Getting ready for Ontario s new Construction Act. Understanding the key changes and how to prepare for them. Howard Krupat

Similar documents
A Summary of Bill An Act to Amend the Construction Lien Act

The Construction Act of Ontario

SEPTEMBER 2016 OVERVIEW BRIEFING STRIKING THE BALANCE. Bruce Reynolds Counsel and Sharon Vogel Co-Counsel

2ND SESSION, 41ST LEGISLATURE, ONTARIO 66 ELIZABETH II, Bill 142. An Act to amend the Construction Lien Act. The Hon. Y. Naqvi Attorney General

DISPUTE RESOLUTION IN THAILAND: LITIGATION

FORM 31 LABOUR AND MATERIAL PAYMENT BOND UNDER SECTION 85.1 OF THE ACT Construction Act

FORM 32 PERFORMANCE BOND UNDER SECTION 85.1 OF THE ACT Construction Act

Overview of the Builders Lien Act

Model letters for use by the Contractor

Resolution Institute. Public consultation: Proposed reforms to the NSW Building and Construction Industry Security of Payment Act 1999

ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL

AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

The How and Who of Adjudication

ADR INSTITUTE OF CANADA, INC. ADRIC ARBITRATION RULES I. MODEL DISPUTE RESOLUTION CLAUSE

Construction Industry Security of Payment Legislation. Development Bureau

CHAPTER Council Substitute for House Bill No. 1157

HOPING FOR THE BEST, PREPARING FOR THE WORST

Special Provisions. Special Instructions to Bidders. Instructions to Bidders. General Conditions

THIS INDEPENDENT ENGINEER'S AGREEMENT (this Independent Engineer's Agreement) is made on [ ]

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018

SAMPLE TENDER DOCUMENTS REQUEST FOR TENDER # 2018-XXX. Contract # XXXX-XXXX #Project Name #Project Limits #Project Description

U.S. TRADE AND DEVELOPMENT AGENCY

Building and Construction Industry Security of Payment Act 1999 No 46

08 LC A BILL TO BE ENTITLED AN ACT

Construction Law: Recent Developments of Importance

City of Toronto Public Appointments Policy

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

SUMMARY OF CHANGES COMMERCIAL ARBITRATION RULES

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

Register, 2014 Commerce, Community, and Ec. Dev.

Unit 5 : ADJUDICATION

Request for Proposal. Physical Security Professional Review. ASIS Chapter Calgary / Southern Alberta

Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes)

DRAFT. OCE Funding Agreement

Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005.

CANADIAN COUNCIL OF MINISTERS OF THE ENVIRONMENT INC. (CCME)

CRITERIA FOR CHOOSING BETWEEN CONSENSUS DOCS AND AIA BOND FORMS. I don't want no ConsensusDOCS bond form or do I???

STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS. 1. Application

NOTICE OF REQUEST FOR PROPOSALS FOR ARCHITECTURAL AND RELATED SERVICES. This is a REQUEST FOR PROPOSAL by UMATILLA SCHOOL DISTRICT

Chapter 36 Mediation and Arbitration 2013 EDITION Declaration of purpose of ORS to

Building and Construction Industry Security of Payment Act 1999

CONSULTANCY SERVICES AGREEMENT

Statutory Instrument 1998 No The Scheme for Construction Contracts (England and Wales) Regulations 1998

SCHEDULE 2 OF BYLAW 7900 CITY OF KELOWNA SERVICING AGREEMENT

Introduction to the A-BBPP Draft Program Agreement December 19, 2017 updated January 8, 2018

REPUBLIC OF SOUTH AFRICA

Bill 47, The Making Ontario Open for Business Act, 2018 What does it do to Labour & Employment Laws in Ontario? BACKGROUND

5(16) General Policy for Advisory Committees. 1. Role Of Advisory Committees

GENERAL TERMS AND CONDITIONS FOR REQUEST FOR BEST VALUE PROPOSALS (RFP) #852G002

C. Public-private partnership construction contracts. (a) Definitions for purposes of this section: (1) Construction contract.

