UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Notice of Proposed Rulemaking ) Grid Resiliency Pricing Rule ) RM

Similar documents
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Grid Reliability and Resilience Pricing ) RM

135 FERC 61,167 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability Corporation

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

BILLING CODE P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission. 18 CFR Part 33. [Docket No. RM ]

155 FERC 61,278 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts 375 and 388. [Docket No. RM ]

152 FERC 61,253 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Pacific Gas and Electric Company ) Docket No.

130 FERC 61,051 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER APPROVING RELIABILITY STANDARD. (Issued January 21, 2010)

UNITED STATES OF AMERICA92 FERC 61,109 FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability ) Docket No. RR16- Corporation )

Case No , & (consolidated) IN THE UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. v. ) Docket No. EL

Before the FEDERAL COMMUNICATIONS COMMISSION Washington, DC 20554

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Lathrop Irrigation District ) Docket No. ER

Sandra Y. Snyder Regulatory Attorney for Environment & Personnel Safety

Case 1:16-cv JDB Document 56 Filed 01/16/18 Page 1 of 8 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Order No. 587-Y Compliance Filing, Colorado Interstate Gas Company, L.L.C.; Docket No. RP19-

JOSEPH L. FIORDALISO, ET AL., Petitioners,

Case 3:10-cv BR Document 123 Filed 11/15/13 Page 1 of 12 Page ID#: 2969

Case , Document 1-1, 04/21/2017, , Page1 of 2

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Vineyard Wind LLC ) Docket No. ER

No UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT

Rules of Procedure. Effective: May 4, 2016

ReliabilityFirst Corporation Reliability Standards Development Procedure Version 4

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. J.P. Morgan Ventures Energy ) Docket No. EL Corporation )

133 FERC 61,214 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability Corporation

Before the Federal Communications Commission Washington, D.C ) ) ) ) ) ) ) ) ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

USCA Case # Document # Filed: 07/19/2011 Page 1 of 8 [NOT SCHEDULED FOR ORAL ARGUMENT] No

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Arizona Public Service Company, Docket No. ER , Agency Agreement

An Update on Federal Matters Affecting Large Energy Consumers

No IN THE United States Court of Appeals for the District of Columbia Circuit. HO-CHUNK, INC. et al., Appellant,

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. North American Electric ( Docket No. NP Reliability Corporation (

Roles and Responsibilities: Standards Drafting Team Activities (Approved by Standards Committee July, 2011)

131 FERC 61,039 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

December 13, 2004 VIA ELECTRONIC FILING

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

A Short Guide to the Prosecution of Market Manipulation in the Energy Industry: CFTC, FERC, and FTC

FOR DISTRIGT OF COLUMBIA 9fHE UNITED STATES COURT OF URAL ELECTRIC COOPERATIVE ASSOCIATION; BASIN ELECTRIC COOPERATIVE; EAST

NERC Notice of Penalty regarding EFS Parlin Holdings LLC FERC Docket No. NP10-_-000

Case 4:16-cv ALM Document 10 Filed 10/18/16 Page 1 of 6 PageID #: 779

USCA Case # Document # Filed: 10/23/2015 Page 1 of Constitution Avenue,

CHAPTER 19. Section 311 of the Natural Gas Policy Act, Its History and Its Potential Future Role in Natural Gas Transportation

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Agenda Compliance Committee Open Session

December 28, Via Electronic Filing

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Berry Petroleum Company ) Docket No. ER _

FOR THE SECOND CIRCUIT. ALLCO FINANCE LIMITED, Plaintiff-Appellant,

US legal and regulatory developments Prohibition on energy market manipulation

September 29, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

140 FERC 61,048 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability Corporation

IN THE UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT MOTION OF AMERICAN CABLE ASSOCIATION FOR LEAVE TO INTERVENE

Case 2:16-cv NDF Document 29 Filed 03/23/17 Page 1 of 9

Before the Federal Communications Commission Washington, D.C ) ) ) ) ) ) COMMENTS OF COMPTEL

WASHINGTON LEGAL FOUNDATION

104 FERC 61,108 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 2. (Docket No. PL ; Order No.

ORAL ARGUMENT SCHEDULED: OCTOBER 17, 2017 IN THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT

EVERSeURCE. ~Ri\1~ ~-~4~O. August 21, 2015

Case 1:14-cv ADB Document 395 Filed 04/06/18 Page 1 of 10 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MASSACHUSETTS BOSTON DIVISION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) ) ) ) ) ) ) )

In the Supreme Court of the United States

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southwest Power Pool, Inc. ) Docket No. ER

