VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

Similar documents
Annex 2: Does the Xayaburi resettlement comply with Lao law?

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007

NAM THEUN 2: HAS THE ADB LEARNED THE LESSONS? Bruce Shoemaker Independent Researcher

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Flagship Capital Corporation

Performance Standard 5 Land Acquisition and Involuntary Resettlement

Gender Equality and Development

Guidance Note 5 Land Acquisition and Involuntary Resettlement

EBRD Performance Requirement 5

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

ASCO CONSULTING ENGINEERS PROJECT MANAGERS URBAN AND REGIONAL PLANNERS TRAINING

SOCIAL DEVELOPMENT PLAN

LAO PEOPLE S DEMOCRATIC REPUBLIC NAM THEUN 2 HYDRO PROJECT

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives

Bangladesh: Urban Public and Environmental Health Sector Development Program

Ministry of Energy and Mining. Development Bank of Jamaica. Energy Security and Efficiency Enhancement Project

Ethnic Minorities Development Framework. PRC: Guiyang Integrated Water Resources Management Sector Project

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

RESETTLEMENT POLICY FRAMEWORK. NATURAL GAS CONNECTION PROJECT IN 11 GOVERNORATES IN EGYPT (March 2014)

Lake Turkana Wind Power Project - Kenya Resettlement Policy Framework

Draft Resettlement Policy Framework

Key Words: Song Hinh Multipurpose Project, Resettlement, Project Management Board

Involuntary Resettlement Due Diligence Report

Standard Environmental and Social Obligations

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

Involuntary Resettlement Due Diligence Report

Income and Livelihood Restoration Plan. Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development

THE WORLD BANK OPERATIONAL MANUAL. Indigenous Peoples

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

Involuntary Resettlement Due Diligence Report

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS

Involuntary Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook Draft Working Document

Involuntary Resettlement Due Diligence Report

Indonesia: Enhanced Water Security Investment Project

Resettlement and Impact Assessment points of intersection

Reconstruction of the Livelihood of Resettlers from the Nam Theun 2 Hydropower Project in Laos. Bounsouk Souksavath & Mikiyasu Nakayama

Subproject: Hai Lang Province: Quang Tri

Resettlement Policy Framework

ABBREVIATED RESETTLEMENT ACTION PLAN

The Republic of Sakha (Yakutia) of the. Russian Federation. Innovative Development of Preschool Education in the Republic of Sakha (Yakutia)

MINISTRY OF COMMERCE, TRADE AND INDUSTRY

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

LAO PEOPLE S DEMOCRATIC REPUBLIC NAM THEUN 2 HYDRO PROJECT

ASIAN DEVELOPMENT BANK

Participatory Negotiation in Decision-Making of Hmong Ethnic People: The Nam Ngiep 1 Hydropower Plant Project, Lao PDR

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

Involuntary Resettlement in Lao PDR. Justin Pauly

Involuntary Resettlement Due Diligence Report

VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT

Framework Resettlement Action Plan

SOCIAL SYSTEMS BASELINE ASSESSMENT

Involuntary Resettlement Due Diligence Report

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft)

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

Involuntary Resettlement Due Diligence Report

Integrating Environmental and Social Impact Assessment into Resettlement Management: Example from NN2 Hydropower Project in Laos

Resettlement Due Diligence Report

FEDERAL REPUBLIC OF ETHIOPIAN MINISTRY OF MINES

Land Rights the New World Bank Safeguards

Managing Social Risks and Impacts in Geothermal Projects Turkey Geothermal Development Project

Indigenous Peoples Development Planning Document. IND: Assam Integrated Flood and Riverbank Erosion Risk Management Investment Program

India: Delhi Meerut Regional Rapid Transit System Project

FINDINGS AND ACTION PLANS FOR EQUIVALENCE LAND ACQUISITION/ INVOLUNTARY RESETTLEMENT. Bappenas, 9 July 2018

USJI Seminar Washington, DC (19 February 2013) Toward a New Paradigm for Resettlement Policy. Mikiyasu Nakayama