STANDARD TERMS AND CONDITIONS FOR TENDERS, PROPOSALS, CONTRACTS AND QUOTATIONS

EXHIBIT F-1 (I) FORM OF DESIGN-BUILD LETTER OF CREDIT VIRGINIA DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VA ATTN: [ ]

STANDARD TERMS AND CONDITIONS

PURCHASING ORDINANCE

LES MAISONS CO-OPERATIVE ST. JACQUES PHASE 2 INVITATION TO TENDER (ITT) # ACCESSIBILITY IMPROVEMENT FEATURES

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS

CITY ATTORNEY MODEL RETAINER AGREEMENT. By and Between THE CITY OF ******* and **************

AGREEMENT WITH BUILDER. NAME or COMPANY NAME: ADDRESS:

THE BOROUGH OF EAST RUTHERFORD REQUEST FOR QUALIFICATIONS

CONSOLIDATION OF BY-LAW NO. 1 AND BY-LAW NO. 2 OF OMBUDSMAN FOR BANKING SERVICES AND INVESTMENTS/ OMBUDSMAN DES SERVICES BANCAIRES ET D INVESTISSEMENT

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION EDITION

Arbitration Rules of the Court of International Commercial Arbitration of the Chamber of Commerce and Industry of Romania

TOWN OF HERNDON, VIRGINIA ORDINANCE DECEMBER 13, 2016

ALBRO COURT HOUSING CO-OPERATIVE INVITATION TO TENDER (ITT) # BATHROOMS

LEASE ADMINISTRATION SERVICES AGREEMENT

LITIGATION ATTORNEY-CLIENT FEE AGREEMENT

9/13/2013 gerard o sullivan Mulcahy McDonagh & Partners 1

National Patent Board Non-Binding Arbitration Rules TABLE OF CONTENTS

Superior Court of Justice (Ontario) NEW CIVIL CASE MANAGEMENT PILOT FOR TORONTO REGION: RULE 78 CASES. By Regional Senior Justice Warren K.

RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017

FUTURESTAR SPORTS SERVICE AGREEMENT. THIS FUTURESTAR SPORTS AGREEMENT (the "Agreement") dated. (The "Client") - AND -

Introductory Guide to Civil Litigation in Ontario

SUPPLY OF SERVICES AGREEMENT GUIDANCE NOTE AND TEMPLATE SUPPLY OF SERVICES AGREEMENT

AGREEMENT. by and between the CITY OF LOS ANGELES. and ERNST & YOUNG INFRASTRUCTURE ADVISORS, LLC. for the DOWNTOWN LA STREETCAR PROJECT

Janata Bank Limited T E N D E R D O C U M E N T FOR THE PROCUREMENT OF

BY-LAW NUMBER tj OF 2012 OF THE CITY OF SARNIA

AMENDED AND RESTATED STANDBY GUARANTEED INVESTMENT CONTRACT. by and among RBC COVERED BOND GUARANTOR LIMITED PARTNERSHIP. as Guarantor LP.

31 USC NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES)

Political Financing Handbook

COMPILATION OF THE ACQUISITION REGULATION OF THE PANAMA CANAL AUTHORITY 1

COLLIER COUNTY SHERIFF S OFFICE Standard Contract Provisions

Minority and Women Business Enterprise Program

Independent Arbitration Scheme for the Chartered Institute of Management Accountants (CIMA)

Chapter Four Transfer and Loss of the Rights Associated with the Mark Article 26 Article 27 Article 28

Request for Proposal. RFP # Non-Profit, Sports Photography

FINAL SUPPLY CHAIN SOLUTION LTD TERMS AND CONDITIONS FOR THE SUPPLY OF LOGISTICS SERVICES

Toronto Municipal Code Chapter 140, Lobbying

Whereas the Recipient intends to participate in the Comprehensive Study in relation to the Project;

RENTAL HOUSING AMENDMENT BILL

The 2017 ICC Rules of Arbitration and the New ICC Expedited Procedure Provisions A View from Inside the Institution

