JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI (Case No.23/ ) QUORUM Shri Mukhtiar Singh, Chairperson Shri P. C. Verma, Member.

Similar documents
BEFORE THE COURT OF ELECTRICITY OMBUDSMAN, JHARKHAND 4 th floor, Bhagirathi Complex, Karamtoli Road, Ranchi

JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI. Case No. 21 & 23 of 2010 ORDER

Sub: In the matter of representation in compliance to the directions of Hon ble High Court, Jabalpur in Writ Petition no.

W.P. (C) No of 2005

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR **** **** ****

Case No. 94 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

BIHAR ELECTRICITY REGULATORY COMMISSION

ORDER (Hearing on & )

IN THE HIGH COURT OF JHARKHAND AT RANCHI. W.P. (L) No of 2008

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No.

ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012)

CASE No. 156 of In the matter of

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH. Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh, Member

IN THE HIGH COURT OF KARNATAKA AT BENGALURU BEFORE THE HON BLE MR.JUSTICE ARAVIND KUMAR. WRIT PETITION Nos /2015 (T-RES)

Grievances No.K/DOS/015/874 of and No. K/DOS/016/875 of

JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI

Respondents. Present in the Hearing: Respondents

IN THE HIGH COURT OF KARNATAKA AT BANGALORE BEFORE THE HON BLE MR. JUSTICE A.S. BOPANNA WRIT PETITION NO.42842/2013 (GM-TEN)

IN THE HIGH COURT OF JHARKHAND AT RANCHI L. P. A. No. 511 of 2009

Case No. 68 of Coram. Shri. I. M. Bohari, Member Shri. Mukesh Khullar, Member. M/s RattanIndia Nasik Power Ltd.

Before the Appellate Tribunal for Electricity Appellate Jurisdiction New Delhi. Appeal No. 166 of Dated this 11 day of May 2006

In the matter of: M/s Rauzagaon Chini Mills (A unit of Balrampur Chini Mills Ltd.) Rauzagaon , District Barabanki (U.P.

Case No. 295 of Coram. Anand B. Kulkarni, Chairperson Mukesh Khullar, Member. Adani Power Maharashtra Limited (APML)

Case No. 02 of Shri V. P. Raja, Chairman Shri S. B. Kulkarni, Member Shri V. L. Sonavane, Member

CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No. CGRF(NUZ)/040/2009

Case No. CGRF(NZ)/91/2018

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Zone, Nagpur Case No.

Case No. 111 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Maharashtra State Electricity Distribution Co.

IN THE HIGH COURT OF JHARKHAND AT RANCHI W. P. (C) No of 2015

Case No.139 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

IN THE HIGH COURT OF KARNATAKA AT BANGALORE BEFORE THE HON BLE MR. JUSTICE AJIT J GUNJAL. WRIT PETITION Nos /2010 (GM-RES),

Case No. 2 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. CGRF(NUZ)/0122/2006. : Shri Vijaykumar Yashwantrao Falke, Plot No. 47, Verma Layout, Ambazari, Nagpur.

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. Investigate and to take appropriate action against M/s Torrent and further to cancel the

IN THE SUPREME COURT OF BANGLADESH APPELLATE DIVISION (CIVIL APPELLATE JURISDICTION) CIVIL PETITION FOR LEAVE TO APPEAL NO OF 2010.

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No.

IN THE HIGH COURT OF JHARKHAND AT RANCHI

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : TRAI ACT, 1997 WP(C) 617/2013 & CM No.1167/2013 (interim relief) DATE OF ORDER :

* IN THE HIGH COURT OF DELHI AT NEW DELHI. % Date of decision: WP(C) No. 416 of 2011 and CM Nos /2011. Versus

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

IN THE MATTER OF GRIEVANCE NO. K/DOS/001/482 OF OF MRS.

Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2017

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL

IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION WRIT PETITION (CIVIL) NO. 184 OF

IN THE HIGH COURT OF JHARKHAND AT RANCHI ---- W.P.(C)

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : PUBLIC PREMISES (EVICTION OF UNAUTHORIZED OCCUPANTS) ACT, Date of decision: 8th February, 2012

In the High Court of Jharkhand at Ranchi. Cr.M.P.No.141 of Binod Kumar Singh..Petitioner V E R S U S

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SERVICE MATTER. Reserved on: Date of decision:

IN THE HIGH COURT OF DELHI AT NEW DELHI. AA No.396/2007. Date of decision: December 3, Vs.

% W.P.(C) No. 5513/2004

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR,

Case No. 99 of Smt. Chandra Iyengar, Chairperson Shri Vijay. L. Sonavane, Member Shri. Azeez M. Khan, Member

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, TRIPURA AND ARUNACHAL PRADESH) W.P(C) 2085/2004

No:- CGRF/AZ/AUR/U/ 446 / 2013 /30 Date :-

IN THE HIGH COURT OF KARNATAKA DHARWAD BENCH BEFORE THE HON BLE MR.JUSTICE ARAVIND KUMAR WRIT PETITION NOS /2014 C/W 85491/2013 (KLR-RES)

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

IN THE HIGH COURT OF JHARKHAND AT RANCHI W.P. (C) No of Bokaro Steel Workers Union 2. N.M.D.C. Mines Workers' Union Petitioners

* IN THE HIGH COURT OF DELHI AT NEW DELHI. Reserved on: % Date of Decision: WP(C) No.7084 of 2010

: 1 : IN THE HIGH COURT OF KARNATAKA CIRCUIT BENCH, AT DHARWAD BEFORE THE HON BLE MR.JUSTICE H.N.NAGAMOHAN DAS. W.P. No /2012 (GM-CPC)

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No.

BEFORE THE H.P. ELECTRICITY REGULATORY COMMISSION AT SHIMLA

IN THE HIGH COURT OF JHARKHAND AT RANCHI. Cr. M.P. No. 944 of 2009

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Notice dated U/s130 of Electricity Act2003.

THE TAMIL NADU ELECTRICITY REGULATORY COMMISSION

MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL. ORDER (Date of Order : 7 th September, 2012)

W.P.No.32054/2014 (GM-RES) ORDER. In Prakash Singh Vs. Union of India, (2006) 8 SCC 1, Apex Court issued several directions in the matter of police

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY MATTER. Date of Decision : January 16, 2007 W.P.(C) 344/2007

IN THE HIGH COURT OF KARNATAKA AT BENGALURU. Before THE HON BLE DR JUSTICE VINEET KOTHARI. Writ Petition No.10976/2015 (LB-BMP)

BEFORE THE NATIONAL GREEN TRIBUNAL, CENTRAL ZONAL BENCH, BHOPAL

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 211/MP/2012

HINDUSTAN CONSTRUCTION COMPANY LTD... Petitioner Through Mr.Dherainder Negi, Adv. with Ms.Smita Bhargava, Adv.

IN THE HIGH COURT OF KARNATAKA AT BENGALURU PRESENT THE HON BLE MR. JUSTICE H.G.RAMESH AND THE HON BLE MR. JUSTICE JOHN MICHAEL CUNHA

ARMED FORCES TRIBUNAL, REGIONAL BENCH, LUCKNOW. Execution Application No. 154 of Tuesday, the 21 st day August, 2018

IN THE HIGH COURT OF KARNATAKA AT BENGALURU PRESENT THE HON BLE MR.JUSTICE VINEET SARAN AND THE HON BLE MRS.JUSTICE S SUJATHA

CONTEMPT APPLICATION No. 09 OF Ram Gopal Sharma. Applicant. Versus. Sh Sanjay Mitra IAS (WB:82), Defence Secretary, 101-A, South

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO Of 2011 SRI MAHABIR PROSAD CHOUDHARY...APPELLANT(S) VERSUS

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : THE ARCHITECTS ACT, 1972 Date of decision: 4th January, 2012 WP(C) NO.8653/2008

Sri. Alex Soharab. V.F, M/s. Southern Engineering Corporation, V/830-A, Development Area, Edayar, Muppathadom , Aluva.

