Challenging the Adjudicator s Decision

Similar documents
IS THE ENFORCEMENT OF AN ADJUDICATOR S DECISION A FOREGONE CONCLUSION? Karen Gidwani. 15 May 2006

Chapter 10. A Note on Dispute Boards. Chapter 10

ADJUDICATION IN AUSTRALIA: AN OVERVIEW. Jeremy Glover. 15 November 2007 THE ADJUDICATION SOCIETY ANNUAL CONFERENCE

GUIDANCE FOR ADJUDICATORS

Recent Developments in Adjudication

Balfour Beatty Construction Northern Ltd v Modus Corovest (Blackpool) Ltd

B e f o r e : HIS HONOUR JUDGE PETER COULSON QC. Between: AC YULE & SON LIMITED - and - SPEEDWELL ROOFING & CLADDING LIMITED

PAY NOW, ARBITRATE LATER?

Before: MR JUSTICE AKENHEAD Between:

The Pre-Action Protocol for Construction and Engineering Disputes (and possible pitfalls)

NOTICES, TIME BARS AND PROPORTIONALITY

Amendments to NEC3 Contracts resulting from The Local Democracy, Economic Development and Construction Act 2009

Construction Law Update. Recent Decisions in Mediation and

Hong Kong International Arbitration Centre ADJUDICATION RULES

Mission Drift in Statutory Adjudication

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

Time and Construction Contracts

Before : MR. JUSTICE EDWARDS-STUART Between :

Between: PHOENIX RECOVERIES (UK) LIMITED. Claimant. - and - DR IAN C. Defendant

Construction & Engineering News

Practice Guideline 9: Guideline for Arbitrators on Making Orders Relating to the Costs of the Arbitration

B: Principles of Law. DGT Steel and Cladding Ltd v Cubbitt Building and Interiors Ltd [2007] Adj.L.R. 07/04

A Useful Contribution? Incorporation of terms

Conditions Precedent to Recovery of Loss and Expense Claims

Freedom of Information Act 2000 (FOIA) Decision notice

In Site. Delivery of an adjudicator s decision what happens if it is not delivered in time?

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

For. the ACCOUNTING FOR AND RECOVERY OF COUNSEL S FEES. Issued by the authority of:- THE FACULTY OF ADVOCATES

Enterprise Managed Services Ltd v East Midland Contracting Ltd [2007] Adj.L.R. 03/27

Section 112 of the HGCR Act is set out below, with the amendments which will be introduced under the LDEDC Act shown in bold:

A Summary of Construction Cases in 2012

Adjudication Society & Chartered Institute of Arbitrators

JUDGMENT REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV BETWEEN D. C. DEVELOPERS LIMITED. Claimant AND

Construction Contracts: No implied obligation to get on with it

Consumer Protection Act 1987 recent cases on causation

Before: HIS HONOUR JUDGE PETER COULSON QC Between: - and - CUBITT BUILDING AND INTERIORS LIMITED

Judicial Review: proposals for reform

Citation Hong Kong Law Journal, 2011, v. 41 n. 2, p

Riaz Hussain QC PRACTICE BUILDING DISPUTES. Call Date: 2001, Silk: 2016 //

The Arbitration Act, 1992

Decision F08-06 TOWNSHIP OF LANGLEY. Celia Francis, Senior Adjudicator. July 16, 2008

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 //

Decision 096/2006 Mr George Waddell and South Lanarkshire Council

Galliford Try Construction Ltd v Mott MacDonald Ltd [2008] APP.L.R. 03/14

Just how final is final and binding?

Orange County Registrar of Voters. Survey Results June 8, 2010 Statewide Primary Election

Adjudication Society & Chartered Institute of Arbitrators

Updating the Construction Act

Building and Construction Industry Security of Payment Act 1999 No 46

Freedom of Information Act 2000 (Section 50) Environmental Information Regulations Decision Notice

The Campaign for Freedom of Information

Unit 5 : ADJUDICATION

KINGS COLLEGE LONDON CENTRE OF CONSTRUCTION LAW AND MANAGEMENT PART D AWARDS AND THEIR DRAFTING A: THE PURPOSE, EFFECT AND ESSENTIALS OF AN AWARD

THE VALIDITY OF ADJUDICATORS DETERMINATIONS CONTAINING ERRORS OF LAW: THE NSW JUDICIAL APPROACH

CONSTRUCTION BRIEFING November 2016

The Attorney General s veto on disclosure of the minutes of the Cabinet Sub-Committee on Devolution for Scotland, Wales and the Regions

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21

Applicant: Mr Norman Brown Authority: The Chief Constable of Strathclyde Police Case No: and Decision Date: 26 July 2007

Code of Practice on the discharge of the obligations of public authorities under the Environmental Information Regulations 2004 (SI 2004 No.

