In the matter of: M/s Rauzagaon Chini Mills (A unit of Balrampur Chini Mills Ltd.) Rauzagaon , District Barabanki (U.P.

Similar documents
ORDER (Hearing on & )

Respondents. Present in the Hearing: Respondents

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

2. Chief Engineer (PPA) UP Power Corporation Limited 14 th Floor, Shakti Bhawan Ext. 14 Ashok Marg, Lucknow.Respondent

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

Petition No 973 of 2014 and 1036,1037,1038,1039 &1040 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. Investigate and to take appropriate action against M/s Torrent and further to cancel the

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW

Petition No.881 of 2013, 952 of 2014, 1043 of 2015, 1092& 1093 of 2016 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

Petition No 768 of 2011 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Date of Order :

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

Draft Supplementary Power Purchase Agreement

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW. Petition No.: 960/2014

Case No.139 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL. ORDER (Date of Order : 7 th September, 2012)

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Notice dated U/s130 of Electricity Act2003.

ORDER (Date of Hearing : 23 rd November, 2010) (Date of Order : 24 th November, 2010)

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI (Case No.23/ ) QUORUM Shri Mukhtiar Singh, Chairperson Shri P. C. Verma, Member.

Case No. 02 of Shri V. P. Raja, Chairman Shri S. B. Kulkarni, Member Shri V. L. Sonavane, Member

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

Sub: In the matter of representation in compliance to the directions of Hon ble High Court, Jabalpur in Writ Petition no.

BIHAR ELECTRICITY REGULATORY COMMISSION

Case No. 61 of In the matter of. Petition of Wardha Power Company Ltd. for Review of Order dated 17 January, 2014 in Case No.

THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Petition No.1258/2017, 1259/2017, 1260/2017, 1261/2017 & 1262/2017

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR **** **** ****

ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012)

Uttar Pradesh Electricity Regulatory Commission

Case No. 64 of Shri. V. P. Raja, Chairman Shri. Vijay L. Sonavane, Member ORDER

BEFORE THE H.P. ELECTRICITY REGULATORY COMMISSION AT SHIMLA

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA

Case No. 295 of Coram. Anand B. Kulkarni, Chairperson Mukesh Khullar, Member. Adani Power Maharashtra Limited (APML)

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL

Sangeeta Verma Secretary. No. Secy/ UPERC/Supply Code/ Lucknow: Dated Sir,

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

Case No. 22 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER

Case No. 68 of Coram. Shri. I. M. Bohari, Member Shri. Mukesh Khullar, Member. M/s RattanIndia Nasik Power Ltd.

MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL ORDER

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH. Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh, Member

Draft JSERC (Terms and Conditions for Intra State Open Access) Regulations, 2016

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL. Original Application No. 129/2013 (CZ)

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

Case No. 167 of Coram. Smt. Chandra Iyengar, Chairperson Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member

KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION

THE RIGHT TO INFORMATION ACT Compliance of section 4

KERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram. November 27, Tamil Nadu Electricity Board

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 211/MP/2012

GUJARAT ELECTRICITY REGULATORY COMMISSION (GERC)

765 kv S/C Mainpuri-Hapur & Mainpuri-Greater Noida Line with 765 kv/400 kv AIS at Hapur & Greater Noida and Associated Schemes/Work

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION NOTIFICATION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2014

Case No. 166 of The Tata Power Co. Ltd. (Generation) [TPC-G] Brihanmumbai Electric Supply & Transport Undertaking (BEST)...

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION 2 nd Floor, Kisan Mandi Bhawan, Vibhuti Khand Gomti Nagar, Lucknow.

Case No. 7 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member

SHARE PURCHASE AGREEMENT. This SHARE PURCHASE AGREEMENT ( Agreement ) is made on this day of.., 20..,

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Notification

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

CASE No. 156 of In the matter of

JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI. Case No. 21 & 23 of 2010 ORDER

Case No. 2 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

NEW DELHI. Shri M. Deena. to the National Load Despatch e Energy Certificates to

Order on. Petition No. 58/2013

Bhopal, Dated: 23rd July, 2004

ARMED FORCES TRIBUNAL, REGIONAL BENCH, LUCKNOW. Original Application No. 113 of Monday, this the 17 th day of April, 2017

TAMIL NADU GOVERNMENT GAZETTE. Part VI --- Section 2 (Supplement)

THE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO)

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. The H.P. State Electricity Board, Vidyut Bhawan, Shimla-4

BEFRE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA.