Case No. 135 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member. (1) M/s B.S.Channabasappa & Sons...Petitioner 1

IN THE HIGH COURT OF DELHI AT NEW DELHI. SUBJECT : Arbitration and Conciliation Act, OMP No.356/2004. Date of decision : 30th November, 2007

IN THE HIGH COURT OF KARNATAKA AT BANGALORE PRESENT THE HON BLE MR. JUSTICE N KUMAR AND THE HON BLE MR. JUSTICE V. SURI APPA RAO

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 119/MP/2013. Date of Hearing: Date of Order :

NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI. Company Appeal (AT) (Insolvency) No. 788 of 2018

IN THE HIGH COURT OF DELHI : NEW DELHI. SUBJECT : Bihar Shops and Establishment Act, W.P.(C) No. 5114/2005. Judgment decided on:

I have had the benefit of perusing the judgment of my. esteemed learned brother, Hon ble Justice Shri S.B. Sinha,

CASE No. 47 of In the matter of Appointment of foreign firm as Management Consultant by Maharashtra State Electricity Board.

II (2013) CPJ 10A (NC) (CN) NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI Hon ble Mr. Justice V.B. Gupta, Presiding Member PARMOD KUMAR

IN THE GAUHATI HIGH COURT

CONSUMER GRIEVANCES REDRESSAL FORUM; NAGPUR (RURAL) COMPLAINT NO. 365/2012

Case No. 61 of In the matter of. Petition of Wardha Power Company Ltd. for Review of Order dated 17 January, 2014 in Case No.

REGISTERED CONSUMERS GRIEVANCES REDRESSAL FORUM AT KASUMPTI SHIMLA-9 No. CGRF/Comp. No. 1453/1/17/005

Transcription:

JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI (Case No.23/2007-08) IN THE MATTER OF QUORUM Shri Mukhtiar Singh, Chairperson Shri P. C. Verma, Member. An application for setting aside the letter No. 2103 dated 14.08.2007 in terms of which the respondent No. 2 has approved the request of respondent No.5 for grant of electrical connection form the NIPL feeder and to disconnect the electrical connection of the respondent No.5 from the NIPL feeder and to maintain uninterrupted power supply to the petitioner s unit. AND IN THE MATTER OF M/s Nilachal Iron & Power Ltd PETITIONER. Vrs. Jharkhand State Electricity Board & Others RESPONDENT. ORDER (26.07.2008) The instant petition is filed by the petitioner for setting aside letter No. 2103 dated 14.08.2007 in terms of which the G.M.-Cum- Chief Engineer, (of Jharkhand State Electricity Board) Singhbhum Area, Jamshedpur has approved the request of respondent No.5 M/s Sri Om Metal Ltd for grant of electrical connection from the NIPL feeder and to disconnect the electrical connection of the Respondent No. 5 from the NIPL feeder and to maintain uninterrupted power supply to the petitioner s unit (industrial). The case, in brief, is that the petitioner M/s Nilachal Iron & Power Ltd applied to the respondent No.1 Jharkhand State Electricity Board, hereinafter called JSEB for brevity, for electric connection to its Sponge Iron Plant at Ratanpur (district of Saraikela-kharsawan), for electrical supply at 33KV (HT) Volt in the year 2003. There being no 33KV (HT) line available near the Sponge Iron Plant of the petitioner, the respondent No. 1 JSEB intimated the petitioner that 33 KV (HT) line will have to be constructed from the Maniqui Grid of JSEB to the petitioner s unit at the cost of the petitioner for providing electricity supply as applied for. Accordingly the 33KV (HT) line from Maniqui Grid to the plant of the petitioner is constructed at the cost of the petitioner and the petitioner is provided with the electrical connection in the year 2005 and is availing electricity at 33 KV Volt through this 33KV (HT) line. The Page 1 of 6

