CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015

Similar documents
CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO. 19/2014

CONSUMER GRIEVANCES REDRESSAL FORUM; NAGPUR (RURAL) COMPLAINT NO. 365/2012

CONSUMER GRIEVANCES REDRESSAL FORUM; NAGPUR (RURAL) COMPLAINT NO. 352/2011

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No.

CONSUMER GRIEVANCE REDRESSAl FORUM,

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

M/s. Heer Enterprises - Applicant

BEFORE THE CONSUMER GRIEVANCES REDRESSAL FORUM O R D E R

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No.

No:- CGRF/AZ/AUR/U/ 446 / 2013 /30 Date :-

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No.

CASE No. 156 of In the matter of

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Zone, Nagpur Case No.

ORDER (passed on 02/07/2015)

Case No. CGRF(NUZ)/0122/2006. : Shri Vijaykumar Yashwantrao Falke, Plot No. 47, Verma Layout, Ambazari, Nagpur.

Case No. 2 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

CONSUMER GRIEVANCE REDRESSAL FORUM M.S.E.D.C.L., PUNE ZONE, PUNE. Case No.07/2016 Date of Grievance : Date of Order :

B - On behalf of Applicant 1) Shri.Pavati Rajkumar Nisad - Consumer Representative

Grievances No.K/DOS/015/874 of and No. K/DOS/016/875 of

Case No.06/2016 Date of Grievance : Date of Order :

Case No. 135 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member. (1) M/s B.S.Channabasappa & Sons...Petitioner 1

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

Case No.25/2016 Date of Grievance : Date of Order :

IN THE MATTER OF GRIEVANCE NO. K/DOS/001/482 OF OF MRS.

No. K/E/1473/1732 K/E/1476/1735 of Date of registration : 12/11/2018 Date of order : 26/12/2018 Total days : 44

Case No. 111 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Maharashtra State Electricity Distribution Co.

Date of Admission : Date of Decision :

Case No. CGRF(NZ)/91/2018

M/s. Neelsidhi Developers - Complainant The Emerald, 2 nd floor, Plot No. 195 B, Besides, Neelsidhi Towers, Sector -12, Vashi, Navi Mumbai

MAHARASTRA STATE ELECTRICITY DISTRIBUTION CO. LtD. KONKAN ZONE RATNAGIRI CONSUMER GREVANCE REDRASSAL FORUM Consumer case No. 37/2009 Date: 08/04/2009

V/s. Maharashtra State Electricity Distribution Company Limited Through it s Nodal Officer/Addl.EE... (Hereinafter referred as Licensee)

Case No. 99 of Smt. Chandra Iyengar, Chairperson Shri Vijay. L. Sonavane, Member Shri. Azeez M. Khan, Member

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No. CGRF(NUZ)/040/2009

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

CONSUMER GRIEVANCE REDRESSAL FORUM, AMRAVATI ZONE, AKOLA.

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION. PETITION No. CP 02/17

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

Case No. 295 of Coram. Anand B. Kulkarni, Chairperson Mukesh Khullar, Member. Adani Power Maharashtra Limited (APML)

Case No. 68 of Coram. Shri. I. M. Bohari, Member Shri. Mukesh Khullar, Member. M/s RattanIndia Nasik Power Ltd.

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES IN SOUTHERN POWER DISTRIBUTION COMPANY OF A.P LIMITED TIRUPATI

JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI (Case No.23/ ) QUORUM Shri Mukhtiar Singh, Chairperson Shri P. C. Verma, Member.

Sri. Alex Soharab. V.F, M/s. Southern Engineering Corporation, V/830-A, Development Area, Edayar, Muppathadom , Aluva.

CASE No. 149 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Shri. Vinod Sadashiv Bhagwat.

STATE CONSUMER DISPUTES REDRESSAL COMMISSION, MAHARASHTRA, MUMBAI. Complaint No.CC/13/172

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No.

CASE No. 173 of Coram. Shri Anand B. Kulkarni, Chairperson Shri Mukesh Khullar, Member

Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) Ph: & Ext: - 122

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

Case No. 94 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member

CASE No. 337 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member ORDER

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

Case No.139 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

REGISTERED CONSUMERS GRIEVANCES REDRESSAL FORUM AT KASUMPTI SHIMLA-9 No. CGRF/Comp. No. 1453/1/17/005

Case No. 7 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member

Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai

Case No. 61 of In the matter of. Petition of Wardha Power Company Ltd. for Review of Order dated 17 January, 2014 in Case No.