V/s. Uttranchal Jal Vidyut Nigam Ltd; (UJJWAL) Maharani Bagh, GMS Road, Dehradun. V/s

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO Of 2011 SRI MAHABIR PROSAD CHOUDHARY...APPELLANT(S) VERSUS

REQUEST FOR PROPOSAL

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION

Index. 1. Introduction: Scope of the Guidelines Preparation for inviting bids Tariff Structure 6. 5.

Case No.83 of In the matter of Petition under Section 67 of the E.A, 2003 seeking directions upon MSETCL in regard to erection of Tower.

Case No. 224 of Coram. Shri. I.M. Bohari, Member Shri. Mukesh Khullar, Member. M/s. Vidarbha Industries Power Ltd (VIPL-G)

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

NIGERIAN ELECTRICITY REGULATORY COMMISSION REGULATIONS FOR EMBEDDED GENERATION 2012

CHAPTER I: PRELIMINARY

3. M. P. Poorv Kshetra Vidyut Vitaran Co. Ltd. - Respondents Shakti Bhawan, Rampur, Jabalpur

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SERVICE MATTER W.P. (C) No. 135/1997 Reserved on: 18th July, 2012 Decided on: 23rd July, 2012

CASE No. 149 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Shri. Vinod Sadashiv Bhagwat.

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No.

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO OF 2018 VERSUS WITH CIVIL APPEAL NO OF 2018 JUDGMENT

STANDARD REQUEST FOR PROPOSAL FOR PROCUREMENT OF POWER FOR MEDIUM TERM. Under Case 1 Bidding Procedure THROUGH

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 119/MP/2013. Date of Hearing: Date of Order :

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 535 OF 2015

Case No. 135 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member. (1) M/s B.S.Channabasappa & Sons...Petitioner 1

CONSUMER GRIEVANCES REDRESSAL FORUM-I OF SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED

Case No. 94 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member

BIHAR ELECTRICITY REGULATORY COMMISSION, PATNA FEES, FINES AND CHARGES REGULATIONS,

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2016 INDEX

Managing Director, Kanpur Electricity Supply Company Ltd. (KESCO) 14/71, Civil Lines, Kanpur Petitioner. ORDER (Hearing on

Sri. Alex Soharab. V.F, M/s. Southern Engineering Corporation, V/830-A, Development Area, Edayar, Muppathadom , Aluva.

POWER PURCHASE AGREEMENT FOR WIND ELECTRIC GENERATORS (For sale to Distribution Licensee only)

Kendriya Vihar-II Apartment Owners Association Community Centre-1, Kendriya Vihar-II, Plot No.3, Sector-82, Noida , U.P.

Transcription:

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Petition No. 1007 /2015 Quorum Shri Desh Deepak Verma, Chairman Smt. Meenakshi Singh, Member Shri I. B. Pandey, Member In the matter of: Petition u/s 86 (1) (f) along with other relevant provisions of the Electricity Act, 2003. In the matter of: M/s Rauzagaon Chini Mills (A unit of Balrampur Chini Mills Ltd.) Rauzagaon 225402, District Barabanki (U.P.) Petitioner 1. Managing Director, Uttar Pradesh Power Corporation Ltd., Shakti Bhawan, 14 Ashok Marg, Lucknow. 2. Director (Operation), Uttar Pradesh Power Transmission Corporation Ltd., Shakti Bhawan, 14 Ashok Marg, Lucknow. 3. Chief Engineer, Power Purchase Agreement Directorate, Shakti Bhawan, 14 Ashok Marg, Lucknow. 4. Director Transmission (Commercial), Uttar Pradesh Power Transmission Corporation Ltd., Shakti Bhawan, 14 Ashok Marg, Lucknow Respondents ORDER (Hearing held on 4.6.2015) Whereas the petitioner M/s Rauzagaon Chini Mills (A unit of Balrampur Chini Mills Ltd.) Rauzagaon 225402, District Barabanki (U.P.) has filed Petition No. 1007 /2015 in the matter of petition u/s 86 (1) (f) along with other relevant provisions of the Electricity Act, 2003 on 20.2.2015 regarding dispute of Annual Maintenance Charges for the 132 KV transmission line. Brief History of the Case: Page 1 of 5

