Lao PDR: G0234-Second Northern GMS Transport Network Improvement Project

Similar documents
Involuntary Resettlement Due Diligence Report

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject)

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report

Viet Nam: GMS Flood and Drought Risk Management and Mitigation Project Thuong Toi Tien Subproject

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Involuntary Resettlement Due Diligence Report

VIE: Greater Mekong Subregion Southern Coastal Corridor

MON: Urban Development Sector Project Bulgan Subproject

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Resettlement and Ethnic Minority Development Plan (REMDP)

Revised Resettlement Plan Tibar-Gleno Road

Subproject: Hai Lang Province: Quang Tri

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Recommendation 1: Establish a compensation deficit payment scheme.

VIET NAM: GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK MANAGEMENT AND MITIGATION PROJECT

Lao PDR: Sustainable Tourism Development Project

Annex 2: Does the Xayaburi resettlement comply with Lao law?

DANANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT DANANG SUSTAINABLE CITY DEVELOPMENT PROJECT

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN. VIE: Northern Power Transmission Expansion Sector Project SON LA HIEP HOA 500 KV TRANSMISSION LINE

Timor-Leste: Baucau to Viqueque Highway Project

Resettlement Planning Document

Involuntary Resettlement Due Diligence Report

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

RESETTLEMENT ACTION PLAN

Kingdom of Cambodia: Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project

VIE: GMS Ben Luc - Long Thanh Expressway

Resettlement Due Diligence Report

Resettlement Plan. September 2016

Proposed Loan People s Republic of China: Hebei Elderly Care Development Project

ASIAN DEVELOPMENT BANK

Land Acquisition and Resettlement Due Diligence Report

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

Viet Nam: University of Science and Technology of Hanoi (New Model University) Project

ABBREVIATED RESETTLEMENT ACTION PLAN

PRC: Liaoning Small Cities and Towns Development Demonstration Sector Project

PRC: Guangxi Southwestern Cities Development Project - Resettlement Due Diligence Report of Shijinglin Road Extension

CAM: Fourth Greater Mekong Subregion Corridor Towns Development

VIE: Development of the Northern Chu and Southern Ma Rivers Irrigation System Project

PRC: Guiyang Integrated Water Resources Management (Sector) Project

VIE: Northern Power Transmission Expansion Sector Project

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

RESETTLEMENT FRAMEWORK HA TINH, QUANG NAM, QUANG NGAI, QUANG TRI, THANH HOA, THUA THIEN HUE

CAN THO URBAN DEVELOPMENT AND RESILIENCE PROJECT

Cambodia: Agriculture Sector Development Program

World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF)

PRC: Yunnan Pu er Regional Integrated Road Network Development Project

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

RESETTLEMENT AND COMMUNITY DEVELOPMENT PLAN

VIE: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Project

Resettlement Plan Dili-Tibar-Liquica Road

Updated Resettlement and Ethnic Minority Development Plan

The World Bank FOR OFFICIAL USE ONLY

Bangladesh: Urban Public and Environmental Health Sector Development Program

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Viet Nam: Secondary Cities Development Project. Package TK-02: Dien Bien Phu Road, Tam Ky City, Quang Nam Province

MLD - Kulhudhuffushi Harbor Expansion Project

Cambodia: Tonle Sap Lowlands Rural Development Project (Loan 2376/Grant 0092-CAM)

DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= RESETTLEMENT PLAN

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

2017 RESETTLEMENT PLAN SCALING-UP URBAN UPGRADING PROJECT VINH LONG CITY SUB PROJECT SFG2836 V7 REV

Shanxi Small Cities and Towns Development Demonstration Sector Project

Gender Equality and Development

AFG: MFF Water Resources Development Investment Program- Tranche 1, Nangarhar Valley Development Authority Grant No: 0167 AFG

Socialist Republic of Viet Nam: Second Greater Mekong Subregion Corridor Towns Development Project. Bac Giang Subproject

NH21/1 NAM DINH - LAC QUAN RESETTLEMENT ACTION PLAN

Internal Monitoring Report. VIE: Second Greater Mekong Subregion Corridor Towns Development Project. Semestral Report (From July to December 2017)

NH18: CUA ONG MONG DUONG RESETTLEMENT ACTION PLAN

IND: Railway Sector Investment Program

Earthquake Emergency Assistance Project

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Resettlement Policy Framework