Revised Resettlement Plan Tibar-Gleno Road

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP

SRI: Local Government Enhancement Project

RESETTLEMENT ACTION PLAN (RAP)

Resettlement Policy Framework

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents

Resettlement Plan Dili-Tibar-Liquica Road

Bui Power Authority Act, 2007 Act 740

Resettlement Framework

Advantages of hydro generation: Resettlement of Indigenous Bote (Fisherman) families: A Case Study of Kali Gandaki "A" Hydroelectric Project of Nepal

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT

Guidance Note 5 Land Acquisition and Involuntary Resettlement

SRI: Local Government Enhancement Project

RESETTLEMENT ACTION PLAN

Resettlement Policy Framework

SYMBION POWER LAKE KIVU LTD.

Public Disclosure Authorized SFG3015 V1. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Technical Assistance Consultant s Report

SFG3481 V1 REPUBLIC OF RWANDA. Final Report

RESETTLEMENT ACTION PLAN (RAP) FOR THE PROPOSED RUSUMO FALLS HYDROELECTRIC PROJECT DAM & POWERPLANT COMPONENT

Activist Guide to Sinohydro s International Corporation Limited s Environmental and Social Policy Commitments

RESETTLEMENT ACTION PLAN

Nepal: Rural Reconstruction and Rehabilitation Sector Development Project

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Securing Free, Prior & Informed Consent to Resettlement. First Quantum s Cobre Panama Project

Tenke Fungurume Mining An affiliate of Freeport-McMoRan Copper & Gold

IAIA Special Symposium Resettlement and Livelihoods October Ted Pollett

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Government of the Republic of Malawi MINISTRY OF FINANCE. Malawi Social Action Fund MASAF 4- Strengthening Safety Net Systems in Malawi

COVER NOTE Tanzania Energy Development and Access Project (TEDAP) Safeguard Documents

EG-Giza North Power Project (P116194)

Transcription:

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE PROJECT LANDS COMPONENT OF THE NT2 PROJECT...3 1.4 PRINCIPLES, OBJECTIVES AND LAYOUT OF PLAN...6 List of Figures Figure 1-1: Project Location & Key Infrastructure...2 Figure 1-2: Map of Project Land Areas (not including Transmission Lines), Subject to Revision as Detailed Design Progresses...4 Figure 1-3: Map of Transmission Line Project Lands, Subject to Revision as Design Progresses...5 March 2005 Nam Theun 2 Project Social Development Plan i