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE

PUBLIC PROCUREMENT AND CONCESSIONS REGULATIONS

AGREEMENT FOR PHYSICIAN SERVICES RECITALS. B. The District owns and operates Hospital in, Washington (the "Hospital");

CHAPTER Senate Bill No. 1960

Schedule "A" OPERATING CHARTER NOVA SCOTIA APPRENTICESHIP AGENCY July 1, 2014

Elements of a Civil Claim

Reinforcing Security of Payment in NSW

Sharon Doner, Manager of Civil Law Division, Polk County Clerk of Courts

Transcription:

Getting ready for Ontario s new Construction Act Understanding the key changes and how to prepare for them Howard Krupat

Getting ready for Ontario s new Construction Act Understanding the key changes and how to prepare for them APR 2019 By: Howard Krupat 1 Overview Industry observers in the Province of Ontario are now well aware of the scope of the changes introduced through the amendments to the old Ontario Construction Lien Act, giving us what is a dramatically different piece of legislation the Construction Act. However, becoming familiar with these significant changes and implementing them in practice are two very different undertakings. With prompt payment and adjudication now around the corner, a refresher is therefore in order. For ease of reference, it is convenient to divide the Construction Act changes into two buckets: 1. the lien modernization provisions; and 2. prompt payment and adjudication. In addition, it is important to remember that subject to the application of the Construction Act s transition provisions, the lien modernization provisions took effect on July 1, 2018, while the prompt payment and adjudication provisions take effect on October 1, 2019. This variation in timing alone will require your organization to pay close attention to the implementation of the Construction Act. It is equally important to understand that the transition provisions mean that we will concurrently have: (a) contracts governed by the old Construction Lien Act; (b) contracts governed by the lien modernization provisions; and (c) contracts governed by both the lien modernization provisions and the prompt payment and adjudication provisions. How do the transition provisions work? Sorting out which version of the Construction Act applies to a particular construction contract requires a careful analysis. The key factors are as follows: 2 1. The old Construction Lien Act will apply where: a. a contract 3 for the improvement 4 was entered into before July 1, 2018; or b. a procurement process 5 for the improvement was commenced before July 1, 2018 by the owner. 2. If neither of the above conditions is met, the lien modernization provisions will apply; and 1 Howard leads DLA Piper s Canadian construction disputes practice and served on the Province of Ontario s Advisory Committee for the review of the Construction Lien Act. 2 See Section 87.3 of the Construction Act for a full understanding of how the transition provisions work. 3 For the purpose of the Construction Act, a contract is an agreement entered into directly with a project owner for an improvement (which is, very loosely, the Construction Act s term for a construction project). 4 See above. 5 The Construction Act includes a very specific definition of a procurement process. It means: (a) a request for qualification; (b) a request for quotation; (c) a request for proposals; or (d) a call for tenders (Section 1(4)). 1

3. If a procurement process is not commenced until after October 1, 2019, or a contract that does not involve a procurement process is entered into after October 1, 2019, both the lien modernization provisions and the prompt payment and adjudication provisions will apply. Refresher: The lien modernization provisions The lien modernization provisions are detailed and technical in nature, so there is no pithy way to capture them in a short paragraph. However, the key revisions include the following: 1. the deadline to preserve a construction lien has been increased from 45 days to 60 days from the applicable trigger date; 2. the deadline to perfect a lien by commencing an action has been increased from 45 days after the last date the lien could have been preserved to 90 days after the last date the lien could have been preserved; 3. holdback release is now mandatory unless the payer first publishes, within the time prescribed by the Construction Act, a notice specifying the amount the payer refuses to pay; 4. provided the proper contractual arrangements are in place and the threshold contract price prescribed by regulation is met, holdback will be permitted to be released either on an annual basis or on a phased basis, for appropriate projects; 6 5. permissible forms of holdback include a letter of credit or holdback release bond, in a prescribed form; 6. termination of a contract is formally recognized as one of the trigger dates to be considered in determining the applicable construction lien deadline. Further, where a contract is terminated, a notice of termination is required to be published in a form prescribed by the Construction Act regulations; 7. landlords who provide tenant inducements under a lease have exposure to construction lien claims, to a maximum of ten percent of the value of the inducement; 8. the formulas for calculating both substantial performance and completion of a contract have been modified to account for inflation since the Construction Lien Act was implemented in 1983; 9. the maximum amount of costs required to be posted to vacate a construction lien has been increased from $50,000 to $250,000, in addition the amount of the lien itself; 10. rigorous accounting requirements have been implemented for trust funds received by a contractor or subcontractor on a project to ensure that all such funds can be traced (although dedicated project accounts will not be necessary). Further, it is specifically noted that the depositing of funds into a single account in accordance with the applicable provisions does not constitute a breach of trust; 11. as of October 1, 2019, construction liens for municipal projects will be required to be served rather than registered, as is presently the case for projects owned by the Provincial Crown; 7 6 As of the date of this paper, the minimum contract price, as prescribed by regulation, is $10,000,000. However, pursuant to s. 26.2(3) of the Construction Act, this threshold requirement is not a prerequisite for contracts permitting holdback release on a phased basis where it is only a specified design phase at issue. 7 Note that this is an exception to the July 1, 2018 date upon which most of the lien modernization provisions took effect. 2