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map. 1. Sector Performance, Problems, and Opportunities

VIET NAM: MEDIUM CITES DEVELOPMENT PROJECT (MCDP) PHU LY CITY SUBPROJECT HA NAM PROVINCE. (Final Draft)

VIE: Greater Mekong subregion Flood and Drought Risk Management and Mitigation Project (GMS1)

PNG: Highlands Region Road Improvement Investment Program

PEOPLE S COMMITTEE OF BEN TRE PROVINCE PEOPLE S COMMITTEE OF BEN TRE CITY

NINH THUAN UPDATED RESETTLEMENT PLAN

SRI: Local Government Enhancement Project

RPF of Additional Financing for Fujian Highway Sector Investment Project Contents

Vulnerability of livelihoods in flood-prone areas: A case study in Kandal of Cambodia and An Giang of Vietnam

SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY

Social Safeguards Monitoring Report. TIM L-2857/2858: Road Network Upgrading Project Contract Packages R4 Tibar - Gleno Road

Resettlement Framework

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION

RESETTLEMENT AND COMMUNITY DEVELOPMENT FRAMEWORK

Resettlement Policy Framework

MYA: Maubin-Phyapon Road Rehabilitation Project

Draft Resettlement Plan

TIM: Road Network Upgrading Sector Project

Viet Nam: Thanh Hoa City Comprehensive Socioeconomic Development Project

Cambodia: Agriculture Sector Development Program

Transcription:

Safeguards Monitoring Report Semiannual Report June 2018 Lao PDR: G0234-Second Northern GMS Transport Network Improvement Project Prepared by the Project Coordination Unit of the Ministry of Public Works and Transport (Department of Water Supply) for the Lao Peoples Democratic Republic and the Asian Development Bank. 1

(i) NOTE In this report, "$" refers to US dollars. This safeguards monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. 2

Social Monitoring Report July December 2017 LAO: SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT Asian Development Bank Grant 0234 LAO and OPEC Fund for International Development (OFID) Loan 1392P and Supplementary Loan 1650P Prepared by the Department of Roads June 2018 (Incorporated comment on dated 15 June 2018)

ABBREVIATIONS ADB - Asian Development Bank AP/AH - affected person/affected household COI - corridor of impact DMS - detailed measurement survey DED - detailed engineering design DOR - Department of Roads DP - displaced person (AP/AH) DRC - District Resettlement Committee EA - executing agency EDL - Electricite du Laos GMS - Greater Mekong Sub-region GRM - grievance redress mechanism Lao PDR - Lao People s Democratic Republic MPWT - Ministry of Public Works and Transport OFID - OPEC Funds for International Development OPEC - Organization of Petroleum Exporting Countries OPWT - Office of Public Works and Transport (district office) PIC - Project Implementation Consultants PMU - Project Management Unit QRN - quarterly report number ROW - right-of-way RP - resettlement plan URP - updated resettlement plan WEIGHTS AND MEASURES km - kilometer m - meter m 2 - square meter i

CONTENTS I. Introduction... 1 II. Background Information on the Project Road Sections... 2 A. NR6A... 3 B. NR6A+9km... 4 C. NR6B... 4 D. NR6-1... 4 III. Objectives of the Social Monitoring Report... 5 IV. Methodology... 6 V. Scope of the Monitoring Report... 6 VI. Status of the Implementation of Land Acquisition and Resettlement... 6 A. NR6A... 6 B. NR6A+9km... 7 C. NR6B... 7 D. NR6-1... 7 E. Other specific resettlement concerns... 8 VII. Conclusion and Recommendations... 8 LIST OF TABLES Table II-1 Project Road Sections... 3 Table II-2 Affected Villages in NR6A... 3 Table II-3 Affected Villages in NR6A+9km... 4 Table II-4 Affected Villages in NR6B... 4 Table II-5 Affected Villages in NR6-1... 5 Table II-6 Encumbered and Unencumbered Sections of NR6-1... 5 Table VI-1 Specific Monitoring Concerns... 8 Table VII-1 Action Plan Agreed on 7 December 2017 Meeting between PMU and ADB...10 LIST OF FIGURES Figure I-1: Project Location Map... 2 ii

