985 with Quantities") expressly reserved a power to the architect/ superintendent to allow an extension of time, despite the loss by the builder of the right to such an extension by failure to comply with the notice provisions. He also said that the effect of Gaymark deleting sub clause GC35.4 of NWPC Edition 3 was to remove the power of the superintendent to grant or allow extensions of time. Whilst clause SC19 made provision for an extension of time for delays for which Gaymark was directly or indirectly responsible, such a right was dependent on strict compliance with the notice provisions of sub clause SC19.1. 14 (1970) 1 BLR 111 at p. 121.

402 The International Construction Law Review 1200~ ABIGROUP CONTRACTORS PTY LTD v. PENINSULA BALMAIN PTY LTD The second and more recent case is the decision of MrJustice Barrett in the New South Wales Supreme Court in Abigroup Contractors Pty Ltd v. Peninsula Balmain Pty Ltd,15 which involved a contract for the reconstruction and refurbishment of two factory buildings in Sydney by Abigroup Contractors Pty Ltd ("Abigroup") for Peninsula Balmain Pty Ltd ("Peninsula"). Abigroup made claims against Peninsula for extension of time, variations and delay costs of$4.5m, and Peninsula cross-claimed for liquidated damages for delay of an amount of $1.26m. The court referred the matter to a referee for inquiry and report. In relation to Abigroup's extension of time claim, the referee found that the superintendent extended the date for practical completion to 26 April 1999, but that there were excusable delays of77 days,and that an extension of that duration was warranted, and therefore the superintendent should have extended the date for practical completion to 5June 1999 as a consequence of delays caused by Peninsula and the superintendent. Clause 35 of the contract provided a mechanism for the con tractor to apply for an extension of time, which the referee accepted was a condition precedent, and found that Abigroup failed to follow the provision. However, the referee said that the superintendent possesses a unilateral power to extend time apart from the mechanism to be initiated by Abigroup under clause 35, and said that the superintendent should have exercised that unilateral power to give Abigroup the additional 77 days. In the Supreme Court, Peninsula argued that the referee understated its entitlement to liquidated damages by $720,000 by reason of extensions of time wrongly granted to Abigroup. Peninsula argued that because Abigroup did not comply with the contractual mechanism prescribed by clause 35, and as this was a pre-condition to an entitlement to extension, no such entitlement arose. Peninsula also argued that the referee had misunderstood the purpose of the superintendent's extending power, arguing that it was for the primary benefit of the owner and not the contractor, relying upon an extract from Hudson's Building and Engineering Contracts describing the benefits to the owner of extension of time clauses in the context of the prevention principle." BarrettJ said that he did not read the extract from Hudson as suggesting that a unilateral power of the kind in subclause 35.5 exists prima facie for the benefit or protection of one party or the other. He upheld the referee's report and adopted the referee's view that the superintendent's unilateral power to extend time under subclause 35.5 was in the nature of an entitlement to Abigroup which the superintendent was obliged to exercise. 15 [2001] NSWSC 752. 16 Hudson's Building and Engineering Contracts (Sweet and Maxwell, 11th ed., 1995), at p. 1172..""j

Pt 3]. "Prevention Principle" and Conditions Precedent 403 He concluded that in these circumstances the dicta of ColeJ in Turner CorpLtd had no application. DISCUSSION Cole js dictum in Turner Corp Ltd had been thought to allow owners carte blanche to amend their extension of time clauses to provide for the giving of notice as a condition precedent. The decisions in Gaymark and Abigroup have significance for the drafting of extension of time provisions and for the superintendent's administration of the contract. The effect of the two decisions may place a substantial fetter on conditions precedent to extensions of time. Applying the decision in Gaymark, if an owner wishes to require a contractor's notice of delay to be a condition precedent to an extension of time and still recover liquidated damages for owner-caused delays, one option is to include in the contract a provision giving the contract administrator a unilateral power to extend time similar to subclause GC35.4 referred to in Gaymark. While such a provision gives rise to some difficulties for the contract administrator as to the circumstances in which he or she should exercise the power, it at least may assist the owner in retaining its right to recover liquidated damages. On the other hand, a similarly phrased unilateral power of the superintendent to extend time contained in the contract in Abigroup was interpreted by the court as the contractor's entitlement which the superintendent was obliged to exercise. This view that the superintendent's power to extend time translates into an obligation to do so is difficult to support from the wording of subclause 35.5 referred to by the court. However, both the referee and the court may have been swayed that an alternative interpretation would lead to Peninsula being rewarded for delays which it had caused. In the light of the decisions in Gaymark and Abigroup, the condition precedent to an extension of time in subclause 20.1 of the new suite offidic forms referred to in the introduction to this article.!" if governed by Australian law, could result in the employer being prohibited from recovering liquidated damages in circumstances where the employer delays the contractor and the contractor fails to comply with subclause 20.1. 18 Employers using the new FIDIC forms under Australian law should therefore consider amending the FIDIC forms to take account of the Gaymark and Abigroup decisions. Few cases have considered the issues raised in Gaymarkand Abigroupand, as a consequence, the law is far from settled in this area. Both of the 17 Conditions of Contract for Construction (1st Edition, 1999) (the New Red Book), Conditions of Contract for Plant and Design-Build (1st Edition, 1999) (the New Yellow Book), and Conditions of Contract for EPC Turnkey Projects (1st Edition, 1999) (the Silver Book). 18 Unlike cl. 35.4 of NPWC Edition 3 (1981), there is no provision in the new suite of FIDIC forms expressly giving the engineer a unilateral power to extend time for completion.

404 The International Construction Law Review {2002 Australian courts in Gaymark and Abigroup, respectively, attempted to grapple with the balance between the owner's right to stipulate a notice of delay or claim as a condition precedent to an extension oftime and the application of the prevention principle. The consequences for owners and contractors are to consider carefully the drafting of extension of time provisions to reflect the prevention principle, while providing for the consequences of the contractor's failure to give notice where the notice is expressed as a condition precedent to an extension of time.