12. specific accommodations have been made to fit project structures commonly known as alternative financing and procurement (AFP) or public-private-partnership (P3) projects more clearly into the Construction Act, with deeming provisions establishing which contracts within the P3 structure are to be used for determining, among other things, holdback obligations, substantial performance and lien rights; and 13. a significant change that doesn t really fall within the lien modernization category provides that contracts for public projects which exceed a value prescribed by regulation require both a performance bond and a labour and material payment bond. 8 As a practical matter, the foregoing can be reduced even further into the following key elements: (a) the critical and unforgiving deadlines for which construction liens are known have changed and the new deadlines must be understood; (b) there are important new requirements and forms that must be followed and used with respect to contract and holdback administration and the enforcement of lien rights; (c) there is an onus on contractors and subcontractors to ensure they are in compliance with strict new accounting obligations; and (d) almost all public contracts require both performance and labour and material payment bonds. 9 While the lien modernization provisions are essential to understand from an operational perspective, the impact they will have on contract drafting is likely limited, particularly when taking into consideration that all contracts and subcontracts are deemed to be amended as may be necessary to conform to the Construction Act. However, the same argument is unlikely to present a workable practical approach to contract drafting in the context of prompt payment and adjudication. First, many existing forms of contract have detailed provisions addressing both payment requirements and dispute resolution provisions. Leaving these provisions in place on the basis that these contracts will be deemed to conform to the Construction Act will only create confusion. Second, there are certainly strategies that industry participants at all levels of the construction pyramid will wish to employ in drafting and negotiating contracts to manage the new processes and risks introduced by prompt payment and adjudication. Any organization considering how it is going to handle the prompt payment and adjudication amendments from the perspectives of contract negotiations, contract administration, operations and dispute resolution will first need to have an understanding of what these changes entail. Refresher: Prompt payment and adjudication Prompt payment and adjudication are, to a certain extent, directly linked. Although adjudication will capture much more than payment disputes, adjudication can also be considered the teeth for ensuring compliance with the pending prompt payment requirements. 8 The current contract price threshold has been set at only $500,000. Importantly, the requirement for bonds does not apply to either architecture or engineering contracts. 9 This requirement is qualified for P3 projects. 3