I. Introduction 1. The Government of Lao People s Democratic Republic (Lao PDR), with assistance from the Asian Development Bank (ADB), is implementing the Second Northern GMS (Greater Mekong Sub-region) Transport Network Improvement Project under ADB Grant 0234-Lao and OPEC Fund for International Development (OFID) Loan 1392P/1650P. The Project is part of the Second Northern GMS Transport Network Improvement Project (referred hereinafter as ADB12) that aims to connect the northern provinces of Lao PDR to Vietnam. It includes upgrading of 3 national roads (NR) in Huaphanh Province, namely, NR6A in Viengxai District and in Sopbao District (61 km long), NR6B (26 km long), and NR6-1 in Viengxai District with a length of approximately 55 km. The Department of Roads (DOR)and ADB in 2017 agreed to extend the scope of NR6A by an additional 9 km, starting from Ban Samphanxay (i.e., km 0+000 of NR6A) going towards Viengxai Town until it joins with NR6-1 in Ban Longkhou.The Ministry of Public Works and Transport (MPWT) is the executing agency (EA), while the DOR is the implementing agency (IA). 2. The DOR set up aproject Management Unit (PMU) each for NR6A, NR6B, and NR6-1. A manager from DOR heads each PMU with an assistant manager from the district Office of Public Works and Transport (OPWT). A task force has been formed within the PMU to overseethe preparation, updating, and implementation of the resettlement plan (RP) prepared for each road section, including monitoring RP implementation. This task force provides overall guidance and technical support to the Provincial Resettlement Committee (PRC) and the District Resettlement Committee(DRC).The PMU is assisted by 3 consultant teams; the first, the Project Management Consultant (PMC) oversaw design modification; the second, a design consultant modified the design; and the third, the Project Implementation Consultants (PIC) is engaged to supervise road upgrading contracts and construction contracts. At various project stages, these consultants have beeninvolved in the preparation, updating, and implementation of resettlement, as well as ensuring that contractors adhere to the agreed resettlement plans (RPs). 3. A provincial resettlement committee (PRC) has been established in the province with members coming from relevant departments, including DPWT Lao Women s Union, Department of Agriculture and Forestry,and Department of Finance and Investment and Planning. The role of PRC in RP updating and implementation includes(i) conducting consultation meetings;(ii) establishing compensation rates at replacement cost for affected assets; (iii) conducting, reviewing and confirming theresults of the detailed measurement survey (DMS); (v) approving final agreement with the affected households (AHs) on their compensation; (v) managing funds for compensation disbursed by the PMU through the Provincial Department of Finance;(vi) monitoring all RP activities; and (vii) acting as a grievance officer. 4. A district resettlement committee (DRC) has been established each in Viengxai District and Sopbao District to provide support to the PRC. With representatives from various sectors, the responsibilities of the DRC include(i)conducting the DMS; (ii) helping in public information and consultation;(iii) assisting in identifying alternative lands for the AHs; (iv) assisting affected villages organize labor and other support for AHs to remove and resettle their structures; (v) 1

assisting in the identification of special needs of vulnerable AHs and providing timely assistance, if any; and (vi) providing first point of contact in the grievance redress mechanism. 5. Funds for the implementation of the RP, including payment of compensation and cash assistance to AHs, is borne by the national government.based on the RP agreed by government and ADB, the PMU sends a request to the Ministry of Finance to disburse to its imprest account the budget to implement the RP. Subsequently, PMU will disburse to the PRC the funds for compensation and allowances, plus administration costs. The PRC, assisted by DRC, pays the AHs their compensation and allowances. The DRC, through the village officials, notifies the AHs on the date and place of payment of compensation and cash allowance. Figure I-1:Project Location Map Source: Project Design Consultants II. Background Information on the Project Road Sections 6. The goal of ADB12 is to improve NR6A, NR6B, and NR6-1 to a modified Class IV road with a minimum of 5.5m carriageway, a shoulder of 0.5m to 2m, and a design speed of 40 km/hour. ADB12 also includes pavement strengthening, shoulder restoration, embankment improvement, provision and improvement of drainage structures and bridges. The indicative 2

