Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore

Similar documents
Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision

Security of payment under FIDIC contracts: more secure, for now

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book

The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works

ENFORCEMENT OF DAB DECISIONS IN ARBITRATION PART I. by Giovanni Di Folco and Mark Tiggeman

Mind the Gap: Analysis of Cases and Principles Concerning the Ability of ICC Arbitral Tribunals to Enforce Binding DAB Decisions

DAAB and Dispute Resolution Under the 2017 FIDIC Forms of Contract

An Engineer s / Dispute Adjudication Board s Decision Is Enforceable By An Arbitral Award

THE ICC S NEW DISPUTE BOARD RULES. CARROLL S DORGAN Jones Day Paris

COMPARISON TABLE OF DISPUTE BOARD RULES

Staying court proceedings in favour of arbitration

Multi-Tier Dispute Resolution Clauses Definition and Examples

Follow us on and for the latest construction and energy legal updates. Contract Corner - FIDIC guidance on enforcing DAB decisions. Inside this issue:

ADR in FIDIC Contracts and the Cyprus perspective

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018

AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin. Gordon L. Jaynes 24 May 2018

FIDIC SUITE OF CONTRACTS 2017 NEW DISPUTE RESOLUTION REGIMES 21 March 2018

FIDIC contracts Claims and disputes under international construction contracts. Claims and dispute resolution procedures under FIDIC contracts

Developments in Construction Law in Singapore (2014)

CONSTRUCTION BULLETIN

CONTACT US. Background

Annual Review of English Construction Law Developments. An international perspective

Expedited arbitration and the future of international construction disputes

Quarella SpA v Scelta Marble Australia Pty Ltd [2012] SGHC 166

Emergency arbitrators: can they be useful to the construction industry?

REQUEST FOR ARBITRATION

Setting aside an international arbitration award based on deficient pleadings

Dispute Board Rules. in force as from 1 September Standard ICC Dispute Board Clauses. Model Dispute Board Member Agreement

Statute of limitation in FIDIC contracts concluded in the public procurement procedures

LIMITATIONS AND CONSTRAINTS IMPOSED BY ROMANIAN LAW ON FIDIC CONDITIONS OF CONTRACT A CONTRACTOR S DILEMMA WHILE PERFORMING PUBLIC WORKS IN ROMANIA

1) ICC ADR proceedings are flexible and party-controlled to the greatest extent possible.

Jurisdictional Issues Relating to Challenges and the New York Convention Fictions, Failures and Finality a Choice of Remedies

Arbitration Agreement

Dispute Resolution in Romania - Before and After Accession to the European Union

New Expert Rules launched by the ICC

Below are standard clauses for use by parties who wish to set up and operate a dispute board under the Rules contained in this booklet.

Chapter 10. A Note on Dispute Boards. Chapter 10

USING DISPUTES BOARDS THE ROMANIAN EXPERIENCE ON DISPUTE BOARDS

Model letters for use by the Contractor

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. Singapore

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

ARBITRATION & CONCILIATION ACT AND MEDIATION

PART 8 ARBITRATION REGULATIONS CONTENTS

Asylum Support for dependants

CASE UPDATE. Singapore Court Considers Basis To Order a Party to be Joined to an Arbitration. Introduction

NOTICE OF ARBITRATION

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:-

Quarella SpA v Scelta Marble Australia Pty Ltd

Luzon Hydro Corp v Transfield Philippines Inc

How widespread is its use in competition cases and in what type of disputes is it used? Euro-defence and/or claim for damages?

Astro v. Lippo: Singapore Court of Appeal Confirms Passive Remedies to Enforcement Available for Domestic International Awards

Let s take a peek at. - Emanuele Lancellotti - Executive Director

The 2017 ICC Rules of Arbitration and the New ICC Expedited Procedure Provisions A View from Inside the Institution

Report of the Adjudicator. Complaint number # Cited WASPA members Clickatell (Pty)Ltd (0004) All. members. Source of the complaint

Japan Arbitration Update: New JCAA Rules Comparison of Key Asian Arbitral Institutions

the governing law of the Agreement is New York law; and

REQUEST FOR ARBITRATION

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

Arbitration Act 1996

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act

Terms of Reference ( TOR ).