ORDER Dated: 11 th August, 2004

Case No. 166 of The Tata Power Co. Ltd. (Generation) [TPC-G] Brihanmumbai Electric Supply & Transport Undertaking (BEST)...

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR **** **** ****

THE TAMIL NADU ELECTRICITY REGULATORY COMMISSION

Shri P J Patel, Gandhinagar Independent Member Harsha S Chauhan, Vadodara Technical Member Medha M Marathe, MGVCL

Case No. 16 of 2007 Date: 19/12/2007. In the matter of Shri Sachin P. Sakpal V/S

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

CASE No. 44 of In the matter of

In the matter of Exorbitant Bill DECISION

Bar & Bench (

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ALLOTMENT MATTER Date of decision: 17th January, 2013 W.P.(C) 2730/2003 & CM No.4607/2013 (for stay)

The complaint dated regarding to give AG connection in dark zone scheme.

Case No. 64 of Shri. V. P. Raja, Chairman Shri. Vijay L. Sonavane, Member ORDER

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 119/MP/2013. Date of Hearing: Date of Order :

* IN THE HIGH COURT OF DELHI AT NEW DELHI. Date of Decision: 11 th March, 2010

Appointment of Internal Ombudsman (IO) For Redressal of Customer Grievance

Sub: In the matter of representation in compliance to the directions of Hon ble High Court, Jabalpur in Writ Petition no.

Case No. 02 of Shri V. P. Raja, Chairman Shri S. B. Kulkarni, Member Shri V. L. Sonavane, Member

Brihan Mumbai Electric Supply & Transport Undertaking (Of the Municipal Corporation of Greater Mumbai)

Shri P J Patel, Gandhinagar Independent Member Harsha S Chauhan, Vadodara Technical Member Smt M M Marathe, MGVCL

ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012)

BEFORE THE COURT OF ELECTRICITY OMBUDSMAN, JHARKHAND 4 th floor, Bhagirathi Complex, Karamtoli Road, Ranchi

Case No. 17 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Reliance Infrastructure Ltd., Santacruz (E).

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR SPECIFIC PERFORMANCE

Case No. DH/CGRF-1595/2017 Date of Institution: Date of Hearing: Date of Order: 25/01/2017

THE BANKING OMBUDSMAN SCHEME 2006 (including May 24, 2007 Amendments) NOTIFICATION. Ref.RPCD.BOS.No. 441 / / December 26, 2005

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CHANGE OF LAND USE MATTER Date of Decision: W.P.(C) 5180/2012

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

ORDER (Date of Hearing : 23 rd November, 2010) (Date of Order : 24 th November, 2010)

W.P. (C) No of 2005

IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH DATED THIS THE 4 TH DAY OF AUGUST, 2015 BEFORE THE HON BLE MR. JUSTICE K.N.

Case No. 20 of 2007 Date: 11/01/2008. In the matter of Mr. Sudhir.V.Batra

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 3307/2005

Case No. 224 of Coram. Shri. I.M. Bohari, Member Shri. Mukesh Khullar, Member. M/s. Vidarbha Industries Power Ltd (VIPL-G)

Case No. 22 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER

IN THE HIGH COURT OF KARNATAKA AT BANGALORE

NORTHERN POWER DISTRIBUTION COMPANY OF A.P. LIMITED WARANGAL

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : NEGOTIABLE INSTRUMENTS ACT. Date of Decision: CRL.A of 2013.