Your address: University Registry, King Edward VII Avenue, Cathays Park, Cardiff CF10 3NS

SUPREME COURT OF QUEENSLAND

UK ATHLETICS LIMITED ( UKA ) DISCIPLINARY RULES AND DISPUTE RESOLUTION AND DISCIPLINARY PROCEDURES

SUPREME COURT OF QUEENSLAND

Justice Committee Civil Litigation (Expenses and Group Proceedings) (Scotland) Bill Written submission from Thompsons Solicitors Scotland

The NEW Pre-Action Protocol for Construction and Engineering Disputes. Simon Tolson

ELA ARBITRATION AND ADR GROUP. Issues arising from Brussels I Recast and Rome I

Developing a Local Violence Against Women and Girls Commissioning Strategy

Judicial review: proposals for reform

In the Blue Corner Construction Law: in the Red Corner Insolvency Law working through the clash RICHARD WILLIAMS

EMPLOYMENT TRIBUNALS (ENGLAND & WALES) Presidential Guidance General Case Management

08/10/2010. Adjudication Process and Timetable. Glossary. Adjudication Process and Timetable ADJUDICATION IN PRINCIPLE AND IN PRACTICE

Freedom of Information Act 2000 (FOIA) Decision notice

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and

The Safari Workaround decision

Agreement for the Supply of Legal Services by a Barrister at Three New Square

The General Teaching Council for Scotland Fitness to Teach Rules 2017 These Rules are available in alternative formats on request

Reinforcing Security of Payment in NSW

SOCIAL SECURITY ACTS

THE COMPANIES NAMED IN THIS GUARANTEE

Guide. Applying for Compensation for an Injury. Social Justice Tribunals Ontario. Criminal Injuries Compensation Board

Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005.

SECURITY OF PAYMENT SECURITY OF PAYMENT THE PENDULUM HAS SWUNG TOO FAR. Philip Davenport

CLIFFORD CHANCE LIMITED LIABILITY PARTNERSHIP

Decision 156/2011 Mr Ralph Lucas and the University of Glasgow

Independent Arbitration Scheme for the Chartered Institute of Management Accountants (CIMA)

Guarantee. THIS DEED is dated. 1. Definitions and Interpretation. 1.1 Definitions. In this Deed:

Agreement for the Supply of Legal Services by a Barrister in a Commercial Case

Guidance on Conducting Litigation

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

Brodyn P/L t/as Time Cost and Quality v Davenport [2004] Adj.L.R. 11/03

Provider Contract for the Provision of Legal Aid Services and Specified Legal Services

GUIDE TO SUPPORTING DETAINEES IN IMMIGRATION BAIL HEARINGS IN SCOTLAND

the availability of other schemes, or the granting of other licences, to other persons in similar circumstances, and

POLICE, PUBLIC ORDER AND CRIMINAL JUSTICE (SCOTLAND) BILL [AS AMENDED AT STAGE 2]

Hitec Power Protection BV v MCI Worldcom Ltd [2002] Adj.L.R. 08/15

FINANCIAL GUIDANCE AND CLAIMS BILL [HL] EXPLANATORY NOTES ON COMMONS AMENDMENTS

USERS GUIDE TO ADJUDICATION

1996 No (L.5) IMMIGRATION. The Asylum Appeals (Procedure) Rules 1996

STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES FROM PREMIER PRODUCE SCOTLAND LTD.

Consultation Response. Consultation on simple procedure rules

Transcription:

Jeremy Glover 1. Mr Justice Coulson, no doubt quite deliberately, noted in 2007 that: With challenges based on jurisdiction and natural justice diffi cult (although not of course impossible) to establish in practice, the resourceful losing party in adjudication has had to look elsewhere for a reason to argue that the adjudicator s decision should not be enforced. 1 2. A look at recent decisions suggests that one of the areas the resourceful losing party is currently giving particular scrutiny to is the actual adjudicator s decision, particularly when that adjudicator has been asked to provide reasons. Parties are increasingly challenging the validity of decisions on the basis that they are, shall we say, not very good. Parties are not saying they are wrong as such, 2 but are asserting either that: (i) (ii) the Decision is so poorly written that it is unintelligible; and/or reading the Decision reveals that the adjudicator has not done what he was supposed to do. 3. 4. 5. 6. Actually and more typically they are suggesting both. Remember that an adjudicator is not necessarily required to give reasons. Under paragraph 22 of the Scheme for Construction Contracts, which has been adopted by the JCT, you do not have to give reasons unless one of the parties requires them. The same is true for the TeCSA, see Rule 31. However, in practice, most adjudicators will be required to give reasons. From a party point of view, it is always a good idea to request reasons, particularly if the matter is a complex one. It makes the decision easier to understand. It also makes the decision easier to explain to others, who may not have had any part to play in the adjudication itself, but are only interested in the outcome. It could also be said that making a request for reasons means that you are guaranteeing that the adjudicator does his job properly. So, if an adjudicator has to give reasons, how detailed do the reasons have to be? Mr Justice Jackson said this in Carillion v Devonport: If an adjudicator is requested to give reasons pursuant to paragraph 22 of the Scheme, in my view a brief statement of those reasons will suffi ce. The reasons should be suffi cient to show that the adjudicator has dealt with the issues remitted to him and what his conclusions are on those issues. It will only be in extreme circumstances, that the court will decline to enforce an otherwise valid adjudicator s decision because of the inadequacy of the reasons given. The complainant would need to show that the reasons were absent or unintelligible and that, as a result, he had suffered substantial prejudice. 7. Alternatively, Lord Justice Clerk in the Scottish case of Diamond v PJW Enterprises Ltd 3 said: 1 AC Yule & Son Ltd v Speedwell Roofi ng & Cladding Ltd [2007] EWHC 1360 2 Patently, a decision will be enforced provided an adjudicator has answered the right question. Bouygues (UK) Ltd v Dahl-Jenson UK Ltd [1999] EWHC 182 3 2004 SC430 4 [2008] CSOH 119 A challenge to the intelligibility of stated reasons can succeed only if the reasons are so incoherent that it is impossible for the reasonable reader to make sense of them. In such a case, the decision is not supported by any reasons at all, and on that account is invalid. 8. So to look at a more recent example or two. In the Scottish case of CSC Braehead Leisure Ltd & Anr v Laing O Rourke Scotland Ltd, 4 there were a

page 2 number of diffi culties with the adjudicator s decision. It was expressed to be interim; the adjudicator had apparently not made up his mind on all the points at issue and requested further information. It was argued that where a contract provides that reasons have to be given, there must be an implied term that those reasons are adequate and intelligible. The court referred to the words of Mr Justice Jackson and Lord Justice Clerk. 9. What the court is looking for is to see that the adjudicator has understood the matter remitted to him for a decision and has issued a decision on that matter. Has the adjudicator considered the issues referred to him, considered both parties submissions on these issues and given a decision on those issues? In this case, the Judge considered that the reasons were at times briefly stated and at times somewhat opaque but they were not so incoherent that it was impossible for the reasonable reader to make sense of them. Therefore the decision was enforced. 10. However the decision was not enforced in Thermal Energy Construction Ltd v AE & E Lentjes UK Ltd. 5 Thermal was engaged as a subcontractor by AE & E to carry out mechanical services on a power station project. Thermal alleged that AE & E had failed to pay it for certain works and referred the dispute to adjudication. The subcontract incorporated the TeCSA adjudication rules. In accordance with paragraph 31 the parties requested the adjudicator to give reasons for his decision. 11. AE & E raised a defence by way of set-off and/or counterclaim seeking 3.75m arising from Thermal s alleged failure to achieve completion by the agreed date. The adjudicator, in a 23-page decision, found in favour of Thermal in the sum of 905k. AE & E failed to pay, which led to enforcement proceedings before Mr HHJ Davies. AE & E claimed that the adjudicator had failed to give reasons for his decision in relation to its set-off/counterclaim defence. Following the Carillion v Devonport case, the Judge noted that the correct test was that AE & E would need to show both that the reasons were absent or unintelligible, and that as a result it had suffered substantial prejudice. The Judge said that: An adjudicator is obliged to give reasons so as to make it clear that he has decided all of the essential issues which he must decide as being issues properly put before him by the parties, and so that the parties can understand, in the context of the adjudication procedure, what it is that the adjudicator has decided and why. 12. Here the Judge noted that there was simply no express reference at all to the set-off defence being one of the issues which the adjudicator recognised he had to decide. This left the question of prejudice. AE & E said that it was unclear whether or not the adjudicator had considered the set-off defence on its merits. Thus, it had lost the opportunity of having that defence dealt with, and had lost the prospect of the adjudicator deciding that point in its favour. If AE & E had had to start a further adjudication to seek to recover its losses, fi rst it would have had to comply with this decision and second there was a risk that a second adjudicator might decline to act on the basis that the point had already been decided. Therefore there was a substantial injustice and the decision was not enforced. 5 [2009] EWHC 408 (TCC) 6 [2008] EWHC 3315 (TCC) 13. In the same way, in Quartzelec Ltd v Honeywell Control Systems Ltd 6 the court considered a responding party s right to raise new defences during the course of adjudication. Quartzelec was engaged by Honeywell to design, supply and install communication systems on a construction project in Liverpool. A dispute arose over an interim valuation of Quartzelec s works. Quartzelec referred the dispute to adjudication