corridor of impact (COI) 1 ranges from 15 m from the road centerline in built-up and flat areas to 50 m in mountainous sections. Table II-1 Project Road Sections Road Number End Points Length (Km) NR6-1 Viengxai Nam Soi (Km 119 Km 174.33) 55.33 NR6A Hang Long-Sop Bao (Km 0 Km 60.78) 60.78 NR6A+9km Ban Samphanxay- Ban Longkhou (Km 0 of NR6A Km 119+000) 9.00 NR6B Sop Bao-Pahang (Km 0-Km 26.1 + Nam Ma Bridge) 26.10 Total 151.21 Source: Quarterly Progress Report No. 11 (pp. 11 and 19). A. NR6A 7. The updated resettlement plan for NR6A was updated and agreed in April 2014. The 60.78 km NR6A traverses 25 villages. Village Existing (km) Table II-2 Affected Villages in NR6A Project (km) Village Existing (km) Project (km) Viengxai District Sam Phanxay 111+000 0+000 Na Sa 127+500 16+500 Vang Hay 114+900 9+900 Poung 129+700 18+700 Na Loung 120+500 9+500 Phon Thong 142+300 23+300 Na Mao 123+400 12+400 KaLeum 133+000 22+000 MeuangPoua 124+600 13+600 Van Xiang 134+300 23+300 Home Phanh 125+800 14+800 Sop Bao District Na Yom 139+300 28+300 HaoSaen 158+200 47+200 Phon Say 147+000 36+000 Vieng Hang 159+700 48+700 Na Xang 149+200 38+200 Na Ngoua 162+000 51+000 Na Phone Souk 149+600 38+600 Meuang Hang 162+600 51+600 Kang Hao 152+300 41+300 PhiengFeuang 168+400 57+400 Sop Bao 153+900 41+900 Hard San 169+000 58+000 Na Farm 157+200 46+200 MeuangHom 169+600 58+600 Source: April 2014 URP for NR6A 8. The DMS carried out in April to August 2013 identified a total of 161 households that wouldbe affected by various forms of losses, in addition to theelectricitedu Laos (EDL) for affected poles.specifically, 132,674m 2 were to be permanently acquired consisting of 39plots of residential land (3,277m 2 ), 73 plots of paddies (127,336 m 2 ), 4 plots of garden land (1,599 m 2 ), and 7 fish ponds (463 m 2 ). Of the affected households, 98 AHs were to be physically displaced and 13 would need to relocate their shops. Other non-land assets included trees, crops and secondary structures. There were 30 vulnerable households requiring special assistance consisting of 26 poor AHs and 4 severely affected women-headed households. 1 Actual width of the right-of-way (ROW) to be cleared (i.e., construction limit) will be defined by the contractor s drawing that is usually narrower than the COI as indicated in the approved detailed engineering design. The construction limit may not exceed the prescribed COI without prior approval by the PMU. 3

B. NR6A+9km 9. The DMS in the 5 villages traversed by NR6A+9km was done in August-September 2017. A total of 222 households would be affected by various forms of losses, in addition to the EDL that need to relocate a number of electric poles. About 49,981.34 m 2 of landholdings inside the ROW, consisting of 247 plots used for residence (35,716.34 m 2 ); 6 plots of rice paddies (1,595.40 m 2 ); 48 plots of garden land (11,338.60 m 2 ); and 6 fish ponds (1,331 m 2 )would be recovered by the project. Also, 24 houses and 20 shops would be affected, of which 9 houses and 14 shops require relocationon the residual area of the ROW or on plots outside of the ROW. The other 15 houses and 6 shops are marginally affected and may be reorganized on the residual area of the ROW. Other structures affected includeelectric poles, porches, kitchens, rice bins, fence, and rice milling machines. A number of timber and fruit treeswould likewise be affected. Table II-3Affected Villages in NR6A+9km Village Existing Project (km) (km) Samphanxay 110+500 0+005 Hanglong 110+092 0+092 Nathean 111+350 1+350 Buck 114+450 4+450 Longkou 116+760 6+760 10. The DMS found 1 male AH head to have physical disability, while another AH was found to belong to the Hmong ethnic minority group. There were 20 women-headed AHs identified in the DMS. C. NR6B 11. The RP for NR6B wasupdated and agreed in March 2014.The 26 km NR6B traverses 4 villages. Table II-4 Affected Villages in NR6B Village Project (km) Na Pung 3+400 Pong 8+500 Pa KhokNgai 18+500 Pa Hang 23+500 12. The DMS carried out in April to August 2013 identified 24 AHs, in addition to the EDL. A total of 919.25m 2 of ROW landwould be acquired permanently, consisting of 16 plots of residential land (879.25m 2 ), and 1 fishpond (40 m 2 ). Thirteen AHswould relocate homes and 1 would relocate its shop. Other affected assets included trees, crops and secondary structures. There were no vulnerable AHs identified. D. NR6-1 13. Project Implementation Consultants (PIC) In August-September 2016 carried out 4