IN THE HIGH COURT OF JUSTICE BETWEEN GORDON WINTER COMPANY LIMITED AND THE NATIONAL GAS COMPANY OF TRINIDAD AND TOBAGO

THE NEW ENGINEERING CONTRACT FOURTH EDITION (NEC4)

CLAIMANT Systembolaget Aktiebolag, Reg. No Stockholm. RESPONDENT V&S Vin & Sprit Aktiebolag, Reg. No Stockholm

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and

Key International Arbitration Rules

ANSWER TO THE REQUEST FOR ARBITRATION [NOTE: OR ANSWER TO THE REQUEST FOR ARBITRATION AND COUNTERCLAIMS, IF

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Singapore High Court: Unravelling the unwind of accumulator contracts.

A Case Study in Litigation in Support of Arbitration: China, England, and The Turks and Caicos Islands

ALTERNATIVES TO ADJUDICATION. Toby Randle. 9 May 2005 THE SAVOY HOTEL, LONDON

IN THE HIGH COURT OF JUSTICE. Between MOOTILAL RAMHIT & SONS CONTRACTING LIMITED. And EDUCATIONAL FACILITIES COMPANY LIMITED

Conditions Precedent to Recovery of Loss and Expense Claims

Multiparty and multicontract disputes and the impact of the new International Chamber of Commerce (ICC) Rules

Enforceability of Multi-Tiered Dispute Resolution Clauses

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

FIDIC Dispute Adjudication Boards

Warrego Energy Limited Level 6, 10 Bridge Street, Sydney NSW 2000 T: E: warregoenergy.com ABN

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CHAPTER 9 INVESTMENT. Section A

ADJUDICATION: RAISING OBJECTIONS TO THE ADJUDICATOR S JURISDICTION OR BREACH OF SOP ACT AT THE EARLIEST POSSIBLE OPPORTUNITY

Resolution Institute. Policy on the Accreditation and Register of Adjudicators

CASE UPDATE. The High Court Considers the Status and Scope of an Arbitration Agreement in the Context of a Termination of the Main Contract

Arbitration from a UAE Legal Perspective

IMPORTANT NOTICE. Information that must be set out in notice of adjudication served on residential occupier.

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. France

General Assembly. United Nations A/CN.9/WG.II/WP.188

RESOLUTION. Resolution No. 1/2000 INTERNATIONAL CIVIL AND COMMERCIAL LITIGATION

This Webcast Will Begin Shortly

NOTICES, TIME BARS AND PROPORTIONALITY

Dallah and the New York Convention

Justice Committee. Tribunals (Scotland) Bill. Response from the Scottish Government to the Committee s Stage 1 Report

THIRD PARTY BENEFICIARY, INCLUDING IN THE CONTEXT OF ARBITRATION

HYDRATIGHT GROUP ANTI-BRIBERY AND ANTI- CORRUPTION POLICY 11 MAY 2016

Arbitration Rules of the Court of International Commercial Arbitration of the Chamber of Commerce and Industry of Romania

PT Tugu Pratama Indonesia v Magma Nusantara Ltd

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC)

View Esteem Sdn Bhd v Bina Puri Holdings Bhd*

ADGM COURTS PRACTICE DIRECTION 4

Transcription:

An Excellent Decision From Singapore Which Should Enhance the Enforceability of Decisions of Dispute Adjudication Boards the Second Persero Case before the Court of Appeal Christopher R Seppälä * Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore Introduction The Singapore Court of Appeal, the country s highest court, has recently issued a decision which demonstrates a complete understanding of how the disputes clause in the International Federation of Consulting Engineers (FIDIC) Conditions of contract is intended to operate. It is the best decision yet by the Singapore courts on this subject and, if followed elsewhere (as it should be), should enhance the enforceability of decisions of Disputes Adjudication Boards (DABs) around the world. The decision concerns a long-running dispute in the Singapore courts between PT Perusahaan Gas Negara (Persero) TBK, an Indonesian employer (the employer), and CRW Joint Operation, an Indonesian contractor (the contractor). The parties dispute gave rise to the following question under a contract based on FIDIC s Conditions of Contract for Construction 1999 (the Red Book ) 1 : whether and in what manner the decision of a DAB ordering the employer to make a payment to the contractor, which has been the subject of a notice of dissatisfaction from the employer under subcl.20.4 and thus been prevented from becoming final and binding, may be enforced by an arbitral award? Consideration of this question has given rise to issues about how both the Singapore International Arbitration Act (SIAA) is to be interpreted and the dispute resolution clause, cl.20, in FIDIC s construction contracts for major works produced in 1999 is to be understood. However, this article will be confined to commenting on what the Court of Appeal had to say about how cl.20 of the FIDIC contracts is * Partner, White & Case LLP, Paris, Legal Adviser, FIDIC Contracts Committee. The views expressed herein are those of the author and not necessarily those of any firm or organisation with which he is affiliated. 2015. 1 As they provide for the same dispute settlement procedure, the Singapore court s analysis is equally relevant to FIDIC s Conditions of Contract for Design-Build (Yellow Book) and Conditions of Contract of EPC/Turnkey Projects (Silver Book). 367