The essence of the prompt payment provisions is a set of statutory deadlines for payments on construction projects, all built around the submission by a contractor to an owner of a proper invoice. The Construction Act prescribes the minimum information that a proper invoice must include, leaving it to the parties to add additional requirements, provided that these contractual requirements do not conflict with the legislation. In addition, the Construction Act crucially permits parties to agree within their contract upon the schedule for the submission of proper invoices but notably also prescribes a default requirement for proper invoices to be submitted monthly if the contract doesn t state otherwise. This means, for example, that it is open to parties to incorporate a milestone schedule for the delivery of proper invoices into their contract. Again, however, if there is no contractual schedule for the delivery of proper invoices, the parties will be stuck with the monthly schedule prescribed by the Construction Act. On the other hand, there is no freedom to contract out of the deadlines that flow down the construction pyramid for payment once a proper invoice is delivered. Subject to the right to deliver a notice of non-payment, as depicted in the graphics below, payments must be made within the prescribed deadlines. Even a contractual provision that makes the giving of a proper invoice contingent upon payment certification or the prior approval of an invoice by an owner is prohibited by the Construction Act. 10 The following graphics show the basic operation and statutory deadlines for prompt payment: Tier One Contractor 11 and Owner Contractor* submits "proper invoice" to Owner Owner does not dispute proper invoice Owner disputes all of proper invoice Owner disputes part of proper invoice Owner must make payment within 28 days of receipt of proper invoice Owner must provide notice of non-payment within 14 days of receipt of proper invoice Owner must provide notice of non-payment of amount disputed (within 14 days) and pay balance remaining (within 28 days) 10 This prohibition does not apply to P3 projects. 11 Under the Construction Act, Contractor means an entity contracting directly with the Owner, including through an agent. A Contractor therefore includes a design consultant hired directly by the Owner. 4

12 13 Tier Two - Contractor* and Subcontractor Contractor* submits "proper invoice" to Owner Contractor receives full payment from Owner Contractor is not paid by Owner and receives notice of non-payment from Owner Contractor receives partial payment from Owner Contractor must make payment to subcontractor within 7 days of being paid by Owner OR deliver notice of non-payment to subcontractor within 35 days of delivering proper invoice to Owner Contractor's options: (i) deliver notice of nonpayment to subcontractor wihtin 7 days of receipt of notice of non-payment from Owner and undertake to refer the matter to adjudication within 21 days of giving notice; OR (ii) pay subcontractor within 35 days of delivering proper invoice to Owner Contractor's options: (i) pay from amount received within 7 days of being paid by Owner, deliver notice of non-payment for the balance to subcontractor within 7 days of receipt of notice of non-payment from Owner and undertake to refer dispute with Owner to adjudication; OR (ii) pay from amount received within 7 days of being paid by Owner and pay subcontractor balance (even if not recieved from Owner) within 35 days of delivering proper invoice to Owner; OR (iii) deliver notice of non-payment to subcontractor for entire amount within prescribed deadlines 12 Prompt payment continues to apply to each tier of the construction pyramid. The Act should therefore be consulted for the deadlines applicable at each tier. For example, a subcontractor who receives full payment from a Contractor in respect of a proper invoice is required to pay its own subcontractor or supplier within 7 days of receipt of payment or, if it chooses not to pay, must deliver a notice of non-payment within 42 days of the date the proper invoice was given to the Owner. If a subcontractor has received a notice of non-payment from the Contractor, it must deliver its own notice of non-payment within 7 days of receiving the notice from the Contractor or otherwise must pay its own subcontractor or supplier within 42 days of the date the proper invoice was given by the Contractor to the Owner. If a subcontractor chooses not to pay its own subcontractor based upon receipt of a notice of non-payment, it must refer the matter to adjudication within 21 days of giving the notice of non-payment. 13 Note that, in addition to required referrals to adjudication in the event of a notice of non-payment, any party to a contract or subcontract is entitled to refer a dispute to adjudication, including any disputes arising from non-payment under the prompt payment rules. 5

Holdback It is also useful in reviewing the prompt payment timelines to demonstrate how the new holdback deadlines in the owner/contractor relationship under the lien modernization provisions fit into the picture, using for simplicity a scenario where the applicable holdback trigger date is the publication of a certificate of substantial performance (as opposed to the trigger dates that are applicable where there is no certificate of substantial performance or where these events come earlier than substantial performance - being completion, abandonment or termination of the contract): Publication of Certificate of Substantial Performance No liens preserved within 60 days or any preserved liens are discharged, satisfied or otherwise provided for in accordance with the Construction Act Owner publishes notice of nonpayment of holdback within 40 days and does not release holdback to Contractor Each payer on a contract or subcontract shall release basic holdback Contractor may refuse to pay subcontractor, in which case the Contractor must refer the matter to adjudication and notify all subcontractors whom it is required to pay that holdback is being withheld and the matter is being referred to adjudication A failure to abide by the prompt payment provisions triggers various remedies, including the requirement to pay a prescribed rate of interest and the potential referral of the dispute to adjudication. Notably, if the basis for a contractor deciding not to pay its subcontractor is the contractor s receipt of a notice of non-payment from the owner, or if the basis for the contractor refusing to release holdback to the subcontractor is the receipt of a notice of non-payment of holdback from the owner, then the contractor is required to refer its dispute with the owner to adjudication. 6