respondent No.2, G.M.-Cum-Chief Engineer (of JSEB), Singhbhum Area, Jamshedpur vide his letter No. 2103 dated 14.08.2007 has approved the request of respondent No. 5 M/s Shri Om Metal Ltd for grant of electrical connection to him (respondent No.5) from the NIPL feeder i.e. 33KV (HT) line from Maniqui Grid to the petitioner s unit constructed at his cost and accordingly respondent No. 5 is connected with the said 33KV (HT) line and is availing electricity through the said 33KV (HT) line i.e NIPL feeder. The case of the petitioner is that due to grant of electricity-connection/electricity-supply to the respondent No. 5 from the said 33KV (HT) line (feeder); the electricity supply to the petitioner s unit has been adversely affected and therefore the concerned respondents be directed forthwith to disconnect the electrical-connection/electricity-supply given to respondent No. 5 from the said independent/ dedicated 33KV (HT) line (feeder) of the petitioner and to direct the respondent JSEB to maintain uninterrupted power supply to the petitioner s unit. Notices were issued to the respondent and case was fixed for hearing on 05.04.2008. On that day Shri M.S. Mittal and Sri PAS Pati, Advocates appeared on behalf of the petitioner and Shri Rajesh Shankar and Shri Abhay Prakash, Advocates appeared on behalf of the respondent JSEB. The Petitioner submitted that the notice should be issued to the respondent No. 5 M/s Om Metal Ltd also and accordingly it was ordered to issue notice to the respondent No.5 and put up the matter for hearing on 02.05.2008. On 02.05.2008 Shri PAS Pati advocate appeared on behalf of the petitioner and Shri A.K.Mishra, Nodal Officer appeared on behalf of the JSEB. The service report of the notice issued to the respondent No.5 was not received and also the learned counsel for the petitioner requested for time and accordingly the case was adjourned to 17.05.2008 for service report and reply if any from the respondent No.5. On 17.05.2008 Shri S.Laheri appeared on behalf of the petitioner and none appeared on behalf of the respondent JSEB. The service report of the notice issued to the respondent No.5 was not received and also representative of the petitioner requested for time and accordingly the case was adjourned to 21.05.2008 for service and reply if any from the respondent No.5. On 21.05.2008 Sri M.S. Mittal and PAS Pati Advocates appeared on behalf of the petitioner and Shri Rajesh Shankar and Shri Abhay Prakash appeared on behalf of the respondent of the JSEB. The learned counsel for the petitioner filed petition/rejoinder on behalf of the petitioner raising preliminary objection to the hearing of the case in view of the fact that quorum as required is not complete in terms of the provisions contained in Clause 12 of Conduct of the Business Regulation of Page 2 of 6