368 Construction Law Journal to be understood, specifically as regards to DAB, leaving to others to comment on the SIAA issue. The Court of Appeal s decisions as regards cl.20 and the DAB It will be recalled that cl.20 of FIDIC s conditions of contract for major works issued in 1999 provides for the following multi-tier procedure for settling disputes: 1) either the contractor or the employer may refer any dispute to the DAB for decision; 2) the DAB, acting as a panel of experts and not as arbitrators, must give its decision to the parties within 84 days; 3) if either party is dissatisfied with the DAB s decision (or the DAB fails to give a decision within 84 days) then either may, within 28 days, notify the other of its dissatisfaction; otherwise, the decision becomes final and binding on the parties; 4) where a party has given a notice of dissatisfaction, both parties have 56 days thereafter to attempt amicably to settle the dispute; and 5) any dispute, which has neither become final and binding, nor been amicably settled, under the preceding steps, is to be finally settled by international arbitration, the Rules of Arbitration of the International Chamber of Commerce (ICC) being specified. In 2009, an ICC arbitration tribunal with its seat in Singapore had issued, by a majority, a final award enforcing the binding but not final decision of a DAB ordering the employer to pay approximately $17 million to the contractor (the 2009 Arbitration ). Subsequently, the employer applied to the Singapore High Court to have the award set aside (Persero I). In 2010, the High Court found, interpreting cl.20, that the failure by a party to comply with a binding but not final DAB decision gave rise to a secondary dispute separate from the primary dispute that had formed the subject matter of the DAB decision (the two dispute approach). This secondary arose from the employer s failure to pay the DAB decision. As the contractor had not referred this secondary dispute to the DAB before commencing arbitration, the High Court found that the arbitrators were without power to deal with it and had exceeded their jurisdiction 2. The High Court also held that the majority of arbitrators had exceeded their jurisdiction by issuing a final award in respect of that DAB decision without first determining the correctness of the DAB s decision on the merits and, thus, set the award aside. 3 In 2011, the Court of Appeal agreed with the High Court that the majority of arbitrators had exceeded their jurisdiction by issuing a final award enforcing the DAB decision without considering the merits underlying that decision, but it did not adopt the High Court s two dispute approach. 4 In its judgment, the Court of Appeal commented obiter dicta that a binding but not final decision of the DAB was directly enforceable by an interim or partial 2 PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2010] SGHC 202; 137 Con. L.R. 69 at [31]. 3 Persero [2010] SGHC 202; 137 Con. L.R. 69 at paras [32] [36] and [43]. 4 PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2011] SGCA 33 at [66] [68].

The Second Persero Case before the Court of Appeal 369 award in an arbitration to which the merits of the DAB decision had been submitted but not by a final award in a separate arbitration, as had occurred in this case. 5 Relying on the Court of Appeal s obiter dicta, in 2011 the contractor began a second ICC arbitration, in which it sought a final determination that the employer was liable on the merits to pay the contractor the amount of the DAB decision and, pending that final determination, an interim or partial award for the sum with interest (the 2011 Arbitration ). In this second arbitration, the majority of the arbitrators held that the DAB decision could and should be enforced by an interim award. They concluded that this would give effect to the parties commercial intent in including the DAB mechanism in the conditions of the contract; otherwise the DAB mechanism would be rendered toothless. 6 Despite the interim award, the employer still refused to pay the amount of the DAB decision, instead applying to the Singapore courts to have this second award set aside as well (Persero II) which the Singapore High Court refused to do. 7 On appeal to the Court of Appeal, the employer advanced a novel argument (in addition to an argument based on the SIAA), namely, that the effect of subcl.20.4 was that the DAB decision would cease to be binding as soon as the tribunal in the 2011 Arbitration made any award on the parties underlying dispute on the merits of the DAB decision. In this case, the tribunal had made certain findings on the merits of the DAB decision by a partial award in September 2014 and the employer argued that the DAB decision thus ceased to have any binding effect as from the date of issuance of that partial award. 8 In response, the contractor argued that the commercially sensible way of reading subcl.20.4 was that the decision of the DAB only ceased to be binding upon the final determination of the parties underlying dispute over the merits of the decision, and even if there were any partial determination of the merits of the decision in the meantime, this would not affect the interim award. 9 In the course of rejecting the employer s position as not commercially sensible 10 (as the contractor had argued), the Court of Appeal addressed and resolved three important issues that have divided commentators and tribunals in relation to cl.20 until now. These issues are as follows: 1) Whether a contractor, who has obtained a non-final decision of a DAB which the employer has refused to pay, may request an arbitral tribunal to enforce that decision directly or whether the contractor must first refer the employer s non-compliance with that decision of the DAB back to the DAB as a separate dispute and thereafter to amicable settlement? 11 2) Whether, given that subcl.20.7 only provides for a failure by a party to comply with a final and binding DAB decision to be referred to arbitration directly, it is to be inferred that a failure by a party to 5 Persero [2011] SGCA 33 at [66] [68]. 6 Interim award in ICC Case No. 18272 at [49] 7 PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2014] SGHC 146; [2015] B.L.R. 119; 155 Con. L.R. 169; and see C.R. Seppälä, Singapore contributes to a better understanding of the FIDIC disputes clauses: the second Persero case (2015) ICLR 4. 8 Persero [2015] SGCA 30 at [32]. 9 Persero [2015] SGCA 30 at [35]. 10 Persero [2015] SGCA 30 at [109]. 11 Persero [2015] SGCA 30 at [63] [76].