Re: Petition for Appeal of GDF SUEZ Gas NA LLC D.P.U

UNITED STATES COURT OF APPEALS FOR THE EIGHTH CIRCUIT

March 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

Case 1:12-cv JDB Document 25-2 Filed 08/20/12 Page 1 of 7 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

132 FERC 61,107 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 376. (Docket No. RM ; Order No.

REPORT OF THE NUCLEAR REGULATION COMMITTEE

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ADOPTING PROTECTIVE ORDER. (Issued January 23, 2012)

Case 1:17-cv RMC Document 12 Filed 11/16/17 Page 1 of 4 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

In the United States Court of Appeals for the Third Circuit

UNITED STATES OF AMERICA 94 FERC 61,141 FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southern California Edison Company ) Docket No.

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

North American Electric Reliability Corporation (NERC) Rules of Procedure Effective in Manitoba April 1, 2012

PARTICIPANTS AGREEMENT. among. ISO New England Inc. as the Regional Transmission Organization for New England. and. the New England Power Pool.

ORAL ARGUMENT SCHEDULED FOR MAY 8, 2017 IN THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT

166 FERC 61,098 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC February 8, In Reply Refer To:

Amendments to the Commission s Freedom of Information Act Regulations

M&A REGULATORY DEVELOPMENTS AT FERC 2016 ANNUAL REVIEW. Mark C. Williams J. Daniel Skees Heather L. Feingold December 15, 2016

UNITED STATES PATENT AND TRADEMARK OFFICE BEFORE THE PATENT TRIAL AND APPEAL BOARD. CISCO SYSTEMS, INC. Petitioner v. CHANBOND, LLC Patent Owner

SETTLEMENT AGREEMENT. This Settlement Agreement is made by and between: 1) Sierra Club; and 2)

ORAL ARGUMENT HEARD ON SEPTEMBER 27, No and Consolidated Cases

47064 Federal Register / Vol. 63, No. 171 / Thursday, September 3, 1998 / Notices

Case 1:18-cv RJL Document 28 Filed 11/07/18 Page 1 of 6 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

Case 1:10-cv JEB Document 13 Filed 08/03/11 Page 1 of 2 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

February 20, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Magalie R. Salas, Secretary

150 FERC 61,212 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

ORAL ARGUMENT NOT YET SCHEDULED IN THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT

Case MFW Doc 151 Filed 12/05/14 Page 1 of 12 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE

Transcription:

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Notice of Proposed Rulemaking ) Grid Resiliency Pricing Rule ) RM18-1-000 JOINT MOTION OF THE ENERGY INDUSTRY ASSOCIATIONS IN RESPONSE TO THE SECRETARY OF ENERGY S REQUESTS FOR AN INTERIM FINAL RULE AND AN EXPEDITED TIME FRAME FOR COMMENT AND CONSIDERATION, AND MOTION FOR A TECHNICAL CONFERENCE Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission ( Commission ), 18 C.F.R. 385.212 &.213 (2016), the Advanced Energy Economy, American Council on Renewable Energy, American Petroleum Institute, American Wind Energy Association, American Public Power Association, Electric Power Supply Association, Electricity Consumers Resource Council, Interstate Natural Gas Association of America, National Rural Electric Cooperative Association, Natural Gas Supply Association, and Solar Energy Industries Association (collectively, Energy Industry Associations ) hereby respectfully submit this joint motion to the Letter from the Secretary of Energy ( Letter ) proposing that the Federal Energy Regulatory Commission ( FERC or Commission ) immediately consider and finalize the Grid Resiliency Pricing Proposed Rule ( NOPR ) in the above-captioned proceeding. 1 I. MOTION The Letter requests an aggressive time frame for consideration of the NOPR. Specifically, the Letter directs the Commission to consider and complete final action on the 1 The undersigned plan to individually submit substantive comments on the proposed Grid Resiliency Pricing Rule once it is noticed for comment. 1