the Commission. After hearing both the parties it was agreed that the issue raised about quorum will be decided along with the case and as such the rejoinder be kept on record. It was further submitted that the report for the notice issued to the respondent No.5 is not received and as such the service cannot be said to be complete. It was ordered that a fresh notice by the registered post with AD be issued to the respondent No.5 because the former notice was issued through courier and the case was fixed for hearing on 07.06.2008 awaiting service report and reply if any from the respondent No.5. On 07.06.2008 Shri P.A.S.Pati Advocate appeared on behalf of the petitioner and Shri Rajesh Shankar and Shri Abhay Prakash, Advocates appeared on behalf of the respondent JSEB. The service report of the notice issued to respondent No.5 was received but none appeared on behalf of the respondent No.5. A counter affidavit was filed by the respondent JSEB raising preliminary objection that the petition filed by the petitioner is not maintainable before the Commission as the dispute raised by the petitioner does not come under the purview of Section 9 of the Electricity Act, 2003 and accordingly the present petition is liable to be dismissed. The learned counsel for the respondent JSEB further submitted that the preliminary issue of the jurisdiction may be decided first before proceeding with the matter. Upon this, the learned counsel for the petitioner submitted that since the objection has been raised for the first time and the counter affidavit on behalf of the respondent JSEB has been filed only today, he needs two weeks time to seek instruction and file reply. Accordingly the counter affidavit of the respondent JSEB is kept on record and the request made by the learned counsel for the petitioner is allowed, the case is fixed for hearing on 21.06.2008. On 21.06.2008 Shri Vibhas Sinha, Advocate appeared on behalf of the petitioner and Shri Rajesh Shankar and Shri Abhay Prakash, Advocates appeared on behalf of the respondent JSEB and Shri Vijay Kumar Gupta, Advocate appeared on behalf of the respondent No.5. The learned counsel for the respondent JSEB again submitted that his preliminary objection that the case is not maintainable on the point of jurisdiction may be decided first before proceeding further in the matter. The learned counsel for the petitioner submitted that since his Senior Advocate in this case is out of station due to some unavoidable reasons, at least two weeks time to file reply to the rejoinder filed by the respondent JSEB on the point of the jurisdiction may be allowed. Allowing the request of time of the learned counsel for the petitioner the case was adjourned for hearing for 19.07.2008 on the issue of maintainability of the petition. Page 3 of 6

On 19.07.2008 Shri M.S. Mittal and Shri PAS Pati advocates appeared on behalf of the petitioner and Shri Rajesh Shankar and Shri Abhaya Prakash advocates appeared on behalf of the respondent JSEB. Heard both parties. Learned counsel for the petitioner Shri M.S. Mittal, at the out set, submitted that he is withdrawing his earlier objection filed about quorum since Chairman has joined in the Commission in addition to existing Member (Tech). The learned counsel for the petitioner, Shri M.S. Mittal, on the other hand, through his written submission and pleadings contended that the petitioner has filed the instant petition for adjudication of the grievance against the respondent licensee JSEB under Section 9 of the Electricity Act, 2003 under the direction of the Hon ble High Court, Ranchi and as such it should be heard and decided by the Commission. The learned counsel for the petitioner further submitted that the petitioner has also come for the rederessal of his grievance against the respondent licensee JSEB under the provisions of the Electricity Act, 2003. The learned counsel for the petitioner further pleaded the petitioner has grievances against the respondent licensee JSEB and rederessal of grievances should be done by some forum. The leaned counsel for the petitioner further pleaded that the other forums like Consumer Grievances Redressal Forum under the Electricity Act, 2003 adjudicated upon only the billing dispute of the consumer and as such they cannot adjudicate upon in this case and therefore the petitioner has filed the instant petition before the Commission for adjudication. The learned counsel for the respondent JSEB Shri Rajesh Shankar through his written submission and pleadings contended that the petition cannot be proceeded with and the petitioner s grievances against the respondent JSEB cannot be adjudicated upon by the Commission under Section 9 of the Electricity Act, 2003 as the said Section 9 of the Act relates clearly to Captive Generating Plant whereas the petitioner M/s Nilachal Iron & Power Ltd is a consumer of the respondent licensee JSEB and not a Captive Generating Plant. The learned counsel for the respondent JSEB further pleaded that the issue in question being the grievances of an individual consumer i.e. the petitioner against the respondent licensee JSEB cannot be adjudicated upon by the Commission as the Commission s adjudicatory function is limited to the adjudication of dispute between the licensee and generating company only as clearly provided in Section 86 (1)(f) of the Electricity Act, 2003. Learned counsel for the Page 4 of 6