1. Balrampur Sugar Mill has its plant at Rauzagaon, District Barabanki entered into PPA with UPPCL on 6.2.2007 for sale of 16 MW power and 23 MW power from Bagasse based Cogeneration Plant. It was interfaced with UPPTCL Grid substation located at Chandauli with dedicated 132 KV line of length 56.5 Km. The power was evacuated at Chandauli till 21.1.2009. As per clause 8.4 of PPA the petitioner has to pay AMC @ of 1.5% of the cost of transmission evacuated system with Annual escalation of 5% to UPPCL towards maintenance of 132 KV lines. 2. In January, 2009, UPPCL decided to terminate the line at newly constructed 132 KV of Ramsanehi Ghat and thus the length of the transmission line became limited to 5.5 Kms. The petitioner has submitted that AMC has not been reduced for the line length from 56.5 (Chandauli to 15.5 Ramsanehi Ghat) despite several reminders and has submitted the AMC of line length 56.5 up to 2013-14. The respondents have denied this claim. During the hearing on 7.4.2015 Shr D. D. Chopra, Advocate appearing on behalf of the petitioner submitted that the petitioner has a sugar plant at Rouzagaon, Distt. Barabanki which has a co-generation plant which generates 16 MW and 23 MW power. Initially the power was evacuated through 132 KV line of line length 56.5 Kms terminating at Chandauli sub-station till 22.1.2009. UPPTCL terminated this line at newly constructed 132 KV substation at Ramsanehi Ghat and now the line length is only 15.5. Kms. UPPTCL has revised the losses for the new line length but has not amended the AMC for the new line length of 15.5 Kms from the initial line length of 56.5 Kms when this issue was raised the UPPTCL they directed us to first enter into connectivity agreement then the AMC will be revised. The petitioner has entered into connectivity agreement with UPPTCL, but UPPTCL has not revised the AMC. The petitioner requested the Commission to: i. Issue directions to respondent no. 2 & respondent no. 4 to revise AMC on the basis of length of transmission line of 15.5 Km. between the petitioner the petitioner s generating plant and UPPCL s 132 KV S/s Ramsanehi Ghat on pro data basis of the cost of original transmission line of length 56.5 Km. and not to include the cost of bay at Ramsanehi Ghat while treating this as transfer of bay from 132 KV sub-station Chandauli, and ii. Issue directions to respondent no. 2 & respondent no. 4 to refund the excess amount of AMC already paid by the petitioner from 22.1.2009 with upto date interest, and Page 2 of 5

iii. Issue directions to respondent no. 2 & respondent no. 4 or the concerned authority to refund the cost incurred by the petitioner in the construction of 56.5 15.5 = 41 Km. length of transmission line. Shri Shalendra Gaur, Executive Engineer appearing on behalf of respondent no. 4 submitted that some time is required to submit the WS. The Commission granted fifteen days time to the respondents to file the reply and one week thereafter to file the counter and directed to list on 7.5.2015. During the hearing on 7.5.2015 Shri S. K. Bhattacharya and Shri Shailendra Gaur, Executive Engineer appeared on behalf of respondent no. 4. Respondent no. 4 submitted that they have submitted the WS on 6.5.2015 and they have nothing more to say. Shri Vinay Tripathi, Executive Engineer, UPPTCL appearing on behalf of Director Operation (UPPTCL) who is respondent no. 2 submitted that they are collecting data from the field and will sent to design only then the AMC will be decided and requested for one month time. None appeared on behalf of UPPCL (respondent no. 1) and Power Purchase Agreement Directorate (respondent no. 3) in the hearing on 7.4.2015 and 7.5.2015. The Commission took serious view of non appearance of respondent no. 1 & 3. Further it seems that there is no convergence of views in UPPTCL as Director (Commercial) and Director (Operation) seem to be giving different views. Managing Director (UPPTCL) advised to hold a meeting, with Director Operation (UPPTCL), Director Commercial (UPPTCL) and representative from UPPCL and Power Purchase Agreement Directorate and come to a definite conclusion and file the reply before 27 th May, 2015. If no reply was received by 27 th May, Commission was to proceed to take its own decision based on the facts available. During the hearing on 4.6.2015 Commission enquired whether the meeting has been held by Managing Director, UPPCL. Shri Puneet Chandra, Advocate for UPPTCL submitted that meeting could not be held by Managing Director, UPPTCL. He however, submitted on behalf of respondent no. 2 & 4 that UPERC has notified Uttar Pradesh Electricity Regulatory Commission (Grant of Connectivity to Intra State Transmission System) Regulation 2010 and thereafter also approved Procedure for Grant of Connectivity to Intra State Transmission System and as per clause 10.3 & 10.4 of the said Regulations. Page 3 of 5