1 PROJECT DESCRIPTION 1.1 THE NT2 PROJECT A full Project Description is provided in Volume 1, Chapter 1 of the SDP, and Chapter 2 of the EAMP. The Nam Theun 2 (NT2) hydroelectric scheme in Khammouane, Bolikhamxay and Savannakhet Provinces in central Laos involves constructing a dam on the Nam Theun River, and the creation of a 450 square kilometre reservoir on the Nakai Plateau (See figure 1-1). Water from the reservoir will be diverted into a tunnel excavated in Phu Ark escarpment, and drop about 350 meters to the turbines located in a Powerhouse at the foot of the escarpment. Immediatly below the Powerhosue, a Regulating Pond/Dam will regulate flows into the Xe Bangfai (XBF) River through a 27 kilometre, purpose-built downstream channel. The Project will also construct Transmission Lines to Thakhek and the Thai border at Savannakhet build or upgrade 150 km. of roads, and establish a number of rock quarries and spoil deposit sites. The NT2 Project is a Build Own Operate Transfer (BOOT) scheme to be developed by the Nam Theun 2 Power Company (NTPC), a limited company registered under Lao law. Major shareholders are the Lao Government (25% equity), EDF International (35% equity), EGCO of Thailand (25% equity), and Italian- Thai Development Public Company (25% equity). NT2 will generate an estimated USD 235 million gross annual revenues from the sale of electricity to Thailand. During the 25 year concession period, GOL will receive an average of USD 80 million a year from taxes, royalties and dividends, a large proportion of which will be used for poverty alleviation programs nationwide. NT2 will also fund the management of the globally important Nakai Nam Theun Protected Area which forms the watershed area of the NT2 Project. 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT The construction and operation of the NT2 Project will result in impacts, both beneficial and adverse, to the biophysical, socio-economic and cultural environments of the Project Area. As the NTPC and GOL are committed to meeting the World Bank s and Asian Development Banks economic, social and environmental standards (as set out in the Safeguard Policies described Appendix B of Volume 1) the Project has identified three main areas of social impact in which it will either mitigate, or will ensure effective livelihood restoration and/or compensation for persons (Project Affected Persons PAPs) impacted by the Project, as follows: i. Reservoir Area on the Nakai Plateau Prior to reservoir inundation, about 1,127 households will be relocated from 17 plateau villages. 15 will be relocated within the plateau itself, on the southern edge of the new reservoir, and 2 relocated some 25 kms to the north. A variety of agriculture, forestry and fishery livelihood programmes will be supported and developed for these affected persons. ii. iii. Project (construction) Lands The acquisition of Project Lands for the construction of Project components will result in the loss of land and assets, and also some disturbance or temporary land acquisition, and all impacted person will receive compensation by way of cash (for those experiencing small impacts), in-kind (land for land etc) or livelihood restoration. Downstream (of the Power Station) and the XBF Communities downstream of the Power Station, along the XBF (and to some extent on the Nam Kathang/Nam Gnom), and downstream of the Nam Theun Dam, and in other down or upstream areas, will experience varying degrees of impact on their livelihoods and infrastructure due to changes in the hydrological regime, water quality and river-bank erosion patterns. March 2005 Nam Theun 2 Project Social Development Plan 1

Figure 1-1: Project Location & Key Infrastructure March 2005 Nam Theun 2 Project Social Development Plan 2

1.3 THE PROJECT LANDS COMPONENT OF THE NT2 PROJECT This Project Lands Resettlement Plan has been prepared to address the social and economic impacts of the need to transfer land use rights to the NTPC (and its contractors) for the construction and operation of the NT2 Project. Thus, 66 parcels of land will be leased to the NTPC on which to build project facilities, and such land has been termed "Project Lands". These Project Lands include areas required for the construction of the Nakai Dam, the Nakai saddle dams, the headrace channel, the power conduit intake structure, the Powerhouse, the Regulating Pond and Dam, Residence Nam Theun, the proposed quarry areas, the construction work camps, as well as corridors for the 500 kv transmission line, the 115 kv transmission line, the downstream channel, and for all roads to be upgraded or constructed. The location of these Project Lands areas is shown in Figure 1-2 and Figure 1-3. The acquisition and either temporary or permanent use of land for construction and operation will result in impacts including disturbance, and temporary or permanent loss of land and assets, all of which will require compensation to those AP s/pap s who may be owners and/or users of the impacted land and assets. Compensation will include asset purchase or cash compensation, direct replacement of land or asset in another location, or restoration of livelihoods or incomes impacted. While not providing a list of these Project Lands required, the Concession Agreement of October 2002 (Annexes A, B and C) does provide maps of Project Lands granted by the GOL to the NTPC in which to choose to construct and locate its facilities. GIS analysis of these maps reveals that the total area granted as either Category 1 or Category 2 land is about 11,000 ha. However, much of this area, and many of the Project Lands map in the CA, are actually corridors within which the Company may choose to build infrastructure or have right of way access. Thus, while the actual area required for construction is somewhat less (than the CA Maps), the precise location and requirement of land will only be known progressively, up until Financial Close (May 2005). It is envisaged that as the exact requirement (in terms of location, and dimension) for each Project Land is finalised, an updated resettlement plan or a series of plans, with includes land acquisition and compensation agreements with PAP s will be developed and reviewed by the Company and the GOL, and then submitted to the IFIs, after which formal approval and payment of compensation or implementation of livelihood rehabilitation programs will be undertaken. In addition, not all Project Lands will impact villagers or communities. Of the 66 Project Lands, there are 38 which have PAP impacts, and 28 which have no impacts on PAPs (these either impacting GOL forests, or are merely upgrading of existing roads). Of the 38 with PAP impacts, 13 have medium to high impact and 18 have low impacts on PAP. A further 8 have low to medium impacts of the Resettlement Area forests. March 2005 Nam Theun 2 Project Social Development Plan 3