thedms of fixed assets in 22 villages traversed by NR6-1 in Viengxai District.The DMS identified 831 AHs thatwould lose various forms assets, in addition to the EDL. Around 30,884 m 2 of landholdings in the road ROW, consisting of 97 plots of residential land (5,692 m 2 ); 152 plots of rice paddies (20,115.50 m 2 ); 41 plots of garden land (2,991.50 m 2 ); and 40 fishponds (2,085 m 2 ) would be recovered permanently. Also, 202 houses and 60 shops would be affected, of which 84 houses and 46 shops require relocationon the residual area of the ROW or on plots outside of the ROW, while the other 118 houses and 14 shops maystill be reorganized on the residual area of the ROW. Other affected assets include electric poles, porches, kitchens, rice bins, fence, water lines, irrigation canals, timber trees, and fruit trees. Village Existing (km) Table II-5Affected Villages in NR6-1 Project (km) Village Existing (km) Project (km) Long Khou 1 119+000 0+000 R/L 2 Kang Thard 139+700 20+700 Na Kai 1 119+000 0+000 R Kang Meuang 140+900 21+900 Na Vid 126+100 7+100 Kang Mong 142+300 23+300 XiengLouang 128+000 9+000 Phoun San 152+700 33+700 Na Mone 130+300 11+300 PhounNeua 154+200 35+200 PoungNakhao 132+300 13+300 Phoun Kang 157+000 38+000 Na Khao 133+200 14+200 Phoun Kao 158+500 39+500 Na Hia 134+400 15+400 Phoun Mai 161+800 42+800 Xiengmen 135+900 16+900 Som 164+700 45+700 Khor 137+200 18+200 Xieng 166+000 47+000 Na San 138+800 19+800 Deuy 168+800 49+800 NOTES: 1 Viengxai Town 2 To the right or left of the road section 14. Information on the locations of encumbered (i.e., with affected assets) and unencumbered (i.e., no affected assets) sections of NR6-1was extracted from the DMS. Table II-6Encumbered and Unencumbered Sections of NR6-1 Encumbered Unencumbered Encumbered Unencumbered Length Length Length Length (m) (m) (m) (m) 0+000-0+399 399 0+400-1+100 700 1+100-1+300 200 1+300-6+800 5,500 6+800-8+500 1,700 8+500-9+200 700 9+200-10+100 900 10+100-11+000 900 11+000-11+500 500 11+500-11+800 300 11+800-12+000 200 12+000-12+800 800 12+800-13+100 300 13+100-13+400 300 13+400-14+600 1,200 14+600-15+000 400 15+000-15+200 200 15+200-16+300 1,100 16+300-17+100 800 17+100-17+700 600 17+700-18+200 500 18+200-19+200 1,000 19+200-19+300 100 19+300-19+500 200 19+500-19+900 400 19+900-20+200 300 20+200-20+500 300 20+500-21+000 500 21+000-22+200 1,200 22+200-22+700 500 22+700-23+200 500 23+200-23+300 100 23+300-24+500 1,200 24+500-32+100 7,600 32+100-32+700 600 32+700-34+300 1,600 34+300-34+700 400 34+700-34+900 200 34+900-35+800 900 35+800-36+900 1,100 36+900-37+600 700 37+600-38+500 900 38+500-38+900 400 38+900-40+300 1,400 40+300-42+500 2,200 42+500-44+500 2,000 44+500-44+800 300 44+800-45+600 800 45+600-46+000 400 46+000-48+300 2,300 48+300-50+200 1,900 50+200-52+200 2,000 52+200-52+300 100 52+300-53+300 1,000 53+300-54+000 700 0 Total 10,199 Total 18,900 Total 9,000 Total 15,900 III. Objectives of the Social Monitoring Report 15. The agreed 2010 resettlement framework tasks the PMU to look into the following concerns in its monitoring activities: 5