Transcription:

CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015 Shri Nilesh M. Kolhe At.Aajanti Po.Tq.Hinganghat District - Wardha.,,VS.. Complainant 1. Executive Engineer, MSEDCL,O&M Division, Hinganghat. 2. Executive Engineer/Nodal Officer, I. G. R. C., Circle Office, MSEDCL,Wardha. Respondents Applicant represented by Respondents represented by CORAM: Shri Vishnu S. Bute, Chairman. Adv. Gauri D. Chandrayan, Member Ms. S. B. Chiwande, Member-Secretary. 1) Shri B.V.Betal, Authorized representative 1) Shri M.S.Vaidya, Executive Engineer Hinganghat 2) Shri A.V.Tupkar, Dy.Exe.Engineer, Hinganghat (R) JUDGEMENT (Delivered on this 24 rd day of February, 2015) 2. Shri Nilesh M. Kolhe, r/o Aajanti, Po. and Tq.Hinganghat, Dist. Wardha had applied to the distribution licensee MSEDCL for new connection to agricultural pump set (for the sake of convenience, the parties are being referred to as the applicant and the respondent.). According to the applicant, inspite of the fact that all the formalities were completed, the respondent had not released the connection within the stipulated period prescribed under the MERC (standards of performance of Distribution Licensees, period for giving supply and determination of compensation) Regulations, 2014. The applicant presented an application to the IGRC Wardha. The applicant presented the

2 instant application under the provisions contained in Regulation 6.4 of the MERC (CGRF and E.O.) Regulations 2006 on 15-01-2015. 3. The respondent submitted reply to the application under no.ee/o&m /H ghat/ Tech/573 dated 30-01-2015. The case was fixed for personal hearing on 23-02-2015. Both the parties were represented through their authorized representatives. Both the parties were heard. 4. It was contended on behalf of the applicant that the applicant submitted an application for connection to his agricultural pump on 16-11-2012. A demand note was received on 12-02-2013. The amount as per demand was deposited on 13-02-2013. The test report was submitted on 13-02-2013. Inspite of the fact that the application was complete in all respect the respondent failed to release the connection till today. So the compensation as provided under the SOP Regulations may be awarded. The applicant s prayer was as under, i) The applicant may be awarded compensation as provided under SOP Regulations. The applicant may be awarded compensation of Rs.2.00 Lakhs towards the loss to agricultural produce, Rs.60,000/- and Rs.70,000/- respectively may be awarded for physical and mental harassment, Rs.5,000/- and Rs.10,000/- may be awarded for travel expenses & the cost of the instant proceeding. ii) The respondent may be directed to release the connection immediately. 5. This claim of the applicant was contested by the respondent. According to them the applicant submitted the application on 16-11-2012. A demand note was issued on 08-02-2013. The applicant deposited the amount on 13-02-2013. The test report was

3 submitted on 13-02-2013. To provide the connection to the applicant augmentation to the existing network i.e. installation of 63 KVA Transformer, laying of 0.9 k.m. H.T. line and LT line admeasuring 0.18 k.m. is necessary. Applicant s name is entered in the paid pending list of 2012-13 at sr.no.243. The prayer for compensation is not acceptable. Agricultural connections are already released to the applicants who have deposited the amount till March 2012. The order to give connections to the applicants who have deposited the amount after April 2012 had been issued to a contractor M/s Rudrani Infrastructure ltd., by name. The connections are released as per the orders from the higher authorities and the availability of funds under SPA scheme. If the applicant want the connection immediately he may apply under non DDF (non refundable) scheme declared by the MSEDCL circular no.4900 dated 12-02-2014. The connection will be released as per seniority. In such circumstances the application may be dismissed. 6. The technical member of the forum submitted a note as under, I have gone through the documents on record & submissions made by both the parties, it is not disputed that the complainant has completed all the formalities for getting electric connection to his Ag pump. However supply of electricity to agricultural pumps is carried out under various schemes such as SPA PE,DPDC, Non Refundable DDF etc. At present, there appears pendency of agricultural pump applications in Hinganghat Division under various schemes. The respondent stated that the work of laying HT/LT lines & T/F for supplying connection is entrusted to the agency & is being carried out as per the seniority of the applications/applicants who have deposited the

4 demand amount & completed the formalities in all respect. The respondent further stated that the works of paid pending list for the year 2010-11 & 2011-12 have been started. The works for the period of April 2012 onward have been entrusted to M/s Rudrani Infrastructure under Infrastructure-II scheme. The works are started by the agency & are being completed soon. MSEDCL issued revised guidelines for releasing new agricultural connections vide CE(Dist.)/RE/Ag.pump/4900 dt.12-02-2014 which gives option to applicants to carry out work under Non Refundable DDF scheme by incurring entire expenditure. It appears that the complainant has not opted for getting done his Ag. connection early under the said scheme, hence his name is placed in the seniority list of the year 2012-13 as per demand paid by him. In view of circumstances mentioned above, we can not held the respondent responsible for the delay in providing electric connection to the complainant s pump. The respondent shall provide the connection to the complainant s Ag pump as per the seniority list, otherwise it will cause great injustice on the part of other applicants who have paid the demand prior to the complainant. Moreover the complainant s cause of grievance about payment of compensation for delay in giving supply will arise only when supply is given to him. In this case the supply is not yet given. The complainant s prayer for compensation for delay in giving supply is premature, in view of the order passed by Hon ble Electricity Ombudsman, Mumbai in representation No. 32/2010 & other representations where similar issues were involved.