Figure 1-2: Map of Project Land Areas (not including Transmission Lines), Subject to Revision as Detailed Design Progresses. March 2005 Nam Theun 2 Project Social Development Plan 4

Figure 1-3: Map of Transmission Line Project Lands, Subject to Revision as Design Progresses. March 2005 Nam Theun 2 Project Social Development Plan 5

1.4 PRINCIPLES, OBJECTIVES AND LAYOUT OF PLAN This Project Lands Resettlement Plan reflects IFIs policy on involuntary resettlement, which has the following objectives: (i) to avoid involuntary resettlement wherever feasible; (ii) to minimize resettlement where population displacement is unavoidable by choosing alternative viable project options; and (iii) where involuntary resettlement is unavoidable, to ensure that affected people receive assistance, preferably under the project, so that they will be at least as well off as they would have been in the absence of the project. Where involuntary resettlement is unavoidable, the policy is designed to include any resulting losses in project budgets. The policy treats involuntary resettlement as a development opportunity and allows planners to manage impoverishment risks and turn the people dispossessed or displaced into project beneficiaries, particularly the poor and vulnerable, who may be disproportionately affected by resettlement losses 1. The NT2 Project's approach to the acquisition of land and assets under Project Lands, and the drafting and implementation of this Resettlement Plan has relied on the following principles: Acquisition of land and other assets, and the resettlement of people will be minimized as much as possible 2 ; and all viable alternative project designs will be explored to reduce unnecessary land acquisition or resettlement; Where it is not feasible to avoid land acquisition or resettlement, activities will be conceived and executed as sustainable development programs, providing sufficient investment resources to enable the persons displaced by the project to share in project benefits. Displaced persons will be meaningfully consulted and have opportunities to participate in planning and implementing resettlement programs. Affected or displaced persons will be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. According to the ADB 3, a full resettlement plan should address the following issues: organizational responsibilities; community participation and disclosure arrangements; findings of the socio-economic survey and social and gender analysis; legal framework, including eligibility criteria and an entitlement matrix; mechanisms for resolution of conflicts and appeals procedures; identification of alternative sites and selection; inventory, valuation of, and compensation for, lost assets; landownership, tenure, acquisition, and transfer; access to training, employment, and credit; shelter, infrastructure, and social services; environmental protection and management; 1 ADB OM Section F2/BP issued on 29 October 2003, page 2. 2 Such minimization has already been seen in the case of Phou Pakho quarry (PL1) and Residence Nam Theun (PL36), two Project Lands part of the PCA (Preliminary Construction Activities). In these areas, the contractors have significantly decreased the areas they require, in comparison to both the Concession Agreement areas and to the HC's original plans for land requirement. The reason for such a decrease in the area required was to minimize impacts on local villagers land and assets. This minimization of land required can be effected for a significant number of the Project Lands. Transmission Lines and access roads are also being aligned to avoid residential areas and productive lands 3 ADB OM on Involuntary Resettlement (OM Section F2/OP, issued on 29 October 2003), page 6. March 2005 Nam Theun 2 Project Social Development Plan 6

monitoring and evaluation; a detailed cost estimate with budget provisions; and an implementation schedule, showing how activities will be scheduled with time-bound actions in coordination with the civil works. This Project Land Resettlement Plan has thus been drafted to comply with these requirements. ********** * * * ********** March 2005 Nam Theun 2 Project Social Development Plan 7