respondent JSEB further pleaded that there are forums under Electricity Act, 2003 to adjudicate upon the grievances of the individual consumers against the licensee. The learned counsel for the respondent JSEB further cited judgments of the Hon ble Supreme Court in Civil Appeal No. 2846 of 2006 and Civil Appeal No.3551 of 2006 and submitted that the Hon ble Supreme Court has clearly held that the grievances of individual consumers against the licensee cannot be adjudicated upon by the Commission. Learned counsel of the respondent JSEB further submitted that it is misconceived that the petitioner came for the adjudication of the grievances under Section 9 of the Act under the direction of the Hon ble High Court. The learned counsel of the respondent JSEB further added that as a matter of fact the case was withdrawn by the petitioner from the Hon ble High Court. As far as the direction of the Hon ble High Court is concerned the order of the Hon ble High Court under reference is quoted below:- 2/25.01.2008 After some argument, Mr. M.S. Mittal, learned counsel, appearing on behalf of the petitioner seeks permission to witdraw this writ petition in order to move before the statutory forum for the purpose of adjudication of the controversies raised in this writ petition in terms of Section 9 of the Electricity Act. Permission is accorded. Accordingly, this writ petition is dismissed, as withdrawn. It is clear from the aforesaid order of the Hon ble High Court dated 25.01.2008 that the petitioner has withdrawn the said petition WP (C) No. 6593 of 2007 praying before the Hon ble High Court that the petitioner wants to move the matter before the statutory forum for the purpose of adjudication of his grievance in terms of Section 9 of the Electricity Act which was accordingly permitted by the Hon ble High Court and accordingly the writ petition was dismissed as withdrawn. Moreover in the aforesaid order of the Hon ble High Court no where there is any direction to or mention of Jharkhand State Electricity Regulatory Commission. The provisions of Section 9 of the Electricity Act, 2003 specifically relates to the Captive Generating Plant and the instant case being in the nature of the grievance of an individual consumer i.e. the petitioner against the respondent licensee JSEB; we agree with the learned counsel for the respondent JSEB that Section 9 of the Act has no applicability in the matter. Therefore we find that the contention of the petitioner that he has filed the instant petition before the Commission for adjudication of grievances for the petitioner against the respondent Page 5 of 6

licensee JSEB as per the directions of the Hon ble High Court is not acceptable. We further agree to the contention of the respondent JSEB that the Commission s adjudicatory function is limited to the adjudication of dispute between the licensee and generating company under the provisions of the Section 86(1)(f) of the Act and as such we hold that the Commission cannot adjudicate upon the grievances of individual consumers against the licensee as clearly held by the Hon ble Supreme Court in its order in Civil Appeal No. 2846 of 2006 the relevant Para 13 of which (the order) is quoted below for ready reference. Quote: 13. It may be noted from a perusal of section 86(1)(f) of the Act that the State Commission has only power to adjudicate upon disputes between licensees and generating companies. It follows that the Commission cannot adjudicate disputes relating to grievances of individual consumers. The adjudicatory function of the Commission is thus limited to the matter prescribed in Section 86(1)(f). Unquote: Nonetheless we find that the contention of the petitioner that the grievances of the petitioner consumer against the respondent licensee JSEB should be adjudicated upon and redressed by some forum is in place and needs to be addressed. There is Consumer Grievances Redressal Forum constituted under Section 42 (5) of The Electricity Act, 2003 for rederessal of grievances of consumers against the respondent licensee JSEB and the forum is competent to take up the grievances of the consumers like the instant petition as per the provisions of Clause 8 of The Guide Lines For Establishment Of Forum For Redressal Of Grievances Of The Consumers And Electricity Ombudsman read with Section 42(5) of the Act. We therefore hold that the contention of the petitioner to the extent that the Consumer Grievance Rederessal Forum adjudicates upon billing disputes of the consumers only is not correct. In view of the above the petition of the petitioner is not maintainable in this Commission and hence rejected. Sd/- (P.C.Verma) Member (Tech) Sd/- (Mukhtiar Singh) Chairperson Page 6 of 6