The Construction Act s new adjudication process, described below, is anticipated to have a sweeping impact upon the way typical construction contract disputes are resolved. Further refresher: Adjudication Adjudication is essentially an interim dispute resolution process that is binding upon the parties. The outcome of adjudication is a determination made by the appointed adjudicator. Subject to the very limited ability to have the adjudicator s determination set aside through a judicial review process, the parties must then abide by that decision and carry on with the project. Should either party wish to re-litigate the issue through a court action or arbitration down the road, they are entitled to do so. However, one of the objectives for the Construction Act changes is for such a scenario to be rare. The following is an updated summary of the adjudication process that was included in my September 2017 bulletin on this topic: 1. a party to a contract or subcontract may refer to adjudication a dispute with the other party to that contract or subcontract; 2. matters may only be adjudicated by a person who has been identified as a qualified adjudicator by an entity called the Authorized Nominating Authority ( ANA ), a body which will be designated by the Ontario government. As set out in the current regulations, adjudicators will come from a broad range of fields of expertise within the construction industry including accounting, architecture, engineering, quantity surveying, project management, arbitration and law; 3. adjudication is only available for disputes relating to matters that are prescribed by the statute or the regulations issued thereunder or otherwise agreed by the parties. However, the prescribed list is sufficiently broad such that most disputes that may arise on a construction project will likely be captured; 4. parties are permitted to set out an adjudication procedure in their contract, if it meets the minimum requirements of the statute. However, they are not permitted to prospectively name an adjudicator in their contract this step is to be taken when the adjudication process is commenced; 5. an adjudication will be commenced by the issuance of a notice of adjudication. The notice is required to contain prescribed information, including the name of a proposed adjudicator; 6. if the named adjudicator does not consent to be appointed within four days of a notice of adjudication being served, then the party giving the notice shall request that the ANA appoint an adjudicator. The ANA shall then have seven days to do so, subject to the adjudicator s consent; 7. within five days of the adjudicator being appointed, the party initiating the adjudication shall provide the adjudicator with the documents it intends to rely upon for the adjudication; 8. while the adjudicator then has a fair bit of latitude to design the adjudication procedure, the adjudicator shall render a decision within 30 days after receiving these documents. That decision is binding until a further determination of the same subject matter is made in a court process or arbitration (which is anticipated to be rare); 9. the 30-day deadline can be extended, but only with the written consent of both parties and the adjudicator; 7

10. a party who is required by the adjudicator s determination to make a payment shall do so within ten days of receiving the decision, failing which interest will be payable and a contractor or subcontractor who does not receive payment shall be entitled to suspend their work, with compensation for costs incurred in so doing; 11. although there are no restrictions on the authority of a court or arbitrator to rule on matters that were already the subject of an adjudication, there are only narrow circumstances in which a determination can successfully be set aside. The requisite process is a judicial review, which first requires a motion for leave That motion must be brought within 30 days of the adjudicator s determination being communicated to the parties; and 12. the determination of an adjudicator may be enforced in court. The timeline for adjudication can also be illustrated with a simple graphic: Adjudication Party refers matter to adjudication by giving written notice of adjudication Adjudicator accepts appointment within 4 days or Authorized Nominating Authority appoints adjudicator within an additional 7 days (maximum of 11 days from notice of adjudication to appointment) Within 5 days of appointment of adjudicator, referring party gives adjudicator and other party: (i) notice; (ii) copy of contract or subcontract; and (iii) any documents the party intends to rely upon Subject to avaliable extensions as permitted by the Construction Act, an adjudicator shall make a determination within 30 days of receiving the documents 8