370 Construction Law Journal comply with a non-final DAB decision may not similarly be referred to arbitration directly? 12 3) Whether a non-final DAB decision may only be enforced in an arbitration to which the dispute over the underlying merits of that decision has been submitted or whether the enforcement of that decision may be referred to a separate arbitration under subcl.20.6 and thus be the subject of a final award? 13 How the majority of the Court addressed there was a dissenting judge and resolved each of these issues is discussed below. Must a failure to comply with a non-final DAB decision be referred back to the DAB? As indicated above, the High Court in Persero I had taken the two dispute approach, that is, it had found that the failure of a party to comply with a binding but not final DAB decision gave rise to a secondary dispute that had to be referred back to the DAB before commencing arbitration. Rejecting this argument, the Court of Appeal in Persero II first asked:... what purpose can it serve to ask a DAB whether a decision which it has already issued requiring one party to make payment to the other should be promptly complied with? Why else would the DAB have issued its decision in the first place? In this regard, it bears reiteration that clause 20.4 (4) of the Conditions of Contract explicitly states that the parties shall promptly give effect [emphasis added] to a non-final DAB decision. 14 Second, the Court stated that the receiving party of the decision (that is, its beneficiary) would encounter a number of practical difficulties if it were required to refer the paying party s non-compliance with a non-final DAB decision through the steps in sub-cll.20.4 and 20.5. Among other things, there would be inordinate delay 15 in waiting for another DAB decision (for up to 84 days), then in seeing whether a notice of dissatisfaction were issued with respect to it (up to 28 days) and then in referring the matter to amicable settlement (56 days). Given the purpose and context of the DAB scheme, the Court finds that: it would not be commercially sensible to interpret clause 20 as requiring the receiving party to satisfy the conditions precedent in clauses 20.4 and 20.5 before it can refer a dispute over the paying party s non-compliance with a binding but not final DAB decision to arbitration. 16 Third, the Court finds support for its position in FIDIC s Guidance Memorandum for Users of the 1999 Red Book issued on April 1, 2013, noting quite correctly that it make[s] explicit the intentions of FIDIC that are already implicit in cl.20, 12 Persero [2015] SGCA 30 at [77] [82]. 13 Persero [2015] SGCA 30 at [83] [88]. 14 Persero [2015] SGCA 30 at [66(a)]. 15 Persero [2015] SGCA 30 at [66(b)]. 16 Persero [2015] SGCA 30 at [66(b)].