NOPR within 60 days from publication in the Federal Register, or as an alternative, issue the NOPR as an interim final rule, effective immediately. In addition, the Letter suggests that the Commission allow 45 days for notice and comment on the NOPR thereby requiring the Commission to complete final action on the rule within 15 days after receiving comments and that organized markets be required to submit compliance filings within 15 days of the effective date of the rule. The Letter does not justify its suggestion that the Commission should issue an interim final rule within the narrow provision for such rules in the Administrative Procedure Act ( APA ), and as a result, the Commission should not pursue this alternative. The APA allows an agency to issue an interim final rule without first publishing a proposed rule only when it can show good cause for doing so. 2 The good cause exemption is to be narrowly construed and rarely countenanced, and is generally limited to emergency situations. 3 To demonstrate good cause, an agency must establish: the existence of an emergency; that prior notice would subvert the underlying statutory scheme; or that Congress intended to waive notice and comment rulemaking requirements. None of these circumstances exists such that the extraordinary use of an interim final rule would be justified, and the Letter does not even attempt to suggest they do. To the extent the Letter implies that an emergency exists to justify the proposed interim final rule 4 (although it provides no justification for this action whatsoever), publicly available information from the Department of Energy ( DOE ) and North American Electric Reliability Corporation ( NERC ), as well as other experts, all demonstrate that no emergency exists that 2 See 5 USC 553. 3 See Tennessee Gas Pipeline Co. v. FERC, 969 F. 2d 1141, 1144 (D.C. Cir. 1992) (citations omitted). 4 See, e.g., Jifry v. FAA, 370 F.3d 1174, 1179-90 (D.C. Cir. 2004) (approving the Federal Aviation Administration s use of an emergency interim rule regarding the suspension and revocation of pilot certificates after the September 11, 2001, terrorist attacks). 2

would justify such an action. 5 To the contrary, both DOE and NERC recently released reports categorically concluding that there is no reliability emergency. For example, DOE s 2017 Staff Report to the Secretary on Electricity Markets and Reliability recently concluded: reliability is adequate today despite the retirement of 11 percent of the generating capacity available in 2002, as significant additions from natural gas, wind, and solar have come online since then; 6 and at the FERC Reliability Conference, NERC s CEO, Gerry W. Cauley, concluded that the state of reliability in North America remains strong, and the trend line shows continuing improvement year over year. 7 The Letter also makes no attempt to argue that notice and comment would subvert the statutory scheme of the Federal Power Act, or that Congress intended for the Commission to waive notice and comment requirements for such a far-reaching rule. In light of the importance and potential implications of the NOPR for Commissionjurisdictional markets, the suggestion in the NOPR for the Commission to only allow for 45 days of public comment does not establish a reasonable and adequate time for the submission of comments in response to the NOPR. Section 403(b) of the Department of Energy Organization Act states: The Commission shall... take final action on any proposal made by the Secretary... in an expeditious manner in accordance with such reasonable time limits as may be set by the Secretary for the completion of action by the Commission on any such proposal. 8 As the time frame laid out in the Letter and NOPR for notice and comment is unreasonable on its face, the 5 See, e.g., NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION, STATE OF RELIABILITY 2017, vi (Jun. 2017) ( finding that the bulk power system provided an adequate level of reliability during 2016 ); DEPARTMENT OF ENERGY, STAFF REPORT TO THE SECRETARY ON ELECTRICITY MARKETS AND RELIABILITY, 16 (Aug. 2017) ( While markets have evolved since their introduction, they are currently functioning as designed to ensure reliability and minimize the short-term costs of wholesale electricity.... ). 6 DEPARTMENT OF ENERGY, STAFF REPORT TO THE SECRETARY ON ELECTRICITY MARKETS AND RELIABILITY, 63. 7 FERC Reliability Conference, Panel I: Overview of the State of Reliability, Remarks of Gerry W. Cauley, CEO of the North American Reliability Corporation, 1 (June 22, 2017). 8 42 USC 7173(b) (emphasis added). 3

Commission is justified in setting its own schedule for seeking comments on the NOPR, should it choose to notice it or a similar proposed rule for comment at all. This is one of the most significant proposed rules in decades related to the energy industry and, if finalized, would unquestionably have significant ramifications for wholesale markets under the Commission s jurisdiction. When agencies consider a proposed rule that could affect electricity prices paid by hundreds of millions of consumers and hundreds of thousands of businesses, as well as entire industries and their tens of thousands of workers, such as the proposal in question, it is customary (indeed, it is a statutory requirement, but for an extraordinary showing that DOE fell well short of here) for an agency to allow time for meaningful comments to be filed in the record so that the agency can make a reasoned decision thereon. In fact, agencies are under an obligation to allow a comment period of not less than 60 days for typical rulemaking proceedings, unless exceptional circumstances exist. 9 Given the importance and complexity of this issue, the Energy Trade Associations recommend that the Commission provide at least 90 days for interested parties to provide initial comments on any proposed rule, as well as affording an opportunity for reply comments, to ensure reasoned decision-making and a robust record to help inform the Commission in developing any final rule. The time frame provided in the Letter for comments is far too short to allow stakeholders to submit careful analysis on this complex and significant rulemaking, and as no emergency exists, the Commission should reject the directive from DOE to circumvent the required bare minimum of a 60-day comment period. Furthermore, in recognition of the significance of the proposed changes in the NOPR, convening a technical conference prior to the comment deadline would provide affected parties 9 Exec. Order No. 12866, 6(a), 58 Fed. Reg. 51735 (Oct. 4, 1993). 4