a. Compensation and/or other entitlements are provided as per final RP, with no discrimination according to gender, ethnicity, vulnerability, or any other factor; b. Livelihood restoration measures are designed and implemented including modifications in the programs and provision of additional cash and in-kind assistance to the participating affected households as and when necessary; c. Public information, public consultation and grievance redress procedures are followed; d. Capacity of DPs (APs/AHs) to restore/re-establish livelihoods and living standards. Special attention given to severely affected and vulnerable households; e. Affected public facilities and infrastructure are restored promptly; and f. The transition between relocation or site clearing and commencement of civil works is smooth and that sites are not handed over for civil works until affected households have been satisfactorily compensated, assisted and relocated. IV. Methodology 16. Information for this report came mainly from a review of the Project Implementation Consultants reports, namely, Quarterly Report Number (QRN) 9 for the period January-March 2017, QRN 10 (April-June 2017), QRN 11 (July-September 2017), and QRN 12 (October- December 2017). Background information on the project road sections were culled from the final agreed RPs (NR6A and NR6B), and draft RPs per the August-September 2016 DMS (NR6-1) and the August-September 2017 DMS (NR6A+9km). Additional information was obtained from the PMU and Project Implementation Consultants (PIC). V. Scope of the Monitoring Report 17. This social monitoring report covers the period July to December 2017. VI. Status of the Implementation of Land Acquisition and Resettlement A. NR6A 18. The cumulative progress of construction work in NR6A was 81.99% by the end of December 2017 (QRN 12, p.5). 19. QRN 10 on page 38 reported that the total number of AHs in the approved RP was 479, while QRN 11 on page 37 said that the total number of AHs in the approved RP was 353. The agreed RP uploaded on the project website said that there were 161 AHs. On the other hand, following the demarcation of the construction limits (i.e., referred in the quarterly reports as minimized COI ), both quarterly reports said that there were 255 AHs in NR6A. 20. Payment of compensation for all structures had reportedly been completed in April 2016. Both QRN 10 (p. 36) and QRN 11 (p. 37) claimed that 738,469,916 Kip was paid to AHs for structures. Payment of transition allowance to AHs that relocated and poor AHs 2 had been 2 Transition allowance is computed at 16 kg milled rice X 5 household members (average household size in the project area) X Kip7,000 per month. Relocated AHs were entitled to 6 months allowance, while poor AHs were entitled to 1-month allowance. 6

completed by May 2017 (QRN 11, p. 35). QRN 11 did not provide a breakdown of how much of the reported81,760,000 Kip transition allowance (QRN 11, p. 36) was paid to relocated AHs and poor AHs in NR6A and in NR6B, however. QRN 10 (p. 39) and QRN 11 (p. 38) merely mentioned that there were 4 poor AHs in NR6A. 21. There were no outstanding grievances in NR6A as of the end of December 2017. B. NR6A+9km 22. QRN 12 (p.7) reported that the RP for this section was still being prepared and would be submitted by February 2018. C. NR6B 23. QRN 10 (April-June 2017) on page 28 reportedthat civil works for 6B had been completed. 24. QRN 10 on page 38 and QRN 11 on page 37 reported that the total number of AHs in the approved RP was 17. The agreed RP uploaded on the project website said that there were 24 AHs. Following the demarcation of the construction limits, both quarterly reports said that there were 35 AHs in NR6B, however. 25. Payment of compensation for all structures had been completed in April 2016. QRN 10 (p. 36) reported that payment of compensation for structures had amounted to 181,931,384 Kip as of the end of the quarter 2. On the other hand, QRN 11 (p. 37) said that only 160,256,730 Kip (or 88.09% of the 181,931,384 Kip) had been disbursed as of quarter 3. If QNR 11 was correct, then, payment of compensation was still not complete as of quarter 3. QRN 12 (October- December 2017) did not contain any update on compensation. 26. Payment of transition allowance to AHs that relocated and poor AHs had been completed by May 2017 (QRN 11, p. 35). QRN 11 did not provide a breakdown of how much of the reported 81,760,000 Kip transition allowance (QRN 11, p. 36) was paid to relocated AHs and poor AHs in NR6B and in NR6A, however. QRN 10 (p. 39) and QRN 11 (p. 38) merely stated that there were 2 poor AHs in NR6B. 27. There were no outstanding grievances in NR6A as of the end of December 2017. D. NR6-1 28. As of 31 December 2017, there was no acceptable updated RP (URP) for NR6-1 yet. The schedule of submission of the updated resettlement plan (URP) for NR6-1 was earlier targeted for July 2017 (QRN, p. 28), and reset to October 2017 (QRN 11, p. 28). In QRN 11 (p. 15), the slow progress in construction works in NR6-1 (i.e., 4% vis-à-vis planned progress) was blamed mainly on the delay in the preparation of the URP. 29. Notwithstanding the aforementioned, the contract of the civil works contractor was signed on 19 January 2017. DOR issued on 29 March 2017 the notice to start construction work in unencumbered sections. In the diagram of construction schedule for NR6-1, clearing and grubbing activities began in July 2017 (QRN 11, p. 31). By end of December 2017, the cumulative progress in construction works in NR6-1 was 11.83% (QRN 12, p. 5). 7