5 In view of above I am of the opinion that the respondent is not responsible for delay in giving supply & any losses caused to the complainant. Hence in my opinion the complainant is not entitled for compensation. 7. After hearing the concerned parties and upon perusal of the record, it reveal that the applicant submitted the application in the prescribed form. The respondent received the amount as per rule. The applicant submitted the test report. Name of the applicant is also entered in the paid pending list prepared by the respondent. So it is clear that the application submitted by the applicant is complete in all respect. It would be appropriate to reproduce Regulation 4.9, which read thus, 4.9 Where the supply of electricity to a premise requires commissioning of a new sub-station forming a part of the distribution system, the Distribution Licensee shall give supply to such premises within one (1) year from the date of receipt of the complete application and payment of charges. The commissioning of new sub-station forming a part of the distribution system will include sub-station having transformation from HT to HT or HT to LT or switching station from where the HT distribution lines originate. After hearing the parties and upon perusal of the record it reveal that the applicant had submitted the complete application. So it was necessary to release the connection within a period of one (1) year from 13-02-2013. The respondent has not released the connection till today. So the applicant is entitle for compensation as provided under Regulation 12 and appendix A item1 (iii) attached the said Regulations. 8. Other claims of the applicant are not cogent, correct and legal so we are not

6 inclined to accept them. 9. The respondent is bound to abide the SOP Regulations and on its failure to do so the respondent is liable to pay compensation. So the note submitted by technical member can not be considered in toto. 10. In view of the position discussed above, we pass the following order, by majority, O R D E R i) Grievance application no.7 of 2015 is partly allowed. The applicant is entitle for compensation from 14-02-2014 till the connection is released. ii) The respondent MSEDCL is directed to pay compensation @ Rs.100/- per week from 14-02-2014 to 24-02-2015. The payment shall be made within ninety days from the date of receipt of this order. iii) The respondent shall pay the remaining amount of compensation as soon as the connection is released to the applicant. iv) In the facts and circumstances of the case there shall be no order to costs. Sd/- sd/- sd/- (Adv.Gauri D.Chandrayan) (Ms.S.B.Chiwande) (Vishnu S. Bute) MEMBER MEMBER SECRETARY CHAIRMAN CONSUMER GRIEVANCES REDRESSAL FORUM; NAGPUR ZONE NAGPUR (Nagpur Dtd.24 th day of February, 2015)

CONSUMER GRIEVANCE REDRESSAL FORUM NAGPUR ZONE (RURAL) M. S. E. D. C. L. Plot No.12, Shrikrupa, Vijaynagar, Chhaoni, NAGPUR 440013 Email.id- cgrfnz@mahadiscom.in (O) 0712-2022198 cgrfnz@gmail.com NO. CGRF/NZ/ Date : enclosed herewith. Certified copy of order dated 24 th February, 2015 in Case No.7 / 2015 is Member-Secy/ Exe.Engineer, C.G.R.F.(NZ)MSEDCL N A G P U R To, Shri Nilesh M. Kolhe, At.Aajanti, Po.Tq.Hinganghat Dist.Wardha Copy s.w.r.to :- 1. The Chief Engineer(NZ), MSEDCL, Vidyut Bhavan,Katol Road, Nagpur. Copy f.w.cs.to: 1. The Executive Engineer/Nodal Officer., O&M Circle Office, MSEDCL.Wardha 2. Executive Engineer, C.C.O&M Dn., MSEDCL, Hinganghat. for information and necessary action. Address of the Electricity Ombudsman is given as below. Office of - The Electricity Ombudsman, 12, Srikrupa, Vijay Nagar, Chhaoni, Nagpur-440 013 0712-2596670