The Second Persero Case before the Court of Appeal 371 specifically that it is unnecessary to refer a failure to comply with a non-final DAB decision back to the DAB and amicable settlement before referring it to arbitration. 17 Finally, the Court notes that subcl.20.4 evinces a clear intention for parties to promptly comply with a DAB decision, irrespective of any disagreement or dissatisfaction with it. This serves the financial objective of safeguarding cash flow in the building and construction industry, especially that of the contractor, who is usually the receiving party. The intention underlying clause 20.4 would be completely undermined if the receiving party were restricted to treating the paying party s non-compliance as a breach of contract that sounds only in damages and must be pursued before the available domestic courts. 18 (emphasis in the original). Thus, the Court rejected the argument that it was necessary to refer non-compliance with the decision of the DAB back to the DAB for a further decision and then to amicable settlement. May a failure to comply with a non-final DAB decision be referred directly to arbitration? Some authors and tribunals have suggested that as subcl.20.7 provides for the referral of a failure to comply with final and binding DAB decision directly to arbitration, a failure to comply with a binding decision cannot be referred directly to arbitration for enforcement. 19 Indeed, this had been part of the reasoning of the Singapore High Court and Court of Appeal in Persero I. After reviewing the history of the incorporation of subcl.20.7 into the Red Book, the Court concluded (following what the present author had written 20 ) that subcl.20.7... was never intended to exclude a receiving party s right to seek an arbitral award in relation to a paying party s failure to comply with a binding but non-final DAB decision. 21 (emphasis in the original) Thus, a paying party s failure to comply with a binding but not final decision is itself capable of being directly referred to arbitration. 22 The present author endorses the court s conclusion. However, in a lengthy dissent, Chan Sek Keong SJ, took issue with the majority stating: While Mr Seppälä s explanation of the origin of cl 20.7 supports his argument that no inference as to the scope of the disputes referable to arbitration under cl 20.6 should be drawn from the insertion of cl 20.7 in the Red Book (in the form of cl 67.4 of the 1987 Red Book), in my view, an inference may reasonably be drawn from the long absence of cl 20.7 until 1987, namely, that disputes over non-compliance with binding but non-final DAB decisions 17 Persero [2015] SGCA 30 at [68]. 18 Persero [2015] SGCA 30 at [71]. 19 E.g. Dr Nael Bunni, The gap in sub-clause 20.7 of the 1999 FIDIC contracts for major works (2005) ICLR 272. 20 See Seppälä, Sub-clause 20.7 of the FIDIC Red Book does not justify denying enforcement of a binding DAB decision (2011) 6(3) Cons. L.I. 17. 21 Persero [2015] SGCA 30 at [82] and see Seppälä, Sub-clause 20.7 of the FIDIC Red Book does not justify denying enforcement of a binding DAB decision (2011) 6(3) Cons. L.I. 17. 22 Persero [2015] SGCA 30 at [83].

372 Construction Law Journal were not intended to be referable to arbitration. When the Red Book was first published in 1957, enforcement by an arbitral award of a DAB decision that had become final and binding (ie, where no NOD had been issued by either party) was unnecessary, or considered unnecessary, because there was a faster and cheaper way to enforce such a DAB decision namely, by way of summary judgment in court proceedings. If an arbitral award were essential for enforcement purposes, FIDIC would surely have inserted cl 20.7 in the Red Book a long time ago. Clause 20.7 became necessary or useful only when the Red Book was adopted for international building and construction contracts in foreign jurisdictions, where disputants might not wish to settle their disputes in local courts [ ] And indeed, cl 20.7 was inserted only in 1987 (in the form of cl 67.4 of the 1987 Red Book) after Mr Seppälä had drawn attention to its desirability in cases where the Red Book was used in international building and construction contracts. 23 (my emphasis) The italicised words, coupled with his earlier words that [t]he dispute resolution provisions in the 1957 Red Book were good enough for the UK building and construction industry at the time, 24 indicate that the dissenting judge believes that the Red Book was, initially at least, for use in the UK where summary judgment in court proceedings would be available. With respect, this is incorrect. As I stated in an earlier article, 25 while the first edition of the FIDIC Red Book published in 1957 had been based on a UK domestic form of contract (the Institution of Civil Engineers (ICE) Conditions), the Red Book was intended and is intended specifically for international use (indeed, FIDIC, as an international organisation, would not be publishing the form otherwise). As it was (and is) for international use there could be no assumption that a summary judgment from a local court to enforce the decision of an engineer (as the DAB only replaced the engineer in his pre-arbitral role of deciding disputes in the 1999 edition of the Red Book) would be available as might have been true in England. Nor could it be assumed that a foreign contractor, for example, would want to go into a local court, quite possibly against a local public body (as many contracts based on the Red Book are signed with states or state-owned entities), in some developing countries where FIDIC contracts are typically used. Indeed it is to assure a neutral forum for the final resolution of disputes that the Red Book provides for international arbitration. As I indicated in my article, while the draftsmen of the first edition of the Red Book had provided for international arbitration in that contract, they had apparently overlooked the fact that a foreign contractor might have no desire to proceed before a local court. This in turn had led me to propose, as the result of an experience involving the need to enforce a final and binding decision, which had gone unpaid, that the next edition of the Red Book, which was the fourth edition of 1987, make a failure to comply with such a final and binding decision referable to arbitration directly. 26 23 Persero [2015] SGCA 30 at [170]. 24 Persero [2015] SGCA 30 at [168]. 25 The dissenting judge quotes what I said in paragraph 167 of his judgment. 26 See Seppälä, The pre-arbitral procedure for the settlement of disputes in the FIDIC (Civil Engineering) Conditions of Contract (1986) ICLR 315, 334.