As described in the above summary, adjudication is a quick process with significant consequences. While adjudication has been subject to criticisms that its outcomes will constitute rough justice and that some parties will seek to leverage the tight timelines to their advantage, the objective is for issues to be resolved as they arise so that they will not aggregate and result in lengthy and expensive litigation or arbitration proceedings. Further, recourse will nonetheless remain available to construction liens, arbitration and litigation. In fact, it is generally understood that Ontario will be the only jurisdiction around the world to have both a robust construction lien regime and adjudication running concurrently. Accordingly, it is difficult to accurately predict to what extent adjudication will reduce traditional forms of construction dispute resolution in Ontario. The one certainty is that it is essential for your organization to be prepared for these changes. Be prepared: A Construction Act checklist It should now be apparent that the Construction Act changes will impact every facet of the industry and that the time has now arrived to move from understanding what they are about to preparing your organization to implement them. The following checklist is a starting point to assist you in preparing for the full range of Construction Act changes: critically, develop a decision tree for determining which version of the Construction Act applies. When in doubt, always take a conservative approach consider how your organization may benefit from the new flexibility for holdback release that can be negotiated into a contract, particularly on lengthy and complex projects consider the use of holdback release security and any financing arrangements that must be made to facilitate their use for public projects, ensure necessary bond arrangements are in place for contractors and subcontractors, ensure accounting systems comply with new trust provisions implement a clear system for monitoring applicable construction lien and holdback release deadlines ensure the relevant individuals in your organization are familiar with the new form that has been prescribed for a written notice of a lien ensure the relevant individuals in your organization are trained on the new thresholds for calculating substantial performance and the circumstances in which a portion of a contract can be hived off to have substantial performance certified early on every project, diarize holdback release dates and the deadline for delivering a notice of non-payment of holdback consider how current and future project structures may be impacted by Construction Act changes. For example, will your contracts need to be revised where milestone payments are used, in order to ensure they comply with the Construction Act? where custom contracts are used, ensure your terms and conditions are properly updated to reflect the Construction Act changes and manage the new processes that are prescribed. For example, how will your organization approach the content, timing and delivery of proper invoices? 9

where standard form contracts are used, ensure your supplementary conditions are updated for the same purpose update accounting systems to clearly diarize new mandatory prompt payment deadlines if your organization is a payer, ensure all internal approvals and administrative procedures that are required for payment release facilitate compliance with the prompt payment deadlines review consulting contracts and corresponding payment certification function to ensure they facilitate compliance with the prompt payment deadlines familiarize your organization with the prescribed forms that will be both received and used for all prompt payment requirements, including notices of non-payment train employees on prompt payment deadlines and steps that must be taken where invoices are in dispute, noting that a missed deadline can result in a stranded risk. For example, a contractor who receives a notice of non-payment from an owner but doesn t deliver a notice of non-payment to a subcontractor will be required to make payment downstream, despite not receiving payment from the owner train key project employees on when and how adjudication process must be used and may be used, including essential deadlines implement clear system for tracking claims, whether your organization is the claimant or respondent, in order to ensure that you will be ready to proceed with adjudication when necessary and you will not be taken by surprise when a notice of adjudication is received This checklist is not intended to be comprehensive and will inevitably require refinement depending upon the role of your organization in the construction pyramid and the nature of the projects in which you are involved. However, with October 1, 2019 around the corner and the lien modernization provisions already in place, it is critical to now take the necessary steps to ensure you are ready for these changes to be implemented. Howard Krupat Partner Toronto howard.krupat@dlapiper.com +1 416 365 3510 DLA Piper (Canada) LLP is part of DLA Piper, a global law firm operating through various separate and distinct legal entities. Further details of these entities can be found at www.dlapiper.com. This publication is intended as a first point of reference and should not be relied on as a substitute for professional advice. Specialist legal advice should always be sought in relation to any particular circumstances and no liability will be accepted for any losses incurred by those relying solely on this publication. 10