10.3 In cases where maintenance of such dedicated transmission line is undertaken by the State Transmission Utility / any other transmission licensee at the option of the applicant, such applicant shall sign an Annual Maintenance Contact on terms and conditions as mutually agreed: Provided that the applicant shall make payment of the annual maintenance charges for meeting expenses towards maintenance of the dedicated transmission line to the State Transmission Utility / any other transmission licensee. 10.4 In cases where construction or maintenance of such dedicated transmission line is undertaken by any other agency (State Transmission Utility / any other transmission licensee) at the option of the applicant, the Commission shall assume no role to adjudicate upon the disputes between such licensee and applicant or refer such dispute for arbitration. Counsel for UPPTCL Shri Chandra also argued that, in view of the above clause the Commission has no jurisdiction to adjudicate upon the present matter and the present petition is non maintainable. He further submitted that AMC can not be revised until necessary amendment is made in Power Purchase Agreement by PPA Unit of UPPCL and PPA Unit has been advised to do so accordingly. Shri V. P. Srivastava, Chief Engineer PPA Unit of UPPCL appearing on behalf of respondent no. 1 & 3 submitted that the petitioner has never approached the PPA Unit for the amendment in the PPA from 22.1.2009 when the line was terminated at Ram Sanehi Ghat, so this petition is pre mature and is bound to be rejected. Respondent No. 1 & 3 further submitted that the UPERC grant of connectivity to Intra State Transmission System unbundling of the erstwhile UPSEB in the year 2002, functions related to transmission of electricity became the job of UPPTCL and it was UPPTCL which must have changed the metering location of power evacuated from Chandauli Sub Station to Ram Sanehi Ghat, Sub Station. It was only for the purpose of Bill Meter Reading and Check Meter reading of the of the Generating Mill that the officers of UPPCL and the representative of the Mill had jointly recorded on 22.01.2009: The 132 KV supply from RCM to Chandauli is diverted to 132 KV S/S RS Ghat metering system commissioned at 132 KV S/S RS Ghat. Further meter reading will be carried out at 132 KV S/S RS Ghat. Page 4 of 5

Without the amendment having being effected in Article 8.1 of the PPA, it was not legally permissible for the petitioner to have agreed to evacuate power from Ram Sanehi Ghat, Power Sub Station instead of Chandauli, Sub Station. Article 8.1 of the PPA dated 6.2.2007 provides: Power from the Generating Plant shall be transmitted at 132 KV through a 132 KV line from the Generating plant located at Rauzagaon Distt. Barabanki. The power so transmitted shall be interfaced with UPPCL s 132 KV grid sub station located at Chandauli by STU. The claim of the petitioner for being charged reduced AMC charges w.e.f. 22.1.2009 is misconceived and erroneous in law for the reason that PPA dated 6.2.2007 is a binding legal document between UPPCL and the petitioner. Without effecting amendments in the relevant articles of the PPA there may be no reduction in the AMC charges on account of shortened transmission line. The reduction in AMC charges will be w.e.f. the date necessary amendments in the PPA are approved by this Hon ble Commission. No retrospective effect, it is submitted, can be given to prospective change in PPA for reduction in AMC charges. The petitioner should have approached UPERC to grant permission to the parties to carry out necessary amendments in article 8.1 of the PPA dated 6.2007. The Commission directs the parties to make necessary amendments in the PPA dated 6.2.2007 within one month and submit to the Commission within next one month for approval. The petition is disposed off. (I. B. Pandey) (Meenakshi Singh) (Desh Deepak Verma) Member Member Chairman Dated: 13.07.2015 Page 5 of 5