The Second Persero Case before the Court of Appeal 373 It also needs to be recalled that FIDIC is a federation of national associations of engineers and its contracts are drafted by engineers. Consequently, it is entirely possible, especially when the early editions of the Red Book were prepared, that limited legal attention was paid to the dispute resolution clause. It also needs to be recalled that, until the quadrupling of oil prices in the early 1970s leading to the construction boom in the oil producing countries, there was much less international construction in the world and, thus, much less use of FIDIC contracts, than today. For this reason, many drafting issues with FIDIC contracts, like this one, did not come to the surface until the 1980s and 1990s. Thus, it should not be surprising that the issues of the enforceability of a final and binding decision were not addressed until 1987 nor that the issue of the enforceability of a non-final decision has not been raised until more recently. Whether a non-final DAB decision may be enforced by a final, as well as an interim, award? The Court of Appeal rejected the position taken both by the courts in Persero I and the High Court in Persero II that all differences between the parties, whether as the result of a party s failure to comply with a binding but not final decision or as a result of the merits underlying that decision, must be submitted to the same arbitration. The Court of Appeal stated that this position: fails to adequately appreciate that an NOD issued in respect of a DAB decision is capable of covering the paying party s dissatisfaction with two aspects of the DAB decision: (a) the quantum that it is required to pay the receiving party; and (b) the need to make prompt payment of that sum [ ] The dispute over the paying party s failure to promptly comply with its obligation to pay the sum that the DAB finds it is liable to pay is a dispute in its own right which is capable of being finally settled by international arbitration. In our judgment, it is possible to refer that dispute to a separate arbitration. 27 (emphasis in the original) Consequently, a majority of the Court of Appeal found that there had been no valid ground to set aside the award of a majority of the arbitrators in the 2009 Arbitration. As the Court put it: We thus do not think that the 2009 Majority Arbitrators were wrong to proceed on the basis that the 2009 Arbitration was limited to giving prompt effect to [the DAB decision] [ ] and to turn down, on the basis, [the employer s] request that the 2009 Tribunal open up, review and revise [the DAB decision] on its merits. 28 The Court of Appeal summarised its conclusions in relation to subcl.20.7 as follows 27 Persero [2015] SGCA 30 at [83]. 28 Persero [2015] SGCA 30 at [87]. As the present author stated in an earlier article: [The Singapore] courts should have left [the award in the 2009 Arbitration] alone. See Seppälä, How not to interpret the FIDIC disputes clause: the Singapore Court of Appeal judgment in Persero (2012) 29(1) ICLR 4, 18.

374 Construction Law Journal [subcl.20.4] imposes a distinct contractual obligation on a paying party to comply promptly with a DAB decision regardless of whether the decision is final and binding or merely binding but non-final, and this obligation is capable of being directly enforced by arbitration without the parties having to first go through the preliminary steps set out in clauses 20.4 and 20.5. Further, we consider that a tribunal would be entitled to make a final determination on the issue of prompt compliance alone if that is all it has been asked to rule on, as was the case in the 2009 Arbitration. Thus, the Court of Appeal found that a non-final DAB decision may be enforced by a final, as well as by an interim, award which will be welcome news to all who, like the author, are advocates of enhancing the efficacy of the DAB. Conclusion Undoubtedly, in hindsight, the drafting of cl.20 could have been clearer and commentators and tribunals would have less likely been misled by it. But the Court of Appeal of Singapore has now, by this decision, recognised how cl.20 was always intended to operate. In arriving at its decision, the Court has displayed a rare and most commendable willingness to review and revise positions which the Singapore courts, including the Court of Appeal itself, had taken, when they are found to have been incorrect. It is to be hoped that other courts and tribunals will be guided by this decision and avoid the misreadings of cl.20 which have occurred in the past. By doing so, they will also be promoting the DAB which has become the preferred method for resolving disputes (that is, preferred to the engineer s decision, or international arbitration) in the international construction industry.