30. QRN 11 reported that grievance boxes had been installed in 22 villages traversed by NR6-1. Usual complaints by residents revolved around rerouting and/or repair of gravity water lines and irrigation canals which the civil works contractor resolved promptly. There were no outstanding grievances by the end of December 2017. E. Other specific resettlement concerns 31. Table below provides a review of specific areas of concern that PMU is mandated to monitor. Resettlement Concerns Compensation and/or other entitlements are provided as per final RP, with no discrimination according to gender, ethnicity, vulnerability, or any other factor Livelihood restoration measures are designed and implemented including modifications in the programs and provision of additional cash and inkind assistance to the participating affected households as and when necessary Public information, public consultation and grievance redress procedures are followed Capacity of DPs (APs/AHs) to restore/re-establish livelihoods and living standards. Special attention given to severely affected and vulnerable households Affected public facilities and infrastructure are restored promptly The transition between relocation or site clearing and commencement of civil works is smooth and that sites are not handed over for civil works until affected households have been satisfactorily compensated, assisted and relocated VII. Conclusion and Recommendations Table VI-1Specific Monitoring Concerns Status/Comments Compensation for structures were provided per the final agreed RPs for NR6A and NR6B. However, no compensation, in cash or in kind, was provided for recovered ROW landholdings (i.e., plots used for residence or cultivation). Also, in lieu of compensation, AHs were requested to execute deeds of voluntary donation for affected trees. Trees will be compensated for in NR6-1 and NR6A+9km. Payment of transition allowance was delayed for about a year until May 2017. Grievance boxes have been installed in all villages of NR6A, NR6B, and NG6-1.The community mobilizer checks all boxes regularly. Complaints usually revolved around damaged water lines, spoils slipping into paddies outside of the construction limits, and blocked irrigation canal. Civil works contractors havereportedly resolved all such complaints. There were no outstanding complaints as of the end of December 2017. All APs/AHs have already resettled. It is not known, though, if this was made possible by the adequacy of compensation and allowances provided by the project. No post-resettlement implementation assessment has been carried as of the end of December 2017. Yes Restoration of access for all subproject roads shall be addressed by the contractor. Encumbered sections of NR6A, NR6B and NR6-1 were not handed over to the civil works contractor until AHs were paid their compensation and have vacated the construction limits. 32. This social monitoring report has noted a number of inconsistencies in data reported in the project quarterly monitoring reports. This pattern of inconsistencies in data has also been noted 8

in the action plan agreed between PMU and ADB during a meeting at the Lao Resident Mission on 7 December 2017 (see Table VII-1). Said meeting was held to discuss the findings of the November 13-15, 2017 ADB Safeguard Mission (resettlement) that visited NR6A, NR6B and NR6-1. The outcome of the agreed actions will be covered in the next semiannual social monitoring report. 33. The brief yet detailed presentation of background information on each road section is intended to be used in tracking developments in project implementation that may include changes in scope of work and/or changes in the number of APs/AHs and impacted assets. 34. In conclusion, this report would like to stress the importance of ensuring consistency of information across all quarterly and semiannual reports. 9

Table VII-1 Action Plan Agreed on 7 December 2017 Meeting between PMU and ADB 10

11

12

13

14

15