page 3 under the Scheme, alleging that Honeywell had wrongly excluded certain amounts from the interim valuation. In its response, Honeywell argued that the amount of the interim valuation should be reduced to account for certain items that had been omitted from the scope of works before Quartzelec had submitted its interim valuation. This defence (the omission defence) was a new argument, which Honeywell had not previously raised, even in its correspondence with Quartzelec. 14. 15. Quartzelec argued that the omission defence was not part of the dispute submitted to the adjudicator, meaning that the adjudicator had no jurisdiction to consider it. As part of his decision, the adjudicator accepted Quartzelec s submission and ignored the omission defence, fi nding in favour of Quartzelec. The adjudicator decided that Honeywell should pay the interim valuation and 85% of the adjudicator s fees and 80% of Quartzelec s costs. As Honeywell refused to pay, Quartzelec started enforcement proceedings in the TCC. In his judgment, HHJ Davies refused to enforce the adjudicator s decision. One reason for this was that the adjudicator should have considered the omission defence. The court accepted that if the adjudicator had considered and then rejected the omission defence on its merits, then the decision would be enforceable. However, the court was unable to fi nd any such rejection in the adjudicator s decision. 16. A fi nal example can be found in the case of HS Works Ltd v Enterprise Managed Services Ltd. 7 Following disputes about the fi nal account and contra-charges, there were two separate adjudications. Following the fi rst, Enterprise were required to pay 1.8m; in the second, the adjudicator made a declaration as to the proper valuation of the works allowing for contra-charges. The result of the second decision meant that at least part of the sums due under the fi rst decision should be repaid. Both parties argued that the decision where they had lost, was invalid. 17. As part of his decision, Mr Justice Akenhead had to consider the approach to kitchen sink adjudications, where the dispute is so extensive that an adjudicator or defending party cannot readily or easily deal with it in the standard adjudication period. The Judge said the courts should have regard to: (i) (ii) Whether and if so upon what basis the adjudicator felt able to reach his decision in the time available; In terms of the opportunity available to the defending party, the court should look at the opportunities available to that party before the adjudication started to address the subject matter of the adjudication and what that party was able to and did do in the time available in the adjudication to address the material provided to it and the adjudicator. 7 [2009] EWHC 729 (TCC) 18. In the fi rst adjudication, Enterprise argued that the decision was unenforceable because the adjudicator failed to address the merits and make fi ndings in relation to the contra-charges which it had put forward. However, on review of the decision, the Judge noted that the dispute referred included the assertion that as there were no or no effective withholding notices, the amounts withheld from the contra-charges were not properly withheld and were duly payable by Enterprise. As a matter of logic, if that primary case was upheld, there was no need for the adjudicator to consider the alternative case as put forward by Enterprise. This was exactly the view expressed by the adjudicator. Mr Justice Akenhead said that:

page 4 it cannot be incumbent upon an Adjudicator, at least generally, to include in his or her decision a commentary let alone fi ndings upon every issue which arises in the reference, save to the extent that it is necessary to provide reasons and explanations for what he or she does decide 19. 20. 21. In the second adjudication, it was suggested that the adjudicator failed to act fairly and/or apply the rules of natural justice; in part this was because of the extent of the adjudication. However, Mr Justice Akenhead noted that it was clear the adjudicator himself did not ultimately consider that he needed more time in which to produce his decision. In his decision, the adjudicator averred to the fact that his job had been onerous but he had been given a week s extension of time and did not ask for more. The Judge also noted that the adjudicator was provided with extensive evidence and argument by each party in relation to the valuation of fi nal account and contra-charge items. The parties had conveniently subdivided the disputed items into categories and in respect of each separate category, the adjudicator took account of the parties representations and, depending on the volume of supporting documentation, either checked all the information or in the case of a large disputed item carried out a series of spot checks. Bearing in mind the tight adjudication timescale, the adjudicator s approach could not be criticised. Thus both decisions were valid and enforceable. On balance, the Judge considered that his order should refl ect the net effect of the decisions. Calculating the net effect would include taking account of the interest position in relation to the payment (or non-payment) of the respective adjudicator s decisions and costs. A related issue is of course the extent to which an adjudicator can do anything once his decision has been released. Of course, it is only in certain circumstances that an adjudicator can correct an admitted accidental slip or omission in his decision. Following the case of Bloor Construction (UK) Ltd v Bowmer & Kirkland (London) Ltd, 8 an adjudicator can correct a slip provided that it is done promptly and provided the parties do not expressly ban a slip rule in the contract. Some contracts, or adjudicator s terms and conditions, make express provision for the correction of an obvious slip or omission. This must be done promptly and the adjudicator must agree that there was a genuine error. 22. For a recent example, however, see YCMS Ltd v Grabiner & Grabiner. 9 Here, an adjudicator awarded YCMS 26k. On the same day YCMS wrote to the adjudicator pointing out an apparent arithmetical error, namely that the sum awarded should have been 41k. Two days later, having re-checked his decision, the adjudicator amended his decision to award YCMS 60k. YCMS sought enforcement of the 60k. This was refused by Mr Justice Akenhead who only granted enforcement in the sum of 26k. Whilst the Judge agreed that the correction was made in time, two days was reasonably prompt, he did not agree that the correction could be allowed. In the fi rst decision, the adjudicator had made an inexplicable arithmetical error the correction of which would have left a fi gure of 41k. What the adjudicator did here was to reject the correction of the simple arithmetical error in favour of a further re-calculation, which included bringing in the sum due and paid under another certifi cate into the equation. Thus it was not simply the correction of a slip, and further the Grabiners were materially prejudiced because the adjudicator got it wrong a second time. 8 At least in England & Wales. The adjudication legislation is currently being amended to ensure that the slip rule will apply in Scotland. 9 [2009] EWHC 127 (TCC) 23. Further, an adjudicator should remember that after having issued their Decision, with the potential exception of the slip rule, that is the end of

page 5 the matter. Certainly an adjudicator should not be advising the parties as to what they should be doing next. See, for example, Birmingham City Council v Paddison Construction Ltd. 10 Here, an adjudicator dismissed claims for loss and expense on the grounds that they were extravagant and exaggerated. That said, he accepted that some of the claim may be valid and he went on to say that he: would grant the Contractor leave to pursue this claim via a further adjudication if they so wish. 24. As Judge Kirkham noted, you cannot do this. Indeed, as a result of the adjudicator considering the claim and deciding that it was extravagant and exaggerated, Paddison was unable to refer its claim for loss and expense to adjudication. Remember, particularly when there are a series of disputes which are referred to the same or different adjudicators over time, that a second adjudicator cannot open up any matters decided by the fi rst adjudicator. 11 Conclusion 25. 26. There seems to be little doubt that parties are examining adjudicators decisions with an even fi ner forensic toothcomb in a bid to overturn decisions. However, although decisions are being roundly and ever-more stridently criticised before the courts, at least for the time being the courts are demonstrating a marked reluctance to decline to enforce an adjudicator s decision because of the quality of that decision. What matters is whether or not the adjudicator has answered the right question. That said, there has clearly been a signifi cant new development in adjudication enforcement cases. If the court considers that an adjudicator has not addressed all the issues (and particularly all the defences) put before him, then the current trend is for that decision not to be enforced. Accordingly, adjudicators would do well to take extra care to ensure that they have both understood everything that they are required to do (and perhaps to some degree this could quite simply be achieved by confi rming with the parties what issues they are required to address) and then to actually go ahead and do it. Indeed, a review of the HS Works decision, both of Mr Justice Akenhead s comments and the careful steps taken by the adjudicators in question, might be a useful starting point. Jeremy Glover June 2009 10 [2008] EWHC 2254 (TCC) 11 Benfi eld Construction Ltd v Trudson (Hatton) Ltd [2008] EWHC 2333 (TCC)