the opportunity to better understand key aspects of the proposed regulations and, ultimately, facilitate the submission of more meaningful comments. These reasonable steps would allow for meaningful public input from all stakeholders, including from energy market participants, grid operators and regulators and the power-consuming public, and will provide the Commission with more detailed and carefully considered comments that will help ensure that it can make a reasoned decision in this matter based on the best-available information. Finally, the Energy Industry Associations note that the other time frames set out in the Letter for consideration of the issues presented in the NOPR are wholly unreasonable and insufficient to allow for an informed consideration of the significant issues proposed therein. For instance, the Letter directs the Commission to complete a final rule 15 days after the end of the proposed comment deadline; this is patently insufficient to allow the Commission time to meaningfully consider the comments submitted and draft a thoughtful final rule. Similarly, the proposed deadline in the Letter for organized markets to submit compliance filings 15 days after the rule becomes effective is clearly inadequate time for these markets to consider, draft and file the type of major reforms contemplated in the NOPR, 10 let alone give their stakeholders time to weigh in on these filings before they are sent to the Commission. The Energy Industry Associations urge the Commission to reject the proposed unreasonable timelines and instead proceed in a manner that would afford meaningful consideration of public comments and be consistent with the normal deliberative process that it typically affords such major undertakings, should it decide to proceed with a rulemaking of this type at all. 10 Compare with Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000, 76 Fed. Reg. 49,842 (Aug. 11, 2011); FERC Stats. & Regs. 31,323, order on reh g; Order No. 1000-A, 139 FERC 61,132 (2012), order on reh g and clarification; Order No. 1000-B, 141 FERC 61,044 (2012) (providing that compliance filings were due within 18 months of the effective date of the rule). 5

II. CONCLUSION For the foregoing reasons, the undersigned Energy Industry Associations respectfully request that the Commission: deny the request for an interim final rule; initiate a technical conference; allow for at least a 90-day comment period for initial comments in this proceeding; provide for an opportunity for reply comments; and reject the expedited timeline for finalization of the rule by the Commission and compliance filings from organized markets thereto. We look forward to working with the Commission as it considers the issues set forth in the Letter and the NOPR. Respectfully submitted, Greg Wetstone Todd Foley Senior Vice President, Policy & Government Relations American Council On Renewable Energy 1600 K St., NW Washington, DC 20006 202-777-7581 wetstone@acore.org Amy L. Farrell Sr. Vice President, Government & Public Affairs Gene Grace Senior Counsel American Wind Energy Association 1501 M Street NW, Suite 900 (202) 383-2521 afarrell@awea.org Arvin Ganesan Vice President, Federal Policy Advanced Energy Economy 1000 Vermont Ave. NW, 3rd Floor Washington, D.C. 20005 (202) 380-1950 aganesan@aee.net Marty Durbin Executive Vice President & Chief Strategy Officer American Petroleum Institute 1220 L Street NW (202) 682-8400 durbinm@api.org 6

Delia Patterson General Counsel John McCaffrey Regulatory Counsel American Public Power Association 2451 Crystal Drive, Suite 1000 Arlington, VA 22202 (202) 467-2900 dpatterson@publicpower.org jmccaffrey@publicpower.org John E. Shelk Nancy E. Bagot Senior Vice President Electric Power Supply Association 1401 New York Avenue, NW, Suite 950 (202) 628-8200 NancyB@epsa.org Joan Dreskin Vice President & General Counsel Interstate Natural Gas Association of America 20 F Street, NW, Suite 450 Washington, DC 20001 (202) 216-5900 jdreskin@ingaa.org John P. Hughes President & CEO Electricity Consumers Resource Council 1101 K Street, NW, Suite 700 (202) 682-1390 jhughes@elcon.org Randolph Elliott Senior Director, Regulatory Counsel National Rural Electric Cooperative Association 4301 Wilson Blvd, Arlington, VA 22203 (703) 907-6818 Randolph.Elliott@nreca.coop Dena E. Wiggins Natural Gas Supply Association 1620 Eye Street, NW, Suite 700 Washington, D.C. 20006 Dena.Wiggins@ngsa.org Abigail Ross Hopper Solar Energy Industries Association 600 14th Street NW Suite 400 (202) 682-0556 ahopper@seia.org 7